1. CHECK LIST FOR 26" HOLE, 18.5/8" CASING AND 17.1/2" HOLE
1. 18.5/8" casing materials
2. 3 jt, 18.5/8" casing coated
3. 5" Weatherford stinger for 18.5/8" Stab-in float shoe
4. 1 Pc. of 18.5/8 x 5" D/P centralizer.
5. 18.5/8" Casing running equipment's ( tong & unit ) and crew
6. 26" Mill Tooth Bit (New or used)
7. 1 X 26" Integral blades string stabilizer.
8. 17.1/2" insert new bit and operator
9. 2 x 17.1/2" string Roller Reamer (Bi-Way Directional)
10.9.5/8" performance motors and operator
CHECK LIST FOR 13.3/8" CASING AND 12.1/4" HOLE
1. 13.3/8" casing materials
2. 3 jt, 13.3/8" casing coated
3. 13.5/8" C.H.H and 12" W.bushing and test plug
4. Cement Recipe and program.
5. 13.3/8" Casing running equipment's and crew
6. 13.3/8" H.D.Clamp
7. 13.5/8" Running Flange and 13.3/8" Landing Jt
8. 13.3/8" Quick Latch Cmt and circ. Head (from E.W or D.Sch w/operator).
9. Weatherford Aerated mud drilling package and crew
10.Gyro Multi Shot Survey
11.Mud chemical and engineer for KCL-PHPA mud.
12.12.1/4" PDC bit and operator
13. 9.5/8" motors and operator
14. 8.1/4" MWD tools, unit and crew
15. 2 x 12.1/4" string Roller reamer (Bi-Way Directional)
16. 8" H-M Drilling Jar
CHECK LIST FOR 9.5/8" CASING AND 8.1/2" DEVIATED HOLE
1. 9.5/8" casing materials
2. 13.5/8" x 11" T.H.S and 10" W.Bushing and Test Plug
3. 9.5/8" Fluted Hanger, P.O.B and running tools
4. Crossover 9.5/8" New Vam Pin x NK3SB box
5. Cleaning equipment's and crew.
6. 9.5/8" casing running equipment's and crew ( C.C.P, Power tong and unit, Jam unit, PC
machine and Stabbing Guide).
7. Cement Recipe and program
8. FMC engineer for fluted hanger
9. Weatherford High power wrench for T.H.S and operator.
10. 9.5/8" Quick Latch Cmt and circ. Head.
11. 6.1/2" LWD tools, unit and crew
12. Additional rental 5" H.W.D.P (± 35 jt)
2. 13. Gyro Steering tool, unit and crew ( w/ S.E.S and orienting sub)
14. 6.1/2" H-M drilling Jar
15. O.B.M cutting boxes
16. 200 bbl rectangular covered tank for waste O.B.M
17. 6.1/2" PDM motors and additional directional driller.
18. Horizontal Bucking Machine for M/U 3.1/2" D/P in stands
19. Hi "G" Dryer and crew (in case of O.B.M)
20. 5 trucks to back load aerated mud drilling package.
21. 2 trucks to back load MWD unit and tool.
22. 2.7/8" x 5" Variable Rams for BOP
CHECK LIST FOR 7" CASING LINER AND 6" HORIZONTAL HOLE
1. 7" Casing materials
2. 7" Liner Hanger complete set wit setting tool and cement manifold
3. Cleaning equipment's and crew for 7" casing.
4. 7" casing liner running equipment's and crew ( Power tong , unit, Jam unit, PC machine and
Stabbing Guide).
5. Cement Recipe and program
6. Liner Hanger engineer
7. 4.3/4" LWD tools.
8. Additional rental 3.1/2" H.W.D.P (± 21 jt)
9. 4.3/4" H-M drilling Jar
10. 4.3/4" PDM motors.
11. Cleaning crew for 2.7/8" and 3.1/2" of completion string.
12. Horizontal Bucking Machine for M/U 3.1/2" and 2.7/8" tubing of completion string
in stands
CHECK LIST FOR DUAL OR SINGLE COMPLETION STRING
1. Completion running programs and sketches.
2. Completion materials and well head (Christmases tree).
3. NRV's and Test Plugs.
4. Completion subassembly
5. Electric wire line unit and crew for perforate 7" casing, and correlate 7" single Hyd. pkr
and 9.5/8" Dual Hyd. Pkr (in case of Dual completion string)
6. 6" Spiral string mill.
7. Completion running equipment's and crew ( Power tong and unit, Jam unit, PC machine,
Stabbing Guide).
8. Completion engineer ( in case of Dual string)
9. FMC engineer for Tubing Hanger and Christmases tree
10. 2.7/8" x 3.1/2" Dual Variable rams for BOP ( in case of Dual completion string )
11. Slick wire line unit and crew .
12. Weatherford High power wrench for Christmases tree and operator.
13. Enough No's of 3.1/2" and 2.7/8" pup jts, tubing different lengths (especially 5 ft)