SlideShare a Scribd company logo
1 of 29
DASC 5303 – TEAM 4
ASSIGNMENT 6
By:
Anvita Ravi (1002164252) axr4252@mavs.uta.edu (Point of Contact)
Saiteja Neela(1002155383)sxn5383@mavs.uta.edu
Rohith Arepally(1002156380)rxa6380@mavs.uta.edu
Julian Farquharson(1002056028)jxf6028@mavs.uta.edu
Anil Kumar Guttur JayaramaReddy(1002157871)axg7871@mavs.uta.edu
ASSIGNED TASK
Do the following exercises from Chapter 6 of the textbook: 23, Case 6.1 (answer
all questions on page 209), Case 6.2 (answer questions on page 209). Scan in
any information as appropriate and add to PowerPoint for submission.
2
CHAPTER 6 – EXERCISE 23
The CyClon project team has started
gathering the information necessary
to develop a project network—predecessor
activities and activity time in days.
The results of their meeting are found in the
following table.
3
EXERCISE 23 – PART A
Create a network based on the information in the table. How long will
the project take? What is the critical path?
Solution:
• The below diagram refers the network Diagram as per the above question
• We calculated Early Start (ES), Early Finish (EF),Late Start (LS), Late Finish
(LF) using the Duration given in the table.
• We calculated the EF and LS by: EF = ES + Duration and LS = LF - Duration.
• Also calculated Slack = (ES – LS) or (EF – LF)
• Critical Path is: 2 -> 3 -> 5 -> 6 -> 7 -> 8 -> 10 -> 11 -> 12 -> 13
• Therefore, the project takes 80 days to complete.
4
PART A – NETWORK DIAGRAM
5
EXERCISE 23 – PART B
Upon further review the team recognize that they missed three finish-to-start lags.
Procure prototype parts will involve only 2 days of work but it will take 8 days for the
parts to be delivered. Likewise, Order stock components will take 2 days of work and 8
days for delivery and Order custom components will take 2 days of work and 13 days
for delivery.
Reconfigure the CyClon schedule by entering the three finish-to-start lags. What impact
did these lags have on the original schedule? On the amount of work required to
complete the project?​
6
EXERCISE 23 – PART B
Solution:
It is clear from the question that they have missed three finish to start lags, which are as
follows:​
• Purchasing prototype parts will only take 2 days of effort, but the delivery of the parts
will take 8 days.​
• It will take 2 days to work on order stock components, and 8 days to supply them.​
• Custom component orders will require 2 workdays and 13 days for delivery.​
It is evident that all three activities have different durations and share two lags in
response to the query.​ The quantity of work for each activity was adjusted after
readjusting the CyClon schedule by adding the three finish-to-start lags, but the project's
completion time of 80 days remained same. ​
7
PART B – NETWORK DIAGRAM
8
EXERCISE 23 – PART C
Management is still not happy with the schedule and wants the project completed
as soon as possible. Unfortunately, they are not willing to approve additional
resources. One team member pointed out that the network contained only finish-to-
start relationships and that it might be possible to reduce project duration by
creating start-to-start lags. After much deliberation the team concluded that the
following relationships could be converted into start-to-start lags:
1. Procure prototype parts could start 6 days after the start of Design.
2. Fabricate parts could start 9 days after the start of Design.
3. Laboratory test could begin 1 day after the start of Assemble prototype.
4. Field test could start 5 days after the start of Laboratory test.
9
EXERCISE 23 – PART C
5. Adjust design could begin 7 days after the start of Field test.
6. Order stock and Order custom components could begin 5 days after Adjust design.
7. Test unit could begin 9 days after the start of Assemble test production unit.
8. Document results could start 3 days after the start of Test unit.
Reconfigure the CyClon schedule by entering all nine start-to-start lags. What impact
did these lags have on the original schedule (Part A)? How long will the project take? Is
there a change in the critical path? Is there a change in the sensitivity of the network?
Why would management like this solution?​​
10
PART C – NETWORK DIAGRAM
11
EXERCISE 23 – PART C
Solution:
The proposed solution with start-to-start lags offers multiple benefits to the company,
including faster project completion, optimized resource utilization and meeting
management expectations. This lags will impact the original schedule (calculated in Part
A) by making the project to complete faster than original like in this case, 77 days.
The change in critical path is
2 -> 4 -> 5 -> 6 -> 7 -> 8 -> 10 -> 11 -> 12 -> 13
The management would like this solution as it will take lesser number of days to
complete the project.
12
CHAPTER 6 – CASE STUDY 6.1
Tasks:
1. Generate a priority matrix for AET’s system move.
2. Develop a WBS for Brian’s project. Include duration (days) and predecessors.
3. Using a project-planning tool, generate a network diagram for this project.
Note: Base your plan on the following guidelines: eight-hour days, five-day weeks
except for when Brian moves the network components over a weekend, no holiday
breaks, and March 1, 2010, is the project start date.
Ordering ventilation system, new racks, and power supplies/cables takes only one actual
day of work. The remaining days are the time necessary for the vendors to fill and ship
the order to Brian. So use finish-to-start lags here. Assume that five days after the start
of the renovation of the data center that the raised floor will be ready for inspection (a
start-to-start lag).
13
OVERVIEW OF THE CASE
AET wants to migrate a large data center to their new office location.
Their large data center provides clients with remote access to AET’s complete suite of
application software systems, hence careful planning is required.
Conditions:
1. From start to finish, it is anticipated the entire project will take three to four months
to complete.
2. It is essential that AET’s 235 clients suffer no downtime
Due to the complexity of this project, Brian will have to use a parallel method of
implementation.
Cons: will increase project costs
14
OVERVIEW OF THE CASE
What the scope team determined ?
1. Three to four months is a feasible project timeline, and first-cut cost estimate is
$80,000–$90,000 (this includes the infrastructure upgrade of the new site).
2. Critical to the “no-downtime” requirement is the need to completely rely on AET’s
remote disaster recovery “hot” site for full functionality.
3. Brian will serve as project manager of a team of 5 consisting of one team member
each from Facilities, Operations/Systems, Operations/Telecommunications, Systems
and Applications, and Customer Service.
15
PRIORITY MATRIX FOR AET’S SYSTEM MOVE
TIME PERFORMANCE COST
CONSTRAIN
ENHANCE
ACCEPT
16
Time given is feasible but can be enhanced if possible.
Performance cannot be compromised as “no-downtime” is critical.
Cost is Accept as increase in cost is possible due to the use of parallel method.
WBS WITH DURATION
17
WORK BREAKDOWN STRUCTURE
18
AET’s System Move
Planning Phase
Initial Team Meeting
(March 1st – I day)
Contractor Screening
and Hiring (5 days)
Designing the Network
(10 days)
Ordering of Ventilation
System, Racks and
Power Supplies (1 days)
Infrastructure
Preparation
Delivery of the
Ventilation System(15
days)
Installing the
Ventilation System (5
days)
Delivery of the Racks
(10 days)
Installing the Racks (15
days)
Construction of the
Data Center (20 days)
City Inspector’s
Inspection and
Approval (2 days)
Delivery of the Power
Supplies (5 days)
Installating the Power
Supplies (5 days)
Initial Power Check (1
day)
System Testing and
Verification
Installating the Test
Server (5 days)
Battery Charging,
Ventilation System Test
and Test Servers up &
running (2 days)
Primary Systems Check
signed off by
Management (1 day)
Implementation Phase
(2 days - weekend)
Official Date Setting for
Network Move
Network Shutdown
over the weekend
Physical Move of
Network Components
Post-Move Testing and
Verification
NETWORK DIAGRAM
19
GANTT TABLE
20
GANTT CHART
21
CHAPTER 6 – CASE STUDY 6.2
The G&E Company is preparing a bid to build the new 47,000-seat
Shoreline baseball stadium. The construction must start on June 10, 2019,
and be completed in time for the start of the 2022 season. A penalty clause
of $500,000 per day of delay beyond April 3rd is written into the contract.
Percival Young, the president of the company, expressed optimism at
obtaining the contract and revealed that the company could net as much as
$5 million on the project. He also said that if they were successful, the
prospects of future projects would be bright, since there is a projected
renaissance in building classic ball parks with modern luxury boxes.
22
CHAPTER 6 – CASE STUDY 6.2
23
NETWORK DIAGRAM
24
CHAPTER 6 – CASE STUDY 6.2
1. Can the project be completed by the April 3rd deadline? How long will it take?
From the Network Diagram , 2 critical routes are visible:
Critical path 1: 2-5-6-7-10-14-15-20 =86+175+170+178+198+107+48+28 = 990
Critical path 2: 2-5-6-9-10-14-15-20 = 86+175+170+178+198+107+48+28 = 990
The project needs to be finished by April 3rd, 2022,
Therefore time from June 10, 2019 to April 03,2022: 1028 days
Given that 990 days are shorter than 1028 days, the project can be finished by the
deadline of April 3, 2022.
25
CHAPTER 6 – CASE STUDY 6.2
2. What is the critical path for the project?
There are 2 critical paths:
Critical path 1: 2-5-6-7-10-14-15-20 = 86+175+170+178+198+107+48+28 =990
Critical path 2: 2-5-6-9-10-14-15-20 = 86+175+170+178+198+107+48+28 =990
3. Based on the schedule, would you recommend that G&E pursue this contact?
Why? Include a one-page Gantt chart for the stadium schedule.
Absolutely, we recommend G&E to pursue this deal as there is a good chance that they
will make a sizable profit of $5 million and the project can be finished by the deadline.
Percival Young also emphasized the possibility for other initiatives in the industry and
expressed hope about landing the contract.
26
GANTT TABLE
27
GANTT CHART
28
29

More Related Content

What's hot

01 nestle sales and distribution
01 nestle sales and distribution01 nestle sales and distribution
01 nestle sales and distribution
Selvakani Nadar
 
Nestle-business-presentation
 Nestle-business-presentation Nestle-business-presentation
Nestle-business-presentation
Manmeet Singh
 
Marketing assignment
Marketing assignmentMarketing assignment
Marketing assignment
abishekvarma
 
Assignment & presentation for prin.marketing
Assignment & presentation for prin.marketingAssignment & presentation for prin.marketing
Assignment & presentation for prin.marketing
Deden As-Syafei
 

What's hot (20)

Chatime
ChatimeChatime
Chatime
 
social and cultural impacts of Nestle
social and cultural impacts of Nestlesocial and cultural impacts of Nestle
social and cultural impacts of Nestle
 
4ps of Cafe coffee day
4ps of Cafe coffee day4ps of Cafe coffee day
4ps of Cafe coffee day
 
Whole Foods Strategic Audit
Whole Foods Strategic AuditWhole Foods Strategic Audit
Whole Foods Strategic Audit
 
01 nestle sales and distribution
01 nestle sales and distribution01 nestle sales and distribution
01 nestle sales and distribution
 
Nestle-business-presentation
 Nestle-business-presentation Nestle-business-presentation
Nestle-business-presentation
 
Nestle- Company profile
Nestle- Company profile Nestle- Company profile
Nestle- Company profile
 
Marketing assignment
Marketing assignmentMarketing assignment
Marketing assignment
 
Measurement of elasticity of demand for ‘Lux & Lifebuoy'
Measurement of elasticity of demand for ‘Lux  & Lifebuoy' Measurement of elasticity of demand for ‘Lux  & Lifebuoy'
Measurement of elasticity of demand for ‘Lux & Lifebuoy'
 
Comparative analysis on mac d and dominos
Comparative analysis on mac d and dominosComparative analysis on mac d and dominos
Comparative analysis on mac d and dominos
 
Business plan of watermelon juice
Business plan of watermelon juiceBusiness plan of watermelon juice
Business plan of watermelon juice
 
Pepsi
Pepsi Pepsi
Pepsi
 
Mini Market & Convenience Store Definition
Mini Market & Convenience Store DefinitionMini Market & Convenience Store Definition
Mini Market & Convenience Store Definition
 
UNILEVER MANAGEMENT DEVELOPMENT AND JOB ANALYSIS & ORGANIZATION STRUCTURE
UNILEVER MANAGEMENT DEVELOPMENT AND JOB ANALYSIS & ORGANIZATION STRUCTUREUNILEVER MANAGEMENT DEVELOPMENT AND JOB ANALYSIS & ORGANIZATION STRUCTURE
UNILEVER MANAGEMENT DEVELOPMENT AND JOB ANALYSIS & ORGANIZATION STRUCTURE
 
Nestlé
NestléNestlé
Nestlé
 
A project report on whether the decreasing sales of pizza hut can be increase...
A project report on whether the decreasing sales of pizza hut can be increase...A project report on whether the decreasing sales of pizza hut can be increase...
A project report on whether the decreasing sales of pizza hut can be increase...
 
Porter's 5 forces on Mac D
Porter's 5 forces on Mac DPorter's 5 forces on Mac D
Porter's 5 forces on Mac D
 
Dominous competative analysis
Dominous competative analysis Dominous competative analysis
Dominous competative analysis
 
Burger king (Project Presentation Report)
Burger king (Project Presentation Report)Burger king (Project Presentation Report)
Burger king (Project Presentation Report)
 
Assignment & presentation for prin.marketing
Assignment & presentation for prin.marketingAssignment & presentation for prin.marketing
Assignment & presentation for prin.marketing
 

Similar to DASC 5303 00 – Team 4 - Assignment 6.pptx

Project Plan - Risk Management & Integration
Project Plan - Risk Management & IntegrationProject Plan - Risk Management & Integration
Project Plan - Risk Management & Integration
Prachi Dikshit
 
Leadership TheoriesWrite a 700- to 1,050-word paper that addre.docx
Leadership TheoriesWrite a 700- to 1,050-word paper that addre.docxLeadership TheoriesWrite a 700- to 1,050-word paper that addre.docx
Leadership TheoriesWrite a 700- to 1,050-word paper that addre.docx
smile790243
 
PMI Scheduling Conference 2016 Bruce Stephan
PMI Scheduling Conference 2016 Bruce StephanPMI Scheduling Conference 2016 Bruce Stephan
PMI Scheduling Conference 2016 Bruce Stephan
Bruce Stephan
 
Team 4, Team PMP”IT Installation of the Adelphi V.docx
Team 4, Team PMP”IT Installation of the Adelphi V.docxTeam 4, Team PMP”IT Installation of the Adelphi V.docx
Team 4, Team PMP”IT Installation of the Adelphi V.docx
mattinsonjanel
 
RUNNING HEAD PROJECT SCHEDULE1PROJECT SCHEDULE5Instr.docx
RUNNING HEAD PROJECT SCHEDULE1PROJECT SCHEDULE5Instr.docxRUNNING HEAD PROJECT SCHEDULE1PROJECT SCHEDULE5Instr.docx
RUNNING HEAD PROJECT SCHEDULE1PROJECT SCHEDULE5Instr.docx
toltonkendal
 
Appendix C – Project Close-out ChecklistSection 1.General Inf.docx
Appendix C – Project Close-out ChecklistSection 1.General Inf.docxAppendix C – Project Close-out ChecklistSection 1.General Inf.docx
Appendix C – Project Close-out ChecklistSection 1.General Inf.docx
festockton
 
Table of ContentsProject ObjectiveRationale for Projec.docx
Table of ContentsProject ObjectiveRationale for Projec.docxTable of ContentsProject ObjectiveRationale for Projec.docx
Table of ContentsProject ObjectiveRationale for Projec.docx
ssuserf9c51d
 

Similar to DASC 5303 00 – Team 4 - Assignment 6.pptx (20)

Project Plan - Risk Management & Integration
Project Plan - Risk Management & IntegrationProject Plan - Risk Management & Integration
Project Plan - Risk Management & Integration
 
Conveyor belt project
Conveyor belt projectConveyor belt project
Conveyor belt project
 
Session 5 gdas pmp study group presentation
Session 5   gdas pmp study group presentationSession 5   gdas pmp study group presentation
Session 5 gdas pmp study group presentation
 
Reduction of Order Delivery Time of Goods.pdf
Reduction of Order Delivery Time of Goods.pdfReduction of Order Delivery Time of Goods.pdf
Reduction of Order Delivery Time of Goods.pdf
 
Leadership TheoriesWrite a 700- to 1,050-word paper that addre.docx
Leadership TheoriesWrite a 700- to 1,050-word paper that addre.docxLeadership TheoriesWrite a 700- to 1,050-word paper that addre.docx
Leadership TheoriesWrite a 700- to 1,050-word paper that addre.docx
 
SCHEDULING.pptdjdgjgjdjgajdjasdjadasgdgdduaa
SCHEDULING.pptdjdgjgjdjgajdjasdjadasgdgdduaaSCHEDULING.pptdjdgjgjdjgajdjasdjadasgdgdduaa
SCHEDULING.pptdjdgjgjdjgajdjasdjadasgdgdduaa
 
PMI Scheduling Conference 2016 Bruce Stephan
PMI Scheduling Conference 2016 Bruce StephanPMI Scheduling Conference 2016 Bruce Stephan
PMI Scheduling Conference 2016 Bruce Stephan
 
45ef51191315a8630a639ff030b4cb67a3df6f49-1657701254277.ppt
45ef51191315a8630a639ff030b4cb67a3df6f49-1657701254277.ppt45ef51191315a8630a639ff030b4cb67a3df6f49-1657701254277.ppt
45ef51191315a8630a639ff030b4cb67a3df6f49-1657701254277.ppt
 
Team 4, Team PMP”IT Installation of the Adelphi V.docx
Team 4, Team PMP”IT Installation of the Adelphi V.docxTeam 4, Team PMP”IT Installation of the Adelphi V.docx
Team 4, Team PMP”IT Installation of the Adelphi V.docx
 
RUNNING HEAD PROJECT SCHEDULE1PROJECT SCHEDULE5Instr.docx
RUNNING HEAD PROJECT SCHEDULE1PROJECT SCHEDULE5Instr.docxRUNNING HEAD PROJECT SCHEDULE1PROJECT SCHEDULE5Instr.docx
RUNNING HEAD PROJECT SCHEDULE1PROJECT SCHEDULE5Instr.docx
 
COMPARATIVE STUDY OF ACTUAL AND CRASHED SCHEDULE OF BUILDING USING MSP
COMPARATIVE STUDY OF ACTUAL AND CRASHED SCHEDULE OF BUILDING USING MSPCOMPARATIVE STUDY OF ACTUAL AND CRASHED SCHEDULE OF BUILDING USING MSP
COMPARATIVE STUDY OF ACTUAL AND CRASHED SCHEDULE OF BUILDING USING MSP
 
Docweb Milestone 2 Report
Docweb Milestone 2 ReportDocweb Milestone 2 Report
Docweb Milestone 2 Report
 
Time Cost Trade Off
Time Cost Trade OffTime Cost Trade Off
Time Cost Trade Off
 
Appendix C – Project Close-out ChecklistSection 1.General Inf.docx
Appendix C – Project Close-out ChecklistSection 1.General Inf.docxAppendix C – Project Close-out ChecklistSection 1.General Inf.docx
Appendix C – Project Close-out ChecklistSection 1.General Inf.docx
 
IRJET- Integration of Job Release Policies and Job Scheduling Policies in...
IRJET-  	  Integration of Job Release Policies and Job Scheduling Policies in...IRJET-  	  Integration of Job Release Policies and Job Scheduling Policies in...
IRJET- Integration of Job Release Policies and Job Scheduling Policies in...
 
Uac Work Plan Presentation Part Iii Ver 2
Uac Work Plan Presentation Part Iii Ver 2Uac Work Plan Presentation Part Iii Ver 2
Uac Work Plan Presentation Part Iii Ver 2
 
Managing over allocation of resource in steel
Managing over allocation of resource in steelManaging over allocation of resource in steel
Managing over allocation of resource in steel
 
Table of ContentsProject ObjectiveRationale for Projec.docx
Table of ContentsProject ObjectiveRationale for Projec.docxTable of ContentsProject ObjectiveRationale for Projec.docx
Table of ContentsProject ObjectiveRationale for Projec.docx
 
CPM-Updating
CPM-UpdatingCPM-Updating
CPM-Updating
 
IQA_Project
IQA_ProjectIQA_Project
IQA_Project
 

Recently uploaded

Recently uploaded (20)

Mattingly "AI and Prompt Design: LLMs with NER"
Mattingly "AI and Prompt Design: LLMs with NER"Mattingly "AI and Prompt Design: LLMs with NER"
Mattingly "AI and Prompt Design: LLMs with NER"
 
How to Manage Website in Odoo 17 Studio App.pptx
How to Manage Website in Odoo 17 Studio App.pptxHow to Manage Website in Odoo 17 Studio App.pptx
How to Manage Website in Odoo 17 Studio App.pptx
 
Stl Algorithms in C++ jjjjjjjjjjjjjjjjjj
Stl Algorithms in C++ jjjjjjjjjjjjjjjjjjStl Algorithms in C++ jjjjjjjjjjjjjjjjjj
Stl Algorithms in C++ jjjjjjjjjjjjjjjjjj
 
Analyzing and resolving a communication crisis in Dhaka textiles LTD.pptx
Analyzing and resolving a communication crisis in Dhaka textiles LTD.pptxAnalyzing and resolving a communication crisis in Dhaka textiles LTD.pptx
Analyzing and resolving a communication crisis in Dhaka textiles LTD.pptx
 
demyelinated disorder: multiple sclerosis.pptx
demyelinated disorder: multiple sclerosis.pptxdemyelinated disorder: multiple sclerosis.pptx
demyelinated disorder: multiple sclerosis.pptx
 
Including Mental Health Support in Project Delivery, 14 May.pdf
Including Mental Health Support in Project Delivery, 14 May.pdfIncluding Mental Health Support in Project Delivery, 14 May.pdf
Including Mental Health Support in Project Delivery, 14 May.pdf
 
e-Sealing at EADTU by Kamakshi Rajagopal
e-Sealing at EADTU by Kamakshi Rajagopale-Sealing at EADTU by Kamakshi Rajagopal
e-Sealing at EADTU by Kamakshi Rajagopal
 
Observing-Correct-Grammar-in-Making-Definitions.pptx
Observing-Correct-Grammar-in-Making-Definitions.pptxObserving-Correct-Grammar-in-Making-Definitions.pptx
Observing-Correct-Grammar-in-Making-Definitions.pptx
 
The Liver & Gallbladder (Anatomy & Physiology).pptx
The Liver &  Gallbladder (Anatomy & Physiology).pptxThe Liver &  Gallbladder (Anatomy & Physiology).pptx
The Liver & Gallbladder (Anatomy & Physiology).pptx
 
diagnosting testing bsc 2nd sem.pptx....
diagnosting testing bsc 2nd sem.pptx....diagnosting testing bsc 2nd sem.pptx....
diagnosting testing bsc 2nd sem.pptx....
 
8 Tips for Effective Working Capital Management
8 Tips for Effective Working Capital Management8 Tips for Effective Working Capital Management
8 Tips for Effective Working Capital Management
 
Spring gala 2024 photo slideshow - Celebrating School-Community Partnerships
Spring gala 2024 photo slideshow - Celebrating School-Community PartnershipsSpring gala 2024 photo slideshow - Celebrating School-Community Partnerships
Spring gala 2024 photo slideshow - Celebrating School-Community Partnerships
 
An Overview of the Odoo 17 Knowledge App
An Overview of the Odoo 17 Knowledge AppAn Overview of the Odoo 17 Knowledge App
An Overview of the Odoo 17 Knowledge App
 
ANTI PARKISON DRUGS.pptx
ANTI         PARKISON          DRUGS.pptxANTI         PARKISON          DRUGS.pptx
ANTI PARKISON DRUGS.pptx
 
An overview of the various scriptures in Hinduism
An overview of the various scriptures in HinduismAn overview of the various scriptures in Hinduism
An overview of the various scriptures in Hinduism
 
How to Send Pro Forma Invoice to Your Customers in Odoo 17
How to Send Pro Forma Invoice to Your Customers in Odoo 17How to Send Pro Forma Invoice to Your Customers in Odoo 17
How to Send Pro Forma Invoice to Your Customers in Odoo 17
 
When Quality Assurance Meets Innovation in Higher Education - Report launch w...
When Quality Assurance Meets Innovation in Higher Education - Report launch w...When Quality Assurance Meets Innovation in Higher Education - Report launch w...
When Quality Assurance Meets Innovation in Higher Education - Report launch w...
 
Basic Civil Engineering notes on Transportation Engineering & Modes of Transport
Basic Civil Engineering notes on Transportation Engineering & Modes of TransportBasic Civil Engineering notes on Transportation Engineering & Modes of Transport
Basic Civil Engineering notes on Transportation Engineering & Modes of Transport
 
TỔNG HỢP HƠN 100 ĐỀ THI THỬ TỐT NGHIỆP THPT TOÁN 2024 - TỪ CÁC TRƯỜNG, TRƯỜNG...
TỔNG HỢP HƠN 100 ĐỀ THI THỬ TỐT NGHIỆP THPT TOÁN 2024 - TỪ CÁC TRƯỜNG, TRƯỜNG...TỔNG HỢP HƠN 100 ĐỀ THI THỬ TỐT NGHIỆP THPT TOÁN 2024 - TỪ CÁC TRƯỜNG, TRƯỜNG...
TỔNG HỢP HƠN 100 ĐỀ THI THỬ TỐT NGHIỆP THPT TOÁN 2024 - TỪ CÁC TRƯỜNG, TRƯỜNG...
 
male presentation...pdf.................
male presentation...pdf.................male presentation...pdf.................
male presentation...pdf.................
 

DASC 5303 00 – Team 4 - Assignment 6.pptx

  • 1. DASC 5303 – TEAM 4 ASSIGNMENT 6 By: Anvita Ravi (1002164252) axr4252@mavs.uta.edu (Point of Contact) Saiteja Neela(1002155383)sxn5383@mavs.uta.edu Rohith Arepally(1002156380)rxa6380@mavs.uta.edu Julian Farquharson(1002056028)jxf6028@mavs.uta.edu Anil Kumar Guttur JayaramaReddy(1002157871)axg7871@mavs.uta.edu
  • 2. ASSIGNED TASK Do the following exercises from Chapter 6 of the textbook: 23, Case 6.1 (answer all questions on page 209), Case 6.2 (answer questions on page 209). Scan in any information as appropriate and add to PowerPoint for submission. 2
  • 3. CHAPTER 6 – EXERCISE 23 The CyClon project team has started gathering the information necessary to develop a project network—predecessor activities and activity time in days. The results of their meeting are found in the following table. 3
  • 4. EXERCISE 23 – PART A Create a network based on the information in the table. How long will the project take? What is the critical path? Solution: • The below diagram refers the network Diagram as per the above question • We calculated Early Start (ES), Early Finish (EF),Late Start (LS), Late Finish (LF) using the Duration given in the table. • We calculated the EF and LS by: EF = ES + Duration and LS = LF - Duration. • Also calculated Slack = (ES – LS) or (EF – LF) • Critical Path is: 2 -> 3 -> 5 -> 6 -> 7 -> 8 -> 10 -> 11 -> 12 -> 13 • Therefore, the project takes 80 days to complete. 4
  • 5. PART A – NETWORK DIAGRAM 5
  • 6. EXERCISE 23 – PART B Upon further review the team recognize that they missed three finish-to-start lags. Procure prototype parts will involve only 2 days of work but it will take 8 days for the parts to be delivered. Likewise, Order stock components will take 2 days of work and 8 days for delivery and Order custom components will take 2 days of work and 13 days for delivery. Reconfigure the CyClon schedule by entering the three finish-to-start lags. What impact did these lags have on the original schedule? On the amount of work required to complete the project?​ 6
  • 7. EXERCISE 23 – PART B Solution: It is clear from the question that they have missed three finish to start lags, which are as follows:​ • Purchasing prototype parts will only take 2 days of effort, but the delivery of the parts will take 8 days.​ • It will take 2 days to work on order stock components, and 8 days to supply them.​ • Custom component orders will require 2 workdays and 13 days for delivery.​ It is evident that all three activities have different durations and share two lags in response to the query.​ The quantity of work for each activity was adjusted after readjusting the CyClon schedule by adding the three finish-to-start lags, but the project's completion time of 80 days remained same. ​ 7
  • 8. PART B – NETWORK DIAGRAM 8
  • 9. EXERCISE 23 – PART C Management is still not happy with the schedule and wants the project completed as soon as possible. Unfortunately, they are not willing to approve additional resources. One team member pointed out that the network contained only finish-to- start relationships and that it might be possible to reduce project duration by creating start-to-start lags. After much deliberation the team concluded that the following relationships could be converted into start-to-start lags: 1. Procure prototype parts could start 6 days after the start of Design. 2. Fabricate parts could start 9 days after the start of Design. 3. Laboratory test could begin 1 day after the start of Assemble prototype. 4. Field test could start 5 days after the start of Laboratory test. 9
  • 10. EXERCISE 23 – PART C 5. Adjust design could begin 7 days after the start of Field test. 6. Order stock and Order custom components could begin 5 days after Adjust design. 7. Test unit could begin 9 days after the start of Assemble test production unit. 8. Document results could start 3 days after the start of Test unit. Reconfigure the CyClon schedule by entering all nine start-to-start lags. What impact did these lags have on the original schedule (Part A)? How long will the project take? Is there a change in the critical path? Is there a change in the sensitivity of the network? Why would management like this solution?​​ 10
  • 11. PART C – NETWORK DIAGRAM 11
  • 12. EXERCISE 23 – PART C Solution: The proposed solution with start-to-start lags offers multiple benefits to the company, including faster project completion, optimized resource utilization and meeting management expectations. This lags will impact the original schedule (calculated in Part A) by making the project to complete faster than original like in this case, 77 days. The change in critical path is 2 -> 4 -> 5 -> 6 -> 7 -> 8 -> 10 -> 11 -> 12 -> 13 The management would like this solution as it will take lesser number of days to complete the project. 12
  • 13. CHAPTER 6 – CASE STUDY 6.1 Tasks: 1. Generate a priority matrix for AET’s system move. 2. Develop a WBS for Brian’s project. Include duration (days) and predecessors. 3. Using a project-planning tool, generate a network diagram for this project. Note: Base your plan on the following guidelines: eight-hour days, five-day weeks except for when Brian moves the network components over a weekend, no holiday breaks, and March 1, 2010, is the project start date. Ordering ventilation system, new racks, and power supplies/cables takes only one actual day of work. The remaining days are the time necessary for the vendors to fill and ship the order to Brian. So use finish-to-start lags here. Assume that five days after the start of the renovation of the data center that the raised floor will be ready for inspection (a start-to-start lag). 13
  • 14. OVERVIEW OF THE CASE AET wants to migrate a large data center to their new office location. Their large data center provides clients with remote access to AET’s complete suite of application software systems, hence careful planning is required. Conditions: 1. From start to finish, it is anticipated the entire project will take three to four months to complete. 2. It is essential that AET’s 235 clients suffer no downtime Due to the complexity of this project, Brian will have to use a parallel method of implementation. Cons: will increase project costs 14
  • 15. OVERVIEW OF THE CASE What the scope team determined ? 1. Three to four months is a feasible project timeline, and first-cut cost estimate is $80,000–$90,000 (this includes the infrastructure upgrade of the new site). 2. Critical to the “no-downtime” requirement is the need to completely rely on AET’s remote disaster recovery “hot” site for full functionality. 3. Brian will serve as project manager of a team of 5 consisting of one team member each from Facilities, Operations/Systems, Operations/Telecommunications, Systems and Applications, and Customer Service. 15
  • 16. PRIORITY MATRIX FOR AET’S SYSTEM MOVE TIME PERFORMANCE COST CONSTRAIN ENHANCE ACCEPT 16 Time given is feasible but can be enhanced if possible. Performance cannot be compromised as “no-downtime” is critical. Cost is Accept as increase in cost is possible due to the use of parallel method.
  • 18. WORK BREAKDOWN STRUCTURE 18 AET’s System Move Planning Phase Initial Team Meeting (March 1st – I day) Contractor Screening and Hiring (5 days) Designing the Network (10 days) Ordering of Ventilation System, Racks and Power Supplies (1 days) Infrastructure Preparation Delivery of the Ventilation System(15 days) Installing the Ventilation System (5 days) Delivery of the Racks (10 days) Installing the Racks (15 days) Construction of the Data Center (20 days) City Inspector’s Inspection and Approval (2 days) Delivery of the Power Supplies (5 days) Installating the Power Supplies (5 days) Initial Power Check (1 day) System Testing and Verification Installating the Test Server (5 days) Battery Charging, Ventilation System Test and Test Servers up & running (2 days) Primary Systems Check signed off by Management (1 day) Implementation Phase (2 days - weekend) Official Date Setting for Network Move Network Shutdown over the weekend Physical Move of Network Components Post-Move Testing and Verification
  • 22. CHAPTER 6 – CASE STUDY 6.2 The G&E Company is preparing a bid to build the new 47,000-seat Shoreline baseball stadium. The construction must start on June 10, 2019, and be completed in time for the start of the 2022 season. A penalty clause of $500,000 per day of delay beyond April 3rd is written into the contract. Percival Young, the president of the company, expressed optimism at obtaining the contract and revealed that the company could net as much as $5 million on the project. He also said that if they were successful, the prospects of future projects would be bright, since there is a projected renaissance in building classic ball parks with modern luxury boxes. 22
  • 23. CHAPTER 6 – CASE STUDY 6.2 23
  • 25. CHAPTER 6 – CASE STUDY 6.2 1. Can the project be completed by the April 3rd deadline? How long will it take? From the Network Diagram , 2 critical routes are visible: Critical path 1: 2-5-6-7-10-14-15-20 =86+175+170+178+198+107+48+28 = 990 Critical path 2: 2-5-6-9-10-14-15-20 = 86+175+170+178+198+107+48+28 = 990 The project needs to be finished by April 3rd, 2022, Therefore time from June 10, 2019 to April 03,2022: 1028 days Given that 990 days are shorter than 1028 days, the project can be finished by the deadline of April 3, 2022. 25
  • 26. CHAPTER 6 – CASE STUDY 6.2 2. What is the critical path for the project? There are 2 critical paths: Critical path 1: 2-5-6-7-10-14-15-20 = 86+175+170+178+198+107+48+28 =990 Critical path 2: 2-5-6-9-10-14-15-20 = 86+175+170+178+198+107+48+28 =990 3. Based on the schedule, would you recommend that G&E pursue this contact? Why? Include a one-page Gantt chart for the stadium schedule. Absolutely, we recommend G&E to pursue this deal as there is a good chance that they will make a sizable profit of $5 million and the project can be finished by the deadline. Percival Young also emphasized the possibility for other initiatives in the industry and expressed hope about landing the contract. 26
  • 29. 29