The document provides an engineer's estimate for the construction of a technical building for a national refinery in Karachi. It includes itemized estimates for excavation, concrete work, masonry, plastering, flooring, painting and other finishing works for the ground floor and first floor. The total estimated cost for civil works is Rs. 11,267,975 with a detailed breakdown provided for individual items on both floors.
APC has become one of the leading businesses of its type by providing professional service & advice. We are now one of the most successful suppliers of masonry products in Australia. APC personnel have a diverse knowledge of the products we sell. Our customers demand this!!
It is our focus to have every person in APC concentrate on exceeding customer needs & expectations. We achieve this by sourcing & appointing good quality products, new ideas, new styles, & new finishes; all at the value for money prices! When APC displays all of these products & ideas within the best displays around Australia, you have a chance to get an incredible shopping advantage. APC displays are landscaped, in situ, well maintained, well designed, & truly amazing!!
APC has become one of the leading businesses of its type by providing professional service & advice. We are now one of the most successful suppliers of masonry products in Australia. APC personnel have a diverse knowledge of the products we sell. Our customers demand this!!
It is our focus to have every person in APC concentrate on exceeding customer needs & expectations. We achieve this by sourcing & appointing good quality products, new ideas, new styles, & new finishes; all at the value for money prices! When APC displays all of these products & ideas within the best displays around Australia, you have a chance to get an incredible shopping advantage. APC displays are landscaped, in situ, well maintained, well designed, & truly amazing!!
Checklist for budgeting: Make sure all important items on the list are accounted for in your preliminary budget
◾Checklist for estimating: Make sure all items get into your detailed estimate
◾Tool for tracking estimated vs. actual costs (called “job costing”)
◾Tool for tracking payments and amount due to vendors and subcontractors
Fire Alarm System Purchasing Guide - Purchasing.comPurchasing.com
Fire alarm systems are one of the most valuable components to any business, protecting life, inventory, and property. By necessity, no two systems are the same. Each is custom tailored and installed with specific business processes in mind.
Find the right system for your business by reading this purchasing guide.
Source: http://www.purchasing.com/security/fire-alarm-systems/purchasing-guide/
How To Estimate Garage Building Costs ?Behm Design
The most reliable method for rough cost estimating of concrete foundation and slab work is to contact a local concrete contractor – one who specializes in this work.
Using composite crews to estimate a construction project is the best and most accurate way to develop a cost estimate. On one condition: we know what we are doing. Browse through this slideshow and see what are the most important points to consider when using composite crews for cost estimating.
Discover a fast way to learn construction cost estimating and start a career which is in high demand. Construction cost estimators usually benefit from secure jobs and constant demand.
Presentation on practical approach of costing in construction industry has been prepared with the objective of spreading and sharing knowledge of flow of costing and key areas among industry, professionals and other related people.
it may be very useful to understand the basic concepts and approach of costing of this fastest growing industry.
Checklist for budgeting: Make sure all important items on the list are accounted for in your preliminary budget
◾Checklist for estimating: Make sure all items get into your detailed estimate
◾Tool for tracking estimated vs. actual costs (called “job costing”)
◾Tool for tracking payments and amount due to vendors and subcontractors
Fire Alarm System Purchasing Guide - Purchasing.comPurchasing.com
Fire alarm systems are one of the most valuable components to any business, protecting life, inventory, and property. By necessity, no two systems are the same. Each is custom tailored and installed with specific business processes in mind.
Find the right system for your business by reading this purchasing guide.
Source: http://www.purchasing.com/security/fire-alarm-systems/purchasing-guide/
How To Estimate Garage Building Costs ?Behm Design
The most reliable method for rough cost estimating of concrete foundation and slab work is to contact a local concrete contractor – one who specializes in this work.
Using composite crews to estimate a construction project is the best and most accurate way to develop a cost estimate. On one condition: we know what we are doing. Browse through this slideshow and see what are the most important points to consider when using composite crews for cost estimating.
Discover a fast way to learn construction cost estimating and start a career which is in high demand. Construction cost estimators usually benefit from secure jobs and constant demand.
Presentation on practical approach of costing in construction industry has been prepared with the objective of spreading and sharing knowledge of flow of costing and key areas among industry, professionals and other related people.
it may be very useful to understand the basic concepts and approach of costing of this fastest growing industry.
1. ENGINEER'S ESTIMATE
CONSTRUCTION OF TECHNICAL BUILDING
FOR NATIONAL REFINERY - KARACHI
GROUND FLOOR
Sr. Description Quantity Unit
No.
1 Excavation in Foundation (as per D.I - 1)
a) 0 to 5 feet depth. 20,500.00 Cft.
b) Below 5 to 10 feet depth. 20,500.00 Cft.
c) Below 10 to 15 feet depth 6,250.00 Cft.
2 Filling earth under floor (as per D.I - 2)
a) From outside sources 25,000.00 Cft.
3 Providing and laying Termite Treatment (as per D.I - 3) 7,500.00 Sft.
4 Providing and laying soling stone under floors
(as per D.I - 4) 3,650.00 Cft.
5 Providing and laying DPC 1:2:4 (as per D.I - 5) 580.00 Sft.
6 Providing & laying C.C. 1:4:8 (Class-E) concrete
(as per D.I - 6)
a. In foundation 2,200.00 Cft.
7 Providing & laying C.C. 1:3:6 (Class-D) concrete
(as per D.I - 7)
a. Under Floor 2,400.00 Cft.
b. In Step 24.00 Cft.
8 Providing & laying C.C. 1:1½:3 (Class-B) concrete
using SR Cement (as per D.I - 8)
a. Column and Wall Footing 5,750.00 Cft.
b. Column upto Plinth 975.00 Cft.
c. Walls upto Plinth 1,150.00 Cft.
d. Plinth Beams 2,300.00 Cft.
9 Providing and laying Class "B" 1:1½:3 Concrete
using O.P. Cement (as per D.I - 9)
a) Column Superstructure 700.00 Cft.
b) Wall Superstructure 1,050.00 Cft.
c) Beams / Lintels 1,550.00 Cft.
d) Slab 6" thick 3,800.00 Cft.
3. Sr. Description Quantity Unit
No.
10 Providing & laying Steel Reinforcement
(as per D.I - 10)
a. Mild Steel Bars 3.00 Tonne
b. TOR Steel Bars 40.00 Tonne
11 Providing & laying Solid Block Masonry walls in
superstructure (as per D.I - 11)
a. 6" thick walls 4,500.00 Cft.
b. 4" thick walls 20.00 Cft.
12 Providing and laying ½" thick plain cement plaster
in 1:4 cement mortar (as per D.I - 12)
a. Ceiling 1,500.00 Sft.
b. Internal walls 13,500.00 Sft.
13 Providing and laying 3/4" thick plain cement plaster
on external walls (as per D.I - 13) 9,000.00 Sft.
14 Providing and laying C.C. 1:2:4 floor (as per D.I - 14) 630.00 Sft.
15 Providing and laying China Verona Marble Tiles
floor (as per D.I - 15) 6,600.00 Sft.
16 Providing and laying China Verona Marble Tiles
skirting (as per D.I - 16) 760.00 Sft.
17 Providing and laying China Verona Marble Tiles
on steps (as per D.I - 17)
a) Treads 400.00 Sft.
b) Risers 250.00 Sft.
18 Providing and laying non-skid Ceramic Tile Floor
in Bath (as per D.I. - 18) 350.00 Sft.
19 Providing and laying Glazed Tiles in Dado
(as per D.I - 19) 1,000.00 Sft.
20 Providing and applying oil bound distemper on ceiling
(as per D.I - 20) 1,500.00 Sft.
21 Providing and applying Plastic Emulsion Paint on
internal walls (as per D.I - 21) 13,500.00 Sft.
4. Sr. Description Quantity Unit
No.
22 Providing and fixing commercial ply flush door
shutter with frame (as per D.I - 22) 600.00 Sft.
23 Providing and fixing aluminum fully glazed door
(as per D.I - 23)
a) With side panels 110.00 Sft.
b) Without side panels 175.00 Sft.
24 Providing and fixing aluminum fully double glazed
sliding or fixed windows / ventilators (as per D.I.-24) 3,050.00 Sft.
25 Providing and fixing Acoustic Tiles false ceiling
(as per D.I. - 26) 7,000.00 Sft.
26 P/F Staircase Railing (as per D.I. - 27) 350.00 Sft.
27 Making flower beds (as per D.I. - 28) 2.00 Each
28 Providing and fixing Wooden Partitions
(as per D.I. - 29) 400.00 Sft.
29 Providing and fixing Weather Shield Paint on
external surface (as per D.I. - 30) 9,000.00 Sft.
30 Providing and fixing M.S. Grills
(as per D.I. - 31) 3,000.00 Sft.
31 Kitchen Cabinet (low level) (as per D.I. 32) 60.00 Sft.
32 Kitchen Cabinet (high level) (as per D.I. 33) 40.00 Sft.
33 Providing and fixing marble portition in urinals
(as per D.I. 35)
a) 2½" x 1½' size 1.00 No.
a) 2½" x 1' size 1.00 No.
Total ======>
9. ENGINEER'S ESTIMATE
CONSTRUCTION OF TECHNICAL BUILDING
FOR NATIONAL REFINERY - KARACHI
FIRST FLOOR
Sr. Description Quantity Unit
No.
1 Providing & laying RCC Class-B (1:1½:3) concrete
(as per D.I - 8)
a. Beams / Lintels 1,300.00 Cft.
b. Column in super structure 850.00 Cft.
c. Roof Slab 3,950.00 Cft.
d. Wall 1,100.00 Cft.
e. Staircase 400.00 Cft.
f. Projection / Pardi 860.00 Cft.
2 Providing & laying Steel Reinforcement
(as per D.I - 10)
a. M.S. Bars 2.00 Tonne
b. TOR Steel Bars 24.00 Tonne
3 Providing & laying Solid Block Masonry wall in
superstructure (as per D.I - 11)
a. 6" thick walls 4,300.00 Cft.
b. 4" thick walls 20.00 Cft.
4 Providing and laying ½" thick plain cement plaster
in 1:4 cement mortar (as per D.I - 12)
a. Ceiling 1,500.00 Sft.
b. Internal walls 16,000.00 Sft.
5 Providing and laying 3/4" thick plain cement plaster
on external walls (as per D.I - 13) 14,500.00 Sft.
6 Providing and laying China Verona Marble Tiles
floor (as per D.I - 15) 6,800.00 Sft.
7 Providing and laying China Verona Marble Tiles
skirting (as per D.I - 16) 875.00 Sft.
8 Providing and laying non-skid Ceramic Tile Floor
in Bath (as per D.I. - 18) 350.00 Sft.
10. Sr. Description Quantity Unit
No.
9 Providing and laying Glazed Tiles in Dado
(as per D.I - 19) 1,200.00 Sft.
10 Providing and applying oil bound distemper on
ceiling (as per D.I - 20) 1,500.00 Sft.
11 Providing and applying Plastic Emulsion Paint on
internal walls (as per D.I - 21) 16,000.00 Sft.
12 Providing and fixing commercial ply flush door
shutter with frame (as per D.I - 22) 650.00 Sft.
13 Providing and fixing aluminum fully glazed sliding
or fixed windows / ventilators (as per D.I. - 24) 3,100.00 Sft.
14 Providing and laying 2½" thick (average) C.C.
1:6 screed over roof (as per D.I. - 25) 6,500.00 Sft.
15 Providing and fixing Acoustic Tiles false ceiling
(as per D.I. - 26) 6,000.00 Sft.
16 P/F Staircase Railing (as per D.I. - 27) 350.00 Sft.
17 P/F Wooden Partitions (as per D.I. 29) 400.00 Sft.
18 P/A Weather Shield Paint on external surface 14,500.00 Sft.
(as per D.I. 30)
19 Providing and laying China Verona Marble Tiles
on steps (as per D.I - 17)
a) Treads 450.00 Sft.
b) Risers 200.00 Sft.
20 Providing and fixing M.S. Grills
(as per D.I. - 31) 3,100.00 Sft.
21 Kitchen Cabinet (low level) (as per D.I. 32) 60.00 Sft.
22 Kitchen Cabinet (high level) (as per D.I. 33) 40.00 Sft.
33 Providing and fixing marble partition in urinals
(as per D.I. 35)
a) 2½" x 1½' size 1.00 No.
a) 2½" x 1' size 1.00 No.
11. Sr. Description Quantity Unit
No.
34 Supply and fixing sand in sunk slab
(as per D.I. 34) 400.00 Cft.
Total ======>
15. ENGINEER'S ESTIMATE
CONSTRUCTION OF TECHNICAL BUILDING
FOR NATIONAL REFINERY - KARACHI
SUMMARY OF COST
FOR
CIVIL WORKS
1 Ground Floor Rs.
2 First Floor Rs.
Total Bid Rs.
Rebate (if any) Rs.
Net Bid Amount Rs.
Rupees in Word
One Crore Twelve Lacs Sixty Seven Thousands Nine
Hundred and Seventy Five Only
16. ENGINEER'S ESTIMATE
STRUCTION OF TECHNICAL BUILDING
OR NATIONAL REFINERY - KARACHI
SUMMARY OF COST
FOR
CIVIL WORKS
6,455,060
4,812,915
11,267,975
11,267,975
One Crore Twelve Lacs Sixty Seven Thousands Nine
Hundred and Seventy Five Only