SlideShare a Scribd company logo
Department of Collegiate and Technical Education
Week – 09, Session - 03
Course outcome: 20CE43P
Site Management ( IV Semester)
Civil Engineering
Civil Engineering – 20CE43P
Table of Content
1. Time-Cost Trade-Off
2. Cost Control in Construction
3. Importance of Management Information System
4. MCQ
Civil Engineering – 20CE43P
1. Time-Cost Trade-Off
Terms related to Time-Cost Trade-Off
a) Direct Project Cost : The cost and expenses that are
accountable on facility, function or product such as cost
incurred on labour, material, equipment etc. are called as
direct costs.
 Normal Time : Normal time is the standard time that an
estimator would usually allowed for an activity.
 Crash Time : Crash time is the minimum possible time in
which an activity can be completed.
 Normal Cost : This is direct cost required to complete the
activity in normal time duration.
 Crash Cost : This is the direct cost corresponding to the
completion of the activity within crash time.
Civil Engineering – 20CE43P
 Cost Slope : This is the slope of the direct cost curve,
approximated as straight line.
𝐶𝑜𝑠𝑡 𝑆𝑙𝑜𝑝𝑒 =
(𝐶𝑟𝑎𝑠ℎ 𝐶𝑜𝑠𝑡 − 𝑁𝑜𝑟𝑚𝑎𝑙 𝐶𝑜𝑠𝑡)
(𝑁𝑜𝑟𝑚𝑎𝑙 𝑇𝑖𝑚𝑒 − 𝐶𝑟𝑎𝑠ℎ 𝑇𝑖𝑚𝑒)
b) Indirect Project Cost : An indirect cost in construction is an
expense that doesn't relate directly to the functions, products
or operations of a construction project such as cost incurred
on administrative processes and staff salaries, overhead cost,
lost profit, loss of revenue, penalty etc.
c) Total Project Cost : This is the sum of direct project cost and
indirect project cost.
d) Optimum Duration & Optimum Cost : The duration in
which minimum total cost is obtained is known as optimum
duration and the corresponding cost is known as optimum
cost.
Civil Engineering – 20CE43P
What is Time-Cost Trade-Off or Crashing ?
The process of reduction of total project duration along the
longest path (time wise) of the network i.e. along the critical path
to obtain the optimum project cost and optimum duration is called
“time-cost trade-off or crashing”.
The activity duration can be reduced by one of the following
actions:
 Applying multiple-shifts work.
 Working extended hours (over time).
 Offering incentive payments to increase the productivity.
 Working on week ends and holidays.
 Using additional resources.
 Using materials with faster installation methods.
 Using alternate construction methods or sequence.
Civil Engineering – 20CE43P
Procedure for crashing the network :
1) Draw the network diagram.
2) Determine the critical path.
3) Indicates critical path along network diagram.
4) Determine cost slope of each activity.
5) Start crashing the activities along the critical path having
minimum cost slope.
6) Activity having minimum cost slope is crashed until its
crashing potential is exhausted and new critical path are
formed.
7) If new critical path is formed then we to crash
combination of critical activity (parallel activity) having
minimum cost slope and continue till there is no further
scope of crashing.
Civil Engineering – 20CE43P
1.1 Example for crashing of project work :
Consider the data of a project as shown in the following table-
1.1which has to be complete in 9days. Take overhead cost of the
project = Rs.200/day
Table-1.1
Civil Engineering – 20CE43P
Activity Normal
Time
(Days)
Normal
Cost
(Rs.)
Crash Time
(Days)
Crash
Cost
(Rs.)
1-2 3 2500 1 3500
2-3 4 2600 2 3400
2-4 7 2500 4 3400
3-4 5 2400 2 3000
Solution :
Step -1 : Draw the network diagram.
Fig-1.1
Step -2 : Determine the critical path.
Fig-1.2 Civil Engineering – 20CE43P
Possible Paths = 1-2-3-4=12days
1-2-7=10days
Critical Path = 1-2-3-4
Project Duration = 12days
Normal Project Cost = 10000
Total Project Cost = 10000+12x200
=12400
Step-3 : Determine cost slope of each activity
𝐶𝑜𝑠𝑡 𝑆𝑙𝑜𝑝𝑒 =
(𝐶𝑟𝑎𝑠ℎ 𝐶𝑜𝑠𝑡 − 𝑁𝑜𝑟𝑚𝑎𝑙 𝐶𝑜𝑠𝑡)
(𝑁𝑜𝑟𝑚𝑎𝑙 𝑇𝑖𝑚𝑒 − 𝐶𝑟𝑎𝑠ℎ 𝑇𝑖𝑚𝑒)
𝐶𝑜𝑠𝑡 𝑆𝑙𝑜𝑝𝑒 𝑜𝑓 1 − 2 =
3500 − 2500
3 − 1
= 500
Similarly calculate the cost slope of each activity and enter as
shown in table-1.2
Table-1.2
Civil Engineering – 20CE43P
Activity Normal
Time
(Days)
Normal
Cost
(Rs.)
Crash
Time
(Days)
Crash
Cost
(Rs.)
Cost
Slope
(Rs.)
1-2 3 2500 1 3500 500
2-3 4 2600 2 3400 400
2-4 7 2500 4 3400 100
3-4 5 2400 2 3000 200
Step-4 : Start crashing the activities along the critical path having
minimum cost slope.
Crashing the activity 3-4 by 2 days which has minimum
cost slope of Rs.200
∴ Total Project Cost = 12400+2x200-2x200= 12400
Step-5 : If new critical path is formed then we have to crash
combination of critical activity (parallel activity) having
minimum cost slope and continue till there is no further scope of
crashing.
Fig-1.3
Civil Engineering – 20CE43P
From the above network (Fig-1.3) we found two critical paths (1-
2-3-4 and 1-2-4) of same duration. From the table-2 it is clear that
we can crash the activities 2-4 by 1day and 3-4 by 1day which
has minimum cost slope value of Rs.100 and Rs.200 respectively
to crash the network to maximum of 9 days.
Fig-1.4
∴ Total Project Cost = 12400+(1x100+1x200)-1x200=12500
Finally the total project cost to complete the project in 9days by
crashing the activities is Rs.12500
Civil Engineering – 20CE43P
Activity Crash
Time
(Days)
Cost
Slope
(Rs.)
1-2 1 500
2-3 2 400
2-4 4 100
3-4 2 200
2. Cost Control in Construction
Cost control in construction is the process by which managers
keep expenses under control by managing labor, material, and
overhead costs to ensure that the project finishes on budget.
Cost Control Techniques :
Following are some of the valuable and essential techniques used
for efficient project cost control:
1. Planning the Project Budget
2. Keeping a Track of Costs
3. Effective Time Management
4. Project Change Control
5. Use of Earned Value
Civil Engineering – 20CE43P
1. Planning the Project Budget
 Planning the project budget at the beginning of the planning
session.
 It involves a lot of research and critical thinking.
 always have to leave room for adjustments as the costs may not
remain the same.
 Adhering to the project budget at all times is key to the profit
from project.
2. Keeping a Track of Costs
 Keeping track of all actual costs is also equally important as any
other technique.
 The actual costs will have to be tracked against the periodic
targets that have been set out in the budget.(monthly or weekly or
yearly basis)
 This is much easier to work with rather than having one complete
budget for the entire period of the project.
Civil Engineering – 20CE43P
3. Effective Time Management
 It is very important with regard to project cost control.
 Cost of project could keep rising if it is not completed in
scheduled time.
 The project manager would need to constantly remind his/her
team about project completion time.
4. Project Change Control
 Project change control is yet another vital technique
 Any change to the scope of the project will have an impact on the
deadlines of the deliverables
 So the changes may increase project cost
5. Use of Earned Value
 This technique is helpful to identify the value of the work that has
been carried out.
 This is particularly helpful for large projects
Civil Engineering – 20CE43P
3.Importance Management Information System
“An information system consisting of the tools and techniques
used to gather, integrate, and disseminate the outputs of project
management processes.
 It support in all aspects of the project from initiating through
closing
 It provides information and data that needs to be managed and
organized.
 It helps project professionals to easily plan and track project
progress in all stages of its lifecycle.
Civil Engineering – 20CE43P
Requirements for selecting a PMIS :
1. Planning & Scheduling
2. Budget & Estimating
3. Resource & Procurement Management
4. Cost Management & Project Performance
5. Progress Reporting
6. Data & System Integration
Civil Engineering – 20CE43P
1. Planning & Scheduling
 A PMIS will be able to plan and compute the project’s schedule
and its critical path.
2. Budget & Estimating
 A PMIS needs to combine project cost estimating, forecasting, cost
data and schedule information in order to determine accurate
project progress and performance.
3. Resource & Procurement Management
 It is important for a PMIS to have functionality to manage the
complete procurement process since resources and procured items
are a large portion of a project’s cost and preliminary budget.
Civil Engineering – 20CE43P
4. Cost Management & Project Performance
 A solid PMIS enables project managers to control project cost
and performance.
 It will allow for updating existing plans as actuals against
planned data changes, and provide what-if scenarios to them
while tracking and managing all project changes.
5. Progress Reporting
 A PMIS will have the capability to create and share reports of
collected and analyzed data.
6. Data & System Integration
 A PMIS needs to be able to integrate with other applications or
software systems.
 This system integration allows for accessing data from different
projects for multi-project analysis and bridging gaps between
systems and applications needed to have all project information
in one place.
Civil Engineering – 20CE43P
Thank You
Moderator : Sudhindra Yeri, GPT Bagalkote/152
Content Developer : Aniket Gachchi, GPT Kalgi/166
Civil Engineering – 20CE43P

More Related Content

What's hot

Earned Value Analysis
Earned Value AnalysisEarned Value Analysis
Earned Value Analysis
Ahmed Rami Elsherif, PMP, ITBMC
 
8. (lecture 6) Project Cost Control.ppt
8. (lecture 6) Project Cost Control.ppt8. (lecture 6) Project Cost Control.ppt
8. (lecture 6) Project Cost Control.ppt
PedadaSaikumar
 
Critical path method
Critical path methodCritical path method
Critical path method
Dushyant Nasit
 
Pert,cpm, resource allocation and gert
Pert,cpm, resource allocation and gertPert,cpm, resource allocation and gert
Pert,cpm, resource allocation and gert
Raj J Das
 
PERT and CPM
PERT and CPMPERT and CPM
PERT and CPM
student
 
Project Management Tools and Techniques (PERT- Project Evaluation and Review ...
Project Management Tools and Techniques (PERT- Project Evaluation and Review ...Project Management Tools and Techniques (PERT- Project Evaluation and Review ...
Project Management Tools and Techniques (PERT- Project Evaluation and Review ...
Zulfiquer Ahmed Amin
 
Construction Project Management
Construction Project ManagementConstruction Project Management
Construction Project Management
Aravind Samala
 
Project management chapter 1 notes
Project management chapter 1 notesProject management chapter 1 notes
Project management chapter 1 notes
Dreams Design
 
Cost analysis of Project
Cost analysis of ProjectCost analysis of Project
Cost analysis of Project
Pravin176
 
Project Control- Overview Presentation Tafseer
Project Control- Overview Presentation   TafseerProject Control- Overview Presentation   Tafseer
Project Control- Overview Presentation Tafseer
Kishan Solankimbaccepmp
 
Line of balance in civil engineering
Line of balance in civil engineeringLine of balance in civil engineering
Line of balance in civil engineering
rathodjaydeep2
 
construction project planing
 construction project planing construction project planing
construction project planing
SANJEEV Wazir
 
An Introduction To Project Management
An Introduction To Project ManagementAn Introduction To Project Management
An Introduction To Project Management
Ashish Mittal
 
Construction Scheduling, Work Study and Work Measurement _ Unit 2 _ Construct...
Construction Scheduling, Work Study and Work Measurement _ Unit 2 _ Construct...Construction Scheduling, Work Study and Work Measurement _ Unit 2 _ Construct...
Construction Scheduling, Work Study and Work Measurement _ Unit 2 _ Construct...
Shrikant Kate
 
Pert & cpm project management
Pert & cpm   project managementPert & cpm   project management
Pert & cpm project management
Rahul Dubey
 
Contracts
ContractsContracts
Contracts
krrish706
 
Types of contract in Project management
Types of contract in Project managementTypes of contract in Project management
Types of contract in Project management
Ali Heydari
 
Project management-planning and scheduling
Project management-planning and schedulingProject management-planning and scheduling
Project management-planning and scheduling
Aditi Garg
 
Project scheduling
Project schedulingProject scheduling
Project scheduling
Carla Fair-Wright
 
Fundamentals of scheduling
Fundamentals of schedulingFundamentals of scheduling
Fundamentals of scheduling
jmd2011
 

What's hot (20)

Earned Value Analysis
Earned Value AnalysisEarned Value Analysis
Earned Value Analysis
 
8. (lecture 6) Project Cost Control.ppt
8. (lecture 6) Project Cost Control.ppt8. (lecture 6) Project Cost Control.ppt
8. (lecture 6) Project Cost Control.ppt
 
Critical path method
Critical path methodCritical path method
Critical path method
 
Pert,cpm, resource allocation and gert
Pert,cpm, resource allocation and gertPert,cpm, resource allocation and gert
Pert,cpm, resource allocation and gert
 
PERT and CPM
PERT and CPMPERT and CPM
PERT and CPM
 
Project Management Tools and Techniques (PERT- Project Evaluation and Review ...
Project Management Tools and Techniques (PERT- Project Evaluation and Review ...Project Management Tools and Techniques (PERT- Project Evaluation and Review ...
Project Management Tools and Techniques (PERT- Project Evaluation and Review ...
 
Construction Project Management
Construction Project ManagementConstruction Project Management
Construction Project Management
 
Project management chapter 1 notes
Project management chapter 1 notesProject management chapter 1 notes
Project management chapter 1 notes
 
Cost analysis of Project
Cost analysis of ProjectCost analysis of Project
Cost analysis of Project
 
Project Control- Overview Presentation Tafseer
Project Control- Overview Presentation   TafseerProject Control- Overview Presentation   Tafseer
Project Control- Overview Presentation Tafseer
 
Line of balance in civil engineering
Line of balance in civil engineeringLine of balance in civil engineering
Line of balance in civil engineering
 
construction project planing
 construction project planing construction project planing
construction project planing
 
An Introduction To Project Management
An Introduction To Project ManagementAn Introduction To Project Management
An Introduction To Project Management
 
Construction Scheduling, Work Study and Work Measurement _ Unit 2 _ Construct...
Construction Scheduling, Work Study and Work Measurement _ Unit 2 _ Construct...Construction Scheduling, Work Study and Work Measurement _ Unit 2 _ Construct...
Construction Scheduling, Work Study and Work Measurement _ Unit 2 _ Construct...
 
Pert & cpm project management
Pert & cpm   project managementPert & cpm   project management
Pert & cpm project management
 
Contracts
ContractsContracts
Contracts
 
Types of contract in Project management
Types of contract in Project managementTypes of contract in Project management
Types of contract in Project management
 
Project management-planning and scheduling
Project management-planning and schedulingProject management-planning and scheduling
Project management-planning and scheduling
 
Project scheduling
Project schedulingProject scheduling
Project scheduling
 
Fundamentals of scheduling
Fundamentals of schedulingFundamentals of scheduling
Fundamentals of scheduling
 

Similar to Time Cost Trade Off

1.2 project management by bee 2
1.2 project management by bee 21.2 project management by bee 2
1.2 project management by bee 2
Narayan Mane
 
Construction Project management
Construction Project management Construction Project management
Construction Project management
Anupama holla
 
Time cost optimisation
Time cost optimisationTime cost optimisation
Time cost optimisation
Charul Sharma
 
Tracking a Typical Apartment Construction using Earned Value Management
Tracking a Typical Apartment Construction using Earned Value ManagementTracking a Typical Apartment Construction using Earned Value Management
Tracking a Typical Apartment Construction using Earned Value Management
IRJET Journal
 
45ef51191315a8630a639ff030b4cb67a3df6f49-1657701254277.ppt
45ef51191315a8630a639ff030b4cb67a3df6f49-1657701254277.ppt45ef51191315a8630a639ff030b4cb67a3df6f49-1657701254277.ppt
45ef51191315a8630a639ff030b4cb67a3df6f49-1657701254277.ppt
TinotendaChivese
 
Chapter 3.pptx
Chapter 3.pptxChapter 3.pptx
Chapter 3.pptx
BetshaTizazu2
 
EJMCM_Volume 7_Issue 4_Pages 310-318.pdf
EJMCM_Volume 7_Issue 4_Pages 310-318.pdfEJMCM_Volume 7_Issue 4_Pages 310-318.pdf
EJMCM_Volume 7_Issue 4_Pages 310-318.pdf
kripeshdubey1
 
Scheduling and Financial Analysis of a High Rise Building
Scheduling and Financial Analysis of a High Rise BuildingScheduling and Financial Analysis of a High Rise Building
Scheduling and Financial Analysis of a High Rise Building
iosrjce
 
A012610106
A012610106A012610106
A012610106
IOSR Journals
 
Projectmanagement anupama-Amit Payal
Projectmanagement anupama-Amit PayalProjectmanagement anupama-Amit Payal
Projectmanagement anupama-Amit Payal
AMIT PAYAL
 
7 cost managmenet
7 cost managmenet7 cost managmenet
7 cost managmenet
Ala Ibrahim
 
Identification of Bottleneck and Reducing Cycle Time of an Industrial Oven by...
Identification of Bottleneck and Reducing Cycle Time of an Industrial Oven by...Identification of Bottleneck and Reducing Cycle Time of an Industrial Oven by...
Identification of Bottleneck and Reducing Cycle Time of an Industrial Oven by...
IRJET Journal
 
project management-cpm and pert methods for managers
project management-cpm and pert methods for managersproject management-cpm and pert methods for managers
project management-cpm and pert methods for managers
Naganna Chetty
 
A760535773_16727_28_2018_u6.ppt
A760535773_16727_28_2018_u6.pptA760535773_16727_28_2018_u6.ppt
A760535773_16727_28_2018_u6.ppt
RajnikantPatel45
 
Project Management
Project ManagementProject Management
Project Management
Kibria Haider
 
CONSTRUCTION-PROJECT-MANAGEMENT-ppt.ppt
CONSTRUCTION-PROJECT-MANAGEMENT-ppt.pptCONSTRUCTION-PROJECT-MANAGEMENT-ppt.ppt
CONSTRUCTION-PROJECT-MANAGEMENT-ppt.ppt
pisal3
 
Chapter 5-Project Management.pptx
Chapter 5-Project Management.pptxChapter 5-Project Management.pptx
Chapter 5-Project Management.pptx
BahredinAbdella1
 
Project management
Project managementProject management
Project management
Kwesi Kissiedu
 
(Presentation) Cis utilization of earned value management for monitoring prod...
(Presentation) Cis utilization of earned value management for monitoring prod...(Presentation) Cis utilization of earned value management for monitoring prod...
(Presentation) Cis utilization of earned value management for monitoring prod...
Скоробогатов Дмитрий
 
Group 12 - Progress and Performance Measurement and Evaluation.pdf
Group 12 - Progress and Performance Measurement and Evaluation.pdfGroup 12 - Progress and Performance Measurement and Evaluation.pdf
Group 12 - Progress and Performance Measurement and Evaluation.pdf
alvieramada23
 

Similar to Time Cost Trade Off (20)

1.2 project management by bee 2
1.2 project management by bee 21.2 project management by bee 2
1.2 project management by bee 2
 
Construction Project management
Construction Project management Construction Project management
Construction Project management
 
Time cost optimisation
Time cost optimisationTime cost optimisation
Time cost optimisation
 
Tracking a Typical Apartment Construction using Earned Value Management
Tracking a Typical Apartment Construction using Earned Value ManagementTracking a Typical Apartment Construction using Earned Value Management
Tracking a Typical Apartment Construction using Earned Value Management
 
45ef51191315a8630a639ff030b4cb67a3df6f49-1657701254277.ppt
45ef51191315a8630a639ff030b4cb67a3df6f49-1657701254277.ppt45ef51191315a8630a639ff030b4cb67a3df6f49-1657701254277.ppt
45ef51191315a8630a639ff030b4cb67a3df6f49-1657701254277.ppt
 
Chapter 3.pptx
Chapter 3.pptxChapter 3.pptx
Chapter 3.pptx
 
EJMCM_Volume 7_Issue 4_Pages 310-318.pdf
EJMCM_Volume 7_Issue 4_Pages 310-318.pdfEJMCM_Volume 7_Issue 4_Pages 310-318.pdf
EJMCM_Volume 7_Issue 4_Pages 310-318.pdf
 
Scheduling and Financial Analysis of a High Rise Building
Scheduling and Financial Analysis of a High Rise BuildingScheduling and Financial Analysis of a High Rise Building
Scheduling and Financial Analysis of a High Rise Building
 
A012610106
A012610106A012610106
A012610106
 
Projectmanagement anupama-Amit Payal
Projectmanagement anupama-Amit PayalProjectmanagement anupama-Amit Payal
Projectmanagement anupama-Amit Payal
 
7 cost managmenet
7 cost managmenet7 cost managmenet
7 cost managmenet
 
Identification of Bottleneck and Reducing Cycle Time of an Industrial Oven by...
Identification of Bottleneck and Reducing Cycle Time of an Industrial Oven by...Identification of Bottleneck and Reducing Cycle Time of an Industrial Oven by...
Identification of Bottleneck and Reducing Cycle Time of an Industrial Oven by...
 
project management-cpm and pert methods for managers
project management-cpm and pert methods for managersproject management-cpm and pert methods for managers
project management-cpm and pert methods for managers
 
A760535773_16727_28_2018_u6.ppt
A760535773_16727_28_2018_u6.pptA760535773_16727_28_2018_u6.ppt
A760535773_16727_28_2018_u6.ppt
 
Project Management
Project ManagementProject Management
Project Management
 
CONSTRUCTION-PROJECT-MANAGEMENT-ppt.ppt
CONSTRUCTION-PROJECT-MANAGEMENT-ppt.pptCONSTRUCTION-PROJECT-MANAGEMENT-ppt.ppt
CONSTRUCTION-PROJECT-MANAGEMENT-ppt.ppt
 
Chapter 5-Project Management.pptx
Chapter 5-Project Management.pptxChapter 5-Project Management.pptx
Chapter 5-Project Management.pptx
 
Project management
Project managementProject management
Project management
 
(Presentation) Cis utilization of earned value management for monitoring prod...
(Presentation) Cis utilization of earned value management for monitoring prod...(Presentation) Cis utilization of earned value management for monitoring prod...
(Presentation) Cis utilization of earned value management for monitoring prod...
 
Group 12 - Progress and Performance Measurement and Evaluation.pdf
Group 12 - Progress and Performance Measurement and Evaluation.pdfGroup 12 - Progress and Performance Measurement and Evaluation.pdf
Group 12 - Progress and Performance Measurement and Evaluation.pdf
 

Recently uploaded

1FIDIC-CONSTRUCTION-CONTRACT-2ND-ED-2017-RED-BOOK.pdf
1FIDIC-CONSTRUCTION-CONTRACT-2ND-ED-2017-RED-BOOK.pdf1FIDIC-CONSTRUCTION-CONTRACT-2ND-ED-2017-RED-BOOK.pdf
1FIDIC-CONSTRUCTION-CONTRACT-2ND-ED-2017-RED-BOOK.pdf
MadhavJungKarki
 
Redefining brain tumor segmentation: a cutting-edge convolutional neural netw...
Redefining brain tumor segmentation: a cutting-edge convolutional neural netw...Redefining brain tumor segmentation: a cutting-edge convolutional neural netw...
Redefining brain tumor segmentation: a cutting-edge convolutional neural netw...
IJECEIAES
 
LLM Fine Tuning with QLoRA Cassandra Lunch 4, presented by Anant
LLM Fine Tuning with QLoRA Cassandra Lunch 4, presented by AnantLLM Fine Tuning with QLoRA Cassandra Lunch 4, presented by Anant
LLM Fine Tuning with QLoRA Cassandra Lunch 4, presented by Anant
Anant Corporation
 
SCALING OF MOS CIRCUITS m .pptx
SCALING OF MOS CIRCUITS m                 .pptxSCALING OF MOS CIRCUITS m                 .pptx
SCALING OF MOS CIRCUITS m .pptx
harshapolam10
 
4. Mosca vol I -Fisica-Tipler-5ta-Edicion-Vol-1.pdf
4. Mosca vol I -Fisica-Tipler-5ta-Edicion-Vol-1.pdf4. Mosca vol I -Fisica-Tipler-5ta-Edicion-Vol-1.pdf
4. Mosca vol I -Fisica-Tipler-5ta-Edicion-Vol-1.pdf
Gino153088
 
Computational Engineering IITH Presentation
Computational Engineering IITH PresentationComputational Engineering IITH Presentation
Computational Engineering IITH Presentation
co23btech11018
 
Data Driven Maintenance | UReason Webinar
Data Driven Maintenance | UReason WebinarData Driven Maintenance | UReason Webinar
Data Driven Maintenance | UReason Webinar
UReason
 
Applications of artificial Intelligence in Mechanical Engineering.pdf
Applications of artificial Intelligence in Mechanical Engineering.pdfApplications of artificial Intelligence in Mechanical Engineering.pdf
Applications of artificial Intelligence in Mechanical Engineering.pdf
Atif Razi
 
132/33KV substation case study Presentation
132/33KV substation case study Presentation132/33KV substation case study Presentation
132/33KV substation case study Presentation
kandramariana6
 
学校原版美国波士顿大学毕业证学历学位证书原版一模一样
学校原版美国波士顿大学毕业证学历学位证书原版一模一样学校原版美国波士顿大学毕业证学历学位证书原版一模一样
学校原版美国波士顿大学毕业证学历学位证书原版一模一样
171ticu
 
Software Engineering and Project Management - Software Testing + Agile Method...
Software Engineering and Project Management - Software Testing + Agile Method...Software Engineering and Project Management - Software Testing + Agile Method...
Software Engineering and Project Management - Software Testing + Agile Method...
Prakhyath Rai
 
原版制作(Humboldt毕业证书)柏林大学毕业证学位证一模一样
原版制作(Humboldt毕业证书)柏林大学毕业证学位证一模一样原版制作(Humboldt毕业证书)柏林大学毕业证学位证一模一样
原版制作(Humboldt毕业证书)柏林大学毕业证学位证一模一样
ydzowc
 
Null Bangalore | Pentesters Approach to AWS IAM
Null Bangalore | Pentesters Approach to AWS IAMNull Bangalore | Pentesters Approach to AWS IAM
Null Bangalore | Pentesters Approach to AWS IAM
Divyanshu
 
Electric vehicle and photovoltaic advanced roles in enhancing the financial p...
Electric vehicle and photovoltaic advanced roles in enhancing the financial p...Electric vehicle and photovoltaic advanced roles in enhancing the financial p...
Electric vehicle and photovoltaic advanced roles in enhancing the financial p...
IJECEIAES
 
DEEP LEARNING FOR SMART GRID INTRUSION DETECTION: A HYBRID CNN-LSTM-BASED MODEL
DEEP LEARNING FOR SMART GRID INTRUSION DETECTION: A HYBRID CNN-LSTM-BASED MODELDEEP LEARNING FOR SMART GRID INTRUSION DETECTION: A HYBRID CNN-LSTM-BASED MODEL
DEEP LEARNING FOR SMART GRID INTRUSION DETECTION: A HYBRID CNN-LSTM-BASED MODEL
ijaia
 
Advanced control scheme of doubly fed induction generator for wind turbine us...
Advanced control scheme of doubly fed induction generator for wind turbine us...Advanced control scheme of doubly fed induction generator for wind turbine us...
Advanced control scheme of doubly fed induction generator for wind turbine us...
IJECEIAES
 
Comparative analysis between traditional aquaponics and reconstructed aquapon...
Comparative analysis between traditional aquaponics and reconstructed aquapon...Comparative analysis between traditional aquaponics and reconstructed aquapon...
Comparative analysis between traditional aquaponics and reconstructed aquapon...
bijceesjournal
 
一比一原版(CalArts毕业证)加利福尼亚艺术学院毕业证如何办理
一比一原版(CalArts毕业证)加利福尼亚艺术学院毕业证如何办理一比一原版(CalArts毕业证)加利福尼亚艺术学院毕业证如何办理
一比一原版(CalArts毕业证)加利福尼亚艺术学院毕业证如何办理
ecqow
 
Embedded machine learning-based road conditions and driving behavior monitoring
Embedded machine learning-based road conditions and driving behavior monitoringEmbedded machine learning-based road conditions and driving behavior monitoring
Embedded machine learning-based road conditions and driving behavior monitoring
IJECEIAES
 
morris_worm_intro_and_source_code_analysis_.pdf
morris_worm_intro_and_source_code_analysis_.pdfmorris_worm_intro_and_source_code_analysis_.pdf
morris_worm_intro_and_source_code_analysis_.pdf
ycwu0509
 

Recently uploaded (20)

1FIDIC-CONSTRUCTION-CONTRACT-2ND-ED-2017-RED-BOOK.pdf
1FIDIC-CONSTRUCTION-CONTRACT-2ND-ED-2017-RED-BOOK.pdf1FIDIC-CONSTRUCTION-CONTRACT-2ND-ED-2017-RED-BOOK.pdf
1FIDIC-CONSTRUCTION-CONTRACT-2ND-ED-2017-RED-BOOK.pdf
 
Redefining brain tumor segmentation: a cutting-edge convolutional neural netw...
Redefining brain tumor segmentation: a cutting-edge convolutional neural netw...Redefining brain tumor segmentation: a cutting-edge convolutional neural netw...
Redefining brain tumor segmentation: a cutting-edge convolutional neural netw...
 
LLM Fine Tuning with QLoRA Cassandra Lunch 4, presented by Anant
LLM Fine Tuning with QLoRA Cassandra Lunch 4, presented by AnantLLM Fine Tuning with QLoRA Cassandra Lunch 4, presented by Anant
LLM Fine Tuning with QLoRA Cassandra Lunch 4, presented by Anant
 
SCALING OF MOS CIRCUITS m .pptx
SCALING OF MOS CIRCUITS m                 .pptxSCALING OF MOS CIRCUITS m                 .pptx
SCALING OF MOS CIRCUITS m .pptx
 
4. Mosca vol I -Fisica-Tipler-5ta-Edicion-Vol-1.pdf
4. Mosca vol I -Fisica-Tipler-5ta-Edicion-Vol-1.pdf4. Mosca vol I -Fisica-Tipler-5ta-Edicion-Vol-1.pdf
4. Mosca vol I -Fisica-Tipler-5ta-Edicion-Vol-1.pdf
 
Computational Engineering IITH Presentation
Computational Engineering IITH PresentationComputational Engineering IITH Presentation
Computational Engineering IITH Presentation
 
Data Driven Maintenance | UReason Webinar
Data Driven Maintenance | UReason WebinarData Driven Maintenance | UReason Webinar
Data Driven Maintenance | UReason Webinar
 
Applications of artificial Intelligence in Mechanical Engineering.pdf
Applications of artificial Intelligence in Mechanical Engineering.pdfApplications of artificial Intelligence in Mechanical Engineering.pdf
Applications of artificial Intelligence in Mechanical Engineering.pdf
 
132/33KV substation case study Presentation
132/33KV substation case study Presentation132/33KV substation case study Presentation
132/33KV substation case study Presentation
 
学校原版美国波士顿大学毕业证学历学位证书原版一模一样
学校原版美国波士顿大学毕业证学历学位证书原版一模一样学校原版美国波士顿大学毕业证学历学位证书原版一模一样
学校原版美国波士顿大学毕业证学历学位证书原版一模一样
 
Software Engineering and Project Management - Software Testing + Agile Method...
Software Engineering and Project Management - Software Testing + Agile Method...Software Engineering and Project Management - Software Testing + Agile Method...
Software Engineering and Project Management - Software Testing + Agile Method...
 
原版制作(Humboldt毕业证书)柏林大学毕业证学位证一模一样
原版制作(Humboldt毕业证书)柏林大学毕业证学位证一模一样原版制作(Humboldt毕业证书)柏林大学毕业证学位证一模一样
原版制作(Humboldt毕业证书)柏林大学毕业证学位证一模一样
 
Null Bangalore | Pentesters Approach to AWS IAM
Null Bangalore | Pentesters Approach to AWS IAMNull Bangalore | Pentesters Approach to AWS IAM
Null Bangalore | Pentesters Approach to AWS IAM
 
Electric vehicle and photovoltaic advanced roles in enhancing the financial p...
Electric vehicle and photovoltaic advanced roles in enhancing the financial p...Electric vehicle and photovoltaic advanced roles in enhancing the financial p...
Electric vehicle and photovoltaic advanced roles in enhancing the financial p...
 
DEEP LEARNING FOR SMART GRID INTRUSION DETECTION: A HYBRID CNN-LSTM-BASED MODEL
DEEP LEARNING FOR SMART GRID INTRUSION DETECTION: A HYBRID CNN-LSTM-BASED MODELDEEP LEARNING FOR SMART GRID INTRUSION DETECTION: A HYBRID CNN-LSTM-BASED MODEL
DEEP LEARNING FOR SMART GRID INTRUSION DETECTION: A HYBRID CNN-LSTM-BASED MODEL
 
Advanced control scheme of doubly fed induction generator for wind turbine us...
Advanced control scheme of doubly fed induction generator for wind turbine us...Advanced control scheme of doubly fed induction generator for wind turbine us...
Advanced control scheme of doubly fed induction generator for wind turbine us...
 
Comparative analysis between traditional aquaponics and reconstructed aquapon...
Comparative analysis between traditional aquaponics and reconstructed aquapon...Comparative analysis between traditional aquaponics and reconstructed aquapon...
Comparative analysis between traditional aquaponics and reconstructed aquapon...
 
一比一原版(CalArts毕业证)加利福尼亚艺术学院毕业证如何办理
一比一原版(CalArts毕业证)加利福尼亚艺术学院毕业证如何办理一比一原版(CalArts毕业证)加利福尼亚艺术学院毕业证如何办理
一比一原版(CalArts毕业证)加利福尼亚艺术学院毕业证如何办理
 
Embedded machine learning-based road conditions and driving behavior monitoring
Embedded machine learning-based road conditions and driving behavior monitoringEmbedded machine learning-based road conditions and driving behavior monitoring
Embedded machine learning-based road conditions and driving behavior monitoring
 
morris_worm_intro_and_source_code_analysis_.pdf
morris_worm_intro_and_source_code_analysis_.pdfmorris_worm_intro_and_source_code_analysis_.pdf
morris_worm_intro_and_source_code_analysis_.pdf
 

Time Cost Trade Off

  • 1. Department of Collegiate and Technical Education Week – 09, Session - 03 Course outcome: 20CE43P Site Management ( IV Semester) Civil Engineering Civil Engineering – 20CE43P
  • 2. Table of Content 1. Time-Cost Trade-Off 2. Cost Control in Construction 3. Importance of Management Information System 4. MCQ Civil Engineering – 20CE43P
  • 3. 1. Time-Cost Trade-Off Terms related to Time-Cost Trade-Off a) Direct Project Cost : The cost and expenses that are accountable on facility, function or product such as cost incurred on labour, material, equipment etc. are called as direct costs.  Normal Time : Normal time is the standard time that an estimator would usually allowed for an activity.  Crash Time : Crash time is the minimum possible time in which an activity can be completed.  Normal Cost : This is direct cost required to complete the activity in normal time duration.  Crash Cost : This is the direct cost corresponding to the completion of the activity within crash time. Civil Engineering – 20CE43P
  • 4.  Cost Slope : This is the slope of the direct cost curve, approximated as straight line. 𝐶𝑜𝑠𝑡 𝑆𝑙𝑜𝑝𝑒 = (𝐶𝑟𝑎𝑠ℎ 𝐶𝑜𝑠𝑡 − 𝑁𝑜𝑟𝑚𝑎𝑙 𝐶𝑜𝑠𝑡) (𝑁𝑜𝑟𝑚𝑎𝑙 𝑇𝑖𝑚𝑒 − 𝐶𝑟𝑎𝑠ℎ 𝑇𝑖𝑚𝑒) b) Indirect Project Cost : An indirect cost in construction is an expense that doesn't relate directly to the functions, products or operations of a construction project such as cost incurred on administrative processes and staff salaries, overhead cost, lost profit, loss of revenue, penalty etc. c) Total Project Cost : This is the sum of direct project cost and indirect project cost. d) Optimum Duration & Optimum Cost : The duration in which minimum total cost is obtained is known as optimum duration and the corresponding cost is known as optimum cost. Civil Engineering – 20CE43P
  • 5. What is Time-Cost Trade-Off or Crashing ? The process of reduction of total project duration along the longest path (time wise) of the network i.e. along the critical path to obtain the optimum project cost and optimum duration is called “time-cost trade-off or crashing”. The activity duration can be reduced by one of the following actions:  Applying multiple-shifts work.  Working extended hours (over time).  Offering incentive payments to increase the productivity.  Working on week ends and holidays.  Using additional resources.  Using materials with faster installation methods.  Using alternate construction methods or sequence. Civil Engineering – 20CE43P
  • 6. Procedure for crashing the network : 1) Draw the network diagram. 2) Determine the critical path. 3) Indicates critical path along network diagram. 4) Determine cost slope of each activity. 5) Start crashing the activities along the critical path having minimum cost slope. 6) Activity having minimum cost slope is crashed until its crashing potential is exhausted and new critical path are formed. 7) If new critical path is formed then we to crash combination of critical activity (parallel activity) having minimum cost slope and continue till there is no further scope of crashing. Civil Engineering – 20CE43P
  • 7. 1.1 Example for crashing of project work : Consider the data of a project as shown in the following table- 1.1which has to be complete in 9days. Take overhead cost of the project = Rs.200/day Table-1.1 Civil Engineering – 20CE43P Activity Normal Time (Days) Normal Cost (Rs.) Crash Time (Days) Crash Cost (Rs.) 1-2 3 2500 1 3500 2-3 4 2600 2 3400 2-4 7 2500 4 3400 3-4 5 2400 2 3000
  • 8. Solution : Step -1 : Draw the network diagram. Fig-1.1 Step -2 : Determine the critical path. Fig-1.2 Civil Engineering – 20CE43P Possible Paths = 1-2-3-4=12days 1-2-7=10days Critical Path = 1-2-3-4 Project Duration = 12days Normal Project Cost = 10000 Total Project Cost = 10000+12x200 =12400
  • 9. Step-3 : Determine cost slope of each activity 𝐶𝑜𝑠𝑡 𝑆𝑙𝑜𝑝𝑒 = (𝐶𝑟𝑎𝑠ℎ 𝐶𝑜𝑠𝑡 − 𝑁𝑜𝑟𝑚𝑎𝑙 𝐶𝑜𝑠𝑡) (𝑁𝑜𝑟𝑚𝑎𝑙 𝑇𝑖𝑚𝑒 − 𝐶𝑟𝑎𝑠ℎ 𝑇𝑖𝑚𝑒) 𝐶𝑜𝑠𝑡 𝑆𝑙𝑜𝑝𝑒 𝑜𝑓 1 − 2 = 3500 − 2500 3 − 1 = 500 Similarly calculate the cost slope of each activity and enter as shown in table-1.2 Table-1.2 Civil Engineering – 20CE43P Activity Normal Time (Days) Normal Cost (Rs.) Crash Time (Days) Crash Cost (Rs.) Cost Slope (Rs.) 1-2 3 2500 1 3500 500 2-3 4 2600 2 3400 400 2-4 7 2500 4 3400 100 3-4 5 2400 2 3000 200
  • 10. Step-4 : Start crashing the activities along the critical path having minimum cost slope. Crashing the activity 3-4 by 2 days which has minimum cost slope of Rs.200 ∴ Total Project Cost = 12400+2x200-2x200= 12400 Step-5 : If new critical path is formed then we have to crash combination of critical activity (parallel activity) having minimum cost slope and continue till there is no further scope of crashing. Fig-1.3 Civil Engineering – 20CE43P
  • 11. From the above network (Fig-1.3) we found two critical paths (1- 2-3-4 and 1-2-4) of same duration. From the table-2 it is clear that we can crash the activities 2-4 by 1day and 3-4 by 1day which has minimum cost slope value of Rs.100 and Rs.200 respectively to crash the network to maximum of 9 days. Fig-1.4 ∴ Total Project Cost = 12400+(1x100+1x200)-1x200=12500 Finally the total project cost to complete the project in 9days by crashing the activities is Rs.12500 Civil Engineering – 20CE43P Activity Crash Time (Days) Cost Slope (Rs.) 1-2 1 500 2-3 2 400 2-4 4 100 3-4 2 200
  • 12. 2. Cost Control in Construction Cost control in construction is the process by which managers keep expenses under control by managing labor, material, and overhead costs to ensure that the project finishes on budget. Cost Control Techniques : Following are some of the valuable and essential techniques used for efficient project cost control: 1. Planning the Project Budget 2. Keeping a Track of Costs 3. Effective Time Management 4. Project Change Control 5. Use of Earned Value Civil Engineering – 20CE43P
  • 13. 1. Planning the Project Budget  Planning the project budget at the beginning of the planning session.  It involves a lot of research and critical thinking.  always have to leave room for adjustments as the costs may not remain the same.  Adhering to the project budget at all times is key to the profit from project. 2. Keeping a Track of Costs  Keeping track of all actual costs is also equally important as any other technique.  The actual costs will have to be tracked against the periodic targets that have been set out in the budget.(monthly or weekly or yearly basis)  This is much easier to work with rather than having one complete budget for the entire period of the project. Civil Engineering – 20CE43P
  • 14. 3. Effective Time Management  It is very important with regard to project cost control.  Cost of project could keep rising if it is not completed in scheduled time.  The project manager would need to constantly remind his/her team about project completion time. 4. Project Change Control  Project change control is yet another vital technique  Any change to the scope of the project will have an impact on the deadlines of the deliverables  So the changes may increase project cost 5. Use of Earned Value  This technique is helpful to identify the value of the work that has been carried out.  This is particularly helpful for large projects Civil Engineering – 20CE43P
  • 15. 3.Importance Management Information System “An information system consisting of the tools and techniques used to gather, integrate, and disseminate the outputs of project management processes.  It support in all aspects of the project from initiating through closing  It provides information and data that needs to be managed and organized.  It helps project professionals to easily plan and track project progress in all stages of its lifecycle. Civil Engineering – 20CE43P
  • 16. Requirements for selecting a PMIS : 1. Planning & Scheduling 2. Budget & Estimating 3. Resource & Procurement Management 4. Cost Management & Project Performance 5. Progress Reporting 6. Data & System Integration Civil Engineering – 20CE43P
  • 17. 1. Planning & Scheduling  A PMIS will be able to plan and compute the project’s schedule and its critical path. 2. Budget & Estimating  A PMIS needs to combine project cost estimating, forecasting, cost data and schedule information in order to determine accurate project progress and performance. 3. Resource & Procurement Management  It is important for a PMIS to have functionality to manage the complete procurement process since resources and procured items are a large portion of a project’s cost and preliminary budget. Civil Engineering – 20CE43P
  • 18. 4. Cost Management & Project Performance  A solid PMIS enables project managers to control project cost and performance.  It will allow for updating existing plans as actuals against planned data changes, and provide what-if scenarios to them while tracking and managing all project changes. 5. Progress Reporting  A PMIS will have the capability to create and share reports of collected and analyzed data. 6. Data & System Integration  A PMIS needs to be able to integrate with other applications or software systems.  This system integration allows for accessing data from different projects for multi-project analysis and bridging gaps between systems and applications needed to have all project information in one place. Civil Engineering – 20CE43P
  • 19. Thank You Moderator : Sudhindra Yeri, GPT Bagalkote/152 Content Developer : Aniket Gachchi, GPT Kalgi/166 Civil Engineering – 20CE43P