CONCRETE PAVEMENT
CONSTRUCTION OF ROAD
Presenters :Aman Shakya
Vijay Kumar Sharma
Ayush Maheshwari
PRESENTING TO : Veerendra Kumar Shivhare
CIVIL Dept. HCST
INTRODUCTION
 Development of a country depends on the connectivity of various places with adequate road
network.
 Roads constitute the most important mode of communication in areas where railways have
not developed much.
 India has one of the largest road networks in the world (over 3 million km at present).For the
purpose of management and administration, roads in India are divided into the following five
categories:
• National Highways (NH)
• State Highways (SH)
• Major District Roads (MDR)
• Other District Roads (ODR)
• Village Roads (VR)
WHAT IS ROAD PAVEMENT
Pavement is finished with a hard smooth surface directly above the
subgrade. It helped make roads durable and able to withstand traffic and
the environment.
One of the primary functions of pavement is load distribution.
TYPES OF PAVEMENTS
• There are various types of pavements depending upon the materials used; a briefs
description of all types is given here-
• FLEXIBLE PAVEMENT
• Bitumen has been widely used in the construction of flexible pavements for a long time.
This is the most convenient and simple type of construction. The cost of construction of
single lane bituminous pavement varies from 20 to 30 lakhs per km in plain area.
• Flexible pavement have-
 Have low flexural strength
 Load is transferred by grain to grain contact
 Have low completion cost but repairing cost is high
RIGID PAVEMENT
• Rigid pavements, though costly in initial investment, are cheap in long run because of low
maintenance costs, The cost of construction of single lane rigid pavement varies from 35 to
50 lakh per km in plain area,
• Rigid pavement have-
 Deformation in the sub grade is not transferred to subsequent layers
 Design is based on flexural strength or slab action
 Have high flexural strength
 No such phenomenon of grain to grain load
transfer exists
 Have low repairing cost but completion cost is high
 Low Maintenance Cost
Difference b/w Flexible and Rigid
Pavement in terms of load
distribution In different layers
Different layers in Flexible and
Rigid Pavement
Basic Components of a Concrete Pavement
• Cement
 Ordinary Portland cement (OPC)
• Ordinary Portland cement and High Strength Ordinary Portland Cement are most
widely used for concrete pavements.
 Rapid hardening Portland cement
• In general, this cement would be used only where time is a critical factor and the road is
required to be opened to traffic at an earlier date than would be possible if Ordinary
Portland Cement or High Strength Ordinary Portland Cement is used.
MINERALS
USED
Aggregates
• There are two types of Aggregates are used during construction of road i.e. Fine
and Coarse Aggregate depending on requirements.
• Maximum size of aggregate should not exceed 1/4th of the pavement slab
thickness.
Water
• Water used in mixing or curing of concrete shall be clean and free from
injurious amounts of oil, salt, acid, vegetable matter or other substances harmful
to the finished concrete.
Mineral used( cont.)
A list of tools, equipment and appliances required for the different phases of
concrete road construction is given below
 Three wheeled or vibratory roller for compaction purpose
 Shovels, spades and Sieving screens
 Concrete mixer for mixing of concrete
 Formwork and iron stakes
 Watering devices - Water Lorries, water carriers or watering cans
 Wooden hand tampers for concrete compaction
 Cycle pump/pneumatic air blower for cleaning of joint
 Mild steel sections and blocks for making joint grooves for finishing purpose
Equipments used
Before construction begins, the construction site must be carefully prepared, This includes preparing the
grade or road base, sub grade and sub base-
 First the site is graded to cut high points and fill low areas to the desired roadway profile
elevations.
 Generally, cut material can be used as embankment fill.
 A course of material is placed on the sub grade to provide drainage and stability.
 A course of fairly rigid material, sometimes cement- or asphalt-treated, that is placed on the sub base to
provide a stable platform for the concrete pavement slab.
Site Preparation
Construction Process
Wooden sheets, battens, plywood, fibre hard board, steel plates, angles, rope etc are
generally use for form work.
 before using form work, it should free from all type material like as dust ,cement.
 To placing the concrete in appropriate depth used 2.5-5cm thick and 3mtr long wooden
sheeting
 The depth of wooden block must be same as level of slab thick.
 After 24hrs, form work displaced next length
of road.
FORM WORK
After site preparation, Construction process consists of
various steps, which are described below-
Watering of base
If the base of the road is dry or construction is taken place during summer seasons
Then watering is done using the sprinkling process, after this concrete should be
Placed.
Construction of
Joints
• There are three basic joint types used in concrete pavement: contraction,
construction and isolation.
• Except for some isolation joints, all joints provide a means to
mechanically connect slabs. The connection helps to spread a load applied
on one slab onto slabs along its perimeter.
• Where it is necessary to provide transverse and Longitudinal joints;
there wedge of woods, metals fix on level of concrete.
• After setting of concrete it should be pull out.
PLACING OF CONCRETE
Two methods generally used in placing of concrete-
1- Alternate bay method-
Placed the concrete on both side of road alternatively like as1,3,5… part at one side and 2,4,6… part other
side, This method have slow process due to road traffic problems.
2- Continuous bay method-
Construct one side of road regularly, and after construction of some part of first side than construct other
side, this method have fast process without no obstruction of traffic
COMPACTION OF CONCRETE
Purpose of compaction is that to pull out air from void and make concrete harden.
Compaction done by-
1.Mechanically surface vibrator
2. Manually hand tempers
 After this, Floating, Belting, Screeding or strike off, Bull floating and Brooming is done
as per requirement for the finishing purpose of concrete pavement to smoothen the top
surface.
CURING
After completion of the finishing operations, the surface of the pavement shall be entirely
covered with wet hessian cloth, burlap or jute mats
Curing is the process of increasing the hydration of cement, after setting the concrete curing
process done till 14-28days.
THANK YOU

More Related Content

What's hot

ROAD CONSTRUCTION(BITUMEN) SUMMER TRAINING REPORT
ROAD CONSTRUCTION(BITUMEN) SUMMER TRAINING REPORTROAD CONSTRUCTION(BITUMEN) SUMMER TRAINING REPORT
ROAD CONSTRUCTION(BITUMEN) SUMMER TRAINING REPORTssuser5fea8f
 
Highway construction or Road work report
Highway construction or Road work reportHighway construction or Road work report
Highway construction or Road work reportAbdul rahman kureshi
 
Construction of rigid pavement
Construction of rigid pavementConstruction of rigid pavement
Construction of rigid pavementpradip dangar
 
Internship report on rcc road
Internship report on rcc roadInternship report on rcc road
Internship report on rcc roaddeepak athwal
 
Summer training report on cement Road Construction
 Summer training report on cement Road Construction Summer training report on cement Road Construction
Summer training report on cement Road ConstructionVijaypal Bagariya
 
construction of flexible pavement
construction of flexible pavementconstruction of flexible pavement
construction of flexible pavementRafi Khan
 
Construction of flexible pavement
Construction of flexible pavementConstruction of flexible pavement
Construction of flexible pavementUTU Dehradun
 
training report on pwd
training report on pwdtraining report on pwd
training report on pwdAjay Upadhyay
 
Highway engineering PPT
Highway engineering PPTHighway engineering PPT
Highway engineering PPTKavin Raval
 
Cc road summer training ppt @akshay kumar
Cc road summer training ppt @akshay kumarCc road summer training ppt @akshay kumar
Cc road summer training ppt @akshay kumarAkshay kumar
 
Highway construction PPT
Highway construction PPTHighway construction PPT
Highway construction PPTVikas Sukhwal
 
Permanent Way of Railway & Components ?(part -1,2,3,4,5)
Permanent Way of Railway & Components ?(part -1,2,3,4,5)Permanent Way of Railway & Components ?(part -1,2,3,4,5)
Permanent Way of Railway & Components ?(part -1,2,3,4,5)RAMPRASAD KUMAWAT
 
Training report of road construction
Training report of road constructionTraining report of road construction
Training report of road constructionManavSinghal8
 

What's hot (20)

ROAD CONSTRUCTION(BITUMEN) SUMMER TRAINING REPORT
ROAD CONSTRUCTION(BITUMEN) SUMMER TRAINING REPORTROAD CONSTRUCTION(BITUMEN) SUMMER TRAINING REPORT
ROAD CONSTRUCTION(BITUMEN) SUMMER TRAINING REPORT
 
road construction
road constructionroad construction
road construction
 
Highway construction or Road work report
Highway construction or Road work reportHighway construction or Road work report
Highway construction or Road work report
 
Construction of cc_road
Construction of cc_roadConstruction of cc_road
Construction of cc_road
 
Construction of rigid pavement
Construction of rigid pavementConstruction of rigid pavement
Construction of rigid pavement
 
Rigid pavements
Rigid pavements Rigid pavements
Rigid pavements
 
Highway drainage
Highway drainageHighway drainage
Highway drainage
 
Internship report on rcc road
Internship report on rcc roadInternship report on rcc road
Internship report on rcc road
 
Summer training report on cement Road Construction
 Summer training report on cement Road Construction Summer training report on cement Road Construction
Summer training report on cement Road Construction
 
construction of flexible pavement
construction of flexible pavementconstruction of flexible pavement
construction of flexible pavement
 
Construction of flexible pavement
Construction of flexible pavementConstruction of flexible pavement
Construction of flexible pavement
 
training report on pwd
training report on pwdtraining report on pwd
training report on pwd
 
Highway engineering PPT
Highway engineering PPTHighway engineering PPT
Highway engineering PPT
 
Cc road summer training ppt @akshay kumar
Cc road summer training ppt @akshay kumarCc road summer training ppt @akshay kumar
Cc road summer training ppt @akshay kumar
 
Highway construction PPT
Highway construction PPTHighway construction PPT
Highway construction PPT
 
Permanent Way of Railway & Components ?(part -1,2,3,4,5)
Permanent Way of Railway & Components ?(part -1,2,3,4,5)Permanent Way of Railway & Components ?(part -1,2,3,4,5)
Permanent Way of Railway & Components ?(part -1,2,3,4,5)
 
Road construction ppt
Road construction pptRoad construction ppt
Road construction ppt
 
Training report of road construction
Training report of road constructionTraining report of road construction
Training report of road construction
 
PERMANANT WAY
PERMANANT WAYPERMANANT WAY
PERMANANT WAY
 
PQC concrete road
PQC concrete roadPQC concrete road
PQC concrete road
 

Similar to Construction of Road

CONSTRUCTION OF CEMENT CONCRETE ROAD
CONSTRUCTION OF CEMENT CONCRETE ROADCONSTRUCTION OF CEMENT CONCRETE ROAD
CONSTRUCTION OF CEMENT CONCRETE ROADGLA University
 
Aryan k tranning file road ppt 07
Aryan k tranning file road ppt 07Aryan k tranning file road ppt 07
Aryan k tranning file road ppt 07aryan kumar
 
RIGID PAVEMENT -ANIL GUPTA (P.W.D)
RIGID PAVEMENT -ANIL GUPTA (P.W.D)RIGID PAVEMENT -ANIL GUPTA (P.W.D)
RIGID PAVEMENT -ANIL GUPTA (P.W.D)Anil Gupta
 
Rigid pavement
Rigid pavementRigid pavement
Rigid pavementpjainrahul
 
ROAD CONSTRUCTION (FLEXIBLE & RIGID) - SLIDES.pdf
ROAD CONSTRUCTION (FLEXIBLE & RIGID) - SLIDES.pdfROAD CONSTRUCTION (FLEXIBLE & RIGID) - SLIDES.pdf
ROAD CONSTRUCTION (FLEXIBLE & RIGID) - SLIDES.pdfDanielWisman1
 
CONSTRUCTION_OF_RIGID_PAVEMENT.pptx
CONSTRUCTION_OF_RIGID_PAVEMENT.pptxCONSTRUCTION_OF_RIGID_PAVEMENT.pptx
CONSTRUCTION_OF_RIGID_PAVEMENT.pptxJaySinghchib1
 
Road construction ppt for college rajkiya presentation
Road construction ppt for college rajkiya presentationRoad construction ppt for college rajkiya presentation
Road construction ppt for college rajkiya presentationmahesh515545
 
Rigid pavement in Magallanes Interchange
Rigid pavement in Magallanes InterchangeRigid pavement in Magallanes Interchange
Rigid pavement in Magallanes Interchangeharoldtaylor1113
 
Geometric design of highway
Geometric design of  highwayGeometric design of  highway
Geometric design of highwayPratikShinde113
 
Roads & Pavements
Roads & PavementsRoads & Pavements
Roads & PavementsAaqib Iqbal
 
Highway failure and their maintenance
Highway failure and their maintenanceHighway failure and their maintenance
Highway failure and their maintenanceMantoshRajput
 
PRESENTATION ON RIGID PAVEMExNT.pptx for
PRESENTATION ON RIGID PAVEMExNT.pptx forPRESENTATION ON RIGID PAVEMExNT.pptx for
PRESENTATION ON RIGID PAVEMExNT.pptx forVishalshukla347388
 
Mukesh ppt cc road
Mukesh ppt cc roadMukesh ppt cc road
Mukesh ppt cc roadHJ Sims
 
highway materials and desihn.pptx
highway materials and desihn.pptxhighway materials and desihn.pptx
highway materials and desihn.pptxSekharJ4
 
Types of pavement- Transportation Engg. I
Types of pavement- Transportation Engg. ITypes of pavement- Transportation Engg. I
Types of pavement- Transportation Engg. IGauri kadam
 

Similar to Construction of Road (20)

CONSTRUCTION OF CEMENT CONCRETE ROAD
CONSTRUCTION OF CEMENT CONCRETE ROADCONSTRUCTION OF CEMENT CONCRETE ROAD
CONSTRUCTION OF CEMENT CONCRETE ROAD
 
Aryan k tranning file road ppt 07
Aryan k tranning file road ppt 07Aryan k tranning file road ppt 07
Aryan k tranning file road ppt 07
 
Highway report
Highway reportHighway report
Highway report
 
RIGID PAVEMENT -ANIL GUPTA (P.W.D)
RIGID PAVEMENT -ANIL GUPTA (P.W.D)RIGID PAVEMENT -ANIL GUPTA (P.W.D)
RIGID PAVEMENT -ANIL GUPTA (P.W.D)
 
Rigid pavement
Rigid pavementRigid pavement
Rigid pavement
 
ROAD CONSTRUCTION (FLEXIBLE & RIGID) - SLIDES.pdf
ROAD CONSTRUCTION (FLEXIBLE & RIGID) - SLIDES.pdfROAD CONSTRUCTION (FLEXIBLE & RIGID) - SLIDES.pdf
ROAD CONSTRUCTION (FLEXIBLE & RIGID) - SLIDES.pdf
 
Construction of rigid pavement
Construction of rigid pavement Construction of rigid pavement
Construction of rigid pavement
 
CONSTRUCTION_OF_RIGID_PAVEMENT.pptx
CONSTRUCTION_OF_RIGID_PAVEMENT.pptxCONSTRUCTION_OF_RIGID_PAVEMENT.pptx
CONSTRUCTION_OF_RIGID_PAVEMENT.pptx
 
Anshuman.pptx
Anshuman.pptxAnshuman.pptx
Anshuman.pptx
 
Road construction ppt for college rajkiya presentation
Road construction ppt for college rajkiya presentationRoad construction ppt for college rajkiya presentation
Road construction ppt for college rajkiya presentation
 
Rigid pavement in Magallanes Interchange
Rigid pavement in Magallanes InterchangeRigid pavement in Magallanes Interchange
Rigid pavement in Magallanes Interchange
 
Geometric design of highway
Geometric design of  highwayGeometric design of  highway
Geometric design of highway
 
Roads & Pavements
Roads & PavementsRoads & Pavements
Roads & Pavements
 
Highway failure and their maintenance
Highway failure and their maintenanceHighway failure and their maintenance
Highway failure and their maintenance
 
PRESENTATION ON RIGID PAVEMExNT.pptx for
PRESENTATION ON RIGID PAVEMExNT.pptx forPRESENTATION ON RIGID PAVEMExNT.pptx for
PRESENTATION ON RIGID PAVEMExNT.pptx for
 
Mukesh ppt cc road
Mukesh ppt cc roadMukesh ppt cc road
Mukesh ppt cc road
 
Pavements PPT
 Pavements PPT  Pavements PPT
Pavements PPT
 
highway materials and desihn.pptx
highway materials and desihn.pptxhighway materials and desihn.pptx
highway materials and desihn.pptx
 
Types of pavement- Transportation Engg. I
Types of pavement- Transportation Engg. ITypes of pavement- Transportation Engg. I
Types of pavement- Transportation Engg. I
 
transportation
transportationtransportation
transportation
 

Recently uploaded

OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...Soham Mondal
 
Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024hassan khalil
 
HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICS
HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICSHARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICS
HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICSRajkumarAkumalla
 
IMPLICATIONS OF THE ABOVE HOLISTIC UNDERSTANDING OF HARMONY ON PROFESSIONAL E...
IMPLICATIONS OF THE ABOVE HOLISTIC UNDERSTANDING OF HARMONY ON PROFESSIONAL E...IMPLICATIONS OF THE ABOVE HOLISTIC UNDERSTANDING OF HARMONY ON PROFESSIONAL E...
IMPLICATIONS OF THE ABOVE HOLISTIC UNDERSTANDING OF HARMONY ON PROFESSIONAL E...RajaP95
 
College Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service NashikCollege Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service NashikCall Girls in Nagpur High Profile
 
Coefficient of Thermal Expansion and their Importance.pptx
Coefficient of Thermal Expansion and their Importance.pptxCoefficient of Thermal Expansion and their Importance.pptx
Coefficient of Thermal Expansion and their Importance.pptxAsutosh Ranjan
 
Call Girls Delhi {Jodhpur} 9711199012 high profile service
Call Girls Delhi {Jodhpur} 9711199012 high profile serviceCall Girls Delhi {Jodhpur} 9711199012 high profile service
Call Girls Delhi {Jodhpur} 9711199012 high profile servicerehmti665
 
SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )Tsuyoshi Horigome
 
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptxDecoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptxJoão Esperancinha
 
HARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IVHARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IVRajaP95
 
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...Dr.Costas Sachpazis
 
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Serviceranjana rawat
 
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur High Profile
 
Software Development Life Cycle By Team Orange (Dept. of Pharmacy)
Software Development Life Cycle By  Team Orange (Dept. of Pharmacy)Software Development Life Cycle By  Team Orange (Dept. of Pharmacy)
Software Development Life Cycle By Team Orange (Dept. of Pharmacy)Suman Mia
 
Porous Ceramics seminar and technical writing
Porous Ceramics seminar and technical writingPorous Ceramics seminar and technical writing
Porous Ceramics seminar and technical writingrakeshbaidya232001
 
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...ranjana rawat
 
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130Suhani Kapoor
 

Recently uploaded (20)

OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
 
Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024
 
HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICS
HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICSHARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICS
HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICS
 
IMPLICATIONS OF THE ABOVE HOLISTIC UNDERSTANDING OF HARMONY ON PROFESSIONAL E...
IMPLICATIONS OF THE ABOVE HOLISTIC UNDERSTANDING OF HARMONY ON PROFESSIONAL E...IMPLICATIONS OF THE ABOVE HOLISTIC UNDERSTANDING OF HARMONY ON PROFESSIONAL E...
IMPLICATIONS OF THE ABOVE HOLISTIC UNDERSTANDING OF HARMONY ON PROFESSIONAL E...
 
College Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service NashikCollege Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
 
Coefficient of Thermal Expansion and their Importance.pptx
Coefficient of Thermal Expansion and their Importance.pptxCoefficient of Thermal Expansion and their Importance.pptx
Coefficient of Thermal Expansion and their Importance.pptx
 
Call Girls Delhi {Jodhpur} 9711199012 high profile service
Call Girls Delhi {Jodhpur} 9711199012 high profile serviceCall Girls Delhi {Jodhpur} 9711199012 high profile service
Call Girls Delhi {Jodhpur} 9711199012 high profile service
 
SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )
 
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptxDecoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
 
HARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IVHARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IV
 
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
 
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service
 
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
 
Software Development Life Cycle By Team Orange (Dept. of Pharmacy)
Software Development Life Cycle By  Team Orange (Dept. of Pharmacy)Software Development Life Cycle By  Team Orange (Dept. of Pharmacy)
Software Development Life Cycle By Team Orange (Dept. of Pharmacy)
 
Porous Ceramics seminar and technical writing
Porous Ceramics seminar and technical writingPorous Ceramics seminar and technical writing
Porous Ceramics seminar and technical writing
 
DJARUM4D - SLOT GACOR ONLINE | SLOT DEMO ONLINE
DJARUM4D - SLOT GACOR ONLINE | SLOT DEMO ONLINEDJARUM4D - SLOT GACOR ONLINE | SLOT DEMO ONLINE
DJARUM4D - SLOT GACOR ONLINE | SLOT DEMO ONLINE
 
Exploring_Network_Security_with_JA3_by_Rakesh Seal.pptx
Exploring_Network_Security_with_JA3_by_Rakesh Seal.pptxExploring_Network_Security_with_JA3_by_Rakesh Seal.pptx
Exploring_Network_Security_with_JA3_by_Rakesh Seal.pptx
 
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
 
9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf
9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf
9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf
 
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
 

Construction of Road

  • 1. CONCRETE PAVEMENT CONSTRUCTION OF ROAD Presenters :Aman Shakya Vijay Kumar Sharma Ayush Maheshwari PRESENTING TO : Veerendra Kumar Shivhare CIVIL Dept. HCST
  • 2. INTRODUCTION  Development of a country depends on the connectivity of various places with adequate road network.  Roads constitute the most important mode of communication in areas where railways have not developed much.  India has one of the largest road networks in the world (over 3 million km at present).For the purpose of management and administration, roads in India are divided into the following five categories: • National Highways (NH) • State Highways (SH) • Major District Roads (MDR) • Other District Roads (ODR) • Village Roads (VR)
  • 3. WHAT IS ROAD PAVEMENT Pavement is finished with a hard smooth surface directly above the subgrade. It helped make roads durable and able to withstand traffic and the environment. One of the primary functions of pavement is load distribution.
  • 4. TYPES OF PAVEMENTS • There are various types of pavements depending upon the materials used; a briefs description of all types is given here- • FLEXIBLE PAVEMENT • Bitumen has been widely used in the construction of flexible pavements for a long time. This is the most convenient and simple type of construction. The cost of construction of single lane bituminous pavement varies from 20 to 30 lakhs per km in plain area. • Flexible pavement have-  Have low flexural strength  Load is transferred by grain to grain contact  Have low completion cost but repairing cost is high
  • 5. RIGID PAVEMENT • Rigid pavements, though costly in initial investment, are cheap in long run because of low maintenance costs, The cost of construction of single lane rigid pavement varies from 35 to 50 lakh per km in plain area, • Rigid pavement have-  Deformation in the sub grade is not transferred to subsequent layers  Design is based on flexural strength or slab action  Have high flexural strength  No such phenomenon of grain to grain load transfer exists  Have low repairing cost but completion cost is high  Low Maintenance Cost
  • 6. Difference b/w Flexible and Rigid Pavement in terms of load distribution In different layers Different layers in Flexible and Rigid Pavement
  • 7. Basic Components of a Concrete Pavement
  • 8. • Cement  Ordinary Portland cement (OPC) • Ordinary Portland cement and High Strength Ordinary Portland Cement are most widely used for concrete pavements.  Rapid hardening Portland cement • In general, this cement would be used only where time is a critical factor and the road is required to be opened to traffic at an earlier date than would be possible if Ordinary Portland Cement or High Strength Ordinary Portland Cement is used. MINERALS USED
  • 9. Aggregates • There are two types of Aggregates are used during construction of road i.e. Fine and Coarse Aggregate depending on requirements. • Maximum size of aggregate should not exceed 1/4th of the pavement slab thickness. Water • Water used in mixing or curing of concrete shall be clean and free from injurious amounts of oil, salt, acid, vegetable matter or other substances harmful to the finished concrete. Mineral used( cont.)
  • 10. A list of tools, equipment and appliances required for the different phases of concrete road construction is given below  Three wheeled or vibratory roller for compaction purpose  Shovels, spades and Sieving screens  Concrete mixer for mixing of concrete  Formwork and iron stakes  Watering devices - Water Lorries, water carriers or watering cans  Wooden hand tampers for concrete compaction  Cycle pump/pneumatic air blower for cleaning of joint  Mild steel sections and blocks for making joint grooves for finishing purpose Equipments used
  • 11. Before construction begins, the construction site must be carefully prepared, This includes preparing the grade or road base, sub grade and sub base-  First the site is graded to cut high points and fill low areas to the desired roadway profile elevations.  Generally, cut material can be used as embankment fill.  A course of material is placed on the sub grade to provide drainage and stability.  A course of fairly rigid material, sometimes cement- or asphalt-treated, that is placed on the sub base to provide a stable platform for the concrete pavement slab. Site Preparation
  • 12. Construction Process Wooden sheets, battens, plywood, fibre hard board, steel plates, angles, rope etc are generally use for form work.  before using form work, it should free from all type material like as dust ,cement.  To placing the concrete in appropriate depth used 2.5-5cm thick and 3mtr long wooden sheeting  The depth of wooden block must be same as level of slab thick.  After 24hrs, form work displaced next length of road. FORM WORK After site preparation, Construction process consists of various steps, which are described below-
  • 13. Watering of base If the base of the road is dry or construction is taken place during summer seasons Then watering is done using the sprinkling process, after this concrete should be Placed. Construction of Joints • There are three basic joint types used in concrete pavement: contraction, construction and isolation. • Except for some isolation joints, all joints provide a means to mechanically connect slabs. The connection helps to spread a load applied on one slab onto slabs along its perimeter. • Where it is necessary to provide transverse and Longitudinal joints; there wedge of woods, metals fix on level of concrete. • After setting of concrete it should be pull out.
  • 14. PLACING OF CONCRETE Two methods generally used in placing of concrete- 1- Alternate bay method- Placed the concrete on both side of road alternatively like as1,3,5… part at one side and 2,4,6… part other side, This method have slow process due to road traffic problems. 2- Continuous bay method- Construct one side of road regularly, and after construction of some part of first side than construct other side, this method have fast process without no obstruction of traffic
  • 15. COMPACTION OF CONCRETE Purpose of compaction is that to pull out air from void and make concrete harden. Compaction done by- 1.Mechanically surface vibrator 2. Manually hand tempers  After this, Floating, Belting, Screeding or strike off, Bull floating and Brooming is done as per requirement for the finishing purpose of concrete pavement to smoothen the top surface. CURING After completion of the finishing operations, the surface of the pavement shall be entirely covered with wet hessian cloth, burlap or jute mats Curing is the process of increasing the hydration of cement, after setting the concrete curing process done till 14-28days.