Rig & equipment
selection continued
Peter Aird
November 2008
Sub Sea Capital drilling equipment
1. Diverter
2. Spider / Gimbal
3. Riser Coupling
4. Upper Flex Joint
5. Telescopic Joint
6. Tensioning Ring
7. Intermediate Flex Joint
8. Termination Joint
9. Riser Adapter
10. Single Flex Joint
11. BOP Connector
12. Wellhead Connector
13. Wellhead
3
1
2
6
4
7
9
13
5
8
10
11
12
3
1
2
6
4
7
9
13
5
8
10
11
12
Standard Diverter system
 Pressure rating
 Internal diameter
 Seals
 Testing
 Limitations!
 Handling gas at
surface
1. Deepwater diverter system
 Used on the majority of floating rigs
 Complete open-hole shutoff with 20”
through-bore
 Rated 1,000 psi for closure on 5” drill pipe;
500 psi for closure on open hole
 10 second closing time on pipe or open
hole
 Housing accommodates large diameter
riser buoyancy modules
 High capacity systems available for
supporting the Riser String from Diverter
Housing in emergency hang-off situations
2.1 Spider
 Hydraulic-gate riser spider
is used when running or
retrieving riser joints
through the rotary table
 Riser handling spider
supports the riser string
on manual or hydraulically
operated sliding dogs
2.2 Riser Gimbal
 Gimbal shock absorber
supports up to 2,000,000
lb and gimbals when the
riser is positioned in the
spider
 Reduces impact loads
when running and landing
marine riser joints
3.1 Riser connector
 Easy stabbing, fast makeup, and positive
alignment
 Suitable for operating in water depths up
to 7,500 ft depending on environmental
and well control conditions; MR-10
designs can operate in depths to 10,000
ft.
 Preloaded connection significantly
reduces the range of alternating stresses
induced by cyclic loading to improve
fatigue life
 Primary load path for tensile and bending
loads through the dogs and into the body,
does not impact actuating screws
3.2 API Riser Coupling Class
API Riser
Coupling Class
Tensile capacity in
millions of pounds
Class A .5
Class B 1
Class C 1.25
Class D 1.5
Class E 2
Class F 2.5
Class H 3.5
API RP 2R establishes riser coupling classes based on the
tensile capacity of the coupling. These are;
3.3 Riser coupling
 Ideal for deep water applications
where high load operating
conditions exist
 Stepped diameter design of pin
and box simplifies engagement,
even with severe vessel
movement
 No loose parts preventing bolt loss
and potential thread damage
 Field removable and replaceable
nose piece
 Locking bolts preloaded in excess
of rated coupling loads to extend
fatigue load of riser system
Drilling riser (1)
 Choke line
 Kill line
 Hydraulic lines
 Prepared for
buoyancy
 Seals
 Testing considerations
Drilling riser (2)
Drilling riser (3)
4. Riser Flex joint
 Tensional capacity
 Through bore
 Ball joint limits
5. Telescopic Joint
 Compensates for heave and
offset of the vessel
 Maximum rated riser tensile
load capacity in locked
position
 Hydraulic latch release for
inner and outer barrels
available
 Dual split/solid packer
elements
 Fixed or rotating integral/non-
integral tensioner rings
6.1 Riser support ring
 The Type Riser Tensioner Ring
shown saves time because the riser
tensioner cables are never
disconnected.
 When the riser is pulled the
tensioner ring will be carried up to
the bottom of the diverter housing.
Hydraulic latches release the ring
from the slip joint and permit it to be
locked onto the diverter housing
using another set of hydraulic latch
dogs. The rest of the riser is
retrieved through its center.
6.2 Tension ring
 Telescopic Joint is run and pulled through the rotary table
without disconnecting the tensioning lines from riser tensiong
ring
 Riser tensioning lines remain properly spaced out at all times
 Hydraulic piping for lockdown/storage dogs remains
permanently connected
 Hydraulically disconnects from telescopic joint and locks to a
mating profile on the bottom of the diverter housing for
convenient, out-of-the-way storage
6.3 Ultra deep tension ring
 Forms a termination point between the riser
tensioner and the marine riser system
 Simplifies running and retrieving marine
riser by eliminating makeup/breakout of
tensioner lines and hydraulic hoses in the
moon pool area
 Choke, kill, and auxiliary line terminations
permanently connected
 Orientation pins on the ring engage slots in
telescopic joint line termination housing for
easy makeup
 Permanently installed tensioner lines
maintain proper orientation with rig drilling
tensioners
7. Intermediate Flex Joint
 Installed below the telescopic joint
 Up to 2.5 million lb tensile load capacity
 Angular deflection to 20 °on either side of its axial
center while subjected to tensile loading and
internal pressure of 1500 psi
Intermediate Flex Joint shown uses a KT ring and no termination joint.
9. Riser extension (adaptor)
10. Single flex joint
 Installed in the LMRP below the
riser/BOP Stack Interface
 Uses a combination elastomeric
bearing and seal unit to eliminate
the need for a pressure balanced
ball and socket interface with
seals
 Up to 2 million lb tensile load
capacity
 Rated for H2S service and oil-
based drilling mud
 Angular deflection to 10° on either
side of its axial center while
subjected to tensile loading and
internal pressures up to 3000 psi
 Pressure balance and lubrication
systems not required
11-12 System design aspects
 System Objective:
 Solution for drilling in
ultra deepwater drilling
 BOP Flange
 Wellhead Connector
 Subsea Wellhead System
 Conductor Sizing
(Analysis)
 Conductor/Casing
Connectors
 15,000 psi to 20,000 psi
rated pressure
 7,000,000 ft.-lbs.
Bending @ 15,000 psi
F
~6.6 MM ft-lbs
~7 MM ft-lbs
~7.7 MM ft-lbs
~14 MM ft-lbs
(40' Below Mudline)
~8.4 MM ft-lbs

BOP Flange
Wellhead
Connector
Wellhead
System
Conductor/
Casing
Connectors
F
~6.6 MM ft-lbs
~7 MM ft-lbs
~7.7 MM ft-lbs
~14 MM ft-lbs
(40' Below Mudline)
~8.4 MM ft-lbs

BOP Flange
Wellhead
Connector
Wellhead
System
Conductor/
Casing
Connectors
BOP Flange
Wellhead
Connector
Wellhead
System
Conductor/
Casing
Connectors
Questions?

More Related Content

What's hot

Drilling Bit Introduction and bit Selection (Part 3)
Drilling Bit Introduction and bit Selection (Part 3)Drilling Bit Introduction and bit Selection (Part 3)
Drilling Bit Introduction and bit Selection (Part 3)Amir Rafati
 
Landing nipples X & XN
Landing nipples X & XN Landing nipples X & XN
Landing nipples X & XN Elsayed Amer
 
Wellhead equipment Introduction Based on API 6a & NACE
Wellhead equipment Introduction Based on API 6a & NACEWellhead equipment Introduction Based on API 6a & NACE
Wellhead equipment Introduction Based on API 6a & NACEAmir Rafati
 
Completion equipment packer part #1
Completion equipment packer part #1Completion equipment packer part #1
Completion equipment packer part #1Elsayed Amer
 
Wenzel Downhole Tools Product Catalogue
Wenzel Downhole Tools Product CatalogueWenzel Downhole Tools Product Catalogue
Wenzel Downhole Tools Product CatalogueWenzel Downhole Tools
 
Best practices day 4 am new
Best practices day 4 am newBest practices day 4 am new
Best practices day 4 am newAhmed Radwan
 
Fundamentals of Petroleum Engineering Module 4
Fundamentals of Petroleum Engineering Module 4Fundamentals of Petroleum Engineering Module 4
Fundamentals of Petroleum Engineering Module 4Aijaz Ali Mooro
 
To Study Well Design Aspects in HPHT Environment
To  Study Well Design Aspects in HPHT EnvironmentTo  Study Well Design Aspects in HPHT Environment
To Study Well Design Aspects in HPHT EnvironmentNikhil Barshettiwar
 
Installation procedures of wellhead
Installation procedures of wellheadInstallation procedures of wellhead
Installation procedures of wellheadElsayed Amer
 
Sequence of well completion part 1
Sequence of well completion part 1Sequence of well completion part 1
Sequence of well completion part 1Elsayed Amer
 
04 Hpht Gas Migration Co2(4 08 06)
04 Hpht Gas Migration Co2(4 08 06)04 Hpht Gas Migration Co2(4 08 06)
04 Hpht Gas Migration Co2(4 08 06)JRThompson8747
 
Drilling Problems.pdf
Drilling Problems.pdfDrilling Problems.pdf
Drilling Problems.pdfTinaMarey
 
Drilling rigs main compnents
Drilling rigs main compnentsDrilling rigs main compnents
Drilling rigs main compnentsRIZWAN KHAN
 
Plug & Abandonment
Plug & AbandonmentPlug & Abandonment
Plug & AbandonmentStatoil
 

What's hot (20)

Drilling Bit Introduction and bit Selection (Part 3)
Drilling Bit Introduction and bit Selection (Part 3)Drilling Bit Introduction and bit Selection (Part 3)
Drilling Bit Introduction and bit Selection (Part 3)
 
Landing nipples X & XN
Landing nipples X & XN Landing nipples X & XN
Landing nipples X & XN
 
Wellhead
WellheadWellhead
Wellhead
 
Wellhead basics
Wellhead basicsWellhead basics
Wellhead basics
 
Wellhead equipment Introduction Based on API 6a & NACE
Wellhead equipment Introduction Based on API 6a & NACEWellhead equipment Introduction Based on API 6a & NACE
Wellhead equipment Introduction Based on API 6a & NACE
 
Completion equipment packer part #1
Completion equipment packer part #1Completion equipment packer part #1
Completion equipment packer part #1
 
Wenzel Downhole Tools Product Catalogue
Wenzel Downhole Tools Product CatalogueWenzel Downhole Tools Product Catalogue
Wenzel Downhole Tools Product Catalogue
 
Best practices day 4 am new
Best practices day 4 am newBest practices day 4 am new
Best practices day 4 am new
 
Fundamentals of Petroleum Engineering Module 4
Fundamentals of Petroleum Engineering Module 4Fundamentals of Petroleum Engineering Module 4
Fundamentals of Petroleum Engineering Module 4
 
To Study Well Design Aspects in HPHT Environment
To  Study Well Design Aspects in HPHT EnvironmentTo  Study Well Design Aspects in HPHT Environment
To Study Well Design Aspects in HPHT Environment
 
Installation procedures of wellhead
Installation procedures of wellheadInstallation procedures of wellhead
Installation procedures of wellhead
 
Wellheads Training .pdf
Wellheads Training .pdfWellheads Training .pdf
Wellheads Training .pdf
 
Sequence of well completion part 1
Sequence of well completion part 1Sequence of well completion part 1
Sequence of well completion part 1
 
04 Hpht Gas Migration Co2(4 08 06)
04 Hpht Gas Migration Co2(4 08 06)04 Hpht Gas Migration Co2(4 08 06)
04 Hpht Gas Migration Co2(4 08 06)
 
Drilling Problems.pdf
Drilling Problems.pdfDrilling Problems.pdf
Drilling Problems.pdf
 
Ssd spm
Ssd   spmSsd   spm
Ssd spm
 
Bits
BitsBits
Bits
 
Drilling rigs main compnents
Drilling rigs main compnentsDrilling rigs main compnents
Drilling rigs main compnents
 
Petroleum drilling fundamentals
Petroleum drilling fundamentalsPetroleum drilling fundamentals
Petroleum drilling fundamentals
 
Plug & Abandonment
Plug & AbandonmentPlug & Abandonment
Plug & Abandonment
 

Similar to Deepwater sub sea capital equipment

BOTTOM HOLE SURVEILLANCE UNIT
BOTTOM HOLE SURVEILLANCE UNITBOTTOM HOLE SURVEILLANCE UNIT
BOTTOM HOLE SURVEILLANCE UNITB. Budi Wicaksono
 
Paper 43 - Deep Water Pipeline CT 9_2_15
Paper 43 - Deep Water Pipeline CT 9_2_15Paper 43 - Deep Water Pipeline CT 9_2_15
Paper 43 - Deep Water Pipeline CT 9_2_15John Grover
 
Subsea Intervention System (SIS) - Worldwide Oilfield Machine
Subsea Intervention System (SIS) - Worldwide Oilfield MachineSubsea Intervention System (SIS) - Worldwide Oilfield Machine
Subsea Intervention System (SIS) - Worldwide Oilfield Machinewomgroup
 
Transocean offshore operation 2
Transocean   offshore operation 2Transocean   offshore operation 2
Transocean offshore operation 2Steffones K
 
Anchor winch. Marina mercante. Maquinaria.pptx
Anchor winch. Marina mercante. Maquinaria.pptxAnchor winch. Marina mercante. Maquinaria.pptx
Anchor winch. Marina mercante. Maquinaria.pptxDarlenysFonseca1
 
FolderTrislotPetrochemie2015_Lowres
FolderTrislotPetrochemie2015_LowresFolderTrislotPetrochemie2015_Lowres
FolderTrislotPetrochemie2015_LowresCorey Brightwell
 
Report steffones
Report steffonesReport steffones
Report steffonesSteffones K
 
Coiled Tubing Introduction and Basics.pdf
Coiled Tubing Introduction and Basics.pdfCoiled Tubing Introduction and Basics.pdf
Coiled Tubing Introduction and Basics.pdfsalem123gmaal
 
Thames Side LeverMount Load Cell and Weighing Assembly (Weigh Module)
Thames Side LeverMount Load Cell and Weighing Assembly (Weigh Module)Thames Side LeverMount Load Cell and Weighing Assembly (Weigh Module)
Thames Side LeverMount Load Cell and Weighing Assembly (Weigh Module)Thames Side Sensors
 
05 drilling methods
05  drilling methods05  drilling methods
05 drilling methodsgraham101231
 
Underbalance drilling equipment
Underbalance  drilling equipmentUnderbalance  drilling equipment
Underbalance drilling equipmentshivan abdalrahman
 

Similar to Deepwater sub sea capital equipment (20)

Hytork water operated valve actuator
Hytork water operated valve actuatorHytork water operated valve actuator
Hytork water operated valve actuator
 
BOTTOM HOLE SURVEILLANCE UNIT
BOTTOM HOLE SURVEILLANCE UNITBOTTOM HOLE SURVEILLANCE UNIT
BOTTOM HOLE SURVEILLANCE UNIT
 
Paper 43 - Deep Water Pipeline CT 9_2_15
Paper 43 - Deep Water Pipeline CT 9_2_15Paper 43 - Deep Water Pipeline CT 9_2_15
Paper 43 - Deep Water Pipeline CT 9_2_15
 
Subsea Intervention System (SIS) - Worldwide Oilfield Machine
Subsea Intervention System (SIS) - Worldwide Oilfield MachineSubsea Intervention System (SIS) - Worldwide Oilfield Machine
Subsea Intervention System (SIS) - Worldwide Oilfield Machine
 
Transocean offshore operation 2
Transocean   offshore operation 2Transocean   offshore operation 2
Transocean offshore operation 2
 
The Fuse gate System
The Fuse gate SystemThe Fuse gate System
The Fuse gate System
 
Anchor winch. Marina mercante. Maquinaria.pptx
Anchor winch. Marina mercante. Maquinaria.pptxAnchor winch. Marina mercante. Maquinaria.pptx
Anchor winch. Marina mercante. Maquinaria.pptx
 
Standing type outdoor full sf6 gas insualted ring main unit
Standing type outdoor full sf6 gas insualted ring main unitStanding type outdoor full sf6 gas insualted ring main unit
Standing type outdoor full sf6 gas insualted ring main unit
 
Standing type GIS RMU
Standing type GIS RMUStanding type GIS RMU
Standing type GIS RMU
 
Hydel Generation and Types Of Turbines
Hydel Generation and Types Of TurbinesHydel Generation and Types Of Turbines
Hydel Generation and Types Of Turbines
 
FolderTrislotPetrochemie2015_Lowres
FolderTrislotPetrochemie2015_LowresFolderTrislotPetrochemie2015_Lowres
FolderTrislotPetrochemie2015_Lowres
 
Report steffones
Report steffonesReport steffones
Report steffones
 
Packers GFK
Packers GFKPackers GFK
Packers GFK
 
Coiled Tubing Introduction and Basics.pdf
Coiled Tubing Introduction and Basics.pdfCoiled Tubing Introduction and Basics.pdf
Coiled Tubing Introduction and Basics.pdf
 
Thames Side LeverMount Load Cell and Weighing Assembly (Weigh Module)
Thames Side LeverMount Load Cell and Weighing Assembly (Weigh Module)Thames Side LeverMount Load Cell and Weighing Assembly (Weigh Module)
Thames Side LeverMount Load Cell and Weighing Assembly (Weigh Module)
 
Control Valves
Control ValvesControl Valves
Control Valves
 
Drilling imp
Drilling impDrilling imp
Drilling imp
 
Packers
PackersPackers
Packers
 
05 drilling methods
05  drilling methods05  drilling methods
05 drilling methods
 
Underbalance drilling equipment
Underbalance  drilling equipmentUnderbalance  drilling equipment
Underbalance drilling equipment
 

More from amrhaggag

بنعمل ايه على الصفحة والجروب - أزاى نتعامل مع السكر 1 و 2 من واقع التجربة
بنعمل ايه على الصفحة والجروب - أزاى نتعامل مع السكر 1 و 2 من واقع التجربةبنعمل ايه على الصفحة والجروب - أزاى نتعامل مع السكر 1 و 2 من واقع التجربة
بنعمل ايه على الصفحة والجروب - أزاى نتعامل مع السكر 1 و 2 من واقع التجربةamrhaggag
 
Drilling rig operations a to z rotary drilling rig components
Drilling rig operations  a to z rotary drilling rig componentsDrilling rig operations  a to z rotary drilling rig components
Drilling rig operations a to z rotary drilling rig componentsamrhaggag
 
Drilling rig components ( illustrated glossary )
Drilling rig components ( illustrated glossary )Drilling rig components ( illustrated glossary )
Drilling rig components ( illustrated glossary )amrhaggag
 
Directional drilling
Directional drillingDirectional drilling
Directional drillingamrhaggag
 
rig drilling_equipment
 rig drilling_equipment rig drilling_equipment
rig drilling_equipmentamrhaggag
 
Wild well wc formulas and graphas
Wild well wc formulas and graphasWild well wc formulas and graphas
Wild well wc formulas and graphasamrhaggag
 
Tubing standard
Tubing standardTubing standard
Tubing standardamrhaggag
 
Sysdrill.pdf
Sysdrill.pdfSysdrill.pdf
Sysdrill.pdfamrhaggag
 
Check list for drilling new well
Check list for drilling new wellCheck list for drilling new well
Check list for drilling new wellamrhaggag
 
Wait and weight vs. driller
Wait and weight vs. drillerWait and weight vs. driller
Wait and weight vs. drilleramrhaggag
 
Directional survey hand book
Directional survey hand book Directional survey hand book
Directional survey hand book amrhaggag
 
Wellhead specifications
Wellhead specificationsWellhead specifications
Wellhead specificationsamrhaggag
 
Well control intro presentation
Well control intro presentationWell control intro presentation
Well control intro presentationamrhaggag
 
Oilfield glossary
Oilfield glossaryOilfield glossary
Oilfield glossaryamrhaggag
 
Land rig handbook
Land rig handbookLand rig handbook
Land rig handbookamrhaggag
 
Intro to petroleum geology
Intro to petroleum geologyIntro to petroleum geology
Intro to petroleum geologyamrhaggag
 
Intro to oil well drilling ops pt 4
Intro to oil well drilling ops pt 4Intro to oil well drilling ops pt 4
Intro to oil well drilling ops pt 4amrhaggag
 
Intro to oil well drilling ops pt 3
Intro to oil well drilling ops pt 3Intro to oil well drilling ops pt 3
Intro to oil well drilling ops pt 3amrhaggag
 

More from amrhaggag (20)

بنعمل ايه على الصفحة والجروب - أزاى نتعامل مع السكر 1 و 2 من واقع التجربة
بنعمل ايه على الصفحة والجروب - أزاى نتعامل مع السكر 1 و 2 من واقع التجربةبنعمل ايه على الصفحة والجروب - أزاى نتعامل مع السكر 1 و 2 من واقع التجربة
بنعمل ايه على الصفحة والجروب - أزاى نتعامل مع السكر 1 و 2 من واقع التجربة
 
Drilling rig operations a to z rotary drilling rig components
Drilling rig operations  a to z rotary drilling rig componentsDrilling rig operations  a to z rotary drilling rig components
Drilling rig operations a to z rotary drilling rig components
 
Drilling rig components ( illustrated glossary )
Drilling rig components ( illustrated glossary )Drilling rig components ( illustrated glossary )
Drilling rig components ( illustrated glossary )
 
Directional drilling
Directional drillingDirectional drilling
Directional drilling
 
rig drilling_equipment
 rig drilling_equipment rig drilling_equipment
rig drilling_equipment
 
Wild well wc formulas and graphas
Wild well wc formulas and graphasWild well wc formulas and graphas
Wild well wc formulas and graphas
 
Tubing standard
Tubing standardTubing standard
Tubing standard
 
Sysdrill.pdf
Sysdrill.pdfSysdrill.pdf
Sysdrill.pdf
 
DDMS
DDMSDDMS
DDMS
 
Check list for drilling new well
Check list for drilling new wellCheck list for drilling new well
Check list for drilling new well
 
Wait and weight vs. driller
Wait and weight vs. drillerWait and weight vs. driller
Wait and weight vs. driller
 
Kill sheet
Kill sheetKill sheet
Kill sheet
 
Directional survey hand book
Directional survey hand book Directional survey hand book
Directional survey hand book
 
Wellhead specifications
Wellhead specificationsWellhead specifications
Wellhead specifications
 
Well control intro presentation
Well control intro presentationWell control intro presentation
Well control intro presentation
 
Oilfield glossary
Oilfield glossaryOilfield glossary
Oilfield glossary
 
Land rig handbook
Land rig handbookLand rig handbook
Land rig handbook
 
Intro to petroleum geology
Intro to petroleum geologyIntro to petroleum geology
Intro to petroleum geology
 
Intro to oil well drilling ops pt 4
Intro to oil well drilling ops pt 4Intro to oil well drilling ops pt 4
Intro to oil well drilling ops pt 4
 
Intro to oil well drilling ops pt 3
Intro to oil well drilling ops pt 3Intro to oil well drilling ops pt 3
Intro to oil well drilling ops pt 3
 

Recently uploaded

chaitra-1.pptx fake news detection using machine learning
chaitra-1.pptx  fake news detection using machine learningchaitra-1.pptx  fake news detection using machine learning
chaitra-1.pptx fake news detection using machine learningmisbanausheenparvam
 
Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024hassan khalil
 
Biology for Computer Engineers Course Handout.pptx
Biology for Computer Engineers Course Handout.pptxBiology for Computer Engineers Course Handout.pptx
Biology for Computer Engineers Course Handout.pptxDeepakSakkari2
 
SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )Tsuyoshi Horigome
 
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort service
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort serviceGurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort service
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort servicejennyeacort
 
ZXCTN 5804 / ZTE PTN / ZTE POTN / ZTE 5804 PTN / ZTE POTN 5804 ( 100/200 GE Z...
ZXCTN 5804 / ZTE PTN / ZTE POTN / ZTE 5804 PTN / ZTE POTN 5804 ( 100/200 GE Z...ZXCTN 5804 / ZTE PTN / ZTE POTN / ZTE 5804 PTN / ZTE POTN 5804 ( 100/200 GE Z...
ZXCTN 5804 / ZTE PTN / ZTE POTN / ZTE 5804 PTN / ZTE POTN 5804 ( 100/200 GE Z...ZTE
 
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escortsranjana rawat
 
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube Exchanger
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube ExchangerStudy on Air-Water & Water-Water Heat Exchange in a Finned Tube Exchanger
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube ExchangerAnamika Sarkar
 
main PPT.pptx of girls hostel security using rfid
main PPT.pptx of girls hostel security using rfidmain PPT.pptx of girls hostel security using rfid
main PPT.pptx of girls hostel security using rfidNikhilNagaraju
 
Introduction to Microprocesso programming and interfacing.pptx
Introduction to Microprocesso programming and interfacing.pptxIntroduction to Microprocesso programming and interfacing.pptx
Introduction to Microprocesso programming and interfacing.pptxvipinkmenon1
 
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...Soham Mondal
 
microprocessor 8085 and its interfacing
microprocessor 8085  and its interfacingmicroprocessor 8085  and its interfacing
microprocessor 8085 and its interfacingjaychoudhary37
 
Artificial-Intelligence-in-Electronics (K).pptx
Artificial-Intelligence-in-Electronics (K).pptxArtificial-Intelligence-in-Electronics (K).pptx
Artificial-Intelligence-in-Electronics (K).pptxbritheesh05
 
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...Dr.Costas Sachpazis
 
Oxy acetylene welding presentation note.
Oxy acetylene welding presentation note.Oxy acetylene welding presentation note.
Oxy acetylene welding presentation note.eptoze12
 
VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...
VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...
VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...VICTOR MAESTRE RAMIREZ
 
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...srsj9000
 

Recently uploaded (20)

chaitra-1.pptx fake news detection using machine learning
chaitra-1.pptx  fake news detection using machine learningchaitra-1.pptx  fake news detection using machine learning
chaitra-1.pptx fake news detection using machine learning
 
Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024
 
Biology for Computer Engineers Course Handout.pptx
Biology for Computer Engineers Course Handout.pptxBiology for Computer Engineers Course Handout.pptx
Biology for Computer Engineers Course Handout.pptx
 
SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )
 
young call girls in Rajiv Chowk🔝 9953056974 🔝 Delhi escort Service
young call girls in Rajiv Chowk🔝 9953056974 🔝 Delhi escort Serviceyoung call girls in Rajiv Chowk🔝 9953056974 🔝 Delhi escort Service
young call girls in Rajiv Chowk🔝 9953056974 🔝 Delhi escort Service
 
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort service
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort serviceGurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort service
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort service
 
ZXCTN 5804 / ZTE PTN / ZTE POTN / ZTE 5804 PTN / ZTE POTN 5804 ( 100/200 GE Z...
ZXCTN 5804 / ZTE PTN / ZTE POTN / ZTE 5804 PTN / ZTE POTN 5804 ( 100/200 GE Z...ZXCTN 5804 / ZTE PTN / ZTE POTN / ZTE 5804 PTN / ZTE POTN 5804 ( 100/200 GE Z...
ZXCTN 5804 / ZTE PTN / ZTE POTN / ZTE 5804 PTN / ZTE POTN 5804 ( 100/200 GE Z...
 
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
 
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube Exchanger
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube ExchangerStudy on Air-Water & Water-Water Heat Exchange in a Finned Tube Exchanger
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube Exchanger
 
main PPT.pptx of girls hostel security using rfid
main PPT.pptx of girls hostel security using rfidmain PPT.pptx of girls hostel security using rfid
main PPT.pptx of girls hostel security using rfid
 
Introduction to Microprocesso programming and interfacing.pptx
Introduction to Microprocesso programming and interfacing.pptxIntroduction to Microprocesso programming and interfacing.pptx
Introduction to Microprocesso programming and interfacing.pptx
 
Exploring_Network_Security_with_JA3_by_Rakesh Seal.pptx
Exploring_Network_Security_with_JA3_by_Rakesh Seal.pptxExploring_Network_Security_with_JA3_by_Rakesh Seal.pptx
Exploring_Network_Security_with_JA3_by_Rakesh Seal.pptx
 
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
 
microprocessor 8085 and its interfacing
microprocessor 8085  and its interfacingmicroprocessor 8085  and its interfacing
microprocessor 8085 and its interfacing
 
Artificial-Intelligence-in-Electronics (K).pptx
Artificial-Intelligence-in-Electronics (K).pptxArtificial-Intelligence-in-Electronics (K).pptx
Artificial-Intelligence-in-Electronics (K).pptx
 
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
 
Oxy acetylene welding presentation note.
Oxy acetylene welding presentation note.Oxy acetylene welding presentation note.
Oxy acetylene welding presentation note.
 
VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...
VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...
VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...
 
9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf
9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf
9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf
 
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...
 

Deepwater sub sea capital equipment

  • 1. Rig & equipment selection continued Peter Aird November 2008
  • 2. Sub Sea Capital drilling equipment 1. Diverter 2. Spider / Gimbal 3. Riser Coupling 4. Upper Flex Joint 5. Telescopic Joint 6. Tensioning Ring 7. Intermediate Flex Joint 8. Termination Joint 9. Riser Adapter 10. Single Flex Joint 11. BOP Connector 12. Wellhead Connector 13. Wellhead 3 1 2 6 4 7 9 13 5 8 10 11 12 3 1 2 6 4 7 9 13 5 8 10 11 12
  • 3. Standard Diverter system  Pressure rating  Internal diameter  Seals  Testing  Limitations!  Handling gas at surface
  • 4. 1. Deepwater diverter system  Used on the majority of floating rigs  Complete open-hole shutoff with 20” through-bore  Rated 1,000 psi for closure on 5” drill pipe; 500 psi for closure on open hole  10 second closing time on pipe or open hole  Housing accommodates large diameter riser buoyancy modules  High capacity systems available for supporting the Riser String from Diverter Housing in emergency hang-off situations
  • 5. 2.1 Spider  Hydraulic-gate riser spider is used when running or retrieving riser joints through the rotary table  Riser handling spider supports the riser string on manual or hydraulically operated sliding dogs
  • 6. 2.2 Riser Gimbal  Gimbal shock absorber supports up to 2,000,000 lb and gimbals when the riser is positioned in the spider  Reduces impact loads when running and landing marine riser joints
  • 7. 3.1 Riser connector  Easy stabbing, fast makeup, and positive alignment  Suitable for operating in water depths up to 7,500 ft depending on environmental and well control conditions; MR-10 designs can operate in depths to 10,000 ft.  Preloaded connection significantly reduces the range of alternating stresses induced by cyclic loading to improve fatigue life  Primary load path for tensile and bending loads through the dogs and into the body, does not impact actuating screws
  • 8. 3.2 API Riser Coupling Class API Riser Coupling Class Tensile capacity in millions of pounds Class A .5 Class B 1 Class C 1.25 Class D 1.5 Class E 2 Class F 2.5 Class H 3.5 API RP 2R establishes riser coupling classes based on the tensile capacity of the coupling. These are;
  • 9. 3.3 Riser coupling  Ideal for deep water applications where high load operating conditions exist  Stepped diameter design of pin and box simplifies engagement, even with severe vessel movement  No loose parts preventing bolt loss and potential thread damage  Field removable and replaceable nose piece  Locking bolts preloaded in excess of rated coupling loads to extend fatigue load of riser system
  • 10. Drilling riser (1)  Choke line  Kill line  Hydraulic lines  Prepared for buoyancy  Seals  Testing considerations
  • 13. 4. Riser Flex joint  Tensional capacity  Through bore  Ball joint limits
  • 14. 5. Telescopic Joint  Compensates for heave and offset of the vessel  Maximum rated riser tensile load capacity in locked position  Hydraulic latch release for inner and outer barrels available  Dual split/solid packer elements  Fixed or rotating integral/non- integral tensioner rings
  • 15. 6.1 Riser support ring  The Type Riser Tensioner Ring shown saves time because the riser tensioner cables are never disconnected.  When the riser is pulled the tensioner ring will be carried up to the bottom of the diverter housing. Hydraulic latches release the ring from the slip joint and permit it to be locked onto the diverter housing using another set of hydraulic latch dogs. The rest of the riser is retrieved through its center.
  • 16. 6.2 Tension ring  Telescopic Joint is run and pulled through the rotary table without disconnecting the tensioning lines from riser tensiong ring  Riser tensioning lines remain properly spaced out at all times  Hydraulic piping for lockdown/storage dogs remains permanently connected  Hydraulically disconnects from telescopic joint and locks to a mating profile on the bottom of the diverter housing for convenient, out-of-the-way storage
  • 17. 6.3 Ultra deep tension ring  Forms a termination point between the riser tensioner and the marine riser system  Simplifies running and retrieving marine riser by eliminating makeup/breakout of tensioner lines and hydraulic hoses in the moon pool area  Choke, kill, and auxiliary line terminations permanently connected  Orientation pins on the ring engage slots in telescopic joint line termination housing for easy makeup  Permanently installed tensioner lines maintain proper orientation with rig drilling tensioners
  • 18. 7. Intermediate Flex Joint  Installed below the telescopic joint  Up to 2.5 million lb tensile load capacity  Angular deflection to 20 °on either side of its axial center while subjected to tensile loading and internal pressure of 1500 psi Intermediate Flex Joint shown uses a KT ring and no termination joint.
  • 19. 9. Riser extension (adaptor)
  • 20. 10. Single flex joint  Installed in the LMRP below the riser/BOP Stack Interface  Uses a combination elastomeric bearing and seal unit to eliminate the need for a pressure balanced ball and socket interface with seals  Up to 2 million lb tensile load capacity  Rated for H2S service and oil- based drilling mud  Angular deflection to 10° on either side of its axial center while subjected to tensile loading and internal pressures up to 3000 psi  Pressure balance and lubrication systems not required
  • 21. 11-12 System design aspects  System Objective:  Solution for drilling in ultra deepwater drilling  BOP Flange  Wellhead Connector  Subsea Wellhead System  Conductor Sizing (Analysis)  Conductor/Casing Connectors  15,000 psi to 20,000 psi rated pressure  7,000,000 ft.-lbs. Bending @ 15,000 psi F ~6.6 MM ft-lbs ~7 MM ft-lbs ~7.7 MM ft-lbs ~14 MM ft-lbs (40' Below Mudline) ~8.4 MM ft-lbs  BOP Flange Wellhead Connector Wellhead System Conductor/ Casing Connectors F ~6.6 MM ft-lbs ~7 MM ft-lbs ~7.7 MM ft-lbs ~14 MM ft-lbs (40' Below Mudline) ~8.4 MM ft-lbs  BOP Flange Wellhead Connector Wellhead System Conductor/ Casing Connectors BOP Flange Wellhead Connector Wellhead System Conductor/ Casing Connectors