Estimate Review / Validation Checklist
Douglas W. Leo CCP CEP FAACE FRICS
Saybrook Associates, Inc.
Chair AACE International Estimating Sub-Committee
AACE Recommended Practices
• Cost Engineers Tool Kit -
– RP 10S-90 Cost Engineering Terminology
– RP 18R-97 Cost Estimating Classification System
– RP 21R-98 Project Code of Accounts
– RP 27R-03 Schedule Classification Systems
– RP 30R-03 Implementing Project Constructability
– RP31R-03 Reviewing, Validating and Documenting an
Estimate
– RP34R-05 Basis of Estimate
– RP 36R-08 Development of Cost Estimating Plans
– RP 38R-06 Documenting the Schedule Basis
Review/Validation Checklist - Introduction
The Project Cost Estimate that was just delivered is
amazing. It is exactly what was expected, costs were
immediately understandable and lower than anticipated.
Management will love this. The work on this project
estimate is worthy of great praise …… outstanding job!!!!
Were these words ever spoken outside of someone’s
dreams? …….. I think not.
Review / Validation Checklist Introduction
• Project Teams universally have the desire to produce
successful outcomes.
• They all want their work to be seen as on time, on
budget, and meeting the desire functionality.
• The desire is for a completed project package that is:
– Transparent
– Explainable
– Defendable
– Acceptable to management
Review / Validation Checklist Introduction
• Three main project drivers: Functionality, Schedule, Cost
• Over the course of the project there is shifting
importance for the three drivers but at some point costs
become the main issue with regards to moving the
project forward.
• When costs become the main focus, a thorough
understanding of the project estimate and how it was
developed is the task at hand.
• A review and validation takes place at multiple levels:
internally by the estimating provider, by the owner
client, by third party reviewers
Review / Validation Checklist Introduction
Completed project estimating package should always
include certain elements:
• Basis of Estimate
• Estimate Summary
• Estimate Detail
• Reconciliation Report
• Historical Cost Metric Report
• Estimate Deliverables Report
• Risk Analysis Report
PHASE 2
SELECT from
Alternatives
Clearly Frame
Goal
Test for
Strategic Fit
Preliminary
Overall Plan
Preliminary
Assessment
~1 % Engr.
AACE Class 5
Cost Estimate
PHASE 1
IDENTIFY & Assess
Opportunity
Fully Define
Scope
Develop
Detailed
Execution Plans
Refine Estimate
Submit Funding
for Approval
~25 % Engr.
AACE Class 3
Cost Estimate
Generate
Alternatives
Preliminary
Development
of Alternatives
Develop
Expected
Value
Identify
Preferred
Alternative
AACE Class 4
Cost Estimate
Operate Asset
Monitor &
Evaluate
Performance
Identify New
Opportunities
PHASE 3
DEVELOP Preferred
Alternative
PHASE 4
EXECUTE
(Detail EPC)
PHASE 5
OPERATE &
Evaluate
Implement
Execution Plan
Minimize
Changes
Finalize
Operating Plan
Business Plan
for Phase 5
Project Review
1 2 3 4 5
AFE
Various Cost Estimates Are Prepared
During the Project Development Process
Process Industry Classification Matrix
Primary Characteristic Secondary Characteristics
LEVEL OF PROJECT
DEFINITION
END USAGE METHODOLOGY ACCURACY RANGE
PREPARATION
EFFORT
ESTIMATE
CLASS
Expressed as % of
complete definition
Typical purpose of
estimate
Typical Estimating
Method
Typical variation in low
and high ranges (a)
Typical degree of effort
relative to least cost
indice of 1 (b)
5 0% to 2% Concept Screening
Capacity Factored,
Parametric Models,
Judgement, or Analogy
-20% to -50%
+30% to +100%
1
4 1% to 15% Study or Feasability
Equipment Factored, or
Parametric Models
-15% to -30%
+20% to +50%
2 to 4
3 10% to 40%
Budget, Authorization,
or Control
Semi-Detailed Unit
Costs w/ Assembly
Level Line Items
-10% to -20%
+10% to +30%
3 to 10
2 30% to 70% Control or Bid/Tender
Detailed Unit Cost w/
Forced Detailed Takeoff
-5% to -15%
+5% to +20%
4 to 20
1 50% to 100%
Check Estimate or
Bid/Tender
Detailed Unit Cost w/
Detailed Takeoff
-3% to -10%
+3% to +15%
5 to 100
Notes: a) The state of process technology and availability of applicable reference cost data affect the range
markedly. The +/- value represents typical percentage variation of actual costs from the cost estimate after
application of contingency (typically at a 50% level of confidence) for given scope.
b) If the range indice value of "1" represents .005%, then an indice value of 100 represents 0.5%
Estimate preparation effort is highly dependent upon the size of the project and the quality of estimating
data and tools.
Estimate Input Checklist and Maturity Matrix
Estimate Classification
CLASS 5 CLASS 4 CLASS 3 CLASS 2 CLASS 1
General Project Data
Project Scope Description General Preliminary Defined Defined Defined
Plant Production/Facility Capacity Assumed Preliminary Defined Defined Defined
Plant Location General Approximate Specific Specific Specific
Soils & Hydrology None Preliminary Defined Defined Defined
Integrated Project Plan None Preliminary Defined Defined Defined
Project Master Schedule None Preliminary Defined Defined Defined
Escalation Strategy None Preliminary Defined Defined Defined
Work Breakdown Structure None Preliminary Defined Defined Defined
Project Code of Accounts None Preliminary Defined Defined Defined
Contracting Strategy Assumed Assumed Preliminary Defined Defined
Engineering Deliverables
Block Flow Diagrams S/P P/C C C C
Plot Plans S P/C C C
Process Flow Diagrams (PFD's) S/P P/C C C
Utility Flow Diagrams (UFD's) S/P P/C C C
Piping & Instrument Diagrams (P&ID's) S P/C C C
Heat & Material Balances S P/C C C
Process Equipment List S/P P/C C C
Utility Equipment List S/P P/C C C
Electrical One-Line Drawings S/P P/C C C
Specifications & Datasheets S P/C C C
General Equipment Arrangement Drawings S P/C C C
Spare Parts Listings S/P P C
Mechanical Discipline Drawings S P P/C
Electrical Discipline Drawings S P P/C
Instrumentation/Control System Discipline Drawings S P P/C
Civi/Structural/Site Discipline Drawings S P P/C
Estimate Review / Validation Checklist
• Total Engineering Completeness - (%) at the time of
MTO creation – primary determination of accuracy and
estimate classification
• Project Estimating Plan – developed, reviewed, agreed
upon by all parties, signed off before start of estimate
• Basis of Estimate – prepared by estimating provider,
reflecting the completed estimate
Estimate Review / Validation Checklist
• Estimate Summary – with a defined WBS / COA
structure
• Estimate Detail – transparent and easily followed that is
in-line with the estimate summary
• Estimate Cost Metrics – how closely are estimated costs
in-line with defendable historical cost metrics (from
established actual costs not estimated costs)
Estimate Review / Validation Checklist
• Estimate Reconciliation – differences and similarities
between Previous estimates for this project or similar
projects
• Estimate Deliverables Checklist – what were the
deliverables utilized to produce the estimate. Who
produced them & when were they available to
estimating (Primary indicator of completeness of scope)
• Project Risk Analysis and Risk Logs – how was
contingency developed and its statistical significance?
How was risk identified and mitigated?
Estimate Review / Validation Checklist
• Material Take Offs – how were MTOs created, by whom
and when in the process? How were updates handled?
Trace MTOs from creation to the estimate
• Equipment pricing – how much is equipment pricing is
from quotes, from historical data or allowances?
• Equipment Bid Tabs – What is the project philosophy
regarding the selection of equipment pricing? Are the
costs in the estimate traceable to quotes?
• Change Management Plan and Change Logs – how is
scope being managed?
Conclusions
• Utilizing the Checklist a reviewer will understand the
development of the project cost and their completeness
and degree of accuracy
• Any items not available will indicate areas of concern
and places to focus greater attention
• But most importantly the checklist, if utilized by
estimating providers and project teams as a guide
during the complete project process, will produce
project costs that will be better understood and
manageable to all project stakeholders.

More Related Content

What's hot

4 an activity analysis of project scheduling problem a case study 1
4 an activity analysis of project scheduling problem   a case study 14 an activity analysis of project scheduling problem   a case study 1
4 an activity analysis of project scheduling problem a case study 1
pmb25
 
Schedule Updates
Schedule UpdatesSchedule Updates
Schedule Updates
Chris Carson
 
30 60 90 percent ifc engineering what is the project progress - Oracle Prim...
30 60 90 percent ifc engineering   what is the project progress - Oracle Prim...30 60 90 percent ifc engineering   what is the project progress - Oracle Prim...
30 60 90 percent ifc engineering what is the project progress - Oracle Prim...
p6academy
 
Schedule Recovery Using Earned Value
Schedule Recovery Using Earned ValueSchedule Recovery Using Earned Value
Schedule Recovery Using Earned Value
Chris Carson
 
BRQ_PortfolioMgmt BRQPresentation
BRQ_PortfolioMgmt BRQPresentationBRQ_PortfolioMgmt BRQPresentation
BRQ_PortfolioMgmt BRQPresentation
Kyle D. Gearhart
 
IWP Timeline
IWP TimelineIWP Timeline
IWP Timeline
Scot Fyfe
 
Session 13 4th edition PMP
Session 13 4th edition PMPSession 13 4th edition PMP
Session 13 4th edition PMP
محمد عصمت عبد الرازق
 
Quality control inspection reports and outcomes wrt contract management
Quality control inspection reports and outcomes wrt contract managementQuality control inspection reports and outcomes wrt contract management
Quality control inspection reports and outcomes wrt contract management
EdwinJacob5
 
Implementation
ImplementationImplementation
Implementation
dbgray00
 
Project Controls Expo 09/10 Nov London 2011 - An Introduction to Performance ...
Project Controls Expo 09/10 Nov London 2011 - An Introduction to Performance ...Project Controls Expo 09/10 Nov London 2011 - An Introduction to Performance ...
Project Controls Expo 09/10 Nov London 2011 - An Introduction to Performance ...
Project Controls Expo
 
Project Scheduling and Control Projects
Project Scheduling and Control ProjectsProject Scheduling and Control Projects
Project Scheduling and Control Projects
haroldtaylor1113
 
Perform quantitative risk analysis
Perform quantitative risk analysis Perform quantitative risk analysis
Perform quantitative risk analysis
Shereef Sabri
 
Major Release Initial Planning Review
Major Release Initial Planning ReviewMajor Release Initial Planning Review
Major Release Initial Planning Review
Mike Wienold
 
EXTENSION OF TIME CLAIMS IN OIL AND GAS CONSTRUCTION PROJECTS
 EXTENSION OF TIME CLAIMS IN OIL AND GAS CONSTRUCTION PROJECTS EXTENSION OF TIME CLAIMS IN OIL AND GAS CONSTRUCTION PROJECTS
EXTENSION OF TIME CLAIMS IN OIL AND GAS CONSTRUCTION PROJECTS
HossamNegidaPMPRMPPS
 
Building a Better PPAP Experience
Building a Better PPAP ExperienceBuilding a Better PPAP Experience
Building a Better PPAP Experience
Peter Patrou
 
Favorite Delay Analysis Methodologies Town Hall SEI
Favorite Delay Analysis Methodologies Town Hall SEIFavorite Delay Analysis Methodologies Town Hall SEI
Favorite Delay Analysis Methodologies Town Hall SEI
Chris Carson
 
CDS Construction Execution Process ^0 Strategy
CDS Construction Execution Process ^0 StrategyCDS Construction Execution Process ^0 Strategy
CDS Construction Execution Process ^0 Strategy
Robert Doig
 
Marshall Esc Lille Defense R2
Marshall Esc Lille Defense R2Marshall Esc Lille Defense R2
Marshall Esc Lille Defense R2
Drmarshallpmp
 
Improving engineering productivity_loss_zhao-dungan
Improving engineering productivity_loss_zhao-dunganImproving engineering productivity_loss_zhao-dungan
Improving engineering productivity_loss_zhao-dungan
ignitetribes
 
How to build a credible performance measurement baseline (v5)
How to build a credible performance measurement baseline (v5)How to build a credible performance measurement baseline (v5)
How to build a credible performance measurement baseline (v5)
Glen Alleman
 

What's hot (20)

4 an activity analysis of project scheduling problem a case study 1
4 an activity analysis of project scheduling problem   a case study 14 an activity analysis of project scheduling problem   a case study 1
4 an activity analysis of project scheduling problem a case study 1
 
Schedule Updates
Schedule UpdatesSchedule Updates
Schedule Updates
 
30 60 90 percent ifc engineering what is the project progress - Oracle Prim...
30 60 90 percent ifc engineering   what is the project progress - Oracle Prim...30 60 90 percent ifc engineering   what is the project progress - Oracle Prim...
30 60 90 percent ifc engineering what is the project progress - Oracle Prim...
 
Schedule Recovery Using Earned Value
Schedule Recovery Using Earned ValueSchedule Recovery Using Earned Value
Schedule Recovery Using Earned Value
 
BRQ_PortfolioMgmt BRQPresentation
BRQ_PortfolioMgmt BRQPresentationBRQ_PortfolioMgmt BRQPresentation
BRQ_PortfolioMgmt BRQPresentation
 
IWP Timeline
IWP TimelineIWP Timeline
IWP Timeline
 
Session 13 4th edition PMP
Session 13 4th edition PMPSession 13 4th edition PMP
Session 13 4th edition PMP
 
Quality control inspection reports and outcomes wrt contract management
Quality control inspection reports and outcomes wrt contract managementQuality control inspection reports and outcomes wrt contract management
Quality control inspection reports and outcomes wrt contract management
 
Implementation
ImplementationImplementation
Implementation
 
Project Controls Expo 09/10 Nov London 2011 - An Introduction to Performance ...
Project Controls Expo 09/10 Nov London 2011 - An Introduction to Performance ...Project Controls Expo 09/10 Nov London 2011 - An Introduction to Performance ...
Project Controls Expo 09/10 Nov London 2011 - An Introduction to Performance ...
 
Project Scheduling and Control Projects
Project Scheduling and Control ProjectsProject Scheduling and Control Projects
Project Scheduling and Control Projects
 
Perform quantitative risk analysis
Perform quantitative risk analysis Perform quantitative risk analysis
Perform quantitative risk analysis
 
Major Release Initial Planning Review
Major Release Initial Planning ReviewMajor Release Initial Planning Review
Major Release Initial Planning Review
 
EXTENSION OF TIME CLAIMS IN OIL AND GAS CONSTRUCTION PROJECTS
 EXTENSION OF TIME CLAIMS IN OIL AND GAS CONSTRUCTION PROJECTS EXTENSION OF TIME CLAIMS IN OIL AND GAS CONSTRUCTION PROJECTS
EXTENSION OF TIME CLAIMS IN OIL AND GAS CONSTRUCTION PROJECTS
 
Building a Better PPAP Experience
Building a Better PPAP ExperienceBuilding a Better PPAP Experience
Building a Better PPAP Experience
 
Favorite Delay Analysis Methodologies Town Hall SEI
Favorite Delay Analysis Methodologies Town Hall SEIFavorite Delay Analysis Methodologies Town Hall SEI
Favorite Delay Analysis Methodologies Town Hall SEI
 
CDS Construction Execution Process ^0 Strategy
CDS Construction Execution Process ^0 StrategyCDS Construction Execution Process ^0 Strategy
CDS Construction Execution Process ^0 Strategy
 
Marshall Esc Lille Defense R2
Marshall Esc Lille Defense R2Marshall Esc Lille Defense R2
Marshall Esc Lille Defense R2
 
Improving engineering productivity_loss_zhao-dungan
Improving engineering productivity_loss_zhao-dunganImproving engineering productivity_loss_zhao-dungan
Improving engineering productivity_loss_zhao-dungan
 
How to build a credible performance measurement baseline (v5)
How to build a credible performance measurement baseline (v5)How to build a credible performance measurement baseline (v5)
How to build a credible performance measurement baseline (v5)
 

Similar to 2015 Toronto Section Presentation

Capital Expenditure Estimating Cost of Project
Capital Expenditure Estimating Cost of ProjectCapital Expenditure Estimating Cost of Project
Capital Expenditure Estimating Cost of Project
ArvinThamsir1
 
Capital Cost Expenditure Estimating .ppt
Capital Cost Expenditure Estimating .pptCapital Cost Expenditure Estimating .ppt
Capital Cost Expenditure Estimating .ppt
ArvinThamsir1
 
Schedule Review PMI
Schedule Review PMISchedule Review PMI
Schedule Review PMI
Chris Carson
 
NASA Project Management Wall Chart
NASA Project Management Wall ChartNASA Project Management Wall Chart
NASA Project Management Wall Chart
Carlos Duarte
 
Practical Application of Value Engineering in Capital Projects
Practical Application of Value Engineering in Capital ProjectsPractical Application of Value Engineering in Capital Projects
Practical Application of Value Engineering in Capital Projects
PMA Consultants
 
Remade Slides.pptx
Remade Slides.pptxRemade Slides.pptx
Remade Slides.pptx
AshokKumar705948
 
Major CAPEX Project Success Assurance-Best Practices and Lessons Learned
Major CAPEX Project Success Assurance-Best Practices and Lessons LearnedMajor CAPEX Project Success Assurance-Best Practices and Lessons Learned
Major CAPEX Project Success Assurance-Best Practices and Lessons Learned
Energy Construction Forum
 
CompTIA Project+ Objectives
CompTIA Project+ ObjectivesCompTIA Project+ Objectives
CompTIA Project+ Objectives
sombat nirund
 
Mitigation And Performance Recovery Using Earned Value
Mitigation And Performance Recovery Using Earned ValueMitigation And Performance Recovery Using Earned Value
Mitigation And Performance Recovery Using Earned Value
Chris Carson
 
Day 1 1620 - 1705 - maple - pranabendu bhattacharyya
Day 1   1620 - 1705 - maple - pranabendu bhattacharyyaDay 1   1620 - 1705 - maple - pranabendu bhattacharyya
Day 1 1620 - 1705 - maple - pranabendu bhattacharyya
PMI2011
 
Day1 1620-1705-maple-pranabendubhattacharyya-131008043643-phpapp02
Day1 1620-1705-maple-pranabendubhattacharyya-131008043643-phpapp02Day1 1620-1705-maple-pranabendubhattacharyya-131008043643-phpapp02
Day1 1620-1705-maple-pranabendubhattacharyya-131008043643-phpapp02
PMI_IREP_TP
 
Intergrated baseline reviews as a tool in assurance
Intergrated baseline reviews as a tool in assurance Intergrated baseline reviews as a tool in assurance
Intergrated baseline reviews as a tool in assurance
Association for Project Management
 
Project Cost Management for IEM talk on 13 January 2018.
Project Cost Management  for IEM talk on 13 January 2018.Project Cost Management  for IEM talk on 13 January 2018.
Project Cost Management for IEM talk on 13 January 2018.
Ir.Noor Iziddin,PMP, P.Eng,REEM,CCPM,TTT.
 
Information Technology Project Management
Information Technology Project ManagementInformation Technology Project Management
Information Technology Project Management
Goutama Bachtiar
 
Using Earned Value Management Concepts to Improve Commercial Project Performance
Using Earned Value Management Concepts to Improve Commercial Project PerformanceUsing Earned Value Management Concepts to Improve Commercial Project Performance
Using Earned Value Management Concepts to Improve Commercial Project Performance
LewisFowlerLLC
 
E success client-software-development
E success client-software-developmentE success client-software-development
E success client-software-development
Riyaan Sharma
 
7.2 Estimate Cost
7.2 Estimate Cost7.2 Estimate Cost
7.2 Estimate Cost
DavidMcLachlan1
 
Pm audit and assessment approach final
Pm audit and assessment approach   finalPm audit and assessment approach   final
Pm audit and assessment approach final
Project Management Solutions
 
2005.04.04.cpp.project.management.adb
2005.04.04.cpp.project.management.adb2005.04.04.cpp.project.management.adb
2005.04.04.cpp.project.management.adb
ngocjos
 
Using Benchmarking to Quantify the Benefits of Software Process Improvement
Using Benchmarking to Quantify the Benefits of Software Process ImprovementUsing Benchmarking to Quantify the Benefits of Software Process Improvement
Using Benchmarking to Quantify the Benefits of Software Process Improvement
Quantitative Software Management, Inc.
 

Similar to 2015 Toronto Section Presentation (20)

Capital Expenditure Estimating Cost of Project
Capital Expenditure Estimating Cost of ProjectCapital Expenditure Estimating Cost of Project
Capital Expenditure Estimating Cost of Project
 
Capital Cost Expenditure Estimating .ppt
Capital Cost Expenditure Estimating .pptCapital Cost Expenditure Estimating .ppt
Capital Cost Expenditure Estimating .ppt
 
Schedule Review PMI
Schedule Review PMISchedule Review PMI
Schedule Review PMI
 
NASA Project Management Wall Chart
NASA Project Management Wall ChartNASA Project Management Wall Chart
NASA Project Management Wall Chart
 
Practical Application of Value Engineering in Capital Projects
Practical Application of Value Engineering in Capital ProjectsPractical Application of Value Engineering in Capital Projects
Practical Application of Value Engineering in Capital Projects
 
Remade Slides.pptx
Remade Slides.pptxRemade Slides.pptx
Remade Slides.pptx
 
Major CAPEX Project Success Assurance-Best Practices and Lessons Learned
Major CAPEX Project Success Assurance-Best Practices and Lessons LearnedMajor CAPEX Project Success Assurance-Best Practices and Lessons Learned
Major CAPEX Project Success Assurance-Best Practices and Lessons Learned
 
CompTIA Project+ Objectives
CompTIA Project+ ObjectivesCompTIA Project+ Objectives
CompTIA Project+ Objectives
 
Mitigation And Performance Recovery Using Earned Value
Mitigation And Performance Recovery Using Earned ValueMitigation And Performance Recovery Using Earned Value
Mitigation And Performance Recovery Using Earned Value
 
Day 1 1620 - 1705 - maple - pranabendu bhattacharyya
Day 1   1620 - 1705 - maple - pranabendu bhattacharyyaDay 1   1620 - 1705 - maple - pranabendu bhattacharyya
Day 1 1620 - 1705 - maple - pranabendu bhattacharyya
 
Day1 1620-1705-maple-pranabendubhattacharyya-131008043643-phpapp02
Day1 1620-1705-maple-pranabendubhattacharyya-131008043643-phpapp02Day1 1620-1705-maple-pranabendubhattacharyya-131008043643-phpapp02
Day1 1620-1705-maple-pranabendubhattacharyya-131008043643-phpapp02
 
Intergrated baseline reviews as a tool in assurance
Intergrated baseline reviews as a tool in assurance Intergrated baseline reviews as a tool in assurance
Intergrated baseline reviews as a tool in assurance
 
Project Cost Management for IEM talk on 13 January 2018.
Project Cost Management  for IEM talk on 13 January 2018.Project Cost Management  for IEM talk on 13 January 2018.
Project Cost Management for IEM talk on 13 January 2018.
 
Information Technology Project Management
Information Technology Project ManagementInformation Technology Project Management
Information Technology Project Management
 
Using Earned Value Management Concepts to Improve Commercial Project Performance
Using Earned Value Management Concepts to Improve Commercial Project PerformanceUsing Earned Value Management Concepts to Improve Commercial Project Performance
Using Earned Value Management Concepts to Improve Commercial Project Performance
 
E success client-software-development
E success client-software-developmentE success client-software-development
E success client-software-development
 
7.2 Estimate Cost
7.2 Estimate Cost7.2 Estimate Cost
7.2 Estimate Cost
 
Pm audit and assessment approach final
Pm audit and assessment approach   finalPm audit and assessment approach   final
Pm audit and assessment approach final
 
2005.04.04.cpp.project.management.adb
2005.04.04.cpp.project.management.adb2005.04.04.cpp.project.management.adb
2005.04.04.cpp.project.management.adb
 
Using Benchmarking to Quantify the Benefits of Software Process Improvement
Using Benchmarking to Quantify the Benefits of Software Process ImprovementUsing Benchmarking to Quantify the Benefits of Software Process Improvement
Using Benchmarking to Quantify the Benefits of Software Process Improvement
 

2015 Toronto Section Presentation

  • 1. Estimate Review / Validation Checklist Douglas W. Leo CCP CEP FAACE FRICS Saybrook Associates, Inc. Chair AACE International Estimating Sub-Committee
  • 2. AACE Recommended Practices • Cost Engineers Tool Kit - – RP 10S-90 Cost Engineering Terminology – RP 18R-97 Cost Estimating Classification System – RP 21R-98 Project Code of Accounts – RP 27R-03 Schedule Classification Systems – RP 30R-03 Implementing Project Constructability – RP31R-03 Reviewing, Validating and Documenting an Estimate – RP34R-05 Basis of Estimate – RP 36R-08 Development of Cost Estimating Plans – RP 38R-06 Documenting the Schedule Basis
  • 3. Review/Validation Checklist - Introduction The Project Cost Estimate that was just delivered is amazing. It is exactly what was expected, costs were immediately understandable and lower than anticipated. Management will love this. The work on this project estimate is worthy of great praise …… outstanding job!!!! Were these words ever spoken outside of someone’s dreams? …….. I think not.
  • 4. Review / Validation Checklist Introduction • Project Teams universally have the desire to produce successful outcomes. • They all want their work to be seen as on time, on budget, and meeting the desire functionality. • The desire is for a completed project package that is: – Transparent – Explainable – Defendable – Acceptable to management
  • 5. Review / Validation Checklist Introduction • Three main project drivers: Functionality, Schedule, Cost • Over the course of the project there is shifting importance for the three drivers but at some point costs become the main issue with regards to moving the project forward. • When costs become the main focus, a thorough understanding of the project estimate and how it was developed is the task at hand. • A review and validation takes place at multiple levels: internally by the estimating provider, by the owner client, by third party reviewers
  • 6. Review / Validation Checklist Introduction Completed project estimating package should always include certain elements: • Basis of Estimate • Estimate Summary • Estimate Detail • Reconciliation Report • Historical Cost Metric Report • Estimate Deliverables Report • Risk Analysis Report
  • 7. PHASE 2 SELECT from Alternatives Clearly Frame Goal Test for Strategic Fit Preliminary Overall Plan Preliminary Assessment ~1 % Engr. AACE Class 5 Cost Estimate PHASE 1 IDENTIFY & Assess Opportunity Fully Define Scope Develop Detailed Execution Plans Refine Estimate Submit Funding for Approval ~25 % Engr. AACE Class 3 Cost Estimate Generate Alternatives Preliminary Development of Alternatives Develop Expected Value Identify Preferred Alternative AACE Class 4 Cost Estimate Operate Asset Monitor & Evaluate Performance Identify New Opportunities PHASE 3 DEVELOP Preferred Alternative PHASE 4 EXECUTE (Detail EPC) PHASE 5 OPERATE & Evaluate Implement Execution Plan Minimize Changes Finalize Operating Plan Business Plan for Phase 5 Project Review 1 2 3 4 5 AFE Various Cost Estimates Are Prepared During the Project Development Process
  • 8. Process Industry Classification Matrix Primary Characteristic Secondary Characteristics LEVEL OF PROJECT DEFINITION END USAGE METHODOLOGY ACCURACY RANGE PREPARATION EFFORT ESTIMATE CLASS Expressed as % of complete definition Typical purpose of estimate Typical Estimating Method Typical variation in low and high ranges (a) Typical degree of effort relative to least cost indice of 1 (b) 5 0% to 2% Concept Screening Capacity Factored, Parametric Models, Judgement, or Analogy -20% to -50% +30% to +100% 1 4 1% to 15% Study or Feasability Equipment Factored, or Parametric Models -15% to -30% +20% to +50% 2 to 4 3 10% to 40% Budget, Authorization, or Control Semi-Detailed Unit Costs w/ Assembly Level Line Items -10% to -20% +10% to +30% 3 to 10 2 30% to 70% Control or Bid/Tender Detailed Unit Cost w/ Forced Detailed Takeoff -5% to -15% +5% to +20% 4 to 20 1 50% to 100% Check Estimate or Bid/Tender Detailed Unit Cost w/ Detailed Takeoff -3% to -10% +3% to +15% 5 to 100 Notes: a) The state of process technology and availability of applicable reference cost data affect the range markedly. The +/- value represents typical percentage variation of actual costs from the cost estimate after application of contingency (typically at a 50% level of confidence) for given scope. b) If the range indice value of "1" represents .005%, then an indice value of 100 represents 0.5% Estimate preparation effort is highly dependent upon the size of the project and the quality of estimating data and tools.
  • 9. Estimate Input Checklist and Maturity Matrix Estimate Classification CLASS 5 CLASS 4 CLASS 3 CLASS 2 CLASS 1 General Project Data Project Scope Description General Preliminary Defined Defined Defined Plant Production/Facility Capacity Assumed Preliminary Defined Defined Defined Plant Location General Approximate Specific Specific Specific Soils & Hydrology None Preliminary Defined Defined Defined Integrated Project Plan None Preliminary Defined Defined Defined Project Master Schedule None Preliminary Defined Defined Defined Escalation Strategy None Preliminary Defined Defined Defined Work Breakdown Structure None Preliminary Defined Defined Defined Project Code of Accounts None Preliminary Defined Defined Defined Contracting Strategy Assumed Assumed Preliminary Defined Defined Engineering Deliverables Block Flow Diagrams S/P P/C C C C Plot Plans S P/C C C Process Flow Diagrams (PFD's) S/P P/C C C Utility Flow Diagrams (UFD's) S/P P/C C C Piping & Instrument Diagrams (P&ID's) S P/C C C Heat & Material Balances S P/C C C Process Equipment List S/P P/C C C Utility Equipment List S/P P/C C C Electrical One-Line Drawings S/P P/C C C Specifications & Datasheets S P/C C C General Equipment Arrangement Drawings S P/C C C Spare Parts Listings S/P P C Mechanical Discipline Drawings S P P/C Electrical Discipline Drawings S P P/C Instrumentation/Control System Discipline Drawings S P P/C Civi/Structural/Site Discipline Drawings S P P/C
  • 10. Estimate Review / Validation Checklist • Total Engineering Completeness - (%) at the time of MTO creation – primary determination of accuracy and estimate classification • Project Estimating Plan – developed, reviewed, agreed upon by all parties, signed off before start of estimate • Basis of Estimate – prepared by estimating provider, reflecting the completed estimate
  • 11. Estimate Review / Validation Checklist • Estimate Summary – with a defined WBS / COA structure • Estimate Detail – transparent and easily followed that is in-line with the estimate summary • Estimate Cost Metrics – how closely are estimated costs in-line with defendable historical cost metrics (from established actual costs not estimated costs)
  • 12. Estimate Review / Validation Checklist • Estimate Reconciliation – differences and similarities between Previous estimates for this project or similar projects • Estimate Deliverables Checklist – what were the deliverables utilized to produce the estimate. Who produced them & when were they available to estimating (Primary indicator of completeness of scope) • Project Risk Analysis and Risk Logs – how was contingency developed and its statistical significance? How was risk identified and mitigated?
  • 13. Estimate Review / Validation Checklist • Material Take Offs – how were MTOs created, by whom and when in the process? How were updates handled? Trace MTOs from creation to the estimate • Equipment pricing – how much is equipment pricing is from quotes, from historical data or allowances? • Equipment Bid Tabs – What is the project philosophy regarding the selection of equipment pricing? Are the costs in the estimate traceable to quotes? • Change Management Plan and Change Logs – how is scope being managed?
  • 14. Conclusions • Utilizing the Checklist a reviewer will understand the development of the project cost and their completeness and degree of accuracy • Any items not available will indicate areas of concern and places to focus greater attention • But most importantly the checklist, if utilized by estimating providers and project teams as a guide during the complete project process, will produce project costs that will be better understood and manageable to all project stakeholders.