SlideShare a Scribd company logo
1 of 12
Milestone Report 2
Patient Tracking Application
IT 4983
KSU CSE
MARCH 17, 2017
Stephen Cain, Chris Cheveresan, Jun-Hao Kuah, Victoria McDonald, Aline Moche Chatue
Project Summary
Alternative final deliverables have been set and agreed upon.
Unanticipated crash of server. Impacted about 18% of timeline.
Some work had to be re-coded.
Server restored March 13th but with slightly older versions of
software.
Client established three critical use cases to complete given the time
left in the project
Project Challenges
The server we were working on had a hardware malfunction and
crashed.
The group participated in the restoring of the SQL server database
on the server once it was reprovisioned.
Due to the two week delay, the group developed an alternate
mode of work
Milestone Assessment - Summary
Add/Delete Patient-Diagnosis - Incomplete
Add/Change Compliance - Incomplete
Print Turnaround Document – 1 - Partially Complete
Report Patients Not In Compliance - Incomplete
These were the deliverables set in the original project plan.
In the revised project plan:
200 hours worth of work remain
Remaining tasks require 34 more hours than the original plan
The group’s level of confidence in completing the project is high
Milestone Assessment - Print
Turnaround Document
Milestone Assessment - Print
Turnaround Document
Lessons Learned
Secure and transfer backups of database and files before starting
work.
Documenting and tracking information as pieces were edited and
take constant “screenshots” of our work.
Learned how to install SQL Server 2008 R2.
Learned the harsh truth about server crashes.
Lessons Learned (Cont.)
Process Challenges
Due to the limited time left, work ethic among all of us will need
to improve to tackle the remainder of the project.
Web application interface is the largest of the remaining tasks and
will need to be our primary focus.
Need tight scheduling to work around the lack of multiple
concurrent logons.
Gantt Chart
Plan for Milestone 3
15 tasks remain
◦ 7 coding tasks
◦ 2 testing tasks
◦ 3 documentation tasks
◦ 3 presentation preparation tasks
Critical to avoid any further delays
Plan for Milestone 3 (Cont.)
Revised Final Deliverables
◦ Add / Change Patient
◦ Record Compliance
◦ Print Turnaround Document – 1

More Related Content

What's hot

Gentile Consulting
Gentile ConsultingGentile Consulting
Gentile Consultingcgentile
 
Project control & Monitoring
Project control & MonitoringProject control & Monitoring
Project control & MonitoringJawad Ahmad
 
2.06 time management 1
2.06 time management 12.06 time management 1
2.06 time management 1reddvise
 
00 Introduction of project scheduling
00 Introduction of project scheduling00 Introduction of project scheduling
00 Introduction of project schedulingSoe Naing Win
 
Presentation on scheduling
Presentation on schedulingPresentation on scheduling
Presentation on schedulingGunjan Lal
 
Green Computing as an Engineering Discipline
Green Computing as an Engineering DisciplineGreen Computing as an Engineering Discipline
Green Computing as an Engineering DisciplineGreenLabAtDI
 
PROJECT SCHEDULE
PROJECT SCHEDULEPROJECT SCHEDULE
PROJECT SCHEDULEAjeesh Mk
 
Db change management automation:- Devops and Ansible
Db change management automation:- Devops and AnsibleDb change management automation:- Devops and Ansible
Db change management automation:- Devops and Ansiblepvemuri
 
Agile Development Practice
Agile Development PracticeAgile Development Practice
Agile Development PracticeKshitiz Goel
 
Critical Chain Slides Part 2
Critical Chain Slides   Part 2Critical Chain Slides   Part 2
Critical Chain Slides Part 2davehinde
 
Risk managementforsponsors barnes
Risk managementforsponsors barnesRisk managementforsponsors barnes
Risk managementforsponsors barnescaptsumit
 
Scheduling MS project 09.13.rev 1
Scheduling MS project 09.13.rev 1Scheduling MS project 09.13.rev 1
Scheduling MS project 09.13.rev 1Gaurav Shrivastava
 
Unit2 scheduling wbs_network
Unit2 scheduling wbs_networkUnit2 scheduling wbs_network
Unit2 scheduling wbs_networkReetesh Gupta
 
Project Management focused on Scheduling of a Project
Project Management focused on Scheduling of a ProjectProject Management focused on Scheduling of a Project
Project Management focused on Scheduling of a ProjectMeryem Yıldız
 
Time --updated 60b084af4f5af-
Time --updated 60b084af4f5af-Time --updated 60b084af4f5af-
Time --updated 60b084af4f5af-seminiMaya
 
The Project Status & The Portfolio
The Project Status & The PortfolioThe Project Status & The Portfolio
The Project Status & The PortfolioNed Johnson
 
Program Management 2.0: Schedule Prediction Accuracy
Program Management 2.0: Schedule Prediction AccuracyProgram Management 2.0: Schedule Prediction Accuracy
Program Management 2.0: Schedule Prediction AccuracyJohn Carter
 

What's hot (20)

Project scheduling
Project schedulingProject scheduling
Project scheduling
 
Gentile Consulting
Gentile ConsultingGentile Consulting
Gentile Consulting
 
Project control & Monitoring
Project control & MonitoringProject control & Monitoring
Project control & Monitoring
 
2.06 time management 1
2.06 time management 12.06 time management 1
2.06 time management 1
 
00 Introduction of project scheduling
00 Introduction of project scheduling00 Introduction of project scheduling
00 Introduction of project scheduling
 
Session 8 4th edition PMP
Session 8 4th edition PMPSession 8 4th edition PMP
Session 8 4th edition PMP
 
Presentation on scheduling
Presentation on schedulingPresentation on scheduling
Presentation on scheduling
 
Green Computing as an Engineering Discipline
Green Computing as an Engineering DisciplineGreen Computing as an Engineering Discipline
Green Computing as an Engineering Discipline
 
PROJECT SCHEDULE
PROJECT SCHEDULEPROJECT SCHEDULE
PROJECT SCHEDULE
 
Db change management automation:- Devops and Ansible
Db change management automation:- Devops and AnsibleDb change management automation:- Devops and Ansible
Db change management automation:- Devops and Ansible
 
Agile Development Practice
Agile Development PracticeAgile Development Practice
Agile Development Practice
 
Critical Chain Slides Part 2
Critical Chain Slides   Part 2Critical Chain Slides   Part 2
Critical Chain Slides Part 2
 
Risk managementforsponsors barnes
Risk managementforsponsors barnesRisk managementforsponsors barnes
Risk managementforsponsors barnes
 
PMIWCI-Dist
PMIWCI-DistPMIWCI-Dist
PMIWCI-Dist
 
Scheduling MS project 09.13.rev 1
Scheduling MS project 09.13.rev 1Scheduling MS project 09.13.rev 1
Scheduling MS project 09.13.rev 1
 
Unit2 scheduling wbs_network
Unit2 scheduling wbs_networkUnit2 scheduling wbs_network
Unit2 scheduling wbs_network
 
Project Management focused on Scheduling of a Project
Project Management focused on Scheduling of a ProjectProject Management focused on Scheduling of a Project
Project Management focused on Scheduling of a Project
 
Time --updated 60b084af4f5af-
Time --updated 60b084af4f5af-Time --updated 60b084af4f5af-
Time --updated 60b084af4f5af-
 
The Project Status & The Portfolio
The Project Status & The PortfolioThe Project Status & The Portfolio
The Project Status & The Portfolio
 
Program Management 2.0: Schedule Prediction Accuracy
Program Management 2.0: Schedule Prediction AccuracyProgram Management 2.0: Schedule Prediction Accuracy
Program Management 2.0: Schedule Prediction Accuracy
 

Similar to Docweb Milestone 2 Report

Doc web milestone 1 report
Doc web milestone 1 report Doc web milestone 1 report
Doc web milestone 1 report Stephen Cain Jr.
 
Pc Order To Installation Cycle Time Reduction Display
Pc Order To Installation Cycle Time Reduction DisplayPc Order To Installation Cycle Time Reduction Display
Pc Order To Installation Cycle Time Reduction Displaywhayes2000
 
Perferred Resources
Perferred ResourcesPerferred Resources
Perferred ResourcesRudy Hubert
 
Visualisation&agile practices ai2014
Visualisation&agile practices ai2014Visualisation&agile practices ai2014
Visualisation&agile practices ai2014Balaji Muniraja
 
The 5S Approach to Performance Tuning by Chuck Ezell
The 5S Approach to Performance Tuning by Chuck EzellThe 5S Approach to Performance Tuning by Chuck Ezell
The 5S Approach to Performance Tuning by Chuck EzellDatavail
 
DASC 5303 00 – Team 4 - Assignment 6.pptx
DASC 5303 00 – Team 4 - Assignment 6.pptxDASC 5303 00 – Team 4 - Assignment 6.pptx
DASC 5303 00 – Team 4 - Assignment 6.pptx17542Saiteja
 
The Federal Open Market Committee (FOMC) will meet on Sept. 25th a.docx
The Federal Open Market Committee (FOMC) will meet on Sept. 25th a.docxThe Federal Open Market Committee (FOMC) will meet on Sept. 25th a.docx
The Federal Open Market Committee (FOMC) will meet on Sept. 25th a.docxtodd771
 
Running Head PROJECT PLAN-BUSINESS REQUIREMENT DOCUMENT .docx
Running Head PROJECT PLAN-BUSINESS REQUIREMENT DOCUMENT      .docxRunning Head PROJECT PLAN-BUSINESS REQUIREMENT DOCUMENT      .docx
Running Head PROJECT PLAN-BUSINESS REQUIREMENT DOCUMENT .docxjeanettehully
 
Chapter-5-Scheduling-and-Resource-Allocation.ppt
Chapter-5-Scheduling-and-Resource-Allocation.pptChapter-5-Scheduling-and-Resource-Allocation.ppt
Chapter-5-Scheduling-and-Resource-Allocation.pptTecnicoItca
 
Conveyor belt project
Conveyor belt projectConveyor belt project
Conveyor belt projectSamehTeleb
 
Golive Presentation.pptx
Golive Presentation.pptxGolive Presentation.pptx
Golive Presentation.pptxSridhar
 
Project management (A Basic Approach)
Project management (A Basic Approach)Project management (A Basic Approach)
Project management (A Basic Approach)Jed Concepcion
 
JeffDavisProjectPortfolio
JeffDavisProjectPortfolioJeffDavisProjectPortfolio
JeffDavisProjectPortfolioJeff Davis
 
Project charter and plan document for millennium upgrade
Project charter and plan document for millennium upgradeProject charter and plan document for millennium upgrade
Project charter and plan document for millennium upgradeTheodore Van Patten, Jr.
 
R squared weekly-status_03012010[1]
R squared  weekly-status_03012010[1]R squared  weekly-status_03012010[1]
R squared weekly-status_03012010[1]Captainsamcox
 
Four Essential Steps for Removing Risk and Downtime from POWER9 Migration
Four Essential Steps for Removing Risk and Downtime from POWER9 MigrationFour Essential Steps for Removing Risk and Downtime from POWER9 Migration
Four Essential Steps for Removing Risk and Downtime from POWER9 MigrationPrecisely
 

Similar to Docweb Milestone 2 Report (20)

Doc web milestone 1 report
Doc web milestone 1 report Doc web milestone 1 report
Doc web milestone 1 report
 
Pc Order To Installation Cycle Time Reduction Display
Pc Order To Installation Cycle Time Reduction DisplayPc Order To Installation Cycle Time Reduction Display
Pc Order To Installation Cycle Time Reduction Display
 
Perferred Resources
Perferred ResourcesPerferred Resources
Perferred Resources
 
Project Plan - Docweb
Project Plan - DocwebProject Plan - Docweb
Project Plan - Docweb
 
Visualisation&agile practices ai2014
Visualisation&agile practices ai2014Visualisation&agile practices ai2014
Visualisation&agile practices ai2014
 
The 5S Approach to Performance Tuning by Chuck Ezell
The 5S Approach to Performance Tuning by Chuck EzellThe 5S Approach to Performance Tuning by Chuck Ezell
The 5S Approach to Performance Tuning by Chuck Ezell
 
DASC 5303 00 – Team 4 - Assignment 6.pptx
DASC 5303 00 – Team 4 - Assignment 6.pptxDASC 5303 00 – Team 4 - Assignment 6.pptx
DASC 5303 00 – Team 4 - Assignment 6.pptx
 
IQA_Project
IQA_ProjectIQA_Project
IQA_Project
 
The Federal Open Market Committee (FOMC) will meet on Sept. 25th a.docx
The Federal Open Market Committee (FOMC) will meet on Sept. 25th a.docxThe Federal Open Market Committee (FOMC) will meet on Sept. 25th a.docx
The Federal Open Market Committee (FOMC) will meet on Sept. 25th a.docx
 
Running Head PROJECT PLAN-BUSINESS REQUIREMENT DOCUMENT .docx
Running Head PROJECT PLAN-BUSINESS REQUIREMENT DOCUMENT      .docxRunning Head PROJECT PLAN-BUSINESS REQUIREMENT DOCUMENT      .docx
Running Head PROJECT PLAN-BUSINESS REQUIREMENT DOCUMENT .docx
 
Chapter-5-Scheduling-and-Resource-Allocation.ppt
Chapter-5-Scheduling-and-Resource-Allocation.pptChapter-5-Scheduling-and-Resource-Allocation.ppt
Chapter-5-Scheduling-and-Resource-Allocation.ppt
 
Conveyor belt project
Conveyor belt projectConveyor belt project
Conveyor belt project
 
CPM-Updating
CPM-UpdatingCPM-Updating
CPM-Updating
 
Golive Presentation.pptx
Golive Presentation.pptxGolive Presentation.pptx
Golive Presentation.pptx
 
Project management (A Basic Approach)
Project management (A Basic Approach)Project management (A Basic Approach)
Project management (A Basic Approach)
 
JeffDavisProjectPortfolio
JeffDavisProjectPortfolioJeffDavisProjectPortfolio
JeffDavisProjectPortfolio
 
Project charter and plan document for millennium upgrade
Project charter and plan document for millennium upgradeProject charter and plan document for millennium upgrade
Project charter and plan document for millennium upgrade
 
Himanshu_Resume
Himanshu_ResumeHimanshu_Resume
Himanshu_Resume
 
R squared weekly-status_03012010[1]
R squared  weekly-status_03012010[1]R squared  weekly-status_03012010[1]
R squared weekly-status_03012010[1]
 
Four Essential Steps for Removing Risk and Downtime from POWER9 Migration
Four Essential Steps for Removing Risk and Downtime from POWER9 MigrationFour Essential Steps for Removing Risk and Downtime from POWER9 Migration
Four Essential Steps for Removing Risk and Downtime from POWER9 Migration
 

Recently uploaded

Re-membering the Bard: Revisiting The Compleat Wrks of Wllm Shkspr (Abridged)...
Re-membering the Bard: Revisiting The Compleat Wrks of Wllm Shkspr (Abridged)...Re-membering the Bard: Revisiting The Compleat Wrks of Wllm Shkspr (Abridged)...
Re-membering the Bard: Revisiting The Compleat Wrks of Wllm Shkspr (Abridged)...Hasting Chen
 
Andrés Ramírez Gossler, Facundo Schinnea - eCommerce Day Chile 2024
Andrés Ramírez Gossler, Facundo Schinnea - eCommerce Day Chile 2024Andrés Ramírez Gossler, Facundo Schinnea - eCommerce Day Chile 2024
Andrés Ramírez Gossler, Facundo Schinnea - eCommerce Day Chile 2024eCommerce Institute
 
Thirunelveli call girls Tamil escorts 7877702510
Thirunelveli call girls Tamil escorts 7877702510Thirunelveli call girls Tamil escorts 7877702510
Thirunelveli call girls Tamil escorts 7877702510Vipesco
 
CTAC 2024 Valencia - Henrik Hanke - Reduce to the max - slideshare.pdf
CTAC 2024 Valencia - Henrik Hanke - Reduce to the max - slideshare.pdfCTAC 2024 Valencia - Henrik Hanke - Reduce to the max - slideshare.pdf
CTAC 2024 Valencia - Henrik Hanke - Reduce to the max - slideshare.pdfhenrik385807
 
Presentation on Engagement in Book Clubs
Presentation on Engagement in Book ClubsPresentation on Engagement in Book Clubs
Presentation on Engagement in Book Clubssamaasim06
 
George Lever - eCommerce Day Chile 2024
George Lever -  eCommerce Day Chile 2024George Lever -  eCommerce Day Chile 2024
George Lever - eCommerce Day Chile 2024eCommerce Institute
 
Exploring protein-protein interactions by Weak Affinity Chromatography (WAC) ...
Exploring protein-protein interactions by Weak Affinity Chromatography (WAC) ...Exploring protein-protein interactions by Weak Affinity Chromatography (WAC) ...
Exploring protein-protein interactions by Weak Affinity Chromatography (WAC) ...Salam Al-Karadaghi
 
Call Girls in Sarojini Nagar Market Delhi 💯 Call Us 🔝8264348440🔝
Call Girls in Sarojini Nagar Market Delhi 💯 Call Us 🔝8264348440🔝Call Girls in Sarojini Nagar Market Delhi 💯 Call Us 🔝8264348440🔝
Call Girls in Sarojini Nagar Market Delhi 💯 Call Us 🔝8264348440🔝soniya singh
 
Navi Mumbai Call Girls Service Pooja 9892124323 Real Russian Girls Looking Mo...
Navi Mumbai Call Girls Service Pooja 9892124323 Real Russian Girls Looking Mo...Navi Mumbai Call Girls Service Pooja 9892124323 Real Russian Girls Looking Mo...
Navi Mumbai Call Girls Service Pooja 9892124323 Real Russian Girls Looking Mo...Pooja Nehwal
 
No Advance 8868886958 Chandigarh Call Girls , Indian Call Girls For Full Nigh...
No Advance 8868886958 Chandigarh Call Girls , Indian Call Girls For Full Nigh...No Advance 8868886958 Chandigarh Call Girls , Indian Call Girls For Full Nigh...
No Advance 8868886958 Chandigarh Call Girls , Indian Call Girls For Full Nigh...Sheetaleventcompany
 
Introduction to Prompt Engineering (Focusing on ChatGPT)
Introduction to Prompt Engineering (Focusing on ChatGPT)Introduction to Prompt Engineering (Focusing on ChatGPT)
Introduction to Prompt Engineering (Focusing on ChatGPT)Chameera Dedduwage
 
ANCHORING SCRIPT FOR A CULTURAL EVENT.docx
ANCHORING SCRIPT FOR A CULTURAL EVENT.docxANCHORING SCRIPT FOR A CULTURAL EVENT.docx
ANCHORING SCRIPT FOR A CULTURAL EVENT.docxNikitaBankoti2
 
Microsoft Copilot AI for Everyone - created by AI
Microsoft Copilot AI for Everyone - created by AIMicrosoft Copilot AI for Everyone - created by AI
Microsoft Copilot AI for Everyone - created by AITatiana Gurgel
 
Russian Call Girls in Kolkata Vaishnavi 🤌 8250192130 🚀 Vip Call Girls Kolkata
Russian Call Girls in Kolkata Vaishnavi 🤌  8250192130 🚀 Vip Call Girls KolkataRussian Call Girls in Kolkata Vaishnavi 🤌  8250192130 🚀 Vip Call Girls Kolkata
Russian Call Girls in Kolkata Vaishnavi 🤌 8250192130 🚀 Vip Call Girls Kolkataanamikaraghav4
 
VVIP Call Girls Nalasopara : 9892124323, Call Girls in Nalasopara Services
VVIP Call Girls Nalasopara : 9892124323, Call Girls in Nalasopara ServicesVVIP Call Girls Nalasopara : 9892124323, Call Girls in Nalasopara Services
VVIP Call Girls Nalasopara : 9892124323, Call Girls in Nalasopara ServicesPooja Nehwal
 
OSCamp Kubernetes 2024 | A Tester's Guide to CI_CD as an Automated Quality Co...
OSCamp Kubernetes 2024 | A Tester's Guide to CI_CD as an Automated Quality Co...OSCamp Kubernetes 2024 | A Tester's Guide to CI_CD as an Automated Quality Co...
OSCamp Kubernetes 2024 | A Tester's Guide to CI_CD as an Automated Quality Co...NETWAYS
 
Mathematics of Finance Presentation.pptx
Mathematics of Finance Presentation.pptxMathematics of Finance Presentation.pptx
Mathematics of Finance Presentation.pptxMoumonDas2
 
SaaStr Workshop Wednesday w: Jason Lemkin, SaaStr
SaaStr Workshop Wednesday w: Jason Lemkin, SaaStrSaaStr Workshop Wednesday w: Jason Lemkin, SaaStr
SaaStr Workshop Wednesday w: Jason Lemkin, SaaStrsaastr
 
BDSM⚡Call Girls in Sector 93 Noida Escorts >༒8448380779 Escort Service
BDSM⚡Call Girls in Sector 93 Noida Escorts >༒8448380779 Escort ServiceBDSM⚡Call Girls in Sector 93 Noida Escorts >༒8448380779 Escort Service
BDSM⚡Call Girls in Sector 93 Noida Escorts >༒8448380779 Escort ServiceDelhi Call girls
 
Governance and Nation-Building in Nigeria: Some Reflections on Options for Po...
Governance and Nation-Building in Nigeria: Some Reflections on Options for Po...Governance and Nation-Building in Nigeria: Some Reflections on Options for Po...
Governance and Nation-Building in Nigeria: Some Reflections on Options for Po...Kayode Fayemi
 

Recently uploaded (20)

Re-membering the Bard: Revisiting The Compleat Wrks of Wllm Shkspr (Abridged)...
Re-membering the Bard: Revisiting The Compleat Wrks of Wllm Shkspr (Abridged)...Re-membering the Bard: Revisiting The Compleat Wrks of Wllm Shkspr (Abridged)...
Re-membering the Bard: Revisiting The Compleat Wrks of Wllm Shkspr (Abridged)...
 
Andrés Ramírez Gossler, Facundo Schinnea - eCommerce Day Chile 2024
Andrés Ramírez Gossler, Facundo Schinnea - eCommerce Day Chile 2024Andrés Ramírez Gossler, Facundo Schinnea - eCommerce Day Chile 2024
Andrés Ramírez Gossler, Facundo Schinnea - eCommerce Day Chile 2024
 
Thirunelveli call girls Tamil escorts 7877702510
Thirunelveli call girls Tamil escorts 7877702510Thirunelveli call girls Tamil escorts 7877702510
Thirunelveli call girls Tamil escorts 7877702510
 
CTAC 2024 Valencia - Henrik Hanke - Reduce to the max - slideshare.pdf
CTAC 2024 Valencia - Henrik Hanke - Reduce to the max - slideshare.pdfCTAC 2024 Valencia - Henrik Hanke - Reduce to the max - slideshare.pdf
CTAC 2024 Valencia - Henrik Hanke - Reduce to the max - slideshare.pdf
 
Presentation on Engagement in Book Clubs
Presentation on Engagement in Book ClubsPresentation on Engagement in Book Clubs
Presentation on Engagement in Book Clubs
 
George Lever - eCommerce Day Chile 2024
George Lever -  eCommerce Day Chile 2024George Lever -  eCommerce Day Chile 2024
George Lever - eCommerce Day Chile 2024
 
Exploring protein-protein interactions by Weak Affinity Chromatography (WAC) ...
Exploring protein-protein interactions by Weak Affinity Chromatography (WAC) ...Exploring protein-protein interactions by Weak Affinity Chromatography (WAC) ...
Exploring protein-protein interactions by Weak Affinity Chromatography (WAC) ...
 
Call Girls in Sarojini Nagar Market Delhi 💯 Call Us 🔝8264348440🔝
Call Girls in Sarojini Nagar Market Delhi 💯 Call Us 🔝8264348440🔝Call Girls in Sarojini Nagar Market Delhi 💯 Call Us 🔝8264348440🔝
Call Girls in Sarojini Nagar Market Delhi 💯 Call Us 🔝8264348440🔝
 
Navi Mumbai Call Girls Service Pooja 9892124323 Real Russian Girls Looking Mo...
Navi Mumbai Call Girls Service Pooja 9892124323 Real Russian Girls Looking Mo...Navi Mumbai Call Girls Service Pooja 9892124323 Real Russian Girls Looking Mo...
Navi Mumbai Call Girls Service Pooja 9892124323 Real Russian Girls Looking Mo...
 
No Advance 8868886958 Chandigarh Call Girls , Indian Call Girls For Full Nigh...
No Advance 8868886958 Chandigarh Call Girls , Indian Call Girls For Full Nigh...No Advance 8868886958 Chandigarh Call Girls , Indian Call Girls For Full Nigh...
No Advance 8868886958 Chandigarh Call Girls , Indian Call Girls For Full Nigh...
 
Introduction to Prompt Engineering (Focusing on ChatGPT)
Introduction to Prompt Engineering (Focusing on ChatGPT)Introduction to Prompt Engineering (Focusing on ChatGPT)
Introduction to Prompt Engineering (Focusing on ChatGPT)
 
ANCHORING SCRIPT FOR A CULTURAL EVENT.docx
ANCHORING SCRIPT FOR A CULTURAL EVENT.docxANCHORING SCRIPT FOR A CULTURAL EVENT.docx
ANCHORING SCRIPT FOR A CULTURAL EVENT.docx
 
Microsoft Copilot AI for Everyone - created by AI
Microsoft Copilot AI for Everyone - created by AIMicrosoft Copilot AI for Everyone - created by AI
Microsoft Copilot AI for Everyone - created by AI
 
Russian Call Girls in Kolkata Vaishnavi 🤌 8250192130 🚀 Vip Call Girls Kolkata
Russian Call Girls in Kolkata Vaishnavi 🤌  8250192130 🚀 Vip Call Girls KolkataRussian Call Girls in Kolkata Vaishnavi 🤌  8250192130 🚀 Vip Call Girls Kolkata
Russian Call Girls in Kolkata Vaishnavi 🤌 8250192130 🚀 Vip Call Girls Kolkata
 
VVIP Call Girls Nalasopara : 9892124323, Call Girls in Nalasopara Services
VVIP Call Girls Nalasopara : 9892124323, Call Girls in Nalasopara ServicesVVIP Call Girls Nalasopara : 9892124323, Call Girls in Nalasopara Services
VVIP Call Girls Nalasopara : 9892124323, Call Girls in Nalasopara Services
 
OSCamp Kubernetes 2024 | A Tester's Guide to CI_CD as an Automated Quality Co...
OSCamp Kubernetes 2024 | A Tester's Guide to CI_CD as an Automated Quality Co...OSCamp Kubernetes 2024 | A Tester's Guide to CI_CD as an Automated Quality Co...
OSCamp Kubernetes 2024 | A Tester's Guide to CI_CD as an Automated Quality Co...
 
Mathematics of Finance Presentation.pptx
Mathematics of Finance Presentation.pptxMathematics of Finance Presentation.pptx
Mathematics of Finance Presentation.pptx
 
SaaStr Workshop Wednesday w: Jason Lemkin, SaaStr
SaaStr Workshop Wednesday w: Jason Lemkin, SaaStrSaaStr Workshop Wednesday w: Jason Lemkin, SaaStr
SaaStr Workshop Wednesday w: Jason Lemkin, SaaStr
 
BDSM⚡Call Girls in Sector 93 Noida Escorts >༒8448380779 Escort Service
BDSM⚡Call Girls in Sector 93 Noida Escorts >༒8448380779 Escort ServiceBDSM⚡Call Girls in Sector 93 Noida Escorts >༒8448380779 Escort Service
BDSM⚡Call Girls in Sector 93 Noida Escorts >༒8448380779 Escort Service
 
Governance and Nation-Building in Nigeria: Some Reflections on Options for Po...
Governance and Nation-Building in Nigeria: Some Reflections on Options for Po...Governance and Nation-Building in Nigeria: Some Reflections on Options for Po...
Governance and Nation-Building in Nigeria: Some Reflections on Options for Po...
 

Docweb Milestone 2 Report

  • 1. Milestone Report 2 Patient Tracking Application IT 4983 KSU CSE MARCH 17, 2017 Stephen Cain, Chris Cheveresan, Jun-Hao Kuah, Victoria McDonald, Aline Moche Chatue
  • 2. Project Summary Alternative final deliverables have been set and agreed upon. Unanticipated crash of server. Impacted about 18% of timeline. Some work had to be re-coded. Server restored March 13th but with slightly older versions of software. Client established three critical use cases to complete given the time left in the project
  • 3. Project Challenges The server we were working on had a hardware malfunction and crashed. The group participated in the restoring of the SQL server database on the server once it was reprovisioned. Due to the two week delay, the group developed an alternate mode of work
  • 4. Milestone Assessment - Summary Add/Delete Patient-Diagnosis - Incomplete Add/Change Compliance - Incomplete Print Turnaround Document – 1 - Partially Complete Report Patients Not In Compliance - Incomplete These were the deliverables set in the original project plan. In the revised project plan: 200 hours worth of work remain Remaining tasks require 34 more hours than the original plan The group’s level of confidence in completing the project is high
  • 5. Milestone Assessment - Print Turnaround Document
  • 6. Milestone Assessment - Print Turnaround Document
  • 7. Lessons Learned Secure and transfer backups of database and files before starting work. Documenting and tracking information as pieces were edited and take constant “screenshots” of our work. Learned how to install SQL Server 2008 R2. Learned the harsh truth about server crashes.
  • 9. Process Challenges Due to the limited time left, work ethic among all of us will need to improve to tackle the remainder of the project. Web application interface is the largest of the remaining tasks and will need to be our primary focus. Need tight scheduling to work around the lack of multiple concurrent logons.
  • 11. Plan for Milestone 3 15 tasks remain ◦ 7 coding tasks ◦ 2 testing tasks ◦ 3 documentation tasks ◦ 3 presentation preparation tasks Critical to avoid any further delays
  • 12. Plan for Milestone 3 (Cont.) Revised Final Deliverables ◦ Add / Change Patient ◦ Record Compliance ◦ Print Turnaround Document – 1