6. Oak Bluffs
Year round population approximately 4000 people
Summer population exceeds 25,000
7. Critical Infrastructure
OB wastewater collection and treatment system serves the heavily populated downtown and commercial areas
Three primary wastewater pump stations serve 90% of the wastewater system, and are located within newly mapped FEMA 100 yr flood plain
Stations have already had flood impacts
11. The Project
Design and construct modifications to these pump stations to ensure safe operation during a 100 year flood event
Elevate all electrical service and control panels above flood elevations
Construct elevated platforms for emergency generators
Install protective flood panels around pump stations
12. Sea Level Rise & Project Design
Design will be based upon a SLR projection of 3.9 feet by Year 2100 (“intermediate-high” scenario)
Pump Station infrastructure has a design life of 40 years
40 year SLR projection = 1.5 feet
14. Tasks & Deliverables
Complete preliminary designs
Submit design plans for DEP Wastewater Treatment Works Plan Approval
Complete final design
Solicit construction bids
Submit Construction Plans and Operation & Maintenance Manual for DEP approval
Obtain Order of Conditions
Complete construction
DEP final inspection