SlideShare a Scribd company logo
Executing the Credible Plan,
Using an Integrated Reporting
and Control System
Part 2
EVM World 2016
Glen B. Alleman
Agile Program Planning and Controls
Prime PM
glen.alleman@niwotridge.com
+1 303 241 9633
Thomas Coonce
Cost Analysis and Research Division
Institute for Defense Analyses
tcoonce@ida.org
+1 703 575 6634
Rick Price
Project Management & Planning
Operations Principal
Lockheed Martin Space Systems
Company
rick.a.price@lmco.com
+1 303 971 1826
2
Learning Objectives
• TLO #1 – the student will learn how to produce an integrated
report of the Technical progress consistent with the
Programmatic progress, detect variances, and suggest
corrective actions.
• TLO #2 – the student will understand how to objectively
measure progress and use the performance to manage the
program.
• Earned Value Management is part of a Technical and
Programmatic control system
– Integrated risk, performance, effectiveness, technical and
other measures provide leading indicators of program
performance.
3
In Part 1, we talked about …
• The five core processes needed to produce a credible
Performance Measurement Baseline (PMB).
• How to use objective measures of progress and how to inform
program performance with these measures.
In Part 2, you’ll see how to execute the program with this
information.
4
Part 1 ‒ Inputs and Outputs for Building the Credible
Performance Measurement Baseline
• Customer Capabilities
• Time phased budget
• Desired completion date
• Available technologies
• Time phased resources
• Reference Class Data
• Programmatic and technical risks with
probabilities and impacts
• Historic uncertainties
• Measures of Effectiveness
• Measures of Performance
• Work Breakdown Structure
• Integrated Master Plan
• Technical Performance Management
Plan
• Initial Integrated Master Schedule
• Time Phased Staffing Plan
• Schedule Reserve (Margin)
• Management Reserve
• Risk Register and Mitigation Plans
• Adjusted Integrated Master Schedule
• Risk Burn Down Plan
Inputs Outputs
5
Part 2 ‒ Executing the Credible Performance
Measurement Baseline
6
A Readable Version
The Four processes needed to execute the credible PMB
❶ Compare Technical and Programmatic Actuals to Plan
❷ Compare BCWP and Cost and Schedule Performance
Data with Management Reserve (MR) and Schedule
Margin (SM) balances
❸ Revise Integrated Master Schedule (IMS) and Risk
Register
❹ Run or Rerun Monte Carlo Simulations
7
❶ COMPARE PLANNED TO
ACTUAL PERFORMANCE
Compare technical and programmatic performance to the planned
performance. Identify variances needed to make decisions about
corrective actions to Keep the Program Green.
8
Compare Planned to Actual Performance
• Physical Percent Complete
– Planned
– Actual
• Do this at the Work Package level
– Quantifiable Backup Data
– Avoid averaging out the variances at the Control Account
level
Objectively assess accomplishments at the Work Performance Level
EIA-748-C, page 1
9
Wright Brothers’ Technical, Cost and
Schedule Progress
0.80
0.85
0.90
0.95
1.00
1.05
1.10
770
780
790
800
810
820
830
840
850
860
870
15-Feb-08 15-Mar-08 15-Apr-08 15-May-08 15-Jun-08 15-Jul-08
CPI/SPI
Pounds
WBs' 1908 Flyer Integrated Progress
(2/28/1908)
Upper Limit Planned Target Achieved SPI CPI
Compare side-by-side the Technical Performance (Weight) with
the Programmatic performance CPI and SPI
10
❷ COMPARE MR AND SM
BALANCES
Using the performance data and the variances, the computed
BCWP from measures of Physical Percent Complete.
Assess planned Management Reserve and Schedule Margin with
the current MR and SM and inform EAC and ETC from past
performance.
11
Compare BCWP with MR and SM
• With actual BCWP assess impact on Estimate at Completion
and Estimate To Complete.
• Assess planned Management Reserve against actual
Management Reserve
• Assess planned Schedule Margin against actual Schedule
Margin
• Assess planned risk burn down against actual Risk Burn Down
12
Wright Brothers’ MR Planned Use vs Actuals
$0
$500
$1,000
$1,500
$2,000
$2,500
$3,000
$3,500
$4,000
WB 1908 Flyer Planned vs Actual MR Use
(15 May 1908)
MR Planned Balance MR Actual Balance
13
Schedule Margin in Final WB’s Flyer IMS
14
Wright Brothers’ Schedule Margin Burn
Planned Use vs Actuals
In May, when the schedule margin went below plan, immediate
corrective action is needed to get back on Schedule Margin Plan
0
2
4
6
8
10
12
15-Feb-08 15-Mar-08 15-Apr-08 15-May-08 15-Jun-08 15-Jul-08 15-Aug-08 15-Sep-08
Days
WB 1908 Flyer Planned vs Actual Schedule Margin Use
(15 May 1908)
Schedule Margin Plan Balance Schedule Margin Actual Balance
This dip is
characterized as
negative slack
15
❸ REVISE IMS AND RISK
REGISTER
With this data, update the Integrated Master Schedule and Risk
levels in the Risk Register for future periods of performance.
16
Revise IMS and Risk Register
• Every reporting period update the Risk Register with actual
assessment of
– Reduced risks
– Actual margin needed for unmitigated and irreducible risks
• Adjust Risk Register contents for current assessments
– New risks
– Retired risks
– Changes in risk attributes
• Update ETC, EAC, and ECD with the statused IMS and Risk
Register
17
❹ RUN AND RERUN THE
SCHEDULE RISK ANALYSIS
MONTE CARLO SIMULATIONS
Schedule Risk Analysis (per DI-MGMT-81861A) at periodic
intervals to ensure acceptable confidence levels for the Estimate to
Complete (ETC), Estimate at Completion, and the Estimated
Completion Date (ECD).
18
Run and Rerun Schedule Risk Analysis
Monte Carlo Simulations
• With updated Risk Register – rerun the Schedule Risk Analysis
Monte Carlo Simulations
• Reassess confidence levels of EAC, ETC, and ECD
• Determine sensitivity indices (which elements are most likely to
cause the forward plan to go awry)
• If needed
– Replan IMS, e.g., change logic, and/or possibly with add
more schedule margin
– Add resources
– Adjust technical solution
19
Summary
• Cost and Schedule performance informed by Technical
Performance
– At IBR Technical Performance plan defines the work activities
in the IMS
• Build a risk adjusted PMB
– Reducible and irreducible risks in the risk register, traceable to
the IMS.
• Budget active mitigation activities
• Protect unmitigated risks with Management Reserve and
Schedule Margin
• Confirm programmatic data validity with Technical Performance
Data
• Perform these activities continually during execution to Keep the
Program Green
20
Questions???
20

More Related Content

What's hot

DM Season Group Calculation in Non Interval Scenario
DM Season Group Calculation in Non Interval ScenarioDM Season Group Calculation in Non Interval Scenario
DM Season Group Calculation in Non Interval Scenario
Rakesh Dasgupta
 
Sage 100 yearend webinar 2018
Sage 100 yearend webinar 2018Sage 100 yearend webinar 2018
Sage 100 yearend webinar 2018
RKLeSolutions
 
4.6co 05qa ans
4.6co 05qa ans4.6co 05qa ans
4.6co 05qa ans
Rui Almeida
 
Time based progress analysis in project system (revenue recognition) sap blogs
Time based progress analysis in project system (revenue recognition)   sap blogsTime based progress analysis in project system (revenue recognition)   sap blogs
Time based progress analysis in project system (revenue recognition) sap blogs
Venu Vemula
 
4.6co 03qa ans
4.6co 03qa ans4.6co 03qa ans
4.6co 03qa ans
Rui Almeida
 
Steven M Jarvis Mba[2][2]
Steven M Jarvis Mba[2][2]Steven M Jarvis Mba[2][2]
Steven M Jarvis Mba[2][2]Steven_M_Jarvis
 
Presentation of Quarterly Report_Deborah Ighagbon
Presentation of Quarterly Report_Deborah IghagbonPresentation of Quarterly Report_Deborah Ighagbon
Presentation of Quarterly Report_Deborah IghagbonAANUOLUWAPO D. IGHAGBON
 
My_Speadsheet_Design_Approach
My_Speadsheet_Design_ApproachMy_Speadsheet_Design_Approach
My_Speadsheet_Design_ApproachPhil Orth
 
Mine excellence drilling platform
Mine excellence drilling platformMine excellence drilling platform
Mine excellence drilling platform
Mason Taylor
 
Bar chart
Bar chart Bar chart
Bar chart
PRASHANT GUPTA
 
markGunthorpcv5novresume
markGunthorpcv5novresumemarkGunthorpcv5novresume
markGunthorpcv5novresumeMark Gunthorpe
 
Mine excellence products description v1.2
Mine excellence  products description v1.2Mine excellence  products description v1.2
Mine excellence products description v1.2
Mason Taylor
 
Total Cost Management - Synergy between Cost Estimating and Project Controls
Total Cost Management - Synergy between Cost Estimating and Project ControlsTotal Cost Management - Synergy between Cost Estimating and Project Controls
Total Cost Management - Synergy between Cost Estimating and Project Controls
Martin van Vliet
 
2016 Allegro EMEA Summit_EMEA Power & Gas_James Stirton
2016 Allegro EMEA Summit_EMEA Power & Gas_James Stirton2016 Allegro EMEA Summit_EMEA Power & Gas_James Stirton
2016 Allegro EMEA Summit_EMEA Power & Gas_James Stirton
AllegroMarketing
 
4.6co 02qa ans
4.6co 02qa ans4.6co 02qa ans
4.6co 02qa ans
Rui Almeida
 

What's hot (18)

DM Season Group Calculation in Non Interval Scenario
DM Season Group Calculation in Non Interval ScenarioDM Season Group Calculation in Non Interval Scenario
DM Season Group Calculation in Non Interval Scenario
 
Sage 100 yearend webinar 2018
Sage 100 yearend webinar 2018Sage 100 yearend webinar 2018
Sage 100 yearend webinar 2018
 
4.6co 05qa ans
4.6co 05qa ans4.6co 05qa ans
4.6co 05qa ans
 
Time based progress analysis in project system (revenue recognition) sap blogs
Time based progress analysis in project system (revenue recognition)   sap blogsTime based progress analysis in project system (revenue recognition)   sap blogs
Time based progress analysis in project system (revenue recognition) sap blogs
 
Gdmp model workshop 4 - structure of dass
Gdmp model workshop   4 - structure of dassGdmp model workshop   4 - structure of dass
Gdmp model workshop 4 - structure of dass
 
4.6co 03qa ans
4.6co 03qa ans4.6co 03qa ans
4.6co 03qa ans
 
Power reporting
Power reportingPower reporting
Power reporting
 
Steven M Jarvis Mba[2][2]
Steven M Jarvis Mba[2][2]Steven M Jarvis Mba[2][2]
Steven M Jarvis Mba[2][2]
 
Presentation of Quarterly Report_Deborah Ighagbon
Presentation of Quarterly Report_Deborah IghagbonPresentation of Quarterly Report_Deborah Ighagbon
Presentation of Quarterly Report_Deborah Ighagbon
 
My_Speadsheet_Design_Approach
My_Speadsheet_Design_ApproachMy_Speadsheet_Design_Approach
My_Speadsheet_Design_Approach
 
Generic rlresume
Generic rlresumeGeneric rlresume
Generic rlresume
 
Mine excellence drilling platform
Mine excellence drilling platformMine excellence drilling platform
Mine excellence drilling platform
 
Bar chart
Bar chart Bar chart
Bar chart
 
markGunthorpcv5novresume
markGunthorpcv5novresumemarkGunthorpcv5novresume
markGunthorpcv5novresume
 
Mine excellence products description v1.2
Mine excellence  products description v1.2Mine excellence  products description v1.2
Mine excellence products description v1.2
 
Total Cost Management - Synergy between Cost Estimating and Project Controls
Total Cost Management - Synergy between Cost Estimating and Project ControlsTotal Cost Management - Synergy between Cost Estimating and Project Controls
Total Cost Management - Synergy between Cost Estimating and Project Controls
 
2016 Allegro EMEA Summit_EMEA Power & Gas_James Stirton
2016 Allegro EMEA Summit_EMEA Power & Gas_James Stirton2016 Allegro EMEA Summit_EMEA Power & Gas_James Stirton
2016 Allegro EMEA Summit_EMEA Power & Gas_James Stirton
 
4.6co 02qa ans
4.6co 02qa ans4.6co 02qa ans
4.6co 02qa ans
 

Similar to Creating Credible Plans, Integrating Reporting and Control Systems - Part 2

Beyond CPI and SPI
Beyond CPI and SPIBeyond CPI and SPI
Beyond CPI and SPI
Glen Alleman
 
Using Technical Performance Progress
Using Technical Performance ProgressUsing Technical Performance Progress
Using Technical Performance Progress
Glen Alleman
 
Building a Credible Performance Measurement Baseline
Building a Credible Performance Measurement BaselineBuilding a Credible Performance Measurement Baseline
Building a Credible Performance Measurement Baseline
Glen Alleman
 
Essential program management views
Essential program management viewsEssential program management views
Essential program management views
Glen Alleman
 
Earned Value Managed Services
Earned Value Managed ServicesEarned Value Managed Services
Earned Value Managed Services
Glen Alleman
 
Earned Value Management Essentials
Earned Value Management EssentialsEarned Value Management Essentials
Earned Value Management Essentials
Glen Alleman
 
Earned Value Management Essentials
Earned Value Management EssentialsEarned Value Management Essentials
Earned Value Management Essentials
Glen Alleman
 
Six ½ Day Sessions on the Road To Becoming a CAM
Six ½ Day Sessions on the Road To Becoming a CAMSix ½ Day Sessions on the Road To Becoming a CAM
Six ½ Day Sessions on the Road To Becoming a CAM
Glen Alleman
 
094 Productivity Measurement
094 Productivity Measurement094 Productivity Measurement
094 Productivity Measurement
Dr Fereidoun Dejahang
 
Essential views of the IPMR
Essential views of the IPMREssential views of the IPMR
Essential views of the IPMR
Glen Alleman
 
Building A Credible Measurement Baseline
Building A Credible Measurement BaselineBuilding A Credible Measurement Baseline
Building A Credible Measurement Baseline
Glen Alleman
 
Building a Credible Performance Measurement Baseline (PM Journal)
Building a Credible Performance Measurement Baseline (PM Journal)Building a Credible Performance Measurement Baseline (PM Journal)
Building a Credible Performance Measurement Baseline (PM Journal)
Glen Alleman
 
Building a Credible Performance Measurement Baseline
Building a Credible Performance Measurement BaselineBuilding a Credible Performance Measurement Baseline
Building a Credible Performance Measurement Baseline
Glen Alleman
 
Mitigation And Performance Recovery Using Earned Value
Mitigation And Performance Recovery Using Earned ValueMitigation And Performance Recovery Using Earned Value
Mitigation And Performance Recovery Using Earned Value
Chris Carson
 
Schedule Recovery Using Earned Value
Schedule Recovery Using Earned ValueSchedule Recovery Using Earned Value
Schedule Recovery Using Earned Value
Chris Carson
 
Reliability Growth Testing (RGT) Plan
Reliability Growth Testing (RGT) Plan Reliability Growth Testing (RGT) Plan
Reliability Growth Testing (RGT) Plan
Hilaire (Ananda) Perera P.Eng.
 
Earning Value from Earned Value Management
Earning Value from Earned Value ManagementEarning Value from Earned Value Management
Earning Value from Earned Value ManagementGlen Alleman
 
Earning value from risk (v4 full charts)
Earning value from risk (v4 full charts)Earning value from risk (v4 full charts)
Earning value from risk (v4 full charts)
Glen Alleman
 

Similar to Creating Credible Plans, Integrating Reporting and Control Systems - Part 2 (20)

Beyond CPI and SPI
Beyond CPI and SPIBeyond CPI and SPI
Beyond CPI and SPI
 
Using Technical Performance Progress
Using Technical Performance ProgressUsing Technical Performance Progress
Using Technical Performance Progress
 
Building a Credible Performance Measurement Baseline
Building a Credible Performance Measurement BaselineBuilding a Credible Performance Measurement Baseline
Building a Credible Performance Measurement Baseline
 
Essential program management views
Essential program management viewsEssential program management views
Essential program management views
 
Earned Value Managed Services
Earned Value Managed ServicesEarned Value Managed Services
Earned Value Managed Services
 
Earned Value Management Essentials
Earned Value Management EssentialsEarned Value Management Essentials
Earned Value Management Essentials
 
Earned Value Management Essentials
Earned Value Management EssentialsEarned Value Management Essentials
Earned Value Management Essentials
 
Six ½ Day Sessions on the Road To Becoming a CAM
Six ½ Day Sessions on the Road To Becoming a CAMSix ½ Day Sessions on the Road To Becoming a CAM
Six ½ Day Sessions on the Road To Becoming a CAM
 
094 Productivity Measurement
094 Productivity Measurement094 Productivity Measurement
094 Productivity Measurement
 
Essential views of the IPMR
Essential views of the IPMREssential views of the IPMR
Essential views of the IPMR
 
Building A Credible Measurement Baseline
Building A Credible Measurement BaselineBuilding A Credible Measurement Baseline
Building A Credible Measurement Baseline
 
Building a Credible Performance Measurement Baseline (PM Journal)
Building a Credible Performance Measurement Baseline (PM Journal)Building a Credible Performance Measurement Baseline (PM Journal)
Building a Credible Performance Measurement Baseline (PM Journal)
 
Building a Credible Performance Measurement Baseline
Building a Credible Performance Measurement BaselineBuilding a Credible Performance Measurement Baseline
Building a Credible Performance Measurement Baseline
 
CV - SimonV7
CV - SimonV7CV - SimonV7
CV - SimonV7
 
CV - SimonV7
CV - SimonV7CV - SimonV7
CV - SimonV7
 
Mitigation And Performance Recovery Using Earned Value
Mitigation And Performance Recovery Using Earned ValueMitigation And Performance Recovery Using Earned Value
Mitigation And Performance Recovery Using Earned Value
 
Schedule Recovery Using Earned Value
Schedule Recovery Using Earned ValueSchedule Recovery Using Earned Value
Schedule Recovery Using Earned Value
 
Reliability Growth Testing (RGT) Plan
Reliability Growth Testing (RGT) Plan Reliability Growth Testing (RGT) Plan
Reliability Growth Testing (RGT) Plan
 
Earning Value from Earned Value Management
Earning Value from Earned Value ManagementEarning Value from Earned Value Management
Earning Value from Earned Value Management
 
Earning value from risk (v4 full charts)
Earning value from risk (v4 full charts)Earning value from risk (v4 full charts)
Earning value from risk (v4 full charts)
 

More from Glen Alleman

Managing risk with deliverables planning
Managing risk with deliverables planningManaging risk with deliverables planning
Managing risk with deliverables planning
Glen Alleman
 
A Gentle Introduction to the IMP/IMS
A Gentle Introduction to the IMP/IMSA Gentle Introduction to the IMP/IMS
A Gentle Introduction to the IMP/IMS
Glen Alleman
 
Increasing the Probability of Project Success
Increasing the Probability of Project SuccessIncreasing the Probability of Project Success
Increasing the Probability of Project Success
Glen Alleman
 
Process Flow and Narrative for Agile+PPM
Process Flow and Narrative for Agile+PPMProcess Flow and Narrative for Agile+PPM
Process Flow and Narrative for Agile+PPM
Glen Alleman
 
Practices of risk management
Practices of risk managementPractices of risk management
Practices of risk management
Glen Alleman
 
Principles of Risk Management
Principles of Risk ManagementPrinciples of Risk Management
Principles of Risk Management
Glen Alleman
 
Deliverables Based Planning, PMBOK® and 5 Immutable Principles of Project Suc...
Deliverables Based Planning, PMBOK® and 5 Immutable Principles of Project Suc...Deliverables Based Planning, PMBOK® and 5 Immutable Principles of Project Suc...
Deliverables Based Planning, PMBOK® and 5 Immutable Principles of Project Suc...
Glen Alleman
 
From Principles to Strategies for Systems Engineering
From Principles to Strategies for Systems EngineeringFrom Principles to Strategies for Systems Engineering
From Principles to Strategies for Systems Engineering
Glen Alleman
 
NAVAIR Integrated Master Schedule Guide guide
NAVAIR Integrated Master Schedule Guide guideNAVAIR Integrated Master Schedule Guide guide
NAVAIR Integrated Master Schedule Guide guide
Glen Alleman
 
Integrated master plan methodology (v2)
Integrated master plan methodology (v2)Integrated master plan methodology (v2)
Integrated master plan methodology (v2)
Glen Alleman
 
IMP / IMS Step by Step
IMP / IMS Step by StepIMP / IMS Step by Step
IMP / IMS Step by Step
Glen Alleman
 
DHS - Using functions points to estimate agile development programs (v2)
DHS - Using functions points to estimate agile development programs (v2)DHS - Using functions points to estimate agile development programs (v2)
DHS - Using functions points to estimate agile development programs (v2)
Glen Alleman
 
Making the impossible possible
Making the impossible possibleMaking the impossible possible
Making the impossible possible
Glen Alleman
 
Heliotropic Abundance
Heliotropic AbundanceHeliotropic Abundance
Heliotropic Abundance
Glen Alleman
 
Capabilities based planning
Capabilities based planningCapabilities based planning
Capabilities based planning
Glen Alleman
 
Process Flow and Narrative for Agile
Process Flow and Narrative for AgileProcess Flow and Narrative for Agile
Process Flow and Narrative for Agile
Glen Alleman
 
Building the Performance Measurement Baseline
Building the Performance Measurement BaselineBuilding the Performance Measurement Baseline
Building the Performance Measurement Baseline
Glen Alleman
 
Program Management Office Lean Software Development and Six Sigma
Program Management Office Lean Software Development and Six SigmaProgram Management Office Lean Software Development and Six Sigma
Program Management Office Lean Software Development and Six Sigma
Glen Alleman
 
Policy and Procedure Rollout
Policy and Procedure RolloutPolicy and Procedure Rollout
Policy and Procedure Rollout
Glen Alleman
 
Integrated Master Plan Development
Integrated Master Plan DevelopmentIntegrated Master Plan Development
Integrated Master Plan Development
Glen Alleman
 

More from Glen Alleman (20)

Managing risk with deliverables planning
Managing risk with deliverables planningManaging risk with deliverables planning
Managing risk with deliverables planning
 
A Gentle Introduction to the IMP/IMS
A Gentle Introduction to the IMP/IMSA Gentle Introduction to the IMP/IMS
A Gentle Introduction to the IMP/IMS
 
Increasing the Probability of Project Success
Increasing the Probability of Project SuccessIncreasing the Probability of Project Success
Increasing the Probability of Project Success
 
Process Flow and Narrative for Agile+PPM
Process Flow and Narrative for Agile+PPMProcess Flow and Narrative for Agile+PPM
Process Flow and Narrative for Agile+PPM
 
Practices of risk management
Practices of risk managementPractices of risk management
Practices of risk management
 
Principles of Risk Management
Principles of Risk ManagementPrinciples of Risk Management
Principles of Risk Management
 
Deliverables Based Planning, PMBOK® and 5 Immutable Principles of Project Suc...
Deliverables Based Planning, PMBOK® and 5 Immutable Principles of Project Suc...Deliverables Based Planning, PMBOK® and 5 Immutable Principles of Project Suc...
Deliverables Based Planning, PMBOK® and 5 Immutable Principles of Project Suc...
 
From Principles to Strategies for Systems Engineering
From Principles to Strategies for Systems EngineeringFrom Principles to Strategies for Systems Engineering
From Principles to Strategies for Systems Engineering
 
NAVAIR Integrated Master Schedule Guide guide
NAVAIR Integrated Master Schedule Guide guideNAVAIR Integrated Master Schedule Guide guide
NAVAIR Integrated Master Schedule Guide guide
 
Integrated master plan methodology (v2)
Integrated master plan methodology (v2)Integrated master plan methodology (v2)
Integrated master plan methodology (v2)
 
IMP / IMS Step by Step
IMP / IMS Step by StepIMP / IMS Step by Step
IMP / IMS Step by Step
 
DHS - Using functions points to estimate agile development programs (v2)
DHS - Using functions points to estimate agile development programs (v2)DHS - Using functions points to estimate agile development programs (v2)
DHS - Using functions points to estimate agile development programs (v2)
 
Making the impossible possible
Making the impossible possibleMaking the impossible possible
Making the impossible possible
 
Heliotropic Abundance
Heliotropic AbundanceHeliotropic Abundance
Heliotropic Abundance
 
Capabilities based planning
Capabilities based planningCapabilities based planning
Capabilities based planning
 
Process Flow and Narrative for Agile
Process Flow and Narrative for AgileProcess Flow and Narrative for Agile
Process Flow and Narrative for Agile
 
Building the Performance Measurement Baseline
Building the Performance Measurement BaselineBuilding the Performance Measurement Baseline
Building the Performance Measurement Baseline
 
Program Management Office Lean Software Development and Six Sigma
Program Management Office Lean Software Development and Six SigmaProgram Management Office Lean Software Development and Six Sigma
Program Management Office Lean Software Development and Six Sigma
 
Policy and Procedure Rollout
Policy and Procedure RolloutPolicy and Procedure Rollout
Policy and Procedure Rollout
 
Integrated Master Plan Development
Integrated Master Plan DevelopmentIntegrated Master Plan Development
Integrated Master Plan Development
 

Recently uploaded

Unsubscribed: Combat Subscription Fatigue With a Membership Mentality by Head...
Unsubscribed: Combat Subscription Fatigue With a Membership Mentality by Head...Unsubscribed: Combat Subscription Fatigue With a Membership Mentality by Head...
Unsubscribed: Combat Subscription Fatigue With a Membership Mentality by Head...
Product School
 
The Future of Platform Engineering
The Future of Platform EngineeringThe Future of Platform Engineering
The Future of Platform Engineering
Jemma Hussein Allen
 
Designing Great Products: The Power of Design and Leadership by Chief Designe...
Designing Great Products: The Power of Design and Leadership by Chief Designe...Designing Great Products: The Power of Design and Leadership by Chief Designe...
Designing Great Products: The Power of Design and Leadership by Chief Designe...
Product School
 
Generating a custom Ruby SDK for your web service or Rails API using Smithy
Generating a custom Ruby SDK for your web service or Rails API using SmithyGenerating a custom Ruby SDK for your web service or Rails API using Smithy
Generating a custom Ruby SDK for your web service or Rails API using Smithy
g2nightmarescribd
 
UiPath Test Automation using UiPath Test Suite series, part 4
UiPath Test Automation using UiPath Test Suite series, part 4UiPath Test Automation using UiPath Test Suite series, part 4
UiPath Test Automation using UiPath Test Suite series, part 4
DianaGray10
 
FIDO Alliance Osaka Seminar: Passkeys and the Road Ahead.pdf
FIDO Alliance Osaka Seminar: Passkeys and the Road Ahead.pdfFIDO Alliance Osaka Seminar: Passkeys and the Road Ahead.pdf
FIDO Alliance Osaka Seminar: Passkeys and the Road Ahead.pdf
FIDO Alliance
 
Neuro-symbolic is not enough, we need neuro-*semantic*
Neuro-symbolic is not enough, we need neuro-*semantic*Neuro-symbolic is not enough, we need neuro-*semantic*
Neuro-symbolic is not enough, we need neuro-*semantic*
Frank van Harmelen
 
Securing your Kubernetes cluster_ a step-by-step guide to success !
Securing your Kubernetes cluster_ a step-by-step guide to success !Securing your Kubernetes cluster_ a step-by-step guide to success !
Securing your Kubernetes cluster_ a step-by-step guide to success !
KatiaHIMEUR1
 
Software Delivery At the Speed of AI: Inflectra Invests In AI-Powered Quality
Software Delivery At the Speed of AI: Inflectra Invests In AI-Powered QualitySoftware Delivery At the Speed of AI: Inflectra Invests In AI-Powered Quality
Software Delivery At the Speed of AI: Inflectra Invests In AI-Powered Quality
Inflectra
 
Smart TV Buyer Insights Survey 2024 by 91mobiles.pdf
Smart TV Buyer Insights Survey 2024 by 91mobiles.pdfSmart TV Buyer Insights Survey 2024 by 91mobiles.pdf
Smart TV Buyer Insights Survey 2024 by 91mobiles.pdf
91mobiles
 
UiPath Test Automation using UiPath Test Suite series, part 3
UiPath Test Automation using UiPath Test Suite series, part 3UiPath Test Automation using UiPath Test Suite series, part 3
UiPath Test Automation using UiPath Test Suite series, part 3
DianaGray10
 
Monitoring Java Application Security with JDK Tools and JFR Events
Monitoring Java Application Security with JDK Tools and JFR EventsMonitoring Java Application Security with JDK Tools and JFR Events
Monitoring Java Application Security with JDK Tools and JFR Events
Ana-Maria Mihalceanu
 
When stars align: studies in data quality, knowledge graphs, and machine lear...
When stars align: studies in data quality, knowledge graphs, and machine lear...When stars align: studies in data quality, knowledge graphs, and machine lear...
When stars align: studies in data quality, knowledge graphs, and machine lear...
Elena Simperl
 
Leading Change strategies and insights for effective change management pdf 1.pdf
Leading Change strategies and insights for effective change management pdf 1.pdfLeading Change strategies and insights for effective change management pdf 1.pdf
Leading Change strategies and insights for effective change management pdf 1.pdf
OnBoard
 
Key Trends Shaping the Future of Infrastructure.pdf
Key Trends Shaping the Future of Infrastructure.pdfKey Trends Shaping the Future of Infrastructure.pdf
Key Trends Shaping the Future of Infrastructure.pdf
Cheryl Hung
 
De-mystifying Zero to One: Design Informed Techniques for Greenfield Innovati...
De-mystifying Zero to One: Design Informed Techniques for Greenfield Innovati...De-mystifying Zero to One: Design Informed Techniques for Greenfield Innovati...
De-mystifying Zero to One: Design Informed Techniques for Greenfield Innovati...
Product School
 
Builder.ai Founder Sachin Dev Duggal's Strategic Approach to Create an Innova...
Builder.ai Founder Sachin Dev Duggal's Strategic Approach to Create an Innova...Builder.ai Founder Sachin Dev Duggal's Strategic Approach to Create an Innova...
Builder.ai Founder Sachin Dev Duggal's Strategic Approach to Create an Innova...
Ramesh Iyer
 
Encryption in Microsoft 365 - ExpertsLive Netherlands 2024
Encryption in Microsoft 365 - ExpertsLive Netherlands 2024Encryption in Microsoft 365 - ExpertsLive Netherlands 2024
Encryption in Microsoft 365 - ExpertsLive Netherlands 2024
Albert Hoitingh
 
LF Energy Webinar: Electrical Grid Modelling and Simulation Through PowSyBl -...
LF Energy Webinar: Electrical Grid Modelling and Simulation Through PowSyBl -...LF Energy Webinar: Electrical Grid Modelling and Simulation Through PowSyBl -...
LF Energy Webinar: Electrical Grid Modelling and Simulation Through PowSyBl -...
DanBrown980551
 
Assuring Contact Center Experiences for Your Customers With ThousandEyes
Assuring Contact Center Experiences for Your Customers With ThousandEyesAssuring Contact Center Experiences for Your Customers With ThousandEyes
Assuring Contact Center Experiences for Your Customers With ThousandEyes
ThousandEyes
 

Recently uploaded (20)

Unsubscribed: Combat Subscription Fatigue With a Membership Mentality by Head...
Unsubscribed: Combat Subscription Fatigue With a Membership Mentality by Head...Unsubscribed: Combat Subscription Fatigue With a Membership Mentality by Head...
Unsubscribed: Combat Subscription Fatigue With a Membership Mentality by Head...
 
The Future of Platform Engineering
The Future of Platform EngineeringThe Future of Platform Engineering
The Future of Platform Engineering
 
Designing Great Products: The Power of Design and Leadership by Chief Designe...
Designing Great Products: The Power of Design and Leadership by Chief Designe...Designing Great Products: The Power of Design and Leadership by Chief Designe...
Designing Great Products: The Power of Design and Leadership by Chief Designe...
 
Generating a custom Ruby SDK for your web service or Rails API using Smithy
Generating a custom Ruby SDK for your web service or Rails API using SmithyGenerating a custom Ruby SDK for your web service or Rails API using Smithy
Generating a custom Ruby SDK for your web service or Rails API using Smithy
 
UiPath Test Automation using UiPath Test Suite series, part 4
UiPath Test Automation using UiPath Test Suite series, part 4UiPath Test Automation using UiPath Test Suite series, part 4
UiPath Test Automation using UiPath Test Suite series, part 4
 
FIDO Alliance Osaka Seminar: Passkeys and the Road Ahead.pdf
FIDO Alliance Osaka Seminar: Passkeys and the Road Ahead.pdfFIDO Alliance Osaka Seminar: Passkeys and the Road Ahead.pdf
FIDO Alliance Osaka Seminar: Passkeys and the Road Ahead.pdf
 
Neuro-symbolic is not enough, we need neuro-*semantic*
Neuro-symbolic is not enough, we need neuro-*semantic*Neuro-symbolic is not enough, we need neuro-*semantic*
Neuro-symbolic is not enough, we need neuro-*semantic*
 
Securing your Kubernetes cluster_ a step-by-step guide to success !
Securing your Kubernetes cluster_ a step-by-step guide to success !Securing your Kubernetes cluster_ a step-by-step guide to success !
Securing your Kubernetes cluster_ a step-by-step guide to success !
 
Software Delivery At the Speed of AI: Inflectra Invests In AI-Powered Quality
Software Delivery At the Speed of AI: Inflectra Invests In AI-Powered QualitySoftware Delivery At the Speed of AI: Inflectra Invests In AI-Powered Quality
Software Delivery At the Speed of AI: Inflectra Invests In AI-Powered Quality
 
Smart TV Buyer Insights Survey 2024 by 91mobiles.pdf
Smart TV Buyer Insights Survey 2024 by 91mobiles.pdfSmart TV Buyer Insights Survey 2024 by 91mobiles.pdf
Smart TV Buyer Insights Survey 2024 by 91mobiles.pdf
 
UiPath Test Automation using UiPath Test Suite series, part 3
UiPath Test Automation using UiPath Test Suite series, part 3UiPath Test Automation using UiPath Test Suite series, part 3
UiPath Test Automation using UiPath Test Suite series, part 3
 
Monitoring Java Application Security with JDK Tools and JFR Events
Monitoring Java Application Security with JDK Tools and JFR EventsMonitoring Java Application Security with JDK Tools and JFR Events
Monitoring Java Application Security with JDK Tools and JFR Events
 
When stars align: studies in data quality, knowledge graphs, and machine lear...
When stars align: studies in data quality, knowledge graphs, and machine lear...When stars align: studies in data quality, knowledge graphs, and machine lear...
When stars align: studies in data quality, knowledge graphs, and machine lear...
 
Leading Change strategies and insights for effective change management pdf 1.pdf
Leading Change strategies and insights for effective change management pdf 1.pdfLeading Change strategies and insights for effective change management pdf 1.pdf
Leading Change strategies and insights for effective change management pdf 1.pdf
 
Key Trends Shaping the Future of Infrastructure.pdf
Key Trends Shaping the Future of Infrastructure.pdfKey Trends Shaping the Future of Infrastructure.pdf
Key Trends Shaping the Future of Infrastructure.pdf
 
De-mystifying Zero to One: Design Informed Techniques for Greenfield Innovati...
De-mystifying Zero to One: Design Informed Techniques for Greenfield Innovati...De-mystifying Zero to One: Design Informed Techniques for Greenfield Innovati...
De-mystifying Zero to One: Design Informed Techniques for Greenfield Innovati...
 
Builder.ai Founder Sachin Dev Duggal's Strategic Approach to Create an Innova...
Builder.ai Founder Sachin Dev Duggal's Strategic Approach to Create an Innova...Builder.ai Founder Sachin Dev Duggal's Strategic Approach to Create an Innova...
Builder.ai Founder Sachin Dev Duggal's Strategic Approach to Create an Innova...
 
Encryption in Microsoft 365 - ExpertsLive Netherlands 2024
Encryption in Microsoft 365 - ExpertsLive Netherlands 2024Encryption in Microsoft 365 - ExpertsLive Netherlands 2024
Encryption in Microsoft 365 - ExpertsLive Netherlands 2024
 
LF Energy Webinar: Electrical Grid Modelling and Simulation Through PowSyBl -...
LF Energy Webinar: Electrical Grid Modelling and Simulation Through PowSyBl -...LF Energy Webinar: Electrical Grid Modelling and Simulation Through PowSyBl -...
LF Energy Webinar: Electrical Grid Modelling and Simulation Through PowSyBl -...
 
Assuring Contact Center Experiences for Your Customers With ThousandEyes
Assuring Contact Center Experiences for Your Customers With ThousandEyesAssuring Contact Center Experiences for Your Customers With ThousandEyes
Assuring Contact Center Experiences for Your Customers With ThousandEyes
 

Creating Credible Plans, Integrating Reporting and Control Systems - Part 2

  • 1. Executing the Credible Plan, Using an Integrated Reporting and Control System Part 2 EVM World 2016 Glen B. Alleman Agile Program Planning and Controls Prime PM glen.alleman@niwotridge.com +1 303 241 9633 Thomas Coonce Cost Analysis and Research Division Institute for Defense Analyses tcoonce@ida.org +1 703 575 6634 Rick Price Project Management & Planning Operations Principal Lockheed Martin Space Systems Company rick.a.price@lmco.com +1 303 971 1826
  • 2. 2 Learning Objectives • TLO #1 – the student will learn how to produce an integrated report of the Technical progress consistent with the Programmatic progress, detect variances, and suggest corrective actions. • TLO #2 – the student will understand how to objectively measure progress and use the performance to manage the program. • Earned Value Management is part of a Technical and Programmatic control system – Integrated risk, performance, effectiveness, technical and other measures provide leading indicators of program performance.
  • 3. 3 In Part 1, we talked about … • The five core processes needed to produce a credible Performance Measurement Baseline (PMB). • How to use objective measures of progress and how to inform program performance with these measures. In Part 2, you’ll see how to execute the program with this information.
  • 4. 4 Part 1 ‒ Inputs and Outputs for Building the Credible Performance Measurement Baseline • Customer Capabilities • Time phased budget • Desired completion date • Available technologies • Time phased resources • Reference Class Data • Programmatic and technical risks with probabilities and impacts • Historic uncertainties • Measures of Effectiveness • Measures of Performance • Work Breakdown Structure • Integrated Master Plan • Technical Performance Management Plan • Initial Integrated Master Schedule • Time Phased Staffing Plan • Schedule Reserve (Margin) • Management Reserve • Risk Register and Mitigation Plans • Adjusted Integrated Master Schedule • Risk Burn Down Plan Inputs Outputs
  • 5. 5 Part 2 ‒ Executing the Credible Performance Measurement Baseline
  • 6. 6 A Readable Version The Four processes needed to execute the credible PMB ❶ Compare Technical and Programmatic Actuals to Plan ❷ Compare BCWP and Cost and Schedule Performance Data with Management Reserve (MR) and Schedule Margin (SM) balances ❸ Revise Integrated Master Schedule (IMS) and Risk Register ❹ Run or Rerun Monte Carlo Simulations
  • 7. 7 ❶ COMPARE PLANNED TO ACTUAL PERFORMANCE Compare technical and programmatic performance to the planned performance. Identify variances needed to make decisions about corrective actions to Keep the Program Green.
  • 8. 8 Compare Planned to Actual Performance • Physical Percent Complete – Planned – Actual • Do this at the Work Package level – Quantifiable Backup Data – Avoid averaging out the variances at the Control Account level Objectively assess accomplishments at the Work Performance Level EIA-748-C, page 1
  • 9. 9 Wright Brothers’ Technical, Cost and Schedule Progress 0.80 0.85 0.90 0.95 1.00 1.05 1.10 770 780 790 800 810 820 830 840 850 860 870 15-Feb-08 15-Mar-08 15-Apr-08 15-May-08 15-Jun-08 15-Jul-08 CPI/SPI Pounds WBs' 1908 Flyer Integrated Progress (2/28/1908) Upper Limit Planned Target Achieved SPI CPI Compare side-by-side the Technical Performance (Weight) with the Programmatic performance CPI and SPI
  • 10. 10 ❷ COMPARE MR AND SM BALANCES Using the performance data and the variances, the computed BCWP from measures of Physical Percent Complete. Assess planned Management Reserve and Schedule Margin with the current MR and SM and inform EAC and ETC from past performance.
  • 11. 11 Compare BCWP with MR and SM • With actual BCWP assess impact on Estimate at Completion and Estimate To Complete. • Assess planned Management Reserve against actual Management Reserve • Assess planned Schedule Margin against actual Schedule Margin • Assess planned risk burn down against actual Risk Burn Down
  • 12. 12 Wright Brothers’ MR Planned Use vs Actuals $0 $500 $1,000 $1,500 $2,000 $2,500 $3,000 $3,500 $4,000 WB 1908 Flyer Planned vs Actual MR Use (15 May 1908) MR Planned Balance MR Actual Balance
  • 13. 13 Schedule Margin in Final WB’s Flyer IMS
  • 14. 14 Wright Brothers’ Schedule Margin Burn Planned Use vs Actuals In May, when the schedule margin went below plan, immediate corrective action is needed to get back on Schedule Margin Plan 0 2 4 6 8 10 12 15-Feb-08 15-Mar-08 15-Apr-08 15-May-08 15-Jun-08 15-Jul-08 15-Aug-08 15-Sep-08 Days WB 1908 Flyer Planned vs Actual Schedule Margin Use (15 May 1908) Schedule Margin Plan Balance Schedule Margin Actual Balance This dip is characterized as negative slack
  • 15. 15 ❸ REVISE IMS AND RISK REGISTER With this data, update the Integrated Master Schedule and Risk levels in the Risk Register for future periods of performance.
  • 16. 16 Revise IMS and Risk Register • Every reporting period update the Risk Register with actual assessment of – Reduced risks – Actual margin needed for unmitigated and irreducible risks • Adjust Risk Register contents for current assessments – New risks – Retired risks – Changes in risk attributes • Update ETC, EAC, and ECD with the statused IMS and Risk Register
  • 17. 17 ❹ RUN AND RERUN THE SCHEDULE RISK ANALYSIS MONTE CARLO SIMULATIONS Schedule Risk Analysis (per DI-MGMT-81861A) at periodic intervals to ensure acceptable confidence levels for the Estimate to Complete (ETC), Estimate at Completion, and the Estimated Completion Date (ECD).
  • 18. 18 Run and Rerun Schedule Risk Analysis Monte Carlo Simulations • With updated Risk Register – rerun the Schedule Risk Analysis Monte Carlo Simulations • Reassess confidence levels of EAC, ETC, and ECD • Determine sensitivity indices (which elements are most likely to cause the forward plan to go awry) • If needed – Replan IMS, e.g., change logic, and/or possibly with add more schedule margin – Add resources – Adjust technical solution
  • 19. 19 Summary • Cost and Schedule performance informed by Technical Performance – At IBR Technical Performance plan defines the work activities in the IMS • Build a risk adjusted PMB – Reducible and irreducible risks in the risk register, traceable to the IMS. • Budget active mitigation activities • Protect unmitigated risks with Management Reserve and Schedule Margin • Confirm programmatic data validity with Technical Performance Data • Perform these activities continually during execution to Keep the Program Green