SlideShare a Scribd company logo
SHELTER FOR PILOT BALOON
Item Description Qty Unit Rate D B
SUB-STRUCTURE (ALL PROVISIONAL)
GROUNDWORK
A Removing trees from site 1.5 - 3.0m girth including,
grubbing up roots, disposal of materials, and filling voids - no.
B Clear site of bushes, scrub, undergrowth, hedges and
trees < 600mm girth. 80 m
2
EXCAVATING
C Excavating topsoil for preservation, 150mm average
depth. 80 m
2
D Excavating trenches for foundation; width > 0.50m, and
maximum depth <1.50m 30 m
3
DISPOSAL
E Removal surplus excavated materials to spoil heap
100m from site. 8 m
3
F Clear away excavated topsoil to a temporary spoil
heap 100m from site. 8 m
3
G Filling and compacting to excavations average thick-
ness > 0.25m, with selected materials arising from the
excavations. 20 m
3
H Approved well compacted laterite filling to make up
levels, average thickness < 0.25m. 20 m
3
I Hardcore ditto. 20 m3
Total Sub-structure 1
Cityscape Associates
19 Kairaba Avenue Page 1 of 7 Bill 5
SHELTER FOR PILOT BALOON
Item Description Qty Unit Rate D B
SURFACE TREATMENTS
A Levelling and compacting bottoms of excavations to
receive concrete 22 m
2
B "Dursban TC" antitermite treatment to faces and bottom
of excavations. 125 m2
2. IN - SITU CONCRETE
FOUNDATIONS
C Plain in-situ concrete grade C20 - Screened gravel in foundations
poured against earth. 4 m
3
REINFORCED
D
Reinforced in-situ concrete grade C25 - Basalt aggregate in columns of
foundations and ground beam 3 m
3
E Plain in-situ concrete grade C20 - Screened gravel in floor bed, thick-
ness 200mm, poured on unblinded hard-core. 16 m3
F
In-situ concrete grade C25 - Basalt aggregate for pad, constructed on 500mm
sand bedding and surrounding with polyeterine material or equivalent against
vibrations. 6 m3
FORMWORK
G Plain vertical formwork to sides of foundations columns. 150 m
H Ditto to sides of floor bed. 100 m
REINFORCEMENT
I 12mm ditto - pads, columns and ground beam 700 m
J Mild steel links reinforcement 6mm diameter bar 300 m
3. MASONRY
BLOCKWALLING
K 150mm thick solid sandcrete vertical blockwalling
bedded and jointed in cement mortar 1:6 mix. 66 m
2
SUNDRY ITEMS FOR BLOCKWALLING
L 1000 (gauge) polythene sheet horizontal damp-proof-
course laid in concrete, width > 225mm 78 m
2
Total Sub-structure 2
4. SURFACE FINISHES
RENDERED COATINGS
M 12mm thick cement and sand (1:3) rendering on
blockwork in one coat, width > 300mm. 28 m
2
PAINTING
N Prepare and apply one undercoat and two finishing
coats of emulsion paint on general surfaces, girth
> 300mm. 56 m
2
Total Sub-structure 3
Total Sub-structure 1
Total Sub-structure 2
Total Sub-structure 3
Total Sub-structure
Cityscape Associates
19 Kairaba Avenue Page 2 of 7 Bill 5
SHELTER FOR PILOT BALOON
Item Description Qty Unit Rate D B
SUPER - STRUCTURE
IN - SITU - CONCRETE
IN - SITU - CONCRETE
A Reinforced in-situ concrete grade C25 - Basalt aggregate in
lintels at ground floors. 1 m
3
B Reinforced in-situ concrete grade C25 - Basalt aggregate in
columns, roof slab and parapet wall. 20 m3
C Reinforced in-situ concrete grade C25 - Basalt aggregate in
roof slab beams. 1 m
3
FORMWORK FOR IN-SITU CONCRETE
D Sawn timber formwork to rectangular beams for,
lintels and roof beams. 70 m
2
Sawn timber formwork to rectangular columns, height
E to soffits < 5.00m and soffit of roof slab. 140 m2
REINFORCEMENT FOR IN SITU CONCRETE
THE FOLLOWING IN HIGH YIELD BENT RE--
INFORCEMENT BARS, AND INCLUDING HOOKS,
TYING WIRE AND SPACERS:
F 12mm diameter in columns. 220 m
G 10mm diameter in lintel. 180 m
H 12mm diameter in main beam to roof slab. 264 m
I 6mm diameter mild steel links 410 m
J 10mm diameter in suspended roof slab 1600 m
MASONRY
BLOCK - WALLING
K 150mm thick hollow sandcrete block vertical blockwork
bedded and jointed in cement mortar ( 1:4 ) mix. 200 m
2
L Louvre or breeze blocks 150mm thick sandcrete block vertical blockwork
bedded and jointed in cement mortar ( 1:4 ) mix. 7 m
2
Total Concrete work and blockwork
Cityscape Associates
19 Kairaba Avenue Page 3 of 7 Bill 5
SHELTER FOR PILOT BALOON
Item Description Qty Unit Rate D B
WINDOWS / DOORS
Metal framed glazed window.
A 1800mm x 2000mm 8 no.
B Provide and fix burglar bars to the above sliding windows item
Pressed steel glazed door framed in 40 x 40 x 2mm SHS with
C 1.5mm thick steel plate and including cylinder lock (3000 X 4000mm) 1 no.
on rollers
WATER INSTALLATION
water supply pipes to building, including excavated trenches
average depth 750mm sand bedding and pipe ducts with bends
J Polythene 25mm. 30 m
Copper pipe, 15mm water supply pipe and fittings, fixed to wall
with clips, (complete with elbows and Tees.)
K Copper Pipe. Item
Total Windows and Doors
Cityscape Associates
19 Kairaba Avenue Page 4 of 7 Bill 5
SHELTER FOR PILOT BALOON
Item Description Qty Unit Rate D B
ELECTRICAL SUPPLY / POWER LIGHTING SYSTEMS
The following in concealed conduit straight PVC pipe 19mm diameter
in chases through blockwork / concrete work and including conduit
accessories; conduit boxes and the like; fixing, bending, cutting,
screwing and jointing; determining routes; draw wires, draw cables,
and the like; and components for earth continuity. Electrical components such
as lighting, switches, sockets, bulbs etc must be watertight and meet the
applicable standards for facilities where explosive gases are in use
A Socket outlet 2P + T / 16A-240V projection explosive atmosphere (flameproof)
with 2.5mm2 cross sectional area cables. 3 no.
Lighting outlets with 1.5mm2 cross sectional area
cables.
B UPVC conduits (final circuit) Item
C Flameproof 10A single stage ignition switch (One gang one way switch) 2 no.
D Flameproof 10A single stage ignition switch (Three gang switch) 3 no.
E Flameproof luminary 1x36w fluorescent for explosive atmosphere 7 no.
G Flameproof luminary 1x36w fluoresent 4 no.
J Provide and fix Electric box for explosive atmosphere 1 no.
K Wiring to all points Item
L Independent earth rod conductor 2 no.
M Allow for testing of electrical installations item
O Change over switch and accessories to accommodate all connections 1 no.
Total Electrical
Cityscape Associates
19 Kairaba Avenue Page 5 of 7 Bill 5
SHELTER FOR PILOT BALOON
Item Description Qty Unit Rate D B
SURFACE FINISHES
RENDERING AND SCREEDING
WALLS
A 12mm cement and sand (1:3 ) rendering on block and concrete
work on all internal and external wall surfaces 400 m
2
FLOORS
B 50mm thick cement and sand ( 1:4 ) floated bed to
receive finishing. 80 m
2
PAINTING
E Prepare and apply one undercoat and two finishing coats of
emulsion paint on general surfaces. 450 m
2
F Allow for painting of metal surfaces (doors &burgular bars with one
undercoat and two finishing coats of oil paint item
Total Finishes and Decorations
Cityscape Associates
19 Kairaba Avenue Page 6 of 7 Bill 5
SHELTER FOR PILOT BALOON
Item Description Qty Unit Rate D B
ELEMENTAL COST SUMMARY
A SUBSTRUCTURE - FOUNDATION TO GROUND FLOOR SLAB
B SUPERSTRUCTURE - CONCRETEWORK AND BLOCKWORK
C DOORS AND WINDOWS
D ELECTRICAL INSTALLATIONS
E FINISHINGS AND DECORATIONS
TOTAL GENERATOR HOUSE TO SUMMARY PAGE -
Cityscape Associates
19 Kairaba Avenue Page 7 of 7 Bill 5

More Related Content

What's hot

Greenbuild 2013
Greenbuild 2013Greenbuild 2013
Greenbuild 2013
nuform
 
10.1.1.452.2904 (1)
10.1.1.452.2904 (1)10.1.1.452.2904 (1)
10.1.1.452.2904 (1)
MapVitco
 
Fusion brochure
Fusion brochureFusion brochure
Fusion brochure
dhatrireddykamineni
 
FBP_1200 Series details-1213
FBP_1200 Series details-1213FBP_1200 Series details-1213
FBP_1200 Series details-1213
Adam Barnett
 
Detailed specifications
Detailed specificationsDetailed specifications
Detailed specifications
Simran Vats
 
Jack_Lambourne - Portfolio
Jack_Lambourne - PortfolioJack_Lambourne - Portfolio
Jack_Lambourne - Portfolio
Jack Lambourne
 
Ktrimbee A-4
Ktrimbee A-4Ktrimbee A-4
Ktrimbee A-4
Kieran Trimbee
 
Presentation Design Drawing for Architectural Drawing
Presentation Design Drawing for Architectural DrawingPresentation Design Drawing for Architectural Drawing
Presentation Design Drawing for Architectural Drawing
Shane Madden
 
Plastering
PlasteringPlastering
Plastering
Shakil Ahmmad
 
01.02 aac masonry units
01.02 aac masonry units01.02 aac masonry units
01.02 aac masonry units
lota123
 
Agilia horizontal datasheet_final_2012_lo_res
Agilia horizontal datasheet_final_2012_lo_resAgilia horizontal datasheet_final_2012_lo_res
Agilia horizontal datasheet_final_2012_lo_res
gunalan7
 
Cement based building_materials_icr_aug2020
Cement based building_materials_icr_aug2020Cement based building_materials_icr_aug2020
Cement based building_materials_icr_aug2020
Dr J.D. Bapat
 
Ktrimbee A-6
Ktrimbee A-6Ktrimbee A-6
Ktrimbee A-6
Kieran Trimbee
 
CONSTRUCTION USING AAC BLOCKS
CONSTRUCTION USING AAC BLOCKSCONSTRUCTION USING AAC BLOCKS
CONSTRUCTION USING AAC BLOCKS
AbhisekS2
 
Specification for different classes of Brickworks
Specification for different classes of BrickworksSpecification for different classes of Brickworks
Specification for different classes of Brickworks
Vighnesh Rane
 
UNIT 1 INTRODUCTION | CE8022 PREFABRICATION STRUCTURES |
UNIT 1 INTRODUCTION | CE8022 PREFABRICATION STRUCTURES |UNIT 1 INTRODUCTION | CE8022 PREFABRICATION STRUCTURES |
UNIT 1 INTRODUCTION | CE8022 PREFABRICATION STRUCTURES |
Venkateswaran S
 
Item 500 - Pipe Culverts and Storm Drains
Item 500 - Pipe Culverts and Storm DrainsItem 500 - Pipe Culverts and Storm Drains
Item 500 - Pipe Culverts and Storm Drains
King Angco
 
Roadwork from CPWD specification
Roadwork from CPWD specificationRoadwork from CPWD specification
Roadwork from CPWD specification
Rajiva Gupta
 
Repair to overcome low member strength
Repair to overcome low member strength Repair to overcome low member strength
Repair to overcome low member strength
RAMPRASAD KUMAWAT
 
AAC Installation Guidelines
AAC Installation GuidelinesAAC Installation Guidelines
AAC Installation Guidelines
BENAY MUNDA
 

What's hot (20)

Greenbuild 2013
Greenbuild 2013Greenbuild 2013
Greenbuild 2013
 
10.1.1.452.2904 (1)
10.1.1.452.2904 (1)10.1.1.452.2904 (1)
10.1.1.452.2904 (1)
 
Fusion brochure
Fusion brochureFusion brochure
Fusion brochure
 
FBP_1200 Series details-1213
FBP_1200 Series details-1213FBP_1200 Series details-1213
FBP_1200 Series details-1213
 
Detailed specifications
Detailed specificationsDetailed specifications
Detailed specifications
 
Jack_Lambourne - Portfolio
Jack_Lambourne - PortfolioJack_Lambourne - Portfolio
Jack_Lambourne - Portfolio
 
Ktrimbee A-4
Ktrimbee A-4Ktrimbee A-4
Ktrimbee A-4
 
Presentation Design Drawing for Architectural Drawing
Presentation Design Drawing for Architectural DrawingPresentation Design Drawing for Architectural Drawing
Presentation Design Drawing for Architectural Drawing
 
Plastering
PlasteringPlastering
Plastering
 
01.02 aac masonry units
01.02 aac masonry units01.02 aac masonry units
01.02 aac masonry units
 
Agilia horizontal datasheet_final_2012_lo_res
Agilia horizontal datasheet_final_2012_lo_resAgilia horizontal datasheet_final_2012_lo_res
Agilia horizontal datasheet_final_2012_lo_res
 
Cement based building_materials_icr_aug2020
Cement based building_materials_icr_aug2020Cement based building_materials_icr_aug2020
Cement based building_materials_icr_aug2020
 
Ktrimbee A-6
Ktrimbee A-6Ktrimbee A-6
Ktrimbee A-6
 
CONSTRUCTION USING AAC BLOCKS
CONSTRUCTION USING AAC BLOCKSCONSTRUCTION USING AAC BLOCKS
CONSTRUCTION USING AAC BLOCKS
 
Specification for different classes of Brickworks
Specification for different classes of BrickworksSpecification for different classes of Brickworks
Specification for different classes of Brickworks
 
UNIT 1 INTRODUCTION | CE8022 PREFABRICATION STRUCTURES |
UNIT 1 INTRODUCTION | CE8022 PREFABRICATION STRUCTURES |UNIT 1 INTRODUCTION | CE8022 PREFABRICATION STRUCTURES |
UNIT 1 INTRODUCTION | CE8022 PREFABRICATION STRUCTURES |
 
Item 500 - Pipe Culverts and Storm Drains
Item 500 - Pipe Culverts and Storm DrainsItem 500 - Pipe Culverts and Storm Drains
Item 500 - Pipe Culverts and Storm Drains
 
Roadwork from CPWD specification
Roadwork from CPWD specificationRoadwork from CPWD specification
Roadwork from CPWD specification
 
Repair to overcome low member strength
Repair to overcome low member strength Repair to overcome low member strength
Repair to overcome low member strength
 
AAC Installation Guidelines
AAC Installation GuidelinesAAC Installation Guidelines
AAC Installation Guidelines
 

Similar to Bo q for shelter

section and detail sheet1
section and detail sheet1section and detail sheet1
section and detail sheet1
Jacob Dobson
 
Project1
Project1Project1
Project1
Hashim Rasool
 
12724469 wtp-cost-estimate
12724469 wtp-cost-estimate12724469 wtp-cost-estimate
12724469 wtp-cost-estimate
imaduddin91
 
Jury Presenatation.pptx
Jury Presenatation.pptxJury Presenatation.pptx
Jury Presenatation.pptx
AmokBajracharya2
 
Freelance project management residential
Freelance project management residentialFreelance project management residential
Freelance project management residential
grahamelanders
 
Freelance project management residential
Freelance project management residentialFreelance project management residential
Freelance project management residential
grahamelanders
 
Leisure Centre
Leisure CentreLeisure Centre
Leisure Centre
Edel Fox
 
E-Tender_Aanganvadi SZ 29-10-15
E-Tender_Aanganvadi SZ 29-10-15E-Tender_Aanganvadi SZ 29-10-15
E-Tender_Aanganvadi SZ 29-10-15
JITEN THAKER (M.E-CIVIL)
 
full section & details
full section & detailsfull section & details
full section & details
Jacob Dobson
 
Fence BOQ with Materials.pdf
Fence BOQ with Materials.pdfFence BOQ with Materials.pdf
Fence BOQ with Materials.pdf
Mutha Morgan
 
Support structure for hdpe
Support structure for hdpeSupport structure for hdpe
electrical sub dwg1.4.5-Layout1
electrical sub dwg1.4.5-Layout1electrical sub dwg1.4.5-Layout1
electrical sub dwg1.4.5-Layout1
Atang Maphela
 
SUBSTATION-30-06-2016-LEVEL -2 BASEMENT
SUBSTATION-30-06-2016-LEVEL -2 BASEMENTSUBSTATION-30-06-2016-LEVEL -2 BASEMENT
SUBSTATION-30-06-2016-LEVEL -2 BASEMENT
Atang Maphela
 
Final Bills of Quantity
Final Bills of QuantityFinal Bills of Quantity
Final Bills of Quantity
Arissa Loh
 
Al Jewaibyah Regulating Tank 70,000m3
Al Jewaibyah Regulating Tank  70,000m3Al Jewaibyah Regulating Tank  70,000m3
Al Jewaibyah Regulating Tank 70,000m3
Vladimir Popovic
 
Man Made River Project IV Phase - Ghadames Project - AJRT Regulating Tank 70....
Man Made River Project IV Phase - Ghadames Project - AJRT Regulating Tank 70....Man Made River Project IV Phase - Ghadames Project - AJRT Regulating Tank 70....
Man Made River Project IV Phase - Ghadames Project - AJRT Regulating Tank 70....
Vladimir Popovic
 
270 .pdf
270 .pdf270 .pdf
270 .pdf
Optional3
 
EARTHQUAKE SAFE CONSTRUCTION OF MASONRY BUILDINGS
EARTHQUAKE SAFE CONSTRUCTION OF MASONRY BUILDINGSEARTHQUAKE SAFE CONSTRUCTION OF MASONRY BUILDINGS
EARTHQUAKE SAFE CONSTRUCTION OF MASONRY BUILDINGS
Mohd Danish
 
2_2._BOQ.pdf
2_2._BOQ.pdf2_2._BOQ.pdf
2_2._BOQ.pdf
SantoshSharma687449
 
rock anchor methodology
rock anchor methodologyrock anchor methodology
rock anchor methodology
Gautam Sharma
 

Similar to Bo q for shelter (20)

section and detail sheet1
section and detail sheet1section and detail sheet1
section and detail sheet1
 
Project1
Project1Project1
Project1
 
12724469 wtp-cost-estimate
12724469 wtp-cost-estimate12724469 wtp-cost-estimate
12724469 wtp-cost-estimate
 
Jury Presenatation.pptx
Jury Presenatation.pptxJury Presenatation.pptx
Jury Presenatation.pptx
 
Freelance project management residential
Freelance project management residentialFreelance project management residential
Freelance project management residential
 
Freelance project management residential
Freelance project management residentialFreelance project management residential
Freelance project management residential
 
Leisure Centre
Leisure CentreLeisure Centre
Leisure Centre
 
E-Tender_Aanganvadi SZ 29-10-15
E-Tender_Aanganvadi SZ 29-10-15E-Tender_Aanganvadi SZ 29-10-15
E-Tender_Aanganvadi SZ 29-10-15
 
full section & details
full section & detailsfull section & details
full section & details
 
Fence BOQ with Materials.pdf
Fence BOQ with Materials.pdfFence BOQ with Materials.pdf
Fence BOQ with Materials.pdf
 
Support structure for hdpe
Support structure for hdpeSupport structure for hdpe
Support structure for hdpe
 
electrical sub dwg1.4.5-Layout1
electrical sub dwg1.4.5-Layout1electrical sub dwg1.4.5-Layout1
electrical sub dwg1.4.5-Layout1
 
SUBSTATION-30-06-2016-LEVEL -2 BASEMENT
SUBSTATION-30-06-2016-LEVEL -2 BASEMENTSUBSTATION-30-06-2016-LEVEL -2 BASEMENT
SUBSTATION-30-06-2016-LEVEL -2 BASEMENT
 
Final Bills of Quantity
Final Bills of QuantityFinal Bills of Quantity
Final Bills of Quantity
 
Al Jewaibyah Regulating Tank 70,000m3
Al Jewaibyah Regulating Tank  70,000m3Al Jewaibyah Regulating Tank  70,000m3
Al Jewaibyah Regulating Tank 70,000m3
 
Man Made River Project IV Phase - Ghadames Project - AJRT Regulating Tank 70....
Man Made River Project IV Phase - Ghadames Project - AJRT Regulating Tank 70....Man Made River Project IV Phase - Ghadames Project - AJRT Regulating Tank 70....
Man Made River Project IV Phase - Ghadames Project - AJRT Regulating Tank 70....
 
270 .pdf
270 .pdf270 .pdf
270 .pdf
 
EARTHQUAKE SAFE CONSTRUCTION OF MASONRY BUILDINGS
EARTHQUAKE SAFE CONSTRUCTION OF MASONRY BUILDINGSEARTHQUAKE SAFE CONSTRUCTION OF MASONRY BUILDINGS
EARTHQUAKE SAFE CONSTRUCTION OF MASONRY BUILDINGS
 
2_2._BOQ.pdf
2_2._BOQ.pdf2_2._BOQ.pdf
2_2._BOQ.pdf
 
rock anchor methodology
rock anchor methodologyrock anchor methodology
rock anchor methodology
 

Recently uploaded

Accident detection system project report.pdf
Accident detection system project report.pdfAccident detection system project report.pdf
Accident detection system project report.pdf
Kamal Acharya
 
Introduction to Computer Networks & OSI MODEL.ppt
Introduction to Computer Networks & OSI MODEL.pptIntroduction to Computer Networks & OSI MODEL.ppt
Introduction to Computer Networks & OSI MODEL.ppt
Dwarkadas J Sanghvi College of Engineering
 
一比一原版(CalArts毕业证)加利福尼亚艺术学院毕业证如何办理
一比一原版(CalArts毕业证)加利福尼亚艺术学院毕业证如何办理一比一原版(CalArts毕业证)加利福尼亚艺术学院毕业证如何办理
一比一原版(CalArts毕业证)加利福尼亚艺术学院毕业证如何办理
ecqow
 
An Introduction to the Compiler Designss
An Introduction to the Compiler DesignssAn Introduction to the Compiler Designss
An Introduction to the Compiler Designss
ElakkiaU
 
SCALING OF MOS CIRCUITS m .pptx
SCALING OF MOS CIRCUITS m                 .pptxSCALING OF MOS CIRCUITS m                 .pptx
SCALING OF MOS CIRCUITS m .pptx
harshapolam10
 
一比一原版(osu毕业证书)美国俄勒冈州立大学毕业证如何办理
一比一原版(osu毕业证书)美国俄勒冈州立大学毕业证如何办理一比一原版(osu毕业证书)美国俄勒冈州立大学毕业证如何办理
一比一原版(osu毕业证书)美国俄勒冈州立大学毕业证如何办理
upoux
 
Pressure Relief valve used in flow line to release the over pressure at our d...
Pressure Relief valve used in flow line to release the over pressure at our d...Pressure Relief valve used in flow line to release the over pressure at our d...
Pressure Relief valve used in flow line to release the over pressure at our d...
cannyengineerings
 
AI + Data Community Tour - Build the Next Generation of Apps with the Einstei...
AI + Data Community Tour - Build the Next Generation of Apps with the Einstei...AI + Data Community Tour - Build the Next Generation of Apps with the Einstei...
AI + Data Community Tour - Build the Next Generation of Apps with the Einstei...
Paris Salesforce Developer Group
 
Software Engineering and Project Management - Introduction, Modeling Concepts...
Software Engineering and Project Management - Introduction, Modeling Concepts...Software Engineering and Project Management - Introduction, Modeling Concepts...
Software Engineering and Project Management - Introduction, Modeling Concepts...
Prakhyath Rai
 
Call For Paper -3rd International Conference on Artificial Intelligence Advan...
Call For Paper -3rd International Conference on Artificial Intelligence Advan...Call For Paper -3rd International Conference on Artificial Intelligence Advan...
Call For Paper -3rd International Conference on Artificial Intelligence Advan...
ijseajournal
 
2. protection of river banks and bed erosion protection works.ppt
2. protection of river banks and bed erosion protection works.ppt2. protection of river banks and bed erosion protection works.ppt
2. protection of river banks and bed erosion protection works.ppt
abdatawakjira
 
SENTIMENT ANALYSIS ON PPT AND Project template_.pptx
SENTIMENT ANALYSIS ON PPT AND Project template_.pptxSENTIMENT ANALYSIS ON PPT AND Project template_.pptx
SENTIMENT ANALYSIS ON PPT AND Project template_.pptx
b0754201
 
Object Oriented Analysis and Design - OOAD
Object Oriented Analysis and Design - OOADObject Oriented Analysis and Design - OOAD
Object Oriented Analysis and Design - OOAD
PreethaV16
 
4. Mosca vol I -Fisica-Tipler-5ta-Edicion-Vol-1.pdf
4. Mosca vol I -Fisica-Tipler-5ta-Edicion-Vol-1.pdf4. Mosca vol I -Fisica-Tipler-5ta-Edicion-Vol-1.pdf
4. Mosca vol I -Fisica-Tipler-5ta-Edicion-Vol-1.pdf
Gino153088
 
原版制作(Humboldt毕业证书)柏林大学毕业证学位证一模一样
原版制作(Humboldt毕业证书)柏林大学毕业证学位证一模一样原版制作(Humboldt毕业证书)柏林大学毕业证学位证一模一样
原版制作(Humboldt毕业证书)柏林大学毕业证学位证一模一样
ydzowc
 
P5 Working Drawings.pdf floor plan, civil
P5 Working Drawings.pdf floor plan, civilP5 Working Drawings.pdf floor plan, civil
P5 Working Drawings.pdf floor plan, civil
AnasAhmadNoor
 
Data Driven Maintenance | UReason Webinar
Data Driven Maintenance | UReason WebinarData Driven Maintenance | UReason Webinar
Data Driven Maintenance | UReason Webinar
UReason
 
一比一原版(爱大毕业证书)爱荷华大学毕业证如何办理
一比一原版(爱大毕业证书)爱荷华大学毕业证如何办理一比一原版(爱大毕业证书)爱荷华大学毕业证如何办理
一比一原版(爱大毕业证书)爱荷华大学毕业证如何办理
nedcocy
 
DEEP LEARNING FOR SMART GRID INTRUSION DETECTION: A HYBRID CNN-LSTM-BASED MODEL
DEEP LEARNING FOR SMART GRID INTRUSION DETECTION: A HYBRID CNN-LSTM-BASED MODELDEEP LEARNING FOR SMART GRID INTRUSION DETECTION: A HYBRID CNN-LSTM-BASED MODEL
DEEP LEARNING FOR SMART GRID INTRUSION DETECTION: A HYBRID CNN-LSTM-BASED MODEL
ijaia
 
LLM Fine Tuning with QLoRA Cassandra Lunch 4, presented by Anant
LLM Fine Tuning with QLoRA Cassandra Lunch 4, presented by AnantLLM Fine Tuning with QLoRA Cassandra Lunch 4, presented by Anant
LLM Fine Tuning with QLoRA Cassandra Lunch 4, presented by Anant
Anant Corporation
 

Recently uploaded (20)

Accident detection system project report.pdf
Accident detection system project report.pdfAccident detection system project report.pdf
Accident detection system project report.pdf
 
Introduction to Computer Networks & OSI MODEL.ppt
Introduction to Computer Networks & OSI MODEL.pptIntroduction to Computer Networks & OSI MODEL.ppt
Introduction to Computer Networks & OSI MODEL.ppt
 
一比一原版(CalArts毕业证)加利福尼亚艺术学院毕业证如何办理
一比一原版(CalArts毕业证)加利福尼亚艺术学院毕业证如何办理一比一原版(CalArts毕业证)加利福尼亚艺术学院毕业证如何办理
一比一原版(CalArts毕业证)加利福尼亚艺术学院毕业证如何办理
 
An Introduction to the Compiler Designss
An Introduction to the Compiler DesignssAn Introduction to the Compiler Designss
An Introduction to the Compiler Designss
 
SCALING OF MOS CIRCUITS m .pptx
SCALING OF MOS CIRCUITS m                 .pptxSCALING OF MOS CIRCUITS m                 .pptx
SCALING OF MOS CIRCUITS m .pptx
 
一比一原版(osu毕业证书)美国俄勒冈州立大学毕业证如何办理
一比一原版(osu毕业证书)美国俄勒冈州立大学毕业证如何办理一比一原版(osu毕业证书)美国俄勒冈州立大学毕业证如何办理
一比一原版(osu毕业证书)美国俄勒冈州立大学毕业证如何办理
 
Pressure Relief valve used in flow line to release the over pressure at our d...
Pressure Relief valve used in flow line to release the over pressure at our d...Pressure Relief valve used in flow line to release the over pressure at our d...
Pressure Relief valve used in flow line to release the over pressure at our d...
 
AI + Data Community Tour - Build the Next Generation of Apps with the Einstei...
AI + Data Community Tour - Build the Next Generation of Apps with the Einstei...AI + Data Community Tour - Build the Next Generation of Apps with the Einstei...
AI + Data Community Tour - Build the Next Generation of Apps with the Einstei...
 
Software Engineering and Project Management - Introduction, Modeling Concepts...
Software Engineering and Project Management - Introduction, Modeling Concepts...Software Engineering and Project Management - Introduction, Modeling Concepts...
Software Engineering and Project Management - Introduction, Modeling Concepts...
 
Call For Paper -3rd International Conference on Artificial Intelligence Advan...
Call For Paper -3rd International Conference on Artificial Intelligence Advan...Call For Paper -3rd International Conference on Artificial Intelligence Advan...
Call For Paper -3rd International Conference on Artificial Intelligence Advan...
 
2. protection of river banks and bed erosion protection works.ppt
2. protection of river banks and bed erosion protection works.ppt2. protection of river banks and bed erosion protection works.ppt
2. protection of river banks and bed erosion protection works.ppt
 
SENTIMENT ANALYSIS ON PPT AND Project template_.pptx
SENTIMENT ANALYSIS ON PPT AND Project template_.pptxSENTIMENT ANALYSIS ON PPT AND Project template_.pptx
SENTIMENT ANALYSIS ON PPT AND Project template_.pptx
 
Object Oriented Analysis and Design - OOAD
Object Oriented Analysis and Design - OOADObject Oriented Analysis and Design - OOAD
Object Oriented Analysis and Design - OOAD
 
4. Mosca vol I -Fisica-Tipler-5ta-Edicion-Vol-1.pdf
4. Mosca vol I -Fisica-Tipler-5ta-Edicion-Vol-1.pdf4. Mosca vol I -Fisica-Tipler-5ta-Edicion-Vol-1.pdf
4. Mosca vol I -Fisica-Tipler-5ta-Edicion-Vol-1.pdf
 
原版制作(Humboldt毕业证书)柏林大学毕业证学位证一模一样
原版制作(Humboldt毕业证书)柏林大学毕业证学位证一模一样原版制作(Humboldt毕业证书)柏林大学毕业证学位证一模一样
原版制作(Humboldt毕业证书)柏林大学毕业证学位证一模一样
 
P5 Working Drawings.pdf floor plan, civil
P5 Working Drawings.pdf floor plan, civilP5 Working Drawings.pdf floor plan, civil
P5 Working Drawings.pdf floor plan, civil
 
Data Driven Maintenance | UReason Webinar
Data Driven Maintenance | UReason WebinarData Driven Maintenance | UReason Webinar
Data Driven Maintenance | UReason Webinar
 
一比一原版(爱大毕业证书)爱荷华大学毕业证如何办理
一比一原版(爱大毕业证书)爱荷华大学毕业证如何办理一比一原版(爱大毕业证书)爱荷华大学毕业证如何办理
一比一原版(爱大毕业证书)爱荷华大学毕业证如何办理
 
DEEP LEARNING FOR SMART GRID INTRUSION DETECTION: A HYBRID CNN-LSTM-BASED MODEL
DEEP LEARNING FOR SMART GRID INTRUSION DETECTION: A HYBRID CNN-LSTM-BASED MODELDEEP LEARNING FOR SMART GRID INTRUSION DETECTION: A HYBRID CNN-LSTM-BASED MODEL
DEEP LEARNING FOR SMART GRID INTRUSION DETECTION: A HYBRID CNN-LSTM-BASED MODEL
 
LLM Fine Tuning with QLoRA Cassandra Lunch 4, presented by Anant
LLM Fine Tuning with QLoRA Cassandra Lunch 4, presented by AnantLLM Fine Tuning with QLoRA Cassandra Lunch 4, presented by Anant
LLM Fine Tuning with QLoRA Cassandra Lunch 4, presented by Anant
 

Bo q for shelter

  • 1. SHELTER FOR PILOT BALOON Item Description Qty Unit Rate D B SUB-STRUCTURE (ALL PROVISIONAL) GROUNDWORK A Removing trees from site 1.5 - 3.0m girth including, grubbing up roots, disposal of materials, and filling voids - no. B Clear site of bushes, scrub, undergrowth, hedges and trees < 600mm girth. 80 m 2 EXCAVATING C Excavating topsoil for preservation, 150mm average depth. 80 m 2 D Excavating trenches for foundation; width > 0.50m, and maximum depth <1.50m 30 m 3 DISPOSAL E Removal surplus excavated materials to spoil heap 100m from site. 8 m 3 F Clear away excavated topsoil to a temporary spoil heap 100m from site. 8 m 3 G Filling and compacting to excavations average thick- ness > 0.25m, with selected materials arising from the excavations. 20 m 3 H Approved well compacted laterite filling to make up levels, average thickness < 0.25m. 20 m 3 I Hardcore ditto. 20 m3 Total Sub-structure 1 Cityscape Associates 19 Kairaba Avenue Page 1 of 7 Bill 5
  • 2. SHELTER FOR PILOT BALOON Item Description Qty Unit Rate D B SURFACE TREATMENTS A Levelling and compacting bottoms of excavations to receive concrete 22 m 2 B "Dursban TC" antitermite treatment to faces and bottom of excavations. 125 m2 2. IN - SITU CONCRETE FOUNDATIONS C Plain in-situ concrete grade C20 - Screened gravel in foundations poured against earth. 4 m 3 REINFORCED D Reinforced in-situ concrete grade C25 - Basalt aggregate in columns of foundations and ground beam 3 m 3 E Plain in-situ concrete grade C20 - Screened gravel in floor bed, thick- ness 200mm, poured on unblinded hard-core. 16 m3 F In-situ concrete grade C25 - Basalt aggregate for pad, constructed on 500mm sand bedding and surrounding with polyeterine material or equivalent against vibrations. 6 m3 FORMWORK G Plain vertical formwork to sides of foundations columns. 150 m H Ditto to sides of floor bed. 100 m REINFORCEMENT I 12mm ditto - pads, columns and ground beam 700 m J Mild steel links reinforcement 6mm diameter bar 300 m 3. MASONRY BLOCKWALLING K 150mm thick solid sandcrete vertical blockwalling bedded and jointed in cement mortar 1:6 mix. 66 m 2 SUNDRY ITEMS FOR BLOCKWALLING L 1000 (gauge) polythene sheet horizontal damp-proof- course laid in concrete, width > 225mm 78 m 2 Total Sub-structure 2 4. SURFACE FINISHES RENDERED COATINGS M 12mm thick cement and sand (1:3) rendering on blockwork in one coat, width > 300mm. 28 m 2 PAINTING N Prepare and apply one undercoat and two finishing coats of emulsion paint on general surfaces, girth > 300mm. 56 m 2 Total Sub-structure 3 Total Sub-structure 1 Total Sub-structure 2 Total Sub-structure 3 Total Sub-structure Cityscape Associates 19 Kairaba Avenue Page 2 of 7 Bill 5
  • 3. SHELTER FOR PILOT BALOON Item Description Qty Unit Rate D B SUPER - STRUCTURE IN - SITU - CONCRETE IN - SITU - CONCRETE A Reinforced in-situ concrete grade C25 - Basalt aggregate in lintels at ground floors. 1 m 3 B Reinforced in-situ concrete grade C25 - Basalt aggregate in columns, roof slab and parapet wall. 20 m3 C Reinforced in-situ concrete grade C25 - Basalt aggregate in roof slab beams. 1 m 3 FORMWORK FOR IN-SITU CONCRETE D Sawn timber formwork to rectangular beams for, lintels and roof beams. 70 m 2 Sawn timber formwork to rectangular columns, height E to soffits < 5.00m and soffit of roof slab. 140 m2 REINFORCEMENT FOR IN SITU CONCRETE THE FOLLOWING IN HIGH YIELD BENT RE-- INFORCEMENT BARS, AND INCLUDING HOOKS, TYING WIRE AND SPACERS: F 12mm diameter in columns. 220 m G 10mm diameter in lintel. 180 m H 12mm diameter in main beam to roof slab. 264 m I 6mm diameter mild steel links 410 m J 10mm diameter in suspended roof slab 1600 m MASONRY BLOCK - WALLING K 150mm thick hollow sandcrete block vertical blockwork bedded and jointed in cement mortar ( 1:4 ) mix. 200 m 2 L Louvre or breeze blocks 150mm thick sandcrete block vertical blockwork bedded and jointed in cement mortar ( 1:4 ) mix. 7 m 2 Total Concrete work and blockwork Cityscape Associates 19 Kairaba Avenue Page 3 of 7 Bill 5
  • 4. SHELTER FOR PILOT BALOON Item Description Qty Unit Rate D B WINDOWS / DOORS Metal framed glazed window. A 1800mm x 2000mm 8 no. B Provide and fix burglar bars to the above sliding windows item Pressed steel glazed door framed in 40 x 40 x 2mm SHS with C 1.5mm thick steel plate and including cylinder lock (3000 X 4000mm) 1 no. on rollers WATER INSTALLATION water supply pipes to building, including excavated trenches average depth 750mm sand bedding and pipe ducts with bends J Polythene 25mm. 30 m Copper pipe, 15mm water supply pipe and fittings, fixed to wall with clips, (complete with elbows and Tees.) K Copper Pipe. Item Total Windows and Doors Cityscape Associates 19 Kairaba Avenue Page 4 of 7 Bill 5
  • 5. SHELTER FOR PILOT BALOON Item Description Qty Unit Rate D B ELECTRICAL SUPPLY / POWER LIGHTING SYSTEMS The following in concealed conduit straight PVC pipe 19mm diameter in chases through blockwork / concrete work and including conduit accessories; conduit boxes and the like; fixing, bending, cutting, screwing and jointing; determining routes; draw wires, draw cables, and the like; and components for earth continuity. Electrical components such as lighting, switches, sockets, bulbs etc must be watertight and meet the applicable standards for facilities where explosive gases are in use A Socket outlet 2P + T / 16A-240V projection explosive atmosphere (flameproof) with 2.5mm2 cross sectional area cables. 3 no. Lighting outlets with 1.5mm2 cross sectional area cables. B UPVC conduits (final circuit) Item C Flameproof 10A single stage ignition switch (One gang one way switch) 2 no. D Flameproof 10A single stage ignition switch (Three gang switch) 3 no. E Flameproof luminary 1x36w fluorescent for explosive atmosphere 7 no. G Flameproof luminary 1x36w fluoresent 4 no. J Provide and fix Electric box for explosive atmosphere 1 no. K Wiring to all points Item L Independent earth rod conductor 2 no. M Allow for testing of electrical installations item O Change over switch and accessories to accommodate all connections 1 no. Total Electrical Cityscape Associates 19 Kairaba Avenue Page 5 of 7 Bill 5
  • 6. SHELTER FOR PILOT BALOON Item Description Qty Unit Rate D B SURFACE FINISHES RENDERING AND SCREEDING WALLS A 12mm cement and sand (1:3 ) rendering on block and concrete work on all internal and external wall surfaces 400 m 2 FLOORS B 50mm thick cement and sand ( 1:4 ) floated bed to receive finishing. 80 m 2 PAINTING E Prepare and apply one undercoat and two finishing coats of emulsion paint on general surfaces. 450 m 2 F Allow for painting of metal surfaces (doors &burgular bars with one undercoat and two finishing coats of oil paint item Total Finishes and Decorations Cityscape Associates 19 Kairaba Avenue Page 6 of 7 Bill 5
  • 7. SHELTER FOR PILOT BALOON Item Description Qty Unit Rate D B ELEMENTAL COST SUMMARY A SUBSTRUCTURE - FOUNDATION TO GROUND FLOOR SLAB B SUPERSTRUCTURE - CONCRETEWORK AND BLOCKWORK C DOORS AND WINDOWS D ELECTRICAL INSTALLATIONS E FINISHINGS AND DECORATIONS TOTAL GENERATOR HOUSE TO SUMMARY PAGE - Cityscape Associates 19 Kairaba Avenue Page 7 of 7 Bill 5