This document summarizes a legal article about notices under the UK's Housing Grants, Construction and Regeneration Act 2009 and the NEC3 construction contract.
The article discusses three recent court cases that dealt with failures to serve payment or pay less notices under the 2009 Act. It also examines issues around distinguishing interim payments from final accounts. Additionally, the document outlines key points in NEC3 regarding compensation event notices and the 8-week time limit for notifying such events. The author notes that in practice, both contractors and project managers often fail to follow the notice procedures as intended by the contracts.
Panel discussion on Statutory or Contractual ADR?
Some insights about the development of Security of Payment Legislation in Hong Kong and recent proposal of implementing SOPL Spirit in the public works sector.
This presentation takes you through the basic provisions of Reverse Charge / Joint Charge mechanism introduced w.e.f 1-7-2012. The provisions have wide ramifications as now very few businesses would be able to avoid taking registration with the service tax department.
EODB INDONESIA 2018 - 2019 - Getting Credit HandbookAydinLemon
Indonesia has progressed significantly in deregulating its economy as its ranking in the Ease of Doing Business (EODB) index for 2018, Further Information : https://www.investindonesia.go.id/en/why-invest/ease-of-doing-business
UK Adjudicators are an Adjudicator Nominating Body (ANB) for the United Kingdom and International construction and engineering industries.
www.ukadjudicators.co.uk
Panel discussion on Statutory or Contractual ADR?
Some insights about the development of Security of Payment Legislation in Hong Kong and recent proposal of implementing SOPL Spirit in the public works sector.
This presentation takes you through the basic provisions of Reverse Charge / Joint Charge mechanism introduced w.e.f 1-7-2012. The provisions have wide ramifications as now very few businesses would be able to avoid taking registration with the service tax department.
EODB INDONESIA 2018 - 2019 - Getting Credit HandbookAydinLemon
Indonesia has progressed significantly in deregulating its economy as its ranking in the Ease of Doing Business (EODB) index for 2018, Further Information : https://www.investindonesia.go.id/en/why-invest/ease-of-doing-business
UK Adjudicators are an Adjudicator Nominating Body (ANB) for the United Kingdom and International construction and engineering industries.
www.ukadjudicators.co.uk
#How to Draft International Sales Contracts# By SN PanigrahiSN Panigrahi, PMP
#How to Draft International Sales Contracts# By SN Panigrahi,
Essenpee Business Solutions,
International Sales Contract,
Essentials Elements of a Valid Contract,
Export Contract,
UNIDROIT Principles of International Commercial Contracts,
ITC MODEL CONTRACT FOR THE INTERNATIONAL COMMERCIAL SALE OF GOODS
My recent presentation on the Construction Lien Law and Prompt Payment Act, two of the most effective tools for addressing payment issues on construction projects in New Jersey. Please do not hesitate to get in touch if you have questions about the presentation or any other legal matters.***
***This presentation is for informational purposes only. You should not construe or consider anything on this website as legal advice, and you should consult with an attorney for advice on your specific legal issues.
Service tax on works contract (Pre-Negative List)sandesh mundra
This ppt gives a glimpse of service tax payment in india as applicable to works contractors before the negative list. This is very relevant to builders and developers. Service Tax posers and illustrations were also covered by the speaker during the presentation.
This ppt is a comprehensive presentation on various aspects for the entities working in the construction domain. Starting from Tendering to Budgeting and going on to indirect tax aspects like VAT and service Tax.
INTER-STATE SUPPLY
Import of Goods
Import of Services
Export of Goods & Services
Supplies made to/by SEZ unit or SEZ Developer
Location of Supplier and Place of Supply in different State/UT
#How to Draft International Sales Contracts# By SN PanigrahiSN Panigrahi, PMP
#How to Draft International Sales Contracts# By SN Panigrahi,
Essenpee Business Solutions,
International Sales Contract,
Essentials Elements of a Valid Contract,
Export Contract,
UNIDROIT Principles of International Commercial Contracts,
ITC MODEL CONTRACT FOR THE INTERNATIONAL COMMERCIAL SALE OF GOODS
My recent presentation on the Construction Lien Law and Prompt Payment Act, two of the most effective tools for addressing payment issues on construction projects in New Jersey. Please do not hesitate to get in touch if you have questions about the presentation or any other legal matters.***
***This presentation is for informational purposes only. You should not construe or consider anything on this website as legal advice, and you should consult with an attorney for advice on your specific legal issues.
Service tax on works contract (Pre-Negative List)sandesh mundra
This ppt gives a glimpse of service tax payment in india as applicable to works contractors before the negative list. This is very relevant to builders and developers. Service Tax posers and illustrations were also covered by the speaker during the presentation.
This ppt is a comprehensive presentation on various aspects for the entities working in the construction domain. Starting from Tendering to Budgeting and going on to indirect tax aspects like VAT and service Tax.
INTER-STATE SUPPLY
Import of Goods
Import of Services
Export of Goods & Services
Supplies made to/by SEZ unit or SEZ Developer
Location of Supplier and Place of Supply in different State/UT
Payment in construction contracts: how to get paidBarry Hembling
A presentation to the Society of Construction Law giving practical advice on how parties should frame payment claims to achieve payment on construction projects and how such claims can be challenged taking account of recent legal developments in this sector.
UK Adjudicators are an adjudicator nominating body who nominate sole adjudicators and dispute board members in the United Kingdom and internationally. The nomination service is a free service to the parties.
The June newsletter features adjudication cases from the UK, NSW, Singapore and updates from Canada and NSW on adjudication legislation.
The spotlight for our first quarterly public sector breakfast club of 2017 is procurement. The last 12 months or so have seen some interesting developments in public procurement, although perhaps not as interesting as the next 24 months might see. In this seminar Peter Ware takes a retrospective look at what has happened over the last year or so and looks at what the world of procurement might look like in the longer term.
Similar to Slides from the niceties of notices and their importance for construction claims (20)
PRECEDENT AS A SOURCE OF LAW (SAIF JAVED).pptxOmGod1
Precedent, or stare decisis, is a cornerstone of common law systems where past judicial decisions guide future cases, ensuring consistency and predictability in the legal system. Binding precedents from higher courts must be followed by lower courts, while persuasive precedents may influence but are not obligatory. This principle promotes fairness and efficiency, allowing for the evolution of the law as higher courts can overrule outdated decisions. Despite criticisms of rigidity and complexity, precedent ensures similar cases are treated alike, balancing stability with flexibility in judicial decision-making.
ALL EYES ON RAFAH BUT WHY Explain more.pdf46adnanshahzad
All eyes on Rafah: But why?. The Rafah border crossing, a crucial point between Egypt and the Gaza Strip, often finds itself at the center of global attention. As we explore the significance of Rafah, we’ll uncover why all eyes are on Rafah and the complexities surrounding this pivotal region.
INTRODUCTION
What makes Rafah so significant that it captures global attention? The phrase ‘All eyes are on Rafah’ resonates not just with those in the region but with people worldwide who recognize its strategic, humanitarian, and political importance. In this guide, we will delve into the factors that make Rafah a focal point for international interest, examining its historical context, humanitarian challenges, and political dimensions.
ASHWINI KUMAR UPADHYAY v/s Union of India.pptxshweeta209
transfer of the P.I.L filed by lawyer Ashwini Kumar Upadhyay in Delhi High Court to Supreme Court.
on the issue of UNIFORM MARRIAGE AGE of men and women.
Car Accident Injury Do I Have a Case....Knowyourright
Every year, thousands of Minnesotans are injured in car accidents. These injuries can be severe – even life-changing. Under Minnesota law, you can pursue compensation through a personal injury lawsuit.
In 2020, the Ministry of Home Affairs established a committee led by Prof. (Dr.) Ranbir Singh, former Vice Chancellor of National Law University (NLU), Delhi. This committee was tasked with reviewing the three codes of criminal law. The primary objective of the committee was to propose comprehensive reforms to the country’s criminal laws in a manner that is both principled and effective.
The committee’s focus was on ensuring the safety and security of individuals, communities, and the nation as a whole. Throughout its deliberations, the committee aimed to uphold constitutional values such as justice, dignity, and the intrinsic value of each individual. Their goal was to recommend amendments to the criminal laws that align with these values and priorities.
Subsequently, in February, the committee successfully submitted its recommendations regarding amendments to the criminal law. These recommendations are intended to serve as a foundation for enhancing the current legal framework, promoting safety and security, and upholding the constitutional principles of justice, dignity, and the inherent worth of every individual.
Introducing New Government Regulation on Toll Road.pdfAHRP Law Firm
For nearly two decades, Government Regulation Number 15 of 2005 on Toll Roads ("GR No. 15/2005") has served as the cornerstone of toll road legislation. However, with the emergence of various new developments and legal requirements, the Government has enacted Government Regulation Number 23 of 2024 on Toll Roads to replace GR No. 15/2005. This new regulation introduces several provisions impacting toll business entities and toll road users. Find out more out insights about this topic in our Legal Brief publication.
NATURE, ORIGIN AND DEVELOPMENT OF INTERNATIONAL LAW.pptxanvithaav
These slides helps the student of international law to understand what is the nature of international law? and how international law was originated and developed?.
The slides was well structured along with the highlighted points for better understanding .
WINDING UP of COMPANY, Modes of DissolutionKHURRAMWALI
Winding up, also known as liquidation, refers to the legal and financial process of dissolving a company. It involves ceasing operations, selling assets, settling debts, and ultimately removing the company from the official business registry.
Here's a breakdown of the key aspects of winding up:
Reasons for Winding Up:
Insolvency: This is the most common reason, where the company cannot pay its debts. Creditors may initiate a compulsory winding up to recover their dues.
Voluntary Closure: The owners may decide to close the company due to reasons like reaching business goals, facing losses, or merging with another company.
Deadlock: If shareholders or directors cannot agree on how to run the company, a court may order a winding up.
Types of Winding Up:
Voluntary Winding Up: This is initiated by the company's shareholders through a resolution passed by a majority vote. There are two main types:
Members' Voluntary Winding Up: The company is solvent (has enough assets to pay off its debts) and shareholders will receive any remaining assets after debts are settled.
Creditors' Voluntary Winding Up: The company is insolvent and creditors will be prioritized in receiving payment from the sale of assets.
Compulsory Winding Up: This is initiated by a court order, typically at the request of creditors, government agencies, or even by the company itself if it's insolvent.
Process of Winding Up:
Appointment of Liquidator: A qualified professional is appointed to oversee the winding-up process. They are responsible for selling assets, paying off debts, and distributing any remaining funds.
Cease Trading: The company stops its regular business operations.
Notification of Creditors: Creditors are informed about the winding up and invited to submit their claims.
Sale of Assets: The company's assets are sold to generate cash to pay off creditors.
Payment of Debts: Creditors are paid according to a set order of priority, with secured creditors receiving payment before unsecured creditors.
Distribution to Shareholders: If there are any remaining funds after all debts are settled, they are distributed to shareholders according to their ownership stake.
Dissolution: Once all claims are settled and distributions made, the company is officially dissolved and removed from the business register.
Impact of Winding Up:
Employees: Employees will likely lose their jobs during the winding-up process.
Creditors: Creditors may not recover their debts in full, especially if the company is insolvent.
Shareholders: Shareholders may not receive any payout if the company's debts exceed its assets.
Winding up is a complex legal and financial process that can have significant consequences for all parties involved. It's important to seek professional legal and financial advice when considering winding up a company.
RIGHTS OF VICTIM EDITED PRESENTATION(SAIF JAVED).pptxOmGod1
Victims of crime have a range of rights designed to ensure their protection, support, and participation in the justice system. These rights include the right to be treated with dignity and respect, the right to be informed about the progress of their case, and the right to be heard during legal proceedings. Victims are entitled to protection from intimidation and harm, access to support services such as counseling and medical care, and the right to restitution from the offender. Additionally, many jurisdictions provide victims with the right to participate in parole hearings and the right to privacy to protect their personal information from public disclosure. These rights aim to acknowledge the impact of crime on victims and to provide them with the necessary resources and involvement in the judicial process.
Responsibilities of the office bearers while registering multi-state cooperat...Finlaw Consultancy Pvt Ltd
Introduction-
The process of register multi-state cooperative society in India is governed by the Multi-State Co-operative Societies Act, 2002. This process requires the office bearers to undertake several crucial responsibilities to ensure compliance with legal and regulatory frameworks. The key office bearers typically include the President, Secretary, and Treasurer, along with other elected members of the managing committee. Their responsibilities encompass administrative, legal, and financial duties essential for the successful registration and operation of the society.
Military Commissions details LtCol Thomas Jasper as Detailed Defense CounselThomas (Tom) Jasper
Military Commissions Trial Judiciary, Guantanamo Bay, Cuba. Notice of the Chief Defense Counsel's detailing of LtCol Thomas F. Jasper, Jr. USMC, as Detailed Defense Counsel for Abd Al Hadi Al-Iraqi on 6 August 2014 in the case of United States v. Hadi al Iraqi (10026)
Military Commissions details LtCol Thomas Jasper as Detailed Defense Counsel
Slides from the niceties of notices and their importance for construction claims
1. 1
www.vwv.co.uk | Offices in London, Bristol & Birmingham
Lawyers & Parliamentary Agents
The niceties of notices
Thursday 11th February 2016
Jeffrey Brown, partner
www.vwv.co.uk | Offices in London, Bristol & Birmingham
Lawyers & Parliamentary Agents
Introduction
Changes introduced by LDEDC Act 2009:
• Payment notice 110A
• Default payment notice S.110B
• Pay less notice S.111
www.vwv.co.uk | Offices in London, Bristol & Birmingham
Lawyers & Parliamentary Agents
Introduction
• ISG Construction Ltd -v- Seevic College [December 2014]
• Paice and Springall -v- Harding [Court of Appeal December 2015]
• Galliford Try Building Ltd -v- Estura Ltd [February 2015]
2. 2
www.vwv.co.uk | Offices in London, Bristol & Birmingham
Lawyers & Parliamentary Agents
Introduction
Two major problems?
(1) Difficulties in distinguishing between:
payee’s entitlement; and
the correct valuation of the payee’s work
They can be, but are not the same
(2) Also payer’s problems with recovering overpayment - a particular
problem with the current increased risk of insolvency within the
industry
www.vwv.co.uk | Offices in London, Bristol & Birmingham
Lawyers & Parliamentary Agents
Changes introduced by LDEDC Act 2009
Act defines the “Payer” ,“ Payee” and “Specified Person”
S. 110A
Payment notice - no later than five days after the payment due date
Specify the amount due and basis for calculation
Must provide the notice even if the sum due is zero
Contract to provide for the payer or the payee to give the payment
notice
www.vwv.co.uk | Offices in London, Bristol & Birmingham
Lawyers & Parliamentary Agents
Changes introduced by LDEDC Act 2009
S.110B
Applies where the contract provides for a payer’s notice to be given
not later than 5 days after the payment due date
If no payment notice provided by payer within this timescale, then
the unpaid party may give a default payment notice at any time after
the payer’s notice was required to be given
In this event the payee must also specify the amount due and basis
for calculation
3. 3
www.vwv.co.uk | Offices in London, Bristol & Birmingham
Lawyers & Parliamentary Agents
Changes introduced by LDEDC Act 2009
S.111
• Requirement is to pay the notified sum
• Payer has a right to provide notice of intention to pay less than the
notified sum Notice will state the sum the paying party considers is
due and the basis on which that sum has been calculated as of the
date that the notice was served (as opposed to the date of the
original valuation)
• To be given within the prescribed period before the final date for
payment. If none in contract Scheme states period is 7 days and
the final date for payment is 17 days from the due date for
payment
www.vwv.co.uk | Offices in London, Bristol & Birmingham
Lawyers & Parliamentary Agents
Changes introduced by LDEDC Act 2009
• Primary purpose of legislation is to preserve cash flow
• Payer has two opportunities to get it right
• Payment is of notified sum considered to be due less the amount
specified within the pay less notice. In such a case the balance
becomes the sum that is due.
• Sum due not defined
• 3 cases. All employer/contractor disputes, involving JCT Standard
Forms where the Employer fails to serve requisite notices.
www.vwv.co.uk | Offices in London, Bristol & Birmingham
Lawyers & Parliamentary Agents
ISG Construction Ltd v Seevic College
2015 BLR 233 (December 2014)
Edwards-Stuart J
• JCT Design and Build Contract 2011
• (Application No 13) in the sum of £1,097,696.29
• Seevic had not served a payment notice or a pay less notice
• Adjudicator (First decision) awards ISG being amount claimed in its
payment application.
4. 4
www.vwv.co.uk | Offices in London, Bristol & Birmingham
Lawyers & Parliamentary Agents
ISG Construction Ltd v Seevic College
2015 BLR 233 (December 2014)
• ISG was successful in its applications. Entitled to be paid in full the
amount awarded in the first adjudication. The Second Adjudication
was invalid and un-enforceable. The issue of ISG’s entitlement had
already been decided.
• The statutory regime would be completely undermined if the
employer, having failed to issue the necessary payment or pay less
notice, could refer to adjudication the question of the value of the
contractor’s work at the time of the interim application and then
seek a decision requiring a payment to or a repayment by the
contractor based on the difference between the value of the work
as determined by the adjudicator and the sums already paid under
the contract (see paras 28, 31-32, 47 of the judgment)
www.vwv.co.uk | Offices in London, Bristol & Birmingham
Lawyers & Parliamentary Agents
Galliford Try Building Ltd v Estura Ltd
(February 2015)
Edwards-Stuart J
Galliford Try (“GT”) applied for summary judgment to enforce an
adjudicator’s decision that Estura should pay it approximately £4
million.
GT made an interim application described as an “Indicative Final
Account and valuation summary” and after Estura failed to serve
either a payment and/or a pay-less notice, the adjudicator found that
GT became entitled to the sum stated in its application.
GT had been awarded all that it has claimed so that little incentive to
submit a final account.
www.vwv.co.uk | Offices in London, Bristol & Birmingham
Lawyers & Parliamentary Agents
Galliford Try Building Ltd v Estura Ltd
(February 2015)
• Estura could not bring a second adjudication to determine the
value of the work at the valuation date of the interim application
but there was nothing to prevent Estura from challenging the value
of the work on the next application. This view would seem to be
supported by the Court of Appeal’s decision Paice and Springall -v-
Harding (see post)
5. 5
www.vwv.co.uk | Offices in London, Bristol & Birmingham
Lawyers & Parliamentary Agents
Paice and Springall -v- Harding
Paice and Springall -v- Harding t/a M J Harding Contractors [Court of
Appeal 01.12.2015]
“I do not need to decide whether or not that passage is correct in
relation to interim valuations and interim payments. In almost all
construction contracts special contractual provisions apply to
interim payments. Mistakes can usually be put right at a later stage,
although that was not possible in Galliford because the contract
prevented negative valuations.
www.vwv.co.uk | Offices in London, Bristol & Birmingham
Lawyers & Parliamentary Agents
Paice and Springall -v- Harding
The important point for present purposes is that the quoted
passage (whether right or wrong in relation to interim valuations)
does not apply to final accounts. Edwards-Stuart J said so in
Galliford at [25], where he emphasised the “fundamental
difference” between payment obligations which arise on an interim
application and those that arise on termination.
www.vwv.co.uk | Offices in London, Bristol & Birmingham
Lawyers & Parliamentary Agents
Paice and Springall -v- Harding
In my view the employer’s failure to serve a Pay Less notice (as held
by the previous adjudicator) had limited consequences. It meant
that the employer had to pay the full amount shown on the
contractor’s account and argue about the figures later. The
employer duly paid that sum, as ordered by the previous
adjudicator. The employer is now entitled to proceed to
adjudication in order to determine the correct value of the
contractor’s claims and the employer’s counter-claims. Therefore
the judge’s decision was correct.”
6. 6
www.vwv.co.uk | Offices in London, Bristol & Birmingham
Lawyers & Parliamentary Agents
Points for discussion
1. It should come as no surprise that the courts will interpret the
timescales strictly and will not grant relief if pay less notices are
made late and out of time. But note the need at all times for
clarity.
(a) In Caledonian Modular Limited v Mar City Developments Limited
[2015]
at paragraph 37, Coulson J said:
"...if contractors want the benefit of these provisions, they are
obliged, in return, to set out their interim payment claims with proper
clarity. If the employer is to be put at risk that a failure to serve a
payless notice at the appropriate time during the payment period will
render him liable in full for the amount claimed, he must be given
www.vwv.co.uk | Offices in London, Bristol & Birmingham
Lawyers & Parliamentary Agents
reasonable notice that the payment period has been triggered in the
first place.";
(b) In Henia Investments v Beck Interiors Limited [2015] Akenhead J
said:
"...the document relied upon as an Interim Application ... must be in
substance, form and intent an Interim Application stating the sum
considered by the Contractor as due at the relevant due date and it
must be free from ambiguity. In this context, the Interim Application
should be considered in the same light as a certificate. If there are to
be potentially serious consequences flowing from it being an Interim
Application, it must be clear that it is what it purports to be so that
the parties know what to do about it and when."
www.vwv.co.uk | Offices in London, Bristol & Birmingham
Lawyers & Parliamentary Agents
Parties will implement the procedures set out in Part 8 CPR as will be
seen in the Caledonian and Henia Investments decisions. Their use
and their effect may be limited, however, to issues of law and the
proper interpretation of agreements and notices. Thus in Geoffrey
Osborne Limited -v- Atkins Rail Limited 2009 the court could hear a
challenge to an adjudicator’s decision provided the issue did not
involve a substantial dispute of fact and was one that could be finally
determined on the material before the court. This related to an
attempt to enforce an adjudicator’s decision by way of summary
judgment.
7. 7
www.vwv.co.uk | Offices in London, Bristol & Birmingham
Lawyers & Parliamentary Agents
Points for discussion
2. It was made clear in Galliford Try and Estura that the failure to
serve a relevant pay less notice did not prevent the employer
from challenging the value of the work on the next application
even if he is contending for a figure that is lower than the
"unchallenged" amount stated in the previous application.
Reliance was made upon the decision of the Court of Appeal in
Rupert Morgan Building Services (LLC) Limited -v- Jarvis [2004
1WR1867] :
The point was mentioned but not decided in the Judgment of Jackson
L.J. in Paice and Springall
www.vwv.co.uk | Offices in London, Bristol & Birmingham
Lawyers & Parliamentary Agents
Points for discussion
3. It was made clear in Galliford Try and Estura (see paragraph 23 of
the judgment) that this form of contract did not provide for a
negative valuation.
"The first, which is a point of general application, is that this form
of contract does not provide for a negative valuation. Although this
point was not fully argued during the hearing, I am prepared, in
principle, to accept that it is correct in the light of the wording of
clause 4.9 of the contract. Mr. Hickey pointed out that this is what
the parties signed up to and they should not be indulged if it proves
to be inconvenient."
www.vwv.co.uk | Offices in London, Bristol & Birmingham
Lawyers & Parliamentary Agents
Points for discussion
4. In Estura, the Court relied upon the Rupert Morgan Building
Services (LLC) Limited -v- Jarvis decision as supporting the principle
that an employer could challenge the value of the work on the
next application.
This was relied upon by the Court of Appeal in Paice and Springall -v-
Harding. However in this judgment the point arose within the context
of the Final Account.
8. 8
www.vwv.co.uk | Offices in London, Bristol & Birmingham
Lawyers & Parliamentary Agents
Points for discussion
5. There is no restriction on the parties agreeing what are to be the
due dates and thus the final dates for payment. It must be
considered good practice for these dates to be identified at the
outset given the specific importance of key dates and the timely
despatch of any pay less notice.
Payer can also insist that the contract affords it and not the payee to
deliver the payment notice.
www.vwv.co.uk | Offices in London, Bristol & Birmingham
Lawyers & Parliamentary Agents
Points for discussion
6. It is important to consider the wording of clause 4.15.2 of the JCT
2011 Standard Form of Contract.
"The Final Certificate shall state:
• the Ascertained Final Sum as calculated in accordance with clause
4.3; and
• the sum of amounts already stated as due;
• the final payment shall be the difference (if any) between the two
sums
www.vwv.co.uk | Offices in London, Bristol & Birmingham
Lawyers & Parliamentary Agents
Points for discussion
This same issue does not arise specifically in the NEC3 standard form.
Clause 50.1, for example, states that:-
"The Project Manager assesses the amount due at each assessment
date".
This is to suggest that each assessment is to be regarded as being a
separate process. For the avoidance of doubt, Clause 50.5 states
that:-
"The Project Manager corrects any wrongly assessed amount due in
a later payment certificate".
9. 9
www.vwv.co.uk | Offices in London, Bristol & Birmingham
Lawyers & Parliamentary Agents
Points for discussion
7. Question the need for adjudication where payer clearly in default.
Benefits of summary judgment application. Part 24 CPR
This topic was discussed in Severfield (UK) Limited -v- Duro Felguera
UK Limited (November 2015)
“Adjudication ……………….is an effective and efficient dispute
resolution process. Far from being a “punishment”, it has been
generally regarded as a blessing by the construction industry”.
www.vwv.co.uk | Offices in London, Bristol & Birmingham
Lawyers & Parliamentary Agents
Drafting checklist
• Employer should insist on payment notice
• Parties should clearly identify within the contract what are the due
dates for payment and final dates for payment
• Main contractors to synchronise main contract dates with those of
its sub-contractors
• Include a severance clause. If one part of the contract not
compliant the whole of the Scheme should not apply.
www.vwv.co.uk | Offices in London, Bristol & Birmingham
Lawyers & Parliamentary Agents
Drafting checklist
• Allow for express right to recover overpayment
• Allow NEC type clause for determining interim valuations
• Specific amendment to 4.15.2 of JCT 2011 Standard Form
• Wide powers for a judge or arbitrator to open up, revise or review
any decision of an adjudicator
• Project Managers need to be aware and vigilant at all times
10. 10
www.vwv.co.uk | Offices in London, Bristol & Birmingham
Lawyers & Parliamentary Agents
Jeffrey Brown
Partner
jbrown@vwv.co.uk
DDI: 020 7665 0844
The Niceties of Notices
An NEC Perspective
February 2016
‘Giving priority to your commercial success’
www.gvecs.co.uk
Introduction
• The NEC is ‘hot’ on notices
• Cl. 60.1 - “The following are compensation events”
• When is a compensation event not a compensation
event?
– When the process hasn’t begun?
– When it is time barred?
• Is Cl. 61.3 complicated?
- “expect” / “believe” / “aware”
- Does the first half of the clause = the second half (time bar)?
• Do we have any case law to help us?
www.gvecs.co.uk
11. 11
NEC Clause 61.3
-The Contractor notifies the Project Manager of an event
which has happened or which he expects to happen as a
compensation event if:
– the Contractor believes that the event is a compensation event
and
– The Project Manager has not notified the event to the Contractor
-If the Contractor does not notify a compensation event
within eight weeks of becoming aware of the event, he is
not entitled to a Change in the Prices, the Completion Date
or a Key Date unless the event arises from the Project
Manager or the Supervisor issuing an instruction, issuing a
certificate, changing an earlier decision or correcting an
assumption
www.gvecs.co.uk
NEC3
• What is the NEC promoting?
– Speedy resolution of ‘claims’
– Non-adversarial approach
– Emphasis on early warning and early resolution
– Simple & speedy final accounts
• What do us consultants see happening?
– Cl. 61.3 time periods reducing
– Project Manager’s (& Contractors) not doing their bit (not issuing
instructions and compensation event notices)
– Both sides ignoring the notice provisions
– End of project reliance on Cl.61.3 time bar
www.gvecs.co.uk
Van Oord v Allseas case
• Van Oord UK Ltd v Allseas UL Ltd 2015
• Shetland Isles – gas pipeline – ground condition claim
• Contract provided for notice within 5 days of the event
• Contract also required full details within 7 further days
• Compliance was noted as a ‘condition precedent’
• Contractor failed:
• Its ground condition claim was unsuccessful
• Notice was 2 days late (very strict!)
• Notice did not refer to correct clause (very strict!)
How might this impact upon the NEC notice provisions?
www.gvecs.co.uk
12. 12
Obrascon case
• Obrascon Huarte Lain SA v Her Majesty’s Attorney
General for Gibraltar – Mr Justice Akenhead – 2014
• FIDIC Yellow Book (usually private – arbitration)
• Cl. 20.1 - Generally regarded as effective and
enforceable ‘condition precedent’ clause
• Cl. 20.1:
– “as soon as practicable, and not later than 28 days after the
Contractor became aware, or should have become aware, of the
event or circumstance”
• Judge said there was an alternative interpretation of
clause 8.4
– “is or will be delayed” AND NOT
– “is or will be delayed, whichever is the earliest”
www.gvecs.co.uk
Obrascon case
• Mr Justice Akenhead said he could “see no reason why it
should be construed strictly against the Contractor” and could “see
reason why it should be construed reasonably broadly, given its
serious effect on what could otherwise be good claims”
• The event or circumstance can mean either the event
itself or the delay (or cost) which results from the event
• What form must the notice take?
– FIDIC doesn’t require a specific form
– Must be in writing
– Must be recognisable as a notice (of a claim)
www.gvecs.co.uk
Northern Ireland case
• Northern Ireland Housing Executive v Health Buildings
(Ireland) Ltd 2014 (non-binding)
• Cl. 61.3 - 2005 version v 2013 version
• When the Project Manager (or Employer – PSC) “should
have” done something but didn’t do it!
• What did the Court say?:
– “the wording in the contract was clear”
– “even if there was an ambiguity in the wording it should be
interpreted against NIHE as it constituted a time bar which would
operate in NIHE’s favour”
– “The requirement to give notice under clause 61.3 was to be
assessed objectively”
www.gvecs.co.uk
13. 13
Conclusion
• Very limited legal commentary on NEC cl. 61.3 and its
time bar provisions
• Suspected ‘raft’ of adjudicator decisions/opinions?
• These cases would suggest the law is undecided?
- (to be strict or not to be strict?)
• My view on Cl. 61.3?
• A Contractor may lose its entitlement if it fails to strictly
comply with notice provisions (Van Oord case)
• Contractors & Sub-contractors - Issue notices!!
• A lot might depend upon:
- How the parties have dealt with one another
- How strictly they have applied the NEC procedures
www.gvecs.co.uk
ANY QUESTIONS ?
www.gvecs.co.uk