The meeting provided updates on several community programs projects: the final phase of the Point Place project was completed in May eliminating overflows; the River Road projects including an equalization basin, pump station, and sewer lines were 80% complete; and the Bay View Wastewater Treatment Plant equalization basin was 80% complete and expected to finish by the end of the year. The meeting also discussed progress on the wastewater treatment plant including ballasted flocculation being 95% done, the grit facility being 95% complete, and an effluent pump station being 5-10% complete; as well as sewer rate increases of 8-10% for the next four years and scheduling the next meeting.