SlideShare a Scribd company logo
Prince George’s PlazaTDDP Implementation Program:Technical Report #1 1
Prince George’s County Planning Department
Community Planning Division
www.pgplanning.org
BELCREST
StreetLightReplacement
PhasingProgram
ROAD
Prince George’s PlazaTDDP Implementation Program:Technical Report #12
Summary
This technical report offers an alternative solution to DPW&T’s current
proposal to replace the failed street lights and conduit on Belcrest Road
with standard cobra-head street light fixtures at 150-foot intervals
(maximum 75 feet from the end of the curb/Point of curvature) based
on DPW&T Standard 500.12 for Street Light Spacing in an Urban Area.
This report assesses the DPW&T proposal in terms of key issues that it
is intended to address. Several other critical issues are identified which
should be taken into consideration by any proposal to replace the
street lights on Belcrest Road. Our report then presents and describes
in detail the suggested alternative street light replacement program
that, in our opinion, will best address all of the critical issues associated
with the ultimate goal of continuous lighting and enhanced safety for
pedestrians and bicyclists along Belcrest after dark.
The balance of this document sets forth general design
recommendations and a suggested three-phase schedule for
completion of this project.
Existing Conditions Belcrest Road
Brick Wall Landscape Green Strip Sidewalk Curb Buffer
1.6’+/- 7.1’+/- 7.6’+/- 3.5’+/- Belcrest
Road
Prince George’s PlazaTDDP Implementation Program:Technical Report #1 3
Introduction
Belcrest Road is the primary north-south thoroughfare in the Prince
George’s PlazaTransit District, and is envisioned to carry a significant
portion of theTransit District’s north-south vehicular, transit, bicycle,
and pedestrian traffic over the next 20 years.The street lights on
Belcrest Road have failed and require immediate replacement.
The Department of PublicWorks andTransportation’s Specifications
and Standards for Roadways and Bridges recommend traditional,
cobra-head street lights at intervals up to 150 feet.This project could
cost several million dollars. DPW&T’s proposed solution will not provide
adequate lighting for pedestrians and is wholly inadequate for the
increased pedestrian activity that future redevelopment will generate
along Belcrest Road.The standard cobra-head lighting retrofit proposed
by DPW&T runs the risk of being inadequate and functionally obsolete
upon its completion.
The need to replace the Belcrest Road street lights presents an
opportunity for the County to invest in a highly visible and needed
public improvement that will actually produce a safe and walkable
after-dark pedestrian environment along Belcrest Road.
Key Issues Addressed by the DPW&T Proposal
1. The street lights have failed and require immediate replacement
because of their non-standard nature and functional obsolescence.
2. The cost of replacing the failed street lights and connecting conduit
is likely to encumber a significant portion of the County’s limited street
lighting budget
3. The DPW&T street light replacement proposal recognizes Belcrest
Road’s importance as theTransit District’s primary north-south
thoroughfare and gateway into the area from the north.
Other Critical Issues for Consideration
4. Pedestrian Volumes: Belcrest Road sees significant pedestrian
traffic both day and night because of the major destinations that border
it (UniversityTown Center, Mall at Prince Georges, and apartment
complexes) and the heavy use of public transit (bus and Metro).
5. Inadequate Pedestrian Lighting: Street lights at 150-
foot intervals will not provide continuous lighting of the sidewalks,
especially with the existing thick tree canopy along Belcrest Road.
6. TDDP Pedestrian Lighting Standards: Should the
preliminary Prince George’s PlazaTransit District Development Plan
(TDDP) be approved, property owners would be required to install
pedestrian-scaled street lighting at intervals not to exceed 40 feet as
redevelopment occurs, regardless of existing lighting that covers the
cartway of Belcrest Road.
7. Anticipated Pedestrian Volumes: The volume of pedestrian
traffic along Belcrest Road is expected to greatly increase with the
redevelopment of the Landy and Percontee properties, the University
Town Center’sToledo Road parking lot, and the Mall at Prince Georges.
As this redevelopment occurs, insufficient lighting along Belcrest Road
may create areas of darkness and shadow along this important
pedestrian commuting route. Future redevelopment might not occur or
succeed if residents and/or workers are concerned about the safety of
pedestrian access to the Metro station, especially after dark.
8. Cycle Track: Should the preliminaryTDDP be approved, property
owners on the west side of Belcrest Road would be required to
construct, or dedicate right-of-way for, a two-way cycle track outside of
the existing west curb. Future streetscape improvements would have to
accommodate this feature.
9. Street Trees: The street trees along Belcrest Road are appropriate
for the envisioned future Downtown and should be retained.
Sidewalk material
precedent
Existing tree
encroaching
pedestrian clear zone
Prince George’s PlazaTDDP Implementation Program:Technical Report #14
What We are Proposing
The intent of our suggested alternative street replacement program is to maintain the existing curb-to-curb dimensions and street trees while
allowing for the retrofit of the frontage zone to support bicycling, increased pedestrian activity, and street-level commerce abutting the sidewalk in
accordance with the requirements of the preliminary Prince George’s PlazaTransit District Development Plan upon its approval.
Phase 1: The County proceeds with its current project but a) installs two-headed street lights that illuminate both the vehicular cartway and the
sidewalk and b) install new street light conduits that will allow access to power for future two-headed street lights installed at 50-foot intervals. A
new 10-foot sidewalk is also installed along the west side of Belcrest Road to serve both pedestrians and bicyclists.
Phase 2: Shouldanindependentfundingsourcebeidentified,the County or other entity installs infill two-headed street lights at the above-
recommended 50-foot intervals.This creates the desired safe pedestrian environment and removes a significant public improvement cost from the
balance sheet of future private redevelopment.
Phase 3: As redevelopment occurs, a new 10-foot sidewalk clear zone will be constructed outside of the existing tree zone and the existing sidewalk
would ultimately be retrofitted as cycle track.
Prince George’s PlazaTDDP Implementation Program:Technical Report #1 5
Phase One: Installation of Replacement Street Lights and Conduit (Years 1-3)
10’
Sidewalk
Existing
Conditions
Belcrest Road (southbound)
Intent:
To construct new infrastructure that will ultimately provide continuous
lighting along Belcrest Road’s sidewalks. In this phase, DPW&T will
work with PEPCO to install initial street lights and electric conduits
while preserving existing landscape, tree canopy, and brick wall. A new
sidewalk would also be installed along the west side of Belcrest Road if
new funding is identified to pay for it (see program details below).
A. New electric conduits should be placed along Belcrest Road
to support new street lights.
B. Conduit access points (marked by protective electric
conduit caps flush to the sidewalk) should be installed every
50 feet in order to support future closely-spaced street lights.
C. Street lights that include both elevated vehicular lamps
and lamps (approximately 14 feet high at most) focused
on the sidewalk, should be installed every 100 feet.
PEPCO’sTeardrop lamp, or similar fixture, should be
used; such fixtures are required of private property
owners within theTransit District.
Program:
1. Replace existing street lights.
2. Replace existing sidewalk on the west side of Belcrest Road with a
new 10-foot sidewalk (to be retrofitted to include a cycle track in Phase
3).
3. Install new street lights five (5) feet from existing curb.
4. Place new street lights every 100 feet center-to-center.
5. Maintain existing tree canopy and landscape.
“ ” marks the
location of new lights
added in PhaseTwo.
Prince George’s PlazaTDDP Implementation Program:Technical Report #16
PhaseTwo: Installation of Infill Light Fixtures (Years 3-6)
Intent:
To eliminate dark zones between light fixtures by installing second
batch of street lights financed by different funding sources. Should this
option not prove feasible, see PhaseThree.
A. New street lights should be placed every 50 feet center-to-
center from existing street lights.
Program:
1. Identify alternative funding source for construction and/or
maintenance of additional street lights.
2. Install pedestrian street lights on the previously-installed conduit
access points, with a five (5)-foot setback from the existing curb.
3. Install new pedestrian street lights every 50 feet center-to-center
from existing street lights. Pedestrian street light should not be taller
than 14 feet in height.
4. Maintain the existing tree canopy and landscape.
10’
Sidewalk
Existing
Conditions
Example of an ideal street light for Belcrest
Road - Two-Headed Teardrop style
Belcrest Road (southbound)
Prince George’s PlazaTDDP Implementation Program:Technical Report #1 7
PhaseThree:Transformation of Belcrest Road Frontage Area (BeyondYear 6)
2’
Cycle Track
10’
Sidewalk
5’
Landscape
Example of mixed-use development along
the cultural trail
Indianapolis Cultural Trail:
Example of a clear landscaped delineation
between sidewalk, trail, and pedestrian street
light.
4’ 4’ 3’
Existing Buffer
(to be repainted)
Intent:
To implement the Prince George’s PlazaTransit District Development
Plan as redevelopment occurs, including the required construction of
an expanded sidewalk and a cycle track (if the expanded sidewalk is
constructed in Phase 1, it would be retrofitted to include a cycle track).
New Development:
1. Development proposals must conform to the newTransit District
Standards:
a. New buildings along Belcrest Road will be at a build to
line framing the sidewalk and helping to create a more active
and safe environment.
b. Property owners are required to construct a new sidewalk
clear zone outside of the existing tree zone, along with any
additional sidewalk frontage they desire to support retail/
restaurant operations.
2. New sidewalks will tie into an at-least five (5)-foot-wide tree/
landscape strip. It is recommended to repurpose existing brick or
sidewalk pavement and place it between green boxes.
3.The two-way cycle track will be installed where the current (or
expanded) sidewalk meets the west-side curb, with the street lights
in its median.This is not optimal, but necessary to support cycle
traffic while maintaining the existing curb-to-curb and not requiring
excessive re-purposing of private property for public use because of the
cycle track.
Program:
1. Maintain existing tree canopy
2. Reduce landscape strip to 5’x 10’green boxes.
3. Between green boxes, special stamped concrete, brick, or other
paving material should be used to demarcate a separation between
sidewalk and cycle track and allow cyclists to enter/exit the track.
4. Stripe, stamped concrete, or landscaping for clear delineation
between bicycle travel lanes.
5. Create physical barrier between the northbound cycle track and the
southbound auto travel lanes.

More Related Content

What's hot

Congestion Reduction Plan Strategies
Congestion Reduction Plan StrategiesCongestion Reduction Plan Strategies
Congestion Reduction Plan Strategies
Mike Iswalt
 
Janwani - LAPP JM Rd
Janwani - LAPP JM RdJanwani - LAPP JM Rd
Janwani - LAPP JM Rd
CEPT University
 
Herndon Station Metro Garage
Herndon Station Metro GarageHerndon Station Metro Garage
Herndon Station Metro Garage
Fairfax County
 
Nicholas DiFrank - Professional Portfolio 2015
Nicholas DiFrank - Professional Portfolio 2015Nicholas DiFrank - Professional Portfolio 2015
Nicholas DiFrank - Professional Portfolio 2015
Nicholas DiFrank
 
Manor Park Neighborhood Urban Park
Manor Park Neighborhood Urban ParkManor Park Neighborhood Urban Park
Manor Park Neighborhood Urban Park
Jose Carlos Ayala
 
Joint Traffic Management Center Parking Structure
Joint Traffic Management Center Parking StructureJoint Traffic Management Center Parking Structure
Joint Traffic Management Center Parking Structure
PostTensioningInstitute
 
120619ppt 12 s1084000 council stratpol presentation
120619ppt 12 s1084000 council stratpol presentation120619ppt 12 s1084000 council stratpol presentation
120619ppt 12 s1084000 council stratpol presentationTransport Planning
 
TA-T3-02-Water-Sewer-and-Traffic-Its-All-About-The-Flow
TA-T3-02-Water-Sewer-and-Traffic-Its-All-About-The-FlowTA-T3-02-Water-Sewer-and-Traffic-Its-All-About-The-Flow
TA-T3-02-Water-Sewer-and-Traffic-Its-All-About-The-FlowMark Oberschmidt
 
Final Presentation (Transportation Planning & Design)
Final Presentation (Transportation Planning & Design)Final Presentation (Transportation Planning & Design)
Final Presentation (Transportation Planning & Design)Josia Tannos, EIT
 
Cork Street Dublin 8 Environmental Improvement Strategy 2003
Cork Street Dublin 8 Environmental Improvement Strategy 2003Cork Street Dublin 8 Environmental Improvement Strategy 2003
Cork Street Dublin 8 Environmental Improvement Strategy 2003
kieran rose
 
Cork street environmental improvement strategy 2003
Cork street environmental improvement strategy 2003Cork street environmental improvement strategy 2003
Cork street environmental improvement strategy 2003
kieran rose
 
Green Screen Parking Structure
Green Screen Parking StructureGreen Screen Parking Structure
Green Screen Parking Structure
PostTensioningInstitute
 
Paverpresentation
PaverpresentationPaverpresentation
Paverpresentation
Don Williams
 
Clairemont CPG Ad Hoc Subcommittee Meeting
Clairemont CPG Ad Hoc Subcommittee MeetingClairemont CPG Ad Hoc Subcommittee Meeting
Clairemont CPG Ad Hoc Subcommittee Meeting
CirculateSD
 
King-Liberty Pedestrian / Cycling Bridge Project Update - Slides
King-Liberty Pedestrian / Cycling Bridge Project Update - Slides King-Liberty Pedestrian / Cycling Bridge Project Update - Slides
King-Liberty Pedestrian / Cycling Bridge Project Update - Slides
Toronto Public Consultation Unit
 
JKRAJEWSKI_ODOT2014_Light Rail Presentation
JKRAJEWSKI_ODOT2014_Light Rail PresentationJKRAJEWSKI_ODOT2014_Light Rail Presentation
JKRAJEWSKI_ODOT2014_Light Rail PresentationJoe Krajewski
 
FCDOT: Rolling Road Widening from Fullerton Road to Delong Drive-Apr.19, 2012
FCDOT: Rolling Road Widening from Fullerton Road to Delong Drive-Apr.19, 2012FCDOT: Rolling Road Widening from Fullerton Road to Delong Drive-Apr.19, 2012
FCDOT: Rolling Road Widening from Fullerton Road to Delong Drive-Apr.19, 2012
Fairfax County
 

What's hot (19)

Congestion Reduction Plan Strategies
Congestion Reduction Plan StrategiesCongestion Reduction Plan Strategies
Congestion Reduction Plan Strategies
 
Janwani - LAPP JM Rd
Janwani - LAPP JM RdJanwani - LAPP JM Rd
Janwani - LAPP JM Rd
 
Herndon Station Metro Garage
Herndon Station Metro GarageHerndon Station Metro Garage
Herndon Station Metro Garage
 
Nicholas DiFrank - Professional Portfolio 2015
Nicholas DiFrank - Professional Portfolio 2015Nicholas DiFrank - Professional Portfolio 2015
Nicholas DiFrank - Professional Portfolio 2015
 
Manor Park Neighborhood Urban Park
Manor Park Neighborhood Urban ParkManor Park Neighborhood Urban Park
Manor Park Neighborhood Urban Park
 
Joint Traffic Management Center Parking Structure
Joint Traffic Management Center Parking StructureJoint Traffic Management Center Parking Structure
Joint Traffic Management Center Parking Structure
 
120619ppt 12 s1084000 council stratpol presentation
120619ppt 12 s1084000 council stratpol presentation120619ppt 12 s1084000 council stratpol presentation
120619ppt 12 s1084000 council stratpol presentation
 
RRL-workpackages
RRL-workpackagesRRL-workpackages
RRL-workpackages
 
Senior Project PSR
Senior Project PSRSenior Project PSR
Senior Project PSR
 
TA-T3-02-Water-Sewer-and-Traffic-Its-All-About-The-Flow
TA-T3-02-Water-Sewer-and-Traffic-Its-All-About-The-FlowTA-T3-02-Water-Sewer-and-Traffic-Its-All-About-The-Flow
TA-T3-02-Water-Sewer-and-Traffic-Its-All-About-The-Flow
 
Final Presentation (Transportation Planning & Design)
Final Presentation (Transportation Planning & Design)Final Presentation (Transportation Planning & Design)
Final Presentation (Transportation Planning & Design)
 
Cork Street Dublin 8 Environmental Improvement Strategy 2003
Cork Street Dublin 8 Environmental Improvement Strategy 2003Cork Street Dublin 8 Environmental Improvement Strategy 2003
Cork Street Dublin 8 Environmental Improvement Strategy 2003
 
Cork street environmental improvement strategy 2003
Cork street environmental improvement strategy 2003Cork street environmental improvement strategy 2003
Cork street environmental improvement strategy 2003
 
Green Screen Parking Structure
Green Screen Parking StructureGreen Screen Parking Structure
Green Screen Parking Structure
 
Paverpresentation
PaverpresentationPaverpresentation
Paverpresentation
 
Clairemont CPG Ad Hoc Subcommittee Meeting
Clairemont CPG Ad Hoc Subcommittee MeetingClairemont CPG Ad Hoc Subcommittee Meeting
Clairemont CPG Ad Hoc Subcommittee Meeting
 
King-Liberty Pedestrian / Cycling Bridge Project Update - Slides
King-Liberty Pedestrian / Cycling Bridge Project Update - Slides King-Liberty Pedestrian / Cycling Bridge Project Update - Slides
King-Liberty Pedestrian / Cycling Bridge Project Update - Slides
 
JKRAJEWSKI_ODOT2014_Light Rail Presentation
JKRAJEWSKI_ODOT2014_Light Rail PresentationJKRAJEWSKI_ODOT2014_Light Rail Presentation
JKRAJEWSKI_ODOT2014_Light Rail Presentation
 
FCDOT: Rolling Road Widening from Fullerton Road to Delong Drive-Apr.19, 2012
FCDOT: Rolling Road Widening from Fullerton Road to Delong Drive-Apr.19, 2012FCDOT: Rolling Road Widening from Fullerton Road to Delong Drive-Apr.19, 2012
FCDOT: Rolling Road Widening from Fullerton Road to Delong Drive-Apr.19, 2012
 

Viewers also liked

2.24 MW Solar Project Proposal
2.24 MW Solar Project Proposal2.24 MW Solar Project Proposal
2.24 MW Solar Project ProposalBrandon McNulty
 
Langley Park Community Legacy Application
Langley Park Community Legacy ApplicationLangley Park Community Legacy Application
Langley Park Community Legacy Application
Jose Carlos Ayala
 
Langley Park Community Legacy Application
Langley Park Community Legacy Application Langley Park Community Legacy Application
Langley Park Community Legacy Application
Jose Carlos Ayala
 
Transit District Draft Standard and Guidelines
Transit District Draft Standard and GuidelinesTransit District Draft Standard and Guidelines
Transit District Draft Standard and Guidelines
Jose Carlos Ayala
 
Market Square
Market SquareMarket Square
Market Square
Jose Carlos Ayala
 
Gold's Gym Re-location Alternatives Proposal
Gold's Gym Re-location Alternatives ProposalGold's Gym Re-location Alternatives Proposal
Gold's Gym Re-location Alternatives Proposal
Jose Carlos Ayala
 
Solar System proposal
Solar System proposalSolar System proposal
Solar System proposal
Sohail Azeem
 
Public Space
Public SpacePublic Space
Public Space
Eman Abdel Sabour
 
solar street light project report.
solar street light project report.solar street light project report.
solar street light project report.
Hagi Sahib
 
Solar Roof top Project proposal delhi
Solar Roof top Project proposal delhiSolar Roof top Project proposal delhi
Solar Roof top Project proposal delhi
Tarun Rathore
 

Viewers also liked (11)

2.24 MW Solar Project Proposal
2.24 MW Solar Project Proposal2.24 MW Solar Project Proposal
2.24 MW Solar Project Proposal
 
Square Intl
Square IntlSquare Intl
Square Intl
 
Langley Park Community Legacy Application
Langley Park Community Legacy ApplicationLangley Park Community Legacy Application
Langley Park Community Legacy Application
 
Langley Park Community Legacy Application
Langley Park Community Legacy Application Langley Park Community Legacy Application
Langley Park Community Legacy Application
 
Transit District Draft Standard and Guidelines
Transit District Draft Standard and GuidelinesTransit District Draft Standard and Guidelines
Transit District Draft Standard and Guidelines
 
Market Square
Market SquareMarket Square
Market Square
 
Gold's Gym Re-location Alternatives Proposal
Gold's Gym Re-location Alternatives ProposalGold's Gym Re-location Alternatives Proposal
Gold's Gym Re-location Alternatives Proposal
 
Solar System proposal
Solar System proposalSolar System proposal
Solar System proposal
 
Public Space
Public SpacePublic Space
Public Space
 
solar street light project report.
solar street light project report.solar street light project report.
solar street light project report.
 
Solar Roof top Project proposal delhi
Solar Roof top Project proposal delhiSolar Roof top Project proposal delhi
Solar Roof top Project proposal delhi
 

Similar to Belcrest Road Phasing Program

Canalside board update dec 2015
Canalside board update dec 2015Canalside board update dec 2015
Canalside board update dec 2015
MetroPR
 
Proposal to reclaim Chicago's lakefront from the highway using immersed tunnels
Proposal to reclaim Chicago's lakefront from the highway using immersed tunnelsProposal to reclaim Chicago's lakefront from the highway using immersed tunnels
Proposal to reclaim Chicago's lakefront from the highway using immersed tunnels
James Chuck
 
Adopted Road and Footpath examples Cellweb TRP
Adopted Road and Footpath examples Cellweb TRPAdopted Road and Footpath examples Cellweb TRP
Adopted Road and Footpath examples Cellweb TRPOwen Hutchison
 
Kennedy Station and East At-Grade Section Open House - December 2017
Kennedy Station and East At-Grade Section Open House - December 2017Kennedy Station and East At-Grade Section Open House - December 2017
Kennedy Station and East At-Grade Section Open House - December 2017
Crosstown TO
 
Sr 826 (palmetto expressway)interchange reconstruction
Sr 826 (palmetto expressway)interchange reconstructionSr 826 (palmetto expressway)interchange reconstruction
Sr 826 (palmetto expressway)interchange reconstructiongbfengineering
 
Mount Pleasant Junior School Meeting May 5
Mount Pleasant Junior School Meeting May 5Mount Pleasant Junior School Meeting May 5
Mount Pleasant Junior School Meeting May 5
Crosstown TO
 
Proposed Leslie Street Closure Town Hall Meeting - April 2019
Proposed Leslie Street Closure Town Hall Meeting - April 2019Proposed Leslie Street Closure Town Hall Meeting - April 2019
Proposed Leslie Street Closure Town Hall Meeting - April 2019
Crosstown TO
 
King Abdullah Road 4 12 07 Presentation
King Abdullah Road 4 12 07 PresentationKing Abdullah Road 4 12 07 Presentation
King Abdullah Road 4 12 07 Presentationguest2d44ee
 
Chain Bridge - Eaton Place Intersection Improvements 5-11-22.pdf
Chain Bridge - Eaton Place Intersection Improvements 5-11-22.pdfChain Bridge - Eaton Place Intersection Improvements 5-11-22.pdf
Chain Bridge - Eaton Place Intersection Improvements 5-11-22.pdf
City of Fairfax, Va.
 
Midway Crossings Project
Midway Crossings ProjectMidway Crossings Project
Midway Crossings Project
Steve Frank
 
Final report design of a pedestrian bridge - fall 2009
Final report   design of a pedestrian bridge - fall 2009Final report   design of a pedestrian bridge - fall 2009
Final report design of a pedestrian bridge - fall 2009
Sanamau Waitogu
 
Congress Parkway Construction Overview, January 2010
Congress Parkway Construction Overview, January 2010Congress Parkway Construction Overview, January 2010
Congress Parkway Construction Overview, January 2010
Daniel X. O'Neil
 
228 congressparkway overview_jan2010
228 congressparkway overview_jan2010228 congressparkway overview_jan2010
228 congressparkway overview_jan2010
Daniel X. O'Neil
 
Police Facility Conceptual Design
Police Facility Conceptual DesignPolice Facility Conceptual Design
Police Facility Conceptual Design
City of College Station
 
Brentcliffe - Victoria Park Construction Liaison Committee Meeting
Brentcliffe - Victoria Park Construction Liaison Committee MeetingBrentcliffe - Victoria Park Construction Liaison Committee Meeting
Brentcliffe - Victoria Park Construction Liaison Committee Meeting
Crosstown TO
 
Solar roadways presented by RK
Solar roadways presented by RKSolar roadways presented by RK
Solar roadways presented by RK
Raam Krishna Prakash Jagali
 
LEED ND Squalicum Lofts
LEED ND Squalicum LoftsLEED ND Squalicum Lofts
LEED ND Squalicum Lofts
Cameron Plommer
 
8th Street Bridge Community Information Session November 19th, 2015
8th Street Bridge Community Information Session November 19th, 20158th Street Bridge Community Information Session November 19th, 2015
8th Street Bridge Community Information Session November 19th, 2015
City Brandon
 
EIA Project - Presentation
EIA Project - PresentationEIA Project - Presentation
EIA Project - PresentationEmma Syrat
 
North West Multi-Modal Transport Hub (NWMTH) Derry – Londonderry webinar
North West Multi-Modal Transport Hub (NWMTH) Derry – Londonderry webinarNorth West Multi-Modal Transport Hub (NWMTH) Derry – Londonderry webinar
North West Multi-Modal Transport Hub (NWMTH) Derry – Londonderry webinar
Association for Project Management
 

Similar to Belcrest Road Phasing Program (20)

Canalside board update dec 2015
Canalside board update dec 2015Canalside board update dec 2015
Canalside board update dec 2015
 
Proposal to reclaim Chicago's lakefront from the highway using immersed tunnels
Proposal to reclaim Chicago's lakefront from the highway using immersed tunnelsProposal to reclaim Chicago's lakefront from the highway using immersed tunnels
Proposal to reclaim Chicago's lakefront from the highway using immersed tunnels
 
Adopted Road and Footpath examples Cellweb TRP
Adopted Road and Footpath examples Cellweb TRPAdopted Road and Footpath examples Cellweb TRP
Adopted Road and Footpath examples Cellweb TRP
 
Kennedy Station and East At-Grade Section Open House - December 2017
Kennedy Station and East At-Grade Section Open House - December 2017Kennedy Station and East At-Grade Section Open House - December 2017
Kennedy Station and East At-Grade Section Open House - December 2017
 
Sr 826 (palmetto expressway)interchange reconstruction
Sr 826 (palmetto expressway)interchange reconstructionSr 826 (palmetto expressway)interchange reconstruction
Sr 826 (palmetto expressway)interchange reconstruction
 
Mount Pleasant Junior School Meeting May 5
Mount Pleasant Junior School Meeting May 5Mount Pleasant Junior School Meeting May 5
Mount Pleasant Junior School Meeting May 5
 
Proposed Leslie Street Closure Town Hall Meeting - April 2019
Proposed Leslie Street Closure Town Hall Meeting - April 2019Proposed Leslie Street Closure Town Hall Meeting - April 2019
Proposed Leslie Street Closure Town Hall Meeting - April 2019
 
King Abdullah Road 4 12 07 Presentation
King Abdullah Road 4 12 07 PresentationKing Abdullah Road 4 12 07 Presentation
King Abdullah Road 4 12 07 Presentation
 
Chain Bridge - Eaton Place Intersection Improvements 5-11-22.pdf
Chain Bridge - Eaton Place Intersection Improvements 5-11-22.pdfChain Bridge - Eaton Place Intersection Improvements 5-11-22.pdf
Chain Bridge - Eaton Place Intersection Improvements 5-11-22.pdf
 
Midway Crossings Project
Midway Crossings ProjectMidway Crossings Project
Midway Crossings Project
 
Final report design of a pedestrian bridge - fall 2009
Final report   design of a pedestrian bridge - fall 2009Final report   design of a pedestrian bridge - fall 2009
Final report design of a pedestrian bridge - fall 2009
 
Congress Parkway Construction Overview, January 2010
Congress Parkway Construction Overview, January 2010Congress Parkway Construction Overview, January 2010
Congress Parkway Construction Overview, January 2010
 
228 congressparkway overview_jan2010
228 congressparkway overview_jan2010228 congressparkway overview_jan2010
228 congressparkway overview_jan2010
 
Police Facility Conceptual Design
Police Facility Conceptual DesignPolice Facility Conceptual Design
Police Facility Conceptual Design
 
Brentcliffe - Victoria Park Construction Liaison Committee Meeting
Brentcliffe - Victoria Park Construction Liaison Committee MeetingBrentcliffe - Victoria Park Construction Liaison Committee Meeting
Brentcliffe - Victoria Park Construction Liaison Committee Meeting
 
Solar roadways presented by RK
Solar roadways presented by RKSolar roadways presented by RK
Solar roadways presented by RK
 
LEED ND Squalicum Lofts
LEED ND Squalicum LoftsLEED ND Squalicum Lofts
LEED ND Squalicum Lofts
 
8th Street Bridge Community Information Session November 19th, 2015
8th Street Bridge Community Information Session November 19th, 20158th Street Bridge Community Information Session November 19th, 2015
8th Street Bridge Community Information Session November 19th, 2015
 
EIA Project - Presentation
EIA Project - PresentationEIA Project - Presentation
EIA Project - Presentation
 
North West Multi-Modal Transport Hub (NWMTH) Derry – Londonderry webinar
North West Multi-Modal Transport Hub (NWMTH) Derry – Londonderry webinarNorth West Multi-Modal Transport Hub (NWMTH) Derry – Londonderry webinar
North West Multi-Modal Transport Hub (NWMTH) Derry – Londonderry webinar
 

More from Jose Carlos Ayala

Town of Upper Marlboro Design Guidelines
Town of Upper Marlboro Design GuidelinesTown of Upper Marlboro Design Guidelines
Town of Upper Marlboro Design Guidelines
Jose Carlos Ayala
 
The Art of Place Making
The Art of Place MakingThe Art of Place Making
The Art of Place Making
Jose Carlos Ayala
 
Silver Spring - To the Future & Beyond
Silver Spring - To the Future & BeyondSilver Spring - To the Future & Beyond
Silver Spring - To the Future & Beyond
Jose Carlos Ayala
 
Veterans Plaza - A Dynamic Cultural District
Veterans Plaza - A Dynamic Cultural DistrictVeterans Plaza - A Dynamic Cultural District
Veterans Plaza - A Dynamic Cultural DistrictJose Carlos Ayala
 
Silver Spring Placemaking Presentation
Silver Spring Placemaking PresentationSilver Spring Placemaking Presentation
Silver Spring Placemaking PresentationJose Carlos Ayala
 
Silver Spring Civic Areas Assessment
Silver Spring Civic Areas Assessment Silver Spring Civic Areas Assessment
Silver Spring Civic Areas Assessment
Jose Carlos Ayala
 
Rollins College At South Lake Nona District
Rollins College At South Lake Nona DistrictRollins College At South Lake Nona District
Rollins College At South Lake Nona District
Jose Carlos Ayala
 
McKey Street, Ocoee Florida.
McKey Street, Ocoee Florida. McKey Street, Ocoee Florida.
McKey Street, Ocoee Florida.
Jose Carlos Ayala
 
Winter Park SunRail Implementation Guide
Winter Park SunRail Implementation GuideWinter Park SunRail Implementation Guide
Winter Park SunRail Implementation GuideJose Carlos Ayala
 
Wells district final project
Wells district final projectWells district final project
Wells district final project
Jose Carlos Ayala
 
Morse Boulevard's Transect Analysis
Morse Boulevard's Transect AnalysisMorse Boulevard's Transect Analysis
Morse Boulevard's Transect Analysis
Jose Carlos Ayala
 
Maitland Planning & Zoning SunRail Station
Maitland Planning & Zoning  SunRail StationMaitland Planning & Zoning  SunRail Station
Maitland Planning & Zoning SunRail StationJose Carlos Ayala
 
Altamonte Springs SunRail Station
Altamonte Springs SunRail StationAltamonte Springs SunRail Station
Altamonte Springs SunRail Station
Jose Carlos Ayala
 

More from Jose Carlos Ayala (13)

Town of Upper Marlboro Design Guidelines
Town of Upper Marlboro Design GuidelinesTown of Upper Marlboro Design Guidelines
Town of Upper Marlboro Design Guidelines
 
The Art of Place Making
The Art of Place MakingThe Art of Place Making
The Art of Place Making
 
Silver Spring - To the Future & Beyond
Silver Spring - To the Future & BeyondSilver Spring - To the Future & Beyond
Silver Spring - To the Future & Beyond
 
Veterans Plaza - A Dynamic Cultural District
Veterans Plaza - A Dynamic Cultural DistrictVeterans Plaza - A Dynamic Cultural District
Veterans Plaza - A Dynamic Cultural District
 
Silver Spring Placemaking Presentation
Silver Spring Placemaking PresentationSilver Spring Placemaking Presentation
Silver Spring Placemaking Presentation
 
Silver Spring Civic Areas Assessment
Silver Spring Civic Areas Assessment Silver Spring Civic Areas Assessment
Silver Spring Civic Areas Assessment
 
Rollins College At South Lake Nona District
Rollins College At South Lake Nona DistrictRollins College At South Lake Nona District
Rollins College At South Lake Nona District
 
McKey Street, Ocoee Florida.
McKey Street, Ocoee Florida. McKey Street, Ocoee Florida.
McKey Street, Ocoee Florida.
 
Winter Park SunRail Implementation Guide
Winter Park SunRail Implementation GuideWinter Park SunRail Implementation Guide
Winter Park SunRail Implementation Guide
 
Wells district final project
Wells district final projectWells district final project
Wells district final project
 
Morse Boulevard's Transect Analysis
Morse Boulevard's Transect AnalysisMorse Boulevard's Transect Analysis
Morse Boulevard's Transect Analysis
 
Maitland Planning & Zoning SunRail Station
Maitland Planning & Zoning  SunRail StationMaitland Planning & Zoning  SunRail Station
Maitland Planning & Zoning SunRail Station
 
Altamonte Springs SunRail Station
Altamonte Springs SunRail StationAltamonte Springs SunRail Station
Altamonte Springs SunRail Station
 

Recently uploaded

一比一原版(MMU毕业证书)曼彻斯特城市大学毕业证成绩单如何办理
一比一原版(MMU毕业证书)曼彻斯特城市大学毕业证成绩单如何办理一比一原版(MMU毕业证书)曼彻斯特城市大学毕业证成绩单如何办理
一比一原版(MMU毕业证书)曼彻斯特城市大学毕业证成绩单如何办理
7sd8fier
 
Top Israeli Products and Brands - Plan it israel.pdf
Top Israeli Products and Brands - Plan it israel.pdfTop Israeli Products and Brands - Plan it israel.pdf
Top Israeli Products and Brands - Plan it israel.pdf
PlanitIsrael
 
一比一原版(NCL毕业证书)纽卡斯尔大学毕业证成绩单如何办理
一比一原版(NCL毕业证书)纽卡斯尔大学毕业证成绩单如何办理一比一原版(NCL毕业证书)纽卡斯尔大学毕业证成绩单如何办理
一比一原版(NCL毕业证书)纽卡斯尔大学毕业证成绩单如何办理
7sd8fier
 
Book Formatting: Quality Control Checks for Designers
Book Formatting: Quality Control Checks for DesignersBook Formatting: Quality Control Checks for Designers
Book Formatting: Quality Control Checks for Designers
Confidence Ago
 
Between Filth and Fortune- Urban Cattle Foraging Realities by Devi S Nair, An...
Between Filth and Fortune- Urban Cattle Foraging Realities by Devi S Nair, An...Between Filth and Fortune- Urban Cattle Foraging Realities by Devi S Nair, An...
Between Filth and Fortune- Urban Cattle Foraging Realities by Devi S Nair, An...
Mansi Shah
 
Design Thinking Design thinking Design thinking
Design Thinking Design thinking Design thinkingDesign Thinking Design thinking Design thinking
Design Thinking Design thinking Design thinking
cy0krjxt
 
一比一原版(Columbia毕业证)哥伦比亚大学毕业证如何办理
一比一原版(Columbia毕业证)哥伦比亚大学毕业证如何办理一比一原版(Columbia毕业证)哥伦比亚大学毕业证如何办理
一比一原版(Columbia毕业证)哥伦比亚大学毕业证如何办理
asuzyq
 
PORTFOLIO FABIANA VILLANI ARCHITECTURE.pdf
PORTFOLIO FABIANA VILLANI ARCHITECTURE.pdfPORTFOLIO FABIANA VILLANI ARCHITECTURE.pdf
PORTFOLIO FABIANA VILLANI ARCHITECTURE.pdf
fabianavillanib
 
一比一原版(UCB毕业证书)伯明翰大学学院毕业证成绩单如何办理
一比一原版(UCB毕业证书)伯明翰大学学院毕业证成绩单如何办理一比一原版(UCB毕业证书)伯明翰大学学院毕业证成绩单如何办理
一比一原版(UCB毕业证书)伯明翰大学学院毕业证成绩单如何办理
h7j5io0
 
20 slides of research movie and artists .pdf
20 slides of research movie and artists .pdf20 slides of research movie and artists .pdf
20 slides of research movie and artists .pdf
ameli25062005
 
Exploring the Future of Smart Garages.pdf
Exploring the Future of Smart Garages.pdfExploring the Future of Smart Garages.pdf
Exploring the Future of Smart Garages.pdf
fastfixgaragedoor
 
vernacular architecture in response to climate.pdf
vernacular architecture in response to climate.pdfvernacular architecture in response to climate.pdf
vernacular architecture in response to climate.pdf
PrabhjeetSingh219035
 
一比一原版(BU毕业证书)伯恩茅斯大学毕业证成绩单如何办理
一比一原版(BU毕业证书)伯恩茅斯大学毕业证成绩单如何办理一比一原版(BU毕业证书)伯恩茅斯大学毕业证成绩单如何办理
一比一原版(BU毕业证书)伯恩茅斯大学毕业证成绩单如何办理
h7j5io0
 
White wonder, Work developed by Eva Tschopp
White wonder, Work developed by Eva TschoppWhite wonder, Work developed by Eva Tschopp
White wonder, Work developed by Eva Tschopp
Mansi Shah
 
7 Alternatives to Bullet Points in PowerPoint
7 Alternatives to Bullet Points in PowerPoint7 Alternatives to Bullet Points in PowerPoint
7 Alternatives to Bullet Points in PowerPoint
Alvis Oh
 
Borys Sutkowski portfolio interior design
Borys Sutkowski portfolio interior designBorys Sutkowski portfolio interior design
Borys Sutkowski portfolio interior design
boryssutkowski
 
一比一原版(Brunel毕业证书)布鲁内尔大学毕业证成绩单如何办理
一比一原版(Brunel毕业证书)布鲁内尔大学毕业证成绩单如何办理一比一原版(Brunel毕业证书)布鲁内尔大学毕业证成绩单如何办理
一比一原版(Brunel毕业证书)布鲁内尔大学毕业证成绩单如何办理
smpc3nvg
 
Common Designing Mistakes and How to avoid them
Common Designing Mistakes and How to avoid themCommon Designing Mistakes and How to avoid them
Common Designing Mistakes and How to avoid them
madhavlakhanpal29
 
RTUYUIJKLDSADAGHBDJNKSMAL,D
RTUYUIJKLDSADAGHBDJNKSMAL,DRTUYUIJKLDSADAGHBDJNKSMAL,D
RTUYUIJKLDSADAGHBDJNKSMAL,D
cy0krjxt
 
projectreportnew-170307082323 nnnnnn(1).pdf
projectreportnew-170307082323 nnnnnn(1).pdfprojectreportnew-170307082323 nnnnnn(1).pdf
projectreportnew-170307082323 nnnnnn(1).pdf
farazahmadas6
 

Recently uploaded (20)

一比一原版(MMU毕业证书)曼彻斯特城市大学毕业证成绩单如何办理
一比一原版(MMU毕业证书)曼彻斯特城市大学毕业证成绩单如何办理一比一原版(MMU毕业证书)曼彻斯特城市大学毕业证成绩单如何办理
一比一原版(MMU毕业证书)曼彻斯特城市大学毕业证成绩单如何办理
 
Top Israeli Products and Brands - Plan it israel.pdf
Top Israeli Products and Brands - Plan it israel.pdfTop Israeli Products and Brands - Plan it israel.pdf
Top Israeli Products and Brands - Plan it israel.pdf
 
一比一原版(NCL毕业证书)纽卡斯尔大学毕业证成绩单如何办理
一比一原版(NCL毕业证书)纽卡斯尔大学毕业证成绩单如何办理一比一原版(NCL毕业证书)纽卡斯尔大学毕业证成绩单如何办理
一比一原版(NCL毕业证书)纽卡斯尔大学毕业证成绩单如何办理
 
Book Formatting: Quality Control Checks for Designers
Book Formatting: Quality Control Checks for DesignersBook Formatting: Quality Control Checks for Designers
Book Formatting: Quality Control Checks for Designers
 
Between Filth and Fortune- Urban Cattle Foraging Realities by Devi S Nair, An...
Between Filth and Fortune- Urban Cattle Foraging Realities by Devi S Nair, An...Between Filth and Fortune- Urban Cattle Foraging Realities by Devi S Nair, An...
Between Filth and Fortune- Urban Cattle Foraging Realities by Devi S Nair, An...
 
Design Thinking Design thinking Design thinking
Design Thinking Design thinking Design thinkingDesign Thinking Design thinking Design thinking
Design Thinking Design thinking Design thinking
 
一比一原版(Columbia毕业证)哥伦比亚大学毕业证如何办理
一比一原版(Columbia毕业证)哥伦比亚大学毕业证如何办理一比一原版(Columbia毕业证)哥伦比亚大学毕业证如何办理
一比一原版(Columbia毕业证)哥伦比亚大学毕业证如何办理
 
PORTFOLIO FABIANA VILLANI ARCHITECTURE.pdf
PORTFOLIO FABIANA VILLANI ARCHITECTURE.pdfPORTFOLIO FABIANA VILLANI ARCHITECTURE.pdf
PORTFOLIO FABIANA VILLANI ARCHITECTURE.pdf
 
一比一原版(UCB毕业证书)伯明翰大学学院毕业证成绩单如何办理
一比一原版(UCB毕业证书)伯明翰大学学院毕业证成绩单如何办理一比一原版(UCB毕业证书)伯明翰大学学院毕业证成绩单如何办理
一比一原版(UCB毕业证书)伯明翰大学学院毕业证成绩单如何办理
 
20 slides of research movie and artists .pdf
20 slides of research movie and artists .pdf20 slides of research movie and artists .pdf
20 slides of research movie and artists .pdf
 
Exploring the Future of Smart Garages.pdf
Exploring the Future of Smart Garages.pdfExploring the Future of Smart Garages.pdf
Exploring the Future of Smart Garages.pdf
 
vernacular architecture in response to climate.pdf
vernacular architecture in response to climate.pdfvernacular architecture in response to climate.pdf
vernacular architecture in response to climate.pdf
 
一比一原版(BU毕业证书)伯恩茅斯大学毕业证成绩单如何办理
一比一原版(BU毕业证书)伯恩茅斯大学毕业证成绩单如何办理一比一原版(BU毕业证书)伯恩茅斯大学毕业证成绩单如何办理
一比一原版(BU毕业证书)伯恩茅斯大学毕业证成绩单如何办理
 
White wonder, Work developed by Eva Tschopp
White wonder, Work developed by Eva TschoppWhite wonder, Work developed by Eva Tschopp
White wonder, Work developed by Eva Tschopp
 
7 Alternatives to Bullet Points in PowerPoint
7 Alternatives to Bullet Points in PowerPoint7 Alternatives to Bullet Points in PowerPoint
7 Alternatives to Bullet Points in PowerPoint
 
Borys Sutkowski portfolio interior design
Borys Sutkowski portfolio interior designBorys Sutkowski portfolio interior design
Borys Sutkowski portfolio interior design
 
一比一原版(Brunel毕业证书)布鲁内尔大学毕业证成绩单如何办理
一比一原版(Brunel毕业证书)布鲁内尔大学毕业证成绩单如何办理一比一原版(Brunel毕业证书)布鲁内尔大学毕业证成绩单如何办理
一比一原版(Brunel毕业证书)布鲁内尔大学毕业证成绩单如何办理
 
Common Designing Mistakes and How to avoid them
Common Designing Mistakes and How to avoid themCommon Designing Mistakes and How to avoid them
Common Designing Mistakes and How to avoid them
 
RTUYUIJKLDSADAGHBDJNKSMAL,D
RTUYUIJKLDSADAGHBDJNKSMAL,DRTUYUIJKLDSADAGHBDJNKSMAL,D
RTUYUIJKLDSADAGHBDJNKSMAL,D
 
projectreportnew-170307082323 nnnnnn(1).pdf
projectreportnew-170307082323 nnnnnn(1).pdfprojectreportnew-170307082323 nnnnnn(1).pdf
projectreportnew-170307082323 nnnnnn(1).pdf
 

Belcrest Road Phasing Program

  • 1. Prince George’s PlazaTDDP Implementation Program:Technical Report #1 1 Prince George’s County Planning Department Community Planning Division www.pgplanning.org BELCREST StreetLightReplacement PhasingProgram ROAD
  • 2. Prince George’s PlazaTDDP Implementation Program:Technical Report #12 Summary This technical report offers an alternative solution to DPW&T’s current proposal to replace the failed street lights and conduit on Belcrest Road with standard cobra-head street light fixtures at 150-foot intervals (maximum 75 feet from the end of the curb/Point of curvature) based on DPW&T Standard 500.12 for Street Light Spacing in an Urban Area. This report assesses the DPW&T proposal in terms of key issues that it is intended to address. Several other critical issues are identified which should be taken into consideration by any proposal to replace the street lights on Belcrest Road. Our report then presents and describes in detail the suggested alternative street light replacement program that, in our opinion, will best address all of the critical issues associated with the ultimate goal of continuous lighting and enhanced safety for pedestrians and bicyclists along Belcrest after dark. The balance of this document sets forth general design recommendations and a suggested three-phase schedule for completion of this project. Existing Conditions Belcrest Road Brick Wall Landscape Green Strip Sidewalk Curb Buffer 1.6’+/- 7.1’+/- 7.6’+/- 3.5’+/- Belcrest Road
  • 3. Prince George’s PlazaTDDP Implementation Program:Technical Report #1 3 Introduction Belcrest Road is the primary north-south thoroughfare in the Prince George’s PlazaTransit District, and is envisioned to carry a significant portion of theTransit District’s north-south vehicular, transit, bicycle, and pedestrian traffic over the next 20 years.The street lights on Belcrest Road have failed and require immediate replacement. The Department of PublicWorks andTransportation’s Specifications and Standards for Roadways and Bridges recommend traditional, cobra-head street lights at intervals up to 150 feet.This project could cost several million dollars. DPW&T’s proposed solution will not provide adequate lighting for pedestrians and is wholly inadequate for the increased pedestrian activity that future redevelopment will generate along Belcrest Road.The standard cobra-head lighting retrofit proposed by DPW&T runs the risk of being inadequate and functionally obsolete upon its completion. The need to replace the Belcrest Road street lights presents an opportunity for the County to invest in a highly visible and needed public improvement that will actually produce a safe and walkable after-dark pedestrian environment along Belcrest Road. Key Issues Addressed by the DPW&T Proposal 1. The street lights have failed and require immediate replacement because of their non-standard nature and functional obsolescence. 2. The cost of replacing the failed street lights and connecting conduit is likely to encumber a significant portion of the County’s limited street lighting budget 3. The DPW&T street light replacement proposal recognizes Belcrest Road’s importance as theTransit District’s primary north-south thoroughfare and gateway into the area from the north. Other Critical Issues for Consideration 4. Pedestrian Volumes: Belcrest Road sees significant pedestrian traffic both day and night because of the major destinations that border it (UniversityTown Center, Mall at Prince Georges, and apartment complexes) and the heavy use of public transit (bus and Metro). 5. Inadequate Pedestrian Lighting: Street lights at 150- foot intervals will not provide continuous lighting of the sidewalks, especially with the existing thick tree canopy along Belcrest Road. 6. TDDP Pedestrian Lighting Standards: Should the preliminary Prince George’s PlazaTransit District Development Plan (TDDP) be approved, property owners would be required to install pedestrian-scaled street lighting at intervals not to exceed 40 feet as redevelopment occurs, regardless of existing lighting that covers the cartway of Belcrest Road. 7. Anticipated Pedestrian Volumes: The volume of pedestrian traffic along Belcrest Road is expected to greatly increase with the redevelopment of the Landy and Percontee properties, the University Town Center’sToledo Road parking lot, and the Mall at Prince Georges. As this redevelopment occurs, insufficient lighting along Belcrest Road may create areas of darkness and shadow along this important pedestrian commuting route. Future redevelopment might not occur or succeed if residents and/or workers are concerned about the safety of pedestrian access to the Metro station, especially after dark. 8. Cycle Track: Should the preliminaryTDDP be approved, property owners on the west side of Belcrest Road would be required to construct, or dedicate right-of-way for, a two-way cycle track outside of the existing west curb. Future streetscape improvements would have to accommodate this feature. 9. Street Trees: The street trees along Belcrest Road are appropriate for the envisioned future Downtown and should be retained. Sidewalk material precedent Existing tree encroaching pedestrian clear zone
  • 4. Prince George’s PlazaTDDP Implementation Program:Technical Report #14 What We are Proposing The intent of our suggested alternative street replacement program is to maintain the existing curb-to-curb dimensions and street trees while allowing for the retrofit of the frontage zone to support bicycling, increased pedestrian activity, and street-level commerce abutting the sidewalk in accordance with the requirements of the preliminary Prince George’s PlazaTransit District Development Plan upon its approval. Phase 1: The County proceeds with its current project but a) installs two-headed street lights that illuminate both the vehicular cartway and the sidewalk and b) install new street light conduits that will allow access to power for future two-headed street lights installed at 50-foot intervals. A new 10-foot sidewalk is also installed along the west side of Belcrest Road to serve both pedestrians and bicyclists. Phase 2: Shouldanindependentfundingsourcebeidentified,the County or other entity installs infill two-headed street lights at the above- recommended 50-foot intervals.This creates the desired safe pedestrian environment and removes a significant public improvement cost from the balance sheet of future private redevelopment. Phase 3: As redevelopment occurs, a new 10-foot sidewalk clear zone will be constructed outside of the existing tree zone and the existing sidewalk would ultimately be retrofitted as cycle track.
  • 5. Prince George’s PlazaTDDP Implementation Program:Technical Report #1 5 Phase One: Installation of Replacement Street Lights and Conduit (Years 1-3) 10’ Sidewalk Existing Conditions Belcrest Road (southbound) Intent: To construct new infrastructure that will ultimately provide continuous lighting along Belcrest Road’s sidewalks. In this phase, DPW&T will work with PEPCO to install initial street lights and electric conduits while preserving existing landscape, tree canopy, and brick wall. A new sidewalk would also be installed along the west side of Belcrest Road if new funding is identified to pay for it (see program details below). A. New electric conduits should be placed along Belcrest Road to support new street lights. B. Conduit access points (marked by protective electric conduit caps flush to the sidewalk) should be installed every 50 feet in order to support future closely-spaced street lights. C. Street lights that include both elevated vehicular lamps and lamps (approximately 14 feet high at most) focused on the sidewalk, should be installed every 100 feet. PEPCO’sTeardrop lamp, or similar fixture, should be used; such fixtures are required of private property owners within theTransit District. Program: 1. Replace existing street lights. 2. Replace existing sidewalk on the west side of Belcrest Road with a new 10-foot sidewalk (to be retrofitted to include a cycle track in Phase 3). 3. Install new street lights five (5) feet from existing curb. 4. Place new street lights every 100 feet center-to-center. 5. Maintain existing tree canopy and landscape. “ ” marks the location of new lights added in PhaseTwo.
  • 6. Prince George’s PlazaTDDP Implementation Program:Technical Report #16 PhaseTwo: Installation of Infill Light Fixtures (Years 3-6) Intent: To eliminate dark zones between light fixtures by installing second batch of street lights financed by different funding sources. Should this option not prove feasible, see PhaseThree. A. New street lights should be placed every 50 feet center-to- center from existing street lights. Program: 1. Identify alternative funding source for construction and/or maintenance of additional street lights. 2. Install pedestrian street lights on the previously-installed conduit access points, with a five (5)-foot setback from the existing curb. 3. Install new pedestrian street lights every 50 feet center-to-center from existing street lights. Pedestrian street light should not be taller than 14 feet in height. 4. Maintain the existing tree canopy and landscape. 10’ Sidewalk Existing Conditions Example of an ideal street light for Belcrest Road - Two-Headed Teardrop style Belcrest Road (southbound)
  • 7. Prince George’s PlazaTDDP Implementation Program:Technical Report #1 7 PhaseThree:Transformation of Belcrest Road Frontage Area (BeyondYear 6) 2’ Cycle Track 10’ Sidewalk 5’ Landscape Example of mixed-use development along the cultural trail Indianapolis Cultural Trail: Example of a clear landscaped delineation between sidewalk, trail, and pedestrian street light. 4’ 4’ 3’ Existing Buffer (to be repainted) Intent: To implement the Prince George’s PlazaTransit District Development Plan as redevelopment occurs, including the required construction of an expanded sidewalk and a cycle track (if the expanded sidewalk is constructed in Phase 1, it would be retrofitted to include a cycle track). New Development: 1. Development proposals must conform to the newTransit District Standards: a. New buildings along Belcrest Road will be at a build to line framing the sidewalk and helping to create a more active and safe environment. b. Property owners are required to construct a new sidewalk clear zone outside of the existing tree zone, along with any additional sidewalk frontage they desire to support retail/ restaurant operations. 2. New sidewalks will tie into an at-least five (5)-foot-wide tree/ landscape strip. It is recommended to repurpose existing brick or sidewalk pavement and place it between green boxes. 3.The two-way cycle track will be installed where the current (or expanded) sidewalk meets the west-side curb, with the street lights in its median.This is not optimal, but necessary to support cycle traffic while maintaining the existing curb-to-curb and not requiring excessive re-purposing of private property for public use because of the cycle track. Program: 1. Maintain existing tree canopy 2. Reduce landscape strip to 5’x 10’green boxes. 3. Between green boxes, special stamped concrete, brick, or other paving material should be used to demarcate a separation between sidewalk and cycle track and allow cyclists to enter/exit the track. 4. Stripe, stamped concrete, or landscaping for clear delineation between bicycle travel lanes. 5. Create physical barrier between the northbound cycle track and the southbound auto travel lanes.