SlideShare a Scribd company logo
1 of 19
PRESENTATION
ON LEAN
MANUFACTURING
By
Ashish R. Sontakke
M.Tech.Cad-Cam
Roll No.-16
VNIT
What is LEAN MANUFACTURING??
“The production of goods using less
of everything by reducing ‘waste’ and
increasing value added activity”
ORIGIN
Lean Manufacturing is sometimes called the
Toyota Production System (TPS) because
Toyota Motor Company’s Eiji Toyoda and
Taiichui Ohno are given credit for its
approach and innovations
“Key” Lean Manufacturing Techniques
1. Elimination of waste
2. 5s
3. JIT/Pull production system
4. Cellular Manufacturing
5. KANBAN
What is Waste?
• Waste is anything that
happens to a product that
does not add value from the
customer’s perspective
• Products being stored,
inspected or delayed,
products waiting in queues,
and defective products do
not add value
The 8 wastes
Introduction to ‘TIM WOODS’
T – Transport
I – Inventory
M – Movement
W – Waiting
O – Over-processing
O – Over-production
D - Defects
S - Skill
5s
1.Seiri -Sorting
2.Seiton-Stabilizing or Straightening Out
3.Seiso-Sweeping or Shining
4.Seiketsu-Standardizing
5.Shitsuke-Sustaining the Practice
5S Examples
Before After
JIT/Pull system
• JIT literally means Just In Time.
• It aims to produce only what is needed, when
it is needed.
• Production is pulled by the downstream
workstation so that each workstation should
only produce what is requested by the next
workstation.
• One-piece flow is key implementation which
means that parts are moved through
operations from step-to-step with no WIP in
between either one piece at a time or a small
batch at a time.
Gravity Conveyor for one piece flow
between two machines
Cellular manufacturing
1.In Functional Manufacturing similar machines
are placed close together (e.g. lathes, millers,
drills etc.).
2.In Cellular Manufacturing systems machines
are grouped together according to the
families of parts produced.
3.The major advantage is that material flow is
significantly improved, which reduces the
distance travelled by materials.
Cellular manufacturing
Example of Cell
KANBAN
A system of continuous supply of components
and parts such that workers have what they
need, where they need, when they need it
KANBAN is the process through JIT is
achieved
Assembly line (KANBAN)
Key Implications of lean
manufacturing
Traditional Lean
Orientation Supply driven Customer driven
Planning Orders are
pushed though
factory based on
production
plan/forecast
Orders are pulled
through factory
based on
customer/downst
ream demand
Batch size Large small
Quality
inspection
Checking of
samples by QC
inspectors
In-line inspection
by workers
Inventory Buffer of work-
in-progress
Little or no work-
in-progress
Advantages
• Increased overall productivity
• Reduced amount of floor space required
• Reduced manufacturing lead time
• Improved flexibility to react to changes
• Improved quality
• Less inventory
• Increases working standards
• Increases worker talents
Disadvantages
• Success of lean requires the
full commitment and
involvement of all employees.
• Long term commitment
required (i.e. workers should
give full support to apply
lean)
THANK YOU

More Related Content

What's hot

Report on JIT , for Projects and Seminars
Report on JIT , for Projects and SeminarsReport on JIT , for Projects and Seminars
Report on JIT , for Projects and Seminarsomkar jagtap
 
Lean manufanturing
Lean manufanturingLean manufanturing
Lean manufanturingshahrool
 
Just in Time and Lean Manufacturing
Just in Time and Lean ManufacturingJust in Time and Lean Manufacturing
Just in Time and Lean Manufacturingshahroze11
 
Implementation of Lean - Case Study
Implementation of Lean - Case StudyImplementation of Lean - Case Study
Implementation of Lean - Case StudyAmeer Hasan Malik
 
Just in time inventory control toyota
Just in time inventory control  toyotaJust in time inventory control  toyota
Just in time inventory control toyotaKavita Antony
 
Just In Time Analysis
Just In Time AnalysisJust In Time Analysis
Just In Time AnalysisAshim Roy
 
Just in time and Lean systems
Just in time and Lean systemsJust in time and Lean systems
Just in time and Lean systemsAyman Aljahdali
 
Process layout operations management
Process layout   operations managementProcess layout   operations management
Process layout operations managementSilas Alexander
 
Introduction to Cellular Manufacturing - ADDVALUE - Nilesh Arora
Introduction to Cellular Manufacturing - ADDVALUE - Nilesh AroraIntroduction to Cellular Manufacturing - ADDVALUE - Nilesh Arora
Introduction to Cellular Manufacturing - ADDVALUE - Nilesh AroraADD VALUE CONSULTING Inc
 
Implementation of Lean Manufacturing Principles in Foundries
Implementation of Lean Manufacturing Principles in FoundriesImplementation of Lean Manufacturing Principles in Foundries
Implementation of Lean Manufacturing Principles in FoundriesIJMER
 
IRJET- Productivity Improvement by Implementing Lean Manufacturing Tools ...
IRJET-  	  Productivity Improvement by Implementing Lean Manufacturing Tools ...IRJET-  	  Productivity Improvement by Implementing Lean Manufacturing Tools ...
IRJET- Productivity Improvement by Implementing Lean Manufacturing Tools ...IRJET Journal
 
Zero Gravity Filters Corporate Presentation
Zero Gravity Filters Corporate PresentationZero Gravity Filters Corporate Presentation
Zero Gravity Filters Corporate PresentationDwayne Deziel
 

What's hot (16)

Report on JIT , for Projects and Seminars
Report on JIT , for Projects and SeminarsReport on JIT , for Projects and Seminars
Report on JIT , for Projects and Seminars
 
Lean manufanturing
Lean manufanturingLean manufanturing
Lean manufanturing
 
Just in Time and Lean Manufacturing
Just in Time and Lean ManufacturingJust in Time and Lean Manufacturing
Just in Time and Lean Manufacturing
 
Implementation of Lean - Case Study
Implementation of Lean - Case StudyImplementation of Lean - Case Study
Implementation of Lean - Case Study
 
Just in time inventory control toyota
Just in time inventory control  toyotaJust in time inventory control  toyota
Just in time inventory control toyota
 
Just In Time Analysis
Just In Time AnalysisJust In Time Analysis
Just In Time Analysis
 
Just in Time Technique
Just in Time TechniqueJust in Time Technique
Just in Time Technique
 
Lean Manufacturing
Lean ManufacturingLean Manufacturing
Lean Manufacturing
 
Just in time and Lean systems
Just in time and Lean systemsJust in time and Lean systems
Just in time and Lean systems
 
10. just in-time
10. just in-time10. just in-time
10. just in-time
 
Process layout operations management
Process layout   operations managementProcess layout   operations management
Process layout operations management
 
Introduction to Cellular Manufacturing - ADDVALUE - Nilesh Arora
Introduction to Cellular Manufacturing - ADDVALUE - Nilesh AroraIntroduction to Cellular Manufacturing - ADDVALUE - Nilesh Arora
Introduction to Cellular Manufacturing - ADDVALUE - Nilesh Arora
 
Implementation of Lean Manufacturing Principles in Foundries
Implementation of Lean Manufacturing Principles in FoundriesImplementation of Lean Manufacturing Principles in Foundries
Implementation of Lean Manufacturing Principles in Foundries
 
IRJET- Productivity Improvement by Implementing Lean Manufacturing Tools ...
IRJET-  	  Productivity Improvement by Implementing Lean Manufacturing Tools ...IRJET-  	  Productivity Improvement by Implementing Lean Manufacturing Tools ...
IRJET- Productivity Improvement by Implementing Lean Manufacturing Tools ...
 
Zero Gravity Filters Corporate Presentation
Zero Gravity Filters Corporate PresentationZero Gravity Filters Corporate Presentation
Zero Gravity Filters Corporate Presentation
 
7 mudas
7 mudas7 mudas
7 mudas
 

Similar to ashish sontakke_lean_mfg

Lean_Manufacturing___Just-in-Time.ppt
Lean_Manufacturing___Just-in-Time.pptLean_Manufacturing___Just-in-Time.ppt
Lean_Manufacturing___Just-in-Time.pptrahul368457
 
JIT and lean operations
JIT and lean operationsJIT and lean operations
JIT and lean operationsRajThakuri
 
Lean production System - TPS
Lean production System - TPSLean production System - TPS
Lean production System - TPSPrakash Prakash
 
Presentation on Just in Time
Presentation on Just in TimePresentation on Just in Time
Presentation on Just in TimeMusfiqur Rahman
 
Overview on Kanban Methodology and its Implementation
Overview on Kanban Methodology and its ImplementationOverview on Kanban Methodology and its Implementation
Overview on Kanban Methodology and its ImplementationLaukik Raut
 
Lean - PPT (Lean manufacturing and six sigma)
Lean - PPT (Lean manufacturing and six sigma)Lean - PPT (Lean manufacturing and six sigma)
Lean - PPT (Lean manufacturing and six sigma)Blankdevil
 
lean manufacturing.ppt cost profit accounts
lean manufacturing.ppt cost profit accountslean manufacturing.ppt cost profit accounts
lean manufacturing.ppt cost profit accountsSabaKhalid48
 
kanban an integrated jit system
kanban an integrated jit systemkanban an integrated jit system
kanban an integrated jit systemSridhar Siddu
 
Lean manufacturing overview
Lean manufacturing overviewLean manufacturing overview
Lean manufacturing overviewPruek Pinyo
 
Ch12 jit+&+lean+systems
Ch12 jit+&+lean+systemsCh12 jit+&+lean+systems
Ch12 jit+&+lean+systemsvideoaakash15
 
Kanbanultimate Adi Apparel Interns
Kanbanultimate Adi Apparel InternsKanbanultimate Adi Apparel Interns
Kanbanultimate Adi Apparel InternsTanuj Kujur
 

Similar to ashish sontakke_lean_mfg (20)

PPT ON Just in time technique (JIT)
PPT ON Just in time technique (JIT)PPT ON Just in time technique (JIT)
PPT ON Just in time technique (JIT)
 
0201B Lean Production
0201B Lean Production0201B Lean Production
0201B Lean Production
 
Lean_Manufacturing___Just-in-Time.ppt
Lean_Manufacturing___Just-in-Time.pptLean_Manufacturing___Just-in-Time.ppt
Lean_Manufacturing___Just-in-Time.ppt
 
Jit In Toyota
Jit In ToyotaJit In Toyota
Jit In Toyota
 
JIT and lean operations
JIT and lean operationsJIT and lean operations
JIT and lean operations
 
LEAN MANUFACTURING USES
LEAN MANUFACTURING USESLEAN MANUFACTURING USES
LEAN MANUFACTURING USES
 
13. lean production system pgp
13. lean production system pgp13. lean production system pgp
13. lean production system pgp
 
Lean production System - TPS
Lean production System - TPSLean production System - TPS
Lean production System - TPS
 
Just in time
Just in timeJust in time
Just in time
 
Presentation on Just in Time
Presentation on Just in TimePresentation on Just in Time
Presentation on Just in Time
 
Overview on Kanban Methodology and its Implementation
Overview on Kanban Methodology and its ImplementationOverview on Kanban Methodology and its Implementation
Overview on Kanban Methodology and its Implementation
 
Lean - PPT (Lean manufacturing and six sigma)
Lean - PPT (Lean manufacturing and six sigma)Lean - PPT (Lean manufacturing and six sigma)
Lean - PPT (Lean manufacturing and six sigma)
 
JUST IN TIME PRODUCTION SYSTEM
JUST IN TIME PRODUCTION SYSTEMJUST IN TIME PRODUCTION SYSTEM
JUST IN TIME PRODUCTION SYSTEM
 
BASICS OF LEAN MANUFACTURING
BASICS OF LEAN MANUFACTURINGBASICS OF LEAN MANUFACTURING
BASICS OF LEAN MANUFACTURING
 
lean manufacturing.ppt cost profit accounts
lean manufacturing.ppt cost profit accountslean manufacturing.ppt cost profit accounts
lean manufacturing.ppt cost profit accounts
 
kanban an integrated jit system
kanban an integrated jit systemkanban an integrated jit system
kanban an integrated jit system
 
Lean manufacturing overview
Lean manufacturing overviewLean manufacturing overview
Lean manufacturing overview
 
Lean manufacturing
Lean manufacturingLean manufacturing
Lean manufacturing
 
Ch12 jit+&+lean+systems
Ch12 jit+&+lean+systemsCh12 jit+&+lean+systems
Ch12 jit+&+lean+systems
 
Kanbanultimate Adi Apparel Interns
Kanbanultimate Adi Apparel InternsKanbanultimate Adi Apparel Interns
Kanbanultimate Adi Apparel Interns
 

More from Akash Maurya

Marketing information system akash deep maurya
Marketing information system akash deep mauryaMarketing information system akash deep maurya
Marketing information system akash deep mauryaAkash Maurya
 
vinay kumar actuators report
vinay kumar   actuators reportvinay kumar   actuators report
vinay kumar actuators reportAkash Maurya
 
vinay kumar actuators presentation
vinay kumar   actuators presentationvinay kumar   actuators presentation
vinay kumar actuators presentationAkash Maurya
 
ashok mule rapid prototyping questions
ashok mule   rapid prototyping questionsashok mule   rapid prototyping questions
ashok mule rapid prototyping questionsAkash Maurya
 
ashok mule rapid prototyping presentation
ashok mule   rapid prototyping presentationashok mule   rapid prototyping presentation
ashok mule rapid prototyping presentationAkash Maurya
 
prakash agrawal rapid tooling questions
prakash agrawal   rapid tooling questionsprakash agrawal   rapid tooling questions
prakash agrawal rapid tooling questionsAkash Maurya
 
prakash agrawal rapid tooling presentation
prakash agrawal   rapid tooling presentationprakash agrawal   rapid tooling presentation
prakash agrawal rapid tooling presentationAkash Maurya
 
shashank soni sensors presentation
shashank soni   sensors presentationshashank soni   sensors presentation
shashank soni sensors presentationAkash Maurya
 
santosh kumar fuzzy logic presentation
santosh kumar   fuzzy logic presentationsantosh kumar   fuzzy logic presentation
santosh kumar fuzzy logic presentationAkash Maurya
 
mohsin dalvi artificial neural networks questions
mohsin dalvi   artificial neural networks questionsmohsin dalvi   artificial neural networks questions
mohsin dalvi artificial neural networks questionsAkash Maurya
 
mohsin dalvi artificial neural networks presentation
mohsin dalvi   artificial neural networks presentationmohsin dalvi   artificial neural networks presentation
mohsin dalvi artificial neural networks presentationAkash Maurya
 
sameer amale edm presentation
sameer amale   edm presentationsameer amale   edm presentation
sameer amale edm presentationAkash Maurya
 
vivek sharma agv and asrs
vivek sharma   agv and asrsvivek sharma   agv and asrs
vivek sharma agv and asrsAkash Maurya
 
nakul agarwal micromachining presentation
nakul agarwal   micromachining presentationnakul agarwal   micromachining presentation
nakul agarwal micromachining presentationAkash Maurya
 
ravi reverseengineeringitsapplication01 121101044845-phpapp02
ravi reverseengineeringitsapplication01 121101044845-phpapp02ravi reverseengineeringitsapplication01 121101044845-phpapp02
ravi reverseengineeringitsapplication01 121101044845-phpapp02Akash Maurya
 
shivkumar pathak web based manufacturing presentation
shivkumar pathak   web based manufacturing presentationshivkumar pathak   web based manufacturing presentation
shivkumar pathak web based manufacturing presentationAkash Maurya
 
nishit ambule special purpose machines questions
nishit ambule   special purpose machines questionsnishit ambule   special purpose machines questions
nishit ambule special purpose machines questionsAkash Maurya
 
nishit ambule special purpose machines presentation
nishit ambule   special purpose machines presentationnishit ambule   special purpose machines presentation
nishit ambule special purpose machines presentationAkash Maurya
 
visheshwar oraon robotics presentation
visheshwar oraon   robotics presentationvisheshwar oraon   robotics presentation
visheshwar oraon robotics presentationAkash Maurya
 
nikhil bhagat cmm presentation
nikhil bhagat   cmm presentationnikhil bhagat   cmm presentation
nikhil bhagat cmm presentationAkash Maurya
 

More from Akash Maurya (20)

Marketing information system akash deep maurya
Marketing information system akash deep mauryaMarketing information system akash deep maurya
Marketing information system akash deep maurya
 
vinay kumar actuators report
vinay kumar   actuators reportvinay kumar   actuators report
vinay kumar actuators report
 
vinay kumar actuators presentation
vinay kumar   actuators presentationvinay kumar   actuators presentation
vinay kumar actuators presentation
 
ashok mule rapid prototyping questions
ashok mule   rapid prototyping questionsashok mule   rapid prototyping questions
ashok mule rapid prototyping questions
 
ashok mule rapid prototyping presentation
ashok mule   rapid prototyping presentationashok mule   rapid prototyping presentation
ashok mule rapid prototyping presentation
 
prakash agrawal rapid tooling questions
prakash agrawal   rapid tooling questionsprakash agrawal   rapid tooling questions
prakash agrawal rapid tooling questions
 
prakash agrawal rapid tooling presentation
prakash agrawal   rapid tooling presentationprakash agrawal   rapid tooling presentation
prakash agrawal rapid tooling presentation
 
shashank soni sensors presentation
shashank soni   sensors presentationshashank soni   sensors presentation
shashank soni sensors presentation
 
santosh kumar fuzzy logic presentation
santosh kumar   fuzzy logic presentationsantosh kumar   fuzzy logic presentation
santosh kumar fuzzy logic presentation
 
mohsin dalvi artificial neural networks questions
mohsin dalvi   artificial neural networks questionsmohsin dalvi   artificial neural networks questions
mohsin dalvi artificial neural networks questions
 
mohsin dalvi artificial neural networks presentation
mohsin dalvi   artificial neural networks presentationmohsin dalvi   artificial neural networks presentation
mohsin dalvi artificial neural networks presentation
 
sameer amale edm presentation
sameer amale   edm presentationsameer amale   edm presentation
sameer amale edm presentation
 
vivek sharma agv and asrs
vivek sharma   agv and asrsvivek sharma   agv and asrs
vivek sharma agv and asrs
 
nakul agarwal micromachining presentation
nakul agarwal   micromachining presentationnakul agarwal   micromachining presentation
nakul agarwal micromachining presentation
 
ravi reverseengineeringitsapplication01 121101044845-phpapp02
ravi reverseengineeringitsapplication01 121101044845-phpapp02ravi reverseengineeringitsapplication01 121101044845-phpapp02
ravi reverseengineeringitsapplication01 121101044845-phpapp02
 
shivkumar pathak web based manufacturing presentation
shivkumar pathak   web based manufacturing presentationshivkumar pathak   web based manufacturing presentation
shivkumar pathak web based manufacturing presentation
 
nishit ambule special purpose machines questions
nishit ambule   special purpose machines questionsnishit ambule   special purpose machines questions
nishit ambule special purpose machines questions
 
nishit ambule special purpose machines presentation
nishit ambule   special purpose machines presentationnishit ambule   special purpose machines presentation
nishit ambule special purpose machines presentation
 
visheshwar oraon robotics presentation
visheshwar oraon   robotics presentationvisheshwar oraon   robotics presentation
visheshwar oraon robotics presentation
 
nikhil bhagat cmm presentation
nikhil bhagat   cmm presentationnikhil bhagat   cmm presentation
nikhil bhagat cmm presentation
 

Recently uploaded

Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...Dr.Costas Sachpazis
 
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...Dr.Costas Sachpazis
 
Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...
Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...
Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...Christo Ananth
 
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...ranjana rawat
 
Booking open Available Pune Call Girls Pargaon 6297143586 Call Hot Indian Gi...
Booking open Available Pune Call Girls Pargaon  6297143586 Call Hot Indian Gi...Booking open Available Pune Call Girls Pargaon  6297143586 Call Hot Indian Gi...
Booking open Available Pune Call Girls Pargaon 6297143586 Call Hot Indian Gi...Call Girls in Nagpur High Profile
 
Introduction to Multiple Access Protocol.pptx
Introduction to Multiple Access Protocol.pptxIntroduction to Multiple Access Protocol.pptx
Introduction to Multiple Access Protocol.pptxupamatechverse
 
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...ranjana rawat
 
University management System project report..pdf
University management System project report..pdfUniversity management System project report..pdf
University management System project report..pdfKamal Acharya
 
KubeKraft presentation @CloudNativeHooghly
KubeKraft presentation @CloudNativeHooghlyKubeKraft presentation @CloudNativeHooghly
KubeKraft presentation @CloudNativeHooghlysanyuktamishra911
 
College Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service NashikCollege Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service NashikCall Girls in Nagpur High Profile
 
Java Programming :Event Handling(Types of Events)
Java Programming :Event Handling(Types of Events)Java Programming :Event Handling(Types of Events)
Java Programming :Event Handling(Types of Events)simmis5
 
MANUFACTURING PROCESS-II UNIT-1 THEORY OF METAL CUTTING
MANUFACTURING PROCESS-II UNIT-1 THEORY OF METAL CUTTINGMANUFACTURING PROCESS-II UNIT-1 THEORY OF METAL CUTTING
MANUFACTURING PROCESS-II UNIT-1 THEORY OF METAL CUTTINGSIVASHANKAR N
 
ONLINE FOOD ORDER SYSTEM PROJECT REPORT.pdf
ONLINE FOOD ORDER SYSTEM PROJECT REPORT.pdfONLINE FOOD ORDER SYSTEM PROJECT REPORT.pdf
ONLINE FOOD ORDER SYSTEM PROJECT REPORT.pdfKamal Acharya
 
BSides Seattle 2024 - Stopping Ethan Hunt From Taking Your Data.pptx
BSides Seattle 2024 - Stopping Ethan Hunt From Taking Your Data.pptxBSides Seattle 2024 - Stopping Ethan Hunt From Taking Your Data.pptx
BSides Seattle 2024 - Stopping Ethan Hunt From Taking Your Data.pptxfenichawla
 
CCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete Record
CCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete RecordCCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete Record
CCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete RecordAsst.prof M.Gokilavani
 
The Most Attractive Pune Call Girls Manchar 8250192130 Will You Miss This Cha...
The Most Attractive Pune Call Girls Manchar 8250192130 Will You Miss This Cha...The Most Attractive Pune Call Girls Manchar 8250192130 Will You Miss This Cha...
The Most Attractive Pune Call Girls Manchar 8250192130 Will You Miss This Cha...ranjana rawat
 
UNIT-II FMM-Flow Through Circular Conduits
UNIT-II FMM-Flow Through Circular ConduitsUNIT-II FMM-Flow Through Circular Conduits
UNIT-II FMM-Flow Through Circular Conduitsrknatarajan
 
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur High Profile
 
Glass Ceramics: Processing and Properties
Glass Ceramics: Processing and PropertiesGlass Ceramics: Processing and Properties
Glass Ceramics: Processing and PropertiesPrabhanshu Chaturvedi
 
UNIT-III FMM. DIMENSIONAL ANALYSIS
UNIT-III FMM.        DIMENSIONAL ANALYSISUNIT-III FMM.        DIMENSIONAL ANALYSIS
UNIT-III FMM. DIMENSIONAL ANALYSISrknatarajan
 

Recently uploaded (20)

Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
 
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
 
Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...
Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...
Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...
 
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...
 
Booking open Available Pune Call Girls Pargaon 6297143586 Call Hot Indian Gi...
Booking open Available Pune Call Girls Pargaon  6297143586 Call Hot Indian Gi...Booking open Available Pune Call Girls Pargaon  6297143586 Call Hot Indian Gi...
Booking open Available Pune Call Girls Pargaon 6297143586 Call Hot Indian Gi...
 
Introduction to Multiple Access Protocol.pptx
Introduction to Multiple Access Protocol.pptxIntroduction to Multiple Access Protocol.pptx
Introduction to Multiple Access Protocol.pptx
 
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
 
University management System project report..pdf
University management System project report..pdfUniversity management System project report..pdf
University management System project report..pdf
 
KubeKraft presentation @CloudNativeHooghly
KubeKraft presentation @CloudNativeHooghlyKubeKraft presentation @CloudNativeHooghly
KubeKraft presentation @CloudNativeHooghly
 
College Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service NashikCollege Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
 
Java Programming :Event Handling(Types of Events)
Java Programming :Event Handling(Types of Events)Java Programming :Event Handling(Types of Events)
Java Programming :Event Handling(Types of Events)
 
MANUFACTURING PROCESS-II UNIT-1 THEORY OF METAL CUTTING
MANUFACTURING PROCESS-II UNIT-1 THEORY OF METAL CUTTINGMANUFACTURING PROCESS-II UNIT-1 THEORY OF METAL CUTTING
MANUFACTURING PROCESS-II UNIT-1 THEORY OF METAL CUTTING
 
ONLINE FOOD ORDER SYSTEM PROJECT REPORT.pdf
ONLINE FOOD ORDER SYSTEM PROJECT REPORT.pdfONLINE FOOD ORDER SYSTEM PROJECT REPORT.pdf
ONLINE FOOD ORDER SYSTEM PROJECT REPORT.pdf
 
BSides Seattle 2024 - Stopping Ethan Hunt From Taking Your Data.pptx
BSides Seattle 2024 - Stopping Ethan Hunt From Taking Your Data.pptxBSides Seattle 2024 - Stopping Ethan Hunt From Taking Your Data.pptx
BSides Seattle 2024 - Stopping Ethan Hunt From Taking Your Data.pptx
 
CCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete Record
CCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete RecordCCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete Record
CCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete Record
 
The Most Attractive Pune Call Girls Manchar 8250192130 Will You Miss This Cha...
The Most Attractive Pune Call Girls Manchar 8250192130 Will You Miss This Cha...The Most Attractive Pune Call Girls Manchar 8250192130 Will You Miss This Cha...
The Most Attractive Pune Call Girls Manchar 8250192130 Will You Miss This Cha...
 
UNIT-II FMM-Flow Through Circular Conduits
UNIT-II FMM-Flow Through Circular ConduitsUNIT-II FMM-Flow Through Circular Conduits
UNIT-II FMM-Flow Through Circular Conduits
 
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
 
Glass Ceramics: Processing and Properties
Glass Ceramics: Processing and PropertiesGlass Ceramics: Processing and Properties
Glass Ceramics: Processing and Properties
 
UNIT-III FMM. DIMENSIONAL ANALYSIS
UNIT-III FMM.        DIMENSIONAL ANALYSISUNIT-III FMM.        DIMENSIONAL ANALYSIS
UNIT-III FMM. DIMENSIONAL ANALYSIS
 

ashish sontakke_lean_mfg

  • 1. PRESENTATION ON LEAN MANUFACTURING By Ashish R. Sontakke M.Tech.Cad-Cam Roll No.-16 VNIT
  • 2. What is LEAN MANUFACTURING?? “The production of goods using less of everything by reducing ‘waste’ and increasing value added activity”
  • 3. ORIGIN Lean Manufacturing is sometimes called the Toyota Production System (TPS) because Toyota Motor Company’s Eiji Toyoda and Taiichui Ohno are given credit for its approach and innovations
  • 4. “Key” Lean Manufacturing Techniques 1. Elimination of waste 2. 5s 3. JIT/Pull production system 4. Cellular Manufacturing 5. KANBAN
  • 5. What is Waste? • Waste is anything that happens to a product that does not add value from the customer’s perspective • Products being stored, inspected or delayed, products waiting in queues, and defective products do not add value
  • 6. The 8 wastes Introduction to ‘TIM WOODS’ T – Transport I – Inventory M – Movement W – Waiting O – Over-processing O – Over-production D - Defects S - Skill
  • 7. 5s 1.Seiri -Sorting 2.Seiton-Stabilizing or Straightening Out 3.Seiso-Sweeping or Shining 4.Seiketsu-Standardizing 5.Shitsuke-Sustaining the Practice
  • 9. JIT/Pull system • JIT literally means Just In Time. • It aims to produce only what is needed, when it is needed. • Production is pulled by the downstream workstation so that each workstation should only produce what is requested by the next workstation. • One-piece flow is key implementation which means that parts are moved through operations from step-to-step with no WIP in between either one piece at a time or a small batch at a time.
  • 10. Gravity Conveyor for one piece flow between two machines
  • 11. Cellular manufacturing 1.In Functional Manufacturing similar machines are placed close together (e.g. lathes, millers, drills etc.). 2.In Cellular Manufacturing systems machines are grouped together according to the families of parts produced. 3.The major advantage is that material flow is significantly improved, which reduces the distance travelled by materials.
  • 14. KANBAN A system of continuous supply of components and parts such that workers have what they need, where they need, when they need it KANBAN is the process through JIT is achieved
  • 16. Key Implications of lean manufacturing Traditional Lean Orientation Supply driven Customer driven Planning Orders are pushed though factory based on production plan/forecast Orders are pulled through factory based on customer/downst ream demand Batch size Large small Quality inspection Checking of samples by QC inspectors In-line inspection by workers Inventory Buffer of work- in-progress Little or no work- in-progress
  • 17. Advantages • Increased overall productivity • Reduced amount of floor space required • Reduced manufacturing lead time • Improved flexibility to react to changes • Improved quality • Less inventory • Increases working standards • Increases worker talents
  • 18. Disadvantages • Success of lean requires the full commitment and involvement of all employees. • Long term commitment required (i.e. workers should give full support to apply lean)