SlideShare a Scribd company logo
Estimation and Costing
RATE ANALYSIS
Submitted By Submitted to
Vansheika (202601) Er. Akash Bhardwaj
RATE ANALYSIS
“ The determination of rate per unit of a particular item of work, from the
cost of quantities of materials, the cost of labourers and other miscellaneous
petty expenses required for its completion is known as the analysis of rates.”
In order to determine the rate of a particular item, the factors affecting
the rate of that item are studied carefully and then finally a rate is
decided for that item.
PURPOSE OF RATE ANALYSIS
•To work out the actual cost of per unit of the items.
•To work out the economical use of materials and processes in completing a
particular item.
•To work out the cost of extra items which are not provided in the contract bond,
but are to be done as per the directions of the department.
•To revise the schedule of rates due to increase in the cost of material and labour
or due to change in technique.
FACTORS AFFECTING RATE ANALYSIS
1. Specification of works and material, quality of materials, proportion of mortar
method of construction and operation.
2. Quantities of materials and their rates
3. Number of different types of labourer and their rates.
4. Location of site of work and its distance from the sources of materials and the
rates of transport, availability of water.
5. Profit and miscellaneous and overhead expenses of contractor.
How is a new unit rate defined?
The starting point to define the new unit rate, is to run a careful analysis of
the elements and resources that build up to form the new work item.
The elementary components, or resources, are generally the following:
• workforce
• materials
• hired equipment
• overheads
• company profits
Labor & Materials
The cost of labor is defined by the type of workers (specialized, qualified operators)
and the hours of work necessary per quantity unit.
To define the cost of the necessary materials, you need to determine the following:
• the purchase price
• on-site transport costs
• unloading
• stacking and storage
• waste (an excess percentage of unwanted material due to the production
processes)
OVERHEAD COSTS
• It includes general office expense, rents, taxes, supervision and other costs which are indirect
expense and not productive expense of job.
• The miscellaneous expense on overheads may be under the following heads;
A.General overheads
1. Establishment (office staff)
2. Stationary, printing, postages etc.
3. Travelling expense
4. Telephone
5. Rent and Taxes
OVERHEAD COSTS
B. Job overheads
1. Supervision (salary of Engg., Overseers, Supervision etc.)
2. Handling of materials
3. Repairs, carriage and depreciation of T&P
4. Amenities of labour
5. Workmen’s compensation and insurance
6. Interest on investment
7. Losses on advances
Note*
• The contractor may allowed to have a net profit of 6%-8%
• The miscellaneous overheads expenses may come to about 5%-10%
• Total 15% of the actual cost may be reasonable amount but it is usually practice to add
10%.
• 1.5% of water charges is also added
• If material has to be transported from more than 8km than transportation cost should
be calculated separately.
• 10% should be extra added to contractors profit if cement and steel has to be arranged
by him.
Lead statement
• The distance between the source of availability of material and construction site is
known as "Lead " and is expected in Km.
• The cost of conveyance of material depends on lead.
• This statement will give the total cost of materials per unit item. It includes first
cost, conveyance loading, unloading stacking, charges etc.
TASK OR TURN-OUT WORK
• Task : the capacity of doing work by an artisan or skilled labour in the form of quantity of work
per day.
• It varies to some extent according to the nature, size, height, situation, location etc.
example
For the excavation of foundation of a building. 4 labours worked out for 2 days and total quantity of
earthwork was 24cu.mt.
So total labours worked = 2 x 4 = 8 Nos
Task of one labour = 24/8 = 3 cu.mt.
Calculations of Quantities
Concrete work
For 1 m3 of wet concrete, dry volume is taken about 52% more
That is 1 m3 of wet concrete = 1.52 m3 of dry concrete
Quantity of materials for 1: 2 : 4 cement concrete
Proportion 1: 2 : 4 C : S : A Total = 7
Cement 1/7x 1.52 0.21714/0.035 6.204 say 7nos. of bags
Sand 2/7 x 1.52 0.434 m3
Aggregate 4/7 x 1.52 0.868 m3
Rate analysis of RCC ( 1:2:4 ) for slab – 10 m3
(A) Material required
Sr Type of material Quantity Rate Per Amount
1 Cement
Q=1/7 x 10 x 1.52 = 2.17 / 0.035
62 280 bags 17360
2 Sand
Q= 2/7 x 10 x 1.52
4.34 1200 m3 5208
3 Course Agg.
Q= 4/7 x 10 x 1.52
8.68 1100 m3 9548
4 Steel (1%) 785 50 Kg 39250
5 Binding wire 8 35 Kg 280
4 Miscellaneous - - Lump sum 100
Total (A) 71,746
Rate analysis of RCC ( 1:2:4 ) for slab – 10 m3
(B) Labour required
Sr Type Quantity Rate Per Amount
1 Head mason 1 500 day 500
2 Mason (Mixing, Trans., Placement) 10 350 day 3500
3 Mason (binding, bending) 9 250 day 2250
4 Mason (centering ,shuttering) Lump sum 5000
6 Rent for Equp. (2000 Rs) Lump sum 2000
Total (B) 13,250
Total ( A + B ) = Rs. 84,996
Add 1.5% of water charges = Rs. 1275
Add 10% of contractor’s profit = Rs. 8500
Rate for 10.0 m3 = Rs. 94,771
Rate for 1.0 m3 = Rs. 9,477

More Related Content

What's hot

Rate analysis
Rate analysisRate analysis
Rate analysis
DhavalMithaiwala
 
114 site layout
114 site layout114 site layout
114 site layout
Dr Fereidoun Dejahang
 
Types of estimates
Types of estimatesTypes of estimates
Types of estimates
Simarpreet Singh
 
Estimating and-costing
Estimating and-costingEstimating and-costing
Estimating and-costing
Aishwarya Deopujari
 
Types of Contract in Construction Management
Types of Contract in Construction ManagementTypes of Contract in Construction Management
Types of Contract in Construction Management
Shahin MB
 
Rates Analysis For Calculating Material and Labour for building works
Rates Analysis For Calculating Material and Labour for building works  Rates Analysis For Calculating Material and Labour for building works
Rates Analysis For Calculating Material and Labour for building works ALI HYDER GADHI
 
Estimation and costing of a commercial building
Estimation and costing of a commercial buildingEstimation and costing of a commercial building
Estimation and costing of a commercial building
lckr117
 
ESTIMATING AND COSTING
ESTIMATING AND COSTINGESTIMATING AND COSTING
ESTIMATING AND COSTING
Namrata Agnihotri
 
estimation,its types and methods
estimation,its types and methodsestimation,its types and methods
estimation,its types and methods
gayu pandian
 
District schedule rates (DSR), specification of items of work as per PWD
District schedule rates (DSR), specification of items of work as per PWDDistrict schedule rates (DSR), specification of items of work as per PWD
District schedule rates (DSR), specification of items of work as per PWD
AshwiniChaudhari13
 
rate analysis
rate analysisrate analysis
rate analysis
Ganesh Tatikonda
 
Estimating part 1
Estimating part 1Estimating part 1
Estimating part 1
ArunRavi43
 
Specifications of buildings
Specifications of buildingsSpecifications of buildings
Specifications of buildings
Simarpreet Singh
 
IMPORTANCE & PURPOSES OF SPECIFICATION
IMPORTANCE & PURPOSES OF SPECIFICATIONIMPORTANCE & PURPOSES OF SPECIFICATION
IMPORTANCE & PURPOSES OF SPECIFICATION
Sagar Kaptan
 
Different rolled steel bars and sections
Different rolled steel bars and sectionsDifferent rolled steel bars and sections
Different rolled steel bars and sections
skytechmetals
 
Introduction-construction management_Construction Management (2180611) (Semes...
Introduction-construction management_Construction Management (2180611) (Semes...Introduction-construction management_Construction Management (2180611) (Semes...
Introduction-construction management_Construction Management (2180611) (Semes...
A Makwana
 
Earth work equipment
Earth work equipmentEarth work equipment
Earth work equipment
swetha110
 
Types of tender and their processing.
Types of tender and their processing.Types of tender and their processing.
Types of tender and their processing.
Abhishek kumar maurya
 

What's hot (20)

Rate analysis
Rate analysisRate analysis
Rate analysis
 
114 site layout
114 site layout114 site layout
114 site layout
 
Types of estimates
Types of estimatesTypes of estimates
Types of estimates
 
Estimating and-costing
Estimating and-costingEstimating and-costing
Estimating and-costing
 
Types of Contract in Construction Management
Types of Contract in Construction ManagementTypes of Contract in Construction Management
Types of Contract in Construction Management
 
Rates Analysis For Calculating Material and Labour for building works
Rates Analysis For Calculating Material and Labour for building works  Rates Analysis For Calculating Material and Labour for building works
Rates Analysis For Calculating Material and Labour for building works
 
Estimation and costing of a commercial building
Estimation and costing of a commercial buildingEstimation and costing of a commercial building
Estimation and costing of a commercial building
 
ESTIMATING AND COSTING
ESTIMATING AND COSTINGESTIMATING AND COSTING
ESTIMATING AND COSTING
 
estimation,its types and methods
estimation,its types and methodsestimation,its types and methods
estimation,its types and methods
 
District schedule rates (DSR), specification of items of work as per PWD
District schedule rates (DSR), specification of items of work as per PWDDistrict schedule rates (DSR), specification of items of work as per PWD
District schedule rates (DSR), specification of items of work as per PWD
 
rate analysis
rate analysisrate analysis
rate analysis
 
Estimating part 1
Estimating part 1Estimating part 1
Estimating part 1
 
Specifications of buildings
Specifications of buildingsSpecifications of buildings
Specifications of buildings
 
Bar chart
Bar chartBar chart
Bar chart
 
IMPORTANCE & PURPOSES OF SPECIFICATION
IMPORTANCE & PURPOSES OF SPECIFICATIONIMPORTANCE & PURPOSES OF SPECIFICATION
IMPORTANCE & PURPOSES OF SPECIFICATION
 
Different rolled steel bars and sections
Different rolled steel bars and sectionsDifferent rolled steel bars and sections
Different rolled steel bars and sections
 
Composite slab
Composite slabComposite slab
Composite slab
 
Introduction-construction management_Construction Management (2180611) (Semes...
Introduction-construction management_Construction Management (2180611) (Semes...Introduction-construction management_Construction Management (2180611) (Semes...
Introduction-construction management_Construction Management (2180611) (Semes...
 
Earth work equipment
Earth work equipmentEarth work equipment
Earth work equipment
 
Types of tender and their processing.
Types of tender and their processing.Types of tender and their processing.
Types of tender and their processing.
 

Similar to Rate analysis vansheika

UNIT 2.pptx
UNIT 2.pptxUNIT 2.pptx
UNIT 2.pptx
AkashM725543
 
Analyis of Rate MODULE VI October 2022.pptx
Analyis of Rate  MODULE VI October 2022.pptxAnalyis of Rate  MODULE VI October 2022.pptx
Analyis of Rate MODULE VI October 2022.pptx
rekhat26
 
Analysis of rates
Analysis of ratesAnalysis of rates
Analysis of rates
vikrant prajapati
 
Notes on Estimation.ppt
Notes on Estimation.pptNotes on Estimation.ppt
Notes on Estimation.ppt
ashoklalwani6
 
Section 3-2.pptx
Section 3-2.pptxSection 3-2.pptx
Section 3-2.pptx
kareemhamad3
 
3.estimating
3.estimating3.estimating
ESTIMATION_AND_COSTING assignmentt-1.pdf
ESTIMATION_AND_COSTING assignmentt-1.pdfESTIMATION_AND_COSTING assignmentt-1.pdf
ESTIMATION_AND_COSTING assignmentt-1.pdf
suchitamantry2002
 
CPM 1 .pdf
CPM 1 .pdfCPM 1 .pdf
CPM 1 .pdf
MD RUKHASAR ALAM
 
Lecture -4.pptxTender & Tender Notice bfh
Lecture -4.pptxTender & Tender Notice bfhLecture -4.pptxTender & Tender Notice bfh
Lecture -4.pptxTender & Tender Notice bfh
2cd
 
Unit 3
Unit 3Unit 3
Unit 3
Aravind Ra
 
INTRODUCTION TO COST ESTIMATION
INTRODUCTION TO COST ESTIMATIONINTRODUCTION TO COST ESTIMATION
INTRODUCTION TO COST ESTIMATION
DJAGADEESH1
 
PPCE UNIT- 3.pptx
PPCE UNIT- 3.pptxPPCE UNIT- 3.pptx
PPCE UNIT- 3.pptx
Aravind Ra
 
Introduction to Quantity Surveying .pptx
Introduction to Quantity Surveying .pptxIntroduction to Quantity Surveying .pptx
Introduction to Quantity Surveying .pptx
NSHYAMANANDASINGH
 
INTRODUCTION TO COST ESTIMATION
INTRODUCTION TO COST ESTIMATIONINTRODUCTION TO COST ESTIMATION
INTRODUCTION TO COST ESTIMATION
SathishkumarM89
 
PPCE Unit-3.pptx
PPCE Unit-3.pptxPPCE Unit-3.pptx
PPCE Unit-3.pptx
DJAGADEESH1
 
PPCE Unit-3.pptx
PPCE Unit-3.pptxPPCE Unit-3.pptx
PPCE Unit-3.pptx
Dr.PERIASAMY K
 
Estimation Costing and Valuation Unit 1 to Unit 6
Estimation Costing and Valuation Unit 1 to Unit 6Estimation Costing and Valuation Unit 1 to Unit 6
Estimation Costing and Valuation Unit 1 to Unit 6
Padmasinh Patil
 
Estimation and costing book
Estimation and costing bookEstimation and costing book
Estimation and costing book
Subash Pathak
 
EstimationandCosting.ppt
EstimationandCosting.pptEstimationandCosting.ppt
EstimationandCosting.ppt
BALAMURUGANR53
 

Similar to Rate analysis vansheika (20)

UNIT 2.pptx
UNIT 2.pptxUNIT 2.pptx
UNIT 2.pptx
 
Analyis of Rate MODULE VI October 2022.pptx
Analyis of Rate  MODULE VI October 2022.pptxAnalyis of Rate  MODULE VI October 2022.pptx
Analyis of Rate MODULE VI October 2022.pptx
 
Analysis of rates
Analysis of ratesAnalysis of rates
Analysis of rates
 
Notes on Estimation.ppt
Notes on Estimation.pptNotes on Estimation.ppt
Notes on Estimation.ppt
 
CEE 6.pptx
CEE 6.pptxCEE 6.pptx
CEE 6.pptx
 
Section 3-2.pptx
Section 3-2.pptxSection 3-2.pptx
Section 3-2.pptx
 
3.estimating
3.estimating3.estimating
3.estimating
 
ESTIMATION_AND_COSTING assignmentt-1.pdf
ESTIMATION_AND_COSTING assignmentt-1.pdfESTIMATION_AND_COSTING assignmentt-1.pdf
ESTIMATION_AND_COSTING assignmentt-1.pdf
 
CPM 1 .pdf
CPM 1 .pdfCPM 1 .pdf
CPM 1 .pdf
 
Lecture -4.pptxTender & Tender Notice bfh
Lecture -4.pptxTender & Tender Notice bfhLecture -4.pptxTender & Tender Notice bfh
Lecture -4.pptxTender & Tender Notice bfh
 
Unit 3
Unit 3Unit 3
Unit 3
 
INTRODUCTION TO COST ESTIMATION
INTRODUCTION TO COST ESTIMATIONINTRODUCTION TO COST ESTIMATION
INTRODUCTION TO COST ESTIMATION
 
PPCE UNIT- 3.pptx
PPCE UNIT- 3.pptxPPCE UNIT- 3.pptx
PPCE UNIT- 3.pptx
 
Introduction to Quantity Surveying .pptx
Introduction to Quantity Surveying .pptxIntroduction to Quantity Surveying .pptx
Introduction to Quantity Surveying .pptx
 
INTRODUCTION TO COST ESTIMATION
INTRODUCTION TO COST ESTIMATIONINTRODUCTION TO COST ESTIMATION
INTRODUCTION TO COST ESTIMATION
 
PPCE Unit-3.pptx
PPCE Unit-3.pptxPPCE Unit-3.pptx
PPCE Unit-3.pptx
 
PPCE Unit-3.pptx
PPCE Unit-3.pptxPPCE Unit-3.pptx
PPCE Unit-3.pptx
 
Estimation Costing and Valuation Unit 1 to Unit 6
Estimation Costing and Valuation Unit 1 to Unit 6Estimation Costing and Valuation Unit 1 to Unit 6
Estimation Costing and Valuation Unit 1 to Unit 6
 
Estimation and costing book
Estimation and costing bookEstimation and costing book
Estimation and costing book
 
EstimationandCosting.ppt
EstimationandCosting.pptEstimationandCosting.ppt
EstimationandCosting.ppt
 

Recently uploaded

CW RADAR, FMCW RADAR, FMCW ALTIMETER, AND THEIR PARAMETERS
CW RADAR, FMCW RADAR, FMCW ALTIMETER, AND THEIR PARAMETERSCW RADAR, FMCW RADAR, FMCW ALTIMETER, AND THEIR PARAMETERS
CW RADAR, FMCW RADAR, FMCW ALTIMETER, AND THEIR PARAMETERS
veerababupersonal22
 
DfMAy 2024 - key insights and contributions
DfMAy 2024 - key insights and contributionsDfMAy 2024 - key insights and contributions
DfMAy 2024 - key insights and contributions
gestioneergodomus
 
MCQ Soil mechanics questions (Soil shear strength).pdf
MCQ Soil mechanics questions (Soil shear strength).pdfMCQ Soil mechanics questions (Soil shear strength).pdf
MCQ Soil mechanics questions (Soil shear strength).pdf
Osamah Alsalih
 
Governing Equations for Fundamental Aerodynamics_Anderson2010.pdf
Governing Equations for Fundamental Aerodynamics_Anderson2010.pdfGoverning Equations for Fundamental Aerodynamics_Anderson2010.pdf
Governing Equations for Fundamental Aerodynamics_Anderson2010.pdf
WENKENLI1
 
Railway Signalling Principles Edition 3.pdf
Railway Signalling Principles Edition 3.pdfRailway Signalling Principles Edition 3.pdf
Railway Signalling Principles Edition 3.pdf
TeeVichai
 
Water Industry Process Automation and Control Monthly - May 2024.pdf
Water Industry Process Automation and Control Monthly - May 2024.pdfWater Industry Process Automation and Control Monthly - May 2024.pdf
Water Industry Process Automation and Control Monthly - May 2024.pdf
Water Industry Process Automation & Control
 
14 Template Contractual Notice - EOT Application
14 Template Contractual Notice - EOT Application14 Template Contractual Notice - EOT Application
14 Template Contractual Notice - EOT Application
SyedAbiiAzazi1
 
Standard Reomte Control Interface - Neometrix
Standard Reomte Control Interface - NeometrixStandard Reomte Control Interface - Neometrix
Standard Reomte Control Interface - Neometrix
Neometrix_Engineering_Pvt_Ltd
 
Fundamentals of Electric Drives and its applications.pptx
Fundamentals of Electric Drives and its applications.pptxFundamentals of Electric Drives and its applications.pptx
Fundamentals of Electric Drives and its applications.pptx
manasideore6
 
一比一原版(SFU毕业证)西蒙菲莎大学毕业证成绩单如何办理
一比一原版(SFU毕业证)西蒙菲莎大学毕业证成绩单如何办理一比一原版(SFU毕业证)西蒙菲莎大学毕业证成绩单如何办理
一比一原版(SFU毕业证)西蒙菲莎大学毕业证成绩单如何办理
bakpo1
 
Final project report on grocery store management system..pdf
Final project report on grocery store management system..pdfFinal project report on grocery store management system..pdf
Final project report on grocery store management system..pdf
Kamal Acharya
 
Unbalanced Three Phase Systems and circuits.pptx
Unbalanced Three Phase Systems and circuits.pptxUnbalanced Three Phase Systems and circuits.pptx
Unbalanced Three Phase Systems and circuits.pptx
ChristineTorrepenida1
 
一比一原版(IIT毕业证)伊利诺伊理工大学毕业证成绩单专业办理
一比一原版(IIT毕业证)伊利诺伊理工大学毕业证成绩单专业办理一比一原版(IIT毕业证)伊利诺伊理工大学毕业证成绩单专业办理
一比一原版(IIT毕业证)伊利诺伊理工大学毕业证成绩单专业办理
zwunae
 
HYDROPOWER - Hydroelectric power generation
HYDROPOWER - Hydroelectric power generationHYDROPOWER - Hydroelectric power generation
HYDROPOWER - Hydroelectric power generation
Robbie Edward Sayers
 
Nuclear Power Economics and Structuring 2024
Nuclear Power Economics and Structuring 2024Nuclear Power Economics and Structuring 2024
Nuclear Power Economics and Structuring 2024
Massimo Talia
 
road safety engineering r s e unit 3.pdf
road safety engineering  r s e unit 3.pdfroad safety engineering  r s e unit 3.pdf
road safety engineering r s e unit 3.pdf
VENKATESHvenky89705
 
Industrial Training at Shahjalal Fertilizer Company Limited (SFCL)
Industrial Training at Shahjalal Fertilizer Company Limited (SFCL)Industrial Training at Shahjalal Fertilizer Company Limited (SFCL)
Industrial Training at Shahjalal Fertilizer Company Limited (SFCL)
MdTanvirMahtab2
 
Gen AI Study Jams _ For the GDSC Leads in India.pdf
Gen AI Study Jams _ For the GDSC Leads in India.pdfGen AI Study Jams _ For the GDSC Leads in India.pdf
Gen AI Study Jams _ For the GDSC Leads in India.pdf
gdsczhcet
 
AKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdf
AKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdfAKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdf
AKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdf
SamSarthak3
 
block diagram and signal flow graph representation
block diagram and signal flow graph representationblock diagram and signal flow graph representation
block diagram and signal flow graph representation
Divya Somashekar
 

Recently uploaded (20)

CW RADAR, FMCW RADAR, FMCW ALTIMETER, AND THEIR PARAMETERS
CW RADAR, FMCW RADAR, FMCW ALTIMETER, AND THEIR PARAMETERSCW RADAR, FMCW RADAR, FMCW ALTIMETER, AND THEIR PARAMETERS
CW RADAR, FMCW RADAR, FMCW ALTIMETER, AND THEIR PARAMETERS
 
DfMAy 2024 - key insights and contributions
DfMAy 2024 - key insights and contributionsDfMAy 2024 - key insights and contributions
DfMAy 2024 - key insights and contributions
 
MCQ Soil mechanics questions (Soil shear strength).pdf
MCQ Soil mechanics questions (Soil shear strength).pdfMCQ Soil mechanics questions (Soil shear strength).pdf
MCQ Soil mechanics questions (Soil shear strength).pdf
 
Governing Equations for Fundamental Aerodynamics_Anderson2010.pdf
Governing Equations for Fundamental Aerodynamics_Anderson2010.pdfGoverning Equations for Fundamental Aerodynamics_Anderson2010.pdf
Governing Equations for Fundamental Aerodynamics_Anderson2010.pdf
 
Railway Signalling Principles Edition 3.pdf
Railway Signalling Principles Edition 3.pdfRailway Signalling Principles Edition 3.pdf
Railway Signalling Principles Edition 3.pdf
 
Water Industry Process Automation and Control Monthly - May 2024.pdf
Water Industry Process Automation and Control Monthly - May 2024.pdfWater Industry Process Automation and Control Monthly - May 2024.pdf
Water Industry Process Automation and Control Monthly - May 2024.pdf
 
14 Template Contractual Notice - EOT Application
14 Template Contractual Notice - EOT Application14 Template Contractual Notice - EOT Application
14 Template Contractual Notice - EOT Application
 
Standard Reomte Control Interface - Neometrix
Standard Reomte Control Interface - NeometrixStandard Reomte Control Interface - Neometrix
Standard Reomte Control Interface - Neometrix
 
Fundamentals of Electric Drives and its applications.pptx
Fundamentals of Electric Drives and its applications.pptxFundamentals of Electric Drives and its applications.pptx
Fundamentals of Electric Drives and its applications.pptx
 
一比一原版(SFU毕业证)西蒙菲莎大学毕业证成绩单如何办理
一比一原版(SFU毕业证)西蒙菲莎大学毕业证成绩单如何办理一比一原版(SFU毕业证)西蒙菲莎大学毕业证成绩单如何办理
一比一原版(SFU毕业证)西蒙菲莎大学毕业证成绩单如何办理
 
Final project report on grocery store management system..pdf
Final project report on grocery store management system..pdfFinal project report on grocery store management system..pdf
Final project report on grocery store management system..pdf
 
Unbalanced Three Phase Systems and circuits.pptx
Unbalanced Three Phase Systems and circuits.pptxUnbalanced Three Phase Systems and circuits.pptx
Unbalanced Three Phase Systems and circuits.pptx
 
一比一原版(IIT毕业证)伊利诺伊理工大学毕业证成绩单专业办理
一比一原版(IIT毕业证)伊利诺伊理工大学毕业证成绩单专业办理一比一原版(IIT毕业证)伊利诺伊理工大学毕业证成绩单专业办理
一比一原版(IIT毕业证)伊利诺伊理工大学毕业证成绩单专业办理
 
HYDROPOWER - Hydroelectric power generation
HYDROPOWER - Hydroelectric power generationHYDROPOWER - Hydroelectric power generation
HYDROPOWER - Hydroelectric power generation
 
Nuclear Power Economics and Structuring 2024
Nuclear Power Economics and Structuring 2024Nuclear Power Economics and Structuring 2024
Nuclear Power Economics and Structuring 2024
 
road safety engineering r s e unit 3.pdf
road safety engineering  r s e unit 3.pdfroad safety engineering  r s e unit 3.pdf
road safety engineering r s e unit 3.pdf
 
Industrial Training at Shahjalal Fertilizer Company Limited (SFCL)
Industrial Training at Shahjalal Fertilizer Company Limited (SFCL)Industrial Training at Shahjalal Fertilizer Company Limited (SFCL)
Industrial Training at Shahjalal Fertilizer Company Limited (SFCL)
 
Gen AI Study Jams _ For the GDSC Leads in India.pdf
Gen AI Study Jams _ For the GDSC Leads in India.pdfGen AI Study Jams _ For the GDSC Leads in India.pdf
Gen AI Study Jams _ For the GDSC Leads in India.pdf
 
AKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdf
AKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdfAKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdf
AKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdf
 
block diagram and signal flow graph representation
block diagram and signal flow graph representationblock diagram and signal flow graph representation
block diagram and signal flow graph representation
 

Rate analysis vansheika

  • 1. Estimation and Costing RATE ANALYSIS Submitted By Submitted to Vansheika (202601) Er. Akash Bhardwaj
  • 2. RATE ANALYSIS “ The determination of rate per unit of a particular item of work, from the cost of quantities of materials, the cost of labourers and other miscellaneous petty expenses required for its completion is known as the analysis of rates.” In order to determine the rate of a particular item, the factors affecting the rate of that item are studied carefully and then finally a rate is decided for that item.
  • 3. PURPOSE OF RATE ANALYSIS •To work out the actual cost of per unit of the items. •To work out the economical use of materials and processes in completing a particular item. •To work out the cost of extra items which are not provided in the contract bond, but are to be done as per the directions of the department. •To revise the schedule of rates due to increase in the cost of material and labour or due to change in technique.
  • 4. FACTORS AFFECTING RATE ANALYSIS 1. Specification of works and material, quality of materials, proportion of mortar method of construction and operation. 2. Quantities of materials and their rates 3. Number of different types of labourer and their rates. 4. Location of site of work and its distance from the sources of materials and the rates of transport, availability of water. 5. Profit and miscellaneous and overhead expenses of contractor.
  • 5. How is a new unit rate defined? The starting point to define the new unit rate, is to run a careful analysis of the elements and resources that build up to form the new work item. The elementary components, or resources, are generally the following: • workforce • materials • hired equipment • overheads • company profits
  • 6. Labor & Materials The cost of labor is defined by the type of workers (specialized, qualified operators) and the hours of work necessary per quantity unit. To define the cost of the necessary materials, you need to determine the following: • the purchase price • on-site transport costs • unloading • stacking and storage • waste (an excess percentage of unwanted material due to the production processes)
  • 7. OVERHEAD COSTS • It includes general office expense, rents, taxes, supervision and other costs which are indirect expense and not productive expense of job. • The miscellaneous expense on overheads may be under the following heads; A.General overheads 1. Establishment (office staff) 2. Stationary, printing, postages etc. 3. Travelling expense 4. Telephone 5. Rent and Taxes
  • 8. OVERHEAD COSTS B. Job overheads 1. Supervision (salary of Engg., Overseers, Supervision etc.) 2. Handling of materials 3. Repairs, carriage and depreciation of T&P 4. Amenities of labour 5. Workmen’s compensation and insurance 6. Interest on investment 7. Losses on advances
  • 9. Note* • The contractor may allowed to have a net profit of 6%-8% • The miscellaneous overheads expenses may come to about 5%-10% • Total 15% of the actual cost may be reasonable amount but it is usually practice to add 10%. • 1.5% of water charges is also added • If material has to be transported from more than 8km than transportation cost should be calculated separately. • 10% should be extra added to contractors profit if cement and steel has to be arranged by him.
  • 10. Lead statement • The distance between the source of availability of material and construction site is known as "Lead " and is expected in Km. • The cost of conveyance of material depends on lead. • This statement will give the total cost of materials per unit item. It includes first cost, conveyance loading, unloading stacking, charges etc.
  • 11. TASK OR TURN-OUT WORK • Task : the capacity of doing work by an artisan or skilled labour in the form of quantity of work per day. • It varies to some extent according to the nature, size, height, situation, location etc. example For the excavation of foundation of a building. 4 labours worked out for 2 days and total quantity of earthwork was 24cu.mt. So total labours worked = 2 x 4 = 8 Nos Task of one labour = 24/8 = 3 cu.mt.
  • 12. Calculations of Quantities Concrete work For 1 m3 of wet concrete, dry volume is taken about 52% more That is 1 m3 of wet concrete = 1.52 m3 of dry concrete Quantity of materials for 1: 2 : 4 cement concrete Proportion 1: 2 : 4 C : S : A Total = 7 Cement 1/7x 1.52 0.21714/0.035 6.204 say 7nos. of bags Sand 2/7 x 1.52 0.434 m3 Aggregate 4/7 x 1.52 0.868 m3
  • 13. Rate analysis of RCC ( 1:2:4 ) for slab – 10 m3 (A) Material required Sr Type of material Quantity Rate Per Amount 1 Cement Q=1/7 x 10 x 1.52 = 2.17 / 0.035 62 280 bags 17360 2 Sand Q= 2/7 x 10 x 1.52 4.34 1200 m3 5208 3 Course Agg. Q= 4/7 x 10 x 1.52 8.68 1100 m3 9548 4 Steel (1%) 785 50 Kg 39250 5 Binding wire 8 35 Kg 280 4 Miscellaneous - - Lump sum 100 Total (A) 71,746
  • 14. Rate analysis of RCC ( 1:2:4 ) for slab – 10 m3 (B) Labour required Sr Type Quantity Rate Per Amount 1 Head mason 1 500 day 500 2 Mason (Mixing, Trans., Placement) 10 350 day 3500 3 Mason (binding, bending) 9 250 day 2250 4 Mason (centering ,shuttering) Lump sum 5000 6 Rent for Equp. (2000 Rs) Lump sum 2000 Total (B) 13,250 Total ( A + B ) = Rs. 84,996 Add 1.5% of water charges = Rs. 1275 Add 10% of contractor’s profit = Rs. 8500 Rate for 10.0 m3 = Rs. 94,771 Rate for 1.0 m3 = Rs. 9,477