SlideShare a Scribd company logo
San Bernard River
Project Update
Presentation to
Friends of the River
September 19, 2015
Scope of work
Develop a RESTORE Act grant application to fund an ecosystem
restoration project on the San Bernard River
• Dredge the historical channel to restore river flow to the Gulf
• Evaluate potential structure solutions to avoid future channel
siltation/shoaling
• Develop a plan to use dredge material beneficially (beach and marsh
restoration)
• Obtain the necessary permits (Corps, GLO,….)
• Work with stakeholders to develop consensus on an actionable plan and
secure a RESTORE grant.
History
Bathymetry Change River Flow Data
Modeling Summary
• The mouth of the San Bernard River is influenced by the Brazos Delta which
continues to evolve.
• The littoral drift and associated tidal wave action will continue to move
material into the mouth
• Current river flow does not sustain a velocity to move sediment away from
the river mouth
• A one time structural project at the mouth of the river will not be feasible
without periodic maintenance
• Structural features will have impacts on sediment flow along the littoral
drift and could cause additional erosion to shoreline south of the jetty.
Management Alternatives
Team looked at six different management options:
• Option A - No Action
• Option B - Dredge re-opening, no stabilization;
• Option C - Dredge re-opening, stabilization with single jetty on east side;
• Option D - Dredge re-opening, stabilization with dual jetties on both sides;
• Option E - Dredge re-opening, stabilization with eastern weir jetty and
western typical jetty; and,
• Option F - Establish a channel to connect to Cedar Lakes to increase tidal
prism.
Channel Configurations
7 channel configurations were investigated:
• Rectangular channel with bottom elevation of MLT-10 ft, bottom width of 100 ft, and
extending 0 ft into Gulf
• Trapezoidal channel with bottom elevation of MLT -8.5 ft, bottom width of 100 ft, and
extending 1050 ft into the Gulf
• Trapezoidal channel with bottom elevation of MLT -10 ft, bottom width of 130 ft, and
extending 1300 ft into the Gulf
• Trapezoidal channel with bottom elevation of MLT -8.5 ft, bottom width of 150 ft, and
extending 1050 ft into the Gulf
• Trapezoidal channel with bottom elevation of MLT -8.5 ft, bottom width of 120 ft, and
extending 1050 ft into the Gulf
• Trapezoidal channel with bottom elevation of MLT -7 ft, bottom width of 160 ft, and
extending 900 ft into the Gulf
• Trapezoidal channel with bottom elevation of MLT -5 ft, bottom width of 240 ft, and
extending 600 ft into the Gulf
Alternative Configuration Results
Option and
Channel
config.
Configuration Est. Initial
dredge
volume
Est. maint.
Interval,chan
nel
(years)
Est. maint.
dredge volume,
channel
Est. time to
shoreline advance
past East jetty
(years)
Est. maint. dredge
volume, bypass
Note
A No action, natural
maintenance
None None None - None Mouth remains closed. No anticipated
benefit to circulation or velocity.
B4 Dredge re-opening,
no stabilization
123,000 cu. yd 2 <123,000 cu. yd
per 2 years1
- None Spit growth and uncertain navigability
toward end of maintenance cycle. 1Some
natural bypassing of westward-moving
littoral sediments.
C4 Dredge re-opening,
long (-8.5ft) jetty
stabilization, east
side only
123,000 cu.
yd
2 <29,000 cu. yd
per 2 years
2
or
122
352,000 cu. yd per 2
years, or 2,112,000 cu.
yd per 12 years2
Maintenance dredging of channel to
remove deposits of eastward moving
sediments. (Tidal flushing may lessen this
amount). East jetty will initially capture
westward sediments; 2If no mechanical
bypass dredging, time until jetty
impoundment: 10-15 years
C7 Dredge re-opening,
long (-5ft) jetty
stabilization, east
side only
94,000 cu. yd 2 14,000 cu. yd
per 2 years
2
or
43
<352,000 cu. yd per 2
years, or <704,000 cu. yd
per 4 years3
Maintenance dredging of channel to
remove deposits of eastward moving
sediments. (Tidal flushing may lessen this
amount). East jetty will initially capture
westward sediments; 3If no mechanical
bypass dredging, time until jetty
impoundment: 4-5 years. Short jetty
anticipated to allow some natural
bypassing of westward moving sediments,
reducing volume for mechanical bypass
dredging.
Alternatives
Option and
Channel
config.
Configuration Est. Initial
dredge volume
Est. maint.
Interval,chan
nel
(years)
Est. maint.
dredge volume,
channel
Est. time to
shoreline advance
past East jetty
(years)
Est. maint. dredge
volume, bypass
Note
D4 Dredge re-opening,
long jetties (-8.5ft)
123,000 cu. yd 12 limited 2
or
124
352,000 cu. yd per 2
years, or 2,112,000 cu. yd
per 12 years4
Extends navigable life between maintenance
events; greater effect on littoral sediment
movement; East jetty will initially capture
westward sediments;4If no mechanical
bypass dredging, time until jetty
impoundment: 10-15 years
D7 Dredge re-opening,
short (-5 ft) jetty to
promote bypassing
94,000 cu. yd 2 <14,000 cu. yd
per 2 years
2
or
45
<352,000 cu. yd per 2
years, or <704,000 cu. yd
per 4 years5
Short jetties allow some natural bypassing
of westward moving sediments, reducing
volume for mechanical bypass dredging.
Short jetties may also allow sediment
deposits from tidal inflows inside channel –
thus requiring channel maintenance. 5If no
mechanical bypass dredging, time until jetty
impoundment: 4-5 years.
DW4 Dredge re-opening,
long jetty with east
side weir to capture
westward sediment
123,000 cu. yd 2 limited 2 352,000 cu. yd per 2
years6
Extends navigable life between maintenance
events; lessens effect on littoral sediment
movement. 6Deposition of littoral sediments
in deposition zone on the inner side of the
weir jetty needs to be dredged every two
years to free up capacity.
CW4 Dredge re-opening,
long jetty east side
only with weir to
capture westward
sediment, no west
jetty
123,000 cu. yd 2 29,000 cu. yd per
2 years
2 352,000 cu. yd per 2
years6
Extends navigable life between maintenance
events; lessens effect on littoral sediment
movement. 6Deposition of littoral sediments
in deposition zone on the inner side of the
weir jetty needs to be dredged every two
years to free up capacity.
Modeling Recommendations
Four structural alternatives are selected to be further evaluated by the larger
project team:
• D4 – Double (east side and west side) jetties extending to -8.5 MLT
• D7 – Double (east side and west side) jetties extending to -5 MLT
• C4 – Single east side jetty extending to -8.5 MLT
• C7 – Single east side jetty extending to -5 feet MLT
Recommendations
Potential Dredge Channel Configurations
Recommended Jetty Alignments
We focused our efforts on D4 which has the highest probability of resolving the
siltation/shoaling issue.
Complete Land and Bathometric Surveys
Courses of Action
Constructions costs: Three Structural Jetty and the dredge only option:
• COA #1- Rock Jetty
• Classic TX Coastal jetty system with a rock subbase and granite stone cover
• Cost- $86.2M
• COA#2- Hybrid Material Jetty
• Jetty with a rock subbase and articulated concrete matt cover
• Cost- $60.9M
• COA #3- Sheet pile Jetty
• Sheet Pile wall system consisting of driven sheets
• Cost- $27.8M
• COA #4- Dredge Only
• Cost- $6.0M
Dredging
• COA #1
• Construction- 600,000 cu yds
• Operations and Maintenance - 352,000 cu. yd per 2 years, or 2,112,000 cu. yd per 12 years
• Remove sediment behind the Jetty to slow eventual bypass and end of jetty shoaling
• COA #2
• Construction- 480,000 cu yds
• Operations and Maintenance - 352,000 cu. yd per 2 years, or 2,112,000 cu. yd per 12 years
• Remove sediment behind the Jetty to slow eventual bypass
• COA #3
• Construction- 450,000 cu yds
• Operations and Maintenance -352,000 cu. yd per 2 years, or 2,112,000 cu. yd per 12 years
• Remove sediment behind the Jetty to slow eventual bypass
• COA #4 (dredging only)-
• Open the channel- 400,000 cy yds
• Operations and Maintenance (2-3 yrs)- Dredge 125,000 cu yds ($2.5M)
Conclusions
• A structural solution is very expensive
• Revenue would need to be budgeted for the short and long term operations and
maintenance requirements
• The Dannenbaum-Berg/Oliver team is working with USACE on a permit for
dredging
• The County and Dannenbaum continue to socialize the project with TCEQ and the
GLO for RESTORE funding
• A grant application will be completed as soon as TCEQ finalizes the process
Section 7001 Study
• Commissioner Payne and Linder have meet with Congressman Weber and USACE
to discuss the Corps taking over the future maintenance dredging
• USACE has no existing authority….the project in 2009 was a one time exception
related to navigational safety
• Brazoria County has submitted a request for a USACE funded study under the
authority outlined in WRRDA 2014, Section 7001 to review the resiliency of the
GIWW and seek potential sources of material to stabilize the waterway banks.
Questions

More Related Content

What's hot

Spe 174119-ms
Spe 174119-msSpe 174119-ms
Spe 174119-ms
Juan Carlos Bonapace
 
Modelling extreme conditions for wave overtopping at Weymouth - Oliver Way (H...
Modelling extreme conditions for wave overtopping at Weymouth - Oliver Way (H...Modelling extreme conditions for wave overtopping at Weymouth - Oliver Way (H...
Modelling extreme conditions for wave overtopping at Weymouth - Oliver Way (H...
Stephen Flood
 
Coal Combustible Presentation 7 30_2015
Coal Combustible Presentation 7 30_2015Coal Combustible Presentation 7 30_2015
Coal Combustible Presentation 7 30_2015
Terry Aylward
 
Mining Operations Optimize Dewatering Processes
Mining Operations Optimize Dewatering ProcessesMining Operations Optimize Dewatering Processes
Mining Operations Optimize Dewatering Processes
Instrument Specialties, Inc.
 
Spe 172724-ms
Spe 172724-msSpe 172724-ms
Spe 172724-ms
Juan Carlos Bonapace
 
Final fall senior design presentation
Final fall senior design presentationFinal fall senior design presentation
Final fall senior design presentation
Julianne Crawford
 
Sharing Experiences of Flood Modelling Using MIKE 21
Sharing Experiences of Flood Modelling Using MIKE 21Sharing Experiences of Flood Modelling Using MIKE 21
Sharing Experiences of Flood Modelling Using MIKE 21
Stephen Flood
 
F041223744
F041223744F041223744
F041223744
IOSR-JEN
 
Desired Future Condition (DFC) Presentation
Desired Future Condition (DFC) PresentationDesired Future Condition (DFC) Presentation
Desired Future Condition (DFC) Presentation
htgcd
 
Spe 180818-ms ttec 2016
Spe 180818-ms ttec 2016Spe 180818-ms ttec 2016
Spe 180818-ms ttec 2016
Juan Carlos Bonapace
 
Borehole Seismic Solutions for Integrated Reservoir Characterization and Moni...
Borehole Seismic Solutions for Integrated Reservoir Characterization and Moni...Borehole Seismic Solutions for Integrated Reservoir Characterization and Moni...
Borehole Seismic Solutions for Integrated Reservoir Characterization and Moni...
Society of Petroleum Engineers
 
Improving Reservoir Simulation Modeling with Seismic Attributes
Improving Reservoir Simulation Modeling with Seismic Attributes Improving Reservoir Simulation Modeling with Seismic Attributes
Improving Reservoir Simulation Modeling with Seismic Attributes
Society of Petroleum Engineers
 
bbwstormwaterbasinstechnicalanalysis
bbwstormwaterbasinstechnicalanalysisbbwstormwaterbasinstechnicalanalysis
bbwstormwaterbasinstechnicalanalysisRegina Majercak, PE
 
Rachel Hamblin - Case Studies
Rachel Hamblin - Case StudiesRachel Hamblin - Case Studies
Rachel Hamblin - Case Studies
PAS_Team
 
Reservoir planing
Reservoir planing Reservoir planing
Reservoir planing
vivek gami
 
Resource Recovery Panel
Resource Recovery PanelResource Recovery Panel
Resource Recovery Panel
U.S. Water Alliance
 
CASFM 2009 Presentation On Stream Stability
CASFM 2009 Presentation On Stream StabilityCASFM 2009 Presentation On Stream Stability
CASFM 2009 Presentation On Stream Stabilityfatire95
 
TERS Presentation
TERS PresentationTERS Presentation
TERS Presentation
htgcd
 

What's hot (20)

Spe 174119-ms
Spe 174119-msSpe 174119-ms
Spe 174119-ms
 
Modelling extreme conditions for wave overtopping at Weymouth - Oliver Way (H...
Modelling extreme conditions for wave overtopping at Weymouth - Oliver Way (H...Modelling extreme conditions for wave overtopping at Weymouth - Oliver Way (H...
Modelling extreme conditions for wave overtopping at Weymouth - Oliver Way (H...
 
Coal Combustible Presentation 7 30_2015
Coal Combustible Presentation 7 30_2015Coal Combustible Presentation 7 30_2015
Coal Combustible Presentation 7 30_2015
 
SPE-15101-PA
SPE-15101-PASPE-15101-PA
SPE-15101-PA
 
Mining Operations Optimize Dewatering Processes
Mining Operations Optimize Dewatering ProcessesMining Operations Optimize Dewatering Processes
Mining Operations Optimize Dewatering Processes
 
Spe 172724-ms
Spe 172724-msSpe 172724-ms
Spe 172724-ms
 
Final fall senior design presentation
Final fall senior design presentationFinal fall senior design presentation
Final fall senior design presentation
 
Sharing Experiences of Flood Modelling Using MIKE 21
Sharing Experiences of Flood Modelling Using MIKE 21Sharing Experiences of Flood Modelling Using MIKE 21
Sharing Experiences of Flood Modelling Using MIKE 21
 
F041223744
F041223744F041223744
F041223744
 
Desired Future Condition (DFC) Presentation
Desired Future Condition (DFC) PresentationDesired Future Condition (DFC) Presentation
Desired Future Condition (DFC) Presentation
 
Spe 180818-ms ttec 2016
Spe 180818-ms ttec 2016Spe 180818-ms ttec 2016
Spe 180818-ms ttec 2016
 
Mc Quirk Sess1 101509
Mc Quirk Sess1 101509Mc Quirk Sess1 101509
Mc Quirk Sess1 101509
 
Borehole Seismic Solutions for Integrated Reservoir Characterization and Moni...
Borehole Seismic Solutions for Integrated Reservoir Characterization and Moni...Borehole Seismic Solutions for Integrated Reservoir Characterization and Moni...
Borehole Seismic Solutions for Integrated Reservoir Characterization and Moni...
 
Improving Reservoir Simulation Modeling with Seismic Attributes
Improving Reservoir Simulation Modeling with Seismic Attributes Improving Reservoir Simulation Modeling with Seismic Attributes
Improving Reservoir Simulation Modeling with Seismic Attributes
 
bbwstormwaterbasinstechnicalanalysis
bbwstormwaterbasinstechnicalanalysisbbwstormwaterbasinstechnicalanalysis
bbwstormwaterbasinstechnicalanalysis
 
Rachel Hamblin - Case Studies
Rachel Hamblin - Case StudiesRachel Hamblin - Case Studies
Rachel Hamblin - Case Studies
 
Reservoir planing
Reservoir planing Reservoir planing
Reservoir planing
 
Resource Recovery Panel
Resource Recovery PanelResource Recovery Panel
Resource Recovery Panel
 
CASFM 2009 Presentation On Stream Stability
CASFM 2009 Presentation On Stream StabilityCASFM 2009 Presentation On Stream Stability
CASFM 2009 Presentation On Stream Stability
 
TERS Presentation
TERS PresentationTERS Presentation
TERS Presentation
 

Similar to Dannenbaum Engineering - River Update 9-19-2015

Roger Falconer and Chris Binnie - Sustainable Severn Forum 2017
Roger Falconer and Chris Binnie - Sustainable Severn Forum 2017Roger Falconer and Chris Binnie - Sustainable Severn Forum 2017
Roger Falconer and Chris Binnie - Sustainable Severn Forum 2017
Sustainable Severn
 
Demzy's Presentation on HDD
Demzy's Presentation on HDDDemzy's Presentation on HDD
Demzy's Presentation on HDDDemzy George
 
Keeping Wastewater Flowing while managing major capital works for NI Water, 9...
Keeping Wastewater Flowing while managing major capital works for NI Water, 9...Keeping Wastewater Flowing while managing major capital works for NI Water, 9...
Keeping Wastewater Flowing while managing major capital works for NI Water, 9...
Association for Project Management
 
Re - Entry Drilling Project
Re - Entry Drilling ProjectRe - Entry Drilling Project
Re - Entry Drilling Project
Andika Mahardika
 
2013 afs lessons learned
2013 afs lessons learned2013 afs lessons learned
2013 afs lessons learnedRiverSHARED
 
Lecture 0 design of spilways an overview
Lecture 0 design of spilways an overviewLecture 0 design of spilways an overview
Lecture 0 design of spilways an overview
Addis Ababa Science and Technology University
 
Advances in Hydraulic Structures, Rubber Dam-A way forward
Advances in Hydraulic Structures, Rubber Dam-A way forwardAdvances in Hydraulic Structures, Rubber Dam-A way forward
Advances in Hydraulic Structures, Rubber Dam-A way forward
IEI GSC
 
Mitigation Symposium - Richard Lindseth
Mitigation Symposium - Richard LindsethMitigation Symposium - Richard Lindseth
Mitigation Symposium - Richard LindsethYourAlberta
 
Waterfront Sanitary Servicing Master Plan Update (Oct. 30 PIE).
Waterfront Sanitary Servicing Master Plan Update (Oct. 30 PIE). Waterfront Sanitary Servicing Master Plan Update (Oct. 30 PIE).
Waterfront Sanitary Servicing Master Plan Update (Oct. 30 PIE).
Toronto Public Consultation Unit
 
The Severn Estuary - A sustainable low carbon energy resource - Peter Kydd
The Severn Estuary - A sustainable low carbon energy resource - Peter KyddThe Severn Estuary - A sustainable low carbon energy resource - Peter Kydd
The Severn Estuary - A sustainable low carbon energy resource - Peter Kydd
Sustainable Severn
 
NI_Water_Dunmurry_2012
NI_Water_Dunmurry_2012NI_Water_Dunmurry_2012
NI_Water_Dunmurry_2012Mike Vernon
 
canutepresentation.ppt
canutepresentation.pptcanutepresentation.ppt
canutepresentation.ppt
MahadArif2
 
canutepresentation.ppt
canutepresentation.pptcanutepresentation.ppt
canutepresentation.ppt
MadavanR
 
Stream rehabilitation seminar june 11 2014
Stream rehabilitation seminar june 11 2014Stream rehabilitation seminar june 11 2014
Stream rehabilitation seminar june 11 2014
Lake Superior Binational Forum
 
Turga PSP_Lower Dam.pptx
Turga PSP_Lower Dam.pptxTurga PSP_Lower Dam.pptx
Turga PSP_Lower Dam.pptx
ssuserde6364
 
Treatment of water
Treatment of waterTreatment of water
Treatment of water
dhavalsshah
 
Submarine outfalls & intakes ppt
Submarine outfalls & intakes pptSubmarine outfalls & intakes ppt
Submarine outfalls & intakes ppt
Abhay Ocean India ltd.
 

Similar to Dannenbaum Engineering - River Update 9-19-2015 (20)

Roger Falconer and Chris Binnie - Sustainable Severn Forum 2017
Roger Falconer and Chris Binnie - Sustainable Severn Forum 2017Roger Falconer and Chris Binnie - Sustainable Severn Forum 2017
Roger Falconer and Chris Binnie - Sustainable Severn Forum 2017
 
Demzy's Presentation on HDD
Demzy's Presentation on HDDDemzy's Presentation on HDD
Demzy's Presentation on HDD
 
Keeping Wastewater Flowing while managing major capital works for NI Water, 9...
Keeping Wastewater Flowing while managing major capital works for NI Water, 9...Keeping Wastewater Flowing while managing major capital works for NI Water, 9...
Keeping Wastewater Flowing while managing major capital works for NI Water, 9...
 
Re - Entry Drilling Project
Re - Entry Drilling ProjectRe - Entry Drilling Project
Re - Entry Drilling Project
 
Paul Helliker - BDCP
Paul Helliker - BDCPPaul Helliker - BDCP
Paul Helliker - BDCP
 
Orlando 2015
Orlando 2015Orlando 2015
Orlando 2015
 
2013 afs lessons learned
2013 afs lessons learned2013 afs lessons learned
2013 afs lessons learned
 
Lecture 0 design of spilways an overview
Lecture 0 design of spilways an overviewLecture 0 design of spilways an overview
Lecture 0 design of spilways an overview
 
Advances in Hydraulic Structures, Rubber Dam-A way forward
Advances in Hydraulic Structures, Rubber Dam-A way forwardAdvances in Hydraulic Structures, Rubber Dam-A way forward
Advances in Hydraulic Structures, Rubber Dam-A way forward
 
Mitigation Symposium - Richard Lindseth
Mitigation Symposium - Richard LindsethMitigation Symposium - Richard Lindseth
Mitigation Symposium - Richard Lindseth
 
Wp mp-update-camp pendleton.-april_25_2013
Wp   mp-update-camp pendleton.-april_25_2013Wp   mp-update-camp pendleton.-april_25_2013
Wp mp-update-camp pendleton.-april_25_2013
 
Waterfront Sanitary Servicing Master Plan Update (Oct. 30 PIE).
Waterfront Sanitary Servicing Master Plan Update (Oct. 30 PIE). Waterfront Sanitary Servicing Master Plan Update (Oct. 30 PIE).
Waterfront Sanitary Servicing Master Plan Update (Oct. 30 PIE).
 
The Severn Estuary - A sustainable low carbon energy resource - Peter Kydd
The Severn Estuary - A sustainable low carbon energy resource - Peter KyddThe Severn Estuary - A sustainable low carbon energy resource - Peter Kydd
The Severn Estuary - A sustainable low carbon energy resource - Peter Kydd
 
NI_Water_Dunmurry_2012
NI_Water_Dunmurry_2012NI_Water_Dunmurry_2012
NI_Water_Dunmurry_2012
 
canutepresentation.ppt
canutepresentation.pptcanutepresentation.ppt
canutepresentation.ppt
 
canutepresentation.ppt
canutepresentation.pptcanutepresentation.ppt
canutepresentation.ppt
 
Stream rehabilitation seminar june 11 2014
Stream rehabilitation seminar june 11 2014Stream rehabilitation seminar june 11 2014
Stream rehabilitation seminar june 11 2014
 
Turga PSP_Lower Dam.pptx
Turga PSP_Lower Dam.pptxTurga PSP_Lower Dam.pptx
Turga PSP_Lower Dam.pptx
 
Treatment of water
Treatment of waterTreatment of water
Treatment of water
 
Submarine outfalls & intakes ppt
Submarine outfalls & intakes pptSubmarine outfalls & intakes ppt
Submarine outfalls & intakes ppt
 

Recently uploaded

2024: The FAR - Federal Acquisition Regulations, Part 37
2024: The FAR - Federal Acquisition Regulations, Part 372024: The FAR - Federal Acquisition Regulations, Part 37
2024: The FAR - Federal Acquisition Regulations, Part 37
JSchaus & Associates
 
Understanding the Challenges of Street Children
Understanding the Challenges of Street ChildrenUnderstanding the Challenges of Street Children
Understanding the Challenges of Street Children
SERUDS INDIA
 
NHAI_Under_Implementation_01-05-2024.pdf
NHAI_Under_Implementation_01-05-2024.pdfNHAI_Under_Implementation_01-05-2024.pdf
NHAI_Under_Implementation_01-05-2024.pdf
AjayVejendla3
 
Opinions on EVs: Metro Atlanta Speaks 2023
Opinions on EVs: Metro Atlanta Speaks 2023Opinions on EVs: Metro Atlanta Speaks 2023
Opinions on EVs: Metro Atlanta Speaks 2023
ARCResearch
 
2024: The FAR - Federal Acquisition Regulations, Part 38
2024: The FAR - Federal Acquisition Regulations, Part 382024: The FAR - Federal Acquisition Regulations, Part 38
2024: The FAR - Federal Acquisition Regulations, Part 38
JSchaus & Associates
 
快速制作(ocad毕业证书)加拿大安大略艺术设计学院毕业证本科学历雅思成绩单原版一模一样
快速制作(ocad毕业证书)加拿大安大略艺术设计学院毕业证本科学历雅思成绩单原版一模一样快速制作(ocad毕业证书)加拿大安大略艺术设计学院毕业证本科学历雅思成绩单原版一模一样
快速制作(ocad毕业证书)加拿大安大略艺术设计学院毕业证本科学历雅思成绩单原版一模一样
850fcj96
 
Russian anarchist and anti-war movement in the third year of full-scale war
Russian anarchist and anti-war movement in the third year of full-scale warRussian anarchist and anti-war movement in the third year of full-scale war
Russian anarchist and anti-war movement in the third year of full-scale war
Antti Rautiainen
 
kupon sample qurban masjid indonesia terbaru.pptx
kupon sample qurban masjid indonesia terbaru.pptxkupon sample qurban masjid indonesia terbaru.pptx
kupon sample qurban masjid indonesia terbaru.pptx
viderakai
 
Effects of Extreme Temperatures From Climate Change on the Medicare Populatio...
Effects of Extreme Temperatures From Climate Change on the Medicare Populatio...Effects of Extreme Temperatures From Climate Change on the Medicare Populatio...
Effects of Extreme Temperatures From Climate Change on the Medicare Populatio...
Congressional Budget Office
 
2024: The FAR - Federal Acquisition Regulations, Part 36
2024: The FAR - Federal Acquisition Regulations, Part 362024: The FAR - Federal Acquisition Regulations, Part 36
2024: The FAR - Federal Acquisition Regulations, Part 36
JSchaus & Associates
 
如何办理(uoit毕业证书)加拿大安大略理工大学毕业证文凭证书录取通知原版一模一样
如何办理(uoit毕业证书)加拿大安大略理工大学毕业证文凭证书录取通知原版一模一样如何办理(uoit毕业证书)加拿大安大略理工大学毕业证文凭证书录取通知原版一模一样
如何办理(uoit毕业证书)加拿大安大略理工大学毕业证文凭证书录取通知原版一模一样
850fcj96
 
PNRR MADRID GREENTECH FOR BROWN NETWORKS NETWORKS MUR_MUSA_TEBALDI.pdf
PNRR MADRID GREENTECH FOR BROWN NETWORKS NETWORKS MUR_MUSA_TEBALDI.pdfPNRR MADRID GREENTECH FOR BROWN NETWORKS NETWORKS MUR_MUSA_TEBALDI.pdf
PNRR MADRID GREENTECH FOR BROWN NETWORKS NETWORKS MUR_MUSA_TEBALDI.pdf
ClaudioTebaldi2
 
ZGB - The Role of Generative AI in Government transformation.pdf
ZGB - The Role of Generative AI in Government transformation.pdfZGB - The Role of Generative AI in Government transformation.pdf
ZGB - The Role of Generative AI in Government transformation.pdf
Saeed Al Dhaheri
 
MHM Roundtable Slide Deck WHA Side-event May 28 2024.pptx
MHM Roundtable Slide Deck WHA Side-event May 28 2024.pptxMHM Roundtable Slide Deck WHA Side-event May 28 2024.pptx
MHM Roundtable Slide Deck WHA Side-event May 28 2024.pptx
ILC- UK
 
Get Government Grants and Assistance Program
Get Government Grants and Assistance ProgramGet Government Grants and Assistance Program
Get Government Grants and Assistance Program
Get Government Grants
 
The Role of a Process Server in real estate
The Role of a Process Server in real estateThe Role of a Process Server in real estate
The Role of a Process Server in real estate
oklahomajudicialproc1
 
PD-1602-as-amended-by-RA-9287-Anti-Illegal-Gambling-Law.pptx
PD-1602-as-amended-by-RA-9287-Anti-Illegal-Gambling-Law.pptxPD-1602-as-amended-by-RA-9287-Anti-Illegal-Gambling-Law.pptx
PD-1602-as-amended-by-RA-9287-Anti-Illegal-Gambling-Law.pptx
RIDPRO11
 
Donate to charity during this holiday season
Donate to charity during this holiday seasonDonate to charity during this holiday season
Donate to charity during this holiday season
SERUDS INDIA
 
State crafting: Changes and challenges for managing the public finances
State crafting: Changes and challenges for managing the public financesState crafting: Changes and challenges for managing the public finances
State crafting: Changes and challenges for managing the public finances
ResolutionFoundation
 
Uniform Guidance 3.0 - The New 2 CFR 200
Uniform Guidance 3.0 - The New 2 CFR 200Uniform Guidance 3.0 - The New 2 CFR 200
Uniform Guidance 3.0 - The New 2 CFR 200
GrantManagementInsti
 

Recently uploaded (20)

2024: The FAR - Federal Acquisition Regulations, Part 37
2024: The FAR - Federal Acquisition Regulations, Part 372024: The FAR - Federal Acquisition Regulations, Part 37
2024: The FAR - Federal Acquisition Regulations, Part 37
 
Understanding the Challenges of Street Children
Understanding the Challenges of Street ChildrenUnderstanding the Challenges of Street Children
Understanding the Challenges of Street Children
 
NHAI_Under_Implementation_01-05-2024.pdf
NHAI_Under_Implementation_01-05-2024.pdfNHAI_Under_Implementation_01-05-2024.pdf
NHAI_Under_Implementation_01-05-2024.pdf
 
Opinions on EVs: Metro Atlanta Speaks 2023
Opinions on EVs: Metro Atlanta Speaks 2023Opinions on EVs: Metro Atlanta Speaks 2023
Opinions on EVs: Metro Atlanta Speaks 2023
 
2024: The FAR - Federal Acquisition Regulations, Part 38
2024: The FAR - Federal Acquisition Regulations, Part 382024: The FAR - Federal Acquisition Regulations, Part 38
2024: The FAR - Federal Acquisition Regulations, Part 38
 
快速制作(ocad毕业证书)加拿大安大略艺术设计学院毕业证本科学历雅思成绩单原版一模一样
快速制作(ocad毕业证书)加拿大安大略艺术设计学院毕业证本科学历雅思成绩单原版一模一样快速制作(ocad毕业证书)加拿大安大略艺术设计学院毕业证本科学历雅思成绩单原版一模一样
快速制作(ocad毕业证书)加拿大安大略艺术设计学院毕业证本科学历雅思成绩单原版一模一样
 
Russian anarchist and anti-war movement in the third year of full-scale war
Russian anarchist and anti-war movement in the third year of full-scale warRussian anarchist and anti-war movement in the third year of full-scale war
Russian anarchist and anti-war movement in the third year of full-scale war
 
kupon sample qurban masjid indonesia terbaru.pptx
kupon sample qurban masjid indonesia terbaru.pptxkupon sample qurban masjid indonesia terbaru.pptx
kupon sample qurban masjid indonesia terbaru.pptx
 
Effects of Extreme Temperatures From Climate Change on the Medicare Populatio...
Effects of Extreme Temperatures From Climate Change on the Medicare Populatio...Effects of Extreme Temperatures From Climate Change on the Medicare Populatio...
Effects of Extreme Temperatures From Climate Change on the Medicare Populatio...
 
2024: The FAR - Federal Acquisition Regulations, Part 36
2024: The FAR - Federal Acquisition Regulations, Part 362024: The FAR - Federal Acquisition Regulations, Part 36
2024: The FAR - Federal Acquisition Regulations, Part 36
 
如何办理(uoit毕业证书)加拿大安大略理工大学毕业证文凭证书录取通知原版一模一样
如何办理(uoit毕业证书)加拿大安大略理工大学毕业证文凭证书录取通知原版一模一样如何办理(uoit毕业证书)加拿大安大略理工大学毕业证文凭证书录取通知原版一模一样
如何办理(uoit毕业证书)加拿大安大略理工大学毕业证文凭证书录取通知原版一模一样
 
PNRR MADRID GREENTECH FOR BROWN NETWORKS NETWORKS MUR_MUSA_TEBALDI.pdf
PNRR MADRID GREENTECH FOR BROWN NETWORKS NETWORKS MUR_MUSA_TEBALDI.pdfPNRR MADRID GREENTECH FOR BROWN NETWORKS NETWORKS MUR_MUSA_TEBALDI.pdf
PNRR MADRID GREENTECH FOR BROWN NETWORKS NETWORKS MUR_MUSA_TEBALDI.pdf
 
ZGB - The Role of Generative AI in Government transformation.pdf
ZGB - The Role of Generative AI in Government transformation.pdfZGB - The Role of Generative AI in Government transformation.pdf
ZGB - The Role of Generative AI in Government transformation.pdf
 
MHM Roundtable Slide Deck WHA Side-event May 28 2024.pptx
MHM Roundtable Slide Deck WHA Side-event May 28 2024.pptxMHM Roundtable Slide Deck WHA Side-event May 28 2024.pptx
MHM Roundtable Slide Deck WHA Side-event May 28 2024.pptx
 
Get Government Grants and Assistance Program
Get Government Grants and Assistance ProgramGet Government Grants and Assistance Program
Get Government Grants and Assistance Program
 
The Role of a Process Server in real estate
The Role of a Process Server in real estateThe Role of a Process Server in real estate
The Role of a Process Server in real estate
 
PD-1602-as-amended-by-RA-9287-Anti-Illegal-Gambling-Law.pptx
PD-1602-as-amended-by-RA-9287-Anti-Illegal-Gambling-Law.pptxPD-1602-as-amended-by-RA-9287-Anti-Illegal-Gambling-Law.pptx
PD-1602-as-amended-by-RA-9287-Anti-Illegal-Gambling-Law.pptx
 
Donate to charity during this holiday season
Donate to charity during this holiday seasonDonate to charity during this holiday season
Donate to charity during this holiday season
 
State crafting: Changes and challenges for managing the public finances
State crafting: Changes and challenges for managing the public financesState crafting: Changes and challenges for managing the public finances
State crafting: Changes and challenges for managing the public finances
 
Uniform Guidance 3.0 - The New 2 CFR 200
Uniform Guidance 3.0 - The New 2 CFR 200Uniform Guidance 3.0 - The New 2 CFR 200
Uniform Guidance 3.0 - The New 2 CFR 200
 

Dannenbaum Engineering - River Update 9-19-2015

  • 1. San Bernard River Project Update Presentation to Friends of the River September 19, 2015
  • 2. Scope of work Develop a RESTORE Act grant application to fund an ecosystem restoration project on the San Bernard River • Dredge the historical channel to restore river flow to the Gulf • Evaluate potential structure solutions to avoid future channel siltation/shoaling • Develop a plan to use dredge material beneficially (beach and marsh restoration) • Obtain the necessary permits (Corps, GLO,….) • Work with stakeholders to develop consensus on an actionable plan and secure a RESTORE grant.
  • 5. Modeling Summary • The mouth of the San Bernard River is influenced by the Brazos Delta which continues to evolve. • The littoral drift and associated tidal wave action will continue to move material into the mouth • Current river flow does not sustain a velocity to move sediment away from the river mouth • A one time structural project at the mouth of the river will not be feasible without periodic maintenance • Structural features will have impacts on sediment flow along the littoral drift and could cause additional erosion to shoreline south of the jetty.
  • 6. Management Alternatives Team looked at six different management options: • Option A - No Action • Option B - Dredge re-opening, no stabilization; • Option C - Dredge re-opening, stabilization with single jetty on east side; • Option D - Dredge re-opening, stabilization with dual jetties on both sides; • Option E - Dredge re-opening, stabilization with eastern weir jetty and western typical jetty; and, • Option F - Establish a channel to connect to Cedar Lakes to increase tidal prism.
  • 7. Channel Configurations 7 channel configurations were investigated: • Rectangular channel with bottom elevation of MLT-10 ft, bottom width of 100 ft, and extending 0 ft into Gulf • Trapezoidal channel with bottom elevation of MLT -8.5 ft, bottom width of 100 ft, and extending 1050 ft into the Gulf • Trapezoidal channel with bottom elevation of MLT -10 ft, bottom width of 130 ft, and extending 1300 ft into the Gulf • Trapezoidal channel with bottom elevation of MLT -8.5 ft, bottom width of 150 ft, and extending 1050 ft into the Gulf • Trapezoidal channel with bottom elevation of MLT -8.5 ft, bottom width of 120 ft, and extending 1050 ft into the Gulf • Trapezoidal channel with bottom elevation of MLT -7 ft, bottom width of 160 ft, and extending 900 ft into the Gulf • Trapezoidal channel with bottom elevation of MLT -5 ft, bottom width of 240 ft, and extending 600 ft into the Gulf
  • 8. Alternative Configuration Results Option and Channel config. Configuration Est. Initial dredge volume Est. maint. Interval,chan nel (years) Est. maint. dredge volume, channel Est. time to shoreline advance past East jetty (years) Est. maint. dredge volume, bypass Note A No action, natural maintenance None None None - None Mouth remains closed. No anticipated benefit to circulation or velocity. B4 Dredge re-opening, no stabilization 123,000 cu. yd 2 <123,000 cu. yd per 2 years1 - None Spit growth and uncertain navigability toward end of maintenance cycle. 1Some natural bypassing of westward-moving littoral sediments. C4 Dredge re-opening, long (-8.5ft) jetty stabilization, east side only 123,000 cu. yd 2 <29,000 cu. yd per 2 years 2 or 122 352,000 cu. yd per 2 years, or 2,112,000 cu. yd per 12 years2 Maintenance dredging of channel to remove deposits of eastward moving sediments. (Tidal flushing may lessen this amount). East jetty will initially capture westward sediments; 2If no mechanical bypass dredging, time until jetty impoundment: 10-15 years C7 Dredge re-opening, long (-5ft) jetty stabilization, east side only 94,000 cu. yd 2 14,000 cu. yd per 2 years 2 or 43 <352,000 cu. yd per 2 years, or <704,000 cu. yd per 4 years3 Maintenance dredging of channel to remove deposits of eastward moving sediments. (Tidal flushing may lessen this amount). East jetty will initially capture westward sediments; 3If no mechanical bypass dredging, time until jetty impoundment: 4-5 years. Short jetty anticipated to allow some natural bypassing of westward moving sediments, reducing volume for mechanical bypass dredging.
  • 9. Alternatives Option and Channel config. Configuration Est. Initial dredge volume Est. maint. Interval,chan nel (years) Est. maint. dredge volume, channel Est. time to shoreline advance past East jetty (years) Est. maint. dredge volume, bypass Note D4 Dredge re-opening, long jetties (-8.5ft) 123,000 cu. yd 12 limited 2 or 124 352,000 cu. yd per 2 years, or 2,112,000 cu. yd per 12 years4 Extends navigable life between maintenance events; greater effect on littoral sediment movement; East jetty will initially capture westward sediments;4If no mechanical bypass dredging, time until jetty impoundment: 10-15 years D7 Dredge re-opening, short (-5 ft) jetty to promote bypassing 94,000 cu. yd 2 <14,000 cu. yd per 2 years 2 or 45 <352,000 cu. yd per 2 years, or <704,000 cu. yd per 4 years5 Short jetties allow some natural bypassing of westward moving sediments, reducing volume for mechanical bypass dredging. Short jetties may also allow sediment deposits from tidal inflows inside channel – thus requiring channel maintenance. 5If no mechanical bypass dredging, time until jetty impoundment: 4-5 years. DW4 Dredge re-opening, long jetty with east side weir to capture westward sediment 123,000 cu. yd 2 limited 2 352,000 cu. yd per 2 years6 Extends navigable life between maintenance events; lessens effect on littoral sediment movement. 6Deposition of littoral sediments in deposition zone on the inner side of the weir jetty needs to be dredged every two years to free up capacity. CW4 Dredge re-opening, long jetty east side only with weir to capture westward sediment, no west jetty 123,000 cu. yd 2 29,000 cu. yd per 2 years 2 352,000 cu. yd per 2 years6 Extends navigable life between maintenance events; lessens effect on littoral sediment movement. 6Deposition of littoral sediments in deposition zone on the inner side of the weir jetty needs to be dredged every two years to free up capacity.
  • 10. Modeling Recommendations Four structural alternatives are selected to be further evaluated by the larger project team: • D4 – Double (east side and west side) jetties extending to -8.5 MLT • D7 – Double (east side and west side) jetties extending to -5 MLT • C4 – Single east side jetty extending to -8.5 MLT • C7 – Single east side jetty extending to -5 feet MLT
  • 12. Potential Dredge Channel Configurations
  • 13. Recommended Jetty Alignments We focused our efforts on D4 which has the highest probability of resolving the siltation/shoaling issue.
  • 14. Complete Land and Bathometric Surveys
  • 15. Courses of Action Constructions costs: Three Structural Jetty and the dredge only option: • COA #1- Rock Jetty • Classic TX Coastal jetty system with a rock subbase and granite stone cover • Cost- $86.2M • COA#2- Hybrid Material Jetty • Jetty with a rock subbase and articulated concrete matt cover • Cost- $60.9M • COA #3- Sheet pile Jetty • Sheet Pile wall system consisting of driven sheets • Cost- $27.8M • COA #4- Dredge Only • Cost- $6.0M
  • 16. Dredging • COA #1 • Construction- 600,000 cu yds • Operations and Maintenance - 352,000 cu. yd per 2 years, or 2,112,000 cu. yd per 12 years • Remove sediment behind the Jetty to slow eventual bypass and end of jetty shoaling • COA #2 • Construction- 480,000 cu yds • Operations and Maintenance - 352,000 cu. yd per 2 years, or 2,112,000 cu. yd per 12 years • Remove sediment behind the Jetty to slow eventual bypass • COA #3 • Construction- 450,000 cu yds • Operations and Maintenance -352,000 cu. yd per 2 years, or 2,112,000 cu. yd per 12 years • Remove sediment behind the Jetty to slow eventual bypass • COA #4 (dredging only)- • Open the channel- 400,000 cy yds • Operations and Maintenance (2-3 yrs)- Dredge 125,000 cu yds ($2.5M)
  • 17. Conclusions • A structural solution is very expensive • Revenue would need to be budgeted for the short and long term operations and maintenance requirements • The Dannenbaum-Berg/Oliver team is working with USACE on a permit for dredging • The County and Dannenbaum continue to socialize the project with TCEQ and the GLO for RESTORE funding • A grant application will be completed as soon as TCEQ finalizes the process
  • 18. Section 7001 Study • Commissioner Payne and Linder have meet with Congressman Weber and USACE to discuss the Corps taking over the future maintenance dredging • USACE has no existing authority….the project in 2009 was a one time exception related to navigational safety • Brazoria County has submitted a request for a USACE funded study under the authority outlined in WRRDA 2014, Section 7001 to review the resiliency of the GIWW and seek potential sources of material to stabilize the waterway banks.