SlideShare a Scribd company logo
QTY UNIT RATE AMOUNT UNIT
BILL NR 1: FENCE AND BOUNDARY WALL
ELEMENT NR. 1: SUBSTRUCTURE
SITE CLEARANCE
Removing bushes, shrubs, trees, etc.
Clearing the site; grubbing up roots, bushes, shrub, undergrowth
or the like; small trees not exceeding 600 mm girth
1519 SM 200 303,800.00
EXCAVATION
Surfaces
Average 150 mm deep; to remove vegetable soil 1519 SM 200 303,800.00
Trenches; to receive foundations; starting from reduced level
Not exceeding 1.5 m deep 81 CM 5,000 405,000.00
Pits; to receive foundations; starting from reduced level
Not exceeding 1.5m deep 21 CM 5,000 105,000.00
BACKFILL AND DISPOSAL
Approved imported granular materials
Backfilling into foundations; depositing and compacting in layers
maximum 200 mm thick 58 CM 5,000 290,000.00
Earth filling; select sand imported material; 200 mm thick;
depositing and compacting in layers to make up levels 0 CM 18,500 0.00 0 CM
1,407,600.00 0.00
LABOUR COST
QUANTITY
ITEM
DESCRIPTION STD BOQ ESTIMATES MATERIAL COST ESTIMATES
Carried Forward
QTY UNIT RATE AMOUNT UNIT LABOUR COST
QUANTITY
ITEM
DESCRIPTION STD BOQ ESTIMATES MATERIAL COST ESTIMATES
1,407,600.00 0.00
Surplus excavated material
Removing from site 44 CM 14,500 638,000.00
PLANKING AND STRUTTING
Generally
To sides of excavations 1 Item 200,000.00
DISPOSAL OF WATER
Generally
Keeping excavations free from all water including spring and
running water 1 Item 200,000.00
Add: Labour earthworks 1,838,000
2,445,600.00 1,838,000.00
Brought Forward
Carried Forward
QTY UNIT RATE AMOUNT UNIT LABOUR COST
QUANTITY
ITEM
DESCRIPTION STD BOQ ESTIMATES MATERIAL COST ESTIMATES
2,445,600.00 1,838,000.00
INSITU CONCRETE; REINFORCED
Normal; grade C20; vibrated
Column bases irrespective of thickness 7 CM 280,000 1,960,000.00
Column; irrespective of thickness 1 CM 280,000 280,000.00
Beds; 100 mm thick 0 SM 28,000 0.00
Ground beams 7 CM 280,000 1,960,000.00
Steps, staircases or strings 0 CM 280,000 0.00
Walls; 230mm thick 0 CM 280,000 0.00
Raft foundation; 500mm thick 0 CM 280,000 0.00
Irrespective of item:
a) Cement (42.R); 50kg 99 BGS
b) Sand 6 CM
c)Aggregates 13 CM
Add: Labour casting concrete 504,000
6,645,600.00 2,342,000.00
Brought Forward
Carried Forward
QTY UNIT RATE AMOUNT UNIT LABOUR COST
QUANTITY
ITEM
DESCRIPTION STD BOQ ESTIMATES MATERIAL COST ESTIMATES
6,645,600.00 2,342,000.00
REINFORCEMENT
Bars; high yield steel; cold worked; B.S 4449
12mm diameter 341 KG 3,200 1,091,200.00 33 PCS
16mm diameter 0 KG 3,200 0.00 0 PCS
8mm diameter 173 KG 3,200 553,600.00 37 PCS
EO; Binding Wire; 30kg 0.26 RLS
Add: Labour for reinforcements 216,000
FORMWORK TO INSITU CONCRETE
Formwork generally
Sides; vertical or battering in:
Foundations in trenches irrespective of thickness 0 SM 20,000 0.00
Column bases irrespective of thickness 31 SM 20,000 620,000.00
Column; irrespective of thickness 2 SM 20,000 40,000.00
Ground beams 31 SM 20,000 620,000.00
Walls; 230mm thick 0 SM 20,000 0.00
Raft foundation; 500mm thick 0 SM 20,000 0.00
Steps; strings and sides 0 SM 20,000 0.00
Edges in:
Beds 75 to 150 mm wide 0 LM 2,000 0.00
Risers of steps or staircases 0 LM 3,000 0.00
9,570,400.00 2,558,000.00
Brought Forward
Carried Forward
QTY UNIT RATE AMOUNT UNIT LABOUR COST
QUANTITY
ITEM
DESCRIPTION STD BOQ ESTIMATES MATERIAL COST ESTIMATES
9,570,400.00 2,558,000.00
Formwork generally:
a) Marine plywood boards; 12mm thk 22 PCS
b) Timber Props 84 PCS
c) Iron Nails 13 KG
d) Concrete Nails 3 KG
e) Oils 2 LTR
Add: Labour for formworks 308,000
BLOCKWORK
Concrete blocks; B.S. 6073; type A; 7.0 N per square millimetre;
solid; in cement mortar (1:4)
Walls; 230mm thick 124 SM 32,000 3,968,000.00
a) Solid Concrete Block 1736 NR
b) Cement (42.R); 50kg 11 BGS
c) Sand 2 CM
DAMP PROOF COURSES
B.S. 8102; bitumen hessian base; 150 mm laps
Horizontal 230mm wide 116 LM 2,000 231,000.00 116 LM
Add: Labour for walling 730,000
13,769,400.00 3,596,000.00
Brought Forward
Carried Forward
QTY UNIT RATE AMOUNT UNIT LABOUR COST
QUANTITY
ITEM
DESCRIPTION STD BOQ ESTIMATES MATERIAL COST ESTIMATES
13,769,400.00 3,596,000.00
WALLING SUNDRIES (PROVISIONAL)
INSITU FINISHINGS
Render; cement and sand (1:4); wood floated; external
15 mm one coat work; to concrete or block work base; generally
to walls 70 SM 8,000 560,000.00
a) Cement (42.R); 50kg 7 BGS
c) Sand 1 CM
Add: Labour for plaster 385,000
Two coats bituminous based paint
Wood floated rendered surfaces; external walls over 300 mm wide
70 SM 8,000 560,000.00 4 TIN
Add: Labour for painting 385,000
CONCRETE WORK SUNDRIES
Generally
Expansion joints in concrete; 25 mm thick; over 300 mm wide;
filling with styrofoam expansion joint materials 0 LM 32,000 0.00
SUMMARY
Total Labour Cost Allowed by Contractor
14,889,400.00 4,366,000.00
Brought Forward
TOTAL ELEMENT NR. 1: SUBSTRUCTURE CARRIED TO BILL SUMMARY
QTY UNIT RATE AMOUNT UNIT
ELEMENT NR. 2: FRAME AND WALLING
INTERNAL WALLING
Concrete blocks; B.S 6073; type A; 7 N per square millimetre;
solid; in cement mortar (1:4)
Walls; 150 mm thick 424 SM 28,000 11,872,000.00
a) Solid Concrete Block 3816 NR
b) Cement (42.R); 50kg 20 BGS
c) Sand 3 CM
Add: Labour for walling 1,603,000
CONCRETE COPING
Copings; finish fair on top one side and part soffit; rebated
once; weathered once; finished; including fabric BRC Mesh,
and necessary ancillaries
100 x 200mm wide 116 LM 10,000 1,155,000.00
a) Cement (42.R); 50kg 15 BGS
b) Sand 0.10 CM
c)Aggregates 0.20 CM
d) BRC Fabric Mesh 0.4 RLS
e) Timber Formwork 32 PCS
13,027,000.00 1,603,000.00
LABOUR COST
QUANTITY
Carried Forward
ITEM DESCRIPTION
STD BOQ ESTIMATES MATERIAL COST ESTIMATES
13,027,000.00 1,603,000.00
INSITU CONCRETE; REINFORCED
Normal; grade C20; vibrated
Column; irrespective of thickness 1 CM 280,000 280,000.00
Irrespective of item:
a) Cement (42.R); 50kg 9 BGS
b) Sand 0 CM
c)Aggregates 1 CM
Add: Labour casting concrete 112,000
REINFORCEMENT
Bars; high yield steel; cold worked; B.S 4449
12mm diameter 26 KG 3,200 83,200.00 3 PCS
16mm diameter 0 KG 3,200 0.00 0 PCS
8mm diameter 16 KG 3,200 51,200.00 3 PCS
EO; Binding Wire; 30kg 0.02 RLS
Add: Labour for reinforcements 18,000
FORMWORK TO INSITU CONCRETE
Formwork generally
Sides; vertical or battering in:
Column; irrespective of thickness 6 SM 20,000 120,000.00
Formwork generally:
a) Marine plywood boards; 12mm thk 2 PCS
b) Timber Props 5 PCS
c) Iron Nails 1 KG
d) Concrete Nails 0 KG
e) Oils 0 LTR
Add: Labour for formworks 140,000
SUMMARY
Total Labour Cost Allowed by Contractor
13,561,400.00 1,873,000.00
TOTAL ELEMENT NR. 2: WALLING CARRIED TO BILL SUMMARY
Brought Forward
QTY UNIT RATE AMOUNT UNIT
ELEMENT NR. 3: FINISHING
Insitu Finishes
Render; 12 mm first coat of cement and sand (1:5) mixed with
Morcemcril Siloxane Synthetic water proofing coat; 3 mm skimming
coat; steel trowelled; externally
15 mm two coats work; walls 707 SM 8,000 5,656,000.00
a) Cement (42.R); 50kg 60 BGS
b) Sand 7 CM
c) Moyashield 20Ltr 18 BKT
d) White Cement; 40kg 54 BGS
Add: Labour for plaster 3,889,000
FITTINGS
Entrance Metal Gates
Allow for supply and fix of main entrance metal gates;size 5000 x
1800mm high, double leaf (1Nr); complete with associated frame and
iron mongeries; grilled and welded to pattern as approved by the
Architect Item 2,500,000 2,500,000.00
Ditto; metal gates;size 1500 x 1800mm high, single leaf (1Nr) Item 1,000,000 1,000,000.00
SUMMARY
Total Labour Cost Allowed by Contractor
TOTAL ELEMENT NR. 3: FINISHING CARRIED TO BILL SUMMARY 9,156,000.00
LABOUR COST
QUANTITY
ITEM DESCRIPTION
STD BOQ ESTIMATES MATERIAL COST ESTIMATES
QTY UNIT RATE AMOUNT UNIT
ELEMENT NR. 4: PAINTING AND DECORATIONS
Wall Painting
One coat of PLASCON textured paint with two coats of pigment
coat on platered surface; external
Walls over 300mm wide 707 SM 8,000 5,656,000.00 43 BKT
Add: Labour for painting 3,889,000
SUMMARY
Total Labour Cost Allowed by Contractor
5,656,000.00
ITEM DESCRIPTION
STD BOQ ESTIMATES MATERIAL COST ESTIMATES
LABOUR COST
QUANTITY
TOTAL ELEMENT NR 4: PAINTING AND DECORATION CARRIED TO BILL SUMMARY
ITEM DESCRIPTION AMOUNT (TZS)
BILLS SUMMARY
ELEMENT NR. 1: SUBSTRUCTURE 14,889,400.00
ELEMENT NR. 2: FRAME AND WALLING 13,561,400.00
ELEMENT NR. 3: FINISHING 9,156,000.00
ELEMENT NR. 4: PAINTING AND DECORATIONS 5,656,000.00
SUB-TOTAL 43,262,800.00
TOTAL 43,262,800.00
1/SUM/11

More Related Content

What's hot

Boq sample
Boq sampleBoq sample
Construction process
Construction processConstruction process
Construction process
Mazen Al-Qadi
 
Assignment - FIDIC Contract
Assignment - FIDIC ContractAssignment - FIDIC Contract
Assignment - FIDIC Contract
Kai Yun Pang
 
Eca presentation-compile
Eca presentation-compileEca presentation-compile
Eca presentation-compile
Timun Loh
 
Stakeholder management In Construction Industry
Stakeholder management In  Construction IndustryStakeholder management In  Construction Industry
Stakeholder management In Construction Industry
Girish Singh
 
Earthwork and excavation
Earthwork  and  excavationEarthwork  and  excavation
Earthwork and excavation
Krishna Spoorthy Rachamalla
 
Roadwork from CPWD specification
Roadwork from CPWD specificationRoadwork from CPWD specification
Roadwork from CPWD specification
Rajiva Gupta
 
Detailed specifications
Detailed specificationsDetailed specifications
Detailed specifications
Simran Vats
 
Unit-4_Specification
Unit-4_SpecificationUnit-4_Specification
Unit-4_Specification
Akash Bharti
 
Construction
ConstructionConstruction
Construction
shivam tomar
 
Estimating part 2
Estimating part 2Estimating part 2
Estimating part 2
ArunRavi43
 
Tendering documentation
Tendering documentationTendering documentation
Tendering documentation
nipuna_bopage
 
Project Report on Concrete Mix Design of Grade M35
Project Report on Concrete Mix Design of Grade M35Project Report on Concrete Mix Design of Grade M35
Project Report on Concrete Mix Design of Grade M35
Gyan Prakash
 
Types of tender and their processing.
Types of tender and their processing.Types of tender and their processing.
Types of tender and their processing.
Abhishek kumar maurya
 
training report on commercial building
training report on commercial buildingtraining report on commercial building
training report on commercial building
Sumit Saini
 
Summer Internship Report of Civil Engineering in Construction Site
Summer Internship Report of Civil Engineering in Construction SiteSummer Internship Report of Civil Engineering in Construction Site
Summer Internship Report of Civil Engineering in Construction Site
RAVI KUMAR
 
Block estimate.ppt (1)
Block estimate.ppt (1)Block estimate.ppt (1)
Block estimate.ppt (1)
kumud singh
 
Boq piling works
Boq   piling worksBoq   piling works
Boq piling works
Rohaidah Aida
 
BUILDING MATERIALS 1
BUILDING MATERIALS 1BUILDING MATERIALS 1
BUILDING MATERIALS 1
Abhishek Mewada
 
DD STAGE COST ESTIMATE SECTION 1 (J102) (1)
DD STAGE COST ESTIMATE SECTION 1 (J102) (1)DD STAGE COST ESTIMATE SECTION 1 (J102) (1)
DD STAGE COST ESTIMATE SECTION 1 (J102) (1)
Gayan Kalpitha Perera
 

What's hot (20)

Boq sample
Boq sampleBoq sample
Boq sample
 
Construction process
Construction processConstruction process
Construction process
 
Assignment - FIDIC Contract
Assignment - FIDIC ContractAssignment - FIDIC Contract
Assignment - FIDIC Contract
 
Eca presentation-compile
Eca presentation-compileEca presentation-compile
Eca presentation-compile
 
Stakeholder management In Construction Industry
Stakeholder management In  Construction IndustryStakeholder management In  Construction Industry
Stakeholder management In Construction Industry
 
Earthwork and excavation
Earthwork  and  excavationEarthwork  and  excavation
Earthwork and excavation
 
Roadwork from CPWD specification
Roadwork from CPWD specificationRoadwork from CPWD specification
Roadwork from CPWD specification
 
Detailed specifications
Detailed specificationsDetailed specifications
Detailed specifications
 
Unit-4_Specification
Unit-4_SpecificationUnit-4_Specification
Unit-4_Specification
 
Construction
ConstructionConstruction
Construction
 
Estimating part 2
Estimating part 2Estimating part 2
Estimating part 2
 
Tendering documentation
Tendering documentationTendering documentation
Tendering documentation
 
Project Report on Concrete Mix Design of Grade M35
Project Report on Concrete Mix Design of Grade M35Project Report on Concrete Mix Design of Grade M35
Project Report on Concrete Mix Design of Grade M35
 
Types of tender and their processing.
Types of tender and their processing.Types of tender and their processing.
Types of tender and their processing.
 
training report on commercial building
training report on commercial buildingtraining report on commercial building
training report on commercial building
 
Summer Internship Report of Civil Engineering in Construction Site
Summer Internship Report of Civil Engineering in Construction SiteSummer Internship Report of Civil Engineering in Construction Site
Summer Internship Report of Civil Engineering in Construction Site
 
Block estimate.ppt (1)
Block estimate.ppt (1)Block estimate.ppt (1)
Block estimate.ppt (1)
 
Boq piling works
Boq   piling worksBoq   piling works
Boq piling works
 
BUILDING MATERIALS 1
BUILDING MATERIALS 1BUILDING MATERIALS 1
BUILDING MATERIALS 1
 
DD STAGE COST ESTIMATE SECTION 1 (J102) (1)
DD STAGE COST ESTIMATE SECTION 1 (J102) (1)DD STAGE COST ESTIMATE SECTION 1 (J102) (1)
DD STAGE COST ESTIMATE SECTION 1 (J102) (1)
 

Similar to Fence BOQ with Materials.pdf

E-Tender_Aanganvadi SZ 29-10-15
E-Tender_Aanganvadi SZ 29-10-15E-Tender_Aanganvadi SZ 29-10-15
E-Tender_Aanganvadi SZ 29-10-15
JITEN THAKER (M.E-CIVIL)
 
12724469 wtp-cost-estimate
12724469 wtp-cost-estimate12724469 wtp-cost-estimate
12724469 wtp-cost-estimate
imaduddin91
 
Building Economics Preliminary Cost Appraisal
Building Economics Preliminary Cost Appraisal Building Economics Preliminary Cost Appraisal
Building Economics Preliminary Cost Appraisal
ashleyyeap
 
Tender_Schedule_Renovation_of_Vadakkechira_Bus_Stand.pdf
Tender_Schedule_Renovation_of_Vadakkechira_Bus_Stand.pdfTender_Schedule_Renovation_of_Vadakkechira_Bus_Stand.pdf
Tender_Schedule_Renovation_of_Vadakkechira_Bus_Stand.pdf
ssuserd43de8
 
RR Nagar
RR NagarRR Nagar
RR Nagar
KARTHIKEYAN R
 
Road work construction proxy(1)
Road work   construction proxy(1)Road work   construction proxy(1)
Road work construction proxy(1)
FeteneBefekadu
 
Bo q for shelter
Bo q  for shelterBo q  for shelter
Bo q for shelter
SantinoDengAchuilAth
 
Road work construction proxy(2)
Road work   construction proxy(2)Road work   construction proxy(2)
Road work construction proxy(2)
FeteneBefekadu
 
Jury Presenatation.pptx
Jury Presenatation.pptxJury Presenatation.pptx
Jury Presenatation.pptx
AmokBajracharya2
 
McsfBudget
McsfBudgetMcsfBudget
McsfBudget
Mcsf Projects
 
270 .pdf
270 .pdf270 .pdf
270 .pdf
Optional3
 
Design and analysis of RC structures with flat slab
Design and analysis of RC structures with flat slabDesign and analysis of RC structures with flat slab
Design and analysis of RC structures with flat slab
Deepak Patil
 
second review.pptx
second review.pptxsecond review.pptx
second review.pptx
KSelvakumarCIVIL
 
PT.pptx
PT.pptxPT.pptx
PT.pptx
ssusere8052d1
 
72747160 estimation
72747160 estimation72747160 estimation
72747160 estimation
imaduddin91
 
L. labour-charges-for-11k v-system-1
L. labour-charges-for-11k v-system-1L. labour-charges-for-11k v-system-1
L. labour-charges-for-11k v-system-1
Ramesh Meti
 
Civil-Paper-II.pdf
Civil-Paper-II.pdfCivil-Paper-II.pdf
Civil-Paper-II.pdf
SatyajitPaikaray2
 
Cbecl clay brick project with tunnel kiln-200000 pcs per day
Cbecl clay brick project with tunnel kiln-200000 pcs per dayCbecl clay brick project with tunnel kiln-200000 pcs per day
Cbecl clay brick project with tunnel kiln-200000 pcs per day
Abu Rayhan
 
47093152 estimation
47093152 estimation47093152 estimation
47093152 estimation
imaduddin91
 
Masonry Design Example for building with brick materials.
Masonry Design Example for building with brick materials.Masonry Design Example for building with brick materials.
Masonry Design Example for building with brick materials.
hbcivil1
 

Similar to Fence BOQ with Materials.pdf (20)

E-Tender_Aanganvadi SZ 29-10-15
E-Tender_Aanganvadi SZ 29-10-15E-Tender_Aanganvadi SZ 29-10-15
E-Tender_Aanganvadi SZ 29-10-15
 
12724469 wtp-cost-estimate
12724469 wtp-cost-estimate12724469 wtp-cost-estimate
12724469 wtp-cost-estimate
 
Building Economics Preliminary Cost Appraisal
Building Economics Preliminary Cost Appraisal Building Economics Preliminary Cost Appraisal
Building Economics Preliminary Cost Appraisal
 
Tender_Schedule_Renovation_of_Vadakkechira_Bus_Stand.pdf
Tender_Schedule_Renovation_of_Vadakkechira_Bus_Stand.pdfTender_Schedule_Renovation_of_Vadakkechira_Bus_Stand.pdf
Tender_Schedule_Renovation_of_Vadakkechira_Bus_Stand.pdf
 
RR Nagar
RR NagarRR Nagar
RR Nagar
 
Road work construction proxy(1)
Road work   construction proxy(1)Road work   construction proxy(1)
Road work construction proxy(1)
 
Bo q for shelter
Bo q  for shelterBo q  for shelter
Bo q for shelter
 
Road work construction proxy(2)
Road work   construction proxy(2)Road work   construction proxy(2)
Road work construction proxy(2)
 
Jury Presenatation.pptx
Jury Presenatation.pptxJury Presenatation.pptx
Jury Presenatation.pptx
 
McsfBudget
McsfBudgetMcsfBudget
McsfBudget
 
270 .pdf
270 .pdf270 .pdf
270 .pdf
 
Design and analysis of RC structures with flat slab
Design and analysis of RC structures with flat slabDesign and analysis of RC structures with flat slab
Design and analysis of RC structures with flat slab
 
second review.pptx
second review.pptxsecond review.pptx
second review.pptx
 
PT.pptx
PT.pptxPT.pptx
PT.pptx
 
72747160 estimation
72747160 estimation72747160 estimation
72747160 estimation
 
L. labour-charges-for-11k v-system-1
L. labour-charges-for-11k v-system-1L. labour-charges-for-11k v-system-1
L. labour-charges-for-11k v-system-1
 
Civil-Paper-II.pdf
Civil-Paper-II.pdfCivil-Paper-II.pdf
Civil-Paper-II.pdf
 
Cbecl clay brick project with tunnel kiln-200000 pcs per day
Cbecl clay brick project with tunnel kiln-200000 pcs per dayCbecl clay brick project with tunnel kiln-200000 pcs per day
Cbecl clay brick project with tunnel kiln-200000 pcs per day
 
47093152 estimation
47093152 estimation47093152 estimation
47093152 estimation
 
Masonry Design Example for building with brick materials.
Masonry Design Example for building with brick materials.Masonry Design Example for building with brick materials.
Masonry Design Example for building with brick materials.
 

Recently uploaded

一比一原版肯特大学毕业证UKC成绩单一模一样
一比一原版肯特大学毕业证UKC成绩单一模一样一比一原版肯特大学毕业证UKC成绩单一模一样
一比一原版肯特大学毕业证UKC成绩单一模一样
tobbk6s8
 
NHL Stenden University of Applied Sciences Diploma Degree Transcript
NHL Stenden University of Applied Sciences Diploma Degree TranscriptNHL Stenden University of Applied Sciences Diploma Degree Transcript
NHL Stenden University of Applied Sciences Diploma Degree Transcript
lhtvqoag
 
LGBTQIA Pride Month presentation Template
LGBTQIA Pride Month presentation TemplateLGBTQIA Pride Month presentation Template
LGBTQIA Pride Month presentation Template
DakshGudwani
 
ARENA - Young adults in the workplace (Knight Moves).pdf
ARENA - Young adults in the workplace (Knight Moves).pdfARENA - Young adults in the workplace (Knight Moves).pdf
ARENA - Young adults in the workplace (Knight Moves).pdf
Knight Moves
 
Practical eLearning Makeovers for Everyone
Practical eLearning Makeovers for EveryonePractical eLearning Makeovers for Everyone
Practical eLearning Makeovers for Everyone
Bianca Woods
 
Getting Data Ready for Culture Hack by Neontribe
Getting Data Ready for Culture Hack by NeontribeGetting Data Ready for Culture Hack by Neontribe
Getting Data Ready for Culture Hack by Neontribe
Harry Harrold
 
一比一原版南安普顿索伦特大学毕业证Southampton成绩单一模一样
一比一原版南安普顿索伦特大学毕业证Southampton成绩单一模一样一比一原版南安普顿索伦特大学毕业证Southampton成绩单一模一样
一比一原版南安普顿索伦特大学毕业证Southampton成绩单一模一样
3vgr39kx
 
原版制作(MDIS毕业证书)新加坡管理发展学院毕业证学位证一模一样
原版制作(MDIS毕业证书)新加坡管理发展学院毕业证学位证一模一样原版制作(MDIS毕业证书)新加坡管理发展学院毕业证学位证一模一样
原版制作(MDIS毕业证书)新加坡管理发展学院毕业证学位证一模一样
hw2xf1m
 
Divertidamente SLIDE.pptxufururururuhrurid8dj
Divertidamente SLIDE.pptxufururururuhrurid8djDivertidamente SLIDE.pptxufururururuhrurid8dj
Divertidamente SLIDE.pptxufururururuhrurid8dj
lunaemel03
 
Introduction to User experience design for beginner
Introduction to User experience design for beginnerIntroduction to User experience design for beginner
Introduction to User experience design for beginner
ellemjani
 
按照学校原版(UIUC文凭证书)伊利诺伊大学|厄巴纳-香槟分校毕业证快速办理
按照学校原版(UIUC文凭证书)伊利诺伊大学|厄巴纳-香槟分校毕业证快速办理按照学校原版(UIUC文凭证书)伊利诺伊大学|厄巴纳-香槟分校毕业证快速办理
按照学校原版(UIUC文凭证书)伊利诺伊大学|厄巴纳-香槟分校毕业证快速办理
kuapy
 
CocaCola_Brand_equity_package_2012__.pdf
CocaCola_Brand_equity_package_2012__.pdfCocaCola_Brand_equity_package_2012__.pdf
CocaCola_Brand_equity_package_2012__.pdf
PabloMartelLpez
 
NHR Engineers Portfolio 2023 2024 NISHANT RATHI
NHR Engineers Portfolio 2023 2024 NISHANT RATHINHR Engineers Portfolio 2023 2024 NISHANT RATHI
NHR Engineers Portfolio 2023 2024 NISHANT RATHI
NishantRathi18
 
定制美国西雅图城市大学毕业证学历证书原版一模一样
定制美国西雅图城市大学毕业证学历证书原版一模一样定制美国西雅图城市大学毕业证学历证书原版一模一样
定制美国西雅图城市大学毕业证学历证书原版一模一样
qo1as76n
 
AHMED TALAAT ARCHITECTURE PORTFOLIO .pdf
AHMED TALAAT ARCHITECTURE PORTFOLIO .pdfAHMED TALAAT ARCHITECTURE PORTFOLIO .pdf
AHMED TALAAT ARCHITECTURE PORTFOLIO .pdf
talaatahm
 
一比一原版亚利桑那大学毕业证(UA毕业证书)如何办理
一比一原版亚利桑那大学毕业证(UA毕业证书)如何办理一比一原版亚利桑那大学毕业证(UA毕业证书)如何办理
一比一原版亚利桑那大学毕业证(UA毕业证书)如何办理
21uul8se
 
一比一原版美国哥伦比亚大学毕业证Columbia成绩单一模一样
一比一原版美国哥伦比亚大学毕业证Columbia成绩单一模一样一比一原版美国哥伦比亚大学毕业证Columbia成绩单一模一样
一比一原版美国哥伦比亚大学毕业证Columbia成绩单一模一样
881evgn0
 
一比一原版(Vancouver毕业证书)温哥华岛大学毕业证如何办理
一比一原版(Vancouver毕业证书)温哥华岛大学毕业证如何办理一比一原版(Vancouver毕业证书)温哥华岛大学毕业证如何办理
一比一原版(Vancouver毕业证书)温哥华岛大学毕业证如何办理
ijk38lw
 
一比一原版马来西亚世纪大学毕业证成绩单一模一样
一比一原版马来西亚世纪大学毕业证成绩单一模一样一比一原版马来西亚世纪大学毕业证成绩单一模一样
一比一原版马来西亚世纪大学毕业证成绩单一模一样
k4krdgxx
 
哪里办理美国中央华盛顿大学毕业证双学位证书原版一模一样
哪里办理美国中央华盛顿大学毕业证双学位证书原版一模一样哪里办理美国中央华盛顿大学毕业证双学位证书原版一模一样
哪里办理美国中央华盛顿大学毕业证双学位证书原版一模一样
qo1as76n
 

Recently uploaded (20)

一比一原版肯特大学毕业证UKC成绩单一模一样
一比一原版肯特大学毕业证UKC成绩单一模一样一比一原版肯特大学毕业证UKC成绩单一模一样
一比一原版肯特大学毕业证UKC成绩单一模一样
 
NHL Stenden University of Applied Sciences Diploma Degree Transcript
NHL Stenden University of Applied Sciences Diploma Degree TranscriptNHL Stenden University of Applied Sciences Diploma Degree Transcript
NHL Stenden University of Applied Sciences Diploma Degree Transcript
 
LGBTQIA Pride Month presentation Template
LGBTQIA Pride Month presentation TemplateLGBTQIA Pride Month presentation Template
LGBTQIA Pride Month presentation Template
 
ARENA - Young adults in the workplace (Knight Moves).pdf
ARENA - Young adults in the workplace (Knight Moves).pdfARENA - Young adults in the workplace (Knight Moves).pdf
ARENA - Young adults in the workplace (Knight Moves).pdf
 
Practical eLearning Makeovers for Everyone
Practical eLearning Makeovers for EveryonePractical eLearning Makeovers for Everyone
Practical eLearning Makeovers for Everyone
 
Getting Data Ready for Culture Hack by Neontribe
Getting Data Ready for Culture Hack by NeontribeGetting Data Ready for Culture Hack by Neontribe
Getting Data Ready for Culture Hack by Neontribe
 
一比一原版南安普顿索伦特大学毕业证Southampton成绩单一模一样
一比一原版南安普顿索伦特大学毕业证Southampton成绩单一模一样一比一原版南安普顿索伦特大学毕业证Southampton成绩单一模一样
一比一原版南安普顿索伦特大学毕业证Southampton成绩单一模一样
 
原版制作(MDIS毕业证书)新加坡管理发展学院毕业证学位证一模一样
原版制作(MDIS毕业证书)新加坡管理发展学院毕业证学位证一模一样原版制作(MDIS毕业证书)新加坡管理发展学院毕业证学位证一模一样
原版制作(MDIS毕业证书)新加坡管理发展学院毕业证学位证一模一样
 
Divertidamente SLIDE.pptxufururururuhrurid8dj
Divertidamente SLIDE.pptxufururururuhrurid8djDivertidamente SLIDE.pptxufururururuhrurid8dj
Divertidamente SLIDE.pptxufururururuhrurid8dj
 
Introduction to User experience design for beginner
Introduction to User experience design for beginnerIntroduction to User experience design for beginner
Introduction to User experience design for beginner
 
按照学校原版(UIUC文凭证书)伊利诺伊大学|厄巴纳-香槟分校毕业证快速办理
按照学校原版(UIUC文凭证书)伊利诺伊大学|厄巴纳-香槟分校毕业证快速办理按照学校原版(UIUC文凭证书)伊利诺伊大学|厄巴纳-香槟分校毕业证快速办理
按照学校原版(UIUC文凭证书)伊利诺伊大学|厄巴纳-香槟分校毕业证快速办理
 
CocaCola_Brand_equity_package_2012__.pdf
CocaCola_Brand_equity_package_2012__.pdfCocaCola_Brand_equity_package_2012__.pdf
CocaCola_Brand_equity_package_2012__.pdf
 
NHR Engineers Portfolio 2023 2024 NISHANT RATHI
NHR Engineers Portfolio 2023 2024 NISHANT RATHINHR Engineers Portfolio 2023 2024 NISHANT RATHI
NHR Engineers Portfolio 2023 2024 NISHANT RATHI
 
定制美国西雅图城市大学毕业证学历证书原版一模一样
定制美国西雅图城市大学毕业证学历证书原版一模一样定制美国西雅图城市大学毕业证学历证书原版一模一样
定制美国西雅图城市大学毕业证学历证书原版一模一样
 
AHMED TALAAT ARCHITECTURE PORTFOLIO .pdf
AHMED TALAAT ARCHITECTURE PORTFOLIO .pdfAHMED TALAAT ARCHITECTURE PORTFOLIO .pdf
AHMED TALAAT ARCHITECTURE PORTFOLIO .pdf
 
一比一原版亚利桑那大学毕业证(UA毕业证书)如何办理
一比一原版亚利桑那大学毕业证(UA毕业证书)如何办理一比一原版亚利桑那大学毕业证(UA毕业证书)如何办理
一比一原版亚利桑那大学毕业证(UA毕业证书)如何办理
 
一比一原版美国哥伦比亚大学毕业证Columbia成绩单一模一样
一比一原版美国哥伦比亚大学毕业证Columbia成绩单一模一样一比一原版美国哥伦比亚大学毕业证Columbia成绩单一模一样
一比一原版美国哥伦比亚大学毕业证Columbia成绩单一模一样
 
一比一原版(Vancouver毕业证书)温哥华岛大学毕业证如何办理
一比一原版(Vancouver毕业证书)温哥华岛大学毕业证如何办理一比一原版(Vancouver毕业证书)温哥华岛大学毕业证如何办理
一比一原版(Vancouver毕业证书)温哥华岛大学毕业证如何办理
 
一比一原版马来西亚世纪大学毕业证成绩单一模一样
一比一原版马来西亚世纪大学毕业证成绩单一模一样一比一原版马来西亚世纪大学毕业证成绩单一模一样
一比一原版马来西亚世纪大学毕业证成绩单一模一样
 
哪里办理美国中央华盛顿大学毕业证双学位证书原版一模一样
哪里办理美国中央华盛顿大学毕业证双学位证书原版一模一样哪里办理美国中央华盛顿大学毕业证双学位证书原版一模一样
哪里办理美国中央华盛顿大学毕业证双学位证书原版一模一样
 

Fence BOQ with Materials.pdf

  • 1. QTY UNIT RATE AMOUNT UNIT BILL NR 1: FENCE AND BOUNDARY WALL ELEMENT NR. 1: SUBSTRUCTURE SITE CLEARANCE Removing bushes, shrubs, trees, etc. Clearing the site; grubbing up roots, bushes, shrub, undergrowth or the like; small trees not exceeding 600 mm girth 1519 SM 200 303,800.00 EXCAVATION Surfaces Average 150 mm deep; to remove vegetable soil 1519 SM 200 303,800.00 Trenches; to receive foundations; starting from reduced level Not exceeding 1.5 m deep 81 CM 5,000 405,000.00 Pits; to receive foundations; starting from reduced level Not exceeding 1.5m deep 21 CM 5,000 105,000.00 BACKFILL AND DISPOSAL Approved imported granular materials Backfilling into foundations; depositing and compacting in layers maximum 200 mm thick 58 CM 5,000 290,000.00 Earth filling; select sand imported material; 200 mm thick; depositing and compacting in layers to make up levels 0 CM 18,500 0.00 0 CM 1,407,600.00 0.00 LABOUR COST QUANTITY ITEM DESCRIPTION STD BOQ ESTIMATES MATERIAL COST ESTIMATES Carried Forward
  • 2. QTY UNIT RATE AMOUNT UNIT LABOUR COST QUANTITY ITEM DESCRIPTION STD BOQ ESTIMATES MATERIAL COST ESTIMATES 1,407,600.00 0.00 Surplus excavated material Removing from site 44 CM 14,500 638,000.00 PLANKING AND STRUTTING Generally To sides of excavations 1 Item 200,000.00 DISPOSAL OF WATER Generally Keeping excavations free from all water including spring and running water 1 Item 200,000.00 Add: Labour earthworks 1,838,000 2,445,600.00 1,838,000.00 Brought Forward Carried Forward
  • 3. QTY UNIT RATE AMOUNT UNIT LABOUR COST QUANTITY ITEM DESCRIPTION STD BOQ ESTIMATES MATERIAL COST ESTIMATES 2,445,600.00 1,838,000.00 INSITU CONCRETE; REINFORCED Normal; grade C20; vibrated Column bases irrespective of thickness 7 CM 280,000 1,960,000.00 Column; irrespective of thickness 1 CM 280,000 280,000.00 Beds; 100 mm thick 0 SM 28,000 0.00 Ground beams 7 CM 280,000 1,960,000.00 Steps, staircases or strings 0 CM 280,000 0.00 Walls; 230mm thick 0 CM 280,000 0.00 Raft foundation; 500mm thick 0 CM 280,000 0.00 Irrespective of item: a) Cement (42.R); 50kg 99 BGS b) Sand 6 CM c)Aggregates 13 CM Add: Labour casting concrete 504,000 6,645,600.00 2,342,000.00 Brought Forward Carried Forward
  • 4. QTY UNIT RATE AMOUNT UNIT LABOUR COST QUANTITY ITEM DESCRIPTION STD BOQ ESTIMATES MATERIAL COST ESTIMATES 6,645,600.00 2,342,000.00 REINFORCEMENT Bars; high yield steel; cold worked; B.S 4449 12mm diameter 341 KG 3,200 1,091,200.00 33 PCS 16mm diameter 0 KG 3,200 0.00 0 PCS 8mm diameter 173 KG 3,200 553,600.00 37 PCS EO; Binding Wire; 30kg 0.26 RLS Add: Labour for reinforcements 216,000 FORMWORK TO INSITU CONCRETE Formwork generally Sides; vertical or battering in: Foundations in trenches irrespective of thickness 0 SM 20,000 0.00 Column bases irrespective of thickness 31 SM 20,000 620,000.00 Column; irrespective of thickness 2 SM 20,000 40,000.00 Ground beams 31 SM 20,000 620,000.00 Walls; 230mm thick 0 SM 20,000 0.00 Raft foundation; 500mm thick 0 SM 20,000 0.00 Steps; strings and sides 0 SM 20,000 0.00 Edges in: Beds 75 to 150 mm wide 0 LM 2,000 0.00 Risers of steps or staircases 0 LM 3,000 0.00 9,570,400.00 2,558,000.00 Brought Forward Carried Forward
  • 5. QTY UNIT RATE AMOUNT UNIT LABOUR COST QUANTITY ITEM DESCRIPTION STD BOQ ESTIMATES MATERIAL COST ESTIMATES 9,570,400.00 2,558,000.00 Formwork generally: a) Marine plywood boards; 12mm thk 22 PCS b) Timber Props 84 PCS c) Iron Nails 13 KG d) Concrete Nails 3 KG e) Oils 2 LTR Add: Labour for formworks 308,000 BLOCKWORK Concrete blocks; B.S. 6073; type A; 7.0 N per square millimetre; solid; in cement mortar (1:4) Walls; 230mm thick 124 SM 32,000 3,968,000.00 a) Solid Concrete Block 1736 NR b) Cement (42.R); 50kg 11 BGS c) Sand 2 CM DAMP PROOF COURSES B.S. 8102; bitumen hessian base; 150 mm laps Horizontal 230mm wide 116 LM 2,000 231,000.00 116 LM Add: Labour for walling 730,000 13,769,400.00 3,596,000.00 Brought Forward Carried Forward
  • 6. QTY UNIT RATE AMOUNT UNIT LABOUR COST QUANTITY ITEM DESCRIPTION STD BOQ ESTIMATES MATERIAL COST ESTIMATES 13,769,400.00 3,596,000.00 WALLING SUNDRIES (PROVISIONAL) INSITU FINISHINGS Render; cement and sand (1:4); wood floated; external 15 mm one coat work; to concrete or block work base; generally to walls 70 SM 8,000 560,000.00 a) Cement (42.R); 50kg 7 BGS c) Sand 1 CM Add: Labour for plaster 385,000 Two coats bituminous based paint Wood floated rendered surfaces; external walls over 300 mm wide 70 SM 8,000 560,000.00 4 TIN Add: Labour for painting 385,000 CONCRETE WORK SUNDRIES Generally Expansion joints in concrete; 25 mm thick; over 300 mm wide; filling with styrofoam expansion joint materials 0 LM 32,000 0.00 SUMMARY Total Labour Cost Allowed by Contractor 14,889,400.00 4,366,000.00 Brought Forward TOTAL ELEMENT NR. 1: SUBSTRUCTURE CARRIED TO BILL SUMMARY
  • 7. QTY UNIT RATE AMOUNT UNIT ELEMENT NR. 2: FRAME AND WALLING INTERNAL WALLING Concrete blocks; B.S 6073; type A; 7 N per square millimetre; solid; in cement mortar (1:4) Walls; 150 mm thick 424 SM 28,000 11,872,000.00 a) Solid Concrete Block 3816 NR b) Cement (42.R); 50kg 20 BGS c) Sand 3 CM Add: Labour for walling 1,603,000 CONCRETE COPING Copings; finish fair on top one side and part soffit; rebated once; weathered once; finished; including fabric BRC Mesh, and necessary ancillaries 100 x 200mm wide 116 LM 10,000 1,155,000.00 a) Cement (42.R); 50kg 15 BGS b) Sand 0.10 CM c)Aggregates 0.20 CM d) BRC Fabric Mesh 0.4 RLS e) Timber Formwork 32 PCS 13,027,000.00 1,603,000.00 LABOUR COST QUANTITY Carried Forward ITEM DESCRIPTION STD BOQ ESTIMATES MATERIAL COST ESTIMATES
  • 8. 13,027,000.00 1,603,000.00 INSITU CONCRETE; REINFORCED Normal; grade C20; vibrated Column; irrespective of thickness 1 CM 280,000 280,000.00 Irrespective of item: a) Cement (42.R); 50kg 9 BGS b) Sand 0 CM c)Aggregates 1 CM Add: Labour casting concrete 112,000 REINFORCEMENT Bars; high yield steel; cold worked; B.S 4449 12mm diameter 26 KG 3,200 83,200.00 3 PCS 16mm diameter 0 KG 3,200 0.00 0 PCS 8mm diameter 16 KG 3,200 51,200.00 3 PCS EO; Binding Wire; 30kg 0.02 RLS Add: Labour for reinforcements 18,000 FORMWORK TO INSITU CONCRETE Formwork generally Sides; vertical or battering in: Column; irrespective of thickness 6 SM 20,000 120,000.00 Formwork generally: a) Marine plywood boards; 12mm thk 2 PCS b) Timber Props 5 PCS c) Iron Nails 1 KG d) Concrete Nails 0 KG e) Oils 0 LTR Add: Labour for formworks 140,000 SUMMARY Total Labour Cost Allowed by Contractor 13,561,400.00 1,873,000.00 TOTAL ELEMENT NR. 2: WALLING CARRIED TO BILL SUMMARY Brought Forward
  • 9. QTY UNIT RATE AMOUNT UNIT ELEMENT NR. 3: FINISHING Insitu Finishes Render; 12 mm first coat of cement and sand (1:5) mixed with Morcemcril Siloxane Synthetic water proofing coat; 3 mm skimming coat; steel trowelled; externally 15 mm two coats work; walls 707 SM 8,000 5,656,000.00 a) Cement (42.R); 50kg 60 BGS b) Sand 7 CM c) Moyashield 20Ltr 18 BKT d) White Cement; 40kg 54 BGS Add: Labour for plaster 3,889,000 FITTINGS Entrance Metal Gates Allow for supply and fix of main entrance metal gates;size 5000 x 1800mm high, double leaf (1Nr); complete with associated frame and iron mongeries; grilled and welded to pattern as approved by the Architect Item 2,500,000 2,500,000.00 Ditto; metal gates;size 1500 x 1800mm high, single leaf (1Nr) Item 1,000,000 1,000,000.00 SUMMARY Total Labour Cost Allowed by Contractor TOTAL ELEMENT NR. 3: FINISHING CARRIED TO BILL SUMMARY 9,156,000.00 LABOUR COST QUANTITY ITEM DESCRIPTION STD BOQ ESTIMATES MATERIAL COST ESTIMATES
  • 10. QTY UNIT RATE AMOUNT UNIT ELEMENT NR. 4: PAINTING AND DECORATIONS Wall Painting One coat of PLASCON textured paint with two coats of pigment coat on platered surface; external Walls over 300mm wide 707 SM 8,000 5,656,000.00 43 BKT Add: Labour for painting 3,889,000 SUMMARY Total Labour Cost Allowed by Contractor 5,656,000.00 ITEM DESCRIPTION STD BOQ ESTIMATES MATERIAL COST ESTIMATES LABOUR COST QUANTITY TOTAL ELEMENT NR 4: PAINTING AND DECORATION CARRIED TO BILL SUMMARY
  • 11. ITEM DESCRIPTION AMOUNT (TZS) BILLS SUMMARY ELEMENT NR. 1: SUBSTRUCTURE 14,889,400.00 ELEMENT NR. 2: FRAME AND WALLING 13,561,400.00 ELEMENT NR. 3: FINISHING 9,156,000.00 ELEMENT NR. 4: PAINTING AND DECORATIONS 5,656,000.00 SUB-TOTAL 43,262,800.00 TOTAL 43,262,800.00 1/SUM/11