Name of Owner:-
Slno Description Nos Length Breadth Depth Total Qty Say
m2
/m3
/kg
1 Earth work excavation for foundation in all
soils except hard rock and depositing earth
on banks within a lead of not more than.
complete.
Column foundation 1 x 15 1.50 1.50 1.50 50.63
Grade beam
Long walls 1 x 3 16.48 0.30 0.35 5.19
Cross walls 1 x 5 6.10 0.30 0.35 3.20
59.02 59.00
2 Supplying & filling with river sand in
foundation and under-floors including
watering , ramming etc.., complete.
a In foundation
Column foundation 1 x 15 1.50 1.50 0.15 5.06
Grade beam
Long walls 1 x 3 16.48 0.30 0.10 1.48
Cross walls 1 x 5 6.10 0.30 0.10 0.91
(a) 7.46
b In basement
Porch cum stairs 1 x 1 3.44 5.52 0.60 11.39
Bed Room I 1 x 1 3.05 2.78 0.60 5.09
Living Hall 1 x 1 3.66 5.52 0.60 12.12
Dining 1 x 1 4.12 2.74 0.60 6.77
Kitchen ,Service Passage & Toilet 1 x 1 5.30 2.78 0.60 8.84
Bed Room II 1 x 1 3.89 3.05 0.60 7.12
(b) 51.33
(a)+(b) 58.79 59.00
3 Providing and laying in foundation trenches
cement concrete 1:5:10 (one cement five
sand and ten HBG metal of 40mm size) for
foundation and underfloors including curing.
consolidation etc., complete.
a In foundation
Qty as per item No.2(a)
7.46 / 0.20 x 0.23 8.58
b In basement
Qty as per item No.2(b)
51.33 / 0.85 x 0.15 9.06
17.64 18.00
4 Providing and laying RCC 1:2:4 (one cement
two sand.& four 20mm graded stone
aggregate nominal size) to the plinth beam
including cost of shuttering . labour minnor
tools etc., but excluding the cost of
reinforcement.
GROUND FLOOR - DETAILED ESTIMATE
Name of Owner:-
Slno Description Nos Length Breadth Depth Total Qty Say
m2
/m3
/kg
GROUND FLOOR - DETAILED ESTIMATE
a Column footings 1 x 15 1.50 1.50 0.30 10.13
(Half pyramid formula) 8.78
18.90
b Core Beams
Long walls 1 x 3 16.48 0.23 0.30 3.41
Cross walls 1 x 5 6.10 0.23 0.30 2.10
5.51
c Lintel
Long walls 1 x 3 16.48 0.23 0.15 1.71
Cross walls 1 x 5 6.10 0.23 0.15 1.05
2.76
d Roof Beam
Long walls 1 x 3 16.48 0.23 0.30 3.41
Cross walls 1 x 5 6.10 0.23 0.30 2.10
5.51
e Pillars 1 x 15 0.23 0.23 2.88 2.29
f Roof slab
Main building 1 x 1 16.48 6.75 0.12 13.35
13.35
Net Qty a+b+c+d+e+f 48.32 48.00
5 Brick work in cement mortar 1:6 (one cement
&six sand) using best available country
bricks in foundation and superstructure.
a In foundation
Long walls 1 x 3 16.48 0.23 0.60 6.82
Cross walls 1 x 5 6.10 0.23 0.60 4.21
Ded Coloumn 1 x 15 0.23 0.23 0.60 -0.48
(a) 10.55
b In superstructure
Long walls 1 x 3 16.48 0.23 2.88 32.75
Cross walls 1 x 5 6.10 0.23 2.88 20.19
(b) 52.94
c DEDUCTIONS
M.D 1 x 1 1.20 0.23 2.40 0.66
D 1 x 4 0.90 0.23 2.10 1.74
D1 1 x 1 0.75 0.23 2.10 0.36
W 1 x 4 1.50 0.23 1.35 1.86
W1 1 x 2 0.90 0.23 1.35 0.56
KW 1 x 1 1.20 0.23 1.35 0.37
V 1 x 3 0.90 0.23 0.60 0.37
Name of Owner:-
Slno Description Nos Length Breadth Depth Total Qty Say
m2
/m3
/kg
GROUND FLOOR - DETAILED ESTIMATE
(c) 5.93
(a+b-c) 57.56 58.00
6 Providing and fixing 38mm thick fully
panelled door shutters single ordouble
hung using best Teakwood including cost
of all fixture and lockingarrangements
andfixing chargesetc.,complete.including
the wood work.( Teak wood )
M.D 1 x 1 1.20 - 2.40 2.88
D 1 x 4 0.90 - 2.10 7.56
D1 1 x 1 0.75 - 2.10 1.58
12.02 12.00
7 Providing and fixing 32mm thick fully
glazed window shutters usingstandard
glass panes of approvedquality including
the cost of allfixture and locking
arrangements and fixing chargesetc..,
complete.including the wood work ( Teak
wood )
W 1 x 4 1.50 - 1.35 8.10
W1 1 x 2 0.90 - 1.35 2.43
KW 1 x 1 1.20 - 1.35 1.62
V 1 x 3 0.90 - 0.60 1.62
13.77 14.00
8 Plastering the both sides of the wall
with cement mortar 1:5 (one cement &
five sand) 15mm thick to give an even
surfaces.
Porch cum stairs 1 x 2 3.44 - 2.88 19.81
1 x 2 5.52 - 2.88 31.80
Bed Room I 1 x 2 3.05 - 2.88 17.57
1 x 2 2.78 - 2.88 16.01
Living Hall 1 x 2 3.66 - 2.88 21.08
1 x 2 5.52 - 2.88 31.80
Dining 1 x 2 4.12 - 2.88 23.73
1 x 2 2.74 - 2.88 15.78
Kitchen ,Service Passage & Toilet 1 x 2 5.30 - 2.88 30.53
1 x 2 2.78 - 2.88 16.01
Bed Room II 1 x 2 3.89 - 2.88 22.41
1 x 2 3.05 - 2.88 17.57
Name of Owner:-
Slno Description Nos Length Breadth Depth Total Qty Say
m2
/m3
/kg
GROUND FLOOR - DETAILED ESTIMATE
(a) 264.10
b Outside plastering
Long walls 1 x 2 16.48 - 2.88 94.92
Cross walls 1 x 2 6.10 - 2.88 35.11
(b) 130.03
c Deductions
M.D 1 x 1 1.20 - 2.40 2.88
D 1 x 4 0.90 - 2.10 7.56
D1 1 x 1 0.75 - 2.10 1.58
W 1 x 4 1.50 - 1.35 8.10
W1 1 x 2 0.90 - 1.35 2.43
KW 1 x 1 1.20 - 1.35 1.62
V 1 x 3 0.90 - 0.60 1.62
(c) 25.79
(a+b-c) 368.34 368.00
9 Plastering the ceiling with cement mortar 1:4
(one cement and four sand) of thickness
6mm to give an even surfaces.
As per item No.4(f) 1 x 1 13.35 / 0.12 111.24 111.00
10 Painting the wood work two coats with
superior quality ready mixed paint
(Shalimar wood kote or equivalent) of
specified shade over and including a
cost of approved ready mixed primer to
give a bright and uniform shade on new
work.
As per item No.6 Qty 1 x 1 12.00 x 2.75 33.00
As per item No.7 Qty 1 x 1 14.00 x 2.50 35.00
68.00 68.00
11 Painting the inner walls, ceiling & outer
walls, with two coats of interior emulsion
and exterior emulsion respectively using
the approved colourover one coat of
white washing thenew work and give an
even shade.
As per item No.8 Qty 368.00
As per item No.9 Qty 111.00
479.00 479.00
12 Providing cutting, bending and
placing in position of M.S.Bars of
various sizes of reinforcement of
all RCC works and binding with
Name of Owner:-
Slno Description Nos Length Breadth Depth Total Qty Say
m2
/m3
/kg
GROUND FLOOR - DETAILED ESTIMATE
16 guage annealed steel wire.,
etc., complete.
As per item No. 4 Qty 48.00 120.00 Kg/m3
5760.00 5760.00
13 Providing and laying Granite flooring with
cement mortar
1:4 ( 1 cement ; 4 coarse sand)
As per item No.9 111.00 111.00
14 Providing and laying Ceramic tiles8mm
thick. With cement mortar1:4 ( 1cement ;4
coarse sand)
Toilet 1 x 2 2.02 - 2.10 8.48
1 x 2 1.46 - 2.10 6.13
Kitchen 1 x 1 3.05 - 0.90 2.75
1 x 1 2.78 - 0.90 2.50
19.86 20.00
15 Providing eletcrification works. LS
16 Providing and fixing Sanitary Instalations LS
17 Providing Septic tank arrangements LS
and Sump arrangements
18 Rain water Harvesting pits and LS
collection chamber.
OWNER PREPARED BY
Name of Owner:-
Sl.No. Description Quantity Rate Unit Amount
1 Earth work excavation for foundation
in all soils except hard rock and
depositing earth on banks within a
lead of not more then. complete. 59.00 350.00 M3
20650.00
2 Supplying &filling with river sand in
foundation and under -floor including
watering, ramming etc., complete 59.00 800.00 M3
47200.00
3 Providing and laying in foundation trenches
cement concrete 1:5:10 (one cement five
sand and ten HBGmetal of 40mm and
underfloorsincluding curing. consolidation
etc.,complete. 18.00 2100.00 M3
37800.00
4 Providing and laying RCC 1:2:4 (one
cement two sand.& foure 20mm
graded stoneaggregate nominal size)
to the plinth beam including cost of
shuttering . labour minnor tools etc.,
but excluding the cost of
reinforcement. 48.00 4000.00 M3
192000.00
5 Brick work in cement mortar 1:6 (one
cement &six sand) using best
availabel country bricks in foundation
and superstructure. 58.00 2200.00 M3
127600.00
6 Providing and fixing 38mm thick fully
panelled door shutters single ordouble
hung using best Teakwood including cost
of all fixture and lockingarrangements
andfixing chargesetc.,complete.including
the wood work.( Teak wood ) 12.00 6000.00 M2
72000.00
7 Providing and fixing 32mm thick fully
glazed window shutters usingstandard
glass panes of approvedquality including
the cost of allfixture and locking
arrangements and fixing chargesetc..,
complete.including the wood work ( Teak
wood ) 14.00 5000.00 M2
70000.00
8 Plastering the both sides of the wallwith
cement mortar 1:5 (one cement& five sand)
15mm thick to give aneven surfaces. 368.00 110.00 M2
40480.00
GROUND FLOOR ABSTRACT
0
Name of Owner:-
Sl.No. Description Quantity Rate Unit Amount
GROUND FLOOR ABSTRACT
0
9 Plastering the ceiling with cementmortar
1:4 (onr cement and four sand)of thickness
6mm to give an evensurfaces. 111.00 100.00 M2
11100.00
10 Painting the wood work two coats with
superior quality ready mixed paint
(Shalimar wood kote or equivalent) of
specified shade over and including a
cost of approved ready mixed primer
to give a bright and uniform shade on
new work. 68.00 125.00 M2
8500.00
11 Painting the inner walls, ceiling & outer
walls, with two coats of interior emulsion
and exterior emulsion respectively using
the approved colourover one coat of 479.00 140.00 M2
67060.00
white washing thenew work and give an
even shade.
12 Providing cutting, bending andplacing in
position of Bars of various sizes of
reinforcement of allRCC works and
binding with 16 guageannealed steel wire.., 5760.00 65.00 Kgs 374400.00
13 Providing and laying granite flooring
with cement mortar
1:4 ( 1 cement ; 4 coarse sand) 111.00 2500.00 M2
277500.00
14 Providing and laying Ceramic tiles
wall tiles 8mm thick. With cement mortar
1:4 ( 1cement ;4 coarse sand) 20.00 700.00 M2
14000.00
15 Providing eletcrification works. L.S 55000.00
16 Providing and fixing Sanitary Instalations L.S 45000.00
17 Providing Septic tank arrangements L.S 35000.00
and Sump arrangements
18 Rain water Harvesting pits and
collection chamber. L.S 22500.00
TOTAL Rs 1517790.00
OWNER PREPARED BY
Name of Owner:-
Slno Description Nos Length Breadth Depth Total Qty Say
m2
/m3
/kg
1 Providing and laying RCC 1:2:4 (one
cement two sand.& four 20mm
graded stoneaggregate nominal size)
to the plinth beam including cost of
shuttering . labour minnor tools etc.,
but excluding the cost of
reinforcement.
a Lintel
Long walls 1 x 3 16.48 0.23 0.15 1.71
Cross walls 1 x 5 6.10 0.23 0.15 1.05
2.76
b Roof Beam
Long walls 1 x 3 16.48 0.23 0.30 3.41
Cross walls 1 x 5 6.10 0.23 0.30 2.10
5.51
c Pillars 1 x 15 0.23 0.23 2.88 2.29
d Roof slab
Main building 1 x 1 16.48 6.75 0.12 13.35
13.35
Net Qty a+b+c+d 23.91 24.00
2 Brick work in cement mortar 1:6 (one
cement &six sand) using best availabel
country bricks in foundation and
superstructure.
a In superstructure
Long walls 1 x 3 16.48 0.23 2.88 32.75
Cross walls 1 x 5 6.10 0.23 2.88 20.19
Parapet wall 1 X 2 16.48 0.23 1.05 7.96
1 X 2 6.10 0.23 1.05 2.94
(b) 63.84
DEDUCTIONS
MD 1 x 1 1.20 0.23 2.40 0.66
D 1 x 4 0.90 0.23 2.10 1.74
D1 1 x 1 0.75 0.23 2.10 0.36
W 1 x 4 1.50 0.23 1.35 1.86
W1 1 x 2 0.90 0.23 1.35 0.56
V 1 x 1 0.90 0.23 0.60 0.12
(b) 5.31
(a-b) 58.53 59.00
FIRST FLOOR DETAILED ESTIMATE
0
Name of Owner:-
Slno Description Nos Length Breadth Depth Total Qty Say
m2
/m3
/kg
FIRST FLOOR DETAILED ESTIMATE
0
3 Providing and fixing 38mm thick fully
panelled door shutters single ordouble
hung using best Teakwood including cost
of all fixture and lockingarrangements
andfixing chargesetc.,complete.including
the wood work.( Teak wood )
MD 1 x 1 1.20 - 2.40 2.88
D 1 x 4 0.90 - 2.10 7.56
D1 1 x 1 0.75 - 2.10 1.58
12.02 12.00
4 Providing and fixing 32mm thick fully
glazed window shutters usingstandard
glass panes of approvedquality including
the cost of allfixture and locking
arrangements and fixing chargesetc..,
complete.including the wood work ( Teak
wood )
W 1 x 4 1.50 - 1.35 8.10
W1 1 x 2 0.90 - 1.35 2.43
V 1 x 1 0.90 - 0.60 0.54
11.07 11.00
5 Plastering the both sides of the wall
with cement mortar 1:5 (one cement &
five sand) 15mm thick to give an even
surfaces.
Lobby 1 x 2 3.44 - 2.88 19.81
1 x 2 5.52 - 2.88 31.80
Bed Room I 1 x 2 3.05 - 2.88 17.57
1 x 2 2.78 - 2.88 16.01
Living Hall 1 x 2 3.66 - 2.88 21.08
1 x 2 5.52 - 2.88 31.80
Dining 1 x 2 4.12 - 2.88 23.73
1 x 2 2.74 - 2.88 15.78
Kitchen ,Service Passage & Toilet 1 x 2 5.30 - 2.88 30.53
1 x 2 2.78 - 2.88 16.01
Bed Room II 1 x 2 3.89 - 2.88 22.41
1 x 2 3.05 - 2.88 17.57
(a) 264.10
b Outside plastering
Long walls 1 x 2 16.48 - 4.05 133.49
Cross walls 1 x 2 6.10 - 4.05 49.37
(b) 182.86
c DEDUCTIONS
MD 1 x 1 1.20 - 2.40 2.88
Name of Owner:-
Slno Description Nos Length Breadth Depth Total Qty Say
m2
/m3
/kg
FIRST FLOOR DETAILED ESTIMATE
0
D 1 x 4 0.90 - 2.10 7.56
D1 1 x 1 0.75 - 2.10 1.58
W 1 x 4 1.50 - 1.35 8.10
W1 1 x 2 0.90 - 1.35 2.43
V 1 x 1 0.90 - 0.60 0.54
(c) 23.09
(a+b-c) 423.87 424.00
6 Plastering the ceiling with cement
mortar 1:4 (one cement and four sand)
of thickness 6mm to give an even
surfaces.
As per item No.1(d)(a) 1 x 1 13.35 / 0.12 111.24 111.00
7 Painting the wood work two coats with
superior quality ready mixed paint
(Shalimar wood kote or equivalent) of
specified shade over and including
cost of approved ready mixed primer to
give a bright and uniform shade on new
work.
As per item No.3 Qty 1 x 1 12.00 x 2.75 33.00
As per item No.4 Qty 1 x 1 11.00 x 2.50 27.50
60.50 61.00
8 Painting the inner walls, ceiling & outer
walls, with two coats of interior emulsion
and exterior emulsion respectively using
the approved colourover one coat of
white washing thenew work and give an
even shade.
As per item No.5 Qty 424.00
As per item No.6 Qty 111.00
535.00 535.00
9 Providing cutting, bending and
placing in position of M.S.Bars of
various sizes of reinforcement of
all RCC works and binding with
16 guage annealed steel wire.,
etc., complete.
As per item No. 1 Qty 24.00 120.00 Kg/m3
2880.00 2880.00
10 Providing and laying granite flooring
Name of Owner:-
Slno Description Nos Length Breadth Depth Total Qty Say
m2
/m3
/kg
FIRST FLOOR DETAILED ESTIMATE
0
with cement mortar
1:4 ( 1 cement ; 4 coarse sand)
111.00 111.00
11 Providing and laying Ceramic tiles
wall tiles 8mm thick. With cement mortar
1:4 ( 1cement ;4 coarse sand)
Toilet 1 x 2 2.02 - 2.10 8.48
1 x 2 1.46 - 2.10 6.13
Kitchen 1 x 1 3.05 - 0.90 2.75
1 x 1 2.78 - 0.90 2.50
19.86 20.00
12 Providing lime concrete terracing on roofs
average thickness 10cms laid to fall with
25mm nominal size brick aggregate and
50% lime mortar 1:2(1 lime putty : 2
surkhi) to a thickness of 10cm including
necessary tamping consolidation and
finished with belgiri treatment complete.
As per item no. 10 qty 111.00
13 Providing and laying bricktiles of
designation 100 over mumty, roofs
grouted with cement mortar 1:3 (1
cement;3 fine sand) mixed with 2% of
integral water proofing compound by
weight of cement over a 12mm thick layer
of cement mortar 1:3 (1 cement : 3 fine
sand) and finished with F.P.S brick tiles
As per item no. 10 qty 111.00
14 Providing eletcrification works. LS
15 Providing and fixing Sanitary Instalations LS
OWNER PREPARED BY
Name of Owner:-
Sl.No. Description Quantity Rate Unit Amount
1 Providing and laying RCC 1:2:4 (one
cement two sand.& four 20mm graded
stone aggregate nominal size) to the plinth
beam including cost of shuttering . labour
minnor tools etc., but excluding the cost
of reinforcement. 24.00 4100.00 M3
98400.00
2 Brick work in cement mortar 1:6 (one
cement &six sand) using best availabel
country bricks in foundation and
superstructure. 59.00 2300.00 M3
135700.00
3 Providing and fixing 38mm thick fully
panelled door shutters single ordouble
hung using best Teakwood including cost
of all fixture and lockingarrangements
andfixing chargesetc.,complete.including
the wood work.( Teak wood ) 12.00 6100.00 M2
73200.00
4 Providing and fixing 32mm thick fully
glazed window shutters usingstandard
glass panes of approvedquality including
the cost of allfixture and locking
arrangements and fixing chargesetc..,
complete.including the wood work ( Teak
wood ) 11.00 5100.00 M2
56100.00
5 Plastering the both sides of the wall with
cement mortar 1:5 (one cement & five
sand) 15mm thick to give an even
surfaces. 424.00 110.00 M2
46640.00
6 Plastering the ceiling with cement mortar
1:4 (onr cement and four sand) of
thickness 6mm to give an even surfaces. 111.00 100.00 M2
11100.00
7 Painting the wood work two coats with
superior quality ready mixed paint
(Shalimar wood kote or equivalent) of
specified shade over and including a cost
of approved ready mixed primer to give a
bright and uniform shade on new work. 61.00 125.00 M2
7625.00
8 Painting the inner walls, ceiling & outer
walls, with two coats of interior emulsion
and exterior emulsion respectively using
the approved colourover one coat of 535.00 140.00 M2
74900.00
FIRST FLOOR ABSTRACT
0
Name of Owner:-
Sl.No. Description Quantity Rate Unit Amount
FIRST FLOOR ABSTRACT
0
white washing thenew work and give an
even shade.
9 Providing cutting, bending andplacing in
position of Bars of various sizes of
reinforcement of allRCC works and
binding with 16 guageannealed steel wire..,
etc.., complete. 2880.00 65.00 Kgs 187200.00
10 Providing and laying granite flooring with
cement mortar1:4 ( 1 cement ; 4 coarse
sand) 111.00 2500.00 M2
277500.00
11 Providing and laying ceramic tilesflooring `
with cement mortar1:4 ( 1 cement ; 4 coarse
sand) 20.00 750.00 M2
15000.00
12 Providing lime concrete terracing onroofs
average thickness 10cms laid tofall with
25mm nominal size brickaggregate and
50% lime mortar 1:2(1lime putty : 2 surkhi)
to a thickness of10cm including necessary
tampingconsolidation and finished with 111.00 450.00 M2
49950.00
belgiritreatment complete.
13 Providing and laying bricktiles of
designation 100 over mumty, roofs
grouted with cement mortar 1:3 (1cement;3
fine sand) mixed with 2% ofintegral water
proofing compound byweight of cement
over a 12mm thicklayer of cement mortar
1:3 (1 cement :3 fine sand) and finished
with F.P.Sbrick tiles 111.00 200.00 M2
22200.00
14 Providing eletcrification works. L.S 35000.00
15 Providing and fixing Sanitary Instalations L.S 22500.00
TOTAL Rs 1113015.00
OWNER PREPARED BY

More Related Content

Viewers also liked

47093152 estimation
47093152 estimation47093152 estimation
47093152 estimationimaduddin91
 
07 a60105 estimatingandcosting
07 a60105 estimatingandcosting07 a60105 estimatingandcosting
07 a60105 estimatingandcostingimaduddin91
 
23262630 unit-derivation-cost-agri-infra
23262630 unit-derivation-cost-agri-infra23262630 unit-derivation-cost-agri-infra
23262630 unit-derivation-cost-agri-infraimaduddin91
 
Estimating calculation
Estimating calculationEstimating calculation
Estimating calculationZIyeeTan
 
91488667 estimation-of-building-house
91488667 estimation-of-building-house91488667 estimation-of-building-house
91488667 estimation-of-building-houseimaduddin91
 
45010341 planning-estimate
45010341 planning-estimate45010341 planning-estimate
45010341 planning-estimateimaduddin91
 

Viewers also liked (6)

47093152 estimation
47093152 estimation47093152 estimation
47093152 estimation
 
07 a60105 estimatingandcosting
07 a60105 estimatingandcosting07 a60105 estimatingandcosting
07 a60105 estimatingandcosting
 
23262630 unit-derivation-cost-agri-infra
23262630 unit-derivation-cost-agri-infra23262630 unit-derivation-cost-agri-infra
23262630 unit-derivation-cost-agri-infra
 
Estimating calculation
Estimating calculationEstimating calculation
Estimating calculation
 
91488667 estimation-of-building-house
91488667 estimation-of-building-house91488667 estimation-of-building-house
91488667 estimation-of-building-house
 
45010341 planning-estimate
45010341 planning-estimate45010341 planning-estimate
45010341 planning-estimate
 

Similar to 72747160 estimation

Tender_Schedule_Renovation_of_Vadakkechira_Bus_Stand.pdf
Tender_Schedule_Renovation_of_Vadakkechira_Bus_Stand.pdfTender_Schedule_Renovation_of_Vadakkechira_Bus_Stand.pdf
Tender_Schedule_Renovation_of_Vadakkechira_Bus_Stand.pdfssuserd43de8
 
12724469 wtp-cost-estimate
12724469 wtp-cost-estimate12724469 wtp-cost-estimate
12724469 wtp-cost-estimateimaduddin91
 
97170708 estimate-of-material-and-labor
97170708 estimate-of-material-and-labor97170708 estimate-of-material-and-labor
97170708 estimate-of-material-and-laborimaduddin91
 
Girls home estimation
Girls home estimationGirls home estimation
Girls home estimationkrkantamneni
 
Girls home estimation
Girls home estimationGirls home estimation
Girls home estimationkrkantamneni
 
Bo q for joint cuart hall block construction in pamir (3)
Bo q for joint cuart hall block construction in pamir (3)Bo q for joint cuart hall block construction in pamir (3)
Bo q for joint cuart hall block construction in pamir (3)Stephen Nzima
 
Fence BOQ with Materials.pdf
Fence BOQ with Materials.pdfFence BOQ with Materials.pdf
Fence BOQ with Materials.pdfMutha Morgan
 
Leisure Centre
Leisure CentreLeisure Centre
Leisure CentreEdel Fox
 
Analysis of rates for labour and material
Analysis of rates for labour and materialAnalysis of rates for labour and material
Analysis of rates for labour and materialALI HYDER GADHI
 
Bolderstone brochure
Bolderstone brochureBolderstone brochure
Bolderstone brochurekristenjames
 
Estimation and quantity surveying
Estimation and quantity surveyingEstimation and quantity surveying
Estimation and quantity surveyingAwanish Shukla
 
SPECIFICATIONS FOR ADDL HOUSING PROJECT.pptx
SPECIFICATIONS FOR ADDL HOUSING PROJECT.pptxSPECIFICATIONS FOR ADDL HOUSING PROJECT.pptx
SPECIFICATIONS FOR ADDL HOUSING PROJECT.pptxswethasekhar5
 
Building materials, Basic civil engineering ,unit-1
Building materials, Basic civil engineering ,unit-1Building materials, Basic civil engineering ,unit-1
Building materials, Basic civil engineering ,unit-1Parimal Jha
 
Building Materials & Construction Module - 5
Building Materials & Construction Module - 5Building Materials & Construction Module - 5
Building Materials & Construction Module - 5Abhilash B L
 

Similar to 72747160 estimation (20)

Tender_Schedule_Renovation_of_Vadakkechira_Bus_Stand.pdf
Tender_Schedule_Renovation_of_Vadakkechira_Bus_Stand.pdfTender_Schedule_Renovation_of_Vadakkechira_Bus_Stand.pdf
Tender_Schedule_Renovation_of_Vadakkechira_Bus_Stand.pdf
 
Office building new
Office building newOffice building new
Office building new
 
rahta.pdf
rahta.pdfrahta.pdf
rahta.pdf
 
2_2._BOQ.pdf
2_2._BOQ.pdf2_2._BOQ.pdf
2_2._BOQ.pdf
 
12724469 wtp-cost-estimate
12724469 wtp-cost-estimate12724469 wtp-cost-estimate
12724469 wtp-cost-estimate
 
97170708 estimate-of-material-and-labor
97170708 estimate-of-material-and-labor97170708 estimate-of-material-and-labor
97170708 estimate-of-material-and-labor
 
Girls home estimation
Girls home estimationGirls home estimation
Girls home estimation
 
Girls home estimation
Girls home estimationGirls home estimation
Girls home estimation
 
Bo q for joint cuart hall block construction in pamir (3)
Bo q for joint cuart hall block construction in pamir (3)Bo q for joint cuart hall block construction in pamir (3)
Bo q for joint cuart hall block construction in pamir (3)
 
Bo q for shelter
Bo q  for shelterBo q  for shelter
Bo q for shelter
 
Fence BOQ with Materials.pdf
Fence BOQ with Materials.pdfFence BOQ with Materials.pdf
Fence BOQ with Materials.pdf
 
Plastering ppt
Plastering pptPlastering ppt
Plastering ppt
 
Leisure Centre
Leisure CentreLeisure Centre
Leisure Centre
 
Analysis of rates for labour and material
Analysis of rates for labour and materialAnalysis of rates for labour and material
Analysis of rates for labour and material
 
Bolderstone brochure
Bolderstone brochureBolderstone brochure
Bolderstone brochure
 
PT.pptx
PT.pptxPT.pptx
PT.pptx
 
Estimation and quantity surveying
Estimation and quantity surveyingEstimation and quantity surveying
Estimation and quantity surveying
 
SPECIFICATIONS FOR ADDL HOUSING PROJECT.pptx
SPECIFICATIONS FOR ADDL HOUSING PROJECT.pptxSPECIFICATIONS FOR ADDL HOUSING PROJECT.pptx
SPECIFICATIONS FOR ADDL HOUSING PROJECT.pptx
 
Building materials, Basic civil engineering ,unit-1
Building materials, Basic civil engineering ,unit-1Building materials, Basic civil engineering ,unit-1
Building materials, Basic civil engineering ,unit-1
 
Building Materials & Construction Module - 5
Building Materials & Construction Module - 5Building Materials & Construction Module - 5
Building Materials & Construction Module - 5
 

More from imaduddin91

07 a80102 groundwaterdevelopmentandmanagement
07 a80102 groundwaterdevelopmentandmanagement07 a80102 groundwaterdevelopmentandmanagement
07 a80102 groundwaterdevelopmentandmanagementimaduddin91
 
Remotesensingandgisapplications
RemotesensingandgisapplicationsRemotesensingandgisapplications
Remotesensingandgisapplicationsimaduddin91
 
R05410107 advancedfoundationengineering
R05410107 advancedfoundationengineeringR05410107 advancedfoundationengineering
R05410107 advancedfoundationengineeringimaduddin91
 
07 a80101 advanced structural design
07 a80101 advanced structural design07 a80101 advanced structural design
07 a80101 advanced structural designimaduddin91
 
07 a70401 remotesensingandgisapplications
07 a70401 remotesensingandgisapplications07 a70401 remotesensingandgisapplications
07 a70401 remotesensingandgisapplicationsimaduddin91
 
07 a70102 finite element methods in civil engineering
07 a70102 finite element methods in civil engineering07 a70102 finite element methods in civil engineering
07 a70102 finite element methods in civil engineeringimaduddin91
 
R05410103 remotesensingandgisapplications
R05410103 remotesensingandgisapplicationsR05410103 remotesensingandgisapplications
R05410103 remotesensingandgisapplicationsimaduddin91
 
R05410102 finiteelementmethodsincivilengineering
R05410102 finiteelementmethodsincivilengineeringR05410102 finiteelementmethodsincivilengineering
R05410102 finiteelementmethodsincivilengineeringimaduddin91
 
07 a60105 estimatingandcosting
07 a60105 estimatingandcosting07 a60105 estimatingandcosting
07 a60105 estimatingandcostingimaduddin91
 
07 a82101 advanced structural design
07 a82101  advanced structural design07 a82101  advanced structural design
07 a82101 advanced structural designimaduddin91
 
07 a80106 pavementanalysisanddesign
07 a80106 pavementanalysisanddesign07 a80106 pavementanalysisanddesign
07 a80106 pavementanalysisanddesignimaduddin91
 
07 a80104 watershedmanagement
07 a80104 watershedmanagement07 a80104 watershedmanagement
07 a80104 watershedmanagementimaduddin91
 
07 a80102 groundwaterdevelopmentandmanagement
07 a80102 groundwaterdevelopmentandmanagement07 a80102 groundwaterdevelopmentandmanagement
07 a80102 groundwaterdevelopmentandmanagementimaduddin91
 
07 a70110 remotesensingandgisapplications
07 a70110 remotesensingandgisapplications07 a70110 remotesensingandgisapplications
07 a70110 remotesensingandgisapplicationsimaduddin91
 
07 a70107 waterresourcessystemplanningandmanagement
07 a70107 waterresourcessystemplanningandmanagement07 a70107 waterresourcessystemplanningandmanagement
07 a70107 waterresourcessystemplanningandmanagementimaduddin91
 
07 a70102 finite element methods in civil engineering
07 a70102  finite element methods in civil engineering07 a70102  finite element methods in civil engineering
07 a70102 finite element methods in civil engineeringimaduddin91
 
Statistical metods
Statistical metodsStatistical metods
Statistical metodsimaduddin91
 
Sas language reference concepts
Sas language reference  conceptsSas language reference  concepts
Sas language reference conceptsimaduddin91
 
Base 9.1 preparation guide
Base 9.1 preparation guideBase 9.1 preparation guide
Base 9.1 preparation guideimaduddin91
 

More from imaduddin91 (20)

07 a80102 groundwaterdevelopmentandmanagement
07 a80102 groundwaterdevelopmentandmanagement07 a80102 groundwaterdevelopmentandmanagement
07 a80102 groundwaterdevelopmentandmanagement
 
Remotesensingandgisapplications
RemotesensingandgisapplicationsRemotesensingandgisapplications
Remotesensingandgisapplications
 
R05410107 advancedfoundationengineering
R05410107 advancedfoundationengineeringR05410107 advancedfoundationengineering
R05410107 advancedfoundationengineering
 
07 a80101 advanced structural design
07 a80101 advanced structural design07 a80101 advanced structural design
07 a80101 advanced structural design
 
07 a70401 remotesensingandgisapplications
07 a70401 remotesensingandgisapplications07 a70401 remotesensingandgisapplications
07 a70401 remotesensingandgisapplications
 
07 a70102 finite element methods in civil engineering
07 a70102 finite element methods in civil engineering07 a70102 finite element methods in civil engineering
07 a70102 finite element methods in civil engineering
 
R05410103 remotesensingandgisapplications
R05410103 remotesensingandgisapplicationsR05410103 remotesensingandgisapplications
R05410103 remotesensingandgisapplications
 
R05410102 finiteelementmethodsincivilengineering
R05410102 finiteelementmethodsincivilengineeringR05410102 finiteelementmethodsincivilengineering
R05410102 finiteelementmethodsincivilengineering
 
07 a60105 estimatingandcosting
07 a60105 estimatingandcosting07 a60105 estimatingandcosting
07 a60105 estimatingandcosting
 
07 a82101 advanced structural design
07 a82101  advanced structural design07 a82101  advanced structural design
07 a82101 advanced structural design
 
07 a80106 pavementanalysisanddesign
07 a80106 pavementanalysisanddesign07 a80106 pavementanalysisanddesign
07 a80106 pavementanalysisanddesign
 
07 a80104 watershedmanagement
07 a80104 watershedmanagement07 a80104 watershedmanagement
07 a80104 watershedmanagement
 
07 a80102 groundwaterdevelopmentandmanagement
07 a80102 groundwaterdevelopmentandmanagement07 a80102 groundwaterdevelopmentandmanagement
07 a80102 groundwaterdevelopmentandmanagement
 
07 a70110 remotesensingandgisapplications
07 a70110 remotesensingandgisapplications07 a70110 remotesensingandgisapplications
07 a70110 remotesensingandgisapplications
 
07 a70107 waterresourcessystemplanningandmanagement
07 a70107 waterresourcessystemplanningandmanagement07 a70107 waterresourcessystemplanningandmanagement
07 a70107 waterresourcessystemplanningandmanagement
 
07 a70102 finite element methods in civil engineering
07 a70102  finite element methods in civil engineering07 a70102  finite element methods in civil engineering
07 a70102 finite element methods in civil engineering
 
Statistical metods
Statistical metodsStatistical metods
Statistical metods
 
Sas cheat
Sas cheatSas cheat
Sas cheat
 
Sas language reference concepts
Sas language reference  conceptsSas language reference  concepts
Sas language reference concepts
 
Base 9.1 preparation guide
Base 9.1 preparation guideBase 9.1 preparation guide
Base 9.1 preparation guide
 

72747160 estimation

  • 1. Name of Owner:- Slno Description Nos Length Breadth Depth Total Qty Say m2 /m3 /kg 1 Earth work excavation for foundation in all soils except hard rock and depositing earth on banks within a lead of not more than. complete. Column foundation 1 x 15 1.50 1.50 1.50 50.63 Grade beam Long walls 1 x 3 16.48 0.30 0.35 5.19 Cross walls 1 x 5 6.10 0.30 0.35 3.20 59.02 59.00 2 Supplying & filling with river sand in foundation and under-floors including watering , ramming etc.., complete. a In foundation Column foundation 1 x 15 1.50 1.50 0.15 5.06 Grade beam Long walls 1 x 3 16.48 0.30 0.10 1.48 Cross walls 1 x 5 6.10 0.30 0.10 0.91 (a) 7.46 b In basement Porch cum stairs 1 x 1 3.44 5.52 0.60 11.39 Bed Room I 1 x 1 3.05 2.78 0.60 5.09 Living Hall 1 x 1 3.66 5.52 0.60 12.12 Dining 1 x 1 4.12 2.74 0.60 6.77 Kitchen ,Service Passage & Toilet 1 x 1 5.30 2.78 0.60 8.84 Bed Room II 1 x 1 3.89 3.05 0.60 7.12 (b) 51.33 (a)+(b) 58.79 59.00 3 Providing and laying in foundation trenches cement concrete 1:5:10 (one cement five sand and ten HBG metal of 40mm size) for foundation and underfloors including curing. consolidation etc., complete. a In foundation Qty as per item No.2(a) 7.46 / 0.20 x 0.23 8.58 b In basement Qty as per item No.2(b) 51.33 / 0.85 x 0.15 9.06 17.64 18.00 4 Providing and laying RCC 1:2:4 (one cement two sand.& four 20mm graded stone aggregate nominal size) to the plinth beam including cost of shuttering . labour minnor tools etc., but excluding the cost of reinforcement. GROUND FLOOR - DETAILED ESTIMATE
  • 2. Name of Owner:- Slno Description Nos Length Breadth Depth Total Qty Say m2 /m3 /kg GROUND FLOOR - DETAILED ESTIMATE a Column footings 1 x 15 1.50 1.50 0.30 10.13 (Half pyramid formula) 8.78 18.90 b Core Beams Long walls 1 x 3 16.48 0.23 0.30 3.41 Cross walls 1 x 5 6.10 0.23 0.30 2.10 5.51 c Lintel Long walls 1 x 3 16.48 0.23 0.15 1.71 Cross walls 1 x 5 6.10 0.23 0.15 1.05 2.76 d Roof Beam Long walls 1 x 3 16.48 0.23 0.30 3.41 Cross walls 1 x 5 6.10 0.23 0.30 2.10 5.51 e Pillars 1 x 15 0.23 0.23 2.88 2.29 f Roof slab Main building 1 x 1 16.48 6.75 0.12 13.35 13.35 Net Qty a+b+c+d+e+f 48.32 48.00 5 Brick work in cement mortar 1:6 (one cement &six sand) using best available country bricks in foundation and superstructure. a In foundation Long walls 1 x 3 16.48 0.23 0.60 6.82 Cross walls 1 x 5 6.10 0.23 0.60 4.21 Ded Coloumn 1 x 15 0.23 0.23 0.60 -0.48 (a) 10.55 b In superstructure Long walls 1 x 3 16.48 0.23 2.88 32.75 Cross walls 1 x 5 6.10 0.23 2.88 20.19 (b) 52.94 c DEDUCTIONS M.D 1 x 1 1.20 0.23 2.40 0.66 D 1 x 4 0.90 0.23 2.10 1.74 D1 1 x 1 0.75 0.23 2.10 0.36 W 1 x 4 1.50 0.23 1.35 1.86 W1 1 x 2 0.90 0.23 1.35 0.56 KW 1 x 1 1.20 0.23 1.35 0.37 V 1 x 3 0.90 0.23 0.60 0.37
  • 3. Name of Owner:- Slno Description Nos Length Breadth Depth Total Qty Say m2 /m3 /kg GROUND FLOOR - DETAILED ESTIMATE (c) 5.93 (a+b-c) 57.56 58.00 6 Providing and fixing 38mm thick fully panelled door shutters single ordouble hung using best Teakwood including cost of all fixture and lockingarrangements andfixing chargesetc.,complete.including the wood work.( Teak wood ) M.D 1 x 1 1.20 - 2.40 2.88 D 1 x 4 0.90 - 2.10 7.56 D1 1 x 1 0.75 - 2.10 1.58 12.02 12.00 7 Providing and fixing 32mm thick fully glazed window shutters usingstandard glass panes of approvedquality including the cost of allfixture and locking arrangements and fixing chargesetc.., complete.including the wood work ( Teak wood ) W 1 x 4 1.50 - 1.35 8.10 W1 1 x 2 0.90 - 1.35 2.43 KW 1 x 1 1.20 - 1.35 1.62 V 1 x 3 0.90 - 0.60 1.62 13.77 14.00 8 Plastering the both sides of the wall with cement mortar 1:5 (one cement & five sand) 15mm thick to give an even surfaces. Porch cum stairs 1 x 2 3.44 - 2.88 19.81 1 x 2 5.52 - 2.88 31.80 Bed Room I 1 x 2 3.05 - 2.88 17.57 1 x 2 2.78 - 2.88 16.01 Living Hall 1 x 2 3.66 - 2.88 21.08 1 x 2 5.52 - 2.88 31.80 Dining 1 x 2 4.12 - 2.88 23.73 1 x 2 2.74 - 2.88 15.78 Kitchen ,Service Passage & Toilet 1 x 2 5.30 - 2.88 30.53 1 x 2 2.78 - 2.88 16.01 Bed Room II 1 x 2 3.89 - 2.88 22.41 1 x 2 3.05 - 2.88 17.57
  • 4. Name of Owner:- Slno Description Nos Length Breadth Depth Total Qty Say m2 /m3 /kg GROUND FLOOR - DETAILED ESTIMATE (a) 264.10 b Outside plastering Long walls 1 x 2 16.48 - 2.88 94.92 Cross walls 1 x 2 6.10 - 2.88 35.11 (b) 130.03 c Deductions M.D 1 x 1 1.20 - 2.40 2.88 D 1 x 4 0.90 - 2.10 7.56 D1 1 x 1 0.75 - 2.10 1.58 W 1 x 4 1.50 - 1.35 8.10 W1 1 x 2 0.90 - 1.35 2.43 KW 1 x 1 1.20 - 1.35 1.62 V 1 x 3 0.90 - 0.60 1.62 (c) 25.79 (a+b-c) 368.34 368.00 9 Plastering the ceiling with cement mortar 1:4 (one cement and four sand) of thickness 6mm to give an even surfaces. As per item No.4(f) 1 x 1 13.35 / 0.12 111.24 111.00 10 Painting the wood work two coats with superior quality ready mixed paint (Shalimar wood kote or equivalent) of specified shade over and including a cost of approved ready mixed primer to give a bright and uniform shade on new work. As per item No.6 Qty 1 x 1 12.00 x 2.75 33.00 As per item No.7 Qty 1 x 1 14.00 x 2.50 35.00 68.00 68.00 11 Painting the inner walls, ceiling & outer walls, with two coats of interior emulsion and exterior emulsion respectively using the approved colourover one coat of white washing thenew work and give an even shade. As per item No.8 Qty 368.00 As per item No.9 Qty 111.00 479.00 479.00 12 Providing cutting, bending and placing in position of M.S.Bars of various sizes of reinforcement of all RCC works and binding with
  • 5. Name of Owner:- Slno Description Nos Length Breadth Depth Total Qty Say m2 /m3 /kg GROUND FLOOR - DETAILED ESTIMATE 16 guage annealed steel wire., etc., complete. As per item No. 4 Qty 48.00 120.00 Kg/m3 5760.00 5760.00 13 Providing and laying Granite flooring with cement mortar 1:4 ( 1 cement ; 4 coarse sand) As per item No.9 111.00 111.00 14 Providing and laying Ceramic tiles8mm thick. With cement mortar1:4 ( 1cement ;4 coarse sand) Toilet 1 x 2 2.02 - 2.10 8.48 1 x 2 1.46 - 2.10 6.13 Kitchen 1 x 1 3.05 - 0.90 2.75 1 x 1 2.78 - 0.90 2.50 19.86 20.00 15 Providing eletcrification works. LS 16 Providing and fixing Sanitary Instalations LS 17 Providing Septic tank arrangements LS and Sump arrangements 18 Rain water Harvesting pits and LS collection chamber. OWNER PREPARED BY
  • 6.
  • 7.
  • 8.
  • 9.
  • 10.
  • 11. Name of Owner:- Sl.No. Description Quantity Rate Unit Amount 1 Earth work excavation for foundation in all soils except hard rock and depositing earth on banks within a lead of not more then. complete. 59.00 350.00 M3 20650.00 2 Supplying &filling with river sand in foundation and under -floor including watering, ramming etc., complete 59.00 800.00 M3 47200.00 3 Providing and laying in foundation trenches cement concrete 1:5:10 (one cement five sand and ten HBGmetal of 40mm and underfloorsincluding curing. consolidation etc.,complete. 18.00 2100.00 M3 37800.00 4 Providing and laying RCC 1:2:4 (one cement two sand.& foure 20mm graded stoneaggregate nominal size) to the plinth beam including cost of shuttering . labour minnor tools etc., but excluding the cost of reinforcement. 48.00 4000.00 M3 192000.00 5 Brick work in cement mortar 1:6 (one cement &six sand) using best availabel country bricks in foundation and superstructure. 58.00 2200.00 M3 127600.00 6 Providing and fixing 38mm thick fully panelled door shutters single ordouble hung using best Teakwood including cost of all fixture and lockingarrangements andfixing chargesetc.,complete.including the wood work.( Teak wood ) 12.00 6000.00 M2 72000.00 7 Providing and fixing 32mm thick fully glazed window shutters usingstandard glass panes of approvedquality including the cost of allfixture and locking arrangements and fixing chargesetc.., complete.including the wood work ( Teak wood ) 14.00 5000.00 M2 70000.00 8 Plastering the both sides of the wallwith cement mortar 1:5 (one cement& five sand) 15mm thick to give aneven surfaces. 368.00 110.00 M2 40480.00 GROUND FLOOR ABSTRACT 0
  • 12. Name of Owner:- Sl.No. Description Quantity Rate Unit Amount GROUND FLOOR ABSTRACT 0 9 Plastering the ceiling with cementmortar 1:4 (onr cement and four sand)of thickness 6mm to give an evensurfaces. 111.00 100.00 M2 11100.00 10 Painting the wood work two coats with superior quality ready mixed paint (Shalimar wood kote or equivalent) of specified shade over and including a cost of approved ready mixed primer to give a bright and uniform shade on new work. 68.00 125.00 M2 8500.00 11 Painting the inner walls, ceiling & outer walls, with two coats of interior emulsion and exterior emulsion respectively using the approved colourover one coat of 479.00 140.00 M2 67060.00 white washing thenew work and give an even shade. 12 Providing cutting, bending andplacing in position of Bars of various sizes of reinforcement of allRCC works and binding with 16 guageannealed steel wire.., 5760.00 65.00 Kgs 374400.00 13 Providing and laying granite flooring with cement mortar 1:4 ( 1 cement ; 4 coarse sand) 111.00 2500.00 M2 277500.00 14 Providing and laying Ceramic tiles wall tiles 8mm thick. With cement mortar 1:4 ( 1cement ;4 coarse sand) 20.00 700.00 M2 14000.00 15 Providing eletcrification works. L.S 55000.00 16 Providing and fixing Sanitary Instalations L.S 45000.00 17 Providing Septic tank arrangements L.S 35000.00 and Sump arrangements 18 Rain water Harvesting pits and collection chamber. L.S 22500.00 TOTAL Rs 1517790.00 OWNER PREPARED BY
  • 13. Name of Owner:- Slno Description Nos Length Breadth Depth Total Qty Say m2 /m3 /kg 1 Providing and laying RCC 1:2:4 (one cement two sand.& four 20mm graded stoneaggregate nominal size) to the plinth beam including cost of shuttering . labour minnor tools etc., but excluding the cost of reinforcement. a Lintel Long walls 1 x 3 16.48 0.23 0.15 1.71 Cross walls 1 x 5 6.10 0.23 0.15 1.05 2.76 b Roof Beam Long walls 1 x 3 16.48 0.23 0.30 3.41 Cross walls 1 x 5 6.10 0.23 0.30 2.10 5.51 c Pillars 1 x 15 0.23 0.23 2.88 2.29 d Roof slab Main building 1 x 1 16.48 6.75 0.12 13.35 13.35 Net Qty a+b+c+d 23.91 24.00 2 Brick work in cement mortar 1:6 (one cement &six sand) using best availabel country bricks in foundation and superstructure. a In superstructure Long walls 1 x 3 16.48 0.23 2.88 32.75 Cross walls 1 x 5 6.10 0.23 2.88 20.19 Parapet wall 1 X 2 16.48 0.23 1.05 7.96 1 X 2 6.10 0.23 1.05 2.94 (b) 63.84 DEDUCTIONS MD 1 x 1 1.20 0.23 2.40 0.66 D 1 x 4 0.90 0.23 2.10 1.74 D1 1 x 1 0.75 0.23 2.10 0.36 W 1 x 4 1.50 0.23 1.35 1.86 W1 1 x 2 0.90 0.23 1.35 0.56 V 1 x 1 0.90 0.23 0.60 0.12 (b) 5.31 (a-b) 58.53 59.00 FIRST FLOOR DETAILED ESTIMATE 0
  • 14. Name of Owner:- Slno Description Nos Length Breadth Depth Total Qty Say m2 /m3 /kg FIRST FLOOR DETAILED ESTIMATE 0 3 Providing and fixing 38mm thick fully panelled door shutters single ordouble hung using best Teakwood including cost of all fixture and lockingarrangements andfixing chargesetc.,complete.including the wood work.( Teak wood ) MD 1 x 1 1.20 - 2.40 2.88 D 1 x 4 0.90 - 2.10 7.56 D1 1 x 1 0.75 - 2.10 1.58 12.02 12.00 4 Providing and fixing 32mm thick fully glazed window shutters usingstandard glass panes of approvedquality including the cost of allfixture and locking arrangements and fixing chargesetc.., complete.including the wood work ( Teak wood ) W 1 x 4 1.50 - 1.35 8.10 W1 1 x 2 0.90 - 1.35 2.43 V 1 x 1 0.90 - 0.60 0.54 11.07 11.00 5 Plastering the both sides of the wall with cement mortar 1:5 (one cement & five sand) 15mm thick to give an even surfaces. Lobby 1 x 2 3.44 - 2.88 19.81 1 x 2 5.52 - 2.88 31.80 Bed Room I 1 x 2 3.05 - 2.88 17.57 1 x 2 2.78 - 2.88 16.01 Living Hall 1 x 2 3.66 - 2.88 21.08 1 x 2 5.52 - 2.88 31.80 Dining 1 x 2 4.12 - 2.88 23.73 1 x 2 2.74 - 2.88 15.78 Kitchen ,Service Passage & Toilet 1 x 2 5.30 - 2.88 30.53 1 x 2 2.78 - 2.88 16.01 Bed Room II 1 x 2 3.89 - 2.88 22.41 1 x 2 3.05 - 2.88 17.57 (a) 264.10 b Outside plastering Long walls 1 x 2 16.48 - 4.05 133.49 Cross walls 1 x 2 6.10 - 4.05 49.37 (b) 182.86 c DEDUCTIONS MD 1 x 1 1.20 - 2.40 2.88
  • 15. Name of Owner:- Slno Description Nos Length Breadth Depth Total Qty Say m2 /m3 /kg FIRST FLOOR DETAILED ESTIMATE 0 D 1 x 4 0.90 - 2.10 7.56 D1 1 x 1 0.75 - 2.10 1.58 W 1 x 4 1.50 - 1.35 8.10 W1 1 x 2 0.90 - 1.35 2.43 V 1 x 1 0.90 - 0.60 0.54 (c) 23.09 (a+b-c) 423.87 424.00 6 Plastering the ceiling with cement mortar 1:4 (one cement and four sand) of thickness 6mm to give an even surfaces. As per item No.1(d)(a) 1 x 1 13.35 / 0.12 111.24 111.00 7 Painting the wood work two coats with superior quality ready mixed paint (Shalimar wood kote or equivalent) of specified shade over and including cost of approved ready mixed primer to give a bright and uniform shade on new work. As per item No.3 Qty 1 x 1 12.00 x 2.75 33.00 As per item No.4 Qty 1 x 1 11.00 x 2.50 27.50 60.50 61.00 8 Painting the inner walls, ceiling & outer walls, with two coats of interior emulsion and exterior emulsion respectively using the approved colourover one coat of white washing thenew work and give an even shade. As per item No.5 Qty 424.00 As per item No.6 Qty 111.00 535.00 535.00 9 Providing cutting, bending and placing in position of M.S.Bars of various sizes of reinforcement of all RCC works and binding with 16 guage annealed steel wire., etc., complete. As per item No. 1 Qty 24.00 120.00 Kg/m3 2880.00 2880.00 10 Providing and laying granite flooring
  • 16. Name of Owner:- Slno Description Nos Length Breadth Depth Total Qty Say m2 /m3 /kg FIRST FLOOR DETAILED ESTIMATE 0 with cement mortar 1:4 ( 1 cement ; 4 coarse sand) 111.00 111.00 11 Providing and laying Ceramic tiles wall tiles 8mm thick. With cement mortar 1:4 ( 1cement ;4 coarse sand) Toilet 1 x 2 2.02 - 2.10 8.48 1 x 2 1.46 - 2.10 6.13 Kitchen 1 x 1 3.05 - 0.90 2.75 1 x 1 2.78 - 0.90 2.50 19.86 20.00 12 Providing lime concrete terracing on roofs average thickness 10cms laid to fall with 25mm nominal size brick aggregate and 50% lime mortar 1:2(1 lime putty : 2 surkhi) to a thickness of 10cm including necessary tamping consolidation and finished with belgiri treatment complete. As per item no. 10 qty 111.00 13 Providing and laying bricktiles of designation 100 over mumty, roofs grouted with cement mortar 1:3 (1 cement;3 fine sand) mixed with 2% of integral water proofing compound by weight of cement over a 12mm thick layer of cement mortar 1:3 (1 cement : 3 fine sand) and finished with F.P.S brick tiles As per item no. 10 qty 111.00 14 Providing eletcrification works. LS 15 Providing and fixing Sanitary Instalations LS OWNER PREPARED BY
  • 17. Name of Owner:- Sl.No. Description Quantity Rate Unit Amount 1 Providing and laying RCC 1:2:4 (one cement two sand.& four 20mm graded stone aggregate nominal size) to the plinth beam including cost of shuttering . labour minnor tools etc., but excluding the cost of reinforcement. 24.00 4100.00 M3 98400.00 2 Brick work in cement mortar 1:6 (one cement &six sand) using best availabel country bricks in foundation and superstructure. 59.00 2300.00 M3 135700.00 3 Providing and fixing 38mm thick fully panelled door shutters single ordouble hung using best Teakwood including cost of all fixture and lockingarrangements andfixing chargesetc.,complete.including the wood work.( Teak wood ) 12.00 6100.00 M2 73200.00 4 Providing and fixing 32mm thick fully glazed window shutters usingstandard glass panes of approvedquality including the cost of allfixture and locking arrangements and fixing chargesetc.., complete.including the wood work ( Teak wood ) 11.00 5100.00 M2 56100.00 5 Plastering the both sides of the wall with cement mortar 1:5 (one cement & five sand) 15mm thick to give an even surfaces. 424.00 110.00 M2 46640.00 6 Plastering the ceiling with cement mortar 1:4 (onr cement and four sand) of thickness 6mm to give an even surfaces. 111.00 100.00 M2 11100.00 7 Painting the wood work two coats with superior quality ready mixed paint (Shalimar wood kote or equivalent) of specified shade over and including a cost of approved ready mixed primer to give a bright and uniform shade on new work. 61.00 125.00 M2 7625.00 8 Painting the inner walls, ceiling & outer walls, with two coats of interior emulsion and exterior emulsion respectively using the approved colourover one coat of 535.00 140.00 M2 74900.00 FIRST FLOOR ABSTRACT 0
  • 18. Name of Owner:- Sl.No. Description Quantity Rate Unit Amount FIRST FLOOR ABSTRACT 0 white washing thenew work and give an even shade. 9 Providing cutting, bending andplacing in position of Bars of various sizes of reinforcement of allRCC works and binding with 16 guageannealed steel wire.., etc.., complete. 2880.00 65.00 Kgs 187200.00 10 Providing and laying granite flooring with cement mortar1:4 ( 1 cement ; 4 coarse sand) 111.00 2500.00 M2 277500.00 11 Providing and laying ceramic tilesflooring ` with cement mortar1:4 ( 1 cement ; 4 coarse sand) 20.00 750.00 M2 15000.00 12 Providing lime concrete terracing onroofs average thickness 10cms laid tofall with 25mm nominal size brickaggregate and 50% lime mortar 1:2(1lime putty : 2 surkhi) to a thickness of10cm including necessary tampingconsolidation and finished with 111.00 450.00 M2 49950.00 belgiritreatment complete. 13 Providing and laying bricktiles of designation 100 over mumty, roofs grouted with cement mortar 1:3 (1cement;3 fine sand) mixed with 2% ofintegral water proofing compound byweight of cement over a 12mm thicklayer of cement mortar 1:3 (1 cement :3 fine sand) and finished with F.P.Sbrick tiles 111.00 200.00 M2 22200.00 14 Providing eletcrification works. L.S 35000.00 15 Providing and fixing Sanitary Instalations L.S 22500.00 TOTAL Rs 1113015.00 OWNER PREPARED BY