SlideShare a Scribd company logo
1 of 34
BALANCED CANTILEVER BRIDGE
SRINIVAS REDDY.S
What is balanced Cantilever method of Bridge Construction :
• The balanced cantilever method of bridge construction used for bridges with few spans ranging
from 50 to 250m. The bridge can be either cast-in-place or precast.
• Moreover, the basic concept of balanced cantilever construction method is to attach the segments
in an alternate manner at opposite ends of cantilevers supported by piers.
• Furthermore, this method is easily adaptable to irregular and long span lengths, congested project
sites, rough and water terrain, rail crossings, and environmentally sensitive areas.
• Additionally, it is highly suitable for building cable-stayed bridges. This is because once segments
are placed, they will be supported by new cable-stays in each erection stage. Therefore, no
auxiliary supports are required, and hence it is both economical and practical method for long
cable-stayed bridges.
ADVANTAGES OF SIMPLY SUPPORTED AS WELLAS
CONTINUOUS STRUCTURES
• The structures are statically determinate and the moments, shears etc., may be
found out by the basic rules of statics and
• The possibility of cracks due to unequal settlement of the foundations is
eliminated.
This type of structure is also comparable to some extent with continuous
structures since the free positive moment at mid-span is partly balanced by the
negative moment caused by the cantilever and thereby leads to economy in
materials.
• Balanced cantilever bridges also require one line of bearings over the piers similar
to continuous bridges.
• For bridging smaller channels, usually one central longer span with two shorter
end spans of the types as shown in Fig 1 a and 1 b are adopted but where the
bridge length is more, repetition of the type of span illustrated in Fig 2 is resorted
to.
FIG 1 : BALANCED CANTILEVER BRIDGES
FIG 2 : MULTISPAN BALANCED CANTILEVER BRIDGES
PROPORTIONING OF MEMBERS
• To get the most economical design, the proportioning of the members should be such that the
sections at mid-span and at support satisfy both the structural and architectural requirements and at
the same time require minimum quantity of materials.
• To achieve this, the cantilever lengths are usually made from 0.20 to 0.30 of the main span. This
ratio depends on the length of the main span and the type of suspended span the cantilever has to
support as well as the number of cantilevers (single or double) available for balancing the mid-span
positive moment etc.
• Types of Superstructure:
• The superstructures may be of solid slab, T-beam and slab, hollow box girder etc. Photograph 3
shows one hollow-box balanced cantilever bridge.
CANTILEVER CONSTRUCTION METHOD
• Cantilever construction method
• Very ancient technique
• Structure is built component by component above ground level
• Most recent : construction of cable stayed bridges, extra-dosed bridges etc
• Prestressed concrete bridges:
Cast in-situ segments or pre-cast segments
Integral with pier or on bearing
3.Construction sequences :
A. Pier head: on ground supported staging
B. Most of segments:
• Erect/cast using segment lifter/from traveller
• Cantilevered out from preceding segment
• Prestressing tendons running one of the cantilever to the other are stressed
• Symmetrical construction to minimize unbalanced moment on substructure and foundation : balanced
cantilever
• Cast portion beyond 0.5 x L of both ends spans ground supported staging
• Cast stitch segments:
Stitch in the end span
Stitch in the mid span
Levels of the cantilever arms being stitched should be matched
C. Segmentation : 2.5m to 4m or even 5m
Construction cycle
Capacity of form traveller/segment lifter
5. Support conditions
• Box girder- on simple bearing
- stability check during construction
-Minimal secondary effect of creep, shrinkage and prestressing
• Box girder integral with intermediate piers
-Check pier for unbalanced moment during construction
-Pronounced secondary effect
Procedure for balanced cantilever method of cast-in-situ bridge
Construction
• After the construction of lower infrastructure of the bridge is
completed, fig.1 Bridge construction begins at each pier.
• Special formwork is positioned and cast-in-situ pier segment is
begun, fig.2. The complete pier segment is then used as an
erection platform to support a form traveler for cast-in-place
segments.
Fig 1: Construction of lower infrastructure of bridge
Fig 2: Position of special formwork
• Thereafter, soffit shuttering, shuttering for web & deck shuttering
is fixed on both sides of pier as shown in fig.3 and fig.4.
Fig.3: Soffit, web, and Deck shuttering
Fig.4: shuttering soffit, web, and decks
• Then concreting is done on both sides of the pier as shown in
fig.5 and fig.6. The segment production rate for form travelers is
usually one segment every 5 days per traveler.
Fig.5: concrete placement
Fig.6: Concrete placement
• Cast-in-situ segments range between 3m to 5m in
length with formwork moving in tandem with each
segment.
• Segment construction is continued until a joining
midpoint is reached where a balanced pair is closed
as demonstrated in fig.7. The construction of closer
section of a bridge is shown in fig.8.
Fig.7: bridge construction progression
Fig.8: Construction of closer section of the bridge
Casting of precast segments
• There are two methods for precast segment casting which include:
• Short line method: In this rate of segment production is slow. Three or
four segments cast at a time.
• Long line method: In this rate of segment production is fast. Segments
equal to one span cast at a time.
Fig.14: Short line segment casting
Fig.15: Long line segment casting
Cast-in-Place Segments Vs precast segments
• Cast-in-place construction proves to be very beneficial when
large, considerably heavy segments are required to be
constructed. So, instead of handling the segments, only
materials have to be transported thus influencing the type
and size of required equipment.
• Alignment variations and corrections are more easily
accommodated in cast-in-place construction; but more
corrections will probably be necessary. The increase in
alignment corrections for cast-in-place construction
compared to precast construction relates directly to the age
of the concrete when loaded. By and large, the concrete is
much younger when loaded in cast-in-place construction.
STUDY AND ANALYSIS OF BALANCED
CANTILEVER BRIDGE AT KOCHI METRO
• the type of bridge in this study is balanced cantilever bridge (Railway bridge), a part of Kochi
Metro Project of Maharajas- Petta stretch at Ernakulum. A cantilever bridge is a bridge built using
cantilevers, structures that project horizontally into space, supported on only one end. It is the fifth
balanced cantilever bridge and first curved balanced cantilever bridge of India. The 90metre span
will be balanced on either end by 65-metre-long concrete spans, taking the total length of the
structure to 220 metres and a curve of 152 m long radius.
• The reason for adopting a cantilever bridge instead of ordinary bridges are the presence of
overhead electric lines of the nearby railway station, underground pipes causing difficulties for
piling, non- availability of vacant space between the tracks for erecting pillar, and to avoid
interruptions of the underneath railway transportation. Due to long span the bridge is constructed as
segments. Segmental bridge construction is one of its specialty. it is even more an engineering
challenge since the span is located at a curve having a 152-metre-long radius. Such spans are
generally made for over bridges carrying vehicles.
methodology
• The details required for analysis are collected from the site and certain parameters are assumed as
per the standard specifications. The study is focused on the deflections of cantilever span under
different loading conditions such as dead load and live loads. The analysis of balanced cantilever
bridge is done using STAAD Pro software and behavior of cantilever bridge is studied by
considering construction methodology, load-deflection characteristics. Since beams curved in plan
cannot be analyzed using STAAD Pro software, the bridge is analyzed as straight.
CAPACITY
• DMC: 191 passengers (Sitting-35, Crush Standing-156)
• TC: 218 passengers (Sitting-44, Crush Standing-174)
• 3 Car Train: 600 Passengers (Sitting-114, Crush Standing-486)
LOAD CALCULATIONS
• Average weight of passenger = 65kg
Coach and bogie is designed for 13 T
Weight of one passenger = 65 x 10 = 650 N
Weight of 600 passengers = 650 x 600 = 390 kN
Weight of coach and bogie = 130 kN
Total weight = 390 + 130= 520 kN
Construction stage analysis
• Since during the construction stage, only self-weight will be acting, therefore self-weight with factor -1 was
assigned to the structure. At this stage bridge will act as a cantilever bridge, so at the free end moments were
released. Using this first load case, bridge was analysed and deflection and bending moment diagrams were
obtained.
Working stage analysis
• During working stage, after prestressing, the bridge will act as a continuous bridge. So in this stage moment
releases were removed. Here live load of metro rolling stock is considered. From the Kochi Metro DPR it
was obtained that train consisting of three-car was 60m in length with concentrated load of 520kN. Thus a
UDL of 8.67kN/m is considered as live load. Two cases were studied to get maximum deflection.
Case:1- Live load given only on one track
• Case:2- Live load given on supports on both tracks
• Case 3: Load given at mid span on single track
• Case 4: Load given at mid span on both the tracks
Results and conclusion
THANKYOU

More Related Content

What's hot

Construction of rigid pavement
Construction of rigid pavementConstruction of rigid pavement
Construction of rigid pavementpradip dangar
 
Bridge loading
Bridge loadingBridge loading
Bridge loadingkapilpant12
 
Presentation on construction of cable stay bridge - a modern technique for su...
Presentation on construction of cable stay bridge - a modern technique for su...Presentation on construction of cable stay bridge - a modern technique for su...
Presentation on construction of cable stay bridge - a modern technique for su...Rajesh Prasad
 
6. BRIDGE ENGINEERING (RBT) 2160603 GTU
6. BRIDGE ENGINEERING (RBT) 2160603 GTU6. BRIDGE ENGINEERING (RBT) 2160603 GTU
6. BRIDGE ENGINEERING (RBT) 2160603 GTUVATSAL PATEL
 
Cable suspension bridge pdf
Cable suspension bridge pdfCable suspension bridge pdf
Cable suspension bridge pdfGaurav Rawat
 
Creep of Rails.pdf
Creep of Rails.pdfCreep of Rails.pdf
Creep of Rails.pdfTVijayaGowri
 
Analysis & design of T-Beam bridge
Analysis & design of T-Beam bridgeAnalysis & design of T-Beam bridge
Analysis & design of T-Beam bridgeElamathy Murugan
 
Truss bridge final presentation
Truss bridge final presentationTruss bridge final presentation
Truss bridge final presentationkaiumbhai
 
Special Concreting Techniques
Special Concreting Techniques Special Concreting Techniques
Special Concreting Techniques GAURAV. H .TANDON
 
Classification of bridges
Classification of bridgesClassification of bridges
Classification of bridgesEddy Ankit Gangani
 
Design of Reinforced Concrete Structure (IS 456:2000)
Design of Reinforced Concrete Structure (IS 456:2000)Design of Reinforced Concrete Structure (IS 456:2000)
Design of Reinforced Concrete Structure (IS 456:2000)MachenLink
 
Sleepers and Ballast
Sleepers and Ballast Sleepers and Ballast
Sleepers and Ballast T.Naga Anusha
 
Well Foundation
Well FoundationWell Foundation
Well Foundationakjain_mkt
 
Failure of weir and barrage
Failure of weir and barrageFailure of weir and barrage
Failure of weir and barrageDivya Vishnoi
 

What's hot (20)

Bridge foundation
Bridge foundationBridge foundation
Bridge foundation
 
Construction of rigid pavement
Construction of rigid pavementConstruction of rigid pavement
Construction of rigid pavement
 
Bridge loading
Bridge loadingBridge loading
Bridge loading
 
Sheet pile presentation
Sheet pile presentationSheet pile presentation
Sheet pile presentation
 
Presentation on construction of cable stay bridge - a modern technique for su...
Presentation on construction of cable stay bridge - a modern technique for su...Presentation on construction of cable stay bridge - a modern technique for su...
Presentation on construction of cable stay bridge - a modern technique for su...
 
6. BRIDGE ENGINEERING (RBT) 2160603 GTU
6. BRIDGE ENGINEERING (RBT) 2160603 GTU6. BRIDGE ENGINEERING (RBT) 2160603 GTU
6. BRIDGE ENGINEERING (RBT) 2160603 GTU
 
Cable suspension bridge pdf
Cable suspension bridge pdfCable suspension bridge pdf
Cable suspension bridge pdf
 
CBR Test
CBR TestCBR Test
CBR Test
 
Fundamentals of-psc-bridge
Fundamentals of-psc-bridgeFundamentals of-psc-bridge
Fundamentals of-psc-bridge
 
Bridge Rule
Bridge RuleBridge Rule
Bridge Rule
 
Creep of Rails.pdf
Creep of Rails.pdfCreep of Rails.pdf
Creep of Rails.pdf
 
Analysis & design of T-Beam bridge
Analysis & design of T-Beam bridgeAnalysis & design of T-Beam bridge
Analysis & design of T-Beam bridge
 
Truss bridge final presentation
Truss bridge final presentationTruss bridge final presentation
Truss bridge final presentation
 
Special Concreting Techniques
Special Concreting Techniques Special Concreting Techniques
Special Concreting Techniques
 
Classification of bridges
Classification of bridgesClassification of bridges
Classification of bridges
 
Pile foundation ppt
Pile foundation pptPile foundation ppt
Pile foundation ppt
 
Design of Reinforced Concrete Structure (IS 456:2000)
Design of Reinforced Concrete Structure (IS 456:2000)Design of Reinforced Concrete Structure (IS 456:2000)
Design of Reinforced Concrete Structure (IS 456:2000)
 
Sleepers and Ballast
Sleepers and Ballast Sleepers and Ballast
Sleepers and Ballast
 
Well Foundation
Well FoundationWell Foundation
Well Foundation
 
Failure of weir and barrage
Failure of weir and barrageFailure of weir and barrage
Failure of weir and barrage
 

Similar to BALANCED CANTILEVER BRIDGE

Bridges in Hilly areas seminar
Bridges in Hilly areas seminarBridges in Hilly areas seminar
Bridges in Hilly areas seminarAbhinav Pateriya
 
2.7 BRIDGE LAUNCHING.ppt
2.7 BRIDGE LAUNCHING.ppt2.7 BRIDGE LAUNCHING.ppt
2.7 BRIDGE LAUNCHING.pptPrasannaRaniB
 
Balanced Cantilever metro bridge.pptx
Balanced Cantilever metro bridge.pptxBalanced Cantilever metro bridge.pptx
Balanced Cantilever metro bridge.pptxLalitIngole1
 
Gaurav-Jhalani-Seminar-ppt.pptx
Gaurav-Jhalani-Seminar-ppt.pptxGaurav-Jhalani-Seminar-ppt.pptx
Gaurav-Jhalani-Seminar-ppt.pptxSanjeevGupta660170
 
1.5 class a,b
1.5 class a,b1.5 class a,b
1.5 class a,bMani Das
 
accelerated bridge construction(ABC)
accelerated bridge construction(ABC)accelerated bridge construction(ABC)
accelerated bridge construction(ABC)varun km
 
Metro rail segments
Metro rail segmentsMetro rail segments
Metro rail segmentsAxay Sharma
 
Essentials slide in bridge construction a guide for bridge designers
Essentials slide in bridge construction a guide for bridge designersEssentials slide in bridge construction a guide for bridge designers
Essentials slide in bridge construction a guide for bridge designersjose bonifacio de souza leite cuadros
 
Segmnetal construction of bridges
Segmnetal construction of bridgesSegmnetal construction of bridges
Segmnetal construction of bridgesCivil Engineers
 
Precast segmental construction of bridges
Precast segmental construction of bridgesPrecast segmental construction of bridges
Precast segmental construction of bridgesmukul srivastava
 
stress ribbon bridge.pptx
stress ribbon bridge.pptxstress ribbon bridge.pptx
stress ribbon bridge.pptxSauravShahane
 
Uses of special kind of technologies for implementation of special kind of st...
Uses of special kind of technologies for implementation of special kind of st...Uses of special kind of technologies for implementation of special kind of st...
Uses of special kind of technologies for implementation of special kind of st...Rajesh Prasad
 
Experimental study of precast portal frame
Experimental study of precast portal frameExperimental study of precast portal frame
Experimental study of precast portal frameSatish Kambaliya
 
Bridge construction (RC girder bridges)
Bridge construction (RC girder bridges)Bridge construction (RC girder bridges)
Bridge construction (RC girder bridges)Mohamed Yassin
 
Running Head BRIDGE DESIGN1BRIDGE DESIGN31.docx
Running Head BRIDGE DESIGN1BRIDGE DESIGN31.docxRunning Head BRIDGE DESIGN1BRIDGE DESIGN31.docx
Running Head BRIDGE DESIGN1BRIDGE DESIGN31.docxtoddr4
 
1. Introduction to Railway engg..pptx
1. Introduction to Railway engg..pptx1. Introduction to Railway engg..pptx
1. Introduction to Railway engg..pptxMayuriPatel90
 
Case study on signature bridge ppt (1)
Case study on signature bridge ppt (1)Case study on signature bridge ppt (1)
Case study on signature bridge ppt (1)varun km
 
Precast Six lane flyover project
Precast Six lane flyover projectPrecast Six lane flyover project
Precast Six lane flyover projectKriShna Sharma
 

Similar to BALANCED CANTILEVER BRIDGE (20)

Bridges in Hilly areas seminar
Bridges in Hilly areas seminarBridges in Hilly areas seminar
Bridges in Hilly areas seminar
 
2.7 BRIDGE LAUNCHING.ppt
2.7 BRIDGE LAUNCHING.ppt2.7 BRIDGE LAUNCHING.ppt
2.7 BRIDGE LAUNCHING.ppt
 
Balanced Cantilever metro bridge.pptx
Balanced Cantilever metro bridge.pptxBalanced Cantilever metro bridge.pptx
Balanced Cantilever metro bridge.pptx
 
Gaurav-Jhalani-Seminar-ppt.pptx
Gaurav-Jhalani-Seminar-ppt.pptxGaurav-Jhalani-Seminar-ppt.pptx
Gaurav-Jhalani-Seminar-ppt.pptx
 
1.5 class a,b
1.5 class a,b1.5 class a,b
1.5 class a,b
 
accelerated bridge construction(ABC)
accelerated bridge construction(ABC)accelerated bridge construction(ABC)
accelerated bridge construction(ABC)
 
Metro rail segments
Metro rail segmentsMetro rail segments
Metro rail segments
 
Essentials slide in bridge construction a guide for bridge designers
Essentials slide in bridge construction a guide for bridge designersEssentials slide in bridge construction a guide for bridge designers
Essentials slide in bridge construction a guide for bridge designers
 
Bridge-SIT-01.pptx
Bridge-SIT-01.pptxBridge-SIT-01.pptx
Bridge-SIT-01.pptx
 
Segmnetal construction of bridges
Segmnetal construction of bridgesSegmnetal construction of bridges
Segmnetal construction of bridges
 
Precast segmental construction of bridges
Precast segmental construction of bridgesPrecast segmental construction of bridges
Precast segmental construction of bridges
 
stress ribbon bridge.pptx
stress ribbon bridge.pptxstress ribbon bridge.pptx
stress ribbon bridge.pptx
 
Uses of special kind of technologies for implementation of special kind of st...
Uses of special kind of technologies for implementation of special kind of st...Uses of special kind of technologies for implementation of special kind of st...
Uses of special kind of technologies for implementation of special kind of st...
 
Experimental study of precast portal frame
Experimental study of precast portal frameExperimental study of precast portal frame
Experimental study of precast portal frame
 
Bridge construction (RC girder bridges)
Bridge construction (RC girder bridges)Bridge construction (RC girder bridges)
Bridge construction (RC girder bridges)
 
Running Head BRIDGE DESIGN1BRIDGE DESIGN31.docx
Running Head BRIDGE DESIGN1BRIDGE DESIGN31.docxRunning Head BRIDGE DESIGN1BRIDGE DESIGN31.docx
Running Head BRIDGE DESIGN1BRIDGE DESIGN31.docx
 
1. Introduction to Railway engg..pptx
1. Introduction to Railway engg..pptx1. Introduction to Railway engg..pptx
1. Introduction to Railway engg..pptx
 
Case study on signature bridge ppt (1)
Case study on signature bridge ppt (1)Case study on signature bridge ppt (1)
Case study on signature bridge ppt (1)
 
Precast Six lane flyover project
Precast Six lane flyover projectPrecast Six lane flyover project
Precast Six lane flyover project
 
Railway over bridge
Railway over bridgeRailway over bridge
Railway over bridge
 

More from srinivas cnu

problems on Staad.pro and analysis of a 5 storey building using Etabs
problems on Staad.pro and analysis of a 5 storey building using Etabsproblems on Staad.pro and analysis of a 5 storey building using Etabs
problems on Staad.pro and analysis of a 5 storey building using Etabssrinivas cnu
 
FLEXURAL VIBRATION OF FIXED SUPPORTED BEAMS
FLEXURAL VIBRATION OF FIXED SUPPORTED BEAMS FLEXURAL VIBRATION OF FIXED SUPPORTED BEAMS
FLEXURAL VIBRATION OF FIXED SUPPORTED BEAMS srinivas cnu
 
PPT PRESENTATION ON COULOMB DAMPING AND VISCOUS DAMPING
PPT PRESENTATION ON  COULOMB DAMPING AND VISCOUS DAMPINGPPT PRESENTATION ON  COULOMB DAMPING AND VISCOUS DAMPING
PPT PRESENTATION ON COULOMB DAMPING AND VISCOUS DAMPINGsrinivas cnu
 
PPT ON DESIGN OF COLUMN BRACES
PPT ON DESIGN OF COLUMN BRACESPPT ON DESIGN OF COLUMN BRACES
PPT ON DESIGN OF COLUMN BRACESsrinivas cnu
 
ADVANCED ANALYSIS OF SPACE STEEL FRAMES
ADVANCED ANALYSIS OF SPACE STEEL FRAMESADVANCED ANALYSIS OF SPACE STEEL FRAMES
ADVANCED ANALYSIS OF SPACE STEEL FRAMESsrinivas cnu
 
SEMINAR PRESENTATION ON BOX CULVERTS
SEMINAR PRESENTATION ON  BOX CULVERTSSEMINAR PRESENTATION ON  BOX CULVERTS
SEMINAR PRESENTATION ON BOX CULVERTSsrinivas cnu
 
Geosynthetics
GeosyntheticsGeosynthetics
Geosyntheticssrinivas cnu
 
Shotcrete concrete
Shotcrete concreteShotcrete concrete
Shotcrete concretesrinivas cnu
 
ppt on Earthquakes
ppt on Earthquakesppt on Earthquakes
ppt on Earthquakessrinivas cnu
 
ppt on Kargil war
ppt on Kargil warppt on Kargil war
ppt on Kargil warsrinivas cnu
 

More from srinivas cnu (11)

problems on Staad.pro and analysis of a 5 storey building using Etabs
problems on Staad.pro and analysis of a 5 storey building using Etabsproblems on Staad.pro and analysis of a 5 storey building using Etabs
problems on Staad.pro and analysis of a 5 storey building using Etabs
 
FLEXURAL VIBRATION OF FIXED SUPPORTED BEAMS
FLEXURAL VIBRATION OF FIXED SUPPORTED BEAMS FLEXURAL VIBRATION OF FIXED SUPPORTED BEAMS
FLEXURAL VIBRATION OF FIXED SUPPORTED BEAMS
 
PPT PRESENTATION ON COULOMB DAMPING AND VISCOUS DAMPING
PPT PRESENTATION ON  COULOMB DAMPING AND VISCOUS DAMPINGPPT PRESENTATION ON  COULOMB DAMPING AND VISCOUS DAMPING
PPT PRESENTATION ON COULOMB DAMPING AND VISCOUS DAMPING
 
PPT ON DESIGN OF COLUMN BRACES
PPT ON DESIGN OF COLUMN BRACESPPT ON DESIGN OF COLUMN BRACES
PPT ON DESIGN OF COLUMN BRACES
 
ADVANCED ANALYSIS OF SPACE STEEL FRAMES
ADVANCED ANALYSIS OF SPACE STEEL FRAMESADVANCED ANALYSIS OF SPACE STEEL FRAMES
ADVANCED ANALYSIS OF SPACE STEEL FRAMES
 
SEMINAR PRESENTATION ON BOX CULVERTS
SEMINAR PRESENTATION ON  BOX CULVERTSSEMINAR PRESENTATION ON  BOX CULVERTS
SEMINAR PRESENTATION ON BOX CULVERTS
 
Geosynthetics
GeosyntheticsGeosynthetics
Geosynthetics
 
Shotcrete concrete
Shotcrete concreteShotcrete concrete
Shotcrete concrete
 
Levelling
LevellingLevelling
Levelling
 
ppt on Earthquakes
ppt on Earthquakesppt on Earthquakes
ppt on Earthquakes
 
ppt on Kargil war
ppt on Kargil warppt on Kargil war
ppt on Kargil war
 

Recently uploaded

Introduction to AI in Higher Education_draft.pptx
Introduction to AI in Higher Education_draft.pptxIntroduction to AI in Higher Education_draft.pptx
Introduction to AI in Higher Education_draft.pptxpboyjonauth
 
Earth Day Presentation wow hello nice great
Earth Day Presentation wow hello nice greatEarth Day Presentation wow hello nice great
Earth Day Presentation wow hello nice greatYousafMalik24
 
Like-prefer-love -hate+verb+ing & silent letters & citizenship text.pdf
Like-prefer-love -hate+verb+ing & silent letters & citizenship text.pdfLike-prefer-love -hate+verb+ing & silent letters & citizenship text.pdf
Like-prefer-love -hate+verb+ing & silent letters & citizenship text.pdfMr Bounab Samir
 
Framing an Appropriate Research Question 6b9b26d93da94caf993c038d9efcdedb.pdf
Framing an Appropriate Research Question 6b9b26d93da94caf993c038d9efcdedb.pdfFraming an Appropriate Research Question 6b9b26d93da94caf993c038d9efcdedb.pdf
Framing an Appropriate Research Question 6b9b26d93da94caf993c038d9efcdedb.pdfUjwalaBharambe
 
Roles & Responsibilities in Pharmacovigilance
Roles & Responsibilities in PharmacovigilanceRoles & Responsibilities in Pharmacovigilance
Roles & Responsibilities in PharmacovigilanceSamikshaHamane
 
AmericanHighSchoolsprezentacijaoskolama.
AmericanHighSchoolsprezentacijaoskolama.AmericanHighSchoolsprezentacijaoskolama.
AmericanHighSchoolsprezentacijaoskolama.arsicmarija21
 
call girls in Kamla Market (DELHI) 🔝 >༒9953330565🔝 genuine Escort Service 🔝✔️✔️
call girls in Kamla Market (DELHI) 🔝 >༒9953330565🔝 genuine Escort Service 🔝✔️✔️call girls in Kamla Market (DELHI) 🔝 >༒9953330565🔝 genuine Escort Service 🔝✔️✔️
call girls in Kamla Market (DELHI) 🔝 >༒9953330565🔝 genuine Escort Service 🔝✔️✔️9953056974 Low Rate Call Girls In Saket, Delhi NCR
 
Types of Journalistic Writing Grade 8.pptx
Types of Journalistic Writing Grade 8.pptxTypes of Journalistic Writing Grade 8.pptx
Types of Journalistic Writing Grade 8.pptxEyham Joco
 
MICROBIOLOGY biochemical test detailed.pptx
MICROBIOLOGY biochemical test detailed.pptxMICROBIOLOGY biochemical test detailed.pptx
MICROBIOLOGY biochemical test detailed.pptxabhijeetpadhi001
 
Procuring digital preservation CAN be quick and painless with our new dynamic...
Procuring digital preservation CAN be quick and painless with our new dynamic...Procuring digital preservation CAN be quick and painless with our new dynamic...
Procuring digital preservation CAN be quick and painless with our new dynamic...Jisc
 
Proudly South Africa powerpoint Thorisha.pptx
Proudly South Africa powerpoint Thorisha.pptxProudly South Africa powerpoint Thorisha.pptx
Proudly South Africa powerpoint Thorisha.pptxthorishapillay1
 
“Oh GOSH! Reflecting on Hackteria's Collaborative Practices in a Global Do-It...
“Oh GOSH! Reflecting on Hackteria's Collaborative Practices in a Global Do-It...“Oh GOSH! Reflecting on Hackteria's Collaborative Practices in a Global Do-It...
“Oh GOSH! Reflecting on Hackteria's Collaborative Practices in a Global Do-It...Marc Dusseiller Dusjagr
 
EPANDING THE CONTENT OF AN OUTLINE using notes.pptx
EPANDING THE CONTENT OF AN OUTLINE using notes.pptxEPANDING THE CONTENT OF AN OUTLINE using notes.pptx
EPANDING THE CONTENT OF AN OUTLINE using notes.pptxRaymartEstabillo3
 
How to Make a Pirate ship Primary Education.pptx
How to Make a Pirate ship Primary Education.pptxHow to Make a Pirate ship Primary Education.pptx
How to Make a Pirate ship Primary Education.pptxmanuelaromero2013
 
Gas measurement O2,Co2,& ph) 04/2024.pptx
Gas measurement O2,Co2,& ph) 04/2024.pptxGas measurement O2,Co2,& ph) 04/2024.pptx
Gas measurement O2,Co2,& ph) 04/2024.pptxDr.Ibrahim Hassaan
 
MARGINALIZATION (Different learners in Marginalized Group
MARGINALIZATION (Different learners in Marginalized GroupMARGINALIZATION (Different learners in Marginalized Group
MARGINALIZATION (Different learners in Marginalized GroupJonathanParaisoCruz
 
Full Stack Web Development Course for Beginners
Full Stack Web Development Course  for BeginnersFull Stack Web Development Course  for Beginners
Full Stack Web Development Course for BeginnersSabitha Banu
 
Capitol Tech U Doctoral Presentation - April 2024.pptx
Capitol Tech U Doctoral Presentation - April 2024.pptxCapitol Tech U Doctoral Presentation - April 2024.pptx
Capitol Tech U Doctoral Presentation - April 2024.pptxCapitolTechU
 
How to Configure Email Server in Odoo 17
How to Configure Email Server in Odoo 17How to Configure Email Server in Odoo 17
How to Configure Email Server in Odoo 17Celine George
 

Recently uploaded (20)

Introduction to AI in Higher Education_draft.pptx
Introduction to AI in Higher Education_draft.pptxIntroduction to AI in Higher Education_draft.pptx
Introduction to AI in Higher Education_draft.pptx
 
Earth Day Presentation wow hello nice great
Earth Day Presentation wow hello nice greatEarth Day Presentation wow hello nice great
Earth Day Presentation wow hello nice great
 
Like-prefer-love -hate+verb+ing & silent letters & citizenship text.pdf
Like-prefer-love -hate+verb+ing & silent letters & citizenship text.pdfLike-prefer-love -hate+verb+ing & silent letters & citizenship text.pdf
Like-prefer-love -hate+verb+ing & silent letters & citizenship text.pdf
 
Framing an Appropriate Research Question 6b9b26d93da94caf993c038d9efcdedb.pdf
Framing an Appropriate Research Question 6b9b26d93da94caf993c038d9efcdedb.pdfFraming an Appropriate Research Question 6b9b26d93da94caf993c038d9efcdedb.pdf
Framing an Appropriate Research Question 6b9b26d93da94caf993c038d9efcdedb.pdf
 
Roles & Responsibilities in Pharmacovigilance
Roles & Responsibilities in PharmacovigilanceRoles & Responsibilities in Pharmacovigilance
Roles & Responsibilities in Pharmacovigilance
 
AmericanHighSchoolsprezentacijaoskolama.
AmericanHighSchoolsprezentacijaoskolama.AmericanHighSchoolsprezentacijaoskolama.
AmericanHighSchoolsprezentacijaoskolama.
 
call girls in Kamla Market (DELHI) 🔝 >༒9953330565🔝 genuine Escort Service 🔝✔️✔️
call girls in Kamla Market (DELHI) 🔝 >༒9953330565🔝 genuine Escort Service 🔝✔️✔️call girls in Kamla Market (DELHI) 🔝 >༒9953330565🔝 genuine Escort Service 🔝✔️✔️
call girls in Kamla Market (DELHI) 🔝 >༒9953330565🔝 genuine Escort Service 🔝✔️✔️
 
Model Call Girl in Tilak Nagar Delhi reach out to us at 🔝9953056974🔝
Model Call Girl in Tilak Nagar Delhi reach out to us at 🔝9953056974🔝Model Call Girl in Tilak Nagar Delhi reach out to us at 🔝9953056974🔝
Model Call Girl in Tilak Nagar Delhi reach out to us at 🔝9953056974🔝
 
Types of Journalistic Writing Grade 8.pptx
Types of Journalistic Writing Grade 8.pptxTypes of Journalistic Writing Grade 8.pptx
Types of Journalistic Writing Grade 8.pptx
 
MICROBIOLOGY biochemical test detailed.pptx
MICROBIOLOGY biochemical test detailed.pptxMICROBIOLOGY biochemical test detailed.pptx
MICROBIOLOGY biochemical test detailed.pptx
 
Procuring digital preservation CAN be quick and painless with our new dynamic...
Procuring digital preservation CAN be quick and painless with our new dynamic...Procuring digital preservation CAN be quick and painless with our new dynamic...
Procuring digital preservation CAN be quick and painless with our new dynamic...
 
Proudly South Africa powerpoint Thorisha.pptx
Proudly South Africa powerpoint Thorisha.pptxProudly South Africa powerpoint Thorisha.pptx
Proudly South Africa powerpoint Thorisha.pptx
 
“Oh GOSH! Reflecting on Hackteria's Collaborative Practices in a Global Do-It...
“Oh GOSH! Reflecting on Hackteria's Collaborative Practices in a Global Do-It...“Oh GOSH! Reflecting on Hackteria's Collaborative Practices in a Global Do-It...
“Oh GOSH! Reflecting on Hackteria's Collaborative Practices in a Global Do-It...
 
EPANDING THE CONTENT OF AN OUTLINE using notes.pptx
EPANDING THE CONTENT OF AN OUTLINE using notes.pptxEPANDING THE CONTENT OF AN OUTLINE using notes.pptx
EPANDING THE CONTENT OF AN OUTLINE using notes.pptx
 
How to Make a Pirate ship Primary Education.pptx
How to Make a Pirate ship Primary Education.pptxHow to Make a Pirate ship Primary Education.pptx
How to Make a Pirate ship Primary Education.pptx
 
Gas measurement O2,Co2,& ph) 04/2024.pptx
Gas measurement O2,Co2,& ph) 04/2024.pptxGas measurement O2,Co2,& ph) 04/2024.pptx
Gas measurement O2,Co2,& ph) 04/2024.pptx
 
MARGINALIZATION (Different learners in Marginalized Group
MARGINALIZATION (Different learners in Marginalized GroupMARGINALIZATION (Different learners in Marginalized Group
MARGINALIZATION (Different learners in Marginalized Group
 
Full Stack Web Development Course for Beginners
Full Stack Web Development Course  for BeginnersFull Stack Web Development Course  for Beginners
Full Stack Web Development Course for Beginners
 
Capitol Tech U Doctoral Presentation - April 2024.pptx
Capitol Tech U Doctoral Presentation - April 2024.pptxCapitol Tech U Doctoral Presentation - April 2024.pptx
Capitol Tech U Doctoral Presentation - April 2024.pptx
 
How to Configure Email Server in Odoo 17
How to Configure Email Server in Odoo 17How to Configure Email Server in Odoo 17
How to Configure Email Server in Odoo 17
 

BALANCED CANTILEVER BRIDGE

  • 2. What is balanced Cantilever method of Bridge Construction : • The balanced cantilever method of bridge construction used for bridges with few spans ranging from 50 to 250m. The bridge can be either cast-in-place or precast. • Moreover, the basic concept of balanced cantilever construction method is to attach the segments in an alternate manner at opposite ends of cantilevers supported by piers. • Furthermore, this method is easily adaptable to irregular and long span lengths, congested project sites, rough and water terrain, rail crossings, and environmentally sensitive areas. • Additionally, it is highly suitable for building cable-stayed bridges. This is because once segments are placed, they will be supported by new cable-stays in each erection stage. Therefore, no auxiliary supports are required, and hence it is both economical and practical method for long cable-stayed bridges.
  • 3. ADVANTAGES OF SIMPLY SUPPORTED AS WELLAS CONTINUOUS STRUCTURES • The structures are statically determinate and the moments, shears etc., may be found out by the basic rules of statics and • The possibility of cracks due to unequal settlement of the foundations is eliminated. This type of structure is also comparable to some extent with continuous structures since the free positive moment at mid-span is partly balanced by the negative moment caused by the cantilever and thereby leads to economy in materials. • Balanced cantilever bridges also require one line of bearings over the piers similar to continuous bridges. • For bridging smaller channels, usually one central longer span with two shorter end spans of the types as shown in Fig 1 a and 1 b are adopted but where the bridge length is more, repetition of the type of span illustrated in Fig 2 is resorted to.
  • 4. FIG 1 : BALANCED CANTILEVER BRIDGES FIG 2 : MULTISPAN BALANCED CANTILEVER BRIDGES
  • 5. PROPORTIONING OF MEMBERS • To get the most economical design, the proportioning of the members should be such that the sections at mid-span and at support satisfy both the structural and architectural requirements and at the same time require minimum quantity of materials. • To achieve this, the cantilever lengths are usually made from 0.20 to 0.30 of the main span. This ratio depends on the length of the main span and the type of suspended span the cantilever has to support as well as the number of cantilevers (single or double) available for balancing the mid-span positive moment etc.
  • 6. • Types of Superstructure: • The superstructures may be of solid slab, T-beam and slab, hollow box girder etc. Photograph 3 shows one hollow-box balanced cantilever bridge.
  • 7. CANTILEVER CONSTRUCTION METHOD • Cantilever construction method • Very ancient technique • Structure is built component by component above ground level • Most recent : construction of cable stayed bridges, extra-dosed bridges etc • Prestressed concrete bridges: Cast in-situ segments or pre-cast segments Integral with pier or on bearing
  • 8.
  • 9.
  • 10. 3.Construction sequences : A. Pier head: on ground supported staging B. Most of segments: • Erect/cast using segment lifter/from traveller • Cantilevered out from preceding segment • Prestressing tendons running one of the cantilever to the other are stressed • Symmetrical construction to minimize unbalanced moment on substructure and foundation : balanced cantilever • Cast portion beyond 0.5 x L of both ends spans ground supported staging • Cast stitch segments: Stitch in the end span Stitch in the mid span Levels of the cantilever arms being stitched should be matched C. Segmentation : 2.5m to 4m or even 5m Construction cycle Capacity of form traveller/segment lifter
  • 11.
  • 12.
  • 13. 5. Support conditions • Box girder- on simple bearing - stability check during construction -Minimal secondary effect of creep, shrinkage and prestressing • Box girder integral with intermediate piers -Check pier for unbalanced moment during construction -Pronounced secondary effect
  • 14.
  • 15.
  • 16.
  • 17.
  • 18. Procedure for balanced cantilever method of cast-in-situ bridge Construction • After the construction of lower infrastructure of the bridge is completed, fig.1 Bridge construction begins at each pier. • Special formwork is positioned and cast-in-situ pier segment is begun, fig.2. The complete pier segment is then used as an erection platform to support a form traveler for cast-in-place segments. Fig 1: Construction of lower infrastructure of bridge
  • 19. Fig 2: Position of special formwork
  • 20. • Thereafter, soffit shuttering, shuttering for web & deck shuttering is fixed on both sides of pier as shown in fig.3 and fig.4. Fig.3: Soffit, web, and Deck shuttering Fig.4: shuttering soffit, web, and decks
  • 21. • Then concreting is done on both sides of the pier as shown in fig.5 and fig.6. The segment production rate for form travelers is usually one segment every 5 days per traveler. Fig.5: concrete placement Fig.6: Concrete placement
  • 22. • Cast-in-situ segments range between 3m to 5m in length with formwork moving in tandem with each segment. • Segment construction is continued until a joining midpoint is reached where a balanced pair is closed as demonstrated in fig.7. The construction of closer section of a bridge is shown in fig.8. Fig.7: bridge construction progression Fig.8: Construction of closer section of the bridge
  • 23. Casting of precast segments • There are two methods for precast segment casting which include: • Short line method: In this rate of segment production is slow. Three or four segments cast at a time. • Long line method: In this rate of segment production is fast. Segments equal to one span cast at a time. Fig.14: Short line segment casting Fig.15: Long line segment casting
  • 24. Cast-in-Place Segments Vs precast segments • Cast-in-place construction proves to be very beneficial when large, considerably heavy segments are required to be constructed. So, instead of handling the segments, only materials have to be transported thus influencing the type and size of required equipment. • Alignment variations and corrections are more easily accommodated in cast-in-place construction; but more corrections will probably be necessary. The increase in alignment corrections for cast-in-place construction compared to precast construction relates directly to the age of the concrete when loaded. By and large, the concrete is much younger when loaded in cast-in-place construction.
  • 25. STUDY AND ANALYSIS OF BALANCED CANTILEVER BRIDGE AT KOCHI METRO • the type of bridge in this study is balanced cantilever bridge (Railway bridge), a part of Kochi Metro Project of Maharajas- Petta stretch at Ernakulum. A cantilever bridge is a bridge built using cantilevers, structures that project horizontally into space, supported on only one end. It is the fifth balanced cantilever bridge and first curved balanced cantilever bridge of India. The 90metre span will be balanced on either end by 65-metre-long concrete spans, taking the total length of the structure to 220 metres and a curve of 152 m long radius. • The reason for adopting a cantilever bridge instead of ordinary bridges are the presence of overhead electric lines of the nearby railway station, underground pipes causing difficulties for piling, non- availability of vacant space between the tracks for erecting pillar, and to avoid interruptions of the underneath railway transportation. Due to long span the bridge is constructed as segments. Segmental bridge construction is one of its specialty. it is even more an engineering challenge since the span is located at a curve having a 152-metre-long radius. Such spans are generally made for over bridges carrying vehicles.
  • 26. methodology • The details required for analysis are collected from the site and certain parameters are assumed as per the standard specifications. The study is focused on the deflections of cantilever span under different loading conditions such as dead load and live loads. The analysis of balanced cantilever bridge is done using STAAD Pro software and behavior of cantilever bridge is studied by considering construction methodology, load-deflection characteristics. Since beams curved in plan cannot be analyzed using STAAD Pro software, the bridge is analyzed as straight.
  • 27.
  • 28. CAPACITY • DMC: 191 passengers (Sitting-35, Crush Standing-156) • TC: 218 passengers (Sitting-44, Crush Standing-174) • 3 Car Train: 600 Passengers (Sitting-114, Crush Standing-486) LOAD CALCULATIONS • Average weight of passenger = 65kg Coach and bogie is designed for 13 T Weight of one passenger = 65 x 10 = 650 N Weight of 600 passengers = 650 x 600 = 390 kN Weight of coach and bogie = 130 kN Total weight = 390 + 130= 520 kN
  • 29. Construction stage analysis • Since during the construction stage, only self-weight will be acting, therefore self-weight with factor -1 was assigned to the structure. At this stage bridge will act as a cantilever bridge, so at the free end moments were released. Using this first load case, bridge was analysed and deflection and bending moment diagrams were obtained.
  • 30. Working stage analysis • During working stage, after prestressing, the bridge will act as a continuous bridge. So in this stage moment releases were removed. Here live load of metro rolling stock is considered. From the Kochi Metro DPR it was obtained that train consisting of three-car was 60m in length with concentrated load of 520kN. Thus a UDL of 8.67kN/m is considered as live load. Two cases were studied to get maximum deflection. Case:1- Live load given only on one track
  • 31. • Case:2- Live load given on supports on both tracks • Case 3: Load given at mid span on single track
  • 32. • Case 4: Load given at mid span on both the tracks