SlideShare a Scribd company logo
1 of 26
15-1
Lecture slides to accompany
Engineering Economy
7th
edition
Leland Blank
Anthony Tarquin
Chapter 15Chapter 15
Cost EstimationCost Estimation
and Indirectand Indirect
CostsCosts
© 2012 by McGraw-Hill All Rights Reserved
LEARNING OUTCOMES
© 2012 by McGraw-Hill All Rights Reserved15-2
1. Approaches to estimation
2. Unit method
3. Cost indexes
4. Cost-capacity equations
5. Factor method
6. Indirect cost rates and allocation
7. ABC allocation
8. Ethical considerations
Direct and Indirect Cost Estimates
© 2012 by McGraw-Hill All Rights Reserved15-3
Direct cost examples
• Physical assets
• Maintenance and operating
costs (M&O)
• Materials
• Direct human labor (costs
and benefits)
• Scrapped and reworked
product
• Direct supervision of
personnel
Indirect cost examples
• Utilities
• IT systems and networks
• Purchasing
• Management
• Taxes
• Legal functions
• Warranty and guarantees
• Quality assurance
• Accounting functions
• Marketing and publicity
What Direct Cost Estimation Includes
© 2012 by McGraw-Hill All Rights Reserved15-4
Direct costs are more commonly estimated than revenue in an
engineering environment. Preliminary decisions required are:
 What cost components should be estimated?
 What approach to estimation is best to apply?
 How accurate should the estimates be?
 What technique(s) will be applied to estimate costs?
Sample direct cost components: first costs and its elements
(P); annual costs (AOC or M&O); salvage/market value (S)
Approaches: bottom-up; design-to-cost (top down)
Accuracy: feasibility stage through detailed design estimates
require more exacting estimates
Some techniques: unit; factor; cost estimating relations (CER)
Different Approaches to Cost Estimation
© 2012 by McGraw-Hill All Rights Reserved15-5
Accuracy of Cost Estimates
© 2012 by McGraw-Hill All Rights Reserved15-6
Characteristic curve of accuracy vs. time to make estimates
General guidelines for accuracy
Conceptual/Feasibility stage – order-of-magnitude
estimates are in range of ±20% of actual costs
Detailed design stage - Detailed estimates are in
range of ±5% of actual costs
Unit Method
© 2012 by McGraw-Hill All Rights Reserved15-7
• Commonly used technique for preliminary design stage estimates
• Total cost estimate CT is per unit cost (u) times number of units (N)
CT = u × N
• Example uses:
 Cost to operate a car at 60¢/mile for 500 miles: CT = 0.60 × 500 = $300
 Cost to build a 250 m2
house at $2250/m2
: CT = 2250 × 250 = $562,500
• Cost factors must be updated periodically to remain timely
When several components are involved, estimate cost of each
component and add to determine total cost estimate CT
Cost Indexes
© 2012 by McGraw-Hill All Rights Reserved15-8
Definition: Cost Index is ratio of cost today to cost in the past
• Indicates change in cost over time; therefore, they account
for the impact of inflation
• Index is dimensionless
• CPI (Consumer Price Index) is a good example
Example: Cost Index Method
© 2012 by McGraw-Hill All Rights Reserved15-9
Problem: Estimate the total cost of labor today in US dollars for a
maritime construction project using data from a similar project in
Europe completed in 1998.
Labor index, 1998: 789.6 Cost in 1998: €3.9 million
Labor index, current: 1165.8 Currently, 1 € = 1.5 US$
Solution: Let t = today and 0 = 1998 base
Ct = 3.9 million × (1165.8/789.6) = €5.76 million
= €5.76 × 1.5 = $8.64 million
Finding Cost Indexes
© 2012 by McGraw-Hill All Rights Reserved15-10
Cost indexes are maintained in areas such as
construction, chemical and mechanical industries
• Updated monthly and annually; many include regionalized and
international project indexes
• Indexes in these areas are often subdivided into smaller
components and can be used in preliminary, as well as
detailed design stages
Examples are:
 Chemical Engineering Plant Cost Index (CEPCI)
www.che.com/pci
 McGraw-Hill Construction Index
www.construction.com
 US Department of Labor, Bureau of Labor Statistics
www.bls.gov
Cost-Estimating Relationships (CER)
© 2012 by McGraw-Hill All Rights Reserved15-11
 CER equations are used in early design stages to
estimate plant, equipment and construction costs
 CERs are generically different from index
relations,
because they estimate based on design variables
(weight, thrust, force, pressure, speed, etc.)
Two commonly used CERs
 Cost-capacity equation (relates cost to capacity)
 Factor method (total plant cost estimator, including
indirect costs)
Cost-Capacity Equation
© 2012 by McGraw-Hill All Rights Reserved15-12
Also called power law and sizing model
Exponent defines relation between capacities
x = 1, relationship is linear
x < 1, economies of scale (larger capacity is less costly than linear)
x > 1, diseconomies of scale
Cost-Capacity Combined with Cost Index
© 2012 by McGraw-Hill All Rights Reserved15-13
Example: A 100 hp air compressor costs $3000 five years ago when
the cost index was 130. Estimate the cost of a 300 hp compressor
today when the cost index is 255. The exponent for a 300 hp air
compressor is 0.9.
Solution: Let C300 represent the cost estimate today
C300 = 3000(300/100)0.9
(255/130)
= $15,817
Multiply the cost-capacity equation by a cost index (It/I0) to adjust for time
differences and obtain estimates of current cost (in constant-value dollars)
Factor Method
© 2012 by McGraw-Hill All Rights Reserved15-14
 Factor method is especially useful in estimating
total plant cost in processing industries
 Both direct and indirect costs can be included
Total plant cost estimate CT is overall cost factor (h) times total cost of
major equipment items (CE)
CT = h × CE
Overall cost factor h is determined using one of two bases:
 Delivered-equipment cost (purchase cost of major equipment)
 Installed-equipment cost (equipment cost plus all make-ready costs)
Cost Factor h
© 2012 by McGraw-Hill All Rights Reserved15-15
The cost factor is commonly the sum of a direct cost component
and an indirect cost component, that is,
h = 1 + Σfi
for i = 1, 2, …, n components, including indirect costs
Example: Equipment is expected to cost $20 million delivered to a
new facility. A cost factor for direct costs of 1.61 will make the
plant ready to operate. An indirect cost factor of 0.25 is used.
What will the plant cost?
Solution: h = 1 + 1.61 + 0.25 = 2.86
CT = 20 million (2.86) = $57.2 million
Cost Factor h
If indirect costs are charged separately against all direct costs,
the indirect cost component is added separately, that is,
h = 1 + Σfi (direct costs components)
and CT = hCE(1 + findirect)
Example: Conveyor delivered-equipment cost is $1.2 million.
Factors for installation costs (0.4) and training (0.2) are
determined. An indirect cost factor of 0.3 is applied to all direct
costs. Estimate total cost.
Solution: h = 1 + 0.4 + 0.2 = 1.6
CT = hCE(1 + findirect)
= 1.6(1.2 million)(1 + 0.3) = $2.5 million
© 2012 by McGraw-Hill All Rights Reserved15-16
Indirect Costs
© 2012 by McGraw-Hill All Rights Reserved15-17
Indirect costs (IDC) are incurred in production, processes and
service delivery that are not easily tracked and assignable to a
specific function.
 Indirect costs (IDC) are
shared by many functions
because they are necessary
to perform the overall
objective of the company
 Indirect costs make up a
significant percentage of
the overall costs in many
organizations – 25 to 50%
Sample indirect costs
 IT services
 Quality assurance
 Human resources
 Management
 Safety and security
 Purchasing; contracting
 Accounting; finance; legal
Indirect Cost Allocation - Traditional Method
 Cost center -- Department, function, or process used by the cost accounting system
to collect both direct and indirect costs
 Indirect-cost rate – Traditionally, a predetermined rate is used to allocate indirect
costs to a cost center using a specified basis. General relation is:
© 2012 by McGraw-Hill All Rights Reserved15-18
Estimated total indirect costs
Estimated basis level
Example:
Allocation rates
for $50,000 to
each machine
Indirect-cost rate =
Machine 1: Rate = $50,000/100,000 = $0.50 per DL $
Machine 2: Rate = $50,000/2,000 = $25 per DL hour
Machine 3: Rate = $50,000/250,000 = $0.20 per DM $
Example: AW Analysis - Traditional IDC Allocation
© 2012 by McGraw-Hill All Rights Reserved
15-19
MAKE/BUY DECISION
Buy: AW = $-2.2 million per year
Make: P = $-2 million S = $50,000 n = 10 years MARR = 15%
• Direct costs of $800,000 per year are detailed below
• Indirect cost rates are established by department
© 2012 by McGraw-Hill All Rights Reserved15-20
Example: Indirect Cost Analysis - Traditional Method
INDIRECT COST ALLOCATION FOR MAKE ALTERNATIVE
Dept A: Basis is -- Direct labor hours 25,000(10) = $250,000
Dept B: Basis is -- Machine hours 25,000(5) = $125,000
Dept C: Basis is -- Direct labor hours 10,000(15) = $150,000
ECONOMIC COMPARISON AT MARR = 15%
AOCmake = direct labor + direct materials + indirect allocation
= 500,000 + 300,000 + 525,000 = $1.325 M
AWmake = - 2 M(A/P,15%,10) + 50,000(A/F,15%,10) - 1.325 M
= $-1.72 M
AWbuy = $-2.2 M
$525,000
Conclusion: Cheaper to make
ABC Allocation
 Activity-Based Costing ─ Provides excellent allocation strategy and analysis of
costs for more advanced, high overhead, technologically-based systems
 Cost Centers (cost pools) ─ Final products/services that receive allocations
 Activities ─ Support departments that generate indirect costs for distribution to cost
centers (maintenance, engineering, management)
 Cost drivers ─ These are the volumes that drive consumption of shared resources (#
of POs, # of machine setups, # of safety violations, # of scrapped items)
© 2012 by McGraw-Hill All Rights Reserved15-21
Steps to implement ABC:
1.Identify each activity and its total cost (e.g., maintenance at $5 million/year)
2.Identify cost drivers and expected volume (e.g., 3,500 requested repairs and 500
scheduled maintenances per year)
3. Calculate cost rate for each activity using the relation:
ABC rate = total activity cost/volume of cost driver
4. Use ABC rate to allocate IDC to cost centers for each activity
Example: ABC Allocation
Use ABC to allocate safety program costs to plants in US and Europe
Cost centers: US and European plants
Activity and cost: Safety program costs $200,200 per year
Cost driver: # of accidents
Volume: 560 accidents; 425 in US plants and 135 in European plants
© 2012 by McGraw-Hill All Rights Reserved15-22
Solution:
ABC rate for accident basis = 200,200/560 = $357.50/accident
US allocation: 357.50(425) = $151,938
Europe allocation: 357.50(135) = $48,262
Example: Traditional Allocation Comparison
© 2012 by McGraw-Hill All Rights Reserved15-23
Solution:
Rate for employee basis = 200,200/1400 = $143/employee
US allocation: 143(900) = $128,700
Europe allocation: 143(500) = $71,500
Use traditional rates to allocate safety costs to US and EU plants
Cost centers: US and European plants
Activity and cost: Safety program costs $200,200 per year
Basis: # of employees
Volume: 1400 employees; 900 in US plants and 500 in European plants
Comparison: US allocation went down;
European allocation increased
Traditional vs. ABC Allocation
© 2012 by McGraw-Hill All Rights Reserved15-24
o Traditional method is easier to set up and use
o Traditional method is usually better when making
cost estimates
o ABC is more accurate when process is in operation
o ABC is more costly, but provides more information
for cost analysis and decision making
o Traditional and ABC methods complement each
other:
 Traditional is good for cost estimation and
allocation
 ABC is better for cost tracking and cost control
Ethics and Cost Estimating
Unethical practices in estimation may be the result of:
 Personal gain motivation
 Bias
 Deception
 Favoritism toward an individual or organization
 Intentional poor accuracy
 Pre-arranged financial favors (bribes, kickbacks)
When making any type of estimates, always comply with the
Code of Ethics for Engineers
© 2012 by McGraw-Hill All Rights Reserved15-25
Avoid deceptive acts
Summary of Important Points
© 2012 by McGraw-Hill All Rights Reserved15-26
Required accuracy of cost estimates depends on the stage of a system
design; accuracy varies from ±20% to ±5% of actual cost
Costs can be updated using the unit method and cost indexes, where time
differences are considered (inflation over time)
The factor method estimates total plant costs, including indirect costs
Traditional indirect cost allocation use bases such as direct labor hours,
costs, and direct materials
Indirect costs comprise a large percentage of product and service costs
The ABC method of indirect cost allocation uses cost drivers to allocate to
cost centers; it is better for understanding and analyzing cost accumulation
Unethical practices in cost estimation result from personal financial
motives, deception, financial pre-arrangements. Avoid deceptive acts

More Related Content

What's hot

Financial Management Slides Ch 15
Financial Management Slides Ch 15Financial Management Slides Ch 15
Financial Management Slides Ch 15Sayyed Naveed Ali
 
Cfa corporate finance chapter2
Cfa corporate finance chapter2Cfa corporate finance chapter2
Cfa corporate finance chapter2gisilowati
 
Time value of money
Time value of moneyTime value of money
Time value of moneyDeeAbsalom
 
Chapter 6 annual worth analysis
Chapter 6   annual worth analysisChapter 6   annual worth analysis
Chapter 6 annual worth analysisBich Lien Pham
 
Comparison and selection among alternatives
Comparison and selection among alternativesComparison and selection among alternatives
Comparison and selection among alternativesNafis Ahmad
 
Chapter 9 benefit & cost analysis
Chapter 9   benefit & cost analysisChapter 9   benefit & cost analysis
Chapter 9 benefit & cost analysisBich Lien Pham
 
Cost of capital, Cost of debt, Cost of equity, Cost of preference shares, Wei...
Cost of capital, Cost of debt, Cost of equity, Cost of preference shares, Wei...Cost of capital, Cost of debt, Cost of equity, Cost of preference shares, Wei...
Cost of capital, Cost of debt, Cost of equity, Cost of preference shares, Wei...Dayana Mastura FCCA CA
 
Chapter 10.The Cost of Capital(WACC)
Chapter 10.The Cost of Capital(WACC)Chapter 10.The Cost of Capital(WACC)
Chapter 10.The Cost of Capital(WACC)ZahraMirzayeva
 
Risk, Real Options and Capital Budgeting.ppt
Risk, Real Options and Capital Budgeting.pptRisk, Real Options and Capital Budgeting.ppt
Risk, Real Options and Capital Budgeting.pptMeghnaPurohit2
 
Fm11 ch 11 cash flow estimation and risk analysis
Fm11 ch 11 cash flow estimation and risk analysisFm11 ch 11 cash flow estimation and risk analysis
Fm11 ch 11 cash flow estimation and risk analysisNhu Tuyet Tran
 
Chapter 7 ror analysis for a single alternative
Chapter 7   ror analysis for a single alternativeChapter 7   ror analysis for a single alternative
Chapter 7 ror analysis for a single alternativeBich Lien Pham
 
time value of money
time value of moneytime value of money
time value of moneyashfaque75
 
Chapter 7 ror analysis for a single alternative
Chapter 7   ror analysis for a single alternativeChapter 7   ror analysis for a single alternative
Chapter 7 ror analysis for a single alternativeBich Lien Pham
 
Accounting by Meigs & Meigs
Accounting by Meigs & Meigs Accounting by Meigs & Meigs
Accounting by Meigs & Meigs Shakeel Ahmed
 
Time Value Of Money
Time Value Of MoneyTime Value Of Money
Time Value Of MoneyArchana
 
Chapter 11 replacement & retention decisions
Chapter 11   replacement & retention decisionsChapter 11   replacement & retention decisions
Chapter 11 replacement & retention decisionsBich Lien Pham
 

What's hot (20)

Financial Management Slides Ch 15
Financial Management Slides Ch 15Financial Management Slides Ch 15
Financial Management Slides Ch 15
 
Cfa corporate finance chapter2
Cfa corporate finance chapter2Cfa corporate finance chapter2
Cfa corporate finance chapter2
 
Time value of money
Time value of moneyTime value of money
Time value of money
 
Chapter 6 annual worth analysis
Chapter 6   annual worth analysisChapter 6   annual worth analysis
Chapter 6 annual worth analysis
 
Comparison and selection among alternatives
Comparison and selection among alternativesComparison and selection among alternatives
Comparison and selection among alternatives
 
Chapter 9 benefit & cost analysis
Chapter 9   benefit & cost analysisChapter 9   benefit & cost analysis
Chapter 9 benefit & cost analysis
 
Cost of capital, Cost of debt, Cost of equity, Cost of preference shares, Wei...
Cost of capital, Cost of debt, Cost of equity, Cost of preference shares, Wei...Cost of capital, Cost of debt, Cost of equity, Cost of preference shares, Wei...
Cost of capital, Cost of debt, Cost of equity, Cost of preference shares, Wei...
 
Chapter 10.The Cost of Capital(WACC)
Chapter 10.The Cost of Capital(WACC)Chapter 10.The Cost of Capital(WACC)
Chapter 10.The Cost of Capital(WACC)
 
Time value-of-money
Time value-of-moneyTime value-of-money
Time value-of-money
 
Risk, Real Options and Capital Budgeting.ppt
Risk, Real Options and Capital Budgeting.pptRisk, Real Options and Capital Budgeting.ppt
Risk, Real Options and Capital Budgeting.ppt
 
Fm11 ch 11 cash flow estimation and risk analysis
Fm11 ch 11 cash flow estimation and risk analysisFm11 ch 11 cash flow estimation and risk analysis
Fm11 ch 11 cash flow estimation and risk analysis
 
Rsh qam11 ch09 ge
Rsh qam11 ch09 geRsh qam11 ch09 ge
Rsh qam11 ch09 ge
 
Chapter 7 ror analysis for a single alternative
Chapter 7   ror analysis for a single alternativeChapter 7   ror analysis for a single alternative
Chapter 7 ror analysis for a single alternative
 
Ch 02
Ch 02Ch 02
Ch 02
 
time value of money
time value of moneytime value of money
time value of money
 
Chapter 7 ror analysis for a single alternative
Chapter 7   ror analysis for a single alternativeChapter 7   ror analysis for a single alternative
Chapter 7 ror analysis for a single alternative
 
Accounting by Meigs & Meigs
Accounting by Meigs & Meigs Accounting by Meigs & Meigs
Accounting by Meigs & Meigs
 
Risk and return
Risk and returnRisk and return
Risk and return
 
Time Value Of Money
Time Value Of MoneyTime Value Of Money
Time Value Of Money
 
Chapter 11 replacement & retention decisions
Chapter 11   replacement & retention decisionsChapter 11   replacement & retention decisions
Chapter 11 replacement & retention decisions
 

Similar to Chapter 15 cost estimation

Economic justification of npd project and financial tools
Economic justification of npd project and financial toolsEconomic justification of npd project and financial tools
Economic justification of npd project and financial toolsOmid Aminzadeh Gohari
 
Eng econ lecture
Eng econ lectureEng econ lecture
Eng econ lectureArul Kumar
 
Cost-Estimation-Techniques unit 2.pptx
Cost-Estimation-Techniques unit 2.pptxCost-Estimation-Techniques unit 2.pptx
Cost-Estimation-Techniques unit 2.pptxSudipBalLama
 
L06 cost management
L06 cost managementL06 cost management
L06 cost managementAsa Chan
 
cost estimation and break even analysis
cost estimation and break even analysiscost estimation and break even analysis
cost estimation and break even analysisDr Naim R Kidwai
 
Cost Indices for Industrial Application
Cost Indices for Industrial ApplicationCost Indices for Industrial Application
Cost Indices for Industrial ApplicationK. Shahzad Baig
 
IRJET- Life Cycle Cost Analysis of a Residential Building
IRJET-  	  Life Cycle Cost Analysis of a Residential BuildingIRJET-  	  Life Cycle Cost Analysis of a Residential Building
IRJET- Life Cycle Cost Analysis of a Residential BuildingIRJET Journal
 
5 costestimation-110716160453-phpapp01
5 costestimation-110716160453-phpapp015 costestimation-110716160453-phpapp01
5 costestimation-110716160453-phpapp01hlksd
 
Bus 7800 week 2
Bus 7800 week 2Bus 7800 week 2
Bus 7800 week 2OUHainesM
 
3.-Benefit-Cost-Analysis.pdf
3.-Benefit-Cost-Analysis.pdf3.-Benefit-Cost-Analysis.pdf
3.-Benefit-Cost-Analysis.pdf18010YeashRahman
 
Project Management C8 -cost_estimation_and_budgeting
Project Management C8  -cost_estimation_and_budgetingProject Management C8  -cost_estimation_and_budgeting
Project Management C8 -cost_estimation_and_budgetingIzah Asmadi
 
Chapter 9 benefit & cost analysis
Chapter 9   benefit & cost analysisChapter 9   benefit & cost analysis
Chapter 9 benefit & cost analysisBich Lien Pham
 
Application of economic model in software maintenance
Application of economic model in software maintenanceApplication of economic model in software maintenance
Application of economic model in software maintenanceAnh Nguyen Duc
 
HSMC301 ejeheve susueue euwueheheue eieueu
HSMC301 ejeheve susueue euwueheheue eieueuHSMC301 ejeheve susueue euwueheheue eieueu
HSMC301 ejeheve susueue euwueheheue eieueuBARUNSINGH43
 
Ch9-Lecture 2018 (2).ppt
Ch9-Lecture 2018 (2).pptCh9-Lecture 2018 (2).ppt
Ch9-Lecture 2018 (2).ppt4723bilal
 

Similar to Chapter 15 cost estimation (20)

Economic justification of npd project and financial tools
Economic justification of npd project and financial toolsEconomic justification of npd project and financial tools
Economic justification of npd project and financial tools
 
Eng econ lecture
Eng econ lectureEng econ lecture
Eng econ lecture
 
Cost managment
Cost managmentCost managment
Cost managment
 
Cost-Estimation-Techniques unit 2.pptx
Cost-Estimation-Techniques unit 2.pptxCost-Estimation-Techniques unit 2.pptx
Cost-Estimation-Techniques unit 2.pptx
 
L06 cost management
L06 cost managementL06 cost management
L06 cost management
 
cost estimation and break even analysis
cost estimation and break even analysiscost estimation and break even analysis
cost estimation and break even analysis
 
Cost Indices for Industrial Application
Cost Indices for Industrial ApplicationCost Indices for Industrial Application
Cost Indices for Industrial Application
 
Chap07
Chap07Chap07
Chap07
 
IRJET- Life Cycle Cost Analysis of a Residential Building
IRJET-  	  Life Cycle Cost Analysis of a Residential BuildingIRJET-  	  Life Cycle Cost Analysis of a Residential Building
IRJET- Life Cycle Cost Analysis of a Residential Building
 
5 costestimation-110716160453-phpapp01
5 costestimation-110716160453-phpapp015 costestimation-110716160453-phpapp01
5 costestimation-110716160453-phpapp01
 
Bus 7800 week 2
Bus 7800 week 2Bus 7800 week 2
Bus 7800 week 2
 
3.-Benefit-Cost-Analysis.pdf
3.-Benefit-Cost-Analysis.pdf3.-Benefit-Cost-Analysis.pdf
3.-Benefit-Cost-Analysis.pdf
 
Project Management C8 -cost_estimation_and_budgeting
Project Management C8  -cost_estimation_and_budgetingProject Management C8  -cost_estimation_and_budgeting
Project Management C8 -cost_estimation_and_budgeting
 
Chapter 9 benefit & cost analysis
Chapter 9   benefit & cost analysisChapter 9   benefit & cost analysis
Chapter 9 benefit & cost analysis
 
Cost Estimation
Cost EstimationCost Estimation
Cost Estimation
 
Application of economic model in software maintenance
Application of economic model in software maintenanceApplication of economic model in software maintenance
Application of economic model in software maintenance
 
HSMC301 ejeheve susueue euwueheheue eieueu
HSMC301 ejeheve susueue euwueheheue eieueuHSMC301 ejeheve susueue euwueheheue eieueu
HSMC301 ejeheve susueue euwueheheue eieueu
 
Nce603 mod unit3
Nce603 mod unit3Nce603 mod unit3
Nce603 mod unit3
 
P cost and budget
P cost and budgetP cost and budget
P cost and budget
 
Ch9-Lecture 2018 (2).ppt
Ch9-Lecture 2018 (2).pptCh9-Lecture 2018 (2).ppt
Ch9-Lecture 2018 (2).ppt
 

More from Bich Lien Pham

Lecture # 13 investment alternatives i
Lecture # 13 investment alternatives iLecture # 13 investment alternatives i
Lecture # 13 investment alternatives iBich Lien Pham
 
Lecture # 12 measures of profitability ii
Lecture # 12 measures of profitability iiLecture # 12 measures of profitability ii
Lecture # 12 measures of profitability iiBich Lien Pham
 
Lecture # 11 measures of profitability i
Lecture # 11 measures of profitability iLecture # 11 measures of profitability i
Lecture # 11 measures of profitability iBich Lien Pham
 
Lecture # 10 eva and disposal of assets
Lecture # 10 eva and disposal of assetsLecture # 10 eva and disposal of assets
Lecture # 10 eva and disposal of assetsBich Lien Pham
 
Lecture # 9 taxes and eva
Lecture # 9 taxes and evaLecture # 9 taxes and eva
Lecture # 9 taxes and evaBich Lien Pham
 
Lecture # 8 depreciation ii
Lecture # 8 depreciation iiLecture # 8 depreciation ii
Lecture # 8 depreciation iiBich Lien Pham
 
Lecture # 7 depreciation i
Lecture # 7 depreciation iLecture # 7 depreciation i
Lecture # 7 depreciation iBich Lien Pham
 
Lecture # 6 cost estimation ii
Lecture # 6 cost estimation iiLecture # 6 cost estimation ii
Lecture # 6 cost estimation iiBich Lien Pham
 
Lecture # 5 cost estimation i
Lecture # 5 cost estimation iLecture # 5 cost estimation i
Lecture # 5 cost estimation iBich Lien Pham
 
Lecture # 4 gradients factors and nominal and effective interest rates
Lecture # 4 gradients factors and nominal and effective interest ratesLecture # 4 gradients factors and nominal and effective interest rates
Lecture # 4 gradients factors and nominal and effective interest ratesBich Lien Pham
 
Lecture # 3 compounding factors effects of inflation
Lecture # 3 compounding factors   effects of inflationLecture # 3 compounding factors   effects of inflation
Lecture # 3 compounding factors effects of inflationBich Lien Pham
 
Lecture # 2 time value of money
Lecture # 2 time value of moneyLecture # 2 time value of money
Lecture # 2 time value of moneyBich Lien Pham
 
Lecture # 1 foundation
Lecture # 1 foundationLecture # 1 foundation
Lecture # 1 foundationBich Lien Pham
 
Chapter 19 decision-making under risk
Chapter 19   decision-making under riskChapter 19   decision-making under risk
Chapter 19 decision-making under riskBich Lien Pham
 
Chapter 18 sensitivity analysis
Chapter 18   sensitivity analysisChapter 18   sensitivity analysis
Chapter 18 sensitivity analysisBich Lien Pham
 
Chapter 17 after-tax economic analysis
Chapter 17   after-tax economic analysisChapter 17   after-tax economic analysis
Chapter 17 after-tax economic analysisBich Lien Pham
 
Chapter 16 depreciation methods
Chapter 16   depreciation methodsChapter 16   depreciation methods
Chapter 16 depreciation methodsBich Lien Pham
 
Chapter 14 effects of inflation
Chapter 14   effects of inflationChapter 14   effects of inflation
Chapter 14 effects of inflationBich Lien Pham
 
Chapter 13 breakeven analysis
Chapter 13   breakeven analysisChapter 13   breakeven analysis
Chapter 13 breakeven analysisBich Lien Pham
 
Chapter 12 independent projects & budget limitation
Chapter 12   independent projects & budget limitationChapter 12   independent projects & budget limitation
Chapter 12 independent projects & budget limitationBich Lien Pham
 

More from Bich Lien Pham (20)

Lecture # 13 investment alternatives i
Lecture # 13 investment alternatives iLecture # 13 investment alternatives i
Lecture # 13 investment alternatives i
 
Lecture # 12 measures of profitability ii
Lecture # 12 measures of profitability iiLecture # 12 measures of profitability ii
Lecture # 12 measures of profitability ii
 
Lecture # 11 measures of profitability i
Lecture # 11 measures of profitability iLecture # 11 measures of profitability i
Lecture # 11 measures of profitability i
 
Lecture # 10 eva and disposal of assets
Lecture # 10 eva and disposal of assetsLecture # 10 eva and disposal of assets
Lecture # 10 eva and disposal of assets
 
Lecture # 9 taxes and eva
Lecture # 9 taxes and evaLecture # 9 taxes and eva
Lecture # 9 taxes and eva
 
Lecture # 8 depreciation ii
Lecture # 8 depreciation iiLecture # 8 depreciation ii
Lecture # 8 depreciation ii
 
Lecture # 7 depreciation i
Lecture # 7 depreciation iLecture # 7 depreciation i
Lecture # 7 depreciation i
 
Lecture # 6 cost estimation ii
Lecture # 6 cost estimation iiLecture # 6 cost estimation ii
Lecture # 6 cost estimation ii
 
Lecture # 5 cost estimation i
Lecture # 5 cost estimation iLecture # 5 cost estimation i
Lecture # 5 cost estimation i
 
Lecture # 4 gradients factors and nominal and effective interest rates
Lecture # 4 gradients factors and nominal and effective interest ratesLecture # 4 gradients factors and nominal and effective interest rates
Lecture # 4 gradients factors and nominal and effective interest rates
 
Lecture # 3 compounding factors effects of inflation
Lecture # 3 compounding factors   effects of inflationLecture # 3 compounding factors   effects of inflation
Lecture # 3 compounding factors effects of inflation
 
Lecture # 2 time value of money
Lecture # 2 time value of moneyLecture # 2 time value of money
Lecture # 2 time value of money
 
Lecture # 1 foundation
Lecture # 1 foundationLecture # 1 foundation
Lecture # 1 foundation
 
Chapter 19 decision-making under risk
Chapter 19   decision-making under riskChapter 19   decision-making under risk
Chapter 19 decision-making under risk
 
Chapter 18 sensitivity analysis
Chapter 18   sensitivity analysisChapter 18   sensitivity analysis
Chapter 18 sensitivity analysis
 
Chapter 17 after-tax economic analysis
Chapter 17   after-tax economic analysisChapter 17   after-tax economic analysis
Chapter 17 after-tax economic analysis
 
Chapter 16 depreciation methods
Chapter 16   depreciation methodsChapter 16   depreciation methods
Chapter 16 depreciation methods
 
Chapter 14 effects of inflation
Chapter 14   effects of inflationChapter 14   effects of inflation
Chapter 14 effects of inflation
 
Chapter 13 breakeven analysis
Chapter 13   breakeven analysisChapter 13   breakeven analysis
Chapter 13 breakeven analysis
 
Chapter 12 independent projects & budget limitation
Chapter 12   independent projects & budget limitationChapter 12   independent projects & budget limitation
Chapter 12 independent projects & budget limitation
 

Recently uploaded

Call Girls In Sikandarpur Gurgaon ❤️8860477959_Russian 100% Genuine Escorts I...
Call Girls In Sikandarpur Gurgaon ❤️8860477959_Russian 100% Genuine Escorts I...Call Girls In Sikandarpur Gurgaon ❤️8860477959_Russian 100% Genuine Escorts I...
Call Girls In Sikandarpur Gurgaon ❤️8860477959_Russian 100% Genuine Escorts I...lizamodels9
 
A DAY IN THE LIFE OF A SALESMAN / WOMAN
A DAY IN THE LIFE OF A  SALESMAN / WOMANA DAY IN THE LIFE OF A  SALESMAN / WOMAN
A DAY IN THE LIFE OF A SALESMAN / WOMANIlamathiKannappan
 
GD Birla and his contribution in management
GD Birla and his contribution in managementGD Birla and his contribution in management
GD Birla and his contribution in managementchhavia330
 
Tech Startup Growth Hacking 101 - Basics on Growth Marketing
Tech Startup Growth Hacking 101  - Basics on Growth MarketingTech Startup Growth Hacking 101  - Basics on Growth Marketing
Tech Startup Growth Hacking 101 - Basics on Growth MarketingShawn Pang
 
Lucknow 💋 Escorts in Lucknow - 450+ Call Girl Cash Payment 8923113531 Neha Th...
Lucknow 💋 Escorts in Lucknow - 450+ Call Girl Cash Payment 8923113531 Neha Th...Lucknow 💋 Escorts in Lucknow - 450+ Call Girl Cash Payment 8923113531 Neha Th...
Lucknow 💋 Escorts in Lucknow - 450+ Call Girl Cash Payment 8923113531 Neha Th...anilsa9823
 
Vip Female Escorts Noida 9711199171 Greater Noida Escorts Service
Vip Female Escorts Noida 9711199171 Greater Noida Escorts ServiceVip Female Escorts Noida 9711199171 Greater Noida Escorts Service
Vip Female Escorts Noida 9711199171 Greater Noida Escorts Serviceankitnayak356677
 
Cash Payment 9602870969 Escort Service in Udaipur Call Girls
Cash Payment 9602870969 Escort Service in Udaipur Call GirlsCash Payment 9602870969 Escort Service in Udaipur Call Girls
Cash Payment 9602870969 Escort Service in Udaipur Call GirlsApsara Of India
 
BEST Call Girls In Old Faridabad ✨ 9773824855 ✨ Escorts Service In Delhi Ncr,
BEST Call Girls In Old Faridabad ✨ 9773824855 ✨ Escorts Service In Delhi Ncr,BEST Call Girls In Old Faridabad ✨ 9773824855 ✨ Escorts Service In Delhi Ncr,
BEST Call Girls In Old Faridabad ✨ 9773824855 ✨ Escorts Service In Delhi Ncr,noida100girls
 
Call Girls In Sikandarpur Gurgaon ❤️8860477959_Russian 100% Genuine Escorts I...
Call Girls In Sikandarpur Gurgaon ❤️8860477959_Russian 100% Genuine Escorts I...Call Girls In Sikandarpur Gurgaon ❤️8860477959_Russian 100% Genuine Escorts I...
Call Girls In Sikandarpur Gurgaon ❤️8860477959_Russian 100% Genuine Escorts I...lizamodels9
 
0183760ssssssssssssssssssssssssssss00101011 (27).pdf
0183760ssssssssssssssssssssssssssss00101011 (27).pdf0183760ssssssssssssssssssssssssssss00101011 (27).pdf
0183760ssssssssssssssssssssssssssss00101011 (27).pdfRenandantas16
 
7.pdf This presentation captures many uses and the significance of the number...
7.pdf This presentation captures many uses and the significance of the number...7.pdf This presentation captures many uses and the significance of the number...
7.pdf This presentation captures many uses and the significance of the number...Paul Menig
 
Sales & Marketing Alignment: How to Synergize for Success
Sales & Marketing Alignment: How to Synergize for SuccessSales & Marketing Alignment: How to Synergize for Success
Sales & Marketing Alignment: How to Synergize for SuccessAggregage
 
VIP Kolkata Call Girl Howrah 👉 8250192130 Available With Room
VIP Kolkata Call Girl Howrah 👉 8250192130  Available With RoomVIP Kolkata Call Girl Howrah 👉 8250192130  Available With Room
VIP Kolkata Call Girl Howrah 👉 8250192130 Available With Roomdivyansh0kumar0
 
Lowrate Call Girls In Laxmi Nagar Delhi ❤️8860477959 Escorts 100% Genuine Ser...
Lowrate Call Girls In Laxmi Nagar Delhi ❤️8860477959 Escorts 100% Genuine Ser...Lowrate Call Girls In Laxmi Nagar Delhi ❤️8860477959 Escorts 100% Genuine Ser...
Lowrate Call Girls In Laxmi Nagar Delhi ❤️8860477959 Escorts 100% Genuine Ser...lizamodels9
 
Enhancing and Restoring Safety & Quality Cultures - Dave Litwiller - May 2024...
Enhancing and Restoring Safety & Quality Cultures - Dave Litwiller - May 2024...Enhancing and Restoring Safety & Quality Cultures - Dave Litwiller - May 2024...
Enhancing and Restoring Safety & Quality Cultures - Dave Litwiller - May 2024...Dave Litwiller
 
VIP Call Girls Pune Kirti 8617697112 Independent Escort Service Pune
VIP Call Girls Pune Kirti 8617697112 Independent Escort Service PuneVIP Call Girls Pune Kirti 8617697112 Independent Escort Service Pune
VIP Call Girls Pune Kirti 8617697112 Independent Escort Service PuneCall girls in Ahmedabad High profile
 
Non Text Magic Studio Magic Design for Presentations L&P.pptx
Non Text Magic Studio Magic Design for Presentations L&P.pptxNon Text Magic Studio Magic Design for Presentations L&P.pptx
Non Text Magic Studio Magic Design for Presentations L&P.pptxAbhayThakur200703
 
Insurers' journeys to build a mastery in the IoT usage
Insurers' journeys to build a mastery in the IoT usageInsurers' journeys to build a mastery in the IoT usage
Insurers' journeys to build a mastery in the IoT usageMatteo Carbone
 

Recently uploaded (20)

Best Practices for Implementing an External Recruiting Partnership
Best Practices for Implementing an External Recruiting PartnershipBest Practices for Implementing an External Recruiting Partnership
Best Practices for Implementing an External Recruiting Partnership
 
Call Girls In Sikandarpur Gurgaon ❤️8860477959_Russian 100% Genuine Escorts I...
Call Girls In Sikandarpur Gurgaon ❤️8860477959_Russian 100% Genuine Escorts I...Call Girls In Sikandarpur Gurgaon ❤️8860477959_Russian 100% Genuine Escorts I...
Call Girls In Sikandarpur Gurgaon ❤️8860477959_Russian 100% Genuine Escorts I...
 
A DAY IN THE LIFE OF A SALESMAN / WOMAN
A DAY IN THE LIFE OF A  SALESMAN / WOMANA DAY IN THE LIFE OF A  SALESMAN / WOMAN
A DAY IN THE LIFE OF A SALESMAN / WOMAN
 
GD Birla and his contribution in management
GD Birla and his contribution in managementGD Birla and his contribution in management
GD Birla and his contribution in management
 
Tech Startup Growth Hacking 101 - Basics on Growth Marketing
Tech Startup Growth Hacking 101  - Basics on Growth MarketingTech Startup Growth Hacking 101  - Basics on Growth Marketing
Tech Startup Growth Hacking 101 - Basics on Growth Marketing
 
Lucknow 💋 Escorts in Lucknow - 450+ Call Girl Cash Payment 8923113531 Neha Th...
Lucknow 💋 Escorts in Lucknow - 450+ Call Girl Cash Payment 8923113531 Neha Th...Lucknow 💋 Escorts in Lucknow - 450+ Call Girl Cash Payment 8923113531 Neha Th...
Lucknow 💋 Escorts in Lucknow - 450+ Call Girl Cash Payment 8923113531 Neha Th...
 
Vip Female Escorts Noida 9711199171 Greater Noida Escorts Service
Vip Female Escorts Noida 9711199171 Greater Noida Escorts ServiceVip Female Escorts Noida 9711199171 Greater Noida Escorts Service
Vip Female Escorts Noida 9711199171 Greater Noida Escorts Service
 
Cash Payment 9602870969 Escort Service in Udaipur Call Girls
Cash Payment 9602870969 Escort Service in Udaipur Call GirlsCash Payment 9602870969 Escort Service in Udaipur Call Girls
Cash Payment 9602870969 Escort Service in Udaipur Call Girls
 
BEST Call Girls In Old Faridabad ✨ 9773824855 ✨ Escorts Service In Delhi Ncr,
BEST Call Girls In Old Faridabad ✨ 9773824855 ✨ Escorts Service In Delhi Ncr,BEST Call Girls In Old Faridabad ✨ 9773824855 ✨ Escorts Service In Delhi Ncr,
BEST Call Girls In Old Faridabad ✨ 9773824855 ✨ Escorts Service In Delhi Ncr,
 
Call Girls In Sikandarpur Gurgaon ❤️8860477959_Russian 100% Genuine Escorts I...
Call Girls In Sikandarpur Gurgaon ❤️8860477959_Russian 100% Genuine Escorts I...Call Girls In Sikandarpur Gurgaon ❤️8860477959_Russian 100% Genuine Escorts I...
Call Girls In Sikandarpur Gurgaon ❤️8860477959_Russian 100% Genuine Escorts I...
 
0183760ssssssssssssssssssssssssssss00101011 (27).pdf
0183760ssssssssssssssssssssssssssss00101011 (27).pdf0183760ssssssssssssssssssssssssssss00101011 (27).pdf
0183760ssssssssssssssssssssssssssss00101011 (27).pdf
 
7.pdf This presentation captures many uses and the significance of the number...
7.pdf This presentation captures many uses and the significance of the number...7.pdf This presentation captures many uses and the significance of the number...
7.pdf This presentation captures many uses and the significance of the number...
 
Sales & Marketing Alignment: How to Synergize for Success
Sales & Marketing Alignment: How to Synergize for SuccessSales & Marketing Alignment: How to Synergize for Success
Sales & Marketing Alignment: How to Synergize for Success
 
VIP Kolkata Call Girl Howrah 👉 8250192130 Available With Room
VIP Kolkata Call Girl Howrah 👉 8250192130  Available With RoomVIP Kolkata Call Girl Howrah 👉 8250192130  Available With Room
VIP Kolkata Call Girl Howrah 👉 8250192130 Available With Room
 
KestrelPro Flyer Japan IT Week 2024 (English)
KestrelPro Flyer Japan IT Week 2024 (English)KestrelPro Flyer Japan IT Week 2024 (English)
KestrelPro Flyer Japan IT Week 2024 (English)
 
Lowrate Call Girls In Laxmi Nagar Delhi ❤️8860477959 Escorts 100% Genuine Ser...
Lowrate Call Girls In Laxmi Nagar Delhi ❤️8860477959 Escorts 100% Genuine Ser...Lowrate Call Girls In Laxmi Nagar Delhi ❤️8860477959 Escorts 100% Genuine Ser...
Lowrate Call Girls In Laxmi Nagar Delhi ❤️8860477959 Escorts 100% Genuine Ser...
 
Enhancing and Restoring Safety & Quality Cultures - Dave Litwiller - May 2024...
Enhancing and Restoring Safety & Quality Cultures - Dave Litwiller - May 2024...Enhancing and Restoring Safety & Quality Cultures - Dave Litwiller - May 2024...
Enhancing and Restoring Safety & Quality Cultures - Dave Litwiller - May 2024...
 
VIP Call Girls Pune Kirti 8617697112 Independent Escort Service Pune
VIP Call Girls Pune Kirti 8617697112 Independent Escort Service PuneVIP Call Girls Pune Kirti 8617697112 Independent Escort Service Pune
VIP Call Girls Pune Kirti 8617697112 Independent Escort Service Pune
 
Non Text Magic Studio Magic Design for Presentations L&P.pptx
Non Text Magic Studio Magic Design for Presentations L&P.pptxNon Text Magic Studio Magic Design for Presentations L&P.pptx
Non Text Magic Studio Magic Design for Presentations L&P.pptx
 
Insurers' journeys to build a mastery in the IoT usage
Insurers' journeys to build a mastery in the IoT usageInsurers' journeys to build a mastery in the IoT usage
Insurers' journeys to build a mastery in the IoT usage
 

Chapter 15 cost estimation

  • 1. 15-1 Lecture slides to accompany Engineering Economy 7th edition Leland Blank Anthony Tarquin Chapter 15Chapter 15 Cost EstimationCost Estimation and Indirectand Indirect CostsCosts © 2012 by McGraw-Hill All Rights Reserved
  • 2. LEARNING OUTCOMES © 2012 by McGraw-Hill All Rights Reserved15-2 1. Approaches to estimation 2. Unit method 3. Cost indexes 4. Cost-capacity equations 5. Factor method 6. Indirect cost rates and allocation 7. ABC allocation 8. Ethical considerations
  • 3. Direct and Indirect Cost Estimates © 2012 by McGraw-Hill All Rights Reserved15-3 Direct cost examples • Physical assets • Maintenance and operating costs (M&O) • Materials • Direct human labor (costs and benefits) • Scrapped and reworked product • Direct supervision of personnel Indirect cost examples • Utilities • IT systems and networks • Purchasing • Management • Taxes • Legal functions • Warranty and guarantees • Quality assurance • Accounting functions • Marketing and publicity
  • 4. What Direct Cost Estimation Includes © 2012 by McGraw-Hill All Rights Reserved15-4 Direct costs are more commonly estimated than revenue in an engineering environment. Preliminary decisions required are:  What cost components should be estimated?  What approach to estimation is best to apply?  How accurate should the estimates be?  What technique(s) will be applied to estimate costs? Sample direct cost components: first costs and its elements (P); annual costs (AOC or M&O); salvage/market value (S) Approaches: bottom-up; design-to-cost (top down) Accuracy: feasibility stage through detailed design estimates require more exacting estimates Some techniques: unit; factor; cost estimating relations (CER)
  • 5. Different Approaches to Cost Estimation © 2012 by McGraw-Hill All Rights Reserved15-5
  • 6. Accuracy of Cost Estimates © 2012 by McGraw-Hill All Rights Reserved15-6 Characteristic curve of accuracy vs. time to make estimates General guidelines for accuracy Conceptual/Feasibility stage – order-of-magnitude estimates are in range of ±20% of actual costs Detailed design stage - Detailed estimates are in range of ±5% of actual costs
  • 7. Unit Method © 2012 by McGraw-Hill All Rights Reserved15-7 • Commonly used technique for preliminary design stage estimates • Total cost estimate CT is per unit cost (u) times number of units (N) CT = u × N • Example uses:  Cost to operate a car at 60¢/mile for 500 miles: CT = 0.60 × 500 = $300  Cost to build a 250 m2 house at $2250/m2 : CT = 2250 × 250 = $562,500 • Cost factors must be updated periodically to remain timely When several components are involved, estimate cost of each component and add to determine total cost estimate CT
  • 8. Cost Indexes © 2012 by McGraw-Hill All Rights Reserved15-8 Definition: Cost Index is ratio of cost today to cost in the past • Indicates change in cost over time; therefore, they account for the impact of inflation • Index is dimensionless • CPI (Consumer Price Index) is a good example
  • 9. Example: Cost Index Method © 2012 by McGraw-Hill All Rights Reserved15-9 Problem: Estimate the total cost of labor today in US dollars for a maritime construction project using data from a similar project in Europe completed in 1998. Labor index, 1998: 789.6 Cost in 1998: €3.9 million Labor index, current: 1165.8 Currently, 1 € = 1.5 US$ Solution: Let t = today and 0 = 1998 base Ct = 3.9 million × (1165.8/789.6) = €5.76 million = €5.76 × 1.5 = $8.64 million
  • 10. Finding Cost Indexes © 2012 by McGraw-Hill All Rights Reserved15-10 Cost indexes are maintained in areas such as construction, chemical and mechanical industries • Updated monthly and annually; many include regionalized and international project indexes • Indexes in these areas are often subdivided into smaller components and can be used in preliminary, as well as detailed design stages Examples are:  Chemical Engineering Plant Cost Index (CEPCI) www.che.com/pci  McGraw-Hill Construction Index www.construction.com  US Department of Labor, Bureau of Labor Statistics www.bls.gov
  • 11. Cost-Estimating Relationships (CER) © 2012 by McGraw-Hill All Rights Reserved15-11  CER equations are used in early design stages to estimate plant, equipment and construction costs  CERs are generically different from index relations, because they estimate based on design variables (weight, thrust, force, pressure, speed, etc.) Two commonly used CERs  Cost-capacity equation (relates cost to capacity)  Factor method (total plant cost estimator, including indirect costs)
  • 12. Cost-Capacity Equation © 2012 by McGraw-Hill All Rights Reserved15-12 Also called power law and sizing model Exponent defines relation between capacities x = 1, relationship is linear x < 1, economies of scale (larger capacity is less costly than linear) x > 1, diseconomies of scale
  • 13. Cost-Capacity Combined with Cost Index © 2012 by McGraw-Hill All Rights Reserved15-13 Example: A 100 hp air compressor costs $3000 five years ago when the cost index was 130. Estimate the cost of a 300 hp compressor today when the cost index is 255. The exponent for a 300 hp air compressor is 0.9. Solution: Let C300 represent the cost estimate today C300 = 3000(300/100)0.9 (255/130) = $15,817 Multiply the cost-capacity equation by a cost index (It/I0) to adjust for time differences and obtain estimates of current cost (in constant-value dollars)
  • 14. Factor Method © 2012 by McGraw-Hill All Rights Reserved15-14  Factor method is especially useful in estimating total plant cost in processing industries  Both direct and indirect costs can be included Total plant cost estimate CT is overall cost factor (h) times total cost of major equipment items (CE) CT = h × CE Overall cost factor h is determined using one of two bases:  Delivered-equipment cost (purchase cost of major equipment)  Installed-equipment cost (equipment cost plus all make-ready costs)
  • 15. Cost Factor h © 2012 by McGraw-Hill All Rights Reserved15-15 The cost factor is commonly the sum of a direct cost component and an indirect cost component, that is, h = 1 + Σfi for i = 1, 2, …, n components, including indirect costs Example: Equipment is expected to cost $20 million delivered to a new facility. A cost factor for direct costs of 1.61 will make the plant ready to operate. An indirect cost factor of 0.25 is used. What will the plant cost? Solution: h = 1 + 1.61 + 0.25 = 2.86 CT = 20 million (2.86) = $57.2 million
  • 16. Cost Factor h If indirect costs are charged separately against all direct costs, the indirect cost component is added separately, that is, h = 1 + Σfi (direct costs components) and CT = hCE(1 + findirect) Example: Conveyor delivered-equipment cost is $1.2 million. Factors for installation costs (0.4) and training (0.2) are determined. An indirect cost factor of 0.3 is applied to all direct costs. Estimate total cost. Solution: h = 1 + 0.4 + 0.2 = 1.6 CT = hCE(1 + findirect) = 1.6(1.2 million)(1 + 0.3) = $2.5 million © 2012 by McGraw-Hill All Rights Reserved15-16
  • 17. Indirect Costs © 2012 by McGraw-Hill All Rights Reserved15-17 Indirect costs (IDC) are incurred in production, processes and service delivery that are not easily tracked and assignable to a specific function.  Indirect costs (IDC) are shared by many functions because they are necessary to perform the overall objective of the company  Indirect costs make up a significant percentage of the overall costs in many organizations – 25 to 50% Sample indirect costs  IT services  Quality assurance  Human resources  Management  Safety and security  Purchasing; contracting  Accounting; finance; legal
  • 18. Indirect Cost Allocation - Traditional Method  Cost center -- Department, function, or process used by the cost accounting system to collect both direct and indirect costs  Indirect-cost rate – Traditionally, a predetermined rate is used to allocate indirect costs to a cost center using a specified basis. General relation is: © 2012 by McGraw-Hill All Rights Reserved15-18 Estimated total indirect costs Estimated basis level Example: Allocation rates for $50,000 to each machine Indirect-cost rate = Machine 1: Rate = $50,000/100,000 = $0.50 per DL $ Machine 2: Rate = $50,000/2,000 = $25 per DL hour Machine 3: Rate = $50,000/250,000 = $0.20 per DM $
  • 19. Example: AW Analysis - Traditional IDC Allocation © 2012 by McGraw-Hill All Rights Reserved 15-19 MAKE/BUY DECISION Buy: AW = $-2.2 million per year Make: P = $-2 million S = $50,000 n = 10 years MARR = 15% • Direct costs of $800,000 per year are detailed below • Indirect cost rates are established by department
  • 20. © 2012 by McGraw-Hill All Rights Reserved15-20 Example: Indirect Cost Analysis - Traditional Method INDIRECT COST ALLOCATION FOR MAKE ALTERNATIVE Dept A: Basis is -- Direct labor hours 25,000(10) = $250,000 Dept B: Basis is -- Machine hours 25,000(5) = $125,000 Dept C: Basis is -- Direct labor hours 10,000(15) = $150,000 ECONOMIC COMPARISON AT MARR = 15% AOCmake = direct labor + direct materials + indirect allocation = 500,000 + 300,000 + 525,000 = $1.325 M AWmake = - 2 M(A/P,15%,10) + 50,000(A/F,15%,10) - 1.325 M = $-1.72 M AWbuy = $-2.2 M $525,000 Conclusion: Cheaper to make
  • 21. ABC Allocation  Activity-Based Costing ─ Provides excellent allocation strategy and analysis of costs for more advanced, high overhead, technologically-based systems  Cost Centers (cost pools) ─ Final products/services that receive allocations  Activities ─ Support departments that generate indirect costs for distribution to cost centers (maintenance, engineering, management)  Cost drivers ─ These are the volumes that drive consumption of shared resources (# of POs, # of machine setups, # of safety violations, # of scrapped items) © 2012 by McGraw-Hill All Rights Reserved15-21 Steps to implement ABC: 1.Identify each activity and its total cost (e.g., maintenance at $5 million/year) 2.Identify cost drivers and expected volume (e.g., 3,500 requested repairs and 500 scheduled maintenances per year) 3. Calculate cost rate for each activity using the relation: ABC rate = total activity cost/volume of cost driver 4. Use ABC rate to allocate IDC to cost centers for each activity
  • 22. Example: ABC Allocation Use ABC to allocate safety program costs to plants in US and Europe Cost centers: US and European plants Activity and cost: Safety program costs $200,200 per year Cost driver: # of accidents Volume: 560 accidents; 425 in US plants and 135 in European plants © 2012 by McGraw-Hill All Rights Reserved15-22 Solution: ABC rate for accident basis = 200,200/560 = $357.50/accident US allocation: 357.50(425) = $151,938 Europe allocation: 357.50(135) = $48,262
  • 23. Example: Traditional Allocation Comparison © 2012 by McGraw-Hill All Rights Reserved15-23 Solution: Rate for employee basis = 200,200/1400 = $143/employee US allocation: 143(900) = $128,700 Europe allocation: 143(500) = $71,500 Use traditional rates to allocate safety costs to US and EU plants Cost centers: US and European plants Activity and cost: Safety program costs $200,200 per year Basis: # of employees Volume: 1400 employees; 900 in US plants and 500 in European plants Comparison: US allocation went down; European allocation increased
  • 24. Traditional vs. ABC Allocation © 2012 by McGraw-Hill All Rights Reserved15-24 o Traditional method is easier to set up and use o Traditional method is usually better when making cost estimates o ABC is more accurate when process is in operation o ABC is more costly, but provides more information for cost analysis and decision making o Traditional and ABC methods complement each other:  Traditional is good for cost estimation and allocation  ABC is better for cost tracking and cost control
  • 25. Ethics and Cost Estimating Unethical practices in estimation may be the result of:  Personal gain motivation  Bias  Deception  Favoritism toward an individual or organization  Intentional poor accuracy  Pre-arranged financial favors (bribes, kickbacks) When making any type of estimates, always comply with the Code of Ethics for Engineers © 2012 by McGraw-Hill All Rights Reserved15-25 Avoid deceptive acts
  • 26. Summary of Important Points © 2012 by McGraw-Hill All Rights Reserved15-26 Required accuracy of cost estimates depends on the stage of a system design; accuracy varies from ±20% to ±5% of actual cost Costs can be updated using the unit method and cost indexes, where time differences are considered (inflation over time) The factor method estimates total plant costs, including indirect costs Traditional indirect cost allocation use bases such as direct labor hours, costs, and direct materials Indirect costs comprise a large percentage of product and service costs The ABC method of indirect cost allocation uses cost drivers to allocate to cost centers; it is better for understanding and analyzing cost accumulation Unethical practices in cost estimation result from personal financial motives, deception, financial pre-arrangements. Avoid deceptive acts