There are different types of capital cost estimates for a process project ranging from a predesign estimate with little information to a detailed estimate based on complete drawings and specifications. Estimates fall into five categories - order-of-magnitude, study, preliminary, definitive, and detailed - with varying levels of accuracy depending on the stage of project development, from ±30% accuracy for order-of-magnitude and study estimates to ±5% accuracy for detailed estimates.