This document outlines the key stages in a project initiation and engineering process. It discusses project licensing, conceptual design, basic engineering, front-end engineering design, and detailed engineering. It also covers types of project cost estimates including order of magnitude estimates (+/- 60%), study estimates (+/- 30%), preliminary estimates (+/- 20%), definitive estimates (+/- 10%), and detailed estimates (+/- 5%). Accurate cost estimates are important for assessing funding needs, economic viability, and avoiding under- or over-funding of projects.