SlideShare a Scribd company logo
Independent expertise in depth
Guidance for good practice in bored pile and diaphragm wall
design and construction for marine structures
Contents
• Introduction
• Recent developments
• Diaphragm wall finish
• Cage detailing practice
• Tremie concreting practice
• Panel stability
• Improvements in safety
• conclusions
Introduction
Introduction
Introduction
Introduction
Introduction
Why concrete at London Gateway ?
• Illustrative design based on combi
wall
• Safer installation of DWall on dry land
• Risk of driving into very dense Thanet
Sand mitigated
• Dwalls will act as foundations for the
gantry cranes
• Steel prices high and volatile in 2007
• Much reduced steel content in DWall
Design of Diaphragm Wall
• Key challenges
• Relatively high retained height (ca.
28m lowest dredge)
• Changing ground conditions
• Complex soil-structure interaction
• Tight displacement criteria - limit
permanent change of gauge ca. 14.75
mm
• Complex load cases involving tidal lag,
crane, vessel berthing and mooring
• Crack widths limited to 0.24 mm (SLS)
in the splash zone
Thanet Sand Section
Soil Model One
London Clay Section
Soil Model Three
W E
Transition
Soil Model Two
London Gateway Port – Typical Section
Recent developments - deeper CFA
Soil Mech SF50 Fundex F3500
CFA pile reach limited by mast
height and pull back winch capacity
• Dia. 300 to 1500mm
• Length max 32 metres
Recent developments – cased CFA secant walls
Cased CFA Rotary
CFA
CFA - Secant wall examples
Cased CFA - Secant wall examples
Diaphragm walls – new horizons
100m+ wall depth
1800mm thickness
Verticality 1 in 300
C60 concrete
Rotary drum cutters
Mud Pump
Inclinometer
Guide Frame
Mud to the
desanding
plant
Mud return into the trench
after treatment
Diaphragm wall - Hydrofraise
Excavation verticality control
Hydraulically
operated
verticality
control pads
Adjust alignment
as excavation
proceeds
Diaphragm wall – Grab versus Hydrofraise comparison
Theoretical position
of wall
Re-excavate to
correct
alignment
Grab Hydrofraise
Specified limits of
deviation
Diaphragm wall – What does a finished Dwall look like?
Diaphragm wall – What does a finished Dwall look like ?
Diaphragm wall – What can a finished Dwall look like ?
Bleed channels Mud inclusion Mattressing
Diaphragm wall – Latest design and execution practice?
• Careful mix design
• Pre-start concrete trials
• Monitor concrete
production facility
• Observe good cage
detailing practice
• Follow good tremie
practice
• Slump and strength are
not sufficient testing eg.
bleed and stability tests
Diaphragm wall – latest guidance on cage detailing
Diaphragm wall – Latest guidance on cage detailing
• Final clear horizontal distance on vertical
bars at least 100 mm
• Can be reduced at laps to 80 mm
• Multiple layers of vertical bars to be lined
up behind eachother
• Final clear vertical distance on horizontal
bars at least 150 mm provided max
aggregate is 20 mm
• 3D model may be required in areas of high
congestion to avoid clashes
• Minimum distance between cages 200 mm
• Ensure nominal cover is sufficient to
achieve required design cover, to satisfy
durability requirements, allowing for
construction tolerances
Diaphragm wall – Latest guidance on tremie practice
Diaphragm wall – Latest guidance on tremie practice
• At start of pour tremie to the panel bottom and raise <200 mm
• Prior to first discharge install effective separator ie. ball or vermiculite volume
to create plug length at least 2x tremie diameter
• Discharge to all tremies simultaneously until at least 3 m depth of concrete
• Thereafter keep difference in concrete level to a minimum
• Avoid repeated raising and lowering of the tremie (surging)
• Minimum tremie embedment 3 m (may be reduced to 2 m if concrete level
accurately known)
• Excessive tremie embedment to be avoided (preferably less than 10m)
• Remember the first concrete which enters the tremie will not usually reach the
top of the pour
Trench instability
How do we check trench stability?
OVERALL STABILITY
• Limit Equilibrium Method
• Finite Element Model
• Limit Analysis
T
T
G
θ
E
Ls
H
Y
X
Z
q
σy,surcharge
q‘K0
σy,poids
Q
φ
Ls
Z Z
Fc
dS
FoS required:
1.1 to 1.3
0.0
2.0
4.0
6.0
8.0
10.0
12.0
14.0
16.0
18.0
20.0
0.00 5.00 10.00 15.00 20.00 25.00 30.00 35.00 40.00
Pressure (KPa)
Depth
(m)
Active Pressure Bentonite Pressure
Trench stability example
0.0
2.0
4.0
6.0
8.0
10.0
12.0
14.0
16.0
18.0
20.0
0.00 5.00 10.00 15.00 20.00 25.00 30.00 35.00 40.00
Pressure (KPa)
Depth
(m) Active Pressure Bentonite Pressure
0.0
2.0
4.0
6.0
8.0
10.0
12.0
14.0
16.0
18.0
20.0
0.00 5.00 10.00 15.00 20.00 25.00 30.00 35.00 40.00
Pressure (KPa)
Depth
(m)
Active Pressure Bentonite Pressure
Add 20KPa
surcharge I.0m drop in
bentonite
level
Guidewall
depth
Potentially
unstable
Trench stability considerations
How to improve trench stability in poor ground
Standard measures
• Slurry level min 1.5m higher than
groundwater level
• Reinforcement continuity along guide
wall sections
• L-shaped guide walls
• Careful consideration of where to
position the plant
• Use short panels (single bite)
Additional measures
• Elevated guide walls (no more than 500mm)
• Increased density of support fluid
• Lower groundwater
• Ground improvement
Horizontal to vertical - Tandem lift D-wall
Temporary works rebar – very important
Additional rebar to ensure safe:
• Fabrication
• Transportation
• On and off loading
• Storage
• Lifting from horizontal to vertical
• Hanging
• splicing
All elements require design e.g. bars,
welds and connectors
Horizontal to vertical lift – tandem lift
Tandem lifting points
@ top of z bars and cathedral bar
• Were developed to splice ropes, not
reinforcement bars
• Must use lowest tested strength and
robust procedure due to high
variation of tensile strength results
Cage splicing - Bulldog grips
New cage splicing systems - SuperlatchTM
• Size of
superlatch
varies with cage
weight
• No fingers in
cage
• Expensive but
safe
Improvements in safe working – platforms and barriers
Conclusions
• Cast in situ concrete diaphragm and secant pile walls have many potential
applications in marine works
• Diaphragm walls in particular have been used on many quay wall projects
• Plant and material developments have brought opportunities and risks
• Recently published industry guidance designed to achieve better outcomes
in terms of quality and safety
• Good practice should be shared by all

More Related Content

What's hot

Construction of flexible pavement
Construction of flexible pavementConstruction of flexible pavement
Construction of flexible pavement
UTU Dehradun
 
Unit 5
Unit 5Unit 5
Tunnelling methods
Tunnelling methodsTunnelling methods
Tunnelling methods
Durgesh Kumar Yadav
 
Backfilling 2014a-Lecture4
Backfilling 2014a-Lecture4Backfilling 2014a-Lecture4
Backfilling 2014a-Lecture4Anne Allan
 
Sheet piles; advantages, types and methods
Sheet piles; advantages, types and methodsSheet piles; advantages, types and methods
Sheet piles; advantages, types and methods
Constrofacilitator
 
17. AASHTO Rigid Pavement Design (Example).pptx
17. AASHTO Rigid  Pavement Design (Example).pptx17. AASHTO Rigid  Pavement Design (Example).pptx
17. AASHTO Rigid Pavement Design (Example).pptx
Ghulam Mehdi Sahito
 
BITUMINOUS ROAD PPT
BITUMINOUS ROAD PPTBITUMINOUS ROAD PPT
BITUMINOUS ROAD PPT
shubham paliwal
 
Diaphragm Wall
Diaphragm WallDiaphragm Wall
Diaphragm Wall
Things Simplified
 
cement concrete road construction procedure
cement concrete road construction procedure cement concrete road construction procedure
cement concrete road construction procedure
jaknap123456
 
Presentation (prc I) Consistency , final & initial setting time test
Presentation (prc I) Consistency , final & initial setting time test Presentation (prc I) Consistency , final & initial setting time test
Presentation (prc I) Consistency , final & initial setting time test
ceky007
 
APPLIED USE OF PVC & RUBBER WATER-STOPS ON CONCRETE STRUCTURES
APPLIED USE OF PVC & RUBBER WATER-STOPS ON CONCRETE STRUCTURESAPPLIED USE OF PVC & RUBBER WATER-STOPS ON CONCRETE STRUCTURES
APPLIED USE OF PVC & RUBBER WATER-STOPS ON CONCRETE STRUCTURES
Vladimir Popovic
 
Failures in flexible pavement
Failures in flexible pavementFailures in flexible pavement
Failures in flexible pavement
Randhir Kumar
 
Lecture#01
Lecture#01Lecture#01
Lecture#01
arslan000
 
Aggregate - coarse aggregates, testing & limits
Aggregate - coarse aggregates, testing & limitsAggregate - coarse aggregates, testing & limits
Aggregate - coarse aggregates, testing & limits
lalitha moorthy
 
INTERLOCKING CONCRETE BLOCKS PAVEMENTS
INTERLOCKING CONCRETE BLOCKS PAVEMENTSINTERLOCKING CONCRETE BLOCKS PAVEMENTS
INTERLOCKING CONCRETE BLOCKS PAVEMENTS
Dileep Gowda
 
water bound macadam road
water bound macadam roadwater bound macadam road
water bound macadam road
Rohan chansoriya
 
Rebound Hammer Test-priciple,procedure,cons&pros.....
Rebound Hammer Test-priciple,procedure,cons&pros.....Rebound Hammer Test-priciple,procedure,cons&pros.....
Rebound Hammer Test-priciple,procedure,cons&pros.....
SJMIT,now NMAMIT NITTE
 
Alkali reaction in concrete
Alkali reaction in concreteAlkali reaction in concrete
Alkali reaction in concrete
Ayaz khan
 
4 Cracks in Concrete.pptx
4 Cracks in Concrete.pptx4 Cracks in Concrete.pptx
4 Cracks in Concrete.pptx
JamilaTrinidad
 
Durability of concrete
Durability of concreteDurability of concrete
Durability of concrete
Selva Prakash
 

What's hot (20)

Construction of flexible pavement
Construction of flexible pavementConstruction of flexible pavement
Construction of flexible pavement
 
Unit 5
Unit 5Unit 5
Unit 5
 
Tunnelling methods
Tunnelling methodsTunnelling methods
Tunnelling methods
 
Backfilling 2014a-Lecture4
Backfilling 2014a-Lecture4Backfilling 2014a-Lecture4
Backfilling 2014a-Lecture4
 
Sheet piles; advantages, types and methods
Sheet piles; advantages, types and methodsSheet piles; advantages, types and methods
Sheet piles; advantages, types and methods
 
17. AASHTO Rigid Pavement Design (Example).pptx
17. AASHTO Rigid  Pavement Design (Example).pptx17. AASHTO Rigid  Pavement Design (Example).pptx
17. AASHTO Rigid Pavement Design (Example).pptx
 
BITUMINOUS ROAD PPT
BITUMINOUS ROAD PPTBITUMINOUS ROAD PPT
BITUMINOUS ROAD PPT
 
Diaphragm Wall
Diaphragm WallDiaphragm Wall
Diaphragm Wall
 
cement concrete road construction procedure
cement concrete road construction procedure cement concrete road construction procedure
cement concrete road construction procedure
 
Presentation (prc I) Consistency , final & initial setting time test
Presentation (prc I) Consistency , final & initial setting time test Presentation (prc I) Consistency , final & initial setting time test
Presentation (prc I) Consistency , final & initial setting time test
 
APPLIED USE OF PVC & RUBBER WATER-STOPS ON CONCRETE STRUCTURES
APPLIED USE OF PVC & RUBBER WATER-STOPS ON CONCRETE STRUCTURESAPPLIED USE OF PVC & RUBBER WATER-STOPS ON CONCRETE STRUCTURES
APPLIED USE OF PVC & RUBBER WATER-STOPS ON CONCRETE STRUCTURES
 
Failures in flexible pavement
Failures in flexible pavementFailures in flexible pavement
Failures in flexible pavement
 
Lecture#01
Lecture#01Lecture#01
Lecture#01
 
Aggregate - coarse aggregates, testing & limits
Aggregate - coarse aggregates, testing & limitsAggregate - coarse aggregates, testing & limits
Aggregate - coarse aggregates, testing & limits
 
INTERLOCKING CONCRETE BLOCKS PAVEMENTS
INTERLOCKING CONCRETE BLOCKS PAVEMENTSINTERLOCKING CONCRETE BLOCKS PAVEMENTS
INTERLOCKING CONCRETE BLOCKS PAVEMENTS
 
water bound macadam road
water bound macadam roadwater bound macadam road
water bound macadam road
 
Rebound Hammer Test-priciple,procedure,cons&pros.....
Rebound Hammer Test-priciple,procedure,cons&pros.....Rebound Hammer Test-priciple,procedure,cons&pros.....
Rebound Hammer Test-priciple,procedure,cons&pros.....
 
Alkali reaction in concrete
Alkali reaction in concreteAlkali reaction in concrete
Alkali reaction in concrete
 
4 Cracks in Concrete.pptx
4 Cracks in Concrete.pptx4 Cracks in Concrete.pptx
4 Cracks in Concrete.pptx
 
Durability of concrete
Durability of concreteDurability of concrete
Durability of concrete
 

Similar to D-wall Presentation - Rebar Cage.pdf

Soldier Bored and Diaphragm
Soldier Bored and DiaphragmSoldier Bored and Diaphragm
Soldier Bored and Diaphragm
YingHongKang
 
self-compacting concrete
self-compacting concrete self-compacting concrete
self-compacting concrete
Sreekutty S
 
MODULE 4 Special Concrete (1).ppt
MODULE 4 Special Concrete (1).pptMODULE 4 Special Concrete (1).ppt
MODULE 4 Special Concrete (1).ppt
VaibhavSoni742163
 
MODULE 4 Special Concrete (1).ppt
MODULE 4 Special Concrete (1).pptMODULE 4 Special Concrete (1).ppt
MODULE 4 Special Concrete (1).ppt
HarshKumarEname
 
1.2 Diaphragm walls.pptx
1.2 Diaphragm walls.pptx1.2 Diaphragm walls.pptx
1.2 Diaphragm walls.pptx
ShahbazKhan379018
 
Soil Nailing
Soil NailingSoil Nailing
Soil Nailing
Seminar Links
 
Retaining wall (1)
Retaining wall (1)Retaining wall (1)
Retaining wall (1)
Orlando Wong Khung
 
MODERN CONSTRUCTION TECHNOLOGIES IN ENGINEERING PERSPECTIVE
MODERN CONSTRUCTION TECHNOLOGIES IN ENGINEERING PERSPECTIVEMODERN CONSTRUCTION TECHNOLOGIES IN ENGINEERING PERSPECTIVE
MODERN CONSTRUCTION TECHNOLOGIES IN ENGINEERING PERSPECTIVE
Dr K M SONI
 
rapid walls- modular construction technology
rapid walls- modular construction technologyrapid walls- modular construction technology
rapid walls- modular construction technology
Anjith Augustine
 
WRE II construction of galleries in gravity dams
WRE II construction of galleries in gravity damsWRE II construction of galleries in gravity dams
WRE II construction of galleries in gravity dams
MitaliShelke
 
FERROCRETE - MATERIAL AND CONSTRUCTION METHODS
FERROCRETE - MATERIAL AND CONSTRUCTION METHODSFERROCRETE - MATERIAL AND CONSTRUCTION METHODS
FERROCRETE - MATERIAL AND CONSTRUCTION METHODS
jagrutib22
 
SEMINAR PRESENTATION ON BOX CULVERTS
SEMINAR PRESENTATION ON  BOX CULVERTSSEMINAR PRESENTATION ON  BOX CULVERTS
SEMINAR PRESENTATION ON BOX CULVERTS
srinivas cnu
 
Diaphragm walls
Diaphragm wallsDiaphragm walls
Diaphragm wallsNguyen Bao
 
Precast Six lane flyover project
Precast Six lane flyover projectPrecast Six lane flyover project
Precast Six lane flyover project
KriShna Sharma
 
Sesión técnica, sala KM 19, Epoxy pipeline technology
Sesión técnica, sala KM 19, Epoxy pipeline technologySesión técnica, sala KM 19, Epoxy pipeline technology
Sesión técnica, sala KM 19, Epoxy pipeline technologyLTDH2013
 
Sample copy of IT PPT.pptx
Sample copy of IT PPT.pptxSample copy of IT PPT.pptx
Sample copy of IT PPT.pptx
Himanshumangal12
 
Materials of sewer
Materials of sewerMaterials of sewer
Materials of sewer
FAISAL A
 
Slip formwork for chimney
Slip formwork for chimneySlip formwork for chimney
Slip formwork for chimney
Axay Sharma
 
Chapter 5 formwork
Chapter 5 formworkChapter 5 formwork
Chapter 5 formwork
KHUSHBU SHAH
 
Pile Foundations and Diaphragm Walls
Pile Foundations and Diaphragm WallsPile Foundations and Diaphragm Walls
Pile Foundations and Diaphragm Walls
Akash Tilokani
 

Similar to D-wall Presentation - Rebar Cage.pdf (20)

Soldier Bored and Diaphragm
Soldier Bored and DiaphragmSoldier Bored and Diaphragm
Soldier Bored and Diaphragm
 
self-compacting concrete
self-compacting concrete self-compacting concrete
self-compacting concrete
 
MODULE 4 Special Concrete (1).ppt
MODULE 4 Special Concrete (1).pptMODULE 4 Special Concrete (1).ppt
MODULE 4 Special Concrete (1).ppt
 
MODULE 4 Special Concrete (1).ppt
MODULE 4 Special Concrete (1).pptMODULE 4 Special Concrete (1).ppt
MODULE 4 Special Concrete (1).ppt
 
1.2 Diaphragm walls.pptx
1.2 Diaphragm walls.pptx1.2 Diaphragm walls.pptx
1.2 Diaphragm walls.pptx
 
Soil Nailing
Soil NailingSoil Nailing
Soil Nailing
 
Retaining wall (1)
Retaining wall (1)Retaining wall (1)
Retaining wall (1)
 
MODERN CONSTRUCTION TECHNOLOGIES IN ENGINEERING PERSPECTIVE
MODERN CONSTRUCTION TECHNOLOGIES IN ENGINEERING PERSPECTIVEMODERN CONSTRUCTION TECHNOLOGIES IN ENGINEERING PERSPECTIVE
MODERN CONSTRUCTION TECHNOLOGIES IN ENGINEERING PERSPECTIVE
 
rapid walls- modular construction technology
rapid walls- modular construction technologyrapid walls- modular construction technology
rapid walls- modular construction technology
 
WRE II construction of galleries in gravity dams
WRE II construction of galleries in gravity damsWRE II construction of galleries in gravity dams
WRE II construction of galleries in gravity dams
 
FERROCRETE - MATERIAL AND CONSTRUCTION METHODS
FERROCRETE - MATERIAL AND CONSTRUCTION METHODSFERROCRETE - MATERIAL AND CONSTRUCTION METHODS
FERROCRETE - MATERIAL AND CONSTRUCTION METHODS
 
SEMINAR PRESENTATION ON BOX CULVERTS
SEMINAR PRESENTATION ON  BOX CULVERTSSEMINAR PRESENTATION ON  BOX CULVERTS
SEMINAR PRESENTATION ON BOX CULVERTS
 
Diaphragm walls
Diaphragm wallsDiaphragm walls
Diaphragm walls
 
Precast Six lane flyover project
Precast Six lane flyover projectPrecast Six lane flyover project
Precast Six lane flyover project
 
Sesión técnica, sala KM 19, Epoxy pipeline technology
Sesión técnica, sala KM 19, Epoxy pipeline technologySesión técnica, sala KM 19, Epoxy pipeline technology
Sesión técnica, sala KM 19, Epoxy pipeline technology
 
Sample copy of IT PPT.pptx
Sample copy of IT PPT.pptxSample copy of IT PPT.pptx
Sample copy of IT PPT.pptx
 
Materials of sewer
Materials of sewerMaterials of sewer
Materials of sewer
 
Slip formwork for chimney
Slip formwork for chimneySlip formwork for chimney
Slip formwork for chimney
 
Chapter 5 formwork
Chapter 5 formworkChapter 5 formwork
Chapter 5 formwork
 
Pile Foundations and Diaphragm Walls
Pile Foundations and Diaphragm WallsPile Foundations and Diaphragm Walls
Pile Foundations and Diaphragm Walls
 

Recently uploaded

Hybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdf
Hybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdfHybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdf
Hybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdf
fxintegritypublishin
 
Immunizing Image Classifiers Against Localized Adversary Attacks
Immunizing Image Classifiers Against Localized Adversary AttacksImmunizing Image Classifiers Against Localized Adversary Attacks
Immunizing Image Classifiers Against Localized Adversary Attacks
gerogepatton
 
English lab ppt no titlespecENG PPTt.pdf
English lab ppt no titlespecENG PPTt.pdfEnglish lab ppt no titlespecENG PPTt.pdf
English lab ppt no titlespecENG PPTt.pdf
BrazilAccount1
 
MCQ Soil mechanics questions (Soil shear strength).pdf
MCQ Soil mechanics questions (Soil shear strength).pdfMCQ Soil mechanics questions (Soil shear strength).pdf
MCQ Soil mechanics questions (Soil shear strength).pdf
Osamah Alsalih
 
Water Industry Process Automation and Control Monthly - May 2024.pdf
Water Industry Process Automation and Control Monthly - May 2024.pdfWater Industry Process Automation and Control Monthly - May 2024.pdf
Water Industry Process Automation and Control Monthly - May 2024.pdf
Water Industry Process Automation & Control
 
Standard Reomte Control Interface - Neometrix
Standard Reomte Control Interface - NeometrixStandard Reomte Control Interface - Neometrix
Standard Reomte Control Interface - Neometrix
Neometrix_Engineering_Pvt_Ltd
 
Final project report on grocery store management system..pdf
Final project report on grocery store management system..pdfFinal project report on grocery store management system..pdf
Final project report on grocery store management system..pdf
Kamal Acharya
 
一比一原版(SFU毕业证)西蒙菲莎大学毕业证成绩单如何办理
一比一原版(SFU毕业证)西蒙菲莎大学毕业证成绩单如何办理一比一原版(SFU毕业证)西蒙菲莎大学毕业证成绩单如何办理
一比一原版(SFU毕业证)西蒙菲莎大学毕业证成绩单如何办理
bakpo1
 
Design and Analysis of Algorithms-DP,Backtracking,Graphs,B&B
Design and Analysis of Algorithms-DP,Backtracking,Graphs,B&BDesign and Analysis of Algorithms-DP,Backtracking,Graphs,B&B
Design and Analysis of Algorithms-DP,Backtracking,Graphs,B&B
Sreedhar Chowdam
 
DESIGN A COTTON SEED SEPARATION MACHINE.docx
DESIGN A COTTON SEED SEPARATION MACHINE.docxDESIGN A COTTON SEED SEPARATION MACHINE.docx
DESIGN A COTTON SEED SEPARATION MACHINE.docx
FluxPrime1
 
H.Seo, ICLR 2024, MLILAB, KAIST AI.pdf
H.Seo,  ICLR 2024, MLILAB,  KAIST AI.pdfH.Seo,  ICLR 2024, MLILAB,  KAIST AI.pdf
H.Seo, ICLR 2024, MLILAB, KAIST AI.pdf
MLILAB
 
CME397 Surface Engineering- Professional Elective
CME397 Surface Engineering- Professional ElectiveCME397 Surface Engineering- Professional Elective
CME397 Surface Engineering- Professional Elective
karthi keyan
 
Governing Equations for Fundamental Aerodynamics_Anderson2010.pdf
Governing Equations for Fundamental Aerodynamics_Anderson2010.pdfGoverning Equations for Fundamental Aerodynamics_Anderson2010.pdf
Governing Equations for Fundamental Aerodynamics_Anderson2010.pdf
WENKENLI1
 
Cosmetic shop management system project report.pdf
Cosmetic shop management system project report.pdfCosmetic shop management system project report.pdf
Cosmetic shop management system project report.pdf
Kamal Acharya
 
ethical hacking in wireless-hacking1.ppt
ethical hacking in wireless-hacking1.pptethical hacking in wireless-hacking1.ppt
ethical hacking in wireless-hacking1.ppt
Jayaprasanna4
 
Hierarchical Digital Twin of a Naval Power System
Hierarchical Digital Twin of a Naval Power SystemHierarchical Digital Twin of a Naval Power System
Hierarchical Digital Twin of a Naval Power System
Kerry Sado
 
Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...
Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...
Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...
Dr.Costas Sachpazis
 
The Benefits and Techniques of Trenchless Pipe Repair.pdf
The Benefits and Techniques of Trenchless Pipe Repair.pdfThe Benefits and Techniques of Trenchless Pipe Repair.pdf
The Benefits and Techniques of Trenchless Pipe Repair.pdf
Pipe Restoration Solutions
 
RAT: Retrieval Augmented Thoughts Elicit Context-Aware Reasoning in Long-Hori...
RAT: Retrieval Augmented Thoughts Elicit Context-Aware Reasoning in Long-Hori...RAT: Retrieval Augmented Thoughts Elicit Context-Aware Reasoning in Long-Hori...
RAT: Retrieval Augmented Thoughts Elicit Context-Aware Reasoning in Long-Hori...
thanhdowork
 
一比一原版(UofT毕业证)多伦多大学毕业证成绩单如何办理
一比一原版(UofT毕业证)多伦多大学毕业证成绩单如何办理一比一原版(UofT毕业证)多伦多大学毕业证成绩单如何办理
一比一原版(UofT毕业证)多伦多大学毕业证成绩单如何办理
ydteq
 

Recently uploaded (20)

Hybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdf
Hybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdfHybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdf
Hybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdf
 
Immunizing Image Classifiers Against Localized Adversary Attacks
Immunizing Image Classifiers Against Localized Adversary AttacksImmunizing Image Classifiers Against Localized Adversary Attacks
Immunizing Image Classifiers Against Localized Adversary Attacks
 
English lab ppt no titlespecENG PPTt.pdf
English lab ppt no titlespecENG PPTt.pdfEnglish lab ppt no titlespecENG PPTt.pdf
English lab ppt no titlespecENG PPTt.pdf
 
MCQ Soil mechanics questions (Soil shear strength).pdf
MCQ Soil mechanics questions (Soil shear strength).pdfMCQ Soil mechanics questions (Soil shear strength).pdf
MCQ Soil mechanics questions (Soil shear strength).pdf
 
Water Industry Process Automation and Control Monthly - May 2024.pdf
Water Industry Process Automation and Control Monthly - May 2024.pdfWater Industry Process Automation and Control Monthly - May 2024.pdf
Water Industry Process Automation and Control Monthly - May 2024.pdf
 
Standard Reomte Control Interface - Neometrix
Standard Reomte Control Interface - NeometrixStandard Reomte Control Interface - Neometrix
Standard Reomte Control Interface - Neometrix
 
Final project report on grocery store management system..pdf
Final project report on grocery store management system..pdfFinal project report on grocery store management system..pdf
Final project report on grocery store management system..pdf
 
一比一原版(SFU毕业证)西蒙菲莎大学毕业证成绩单如何办理
一比一原版(SFU毕业证)西蒙菲莎大学毕业证成绩单如何办理一比一原版(SFU毕业证)西蒙菲莎大学毕业证成绩单如何办理
一比一原版(SFU毕业证)西蒙菲莎大学毕业证成绩单如何办理
 
Design and Analysis of Algorithms-DP,Backtracking,Graphs,B&B
Design and Analysis of Algorithms-DP,Backtracking,Graphs,B&BDesign and Analysis of Algorithms-DP,Backtracking,Graphs,B&B
Design and Analysis of Algorithms-DP,Backtracking,Graphs,B&B
 
DESIGN A COTTON SEED SEPARATION MACHINE.docx
DESIGN A COTTON SEED SEPARATION MACHINE.docxDESIGN A COTTON SEED SEPARATION MACHINE.docx
DESIGN A COTTON SEED SEPARATION MACHINE.docx
 
H.Seo, ICLR 2024, MLILAB, KAIST AI.pdf
H.Seo,  ICLR 2024, MLILAB,  KAIST AI.pdfH.Seo,  ICLR 2024, MLILAB,  KAIST AI.pdf
H.Seo, ICLR 2024, MLILAB, KAIST AI.pdf
 
CME397 Surface Engineering- Professional Elective
CME397 Surface Engineering- Professional ElectiveCME397 Surface Engineering- Professional Elective
CME397 Surface Engineering- Professional Elective
 
Governing Equations for Fundamental Aerodynamics_Anderson2010.pdf
Governing Equations for Fundamental Aerodynamics_Anderson2010.pdfGoverning Equations for Fundamental Aerodynamics_Anderson2010.pdf
Governing Equations for Fundamental Aerodynamics_Anderson2010.pdf
 
Cosmetic shop management system project report.pdf
Cosmetic shop management system project report.pdfCosmetic shop management system project report.pdf
Cosmetic shop management system project report.pdf
 
ethical hacking in wireless-hacking1.ppt
ethical hacking in wireless-hacking1.pptethical hacking in wireless-hacking1.ppt
ethical hacking in wireless-hacking1.ppt
 
Hierarchical Digital Twin of a Naval Power System
Hierarchical Digital Twin of a Naval Power SystemHierarchical Digital Twin of a Naval Power System
Hierarchical Digital Twin of a Naval Power System
 
Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...
Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...
Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...
 
The Benefits and Techniques of Trenchless Pipe Repair.pdf
The Benefits and Techniques of Trenchless Pipe Repair.pdfThe Benefits and Techniques of Trenchless Pipe Repair.pdf
The Benefits and Techniques of Trenchless Pipe Repair.pdf
 
RAT: Retrieval Augmented Thoughts Elicit Context-Aware Reasoning in Long-Hori...
RAT: Retrieval Augmented Thoughts Elicit Context-Aware Reasoning in Long-Hori...RAT: Retrieval Augmented Thoughts Elicit Context-Aware Reasoning in Long-Hori...
RAT: Retrieval Augmented Thoughts Elicit Context-Aware Reasoning in Long-Hori...
 
一比一原版(UofT毕业证)多伦多大学毕业证成绩单如何办理
一比一原版(UofT毕业证)多伦多大学毕业证成绩单如何办理一比一原版(UofT毕业证)多伦多大学毕业证成绩单如何办理
一比一原版(UofT毕业证)多伦多大学毕业证成绩单如何办理
 

D-wall Presentation - Rebar Cage.pdf

  • 1. Independent expertise in depth Guidance for good practice in bored pile and diaphragm wall design and construction for marine structures
  • 2. Contents • Introduction • Recent developments • Diaphragm wall finish • Cage detailing practice • Tremie concreting practice • Panel stability • Improvements in safety • conclusions
  • 8. Why concrete at London Gateway ? • Illustrative design based on combi wall • Safer installation of DWall on dry land • Risk of driving into very dense Thanet Sand mitigated • Dwalls will act as foundations for the gantry cranes • Steel prices high and volatile in 2007 • Much reduced steel content in DWall
  • 9. Design of Diaphragm Wall • Key challenges • Relatively high retained height (ca. 28m lowest dredge) • Changing ground conditions • Complex soil-structure interaction • Tight displacement criteria - limit permanent change of gauge ca. 14.75 mm • Complex load cases involving tidal lag, crane, vessel berthing and mooring • Crack widths limited to 0.24 mm (SLS) in the splash zone
  • 10. Thanet Sand Section Soil Model One London Clay Section Soil Model Three W E Transition Soil Model Two
  • 11. London Gateway Port – Typical Section
  • 12. Recent developments - deeper CFA Soil Mech SF50 Fundex F3500 CFA pile reach limited by mast height and pull back winch capacity • Dia. 300 to 1500mm • Length max 32 metres
  • 13. Recent developments – cased CFA secant walls Cased CFA Rotary CFA
  • 14. CFA - Secant wall examples
  • 15. Cased CFA - Secant wall examples
  • 16. Diaphragm walls – new horizons 100m+ wall depth 1800mm thickness Verticality 1 in 300 C60 concrete
  • 17. Rotary drum cutters Mud Pump Inclinometer Guide Frame Mud to the desanding plant Mud return into the trench after treatment Diaphragm wall - Hydrofraise
  • 19. Adjust alignment as excavation proceeds Diaphragm wall – Grab versus Hydrofraise comparison Theoretical position of wall Re-excavate to correct alignment Grab Hydrofraise Specified limits of deviation
  • 20. Diaphragm wall – What does a finished Dwall look like?
  • 21. Diaphragm wall – What does a finished Dwall look like ?
  • 22. Diaphragm wall – What can a finished Dwall look like ? Bleed channels Mud inclusion Mattressing
  • 23. Diaphragm wall – Latest design and execution practice? • Careful mix design • Pre-start concrete trials • Monitor concrete production facility • Observe good cage detailing practice • Follow good tremie practice • Slump and strength are not sufficient testing eg. bleed and stability tests
  • 24. Diaphragm wall – latest guidance on cage detailing
  • 25. Diaphragm wall – Latest guidance on cage detailing • Final clear horizontal distance on vertical bars at least 100 mm • Can be reduced at laps to 80 mm • Multiple layers of vertical bars to be lined up behind eachother • Final clear vertical distance on horizontal bars at least 150 mm provided max aggregate is 20 mm • 3D model may be required in areas of high congestion to avoid clashes • Minimum distance between cages 200 mm • Ensure nominal cover is sufficient to achieve required design cover, to satisfy durability requirements, allowing for construction tolerances
  • 26. Diaphragm wall – Latest guidance on tremie practice
  • 27. Diaphragm wall – Latest guidance on tremie practice • At start of pour tremie to the panel bottom and raise <200 mm • Prior to first discharge install effective separator ie. ball or vermiculite volume to create plug length at least 2x tremie diameter • Discharge to all tremies simultaneously until at least 3 m depth of concrete • Thereafter keep difference in concrete level to a minimum • Avoid repeated raising and lowering of the tremie (surging) • Minimum tremie embedment 3 m (may be reduced to 2 m if concrete level accurately known) • Excessive tremie embedment to be avoided (preferably less than 10m) • Remember the first concrete which enters the tremie will not usually reach the top of the pour
  • 29. How do we check trench stability? OVERALL STABILITY • Limit Equilibrium Method • Finite Element Model • Limit Analysis T T G θ E Ls H Y X Z q σy,surcharge q‘K0 σy,poids Q φ Ls Z Z Fc dS FoS required: 1.1 to 1.3
  • 30. 0.0 2.0 4.0 6.0 8.0 10.0 12.0 14.0 16.0 18.0 20.0 0.00 5.00 10.00 15.00 20.00 25.00 30.00 35.00 40.00 Pressure (KPa) Depth (m) Active Pressure Bentonite Pressure Trench stability example
  • 31. 0.0 2.0 4.0 6.0 8.0 10.0 12.0 14.0 16.0 18.0 20.0 0.00 5.00 10.00 15.00 20.00 25.00 30.00 35.00 40.00 Pressure (KPa) Depth (m) Active Pressure Bentonite Pressure 0.0 2.0 4.0 6.0 8.0 10.0 12.0 14.0 16.0 18.0 20.0 0.00 5.00 10.00 15.00 20.00 25.00 30.00 35.00 40.00 Pressure (KPa) Depth (m) Active Pressure Bentonite Pressure Add 20KPa surcharge I.0m drop in bentonite level Guidewall depth Potentially unstable Trench stability considerations
  • 32. How to improve trench stability in poor ground Standard measures • Slurry level min 1.5m higher than groundwater level • Reinforcement continuity along guide wall sections • L-shaped guide walls • Careful consideration of where to position the plant • Use short panels (single bite) Additional measures • Elevated guide walls (no more than 500mm) • Increased density of support fluid • Lower groundwater • Ground improvement
  • 33. Horizontal to vertical - Tandem lift D-wall
  • 34. Temporary works rebar – very important Additional rebar to ensure safe: • Fabrication • Transportation • On and off loading • Storage • Lifting from horizontal to vertical • Hanging • splicing All elements require design e.g. bars, welds and connectors
  • 35. Horizontal to vertical lift – tandem lift Tandem lifting points @ top of z bars and cathedral bar
  • 36. • Were developed to splice ropes, not reinforcement bars • Must use lowest tested strength and robust procedure due to high variation of tensile strength results Cage splicing - Bulldog grips
  • 37. New cage splicing systems - SuperlatchTM • Size of superlatch varies with cage weight • No fingers in cage • Expensive but safe
  • 38. Improvements in safe working – platforms and barriers
  • 39. Conclusions • Cast in situ concrete diaphragm and secant pile walls have many potential applications in marine works • Diaphragm walls in particular have been used on many quay wall projects • Plant and material developments have brought opportunities and risks • Recently published industry guidance designed to achieve better outcomes in terms of quality and safety • Good practice should be shared by all