Daily Mobile Crane Inspection Checklist
Section A: Inspection
Contractor Company
LM Cert No.

s/no

Date of Expiry

Items

OK

Not OK

N/A

Remarks

Truck
1.

Carrier Structure

2.

Tyre pressure

3.

Wheel Nuts

4.

Radiator water

5.

Engine Oil Level

6.

Diesel Level

7.

Diesel Tank

8.

Any Retrofitted Fuel Tanks

9.

Battery water level
Power Transmission System

10.

Power take-off (PTO)

11.

Propeller Shaft
Hydraulic System

12.

Hydraulic tank

13.

Hydraulic Pump

14.

Hydraulic hose

15.

Hydraulic Oil
Slewing System

16.

Slewing Table

17.

Slewing Gear and bearing
Boom Elevation System

18.

Elevating Cylinder
Boom Telescopic System

19.

Boom Structure

20.

Fly-jib

21

Single Top
Sheave and hook block

22.

Sheave and hook block
Wire Rope

23.

Boom Hoist wire

24.

Load hoist wire
Hoisting System

25.

Winch motor

26.

Clutch

27.

Brake
SWP– 04.38
Rev 0

Page 1 of 2
Daily Mobile Crane Inspection Checklist
s/no

Items

28.

Not OK

N/A

Remarks

Wire rope

29.

OK

Hook Block
Crane Control System

30.

Operation Control

31.

Selector Switch
Safety Device

32.

Angle indicator

33.

Pressure Gauge

34.

LRI

35.

Anti-two block

36.

Boom Stop
Outrigger System

37.

Outrigger

38.

Jack Cylinder

39.

Float

Additional Remarks:

* Item No.8: Provide crane specification
Section B: Endorsement by Appointed Personnel
Inspected by
(shall be done by Crane Operator)

Date / Time

Signature

Note: All the above checklist items must be completed. All deficiencies must be reported to the lifting
supervisors and must be rectified before using the crane.
Record of Corrective actions Taken (if any):
_______________________________________________________________________________________
_______________________________________________________________________________________

Approved by
(shall be done by Lifting Supervisor)

Date / Time

Signature

Note: Lifting Supervisor must complete the “Lifting Operation Safety Inspection Checklist” after verifying this
checklist.

SWP– 04.38
Rev 0

Page 2 of 2

Daily mobile crane inspection checklist

  • 1.
    Daily Mobile CraneInspection Checklist Section A: Inspection Contractor Company LM Cert No. s/no Date of Expiry Items OK Not OK N/A Remarks Truck 1. Carrier Structure 2. Tyre pressure 3. Wheel Nuts 4. Radiator water 5. Engine Oil Level 6. Diesel Level 7. Diesel Tank 8. Any Retrofitted Fuel Tanks 9. Battery water level Power Transmission System 10. Power take-off (PTO) 11. Propeller Shaft Hydraulic System 12. Hydraulic tank 13. Hydraulic Pump 14. Hydraulic hose 15. Hydraulic Oil Slewing System 16. Slewing Table 17. Slewing Gear and bearing Boom Elevation System 18. Elevating Cylinder Boom Telescopic System 19. Boom Structure 20. Fly-jib 21 Single Top Sheave and hook block 22. Sheave and hook block Wire Rope 23. Boom Hoist wire 24. Load hoist wire Hoisting System 25. Winch motor 26. Clutch 27. Brake SWP– 04.38 Rev 0 Page 1 of 2
  • 2.
    Daily Mobile CraneInspection Checklist s/no Items 28. Not OK N/A Remarks Wire rope 29. OK Hook Block Crane Control System 30. Operation Control 31. Selector Switch Safety Device 32. Angle indicator 33. Pressure Gauge 34. LRI 35. Anti-two block 36. Boom Stop Outrigger System 37. Outrigger 38. Jack Cylinder 39. Float Additional Remarks: * Item No.8: Provide crane specification Section B: Endorsement by Appointed Personnel Inspected by (shall be done by Crane Operator) Date / Time Signature Note: All the above checklist items must be completed. All deficiencies must be reported to the lifting supervisors and must be rectified before using the crane. Record of Corrective actions Taken (if any): _______________________________________________________________________________________ _______________________________________________________________________________________ Approved by (shall be done by Lifting Supervisor) Date / Time Signature Note: Lifting Supervisor must complete the “Lifting Operation Safety Inspection Checklist” after verifying this checklist. SWP– 04.38 Rev 0 Page 2 of 2