factors affecting rate analysis for various items.pptx
1.
Er.A.B.Jadhav 90750
09500
Estimating andCosting
Factors affecting the Rate analysis forVarious Items of
Construction in Civil Engineering
1
SHARAD INSTITUTE OF TECHNOLOGY,
COLLEGE OF ENGINEERING,YADRAV
2.
Er.A.B.Jadhav 90750
09500
Factors AffectingRate Analysis
2
Rate analysis is the process of determining the cost per unit of
an item of work, considering all associated expenses. Several
factors influence rate analysis, which can be broadly classified
into technical, labor-related, material-related, and external
factors.
1. Material Cost
Type, quality, and quantity of materials required
Source of procurement and transportation cost
Market fluctuations in material prices
Wastage and handling losses
3.
Er.A.B.Jadhav 90750
09500
Factors AffectingRate Analysis
3
2. Labor Cost
Type of skilled, semi-skilled, and unskilled labor required
Wage rates based on location, government regulations, and trade
unions
Productivity and efficiency of labor
Working conditions and site constraints
3. Equipment and Machinery Cost
Type and size of machinery required
Ownership cost (depreciation, interest, maintenance) or rental cost
Fuel, power, and lubricants consumption
Operator wages and maintenance cost
4.
Er.A.B.Jadhav 90750
09500
Factors AffectingRate Analysis
4
4. Transportation Cost
Distance of material sources from the site
Mode of transportation and handling charges
Site accessibility and road conditions
5. Site Conditions and Location
Nature of the soil and site topography
Availability of water, electricity, and storage space
Climatic conditions affecting work progress
5.
Er.A.B.Jadhav 90750
09500
Factors AffectingRate Analysis
5
6. Overheads and Contingencies
Establishment charges (office expenses, staff salaries, etc.)
Contractor’s profit margin
Insurance, permits, and legal fees
Contingency provisions for unforeseen costs
7. Government Regulations and Taxes
GST, VAT, excise duty, and import duties on materials
Minimum wages act, labor welfare laws, and safety regulations
Environmental and pollution control norms
6.
Er.A.B.Jadhav 90750
09500
Factors AffectingRate Analysis
6
8. Method of Execution and Work Efficiency
Manual or mechanized construction methods
Productivity of labor and equipment
Use of prefabrication or modular construction
9. Market Conditions and Inflation
Demand and supply of materials and labor
Seasonal variations affecting availability and cost
Inflation and price escalation trends
10. Contractual and Specification Requirements
Type of contract (item rate, lump sum, cost-plus, etc.)
Specification standards (IS codes, CPWD specifications, etc.)
Quality requirements and testing provisions