This document discusses various types of building contracts and key cases related to payment terms. It addresses:
- Lump sum contracts generally require completion of work before payment is due, while interim payments may be allowed. Substantial performance, not absolute compliance, is required.
- Entire contracts require full performance as a condition of payment. If a party abandons work before completion, they cannot recover payment for partial work.
- Case law explores exceptions, such as allowing partial payment on a quantum meruit basis if the client benefits from partial work, or deducting costs to remedy defects from final payment.
- Standard form contracts must be interpreted in light of general contract law and precedent cases on conditions, warrant