SlideShare a Scribd company logo
Capacity Planning
Factory capacity
• 500 operators working 48 hour week.
• Work content of 30 minutes per garment
• Therefore capacity of 500 x 48x 60
30
= 48000 garments per week
Definitions
• “On –standard” : that time the operator spends on
“measured” work earning Standard Minutes.
• “Off-standard” : that time the operator spends on
“un-measured” work or “measured” work that is
classified as “off-standard”.
Definitions- “Measured work”
• That work to which a standard measure (SMV,
SAM) has been applied.
• Example of “measured work” that may be
classified as “off-standard”. An operator may
whilst learning a new operation be taken off
standard for payment purposes but will still be
contributing SMS as the operation they complete
will have SMV applied.
SMV/SAM?
• Standard Minute Value (S.M.V.) is the time allocated
through work measurement for an operation to be
completed at a 100 rating.
• Standard Allocated (Allotted) Minute (S.A.M.) is an
S.M.V. + any policy allowances added.
Operator Performance
• Primarily a measure of the effectiveness of the individual
operator
• = SMs earned “on standard” x 100
Time spent “on standard”
Sometimes referred to as “Pay” performance as it is usually
measured within an incentive scheme.
Operator utilisation
• A measure of how well the
supervisor manages to keep the
operators “on-standard”
= time “on-standard x 100
time attended
Efficiency
• A measure of how well the
section/factory is run.
= SMs earned x 100
time attended.
• A measure of both the operator
and the supervisor
Efficiency
•Incorporates elements of
operator performance &
utilisation into the single
measure.
Absence/attendance
= total operator time attended x
100
total contracted time
= attendance.
Measures - Examples
• Section = 20 operators working 9 hour/540 minute
day
• 2 operators are absent all day
• Attendance = 18 x 540 x 100
20 x 540
= 9720 = 90% or 10% absence
10800
Measures- examples
• An operator attends for 540 minutes
• Produces 1500 pieces @ SMV of 0.30
• Waits 60 minutes for work
• Waits 20 minutes machine breakdown
Find
• SAM produced?
• On standard time?
• Performance?
• Utilization?
• Efficiency?
Measures- examples
• Sms produced = 1500 x 0.30 = 450.
• Time “on-standard” = 540 – (60+20)
= 460 minutes
• Performance = 450 x 100
460
= 97.8 or 98%
Measures- examples
•Operator utilisation
= 460 x 100 = 85.2%
540
Measures- examples
•Efficiency = 450 x 100
540
= 83%
Exercise- definitions
• Attendance = 4800/5400 = 89%
• total sms earned = 3982.30
Capacity planning - people
• 500 direct operators working 48 hours/week
• S.M.V. = 25 per garment
• Absence level of 8%
• Average efficiency of 85%
• Contracted time 540
1. Calculate standard hour/minutes that can be
produced by operators.
2. Calculate no. of garments produced.
Capacity planning - people
• 500 operators x 48 hours = 24000 contracted
hours
• 24000 – 8% (1920 hours) absence = 22080
attended hours (absence costs 40 operators)
• At efficiency of 85% std. hours produced =
22080 x 85% = 18768 std hrs.
• 5232 hours lost to absence & inefficiency.=
21.8% of original contracted hours
Capacity planning - people
• 18768 std hrs produced
• S.M.V. = 25 mins. or 0.417 std. hrs.
• Garment capacity = 18768
0.417
= 45007 garments.
Capacity planning
• Under the same conditions how many people are
needed to produce 70000 garments per week.?
• 70000 x 0.417 = 29190 standard hours required.
• Each operator will produce 39 hours @ 85%
efficiency
= 39 x 85% = 33.15 std. hrs/week
Capacity planning
• 29190 standard hours required.
• Each operator will produce 33.15 std. hrs/week
• Number of operators = 29190
33.15
= 880.54 people.
• + Absence of 8% = 880.54 +8%.= 951
Capacity planning-machines
• Auto pocket set machine
• S.M.V. 0.60
• Efficiency = 95%
• 15 machines available
• 8.50 hour day
• How many garments can they supply to sections?
Capacity planning-machines
• 15 machines x 8.50 hours = 127.50 hours/day.
• @95% efficiency std. hrs produced = 121.13 hrs
• SMV = 0.60 = 100 per hour at standard
• Output = 100 x 121.13 = 12113 garments
Capacity planning-machines
• Capacity must be increased to 25000 per day.
• Each machine does 100 x 95% = 95 per hour.
25000/95 = 263.15 hours. In 8.5 hour day = 31
machines
Capacity planning-machines
• Each machine will produce 95 per hour worked.
• 25000/95 = 263.15 hours
• 263.15 hours / 15 machines = 17.54 hrs per machine
per day
• 2 shifts
Capacity planning- Department
• Cutting room using semi-auto spreading machines
and computerised cutting head.
• SMV for spreading = 0.1584 per metre
• SMV for cutting = 0.050 per metre
• Average fabric content per gmt. = 90 cms.
• Standard working day= 8.50 hours (39 week)
• 3 spreading machines on 4 tables
• 1 cutting machine.
• Department runs at 90% efficiency and 8% absence
Capacity planning- Exercise
• How many people are needed to supply the factory
with 50000 garments per week?
• What is machine requirement for 50000 garments per
week?
• What do you recommend if production cut to 24000
garments per week?
• All operators are able to use both spread and cut
equipment.
Capacity planning-spreading
• 50000 garments x 0.90 metres = 45000 metres to be
cut each week.
• Each metre Smv = 0.1584 therefore 45000 x 0.1584
= 0.1584 x 45000
60
= 118.80 std.hrs required
@ 90% efficiency = 132 operated hours./ 3machines =
44 hour week
Capacity planning- cutting
• 50000 garments x 0.90 metres = 45000 metres to be
cut each week.
• Each metre Smv. = 0.05 therefore 45000 x 0.05 =
0.05 x 45000
60
= 37.5 std.hrs required
@ 90% efficiency = 41.70 operated hours
Capacity planning –cutting room
• Spreading 132 hours needed over 3 machines
• Cutting 41.70 hours needed.
• Total operating hours = 173.9
• Absence = 8% = 187.18 contracted hours needed = 4.8
(5) people at 39 hour week.
• 4 operators work 8.50 hours (when all attending). 1
operator works 2 hours early
and through lunch break = 14 hour extra machine time per
week. Helps on non-machine elements.
Capacity planning-spreading
• 24000 garments x 0.90 metres = 21600 metres to be
cut each week.
• Each metre Smv = 0.1584 therefore 21600 x 0.1584
= 0.1584 x 21600
60
= 61.60 std.hrs required
@ 90% efficiency = 68.40 operated hours./ 3machines
= 22.80 hour week
Capacity planning- cutting
• 24000 garments x 0.90 metres = 21600 metres to be
cut each week.
• Each metre Smv = 0.05 therefore 21600 x 0.05 =
0.05 x 21600
60
= 18.0 std.hrs required
@ 90% efficiency = 20 operated hours
Capacity planning –cutting room
• Spreading 68.4 hours needed over 3 machines
• Cutting 20 hours needed.
• Total operating hours = 84.4
• Absence = 8% = 91.2 contracted hours needed = 2.3
(3) people at 39 hour week.
• 2 operators to be released.
• Can 1 operator be redeployed for part of the day?
Floater
Floaters generally can perform all operations but at
much lower efficiency. They should not be allocated
to any specific operation in any line plan. They are
available to handle unforeseen circumstances.
Pitch Time
Pitch time is the theoretical operation time, each
operator should take for a planned balanced line. It is
calculated as:-
=(SAM value of style)/ (No of operator required to
meet the target)

More Related Content

What's hot

Assignment: Comparative Study on Various Types of Garment Production System.
Assignment: Comparative Study on Various  Types of Garment Production System.Assignment: Comparative Study on Various  Types of Garment Production System.
Assignment: Comparative Study on Various Types of Garment Production System.
Proshanto Saha
 
End breakage at ring frame. Ring frame machine breakage
End breakage at ring frame. Ring frame machine breakageEnd breakage at ring frame. Ring frame machine breakage
End breakage at ring frame. Ring frame machine breakage
MukulpratapHarijan
 
Standard, Monitoring & Evaluation of dyeing process
Standard, Monitoring & Evaluation of dyeing process   Standard, Monitoring & Evaluation of dyeing process
Standard, Monitoring & Evaluation of dyeing process
Asaye Dessie
 
ROLE OF COMPUTER IN TEXTILE
ROLE OF COMPUTER IN TEXTILEROLE OF COMPUTER IN TEXTILE
ROLE OF COMPUTER IN TEXTILE
ItiDubey3
 
startup breakages in ring frame and their control
startup breakages in ring frame and their controlstartup breakages in ring frame and their control
startup breakages in ring frame and their control
Vicky Raj
 
Dyeing Faults & Remedies
Dyeing Faults & RemediesDyeing Faults & Remedies
Dyeing Faults & Remedies
Mazharul Islam
 
Comparing rolar and rotary printing
Comparing rolar and rotary printingComparing rolar and rotary printing
Comparing rolar and rotary printing
Haseeb Ahmad
 
ppt on summer training Vardhman's Mahavir Spinning Mills Baddi (weaving devis...
ppt on summer training Vardhman's Mahavir Spinning Mills Baddi (weaving devis...ppt on summer training Vardhman's Mahavir Spinning Mills Baddi (weaving devis...
ppt on summer training Vardhman's Mahavir Spinning Mills Baddi (weaving devis...
Bharat Rana
 
HVI (High Volume Instrument )
HVI (High Volume Instrument )HVI (High Volume Instrument )
HVI (High Volume Instrument )
Nayeem Pub
 
Physical structure of fibers
Physical structure of fibersPhysical structure of fibers
Physical structure of fibers
Zaki Mujahid
 
Tensile properties
Tensile propertiesTensile properties
Tensile properties
Vijay Prakash
 
Finihing machine
Finihing  machineFinihing  machine
Finihing machine
Md. Mazadul Hasan Shishir
 
Hank dyeing machine
Hank dyeing machine  Hank dyeing machine
Hank dyeing machine
Asaye Dessie
 
Dyeing of polyester at low temperature
Dyeing of polyester at low temperatureDyeing of polyester at low temperature
Dyeing of polyester at low temperature
Jamshedul Islam
 
Pigment dyeing
Pigment dyeingPigment dyeing
Pigment dyeing
Rinku Shemar
 
Chemicals and Auxiliaries used in Textile Wet Processing
Chemicals and Auxiliaries used in Textile Wet ProcessingChemicals and Auxiliaries used in Textile Wet Processing
Chemicals and Auxiliaries used in Textile Wet Processing
Mashrur Wasity
 
Dying Printing Finishing
Dying Printing FinishingDying Printing Finishing
Dying Printing Finishing
400439
 
FIBER LENGTH
FIBER LENGTHFIBER LENGTH
FIBER LENGTH
Nitish Sharma
 
Introduction to preparatory processes in textile chemical processing
Introduction to preparatory processes in textile chemical processingIntroduction to preparatory processes in textile chemical processing
Introduction to preparatory processes in textile chemical processing
SK RAJU
 
Technical textile 2
Technical textile 2Technical textile 2
Technical textile 2
Amit kumar
 

What's hot (20)

Assignment: Comparative Study on Various Types of Garment Production System.
Assignment: Comparative Study on Various  Types of Garment Production System.Assignment: Comparative Study on Various  Types of Garment Production System.
Assignment: Comparative Study on Various Types of Garment Production System.
 
End breakage at ring frame. Ring frame machine breakage
End breakage at ring frame. Ring frame machine breakageEnd breakage at ring frame. Ring frame machine breakage
End breakage at ring frame. Ring frame machine breakage
 
Standard, Monitoring & Evaluation of dyeing process
Standard, Monitoring & Evaluation of dyeing process   Standard, Monitoring & Evaluation of dyeing process
Standard, Monitoring & Evaluation of dyeing process
 
ROLE OF COMPUTER IN TEXTILE
ROLE OF COMPUTER IN TEXTILEROLE OF COMPUTER IN TEXTILE
ROLE OF COMPUTER IN TEXTILE
 
startup breakages in ring frame and their control
startup breakages in ring frame and their controlstartup breakages in ring frame and their control
startup breakages in ring frame and their control
 
Dyeing Faults & Remedies
Dyeing Faults & RemediesDyeing Faults & Remedies
Dyeing Faults & Remedies
 
Comparing rolar and rotary printing
Comparing rolar and rotary printingComparing rolar and rotary printing
Comparing rolar and rotary printing
 
ppt on summer training Vardhman's Mahavir Spinning Mills Baddi (weaving devis...
ppt on summer training Vardhman's Mahavir Spinning Mills Baddi (weaving devis...ppt on summer training Vardhman's Mahavir Spinning Mills Baddi (weaving devis...
ppt on summer training Vardhman's Mahavir Spinning Mills Baddi (weaving devis...
 
HVI (High Volume Instrument )
HVI (High Volume Instrument )HVI (High Volume Instrument )
HVI (High Volume Instrument )
 
Physical structure of fibers
Physical structure of fibersPhysical structure of fibers
Physical structure of fibers
 
Tensile properties
Tensile propertiesTensile properties
Tensile properties
 
Finihing machine
Finihing  machineFinihing  machine
Finihing machine
 
Hank dyeing machine
Hank dyeing machine  Hank dyeing machine
Hank dyeing machine
 
Dyeing of polyester at low temperature
Dyeing of polyester at low temperatureDyeing of polyester at low temperature
Dyeing of polyester at low temperature
 
Pigment dyeing
Pigment dyeingPigment dyeing
Pigment dyeing
 
Chemicals and Auxiliaries used in Textile Wet Processing
Chemicals and Auxiliaries used in Textile Wet ProcessingChemicals and Auxiliaries used in Textile Wet Processing
Chemicals and Auxiliaries used in Textile Wet Processing
 
Dying Printing Finishing
Dying Printing FinishingDying Printing Finishing
Dying Printing Finishing
 
FIBER LENGTH
FIBER LENGTHFIBER LENGTH
FIBER LENGTH
 
Introduction to preparatory processes in textile chemical processing
Introduction to preparatory processes in textile chemical processingIntroduction to preparatory processes in textile chemical processing
Introduction to preparatory processes in textile chemical processing
 
Technical textile 2
Technical textile 2Technical textile 2
Technical textile 2
 

Similar to Capacity-Planning-I.ppt

Chap 2 How to Calculat line efficiency in Garment industry.pptx
Chap 2 How to Calculat line efficiency in Garment industry.pptxChap 2 How to Calculat line efficiency in Garment industry.pptx
Chap 2 How to Calculat line efficiency in Garment industry.pptx
Fouzia Mirza
 
All in 1 IE
All in 1 IEAll in 1 IE
All in 1 IE
shakil tutul
 
Olio ie training for all stuff
Olio ie training for all stuffOlio ie training for all stuff
Olio ie training for all stuff
MaududAhmmad
 
4AD15ME042.pptx
4AD15ME042.pptx4AD15ME042.pptx
4AD15ME042.pptx
MrHAD
 
In apparel manufacturing (2 files merged)
In apparel manufacturing (2 files merged)In apparel manufacturing (2 files merged)
In apparel manufacturing (2 files merged)
Ankur Shukla
 
Aggregate Planning for industrial engineering
Aggregate Planning for industrial engineeringAggregate Planning for industrial engineering
Aggregate Planning for industrial engineering
ashaby
 
Project Reportof Velocity Apparelz Nort Africa
Project Reportof Velocity Apparelz  Nort AfricaProject Reportof Velocity Apparelz  Nort Africa
Project Reportof Velocity Apparelz Nort Africa
Amethia Export (Director- P K Sahab)
 
Cost & management Accounting
Cost & management AccountingCost & management Accounting
Cost & management Accounting
JisjissyChandran
 
Line balancing
Line balancing Line balancing
Line balancing
Md. Mazadul Hasan Shishir
 
Total productive maintenance
Total productive maintenanceTotal productive maintenance
Total productive maintenance
Sasidharan Mohanakrishnan
 
Pomppt
PompptPomppt
Pomppt
arggarg
 
Operation bulletin of dungaree
Operation bulletin of dungareeOperation bulletin of dungaree
Operation bulletin of dungaree
ShamimaAkter41
 
Capacity planning in garment industry22 (3 files merged)
Capacity planning in garment industry22 (3 files merged)Capacity planning in garment industry22 (3 files merged)
Capacity planning in garment industry22 (3 files merged)
Ankur Shukla
 
Operation management problems
Operation management problemsOperation management problems
Operation management problems
venkataramanan Thiru
 
Product1 [4] capacity planning
Product1 [4]   capacity planningProduct1 [4]   capacity planning
Product1 [4] capacity planning
nickoleaaronlinog
 
APPAREL PRODUCTION MANAGEMNET
APPAREL PRODUCTION MANAGEMNETAPPAREL PRODUCTION MANAGEMNET
APPAREL PRODUCTION MANAGEMNET
MdRakibHasan27
 
Sewing line setting
Sewing line settingSewing line setting
Sewing line setting
SharifulHasan9
 
Implémentation Méthode Single Minute Exchange of Dies(SMED)
Implémentation Méthode Single Minute Exchange of Dies(SMED)Implémentation Méthode Single Minute Exchange of Dies(SMED)
Implémentation Méthode Single Minute Exchange of Dies(SMED)
MohammedLahssaini1
 
Process Selection and Facility layout.ppt
Process Selection and Facility layout.pptProcess Selection and Facility layout.ppt
Process Selection and Facility layout.ppt
SandipanMaji3
 
zone 3 ppt.pptx
zone 3 ppt.pptxzone 3 ppt.pptx
zone 3 ppt.pptx
NasrullahKhan406671
 

Similar to Capacity-Planning-I.ppt (20)

Chap 2 How to Calculat line efficiency in Garment industry.pptx
Chap 2 How to Calculat line efficiency in Garment industry.pptxChap 2 How to Calculat line efficiency in Garment industry.pptx
Chap 2 How to Calculat line efficiency in Garment industry.pptx
 
All in 1 IE
All in 1 IEAll in 1 IE
All in 1 IE
 
Olio ie training for all stuff
Olio ie training for all stuffOlio ie training for all stuff
Olio ie training for all stuff
 
4AD15ME042.pptx
4AD15ME042.pptx4AD15ME042.pptx
4AD15ME042.pptx
 
In apparel manufacturing (2 files merged)
In apparel manufacturing (2 files merged)In apparel manufacturing (2 files merged)
In apparel manufacturing (2 files merged)
 
Aggregate Planning for industrial engineering
Aggregate Planning for industrial engineeringAggregate Planning for industrial engineering
Aggregate Planning for industrial engineering
 
Project Reportof Velocity Apparelz Nort Africa
Project Reportof Velocity Apparelz  Nort AfricaProject Reportof Velocity Apparelz  Nort Africa
Project Reportof Velocity Apparelz Nort Africa
 
Cost & management Accounting
Cost & management AccountingCost & management Accounting
Cost & management Accounting
 
Line balancing
Line balancing Line balancing
Line balancing
 
Total productive maintenance
Total productive maintenanceTotal productive maintenance
Total productive maintenance
 
Pomppt
PompptPomppt
Pomppt
 
Operation bulletin of dungaree
Operation bulletin of dungareeOperation bulletin of dungaree
Operation bulletin of dungaree
 
Capacity planning in garment industry22 (3 files merged)
Capacity planning in garment industry22 (3 files merged)Capacity planning in garment industry22 (3 files merged)
Capacity planning in garment industry22 (3 files merged)
 
Operation management problems
Operation management problemsOperation management problems
Operation management problems
 
Product1 [4] capacity planning
Product1 [4]   capacity planningProduct1 [4]   capacity planning
Product1 [4] capacity planning
 
APPAREL PRODUCTION MANAGEMNET
APPAREL PRODUCTION MANAGEMNETAPPAREL PRODUCTION MANAGEMNET
APPAREL PRODUCTION MANAGEMNET
 
Sewing line setting
Sewing line settingSewing line setting
Sewing line setting
 
Implémentation Méthode Single Minute Exchange of Dies(SMED)
Implémentation Méthode Single Minute Exchange of Dies(SMED)Implémentation Méthode Single Minute Exchange of Dies(SMED)
Implémentation Méthode Single Minute Exchange of Dies(SMED)
 
Process Selection and Facility layout.ppt
Process Selection and Facility layout.pptProcess Selection and Facility layout.ppt
Process Selection and Facility layout.ppt
 
zone 3 ppt.pptx
zone 3 ppt.pptxzone 3 ppt.pptx
zone 3 ppt.pptx
 

Recently uploaded

一比一原版(UO毕业证)渥太华大学毕业证如何办理
一比一原版(UO毕业证)渥太华大学毕业证如何办理一比一原版(UO毕业证)渥太华大学毕业证如何办理
一比一原版(UO毕业证)渥太华大学毕业证如何办理
bmucuha
 
Cell The Unit of Life for NEET Multiple Choice Questions.docx
Cell The Unit of Life for NEET Multiple Choice Questions.docxCell The Unit of Life for NEET Multiple Choice Questions.docx
Cell The Unit of Life for NEET Multiple Choice Questions.docx
vasanthatpuram
 
[VCOSA] Monthly Report - Cotton & Yarn Statistics March 2024
[VCOSA] Monthly Report - Cotton & Yarn Statistics March 2024[VCOSA] Monthly Report - Cotton & Yarn Statistics March 2024
[VCOSA] Monthly Report - Cotton & Yarn Statistics March 2024
Vietnam Cotton & Spinning Association
 
一比一原版莱斯大学毕业证(rice毕业证)如何办理
一比一原版莱斯大学毕业证(rice毕业证)如何办理一比一原版莱斯大学毕业证(rice毕业证)如何办理
一比一原版莱斯大学毕业证(rice毕业证)如何办理
zsafxbf
 
一比一原版兰加拉学院毕业证(Langara毕业证书)学历如何办理
一比一原版兰加拉学院毕业证(Langara毕业证书)学历如何办理一比一原版兰加拉学院毕业证(Langara毕业证书)学历如何办理
一比一原版兰加拉学院毕业证(Langara毕业证书)学历如何办理
hyfjgavov
 
Digital Marketing Performance Marketing Sample .pdf
Digital Marketing Performance Marketing  Sample .pdfDigital Marketing Performance Marketing  Sample .pdf
Digital Marketing Performance Marketing Sample .pdf
Vineet
 
Drownings spike from May to August in children
Drownings spike from May to August in childrenDrownings spike from May to August in children
Drownings spike from May to August in children
Bisnar Chase Personal Injury Attorneys
 
Discovering Digital Process Twins for What-if Analysis: a Process Mining Appr...
Discovering Digital Process Twins for What-if Analysis: a Process Mining Appr...Discovering Digital Process Twins for What-if Analysis: a Process Mining Appr...
Discovering Digital Process Twins for What-if Analysis: a Process Mining Appr...
Marlon Dumas
 
How To Control IO Usage using Resource Manager
How To Control IO Usage using Resource ManagerHow To Control IO Usage using Resource Manager
How To Control IO Usage using Resource Manager
Alireza Kamrani
 
Sample Devops SRE Product Companies .pdf
Sample Devops SRE  Product Companies .pdfSample Devops SRE  Product Companies .pdf
Sample Devops SRE Product Companies .pdf
Vineet
 
Module 1 ppt BIG DATA ANALYTICS NOTES FOR MCA
Module 1 ppt BIG DATA ANALYTICS NOTES FOR MCAModule 1 ppt BIG DATA ANALYTICS NOTES FOR MCA
Module 1 ppt BIG DATA ANALYTICS NOTES FOR MCA
yuvarajkumar334
 
一比一原版加拿大渥太华大学毕业证(uottawa毕业证书)如何办理
一比一原版加拿大渥太华大学毕业证(uottawa毕业证书)如何办理一比一原版加拿大渥太华大学毕业证(uottawa毕业证书)如何办理
一比一原版加拿大渥太华大学毕业证(uottawa毕业证书)如何办理
uevausa
 
原版一比一多伦多大学毕业证(UofT毕业证书)如何办理
原版一比一多伦多大学毕业证(UofT毕业证书)如何办理原版一比一多伦多大学毕业证(UofT毕业证书)如何办理
原版一比一多伦多大学毕业证(UofT毕业证书)如何办理
mkkikqvo
 
Module 1 ppt BIG DATA ANALYTICS_NOTES FOR MCA
Module 1 ppt BIG DATA ANALYTICS_NOTES FOR MCAModule 1 ppt BIG DATA ANALYTICS_NOTES FOR MCA
Module 1 ppt BIG DATA ANALYTICS_NOTES FOR MCA
yuvarajkumar334
 
Experts live - Improving user adoption with AI
Experts live - Improving user adoption with AIExperts live - Improving user adoption with AI
Experts live - Improving user adoption with AI
jitskeb
 
DATA COMMS-NETWORKS YR2 lecture 08 NAT & CLOUD.docx
DATA COMMS-NETWORKS YR2 lecture 08 NAT & CLOUD.docxDATA COMMS-NETWORKS YR2 lecture 08 NAT & CLOUD.docx
DATA COMMS-NETWORKS YR2 lecture 08 NAT & CLOUD.docx
SaffaIbrahim1
 
一比一原版澳洲西澳大学毕业证(uwa毕业证书)如何办理
一比一原版澳洲西澳大学毕业证(uwa毕业证书)如何办理一比一原版澳洲西澳大学毕业证(uwa毕业证书)如何办理
一比一原版澳洲西澳大学毕业证(uwa毕业证书)如何办理
aguty
 
Build applications with generative AI on Google Cloud
Build applications with generative AI on Google CloudBuild applications with generative AI on Google Cloud
Build applications with generative AI on Google Cloud
Márton Kodok
 
一比一原版加拿大麦吉尔大学毕业证(mcgill毕业证书)如何办理
一比一原版加拿大麦吉尔大学毕业证(mcgill毕业证书)如何办理一比一原版加拿大麦吉尔大学毕业证(mcgill毕业证书)如何办理
一比一原版加拿大麦吉尔大学毕业证(mcgill毕业证书)如何办理
agdhot
 
一比一原版(lbs毕业证书)伦敦商学院毕业证如何办理
一比一原版(lbs毕业证书)伦敦商学院毕业证如何办理一比一原版(lbs毕业证书)伦敦商学院毕业证如何办理
一比一原版(lbs毕业证书)伦敦商学院毕业证如何办理
ywqeos
 

Recently uploaded (20)

一比一原版(UO毕业证)渥太华大学毕业证如何办理
一比一原版(UO毕业证)渥太华大学毕业证如何办理一比一原版(UO毕业证)渥太华大学毕业证如何办理
一比一原版(UO毕业证)渥太华大学毕业证如何办理
 
Cell The Unit of Life for NEET Multiple Choice Questions.docx
Cell The Unit of Life for NEET Multiple Choice Questions.docxCell The Unit of Life for NEET Multiple Choice Questions.docx
Cell The Unit of Life for NEET Multiple Choice Questions.docx
 
[VCOSA] Monthly Report - Cotton & Yarn Statistics March 2024
[VCOSA] Monthly Report - Cotton & Yarn Statistics March 2024[VCOSA] Monthly Report - Cotton & Yarn Statistics March 2024
[VCOSA] Monthly Report - Cotton & Yarn Statistics March 2024
 
一比一原版莱斯大学毕业证(rice毕业证)如何办理
一比一原版莱斯大学毕业证(rice毕业证)如何办理一比一原版莱斯大学毕业证(rice毕业证)如何办理
一比一原版莱斯大学毕业证(rice毕业证)如何办理
 
一比一原版兰加拉学院毕业证(Langara毕业证书)学历如何办理
一比一原版兰加拉学院毕业证(Langara毕业证书)学历如何办理一比一原版兰加拉学院毕业证(Langara毕业证书)学历如何办理
一比一原版兰加拉学院毕业证(Langara毕业证书)学历如何办理
 
Digital Marketing Performance Marketing Sample .pdf
Digital Marketing Performance Marketing  Sample .pdfDigital Marketing Performance Marketing  Sample .pdf
Digital Marketing Performance Marketing Sample .pdf
 
Drownings spike from May to August in children
Drownings spike from May to August in childrenDrownings spike from May to August in children
Drownings spike from May to August in children
 
Discovering Digital Process Twins for What-if Analysis: a Process Mining Appr...
Discovering Digital Process Twins for What-if Analysis: a Process Mining Appr...Discovering Digital Process Twins for What-if Analysis: a Process Mining Appr...
Discovering Digital Process Twins for What-if Analysis: a Process Mining Appr...
 
How To Control IO Usage using Resource Manager
How To Control IO Usage using Resource ManagerHow To Control IO Usage using Resource Manager
How To Control IO Usage using Resource Manager
 
Sample Devops SRE Product Companies .pdf
Sample Devops SRE  Product Companies .pdfSample Devops SRE  Product Companies .pdf
Sample Devops SRE Product Companies .pdf
 
Module 1 ppt BIG DATA ANALYTICS NOTES FOR MCA
Module 1 ppt BIG DATA ANALYTICS NOTES FOR MCAModule 1 ppt BIG DATA ANALYTICS NOTES FOR MCA
Module 1 ppt BIG DATA ANALYTICS NOTES FOR MCA
 
一比一原版加拿大渥太华大学毕业证(uottawa毕业证书)如何办理
一比一原版加拿大渥太华大学毕业证(uottawa毕业证书)如何办理一比一原版加拿大渥太华大学毕业证(uottawa毕业证书)如何办理
一比一原版加拿大渥太华大学毕业证(uottawa毕业证书)如何办理
 
原版一比一多伦多大学毕业证(UofT毕业证书)如何办理
原版一比一多伦多大学毕业证(UofT毕业证书)如何办理原版一比一多伦多大学毕业证(UofT毕业证书)如何办理
原版一比一多伦多大学毕业证(UofT毕业证书)如何办理
 
Module 1 ppt BIG DATA ANALYTICS_NOTES FOR MCA
Module 1 ppt BIG DATA ANALYTICS_NOTES FOR MCAModule 1 ppt BIG DATA ANALYTICS_NOTES FOR MCA
Module 1 ppt BIG DATA ANALYTICS_NOTES FOR MCA
 
Experts live - Improving user adoption with AI
Experts live - Improving user adoption with AIExperts live - Improving user adoption with AI
Experts live - Improving user adoption with AI
 
DATA COMMS-NETWORKS YR2 lecture 08 NAT & CLOUD.docx
DATA COMMS-NETWORKS YR2 lecture 08 NAT & CLOUD.docxDATA COMMS-NETWORKS YR2 lecture 08 NAT & CLOUD.docx
DATA COMMS-NETWORKS YR2 lecture 08 NAT & CLOUD.docx
 
一比一原版澳洲西澳大学毕业证(uwa毕业证书)如何办理
一比一原版澳洲西澳大学毕业证(uwa毕业证书)如何办理一比一原版澳洲西澳大学毕业证(uwa毕业证书)如何办理
一比一原版澳洲西澳大学毕业证(uwa毕业证书)如何办理
 
Build applications with generative AI on Google Cloud
Build applications with generative AI on Google CloudBuild applications with generative AI on Google Cloud
Build applications with generative AI on Google Cloud
 
一比一原版加拿大麦吉尔大学毕业证(mcgill毕业证书)如何办理
一比一原版加拿大麦吉尔大学毕业证(mcgill毕业证书)如何办理一比一原版加拿大麦吉尔大学毕业证(mcgill毕业证书)如何办理
一比一原版加拿大麦吉尔大学毕业证(mcgill毕业证书)如何办理
 
一比一原版(lbs毕业证书)伦敦商学院毕业证如何办理
一比一原版(lbs毕业证书)伦敦商学院毕业证如何办理一比一原版(lbs毕业证书)伦敦商学院毕业证如何办理
一比一原版(lbs毕业证书)伦敦商学院毕业证如何办理
 

Capacity-Planning-I.ppt

  • 2. Factory capacity • 500 operators working 48 hour week. • Work content of 30 minutes per garment • Therefore capacity of 500 x 48x 60 30 = 48000 garments per week
  • 3. Definitions • “On –standard” : that time the operator spends on “measured” work earning Standard Minutes. • “Off-standard” : that time the operator spends on “un-measured” work or “measured” work that is classified as “off-standard”.
  • 4. Definitions- “Measured work” • That work to which a standard measure (SMV, SAM) has been applied. • Example of “measured work” that may be classified as “off-standard”. An operator may whilst learning a new operation be taken off standard for payment purposes but will still be contributing SMS as the operation they complete will have SMV applied.
  • 5. SMV/SAM? • Standard Minute Value (S.M.V.) is the time allocated through work measurement for an operation to be completed at a 100 rating. • Standard Allocated (Allotted) Minute (S.A.M.) is an S.M.V. + any policy allowances added.
  • 6. Operator Performance • Primarily a measure of the effectiveness of the individual operator • = SMs earned “on standard” x 100 Time spent “on standard” Sometimes referred to as “Pay” performance as it is usually measured within an incentive scheme.
  • 7. Operator utilisation • A measure of how well the supervisor manages to keep the operators “on-standard” = time “on-standard x 100 time attended
  • 8. Efficiency • A measure of how well the section/factory is run. = SMs earned x 100 time attended. • A measure of both the operator and the supervisor
  • 9. Efficiency •Incorporates elements of operator performance & utilisation into the single measure.
  • 10. Absence/attendance = total operator time attended x 100 total contracted time = attendance.
  • 11. Measures - Examples • Section = 20 operators working 9 hour/540 minute day • 2 operators are absent all day • Attendance = 18 x 540 x 100 20 x 540 = 9720 = 90% or 10% absence 10800
  • 12. Measures- examples • An operator attends for 540 minutes • Produces 1500 pieces @ SMV of 0.30 • Waits 60 minutes for work • Waits 20 minutes machine breakdown Find • SAM produced? • On standard time? • Performance? • Utilization? • Efficiency?
  • 13. Measures- examples • Sms produced = 1500 x 0.30 = 450. • Time “on-standard” = 540 – (60+20) = 460 minutes • Performance = 450 x 100 460 = 97.8 or 98%
  • 15. Measures- examples •Efficiency = 450 x 100 540 = 83%
  • 16. Exercise- definitions • Attendance = 4800/5400 = 89% • total sms earned = 3982.30
  • 17. Capacity planning - people • 500 direct operators working 48 hours/week • S.M.V. = 25 per garment • Absence level of 8% • Average efficiency of 85% • Contracted time 540 1. Calculate standard hour/minutes that can be produced by operators. 2. Calculate no. of garments produced.
  • 18. Capacity planning - people • 500 operators x 48 hours = 24000 contracted hours • 24000 – 8% (1920 hours) absence = 22080 attended hours (absence costs 40 operators) • At efficiency of 85% std. hours produced = 22080 x 85% = 18768 std hrs. • 5232 hours lost to absence & inefficiency.= 21.8% of original contracted hours
  • 19. Capacity planning - people • 18768 std hrs produced • S.M.V. = 25 mins. or 0.417 std. hrs. • Garment capacity = 18768 0.417 = 45007 garments.
  • 20. Capacity planning • Under the same conditions how many people are needed to produce 70000 garments per week.? • 70000 x 0.417 = 29190 standard hours required. • Each operator will produce 39 hours @ 85% efficiency = 39 x 85% = 33.15 std. hrs/week
  • 21. Capacity planning • 29190 standard hours required. • Each operator will produce 33.15 std. hrs/week • Number of operators = 29190 33.15 = 880.54 people. • + Absence of 8% = 880.54 +8%.= 951
  • 22. Capacity planning-machines • Auto pocket set machine • S.M.V. 0.60 • Efficiency = 95% • 15 machines available • 8.50 hour day • How many garments can they supply to sections?
  • 23. Capacity planning-machines • 15 machines x 8.50 hours = 127.50 hours/day. • @95% efficiency std. hrs produced = 121.13 hrs • SMV = 0.60 = 100 per hour at standard • Output = 100 x 121.13 = 12113 garments
  • 24. Capacity planning-machines • Capacity must be increased to 25000 per day. • Each machine does 100 x 95% = 95 per hour. 25000/95 = 263.15 hours. In 8.5 hour day = 31 machines
  • 25. Capacity planning-machines • Each machine will produce 95 per hour worked. • 25000/95 = 263.15 hours • 263.15 hours / 15 machines = 17.54 hrs per machine per day • 2 shifts
  • 26. Capacity planning- Department • Cutting room using semi-auto spreading machines and computerised cutting head. • SMV for spreading = 0.1584 per metre • SMV for cutting = 0.050 per metre • Average fabric content per gmt. = 90 cms. • Standard working day= 8.50 hours (39 week) • 3 spreading machines on 4 tables • 1 cutting machine. • Department runs at 90% efficiency and 8% absence
  • 27. Capacity planning- Exercise • How many people are needed to supply the factory with 50000 garments per week? • What is machine requirement for 50000 garments per week? • What do you recommend if production cut to 24000 garments per week? • All operators are able to use both spread and cut equipment.
  • 28. Capacity planning-spreading • 50000 garments x 0.90 metres = 45000 metres to be cut each week. • Each metre Smv = 0.1584 therefore 45000 x 0.1584 = 0.1584 x 45000 60 = 118.80 std.hrs required @ 90% efficiency = 132 operated hours./ 3machines = 44 hour week
  • 29. Capacity planning- cutting • 50000 garments x 0.90 metres = 45000 metres to be cut each week. • Each metre Smv. = 0.05 therefore 45000 x 0.05 = 0.05 x 45000 60 = 37.5 std.hrs required @ 90% efficiency = 41.70 operated hours
  • 30. Capacity planning –cutting room • Spreading 132 hours needed over 3 machines • Cutting 41.70 hours needed. • Total operating hours = 173.9 • Absence = 8% = 187.18 contracted hours needed = 4.8 (5) people at 39 hour week. • 4 operators work 8.50 hours (when all attending). 1 operator works 2 hours early and through lunch break = 14 hour extra machine time per week. Helps on non-machine elements.
  • 31. Capacity planning-spreading • 24000 garments x 0.90 metres = 21600 metres to be cut each week. • Each metre Smv = 0.1584 therefore 21600 x 0.1584 = 0.1584 x 21600 60 = 61.60 std.hrs required @ 90% efficiency = 68.40 operated hours./ 3machines = 22.80 hour week
  • 32. Capacity planning- cutting • 24000 garments x 0.90 metres = 21600 metres to be cut each week. • Each metre Smv = 0.05 therefore 21600 x 0.05 = 0.05 x 21600 60 = 18.0 std.hrs required @ 90% efficiency = 20 operated hours
  • 33. Capacity planning –cutting room • Spreading 68.4 hours needed over 3 machines • Cutting 20 hours needed. • Total operating hours = 84.4 • Absence = 8% = 91.2 contracted hours needed = 2.3 (3) people at 39 hour week. • 2 operators to be released. • Can 1 operator be redeployed for part of the day?
  • 34. Floater Floaters generally can perform all operations but at much lower efficiency. They should not be allocated to any specific operation in any line plan. They are available to handle unforeseen circumstances.
  • 35. Pitch Time Pitch time is the theoretical operation time, each operator should take for a planned balanced line. It is calculated as:- =(SAM value of style)/ (No of operator required to meet the target)