This document contains an architectural plan for a multi-level building with various workshops, studios, and other facilities. It includes floor plans for the ground level, first floor, roof top, upper ground level, and second floor. Sections and elevations are provided with callouts for structural and material details. The document also lists relevant architects, engineers, and the client for the project.
INTRODUCTION
In recent years,the faculty of architecture design and development has expirience a rapid increase in
population,causing a strain on its physical resources,and hence necessitating the exploration of a novel idea of
separation and design of a separate school of architecture.The new school of architectue would free space
within the existing FADD building to be used by the school ofv art and design,School of planning,and school of
real estate and construction management ,jointly used spaces such us the workshop and space 10,
environmental laboratory and exhibition spaces would continue to be used by the school of architecture.
REQUIREMENTS
1.Department of landscape architecture
2.Interior architecture
3.Conservation architecture
4.Environmental architecture
5.Housing architecture and Urban design architecture
6.meffert centre
7.lecture theatre
8.studio spaces
9. architecture Library
10.convocation rooms
India’s !st & only Hollywood benchmarked studio facilityarchana jhangiani
Introducing India’s first and only Hollywood benchmarked studio facility
Special Mentions:
“The newly built Reliance Media Works Studio... woah! Stunning! I've never seen such opulence and systems in a film studio..”- Referenced from Twitter handle of Mr. Amitabh Bachchan.
"After what I have seen here, there is a possibility of me coming back to make a movie here, after all"- Oliver Stone, as said to The Economic Times, India.
INTRODUCTION
A developer has acquired a plot measuring about 43 by 21m,between Ndia kuu and thika street of old town mombasa,and has approached you
to redevelop the plot.an existing building built around 1900,was demolisjed under mysterious circumstances. The developer's intentionis to develop
a mixed urban development to maximize the potential for the site,while adhering to the concservation requirements posed by the stakeholder of oldtown
mombasa
The challenge presented by the project is in responding to the diversity of requirements in comprehensive urban development,site conditions and local
authority requirements and in achieving a sustainable design
REQUIREMENTS AND ACCOMMODATION SCHEDULE
1.commercial shop front
2.2bedroom unit
3.3bedroom units
3.club house
4.swimming pool
5.gym
6.parking
INTRODUCTION
A developer has acquired a plot measuring about 43 by 21m,between Ndia kuu and thika street of old town mombasa,and has approached you
to redevelop the plot.an existing building built around 1900,was demolisjed under mysterious circumstances. The developer's intentionis to develop
a mixed urban development to maximize the potential for the site,while adhering to the concservation requirements posed by the stakeholder of oldtown
mombasa
The challenge presented by the project is in responding to the diversity of requirements in comprehensive urban development,site conditions and local
authority requirements and in achieving a sustainable design
REQUIREMENTS AND ACCOMMODATION SCHEDULE
1.commercial shop front
2.2bedroom unit
3.3bedroom units
3.club house
4.swimming pool
5.gym
6.parking
Accessibility of Visually Impaired Passengers at Urban Railway Stations in th...drboon
Ensuring access to the built environment and public transportation is a crucial element in reducing the mobility constraints of people with disabilities. This study intends to investigate the accessibility of visual impaired passengers regards to interior design of Kelana Jaya Line LRT station. The access audit was evaluated at core area, transition area and peripheral area of selected LRT stations by using site observation and interview research method. A standard checklist was taken in accordance to the Malaysia Standards Code of Practice for Access of Disabled People to Public Buildings (MS1184:2002).The result shows that, although most of the stations accommodate access for disabled people however the design of facilities provided was not fully incorporate with standard requirement and user-friendly. These lead barriers to independent living for persons with disability. As a conclusion, aside from providing a complete of public access facilities, comprehension of social sensitivity and capability to plan for continuity and uniformity should be taken into consideration to eliminate the architectural barriers in the built environment in the future.
INTRODUCTION
In recent years,the faculty of architecture design and development has expirience a rapid increase in
population,causing a strain on its physical resources,and hence necessitating the exploration of a novel idea of
separation and design of a separate school of architecture.The new school of architectue would free space
within the existing FADD building to be used by the school ofv art and design,School of planning,and school of
real estate and construction management ,jointly used spaces such us the workshop and space 10,
environmental laboratory and exhibition spaces would continue to be used by the school of architecture.
REQUIREMENTS
1.Department of landscape architecture
2.Interior architecture
3.Conservation architecture
4.Environmental architecture
5.Housing architecture and Urban design architecture
6.meffert centre
7.lecture theatre
8.studio spaces
9. architecture Library
10.convocation rooms
India’s !st & only Hollywood benchmarked studio facilityarchana jhangiani
Introducing India’s first and only Hollywood benchmarked studio facility
Special Mentions:
“The newly built Reliance Media Works Studio... woah! Stunning! I've never seen such opulence and systems in a film studio..”- Referenced from Twitter handle of Mr. Amitabh Bachchan.
"After what I have seen here, there is a possibility of me coming back to make a movie here, after all"- Oliver Stone, as said to The Economic Times, India.
INTRODUCTION
A developer has acquired a plot measuring about 43 by 21m,between Ndia kuu and thika street of old town mombasa,and has approached you
to redevelop the plot.an existing building built around 1900,was demolisjed under mysterious circumstances. The developer's intentionis to develop
a mixed urban development to maximize the potential for the site,while adhering to the concservation requirements posed by the stakeholder of oldtown
mombasa
The challenge presented by the project is in responding to the diversity of requirements in comprehensive urban development,site conditions and local
authority requirements and in achieving a sustainable design
REQUIREMENTS AND ACCOMMODATION SCHEDULE
1.commercial shop front
2.2bedroom unit
3.3bedroom units
3.club house
4.swimming pool
5.gym
6.parking
INTRODUCTION
A developer has acquired a plot measuring about 43 by 21m,between Ndia kuu and thika street of old town mombasa,and has approached you
to redevelop the plot.an existing building built around 1900,was demolisjed under mysterious circumstances. The developer's intentionis to develop
a mixed urban development to maximize the potential for the site,while adhering to the concservation requirements posed by the stakeholder of oldtown
mombasa
The challenge presented by the project is in responding to the diversity of requirements in comprehensive urban development,site conditions and local
authority requirements and in achieving a sustainable design
REQUIREMENTS AND ACCOMMODATION SCHEDULE
1.commercial shop front
2.2bedroom unit
3.3bedroom units
3.club house
4.swimming pool
5.gym
6.parking
Accessibility of Visually Impaired Passengers at Urban Railway Stations in th...drboon
Ensuring access to the built environment and public transportation is a crucial element in reducing the mobility constraints of people with disabilities. This study intends to investigate the accessibility of visual impaired passengers regards to interior design of Kelana Jaya Line LRT station. The access audit was evaluated at core area, transition area and peripheral area of selected LRT stations by using site observation and interview research method. A standard checklist was taken in accordance to the Malaysia Standards Code of Practice for Access of Disabled People to Public Buildings (MS1184:2002).The result shows that, although most of the stations accommodate access for disabled people however the design of facilities provided was not fully incorporate with standard requirement and user-friendly. These lead barriers to independent living for persons with disability. As a conclusion, aside from providing a complete of public access facilities, comprehension of social sensitivity and capability to plan for continuity and uniformity should be taken into consideration to eliminate the architectural barriers in the built environment in the future.
Transforming The Academic Library Services For Generation Y Using Knowledge M...tulipbiru64
Paper presented by Sharifah Fahimah Saiyed Yeop at the 4th PERPUN International Conference 2015: Information Revolution, 11-12th August 2015 at Avillion Legacy Hotel, Melaka.
PENGENALAN
Puncak Kiara Trading Enterprise adalah syarikat berdaftar dengan Suruhanjaya Syarikat Malaysia di bawah Akta Pendaftaran Perniagaan, 1956 (Pindaan 2014).
Puncak Kiara Trading telah mula beroperasi sejak tahun 2014 secara rasminya berpengkalan di Sepang, Selangor dimana pada mulanya beroperasi secara kecil-kecilan tanpa berdaftar sejak 2012 (2 tahun pengalaman). Sehingga Disember 2016, Puncak Kiara Trading telah membina lebih beberapa buah kediaman di Selangor dan Negeri Sembilan dengan rekod tiada projek terbengkalai. Bidang perniagaan utama syarikat ini adalah menjalankan kerja-kerja berkaitan dengan pembinaan bangunan terutama kerja-kerja membina banglo persendirian dan pengubahsuaian. Tanah lot banglo yang diuruskan meliputi tanah persendirian, tanah koperasi dan tanah individu atau syarikat lain.
Sejak penubuhan, syarikat Puncak Kiara Trading telah didokong oleh rangkaian tenaga mahir dan berpengalaman dalam bidang hartanah dan pembinaan bangunan. Berbekalkan kemahiran dan pengalaman ini, syarikat bertekad dan komited untuk memberikan perkhidmatan yang berkesan dan berdaya maju seterusnya dapat memberikan kepuasan kepada pelanggannya.
A report on the procedures and construction process of buildings based on real life site visits at Taman Bukit Segar, Cheras and Glenmarie Cove, Klang.
By students of Bsc(Hons) Architecture of Taylor's University.
EASY TUTORIAL OF HOW TO USE CAPCUT BY: FEBLESS HERNANEFebless Hernane
CapCut is an easy-to-use video editing app perfect for beginners. To start, download and open CapCut on your phone. Tap "New Project" and select the videos or photos you want to edit. You can trim clips by dragging the edges, add text by tapping "Text," and include music by selecting "Audio." Enhance your video with filters and effects from the "Effects" menu. When you're happy with your video, tap the export button to save and share it. CapCut makes video editing simple and fun for everyone!
Visual Style and Aesthetics: Basics of Visual Design
Visual Design for Enterprise Applications
Range of Visual Styles.
Mobile Interfaces:
Challenges and Opportunities of Mobile Design
Approach to Mobile Design
Patterns
Technoblade The Legacy of a Minecraft Legend.Techno Merch
Technoblade, born Alex on June 1, 1999, was a legendary Minecraft YouTuber known for his sharp wit and exceptional PvP skills. Starting his channel in 2013, he gained nearly 11 million subscribers. His private battle with metastatic sarcoma ended in June 2022, but his enduring legacy continues to inspire millions.
PDF SubmissionDigital Marketing Institute in NoidaPoojaSaini954651
https://www.safalta.com/online-digital-marketing/advance-digital-marketing-training-in-noidaTop Digital Marketing Institute in Noida: Boost Your Career Fast
[3:29 am, 30/05/2024] +91 83818 43552: Safalta Digital Marketing Institute in Noida also provides advanced classes for individuals seeking to develop their expertise and skills in this field. These classes, led by industry experts with vast experience, focus on specific aspects of digital marketing such as advanced SEO strategies, sophisticated content creation techniques, and data-driven analytics.
Hello everyone! I am thrilled to present my latest portfolio on LinkedIn, marking the culmination of my architectural journey thus far. Over the span of five years, I've been fortunate to acquire a wealth of knowledge under the guidance of esteemed professors and industry mentors. From rigorous academic pursuits to practical engagements, each experience has contributed to my growth and refinement as an architecture student. This portfolio not only showcases my projects but also underscores my attention to detail and to innovative architecture as a profession.
Between Filth and Fortune- Urban Cattle Foraging Realities by Devi S Nair, An...Mansi Shah
This study examines cattle rearing in urban and rural settings, focusing on milk production and consumption. By exploring a case in Ahmedabad, it highlights the challenges and processes in dairy farming across different environments, emphasising the need for sustainable practices and the essential role of milk in daily consumption.
ARENA - Young adults in the workplace (Knight Moves).pdfKnight Moves
Presentations of Bavo Raeymaekers (Project lead youth unemployment at the City of Antwerp), Suzan Martens (Service designer at Knight Moves) and Adriaan De Keersmaeker (Community manager at Talk to C)
during the 'Arena • Young adults in the workplace' conference hosted by Knight Moves.
Fonts play a crucial role in both User Interface (UI) and User Experience (UX) design. They affect readability, accessibility, aesthetics, and overall user perception.
1. RESOURCE LIBRARY
KOPITIAM
LEARNING WORKSHOP
CARPENTRY
WORKSHOP
METAL LEARNING
WORKSHOP
OPEN TOOLS
WORKSHOP
MACHINERY ROOM
LOADING BAYS
SHOP
ARTISTS' STUDIOSOFFICE
GROUND LEVEL
FFL 0.000
FIRST FLOOR LEVEL
FFL +7.900
ROOF TOP LEVEL
FFL +17.050
UPPER GROUND LEVEL
FFL +3.400
ACCOMMODATION
VOID
VOID
VOID
FULL WALL SECTION
UPPER GROUND LEVEL
FFL +4.000
LOWER GROUND LEVEL
FFL +0.100
CARPARK
COURTYARD
PANTRY
CARPARK
COURTYARD
LAUNDRY ROOM
LEARNING WORKSHOP TOILET
TOILET
ROOF TOP LEVEL
FFL +12.300
1 2 3 4 5 6 7 8 9 10 11 12
SECOND FLOOR LEVEL
FFL +11.150
LEARNING WORKSHOP
EGRESS INGRESS
VOID
OPEN TOOLS
WORKSHOP
FFL 4.000
OPEN
SCREENING
SHOP
FFL 4.000
EXHIBITION
FFL 3.400
RESOURCE
LIBRARY
FFL 4.000
MACHINERY
ROOM
FFL 4.000
BRIDGE
5.200
DRTEL
ELE CW
EXHIBITION
FFL 2.800
DOWN
DOWN
FFL 4.000
FFL 4.000
RECEPTION
UP
1
2
3
4
5
6
7
8
9
10
11
21
20
19
18
17
16
15
14
13
12
22
UP
1
2
3
4
5
6
7
8
9
10
21
20
19
18
17
16
15
14
13
1211
22
GREEN SPACE
1.2
UP
1
2
2.2
AS SHOWN
1
BUILDING SECTION
1.0
CONSTRUCTION DRAWING
menurut kehendak-kehendak undang-undang Bangunan Seragam
CIVIL & STRUCTURE ENGINEER :
Taman Melaka Raya,
Tel/Fax : 6082-233666
Melaka, Malaysia.
No.1, 1-1 & 1-2, Jalan Melaka Raya 30,
Tropikamaju Construction Engineering Sdn Bhd(No Syarikat :417634A)
MECHANICAL & ELECTRICAL ENGINEER :
Kawasan Perindustrian HICOM,
Tel/Fax : 6082-233666
Seksyen 26, Malaysia.
No 2A, Jalan Serendah 26/39,
Buler Engineering Sdn. Bhd. (No Syarikat : 641462-W)
QUANTITY SURVEYOR :
Taman Ungku Tun Aminah,
Tel/Fax : 6082-233666
Shanh Alam, Malaysia.
No.24,Jalan Asia Maju 30,
LEE Consultant Sdn Bhd (No Syarikat :5265637S)
Company Chop & Signature
PROJECT:
SHEET NO.:
ARCHITECT:
Signature
DRAWING TITLE:
CLIENT:
EFFECTOR CORPORATION
EFFECTOR CORPORATION
MR. PRINCE FAVIS ISIP
No. 1 Jalan Taylor's,
47500 Subang Jaya,
Tel: 603-5629 5000 Fax: 603-5629 5001
Selangor Darul Ehsan, Malaysia.
No. 1 Jalan Taylor's,
47500 Subang Jaya,
Selangor Darul Ehsan, Malaysia.
GENERAL NOTES
1. THIS DRAWING IS COPYRIGHT AND IS THE PROPERTY OF
EFFECTOR CORPORATION. NO PART OR WHOLE DRAWINGS
SHALL BE COPIED/REPRODUCED WITHOUT PERMISSION.
2. CONTRACTORS MUST CHECK ALL DIMENSION ON SITE. ONLY
FIGURE DIMENSIONS ARE TO BE WORKED ON.
3. ALL DISCREPANCIES MUST BE REPORTED IMMEDIATELY TO
THE ARCHITECT BEFORE PROCEEDING.
Ar. CH'NG XING YUE
Professional Architect
B.Sc. (HONOURS) (ARCHITECTURE)
PAM Registration number -
*Saya memperakui bahawa detail-detail dalam pelan-pelan ini adalah
(Wilayah Persekutuan Kuala Lumpur) 1954 dan saya setuju terima
terima tanggungjawab penuh dengan sewajarnya.
DRAWING NO.:
DRAWN BY CHECKED BY
DATE
SCALE
MR. PRINCE FAVIS ISIP
25TH NOV 2015
5
CH'NG XING YUE
R.C.BEAM AND
SLAB TO ENGR'S
DETAIL
BAMBOO ROOF
STRUCTURE
WITH PROFILED
STEEL ROOFING
SHEET
300mm THK GREEN ROOF SYSTEM
W/ 150mm SOIL DEPTH
1000MM HIGH WROUGHT IRON FIRE
STAIRCASE HANDRAIL
200mm THK CONCRETE WALL
R.C GROUND
COLUMN AND
PILE CAP TO
ENGR'S DETAIL
300mm THK R.C.
RETAINING WALL
TO ENGR'S DETAIL
ALUMINIUM FRAME
SLIDING GLASS
PANELS
TO SUPPLIER'S
DETAIL
Ø100mm BAMBOO
COLUMN (BAMBUSA
MULTIPLEX) TREATED
WITH SODIUM
BORATE TO ARCH'S
DETAIL
ALUMINIUM FRAME SLIDING GLASS
PANELS TO SUPPLIER'S DETAIL
300mm THK GREEN ROOF SYSTEM
W/ 150mm SOIL DEPTH
BAMBOO ROOF STRUCTURE
WITH PROFILED STEEL
ROOFING SHEET
2. VOID
VOIDVOID
GROUND LEVEL
FFL 0.000
FIRST FLOOR LEVEL
FFL +7.900
ROOF TOP LEVEL
FFL +17.050
UPPER GROUND LEVEL
FFL +3.400
UPPER GROUND LEVEL
FFL +4.000
LOWER GROUND LEVEL
FFL +0.100
ROOF TOP LEVEL
FFL +12.300
1 2 3 4 5 6 7 8 9 10 11 12
SECOND FLOOR LEVEL
FFL +11.150
OPEN TOOLS
WORKSHOP
FFL 4.000
OPEN
SCREENING
SHOP
FFL 4.000
EXHIBITION
FFL 3.400
RESOURCE
LIBRARY
FFL 4.000
MACHINERY
ROOM
FFL 4.000
BRIDGE
5.200
DRTEL
ELE CW
EXHIBITION
FFL 2.800
DOWN
DOWN
FFL 4.000
FFL 4.000
RECEPTION
UP
1
2
3
4
5
6
7
8
9
10
11
21
20
19
18
17
16
15
14
13
12
22
UP
1
2
3
4
5
6
7
8
9
10
21
20
19
18
17
16
15
14
13
1211
22
GREEN SPACE
1.2
UP
1
2
2.2
1:100
2
ELEVATION
2.0
CONSTRUCTION DRAWING
menurut kehendak-kehendak undang-undang Bangunan Seragam
CIVIL & STRUCTURE ENGINEER :
Taman Melaka Raya,
Tel/Fax : 6082-233666
Melaka, Malaysia.
No.1, 1-1 & 1-2, Jalan Melaka Raya 30,
Tropikamaju Construction Engineering Sdn Bhd(No Syarikat :417634A)
MECHANICAL & ELECTRICAL ENGINEER :
Kawasan Perindustrian HICOM,
Tel/Fax : 6082-233666
Seksyen 26, Malaysia.
No 2A, Jalan Serendah 26/39,
Buler Engineering Sdn. Bhd. (No Syarikat : 641462-W)
QUANTITY SURVEYOR :
Taman Ungku Tun Aminah,
Tel/Fax : 6082-233666
Shanh Alam, Malaysia.
No.24,Jalan Asia Maju 30,
LEE Consultant Sdn Bhd (No Syarikat :5265637S)
Company Chop & Signature
PROJECT:
SHEET NO.:
ARCHITECT:
Signature
DRAWING TITLE:
CLIENT:
EFFECTOR CORPORATION
EFFECTOR CORPORATION
MR. PRINCE FAVIS ISIP
No. 1 Jalan Taylor's,
47500 Subang Jaya,
Tel: 603-5629 5000 Fax: 603-5629 5001
Selangor Darul Ehsan, Malaysia.
No. 1 Jalan Taylor's,
47500 Subang Jaya,
Selangor Darul Ehsan, Malaysia.
GENERAL NOTES
1. THIS DRAWING IS COPYRIGHT AND IS THE PROPERTY OF
EFFECTOR CORPORATION. NO PART OR WHOLE DRAWINGS
SHALL BE COPIED/REPRODUCED WITHOUT PERMISSION.
2. CONTRACTORS MUST CHECK ALL DIMENSION ON SITE. ONLY
FIGURE DIMENSIONS ARE TO BE WORKED ON.
3. ALL DISCREPANCIES MUST BE REPORTED IMMEDIATELY TO
THE ARCHITECT BEFORE PROCEEDING.
Ar. CH'NG XING YUE
Professional Architect
B.Sc. (HONOURS) (ARCHITECTURE)
PAM Registration number -
*Saya memperakui bahawa detail-detail dalam pelan-pelan ini adalah
(Wilayah Persekutuan Kuala Lumpur) 1954 dan saya setuju terima
terima tanggungjawab penuh dengan sewajarnya.
DRAWING NO.:
DRAWN BY CHECKED BY
DATE
SCALE
MR. PRINCE FAVIS ISIP
25TH NOV 2015
5
CH'NG XING YUE
115mm THK BRICK
WALL W/ 19mm THK
PLASTERING AT
BOTH SIDE
BAMBOO ROOF
STRUCTURE WITH
PROFILED STEEL
ROOFING SHEET
300mm THK GREEN ROOF SYSTEM
W/ 150mm SOIL DEPTH
1000MM HIGH WROUGHT IRON FIRE
STAIRCASE HANDRAIL
ALUMINIUM FRAME SLIDING GLASS
PANELS TO SUPPLIER'S DETAIL
ALUMINIUM FRAME
SLIDING GLASS
PANELS TO
SUPPLIER'S DETAIL
Ø100mm BAMBOO COLUMN
(BAMBUSA MULTIPLEX) TREATED
WITH SODIUM BORATE TO ARCH'S
DETAIL
BAMBOO ROOF
STRUCTURE WITH
PROFILED STEEL
ROOFING SHEET
3. UPPER GROUND LEVEL
FFL +4.000
LOWER GROUND LEVEL
FFL +0.100
GROUND LEVEL
FFL 0.000
FIRST FLOOR LEVEL
FFL +7.900
UPPER GROUND LEVEL
FFL +3.400
ROOF TOP LEVEL
FFL +12.300
SECOND FLOOR LEVEL
FFL +7.900
BLOW UP DETAIL 1
BLOW UP DETAIL 2
210050010202880
1325
11003250
500
500
155
600
30
200
100
1325
14
150
100
200
140
500
450
400
130
1:30
3
FULL WALL SECTION AND
3.0
CONSTRUCTION DRAWING
menurut kehendak-kehendak undang-undang Bangunan Seragam
CIVIL & STRUCTURE ENGINEER :
Taman Melaka Raya,
Tel/Fax : 6082-233666
Melaka, Malaysia.
No.1, 1-1 & 1-2, Jalan Melaka Raya 30,
Tropikamaju Construction Engineering Sdn Bhd(No Syarikat :417634A)
MECHANICAL & ELECTRICAL ENGINEER :
Kawasan Perindustrian HICOM,
Tel/Fax : 6082-233666
Seksyen 26, Malaysia.
No 2A, Jalan Serendah 26/39,
Buler Engineering Sdn. Bhd. (No Syarikat : 641462-W)
QUANTITY SURVEYOR :
Taman Ungku Tun Aminah,
Tel/Fax : 6082-233666
Shanh Alam, Malaysia.
No.24,Jalan Asia Maju 30,
LEE Consultant Sdn Bhd (No Syarikat :5265637S)
Company Chop & Signature
PROJECT:
SHEET NO.:
ARCHITECT:
Signature
DRAWING TITLE:
CLIENT:
EFFECTOR CORPORATION
EFFECTOR CORPORATION
MR. PRINCE FAVIS ISIP
No. 1 Jalan Taylor's,
47500 Subang Jaya,
Tel: 603-5629 5000 Fax: 603-5629 5001
Selangor Darul Ehsan, Malaysia.
No. 1 Jalan Taylor's,
47500 Subang Jaya,
Selangor Darul Ehsan, Malaysia.
GENERAL NOTES
1. THIS DRAWING IS COPYRIGHT AND IS THE PROPERTY OF
EFFECTOR CORPORATION. NO PART OR WHOLE DRAWINGS
SHALL BE COPIED/REPRODUCED WITHOUT PERMISSION.
2. CONTRACTORS MUST CHECK ALL DIMENSION ON SITE. ONLY
FIGURE DIMENSIONS ARE TO BE WORKED ON.
3. ALL DISCREPANCIES MUST BE REPORTED IMMEDIATELY TO
THE ARCHITECT BEFORE PROCEEDING.
Ar. CH'NG XING YUE
Professional Architect
B.Sc. (HONOURS) (ARCHITECTURE)
PAM Registration number -
*Saya memperakui bahawa detail-detail dalam pelan-pelan ini adalah
(Wilayah Persekutuan Kuala Lumpur) 1954 dan saya setuju terima
terima tanggungjawab penuh dengan sewajarnya.
DRAWING NO.:
DRAWN BY CHECKED BY
DATE
SCALE
MR. PRINCE FAVIS ISIP
25TH NOV 2015
5
CH'NG XING YUE
500mm x Ø80mm
BAMBOO SUPPORT
BETWEEN RAFTERS
STEEL DOWEL WITH
NUT AND BOLT
NYLON LASHING
500mm xØ80mm
BAMBOO SUPPORT
BETWEEN RAFTERS
ALUMINIUM FRAME
SLIDING GLASS PANELS
TO SUPPLIER'S DETAIL
TRIPLE LAYERS
Ø100mm BAMBOO
RAFTER (BAMBUSA
MULTIPLEX)
FASCIA
RAINWATER GUTTER
GUTTER STRAP FOR
EXTRA SUPPORT
DRIP EDGE
9MM DOUBLE
ALUMINIUM FOIL
SHEET WITH
INSULATION
GALVANIZED
FASCIA
BRACKET
115mm THK BRICK
WALL W/ 19mm THK
PLASTERING AT
BOTH SIDE
PROFILED METAL
ROOFING SHEET
ALUMINIUM FRAME
SLIDING GLASS PANELS
TO SUPPLIER'S DETAIL
STEEL DOWEL WITH
NUT AND BOLT
NYLON LASHING
500mm xØ80mm
BAMBOO SUPPORT
BETWEEN RAFTERS
DOUBLE LAYERS Ø100mm
BAMBOO RAFTER
(BAMBUSA MULTIPLEX)
R.C.BEAM AND SLAB TO
ENGR'S DETAIL
Ø80mm BAMBOO
COLUMN SUPPORTING
RAFTER
BLOW UP DETAILS
R.C GROUND COLUMN
AND PILE CAP TO
ENGR'S DETAIL
R.C.BEAM AND SLAB TO
ENGR'S DETAIL
ALUMINIUM FRAME
SLIDING GLASS
PANELS TO
SUPPLIER'S DETAIL
BAMBOO ROOF
STRUCTURE WITH
PROFILED STEEL
ROOFING SHEET
115mm THK BRICK
WALL W/ 19mm THK
PLASTERING AT
BOTH SIDE
Ø80mm BAMBOO
COLUMN SUPPORTING
RAFTER
4. UP
8
7
6
5
4
3
2
1
9
17
16
15
14
13
12
11
10
18
5700
1650
5.2
A
1540 260
180220220230
900
5.3
B
800
290 30
60
THREAD LEVEL
220220230
900
LOWER GROUND LEVEL
FFL +0.100
GROUND LEVEL
FFL 0.000
DETAIL A
5.3
B
UPPER GROUND LEVEL
FFL +3.400
OPEN TOOLS
WORKSHOP
FFL 4.000
OPEN
SCREENING
SHOP
FFL 4.000
EXHIBITION
FFL 3.400
RESOURCE
LIBRARY
FFL 4.000
MACHINERY
ROOM
FFL 4.000
BRIDGE
5.200
DRTEL
ELE CW
EXHIBITION
FFL 2.800
DOWN
DOWN
FFL 4.000
FFL 4.000
RECEPTION
UP
1
2
3
4
5
6
7
8
9
10
11
21
20
19
18
17
16
15
14
13
12
22
UP
1
2
3
4
5
6
7
8
9
10
21
20
19
18
17
16
15
14
13
1211
22
GREEN SPACE
UP
1.2
1
2.2
2
AS SHOWN
4
STAIRCASE DETAIL
4.0
CONSTRUCTION DRAWING
menurut kehendak-kehendak undang-undang Bangunan Seragam
CIVIL & STRUCTURE ENGINEER :
Taman Melaka Raya,
Tel/Fax : 6082-233666
Melaka, Malaysia.
No.1, 1-1 & 1-2, Jalan Melaka Raya 30,
Tropikamaju Construction Engineering Sdn Bhd(No Syarikat :417634A)
MECHANICAL & ELECTRICAL ENGINEER :
Kawasan Perindustrian HICOM,
Tel/Fax : 6082-233666
Seksyen 26, Malaysia.
No 2A, Jalan Serendah 26/39,
Buler Engineering Sdn. Bhd. (No Syarikat : 641462-W)
QUANTITY SURVEYOR :
Taman Ungku Tun Aminah,
Tel/Fax : 6082-233666
Shanh Alam, Malaysia.
No.24,Jalan Asia Maju 30,
LEE Consultant Sdn Bhd (No Syarikat :5265637S)
Company Chop & Signature
PROJECT:
SHEET NO.:
ARCHITECT:
Signature
DRAWING TITLE:
CLIENT:
EFFECTOR CORPORATION
EFFECTOR CORPORATION
MR. PRINCE FAVIS ISIP
No. 1 Jalan Taylor's,
47500 Subang Jaya,
Tel: 603-5629 5000 Fax: 603-5629 5001
Selangor Darul Ehsan, Malaysia.
No. 1 Jalan Taylor's,
47500 Subang Jaya,
Selangor Darul Ehsan, Malaysia.
GENERAL NOTES
1. THIS DRAWING IS COPYRIGHT AND IS THE PROPERTY OF
EFFECTOR CORPORATION. NO PART OR WHOLE DRAWINGS
SHALL BE COPIED/REPRODUCED WITHOUT PERMISSION.
2. CONTRACTORS MUST CHECK ALL DIMENSION ON SITE. ONLY
FIGURE DIMENSIONS ARE TO BE WORKED ON.
3. ALL DISCREPANCIES MUST BE REPORTED IMMEDIATELY TO
THE ARCHITECT BEFORE PROCEEDING.
Ar. CH'NG XING YUE
Professional Architect
B.Sc. (HONOURS) (ARCHITECTURE)
PAM Registration number -
*Saya memperakui bahawa detail-detail dalam pelan-pelan ini adalah
(Wilayah Persekutuan Kuala Lumpur) 1954 dan saya setuju terima
terima tanggungjawab penuh dengan sewajarnya.
DRAWING NO.:
DRAWN BY CHECKED BY
DATE
SCALE
MR. PRINCE FAVIS ISIP
25TH NOV 2015
5
CH'NG XING YUE
Ø60mm x 2mm THK S.S. CHS HANDRAIL
Ø30mm x 2mm THK S.S. CHS
INTERMEDIATE RAIL
50mm x 12mm THK S.S. BAR FLAT BALUSTER
WELDED TO S.S. STRINGER
30mm THK RECYCLED TIMBER TREAD SCREWED TO
S.S. STAGGERED STRINGER
20mm x 10mm THK S.S STAGGERED STRINGER
150mm x 12mm THK S.S CHANNEL STRINGER
Ø60mm x 2mm THK S.S. CHS HANDRAIL
50mm x 12mm THK S.S. BAR FLAT BALUSTER
Ø30mm x 2mm THK S.S. CHS INTERMEDIATE RAIL
30mm THK RECYCLED TIMBER TREAD
12mm THK S.S PLATE STRINGER
150mm x 12mm THK S.S CHANNEL STRINGER
10mm THK U-PROFILE S.S. CHANNEL
CLIP ANGLE W/ ANCHOR BOLTS
TO SECURE STRINGER TO FLOOR STRUCTURE
150mm THK R.C. SLAB TO ENGR'S DETAILS
STEEL STAIRCASE
R= 180mm x 18
T= 260mm
NOSING = 25mm
5. 5.6
A
A
5.7
B
C
5.8
18908008006001150
5440
18908008007001120
5440
200 900 650 2800 625 900 200
4
5
A B
6275
140mm THK BRICK WALL WITH 19MM CEMENT PLASTER ON THE
EXTERNAL WALL AND SELECTED WALL TILES TO UNDERSIDE OF SLAB
300mm x 300mm HOMOGENEOUS TILES TO ARCH'S SPECS
30mm THK LAMINATED PHENOLIC PANEL TO ENGR'S DETAIL
50mm THK GYPSUM BOARD TO ARCH'S SPECS
R.C.BEAM AND SLAB TO ENGR'S DETAIL
MALE TOILET
CONCRETE SINK TO ARCH'S SPECS
SELECTED SURFACE MOUNTED TOILET PAPER DISPENSER
TO SPECIFICATION
Ø100mm BAMBOO (BAMBUSA MULTIPLEX) TREATED
WITH SODIUM BORATE TO ARCH'S DETAIL
STEEL ANGLE TO HOLD BAMBOO
VOID
4 5
DETAIL A
UPPER GROUND LEVEL
FFL +4.000
3150400
900
3750
80mm X 60mm STAINLESS
STEEL ANGLE BRACKET
Ø30mm STAINLESS STEEL
CUBICLE LEG ANCHORED BY
S.S. SCREW TO GROUND
30mm THK LAMINATED PHENOLIC
PANEL TO ENGR'S DETAIL
300mm x 300mm HOMOGENEOUS
TILES TO ARCH'S SPECS
25200280
30
Ø40mm S-TRAP AND PVC PIPE
Ø22mm WATER SUPPLY PIPE
FROM WATER TANK
SERVICE VALVE
DOUBLE ACTING
NON-RETURN VALVE
TAP
CONCRETE SINK TO ARCH'S SPECS
360
660240
140
500
120
900
Ø75mm DISCHARGE PIPE
AND CONNECTION
FEMALE TOILET
140mm THK BRICK WALL WITH 19MM
CEMENT PLASTER ON THE EXTERNAL
WALL AND SELECTED WALL TILES TO
UNDERSIDE OF SLAB
300mm x 300mm HOMOGENEOUS TILES TO ARCH'S SPECS
50mm THK GYPSUM BOARD TO ARCH'S SPECS
R.C.BEAM AND SLAB TO ENGR'S DETAIL
CONCRETE SINK TO ARCH'S SPECS
SELECTED SURFACE MOUNTED
TOILET PAPER DISPENSER
TO SPECIFICATION
30mm THK LAMINATED PHENOLIC PANEL TO ENGR'S DETAIL
VOID
5 4
DETAIL A
UPPER GROUND LEVEL
FFL +4.000
Ø100mm BAMBOO (BAMBUSA
MULTIPLEX) TREATED WITH SODIUM
BORATE TO ARCH'S DETAIL
2000
1080
16958108102001750
5640
900mm x 1800mm x 8mm THK FROSTED TEMPERED
GLASS FIXED TO Ø30mm GLASS FITTINGS TO
ARCH'S SPECS
SELECTED ALUMINIUM FRAMED MIRROR TO
ARCH'S DETAIL
SELECTED SURFACE MOUNTED TOILET PAPER
DISPENSER TO SPECIFICATION
140mm THK BRICK WALL WITH 19MM CEMENT
PLASTER ON THE EXTERNAL WALL AND
SELECTED WALL TILES TO UNDERSIDE OF SLAB
CONCRETE SINK TO ARCH'S SPECS
B A
UPPER GROUND LEVEL
FFL +4.000
3750
2700
1200
900 9004075200 200
6275
300mm x 300mm HOMOGENEOUS TILES TO ARCH'S SPECS
900mm x 1800mm x 8mm THK
FROSTED TEMPERED GLASS
FIXED TO Ø30mm GLASS
FITTINGS TO ARCH'S SPECS
R.C.BEAM AND SLAB TO ENGR'S DETAIL
140mm THK BRICK WALL WITH 19MM CEMENT PLASTER
ON THE EXTERNAL WALL AND SELECTED WALL TILES
TO UNDERSIDE OF SLAB
50mm THK GYPSUM BOARD TO ARCH'S SPECS
POWDER COATED ALUMINIUM FIXED WINDOW
WITH 6MM GLASS TO ARCH'S SPECS
30mm THK LAMINATED PHENOLIC PANEL TO ENGR'S DETAIL
VOID
DETAIL B
A B
UPPER GROUND LEVEL
FFL +4.000
Ø100mm BAMBOO (BAMBUSA MULTIPLEX) TREATED
WITH SODIUM BORATE TO ARCH'S DETAIL
900mm HIGH WROUGHT IRON
HANDRAIL
1425
670
1025
8501700600
3750
1800 1800 102598070
6075
OPEN TOOLS
WORKSHOP
FFL 4.000
OPEN
SCREENING
SHOP
FFL 4.000
EXHIBITION
FFL 3.400
RESOURCE
LIBRARY
FFL 4.000
MACHINERY
ROOM
FFL 4.000
BRIDGE
5.200
DRTEL
ELE CW
EXHIBITION
FFL 2.800
DOWN
DOWN
FFL 4.000
FFL 4.000
RECEPTION
UP
1
2
3
4
5
6
7
8
9
10
11
21
20
19
18
17
16
15
14
13
12
22
UP
1
2
3
4
5
6
7
8
9
10
21
20
19
18
17
16
15
14
13
1211
22
GREEN SPACE
UP
1.2
1
2.2
2
AS SHOWN
5
TOILET DETAIL
5.0
CONSTRUCTION DRAWING
menurut kehendak-kehendak undang-undang Bangunan Seragam
CIVIL & STRUCTURE ENGINEER :
Taman Melaka Raya,
Tel/Fax : 6082-233666
Melaka, Malaysia.
No.1, 1-1 & 1-2, Jalan Melaka Raya 30,
Tropikamaju Construction Engineering Sdn Bhd(No Syarikat :417634A)
MECHANICAL & ELECTRICAL ENGINEER :
Kawasan Perindustrian HICOM,
Tel/Fax : 6082-233666
Seksyen 26, Malaysia.
No 2A, Jalan Serendah 26/39,
Buler Engineering Sdn. Bhd. (No Syarikat : 641462-W)
QUANTITY SURVEYOR :
Taman Ungku Tun Aminah,
Tel/Fax : 6082-233666
Shanh Alam, Malaysia.
No.24,Jalan Asia Maju 30,
LEE Consultant Sdn Bhd (No Syarikat :5265637S)
Company Chop & Signature
PROJECT:
SHEET NO.:
ARCHITECT:
Signature
DRAWING TITLE:
CLIENT:
EFFECTOR CORPORATION
EFFECTOR CORPORATION
MR. PRINCE FAVIS ISIP
No. 1 Jalan Taylor's,
47500 Subang Jaya,
Tel: 603-5629 5000 Fax: 603-5629 5001
Selangor Darul Ehsan, Malaysia.
No. 1 Jalan Taylor's,
47500 Subang Jaya,
Selangor Darul Ehsan, Malaysia.
GENERAL NOTES
1. THIS DRAWING IS COPYRIGHT AND IS THE PROPERTY OF
EFFECTOR CORPORATION. NO PART OR WHOLE DRAWINGS
SHALL BE COPIED/REPRODUCED WITHOUT PERMISSION.
2. CONTRACTORS MUST CHECK ALL DIMENSION ON SITE. ONLY
FIGURE DIMENSIONS ARE TO BE WORKED ON.
3. ALL DISCREPANCIES MUST BE REPORTED IMMEDIATELY TO
THE ARCHITECT BEFORE PROCEEDING.
Ar. CH'NG XING YUE
Professional Architect
B.Sc. (HONOURS) (ARCHITECTURE)
PAM Registration number -
*Saya memperakui bahawa detail-detail dalam pelan-pelan ini adalah
(Wilayah Persekutuan Kuala Lumpur) 1954 dan saya setuju terima
terima tanggungjawab penuh dengan sewajarnya.
DRAWING NO.:
DRAWN BY CHECKED BY
DATE
SCALE
MR. PRINCE FAVIS ISIP
25TH NOV 2015
5
CH'NG XING YUE