BID PROCESS MANAGEMENT
SYSTEM
Tweet @smylingassasin, Email: biswa.prakash@hotmail.com
Agenda
1. Fundamental of Bidding
2. Bidding Process
3. Evaluation criteria
4. Bid Evaluation Methodology
5. e-Auction process
6. Reverse auction
7. Swiss challenge method
9. Other general terms &
conditions
10. Govt. Procurement process
11. PSU Procurement process
12. Procurement process of
funding agency
13. Vendor Registration process
Tweet @smylingassasin, Email: biswa.prakash@hotmail.com
Fundamental of Bidding
 A Bid Management System, either manual or
electronic, is required to ensure an effective and
efficient process for:
a) the buyer wishing to source products or
services and
b) the seller wishing to bid to supply products
or services.
Tweet @smylingassasin, Email: biswa.prakash@hotmail.com
Govt. Procurement Process
 Covers the procurement of GOODS,WORKS
AND SERVICES by all Government Ministries,
Departments, Agencies, Statutory Corporations
and Public sector undertakings in the Center
and the States, Municipal Corporations and
other Local bodies and even by private sector
undertakings providing public service on
monopoly basis.
Tweet @smylingassasin, Email: biswa.prakash@hotmail.com
Objective of Govt. Procurement
Process
 TO PROCURE WORK, MATERIAL,
SERVICES OF THE SPECIFIED QUALITY
WITHIN THE SPECIFIED TIME AT THE
MOST COMPETITIVE PRICES IN A FAIR,
JUST & TRANSPARENT MANNER----
Tweet @smylingassasin, Email: biswa.prakash@hotmail.com
Stages in Govt. Procurement
Process
1. PRE-TENDER STAGE
2. TENDER STAGE
3. EXECUTION STAGE
Tweet @smylingassasin, Email: biswa.prakash@hotmail.com
Stages in Govt. Procurement
Process
1. PRE-TENDER STAGE
i. Project Formulation
ii. Appointment of Consultants
iii. Preparation of Detailed Project Report
(Estimate, Design, etc.)
Tweet @smylingassasin, Email: biswa.prakash@hotmail.com
Stages in Govt. Procurement
Process
2. TENDER STAGE
i. Preparation of Tender Documents
ii. Inviting & Opening of Tenders
iii. Prequalification
iv. Tender Evaluation &Award of Work
Tweet @smylingassasin, Email: biswa.prakash@hotmail.com
Stages in Govt. Procurement
Process
3.EXECUTION STAGE
i. Agreement/Purchase Order
ii. Contract Performance
(A) Advance Payments
(B) Implementation Of Contract Provisions
(C ) Time And Cost Overrun
(D) Payments
(E) Quality Of Work/Inspection
Tweet @smylingassasin, Email: biswa.prakash@hotmail.com
Vendor Selection Process
 Selection and registration of firms/suppliers and their
evaluation must be clear and transparent.
 PQ evaluation criteria must be incorporated in the bid
documents in clear and unambiguous terms
 Prepare the PQ criteria specific to the requirement of the
work.
 Evaluate the bids exactly as per the notified criteria.
Tweet @smylingassasin, Email: biswa.prakash@hotmail.com
Vendor Selection Process
 Prequalification necessary to bring competent contractors into
competition with technical & financial capability required for
the particular procurement. To be done on the basis of :
 Experience and past performance on similar contracts
 Capabilities with respect to personnel, equipment and
manufacturing facilities
 Financial standing through latest Annual report
(balance sheet and P & L account) of last three years.
Tweet @smylingassasin, Email: biswa.prakash@hotmail.com
Bidding Process
• Single bid or two bid (for IT and
communications systems, turn key projects)
• Two bid system: techno-commercial and price
bids are called separately.
• The techno-commercial bid contains all terms
and conditions including commercial terms
except price.
Tweet @smylingassasin, Email: biswa.prakash@hotmail.com
Bidding Process
• Technical bids will be evaluated by Tender
Evaluation Committee
• Price bids of only technically acceptable offers are
to be opened to ensure an objective evaluation of
tenders.
• In case of two-stage two bid system,
price/commercial bids are called from only
technically acceptable vendors after technical
evaluation.
Tweet @smylingassasin, Email: biswa.prakash@hotmail.com
Bid Evaluation
Methodology There are two process used for awarding various e-governance
contracts (both Consulting and Software Implementation).
 QCBS (Quality cum Cost Basis) method gives
weightage to both quality and cost. The weights are usually
more for technical (or quality) and less for commercial (or
cost) aspects of the bid (usually 60:40 or 70:30 or
sometimes even 80:20).
 L1 gives the weightage to Commercial aspect of the bid
only where Bidder who quotes lowest wins the bid.
Tweet @smylingassasin, Email: biswa.prakash@hotmail.com
Earnest Money Deposit
 To safeguard the interest of Dept. (withdrawal /
alter the bid by bidder)
 Exemption – Regd. With Central Purchase
Organization / National Small Industries
Corporation
 EMD - 2 % to 5% of estimated value
 Can be DD/Banker Cheque /BG
 Unsuccessful bidders EMD should be returned
/refunded at the earliest.
Tweet @smylingassasin, Email: biswa.prakash@hotmail.com
Performance Security
 From the successful bidders
 Amount – 5% to 10%
 DD
 Should be valid for 60 days beyond the date of
completion of all the contractual obligations of
the supplier including warranty
 Bid Security should be refunded on receipt of
Performance Security
Tweet @smylingassasin, Email: biswa.prakash@hotmail.com
e-Auction
 e-Auction is introduced to negotiate terms of
contract between suppliers and buyers mainly in
the industrial sector.
 The electronic auction (e-Auction) is an e-
business between auctioneers and bidders, which
takes place on an electronic marketplace.
 It is an electronic commerce which occurs
business to business (B2B), business to
consumer (B2C), or consumer-to-consumer
(C2C)
Tweet @smylingassasin, Email: biswa.prakash@hotmail.com
Reverse Auction
 The two major types of the electronic auction
are forward auction in which several buyers bid for
one seller's goods and reverse auction in which
several sellers bid for one buyer's order.
 Reverse auctions are the other major form of
auctions. In a reverse auction, a single buyer makes
potential sellers aware of their intent to buy a
specified good or service
 During the course of the actual reverse auction event,
the sellers bid against one another to secure the
buyer’s business, driving the price to be paid for the
item downward. Thus, the winning bidder is the seller
who offers the lowest price.
Tweet @smylingassasin, Email: biswa.prakash@hotmail.com
Reverse Auction
 Reverse auctions are most typically used for
procurement by private companies, public
sector agencies, and non-profit organizations.
Tweet @smylingassasin, Email: biswa.prakash@hotmail.com
Swiss Challenge Method
 Swiss Challenge System is a new bidding process to help
private sector initiative in core sector projects. It's an offer
made by the original proponent to the government
ensuring his process to be best (in terms of effectiveness
including both the factors cost and time) by his initiative
as a result of his own innovative approach or on the
demand of the government to perform certain task.
 The Swiss challenge system, like the bonus system, further
allows third parties to make better offers (challenges) for a
project during a designated period with simple objective
to discourage frivolous project, or to avoid exaggerated
project development costs. Then accordingly, the original
proponent gets the right to counter-match any superior
offers given by the third party.
Tweet @smylingassasin, Email: biswa.prakash@hotmail.com
Working of Swiss Challenge
Method
 The system basically works on two different patterns, its
up to the Government to decide as to which one they
want to adopt. The two main ways are as follows:
 The Government can either purchase the intellectual
property rights for a project concept from the
proponent or then award the project through a
competitive bidding process in which no bidder has a
predefined advantage.
 The Government can offer the original proponent an
advantage in a competitive bidding process. In this case
the government should create rewards that satisfy the
original proponent while still allowing a truly
competitive process.
Tweet @smylingassasin, Email: biswa.prakash@hotmail.com
General Evaluation
Criteria
 Satisfaction of Conditions specific to the contract
 Sample Testing
 Capacity Evaluation.
 Turnover
 Statutory documentation
 Arrival at Outcome Price of the bid
 Determination of L-1, L-2, L-3……
 Determining Reasonableness of the L-1 Rates
 Recommendation for Negotiation (if require)
Tweet @smylingassasin, Email: biswa.prakash@hotmail.com
General Evaluation
Criteria
 Financial and Technical sanction of competent
authority is available.
 Adequate and wide publicity is given. Advertisement is
posted on website and tender documents are available
for downloading.
 Convenient tender receiving/opening time and address
of the tender receiving officials/tender box are
properly notified.
 In the case of limited tender, panel is prepared in a
transparent manner clearly publishing the eligibility
criteria. The panel is updated regularly.
 Pre-qualification criteria are properly defined/ notified.
Tweet @smylingassasin, Email: biswa.prakash@hotmail.com
General Evaluation
Criteria
 Short listed firms/consultants are fulfilling the eligibility
criteria. There is no deviation from notified criteria
during evaluation.
 Experience certificates submitted have been duly
verified.
 Tenders/bids are opened in the presence of
bidders/their authorised representative.
 Corrections/omissions/additions etc., in price bid are
properly numbered and attested and accounted page –
wise. Tender summary note/ Tender opening register is
scrupulously maintained.
 Conditions having financial implications are not altered
after opening of the price bids.
Tweet @smylingassasin, Email: biswa.prakash@hotmail.com
Tweet @smylingassasin, Email: biswa.prakash@hotmail.com

More Related Content

What's hot

Tendering
TenderingTendering
Tendering
kusha Ahmed
 
Construction Bidding Step-by-Step
Construction Bidding Step-by-StepConstruction Bidding Step-by-Step
Construction Bidding Step-by-Step
Doina Dobre, P.Eng, GSC
 
Bid propsl evaluation
Bid propsl evaluation Bid propsl evaluation
Bid propsl evaluation
Veluppillai Mohan
 
The Basics of Tendering & Bidding
The Basics of Tendering & BiddingThe Basics of Tendering & Bidding
The Basics of Tendering & Bidding
Moatasem Mabrouk
 
Mechanisms to implement wind energy projects “egyptian experience”
Mechanisms to implement wind energy projects “egyptian experience”Mechanisms to implement wind energy projects “egyptian experience”
Mechanisms to implement wind energy projects “egyptian experience”
RCREEE
 
3 tender stage
3 tender stage3 tender stage
3 tender stage
Aberra Beri
 
Tender processing
Tender processingTender processing
Tender processing
dnyandev_d
 
Tenders for construction
Tenders for constructionTenders for construction
Tenders for construction
gandrajuadityavarmagav
 
Tender writing – point of difference – important in wining tenders?
Tender writing – point of difference – important in wining tenders?Tender writing – point of difference – important in wining tenders?
Tender writing – point of difference – important in wining tenders?
Red Tape Busters
 
Bid Evaluation
Bid EvaluationBid Evaluation
Bid Evaluation
Sanoon Mohideen
 
Tender Management
Tender ManagementTender Management
Tender Management
Awais Tahir
 
4th Day Basic PPT
4th Day Basic PPT4th Day Basic PPT
4th Day Basic PPT
Veluppillai Mohan
 
Tender and tender document
Tender and tender documentTender and tender document
Tender and tender document
AkshataFarakate
 
Tendering Bidding & Award of Contract Final Draft
Tendering Bidding & Award of Contract Final DraftTendering Bidding & Award of Contract Final Draft
Tendering Bidding & Award of Contract Final Draft
Muneesh Methwani
 
Tender Writing – Understanding the Tendering Process
Tender Writing – Understanding the Tendering ProcessTender Writing – Understanding the Tendering Process
Tender Writing – Understanding the Tendering Process
Red Tape Busters
 
Contract & Tender Management
Contract & Tender ManagementContract & Tender Management
Contract & Tender Management
Anand Subramaniam
 
Tenders and procedure of tendering
Tenders and procedure of tenderingTenders and procedure of tendering
Tenders and procedure of tendering
vvsasane
 
procurement overview
procurement overviewprocurement overview
Tender & Tender Notice
Tender & Tender NoticeTender & Tender Notice
Tender & Tender Notice
Sakshi Kirar
 
The Basics of Contracting
The Basics of ContractingThe Basics of Contracting
The Basics of Contracting
Moatasem Mabrouk
 

What's hot (20)

Tendering
TenderingTendering
Tendering
 
Construction Bidding Step-by-Step
Construction Bidding Step-by-StepConstruction Bidding Step-by-Step
Construction Bidding Step-by-Step
 
Bid propsl evaluation
Bid propsl evaluation Bid propsl evaluation
Bid propsl evaluation
 
The Basics of Tendering & Bidding
The Basics of Tendering & BiddingThe Basics of Tendering & Bidding
The Basics of Tendering & Bidding
 
Mechanisms to implement wind energy projects “egyptian experience”
Mechanisms to implement wind energy projects “egyptian experience”Mechanisms to implement wind energy projects “egyptian experience”
Mechanisms to implement wind energy projects “egyptian experience”
 
3 tender stage
3 tender stage3 tender stage
3 tender stage
 
Tender processing
Tender processingTender processing
Tender processing
 
Tenders for construction
Tenders for constructionTenders for construction
Tenders for construction
 
Tender writing – point of difference – important in wining tenders?
Tender writing – point of difference – important in wining tenders?Tender writing – point of difference – important in wining tenders?
Tender writing – point of difference – important in wining tenders?
 
Bid Evaluation
Bid EvaluationBid Evaluation
Bid Evaluation
 
Tender Management
Tender ManagementTender Management
Tender Management
 
4th Day Basic PPT
4th Day Basic PPT4th Day Basic PPT
4th Day Basic PPT
 
Tender and tender document
Tender and tender documentTender and tender document
Tender and tender document
 
Tendering Bidding & Award of Contract Final Draft
Tendering Bidding & Award of Contract Final DraftTendering Bidding & Award of Contract Final Draft
Tendering Bidding & Award of Contract Final Draft
 
Tender Writing – Understanding the Tendering Process
Tender Writing – Understanding the Tendering ProcessTender Writing – Understanding the Tendering Process
Tender Writing – Understanding the Tendering Process
 
Contract & Tender Management
Contract & Tender ManagementContract & Tender Management
Contract & Tender Management
 
Tenders and procedure of tendering
Tenders and procedure of tenderingTenders and procedure of tendering
Tenders and procedure of tendering
 
procurement overview
procurement overviewprocurement overview
procurement overview
 
Tender & Tender Notice
Tender & Tender NoticeTender & Tender Notice
Tender & Tender Notice
 
The Basics of Contracting
The Basics of ContractingThe Basics of Contracting
The Basics of Contracting
 

Viewers also liked

Proposal Management Process
Proposal  Management  ProcessProposal  Management  Process
Proposal Management Process
Anand Subramaniam
 
Presales, solution design & bid management an overview
Presales, solution design & bid management   an overviewPresales, solution design & bid management   an overview
Presales, solution design & bid management an overview
Mukesh Yadav
 
Bid management ppt
Bid management pptBid management ppt
Bid management ppt
Position2BrandMonitor
 
Tender Process | A Complete Procurement Guide
Tender Process | A Complete Procurement GuideTender Process | A Complete Procurement Guide
Tender Process | A Complete Procurement Guide
Tender Process
 
A Survey on Cloud Computing Security Issues, Vendor Evaluation and Selection ...
A Survey on Cloud Computing Security Issues, Vendor Evaluation and Selection ...A Survey on Cloud Computing Security Issues, Vendor Evaluation and Selection ...
A Survey on Cloud Computing Security Issues, Vendor Evaluation and Selection ...
Eswar Publications
 
Apresentaçao BID Blumenau
Apresentaçao BID BlumenauApresentaçao BID Blumenau
Apresentaçao BID Blumenau
jcgernhard
 
Bid Management
Bid ManagementBid Management
Bid Management
TobivanKenobi123
 
Ten Slides in Ten Minutes - To Bid or not to Bid
Ten Slides in Ten Minutes - To Bid or not to BidTen Slides in Ten Minutes - To Bid or not to Bid
Ten Slides in Ten Minutes - To Bid or not to Bid
Bill Graham CP.APMP
 
Ten Slides in Ten Minutes - Bid Qualification across Workstreams
Ten Slides in Ten Minutes - Bid Qualification across WorkstreamsTen Slides in Ten Minutes - Bid Qualification across Workstreams
Ten Slides in Ten Minutes - Bid Qualification across Workstreams
Bill Graham CP.APMP
 
Useful Homework Cheat Sheets
Useful Homework Cheat SheetsUseful Homework Cheat Sheets
Useful Homework Cheat Sheets
My Cheat Sheet
 
Research retail software products
Research   retail software productsResearch   retail software products
Research retail software products
Suresh Koujalagi
 
SugarCRM CE Detailed presentation
SugarCRM CE Detailed presentation SugarCRM CE Detailed presentation
SugarCRM CE Detailed presentation
Suresh Koujalagi
 
Doorstep banking Brochure
Doorstep banking BrochureDoorstep banking Brochure
Doorstep banking Brochure
Suresh Koujalagi
 
Ensuring a Successful Bid Process
Ensuring a Successful Bid ProcessEnsuring a Successful Bid Process
Ensuring a Successful Bid Process
Taylor Management Company
 
Weaving the Sales and Bid Management fabric
Weaving the Sales and Bid Management fabricWeaving the Sales and Bid Management fabric
Weaving the Sales and Bid Management fabric
Bill Graham CP.APMP
 
Study on intraday liquidity
Study on intraday liquidityStudy on intraday liquidity
Study on intraday liquidity
Suresh Koujalagi
 
Bid to Win
Bid to WinBid to Win
Bid to Win
PMLGroup
 
Sales Qualification
Sales QualificationSales Qualification
Sales Qualification
Mike McCormac
 
SDLC - Software Development Life Cycle
SDLC - Software Development Life CycleSDLC - Software Development Life Cycle
SDLC - Software Development Life Cycle
Suresh Koujalagi
 

Viewers also liked (19)

Proposal Management Process
Proposal  Management  ProcessProposal  Management  Process
Proposal Management Process
 
Presales, solution design & bid management an overview
Presales, solution design & bid management   an overviewPresales, solution design & bid management   an overview
Presales, solution design & bid management an overview
 
Bid management ppt
Bid management pptBid management ppt
Bid management ppt
 
Tender Process | A Complete Procurement Guide
Tender Process | A Complete Procurement GuideTender Process | A Complete Procurement Guide
Tender Process | A Complete Procurement Guide
 
A Survey on Cloud Computing Security Issues, Vendor Evaluation and Selection ...
A Survey on Cloud Computing Security Issues, Vendor Evaluation and Selection ...A Survey on Cloud Computing Security Issues, Vendor Evaluation and Selection ...
A Survey on Cloud Computing Security Issues, Vendor Evaluation and Selection ...
 
Apresentaçao BID Blumenau
Apresentaçao BID BlumenauApresentaçao BID Blumenau
Apresentaçao BID Blumenau
 
Bid Management
Bid ManagementBid Management
Bid Management
 
Ten Slides in Ten Minutes - To Bid or not to Bid
Ten Slides in Ten Minutes - To Bid or not to BidTen Slides in Ten Minutes - To Bid or not to Bid
Ten Slides in Ten Minutes - To Bid or not to Bid
 
Ten Slides in Ten Minutes - Bid Qualification across Workstreams
Ten Slides in Ten Minutes - Bid Qualification across WorkstreamsTen Slides in Ten Minutes - Bid Qualification across Workstreams
Ten Slides in Ten Minutes - Bid Qualification across Workstreams
 
Useful Homework Cheat Sheets
Useful Homework Cheat SheetsUseful Homework Cheat Sheets
Useful Homework Cheat Sheets
 
Research retail software products
Research   retail software productsResearch   retail software products
Research retail software products
 
SugarCRM CE Detailed presentation
SugarCRM CE Detailed presentation SugarCRM CE Detailed presentation
SugarCRM CE Detailed presentation
 
Doorstep banking Brochure
Doorstep banking BrochureDoorstep banking Brochure
Doorstep banking Brochure
 
Ensuring a Successful Bid Process
Ensuring a Successful Bid ProcessEnsuring a Successful Bid Process
Ensuring a Successful Bid Process
 
Weaving the Sales and Bid Management fabric
Weaving the Sales and Bid Management fabricWeaving the Sales and Bid Management fabric
Weaving the Sales and Bid Management fabric
 
Study on intraday liquidity
Study on intraday liquidityStudy on intraday liquidity
Study on intraday liquidity
 
Bid to Win
Bid to WinBid to Win
Bid to Win
 
Sales Qualification
Sales QualificationSales Qualification
Sales Qualification
 
SDLC - Software Development Life Cycle
SDLC - Software Development Life CycleSDLC - Software Development Life Cycle
SDLC - Software Development Life Cycle
 

Similar to A primer on bid management b2 b_egovernance_biswa.prakash@hotmail.com

As a supplier, know tpt's governance
As a supplier, know tpt's  governanceAs a supplier, know tpt's  governance
As a supplier, know tpt's governance
Transnet Port Terminals
 
PURCHASE PROCEDURE IN AUTONOMOUS EDUCATIONAL ORGANISATIONS
PURCHASE PROCEDURE IN AUTONOMOUS EDUCATIONAL ORGANISATIONSPURCHASE PROCEDURE IN AUTONOMOUS EDUCATIONAL ORGANISATIONS
PURCHASE PROCEDURE IN AUTONOMOUS EDUCATIONAL ORGANISATIONS
Ganesh Bhorkade
 
Public Contracts Scotland
Public Contracts ScotlandPublic Contracts Scotland
Tenders
TendersTenders
Tenders
GANESH KUMAR
 
Meet the buyer - July 2010
Meet the buyer - July 2010Meet the buyer - July 2010
Meet the buyer - July 2010
Business Link South West - Events
 
Procurement of goods , GFR provisions
Procurement of goods , GFR provisionsProcurement of goods , GFR provisions
Procurement of goods , GFR provisions
Avinash Kumar Gupta
 
Understanding Pre Qualification Questionnaires
Understanding Pre Qualification QuestionnairesUnderstanding Pre Qualification Questionnaires
Understanding Pre Qualification Questionnaires
Lloyd Sewell
 
eThekwini Supply Chain Management by Bongi Blose
eThekwini Supply Chain Management by Bongi BloseeThekwini Supply Chain Management by Bongi Blose
eThekwini Supply Chain Management by Bongi Blose
Durban Chamber of Commerce and Industry
 
Government e Marketplace GeM Presentation
Government e Marketplace GeM PresentationGovernment e Marketplace GeM Presentation
Government e Marketplace GeM Presentation
gememarket11
 
Adding value to public procurement
Adding value to public procurementAdding value to public procurement
Adding value to public procurement
Association for Project Management
 
How to apply forane-tender for Sewage Treatment
How to apply forane-tender for Sewage TreatmentHow to apply forane-tender for Sewage Treatment
How to apply forane-tender for Sewage Treatment
Tender Detail
 
Pm0018 contracts management in projects
Pm0018  contracts management in projectsPm0018  contracts management in projects
Pm0018 contracts management in projects
smumbahelp
 
Project management tender
Project management tenderProject management tender
Project management tender
Channappa Mudagal
 
15.09.10 meet the buyer all presentations
15.09.10 meet the buyer   all presentations15.09.10 meet the buyer   all presentations
15.09.10 meet the buyer all presentations
Business Link South West - Events
 
Construction Futures Wales - Project Bank Accounts
Construction Futures Wales - Project Bank AccountsConstruction Futures Wales - Project Bank Accounts
Construction Futures Wales - Project Bank Accounts
Rae Davies
 
Construction Futures Wales Project Bank Accounts - November 2018
Construction Futures Wales Project Bank Accounts  - November 2018Construction Futures Wales Project Bank Accounts  - November 2018
Construction Futures Wales Project Bank Accounts - November 2018
Rae Davies
 
Tendering process cvc_guidelines
Tendering process cvc_guidelinesTendering process cvc_guidelines
Tendering process cvc_guidelines
Ritesh Kumar Baranwal
 
Sutton procurement presentation
Sutton procurement presentationSutton procurement presentation
Sutton procurement presentation
benbioregional
 
Understanding the Tender Process in Mexico
Understanding the Tender Process in MexicoUnderstanding the Tender Process in Mexico
Understanding the Tender Process in Mexico
Wanda Barquin
 
Accelerated construction - an overview
Accelerated construction - an overviewAccelerated construction - an overview
Accelerated construction - an overview
Homes and Communities Agency (HCA)
 

Similar to A primer on bid management b2 b_egovernance_biswa.prakash@hotmail.com (20)

As a supplier, know tpt's governance
As a supplier, know tpt's  governanceAs a supplier, know tpt's  governance
As a supplier, know tpt's governance
 
PURCHASE PROCEDURE IN AUTONOMOUS EDUCATIONAL ORGANISATIONS
PURCHASE PROCEDURE IN AUTONOMOUS EDUCATIONAL ORGANISATIONSPURCHASE PROCEDURE IN AUTONOMOUS EDUCATIONAL ORGANISATIONS
PURCHASE PROCEDURE IN AUTONOMOUS EDUCATIONAL ORGANISATIONS
 
Public Contracts Scotland
Public Contracts ScotlandPublic Contracts Scotland
Public Contracts Scotland
 
Tenders
TendersTenders
Tenders
 
Meet the buyer - July 2010
Meet the buyer - July 2010Meet the buyer - July 2010
Meet the buyer - July 2010
 
Procurement of goods , GFR provisions
Procurement of goods , GFR provisionsProcurement of goods , GFR provisions
Procurement of goods , GFR provisions
 
Understanding Pre Qualification Questionnaires
Understanding Pre Qualification QuestionnairesUnderstanding Pre Qualification Questionnaires
Understanding Pre Qualification Questionnaires
 
eThekwini Supply Chain Management by Bongi Blose
eThekwini Supply Chain Management by Bongi BloseeThekwini Supply Chain Management by Bongi Blose
eThekwini Supply Chain Management by Bongi Blose
 
Government e Marketplace GeM Presentation
Government e Marketplace GeM PresentationGovernment e Marketplace GeM Presentation
Government e Marketplace GeM Presentation
 
Adding value to public procurement
Adding value to public procurementAdding value to public procurement
Adding value to public procurement
 
How to apply forane-tender for Sewage Treatment
How to apply forane-tender for Sewage TreatmentHow to apply forane-tender for Sewage Treatment
How to apply forane-tender for Sewage Treatment
 
Pm0018 contracts management in projects
Pm0018  contracts management in projectsPm0018  contracts management in projects
Pm0018 contracts management in projects
 
Project management tender
Project management tenderProject management tender
Project management tender
 
15.09.10 meet the buyer all presentations
15.09.10 meet the buyer   all presentations15.09.10 meet the buyer   all presentations
15.09.10 meet the buyer all presentations
 
Construction Futures Wales - Project Bank Accounts
Construction Futures Wales - Project Bank AccountsConstruction Futures Wales - Project Bank Accounts
Construction Futures Wales - Project Bank Accounts
 
Construction Futures Wales Project Bank Accounts - November 2018
Construction Futures Wales Project Bank Accounts  - November 2018Construction Futures Wales Project Bank Accounts  - November 2018
Construction Futures Wales Project Bank Accounts - November 2018
 
Tendering process cvc_guidelines
Tendering process cvc_guidelinesTendering process cvc_guidelines
Tendering process cvc_guidelines
 
Sutton procurement presentation
Sutton procurement presentationSutton procurement presentation
Sutton procurement presentation
 
Understanding the Tender Process in Mexico
Understanding the Tender Process in MexicoUnderstanding the Tender Process in Mexico
Understanding the Tender Process in Mexico
 
Accelerated construction - an overview
Accelerated construction - an overviewAccelerated construction - an overview
Accelerated construction - an overview
 

Recently uploaded

Organizational Change Leadership Agile Tour Geneve 2024
Organizational Change Leadership Agile Tour Geneve 2024Organizational Change Leadership Agile Tour Geneve 2024
Organizational Change Leadership Agile Tour Geneve 2024
Kirill Klimov
 
Digital Transformation Frameworks: Driving Digital Excellence
Digital Transformation Frameworks: Driving Digital ExcellenceDigital Transformation Frameworks: Driving Digital Excellence
Digital Transformation Frameworks: Driving Digital Excellence
Operational Excellence Consulting
 
Zodiac Signs and Food Preferences_ What Your Sign Says About Your Taste
Zodiac Signs and Food Preferences_ What Your Sign Says About Your TasteZodiac Signs and Food Preferences_ What Your Sign Says About Your Taste
Zodiac Signs and Food Preferences_ What Your Sign Says About Your Taste
my Pandit
 
2024-6-01-IMPACTSilver-Corp-Presentation.pdf
2024-6-01-IMPACTSilver-Corp-Presentation.pdf2024-6-01-IMPACTSilver-Corp-Presentation.pdf
2024-6-01-IMPACTSilver-Corp-Presentation.pdf
hartfordclub1
 
Innovation Management Frameworks: Your Guide to Creativity & Innovation
Innovation Management Frameworks: Your Guide to Creativity & InnovationInnovation Management Frameworks: Your Guide to Creativity & Innovation
Innovation Management Frameworks: Your Guide to Creativity & Innovation
Operational Excellence Consulting
 
Call8328958814 satta matka Kalyan result satta guessing
Call8328958814 satta matka Kalyan result satta guessingCall8328958814 satta matka Kalyan result satta guessing
Call8328958814 satta matka Kalyan result satta guessing
➑➌➋➑➒➎➑➑➊➍
 
Creative Web Design Company in Singapore
Creative Web Design Company in SingaporeCreative Web Design Company in Singapore
Creative Web Design Company in Singapore
techboxsqauremedia
 
How MJ Global Leads the Packaging Industry.pdf
How MJ Global Leads the Packaging Industry.pdfHow MJ Global Leads the Packaging Industry.pdf
How MJ Global Leads the Packaging Industry.pdf
MJ Global
 
Maksym Vyshnivetskyi: PMO KPIs (UA) (#12)
Maksym Vyshnivetskyi: PMO KPIs (UA) (#12)Maksym Vyshnivetskyi: PMO KPIs (UA) (#12)
Maksym Vyshnivetskyi: PMO KPIs (UA) (#12)
Lviv Startup Club
 
How are Lilac French Bulldogs Beauty Charming the World and Capturing Hearts....
How are Lilac French Bulldogs Beauty Charming the World and Capturing Hearts....How are Lilac French Bulldogs Beauty Charming the World and Capturing Hearts....
How are Lilac French Bulldogs Beauty Charming the World and Capturing Hearts....
Lacey Max
 
The latest Heat Pump Manual from Newentide
The latest Heat Pump Manual from NewentideThe latest Heat Pump Manual from Newentide
The latest Heat Pump Manual from Newentide
JoeYangGreatMachiner
 
Understanding User Needs and Satisfying Them
Understanding User Needs and Satisfying ThemUnderstanding User Needs and Satisfying Them
Understanding User Needs and Satisfying Them
Aggregage
 
The APCO Geopolitical Radar - Q3 2024 The Global Operating Environment for Bu...
The APCO Geopolitical Radar - Q3 2024 The Global Operating Environment for Bu...The APCO Geopolitical Radar - Q3 2024 The Global Operating Environment for Bu...
The APCO Geopolitical Radar - Q3 2024 The Global Operating Environment for Bu...
APCO
 
Dpboss Matka Guessing Satta Matta Matka Kalyan Chart Satta Matka
Dpboss Matka Guessing Satta Matta Matka Kalyan Chart Satta MatkaDpboss Matka Guessing Satta Matta Matka Kalyan Chart Satta Matka
Dpboss Matka Guessing Satta Matta Matka Kalyan Chart Satta Matka
➒➌➎➏➑➐➋➑➐➐Dpboss Matka Guessing Satta Matka Kalyan Chart Indian Matka
 
Anny Serafina Love - Letter of Recommendation by Kellen Harkins, MS.
Anny Serafina Love - Letter of Recommendation by Kellen Harkins, MS.Anny Serafina Love - Letter of Recommendation by Kellen Harkins, MS.
Anny Serafina Love - Letter of Recommendation by Kellen Harkins, MS.
AnnySerafinaLove
 
The 10 Most Influential Leaders Guiding Corporate Evolution, 2024.pdf
The 10 Most Influential Leaders Guiding Corporate Evolution, 2024.pdfThe 10 Most Influential Leaders Guiding Corporate Evolution, 2024.pdf
The 10 Most Influential Leaders Guiding Corporate Evolution, 2024.pdf
thesiliconleaders
 
How to Implement a Strategy: Transform Your Strategy with BSC Designer's Comp...
How to Implement a Strategy: Transform Your Strategy with BSC Designer's Comp...How to Implement a Strategy: Transform Your Strategy with BSC Designer's Comp...
How to Implement a Strategy: Transform Your Strategy with BSC Designer's Comp...
Aleksey Savkin
 
TIMES BPO: Business Plan For Startup Industry
TIMES BPO: Business Plan For Startup IndustryTIMES BPO: Business Plan For Startup Industry
TIMES BPO: Business Plan For Startup Industry
timesbpobusiness
 
GKohler - Retail Scavenger Hunt Presentation
GKohler - Retail Scavenger Hunt PresentationGKohler - Retail Scavenger Hunt Presentation
GKohler - Retail Scavenger Hunt Presentation
GraceKohler1
 
Event Report - SAP Sapphire 2024 Orlando - lots of innovation and old challenges
Event Report - SAP Sapphire 2024 Orlando - lots of innovation and old challengesEvent Report - SAP Sapphire 2024 Orlando - lots of innovation and old challenges
Event Report - SAP Sapphire 2024 Orlando - lots of innovation and old challenges
Holger Mueller
 

Recently uploaded (20)

Organizational Change Leadership Agile Tour Geneve 2024
Organizational Change Leadership Agile Tour Geneve 2024Organizational Change Leadership Agile Tour Geneve 2024
Organizational Change Leadership Agile Tour Geneve 2024
 
Digital Transformation Frameworks: Driving Digital Excellence
Digital Transformation Frameworks: Driving Digital ExcellenceDigital Transformation Frameworks: Driving Digital Excellence
Digital Transformation Frameworks: Driving Digital Excellence
 
Zodiac Signs and Food Preferences_ What Your Sign Says About Your Taste
Zodiac Signs and Food Preferences_ What Your Sign Says About Your TasteZodiac Signs and Food Preferences_ What Your Sign Says About Your Taste
Zodiac Signs and Food Preferences_ What Your Sign Says About Your Taste
 
2024-6-01-IMPACTSilver-Corp-Presentation.pdf
2024-6-01-IMPACTSilver-Corp-Presentation.pdf2024-6-01-IMPACTSilver-Corp-Presentation.pdf
2024-6-01-IMPACTSilver-Corp-Presentation.pdf
 
Innovation Management Frameworks: Your Guide to Creativity & Innovation
Innovation Management Frameworks: Your Guide to Creativity & InnovationInnovation Management Frameworks: Your Guide to Creativity & Innovation
Innovation Management Frameworks: Your Guide to Creativity & Innovation
 
Call8328958814 satta matka Kalyan result satta guessing
Call8328958814 satta matka Kalyan result satta guessingCall8328958814 satta matka Kalyan result satta guessing
Call8328958814 satta matka Kalyan result satta guessing
 
Creative Web Design Company in Singapore
Creative Web Design Company in SingaporeCreative Web Design Company in Singapore
Creative Web Design Company in Singapore
 
How MJ Global Leads the Packaging Industry.pdf
How MJ Global Leads the Packaging Industry.pdfHow MJ Global Leads the Packaging Industry.pdf
How MJ Global Leads the Packaging Industry.pdf
 
Maksym Vyshnivetskyi: PMO KPIs (UA) (#12)
Maksym Vyshnivetskyi: PMO KPIs (UA) (#12)Maksym Vyshnivetskyi: PMO KPIs (UA) (#12)
Maksym Vyshnivetskyi: PMO KPIs (UA) (#12)
 
How are Lilac French Bulldogs Beauty Charming the World and Capturing Hearts....
How are Lilac French Bulldogs Beauty Charming the World and Capturing Hearts....How are Lilac French Bulldogs Beauty Charming the World and Capturing Hearts....
How are Lilac French Bulldogs Beauty Charming the World and Capturing Hearts....
 
The latest Heat Pump Manual from Newentide
The latest Heat Pump Manual from NewentideThe latest Heat Pump Manual from Newentide
The latest Heat Pump Manual from Newentide
 
Understanding User Needs and Satisfying Them
Understanding User Needs and Satisfying ThemUnderstanding User Needs and Satisfying Them
Understanding User Needs and Satisfying Them
 
The APCO Geopolitical Radar - Q3 2024 The Global Operating Environment for Bu...
The APCO Geopolitical Radar - Q3 2024 The Global Operating Environment for Bu...The APCO Geopolitical Radar - Q3 2024 The Global Operating Environment for Bu...
The APCO Geopolitical Radar - Q3 2024 The Global Operating Environment for Bu...
 
Dpboss Matka Guessing Satta Matta Matka Kalyan Chart Satta Matka
Dpboss Matka Guessing Satta Matta Matka Kalyan Chart Satta MatkaDpboss Matka Guessing Satta Matta Matka Kalyan Chart Satta Matka
Dpboss Matka Guessing Satta Matta Matka Kalyan Chart Satta Matka
 
Anny Serafina Love - Letter of Recommendation by Kellen Harkins, MS.
Anny Serafina Love - Letter of Recommendation by Kellen Harkins, MS.Anny Serafina Love - Letter of Recommendation by Kellen Harkins, MS.
Anny Serafina Love - Letter of Recommendation by Kellen Harkins, MS.
 
The 10 Most Influential Leaders Guiding Corporate Evolution, 2024.pdf
The 10 Most Influential Leaders Guiding Corporate Evolution, 2024.pdfThe 10 Most Influential Leaders Guiding Corporate Evolution, 2024.pdf
The 10 Most Influential Leaders Guiding Corporate Evolution, 2024.pdf
 
How to Implement a Strategy: Transform Your Strategy with BSC Designer's Comp...
How to Implement a Strategy: Transform Your Strategy with BSC Designer's Comp...How to Implement a Strategy: Transform Your Strategy with BSC Designer's Comp...
How to Implement a Strategy: Transform Your Strategy with BSC Designer's Comp...
 
TIMES BPO: Business Plan For Startup Industry
TIMES BPO: Business Plan For Startup IndustryTIMES BPO: Business Plan For Startup Industry
TIMES BPO: Business Plan For Startup Industry
 
GKohler - Retail Scavenger Hunt Presentation
GKohler - Retail Scavenger Hunt PresentationGKohler - Retail Scavenger Hunt Presentation
GKohler - Retail Scavenger Hunt Presentation
 
Event Report - SAP Sapphire 2024 Orlando - lots of innovation and old challenges
Event Report - SAP Sapphire 2024 Orlando - lots of innovation and old challengesEvent Report - SAP Sapphire 2024 Orlando - lots of innovation and old challenges
Event Report - SAP Sapphire 2024 Orlando - lots of innovation and old challenges
 

A primer on bid management b2 b_egovernance_biswa.prakash@hotmail.com

  • 1. BID PROCESS MANAGEMENT SYSTEM Tweet @smylingassasin, Email: biswa.prakash@hotmail.com
  • 2. Agenda 1. Fundamental of Bidding 2. Bidding Process 3. Evaluation criteria 4. Bid Evaluation Methodology 5. e-Auction process 6. Reverse auction 7. Swiss challenge method 9. Other general terms & conditions 10. Govt. Procurement process 11. PSU Procurement process 12. Procurement process of funding agency 13. Vendor Registration process Tweet @smylingassasin, Email: biswa.prakash@hotmail.com
  • 3. Fundamental of Bidding  A Bid Management System, either manual or electronic, is required to ensure an effective and efficient process for: a) the buyer wishing to source products or services and b) the seller wishing to bid to supply products or services. Tweet @smylingassasin, Email: biswa.prakash@hotmail.com
  • 4. Govt. Procurement Process  Covers the procurement of GOODS,WORKS AND SERVICES by all Government Ministries, Departments, Agencies, Statutory Corporations and Public sector undertakings in the Center and the States, Municipal Corporations and other Local bodies and even by private sector undertakings providing public service on monopoly basis. Tweet @smylingassasin, Email: biswa.prakash@hotmail.com
  • 5. Objective of Govt. Procurement Process  TO PROCURE WORK, MATERIAL, SERVICES OF THE SPECIFIED QUALITY WITHIN THE SPECIFIED TIME AT THE MOST COMPETITIVE PRICES IN A FAIR, JUST & TRANSPARENT MANNER---- Tweet @smylingassasin, Email: biswa.prakash@hotmail.com
  • 6. Stages in Govt. Procurement Process 1. PRE-TENDER STAGE 2. TENDER STAGE 3. EXECUTION STAGE Tweet @smylingassasin, Email: biswa.prakash@hotmail.com
  • 7. Stages in Govt. Procurement Process 1. PRE-TENDER STAGE i. Project Formulation ii. Appointment of Consultants iii. Preparation of Detailed Project Report (Estimate, Design, etc.) Tweet @smylingassasin, Email: biswa.prakash@hotmail.com
  • 8. Stages in Govt. Procurement Process 2. TENDER STAGE i. Preparation of Tender Documents ii. Inviting & Opening of Tenders iii. Prequalification iv. Tender Evaluation &Award of Work Tweet @smylingassasin, Email: biswa.prakash@hotmail.com
  • 9. Stages in Govt. Procurement Process 3.EXECUTION STAGE i. Agreement/Purchase Order ii. Contract Performance (A) Advance Payments (B) Implementation Of Contract Provisions (C ) Time And Cost Overrun (D) Payments (E) Quality Of Work/Inspection Tweet @smylingassasin, Email: biswa.prakash@hotmail.com
  • 10. Vendor Selection Process  Selection and registration of firms/suppliers and their evaluation must be clear and transparent.  PQ evaluation criteria must be incorporated in the bid documents in clear and unambiguous terms  Prepare the PQ criteria specific to the requirement of the work.  Evaluate the bids exactly as per the notified criteria. Tweet @smylingassasin, Email: biswa.prakash@hotmail.com
  • 11. Vendor Selection Process  Prequalification necessary to bring competent contractors into competition with technical & financial capability required for the particular procurement. To be done on the basis of :  Experience and past performance on similar contracts  Capabilities with respect to personnel, equipment and manufacturing facilities  Financial standing through latest Annual report (balance sheet and P & L account) of last three years. Tweet @smylingassasin, Email: biswa.prakash@hotmail.com
  • 12. Bidding Process • Single bid or two bid (for IT and communications systems, turn key projects) • Two bid system: techno-commercial and price bids are called separately. • The techno-commercial bid contains all terms and conditions including commercial terms except price. Tweet @smylingassasin, Email: biswa.prakash@hotmail.com
  • 13. Bidding Process • Technical bids will be evaluated by Tender Evaluation Committee • Price bids of only technically acceptable offers are to be opened to ensure an objective evaluation of tenders. • In case of two-stage two bid system, price/commercial bids are called from only technically acceptable vendors after technical evaluation. Tweet @smylingassasin, Email: biswa.prakash@hotmail.com
  • 14. Bid Evaluation Methodology There are two process used for awarding various e-governance contracts (both Consulting and Software Implementation).  QCBS (Quality cum Cost Basis) method gives weightage to both quality and cost. The weights are usually more for technical (or quality) and less for commercial (or cost) aspects of the bid (usually 60:40 or 70:30 or sometimes even 80:20).  L1 gives the weightage to Commercial aspect of the bid only where Bidder who quotes lowest wins the bid. Tweet @smylingassasin, Email: biswa.prakash@hotmail.com
  • 15. Earnest Money Deposit  To safeguard the interest of Dept. (withdrawal / alter the bid by bidder)  Exemption – Regd. With Central Purchase Organization / National Small Industries Corporation  EMD - 2 % to 5% of estimated value  Can be DD/Banker Cheque /BG  Unsuccessful bidders EMD should be returned /refunded at the earliest. Tweet @smylingassasin, Email: biswa.prakash@hotmail.com
  • 16. Performance Security  From the successful bidders  Amount – 5% to 10%  DD  Should be valid for 60 days beyond the date of completion of all the contractual obligations of the supplier including warranty  Bid Security should be refunded on receipt of Performance Security Tweet @smylingassasin, Email: biswa.prakash@hotmail.com
  • 17. e-Auction  e-Auction is introduced to negotiate terms of contract between suppliers and buyers mainly in the industrial sector.  The electronic auction (e-Auction) is an e- business between auctioneers and bidders, which takes place on an electronic marketplace.  It is an electronic commerce which occurs business to business (B2B), business to consumer (B2C), or consumer-to-consumer (C2C) Tweet @smylingassasin, Email: biswa.prakash@hotmail.com
  • 18. Reverse Auction  The two major types of the electronic auction are forward auction in which several buyers bid for one seller's goods and reverse auction in which several sellers bid for one buyer's order.  Reverse auctions are the other major form of auctions. In a reverse auction, a single buyer makes potential sellers aware of their intent to buy a specified good or service  During the course of the actual reverse auction event, the sellers bid against one another to secure the buyer’s business, driving the price to be paid for the item downward. Thus, the winning bidder is the seller who offers the lowest price. Tweet @smylingassasin, Email: biswa.prakash@hotmail.com
  • 19. Reverse Auction  Reverse auctions are most typically used for procurement by private companies, public sector agencies, and non-profit organizations. Tweet @smylingassasin, Email: biswa.prakash@hotmail.com
  • 20. Swiss Challenge Method  Swiss Challenge System is a new bidding process to help private sector initiative in core sector projects. It's an offer made by the original proponent to the government ensuring his process to be best (in terms of effectiveness including both the factors cost and time) by his initiative as a result of his own innovative approach or on the demand of the government to perform certain task.  The Swiss challenge system, like the bonus system, further allows third parties to make better offers (challenges) for a project during a designated period with simple objective to discourage frivolous project, or to avoid exaggerated project development costs. Then accordingly, the original proponent gets the right to counter-match any superior offers given by the third party. Tweet @smylingassasin, Email: biswa.prakash@hotmail.com
  • 21. Working of Swiss Challenge Method  The system basically works on two different patterns, its up to the Government to decide as to which one they want to adopt. The two main ways are as follows:  The Government can either purchase the intellectual property rights for a project concept from the proponent or then award the project through a competitive bidding process in which no bidder has a predefined advantage.  The Government can offer the original proponent an advantage in a competitive bidding process. In this case the government should create rewards that satisfy the original proponent while still allowing a truly competitive process. Tweet @smylingassasin, Email: biswa.prakash@hotmail.com
  • 22. General Evaluation Criteria  Satisfaction of Conditions specific to the contract  Sample Testing  Capacity Evaluation.  Turnover  Statutory documentation  Arrival at Outcome Price of the bid  Determination of L-1, L-2, L-3……  Determining Reasonableness of the L-1 Rates  Recommendation for Negotiation (if require) Tweet @smylingassasin, Email: biswa.prakash@hotmail.com
  • 23. General Evaluation Criteria  Financial and Technical sanction of competent authority is available.  Adequate and wide publicity is given. Advertisement is posted on website and tender documents are available for downloading.  Convenient tender receiving/opening time and address of the tender receiving officials/tender box are properly notified.  In the case of limited tender, panel is prepared in a transparent manner clearly publishing the eligibility criteria. The panel is updated regularly.  Pre-qualification criteria are properly defined/ notified. Tweet @smylingassasin, Email: biswa.prakash@hotmail.com
  • 24. General Evaluation Criteria  Short listed firms/consultants are fulfilling the eligibility criteria. There is no deviation from notified criteria during evaluation.  Experience certificates submitted have been duly verified.  Tenders/bids are opened in the presence of bidders/their authorised representative.  Corrections/omissions/additions etc., in price bid are properly numbered and attested and accounted page – wise. Tender summary note/ Tender opening register is scrupulously maintained.  Conditions having financial implications are not altered after opening of the price bids. Tweet @smylingassasin, Email: biswa.prakash@hotmail.com
  • 25. Tweet @smylingassasin, Email: biswa.prakash@hotmail.com