SlideShare a Scribd company logo
1 of 15
Download to read offline
©JGC
Indonesia
©JGC Indonesia
Sumbawa LNG Terminal
& Regas Facility Project
PICA | ARMOR ROCK SUPPLY (Live Doc.)
(Problem, Identification & Corrective Action)
Sumbawa, 07 March 2024
Rev. 05
@ws
©JGC
Indonesia
K. AMNT MINING QUARRY AT A GLANCE
26
©JGC
Indonesia
K.1 ARM0R ROCK LAB. RESULT
27
Conclusion:
Armor rock from AMNT mining area has been tested at Sucofindo
and comply with approved project specification.
©JGC
Indonesia
K.2 ARM0R ROCK DUMPING LOCATION
28
Conclusion:
Armor rock from AMNT mining
area will be dumped out to
dumping location at AMNT
Regas area (Laydown E – 2010
m2 approx.).
©JGC
Indonesia
K.3 ARM0R ROCK DUMPING LOCATION JOIN SURVEY
29
Conclusion:
AMNT, CPY, CTR (JGC/PDP) conducted join survey on
29 February 2024 and all parties confirmed and
agreed with the proposed armor rock dumping area.
©JGC
Indonesia
K.4 AMNT - CHANGE MANAGEMENT PLAN
30
Conclusion:
Change Management
Plan (CMP) has been
approved by AMNT
authority and CTR is
allowed to use armor rock
from mining area.
©JGC
Indonesia
K.5. CONTRACTOR READINESS
31
Checklist:
✓ Authority to Work (ATW) → Approved
✓ Excavator → Available
✓ Tower Lamp → Available
✓ Operator Shelter → Available
✓ Site Preparation → Done
✓ HDPE Pipe Shifting → Done
K.5.1 Laydown-E Readiness
©JGC
Indonesia
K.5. CONTRACTOR READINESS
32
✓ Escort Driver #1 - Day Shift
K.5.2 Manpower
✓ Escort Driver #2 - Night Shift
Superintendent:
✓ Harly Maulana
HSSE:
✓ Sulthana Caesa Adiya (Day Shift)
✓ Matari Intan Pranata (Night Shift)
Spotter:
✓ Tuslihun (Day Shift)
✓ Arifin (Day Shift)
✓ Mafud (Night Shift)
✓ Widiyatmoko (Night Shift)
©JGC
Indonesia
K.5. CONTRACTOR READINESS
33
Checklist:
✓ Escort vehicle (1 unit)
✓ Escort board : “Escort Vehicle” and “Over Size” Type (1 unit).
K.5.3 Escort Vehicle & Board
©JGC
Indonesia
K.6 SCHEDULE
34
K.6.1 Armor Rock Delivery Schedule
Date Time Location Activity Remark
8 March 2024 07:00 am Pondok CWA 02
Section 6
Pre-Safety Briefing All required CTR’s manpower
shall attend to this location
i.e., SI, HSSE, Escort Driver,
Spotter.
08:00 am -
Finish
AMNT Mining to
LNG Regas area
(Vice versa)
1st Delivery of Armor
Rock Material
CTR to be assisted by AMNT
Escort team for day shift (3
(three) first trips) and night
shift (3 (three) first trips).
Agreed Completion
Date
Day shift:
07:00 am -
04:00 pm
Night shift:
07:00 pm -
04:00 am
AMNT Mining to
LNG Regas area
(Vice versa)
Delivery of Armor Rock
Material
ADT to be escorted by CTR
with CPY approval and
guidance.
Table-K.6.1. Armor Rock Delivery Schedule
©JGC
Indonesia
K.7 FIRST MEETING POINT
35
K.7.1 Pondok CWA 02 Section 6
©JGC
Indonesia
L. CONTRACTOR COUNTERMEASURES #2
36
No. Description/Summary Action by Due Date
Remar
ks
A CONSTRUCTION (CONST)
1 AMNT, JGC and PDP have conducted join survey to the proposed armor rock
dumping area on 29 February 2024. As supported by CPY, the armor rock quarry will
be located at AMNT mining area.
ALL Info CLOSE
2 AMNT informed that 7 meter wide along the west toe slope shall be free from any
activity and will be utilized for shotcrete Contractor.
CPY Info CLOSE
3 AMNT confirmed to use three (3) ADT to transporting armor rock from AMNT loading
point to AMNT dumping point.
CPY ASAP Open
4 AMNT will apply two shift (day and night shift) delivery with 2 trips for each shift. The
total ADT delivery are 12 trips/day.
CPY ASAP Open
5 CTR will provide 1 (one) escort car for every armor rock delivery (3 ADT for each trip).
→ Day shift JGC: Neksen (G-LV04) | NV 8467 | DK 8656 DJ
→ Night shift PDP: Muhtar (G-LV04) | NV 8609 | F 8867 HT
CTR/PDP Continue Open
6 CPY will ensure the availability of armor rock acid test to AMNT mining and inform
the result to CTR later on. → CTR/PDP in-progress for acid testing of armor rock (1
week duration approx). → Continue
CPY 1 March 2024
12 March 2024
Open
7 CTR to mobilize excavator to the dumping area and shifting the existing HDPE pipe to
west area (near to the toe slope). → CTR has mobilized excavator to laydown E and
in progress for shifting HDPE pipe. → This activity is completed.
CTR/PDP 1 March 2024
2 March 2024
6 March 2024
Open
CLOSE
8 CTR to provide lamp tower at dumping area for night shift purpose. → CTR to
mobilize tower lamp on 6 March 2024. → This activity is completed.
CTR 1 March 2024
3 March 2024
6 March 2024
Open
CLOSE
©JGC
Indonesia
L. CONTRACTOR COUNTERMEASURES #2
37
No. Description/Summary Action by Due Date Remarks
A CONSTRUCTION (CONST)
9 CPY informed that currently the permit and CMP (Change Management Plan) are
being reviewed internally and it is expected the 1st armor rock delivery can be
proceed on 4-5 March 2024. → AMNT inform that the permit/CMP had been
approved by KTT on 2 March 2024.
CPY 4-5 March 2024
2 March 2024
Open
CLOSE
10 Related to armor rock acid test, CTR also request to CPY to provide rock specimen
with 250-300 mm diameter.
<Post Meeting Notes>
CPY confirmed and CTR is allowed to picking up the rock material at MMA AMNT
Office. → CTR had picking up the armor rock specimen on 1 March 2024 at MMA
AMNT office.
CPY 29 February
2024
1 March 2024
Open
CLOSE
11 Split of Work & Supply:
▪ Armor Rock Transportation from AMNT Shift Change Shelter Pondok CWA 02 Section
6 area to AMNT Regas Dumping area → AMNT Mining
▪ Armor Rock screening and selection work → CTR
▪ Armor Rock Transportation from AMNT Regas Dumping area to Causeway area.
→ CTR
ALL ASAP Open
12 CPY to provide armor rock with minimum weight of 200 kg/pcs or 600 mm diameter. CPY ASAP Open
13 In case in this proposed dumping area are fully occupied, CTR will utilize the other
AMNT laydown area.
ALL Info CLOSE
©JGC
Indonesia
L. CONTRACTOR COUNTERMEASURES #2
38
No. Description/Summary Action by Due Date Remarks
A CONSTRUCTION (CONST)
14 CTR to prepare ATW for shifting HDPE pipe and armor rock screening at AMNT
dumping area (Laydown E). → ATW is now being reviewed by CPY → ATW for day
shift had been approved by CPY on 2 March 2024.
CTR/PDP 1 March 2024
2 March 2024
Continue
Open
15 CTR to provide shelter for personnel rest area.→ This activity is completed. CTR/PDP 2 March 2024
3 March 2024
6 March 2024
Open
CLOSE
16 MAR for armor rock doc. No. V-31M0-001-A-426 Rev. 2 has been submitted to CPY
with approval code B.
CTR/PDP Info CLOSE
17 CTR to mobilize related heavy equipment to AMNT dumping area → Excavator and
stone breaker. → As of 5 March 2024, CTR has mobilized excavator to Laydown E.
Stone braker to be provided by CTR immediately. → Continue for mobilization stone
breaker
CTR/PDP 4 March 2024
2 March 2024
3 March 2024
6 March 2024
Continue
Open
18 Safety briefing to be conducted at Shift Change area at 07:00 am (Sumbawa time) for
escorter and spotter. → This activity was postponed due to new underground facility
at around Gate2A is still under construction and will be tentatively opened on 6
March 2024. → Resume on 8 March 2024 at Pondok CWA 02 Section 6.
ALL 3 March 2024
6 March 2024
8 March 2024
Open
19 CTR to be assisted by AMNT Escort team for day shift (3 trips) and night shift (3
trips).
CPY 8 March 2024 Open
©JGC
Indonesia
39

More Related Content

Similar to 2024.03.07 PICA Armor Rock_Rev. 05 (Live Doc.)_CPY.pdf

DATA2015-12-06 Ashghal Presentation 2
DATA2015-12-06 Ashghal Presentation 2DATA2015-12-06 Ashghal Presentation 2
DATA2015-12-06 Ashghal Presentation 2
Ian Kelly
 
M rly presentation_22.5.13
M rly presentation_22.5.13M rly presentation_22.5.13
M rly presentation_22.5.13
rdhyshym
 
2015 First Quarter Budget Review
2015 First Quarter Budget Review2015 First Quarter Budget Review
2015 First Quarter Budget Review
Gibson Ali Holemba
 
QP_Safety_executive_procedure_final
QP_Safety_executive_procedure_finalQP_Safety_executive_procedure_final
QP_Safety_executive_procedure_final
Ian Kelly
 
ALVIN'S CURRICULUM VITAE 2017
ALVIN'S CURRICULUM VITAE 2017ALVIN'S CURRICULUM VITAE 2017
ALVIN'S CURRICULUM VITAE 2017
Alvin Chen
 
Resume- Tiwari
Resume- TiwariResume- Tiwari
Resume- Tiwari
Ak Tiwari
 
Remote Region LNG Supply Study - Makassar Project
Remote Region LNG Supply Study - Makassar ProjectRemote Region LNG Supply Study - Makassar Project
Remote Region LNG Supply Study - Makassar Project
Achmad Agung P
 
Financial viability report_-_may_21,2010
Financial viability report_-_may_21,2010Financial viability report_-_may_21,2010
Financial viability report_-_may_21,2010
PRABIR DATTA
 
cvPaoloAguzziNov16
cvPaoloAguzziNov16cvPaoloAguzziNov16
cvPaoloAguzziNov16
Paolo Aguzzi
 
OCS CV Field Engr_Aaron Lian Kian Hoe_April 15
OCS CV Field Engr_Aaron Lian Kian Hoe_April 15OCS CV Field Engr_Aaron Lian Kian Hoe_April 15
OCS CV Field Engr_Aaron Lian Kian Hoe_April 15
Aaron Lian Kian Hoe
 

Similar to 2024.03.07 PICA Armor Rock_Rev. 05 (Live Doc.)_CPY.pdf (20)

DATA2015-12-06 Ashghal Presentation 2
DATA2015-12-06 Ashghal Presentation 2DATA2015-12-06 Ashghal Presentation 2
DATA2015-12-06 Ashghal Presentation 2
 
M rly presentation_22.5.13
M rly presentation_22.5.13M rly presentation_22.5.13
M rly presentation_22.5.13
 
2015 First Quarter Budget Review
2015 First Quarter Budget Review2015 First Quarter Budget Review
2015 First Quarter Budget Review
 
QP_Safety_executive_procedure_final
QP_Safety_executive_procedure_finalQP_Safety_executive_procedure_final
QP_Safety_executive_procedure_final
 
Design Status.pptx
Design Status.pptxDesign Status.pptx
Design Status.pptx
 
Power Plant Demobilisation
Power Plant DemobilisationPower Plant Demobilisation
Power Plant Demobilisation
 
ALVIN'S CURRICULUM VITAE 2017
ALVIN'S CURRICULUM VITAE 2017ALVIN'S CURRICULUM VITAE 2017
ALVIN'S CURRICULUM VITAE 2017
 
Resume- Tiwari
Resume- TiwariResume- Tiwari
Resume- Tiwari
 
Remote Region LNG Supply Study - Makassar Project
Remote Region LNG Supply Study - Makassar ProjectRemote Region LNG Supply Study - Makassar Project
Remote Region LNG Supply Study - Makassar Project
 
Financial viability report_-_may_21,2010
Financial viability report_-_may_21,2010Financial viability report_-_may_21,2010
Financial viability report_-_may_21,2010
 
cvPaoloAguzziNov16
cvPaoloAguzziNov16cvPaoloAguzziNov16
cvPaoloAguzziNov16
 
Cv paoloaguzzinov16
Cv paoloaguzzinov16Cv paoloaguzzinov16
Cv paoloaguzzinov16
 
Pulak Bhattacharjee-CV
Pulak Bhattacharjee-CVPulak Bhattacharjee-CV
Pulak Bhattacharjee-CV
 
Sbhep vivek kumar
Sbhep vivek kumarSbhep vivek kumar
Sbhep vivek kumar
 
HPCL Shapoorji Environment Impact AssessmentA.pptx
HPCL Shapoorji Environment Impact AssessmentA.pptxHPCL Shapoorji Environment Impact AssessmentA.pptx
HPCL Shapoorji Environment Impact AssessmentA.pptx
 
CV 2017 QC
CV 2017 QCCV 2017 QC
CV 2017 QC
 
Complete Report Of Nelum Jehlum Hydro Electric Project
Complete Report Of Nelum Jehlum Hydro Electric ProjectComplete Report Of Nelum Jehlum Hydro Electric Project
Complete Report Of Nelum Jehlum Hydro Electric Project
 
Project Review Meeting - 14.02.23.ppt
Project Review Meeting - 14.02.23.pptProject Review Meeting - 14.02.23.ppt
Project Review Meeting - 14.02.23.ppt
 
OCS CV Field Engr_Aaron Lian Kian Hoe_April 15
OCS CV Field Engr_Aaron Lian Kian Hoe_April 15OCS CV Field Engr_Aaron Lian Kian Hoe_April 15
OCS CV Field Engr_Aaron Lian Kian Hoe_April 15
 
Pa pipeline kauffman and woomer
Pa pipeline kauffman and woomerPa pipeline kauffman and woomer
Pa pipeline kauffman and woomer
 

Recently uploaded

INTERRUPT CONTROLLER 8259 MICROPROCESSOR
INTERRUPT CONTROLLER 8259 MICROPROCESSORINTERRUPT CONTROLLER 8259 MICROPROCESSOR
INTERRUPT CONTROLLER 8259 MICROPROCESSOR
TanishkaHira1
 
Cybercrimes in the Darknet and Their Detections: A Comprehensive Analysis and...
Cybercrimes in the Darknet and Their Detections: A Comprehensive Analysis and...Cybercrimes in the Darknet and Their Detections: A Comprehensive Analysis and...
Cybercrimes in the Darknet and Their Detections: A Comprehensive Analysis and...
dannyijwest
 
Standard vs Custom Battery Packs - Decoding the Power Play
Standard vs Custom Battery Packs - Decoding the Power PlayStandard vs Custom Battery Packs - Decoding the Power Play
Standard vs Custom Battery Packs - Decoding the Power Play
Epec Engineered Technologies
 
Digital Communication Essentials: DPCM, DM, and ADM .pptx
Digital Communication Essentials: DPCM, DM, and ADM .pptxDigital Communication Essentials: DPCM, DM, and ADM .pptx
Digital Communication Essentials: DPCM, DM, and ADM .pptx
pritamlangde
 
scipt v1.pptxcxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxx...
scipt v1.pptxcxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxx...scipt v1.pptxcxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxx...
scipt v1.pptxcxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxx...
HenryBriggs2
 
Hospital management system project report.pdf
Hospital management system project report.pdfHospital management system project report.pdf
Hospital management system project report.pdf
Kamal Acharya
 
Cara Menggugurkan Sperma Yang Masuk Rahim Biyar Tidak Hamil
Cara Menggugurkan Sperma Yang Masuk Rahim Biyar Tidak HamilCara Menggugurkan Sperma Yang Masuk Rahim Biyar Tidak Hamil
Cara Menggugurkan Sperma Yang Masuk Rahim Biyar Tidak Hamil
Cara Menggugurkan Kandungan 087776558899
 
Integrated Test Rig For HTFE-25 - Neometrix
Integrated Test Rig For HTFE-25 - NeometrixIntegrated Test Rig For HTFE-25 - Neometrix
Integrated Test Rig For HTFE-25 - Neometrix
Neometrix_Engineering_Pvt_Ltd
 

Recently uploaded (20)

Adsorption (mass transfer operations 2) ppt
Adsorption (mass transfer operations 2) pptAdsorption (mass transfer operations 2) ppt
Adsorption (mass transfer operations 2) ppt
 
INTERRUPT CONTROLLER 8259 MICROPROCESSOR
INTERRUPT CONTROLLER 8259 MICROPROCESSORINTERRUPT CONTROLLER 8259 MICROPROCESSOR
INTERRUPT CONTROLLER 8259 MICROPROCESSOR
 
8086 Microprocessor Architecture: 16-bit microprocessor
8086 Microprocessor Architecture: 16-bit microprocessor8086 Microprocessor Architecture: 16-bit microprocessor
8086 Microprocessor Architecture: 16-bit microprocessor
 
Ground Improvement Technique: Earth Reinforcement
Ground Improvement Technique: Earth ReinforcementGround Improvement Technique: Earth Reinforcement
Ground Improvement Technique: Earth Reinforcement
 
Cybercrimes in the Darknet and Their Detections: A Comprehensive Analysis and...
Cybercrimes in the Darknet and Their Detections: A Comprehensive Analysis and...Cybercrimes in the Darknet and Their Detections: A Comprehensive Analysis and...
Cybercrimes in the Darknet and Their Detections: A Comprehensive Analysis and...
 
Danikor Product Catalog- Screw Feeder.pdf
Danikor Product Catalog- Screw Feeder.pdfDanikor Product Catalog- Screw Feeder.pdf
Danikor Product Catalog- Screw Feeder.pdf
 
Standard vs Custom Battery Packs - Decoding the Power Play
Standard vs Custom Battery Packs - Decoding the Power PlayStandard vs Custom Battery Packs - Decoding the Power Play
Standard vs Custom Battery Packs - Decoding the Power Play
 
S1S2 B.Arch MGU - HOA1&2 Module 3 -Temple Architecture of Kerala.pptx
S1S2 B.Arch MGU - HOA1&2 Module 3 -Temple Architecture of Kerala.pptxS1S2 B.Arch MGU - HOA1&2 Module 3 -Temple Architecture of Kerala.pptx
S1S2 B.Arch MGU - HOA1&2 Module 3 -Temple Architecture of Kerala.pptx
 
Digital Communication Essentials: DPCM, DM, and ADM .pptx
Digital Communication Essentials: DPCM, DM, and ADM .pptxDigital Communication Essentials: DPCM, DM, and ADM .pptx
Digital Communication Essentials: DPCM, DM, and ADM .pptx
 
scipt v1.pptxcxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxx...
scipt v1.pptxcxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxx...scipt v1.pptxcxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxx...
scipt v1.pptxcxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxx...
 
Electromagnetic relays used for power system .pptx
Electromagnetic relays used for power system .pptxElectromagnetic relays used for power system .pptx
Electromagnetic relays used for power system .pptx
 
Hospital management system project report.pdf
Hospital management system project report.pdfHospital management system project report.pdf
Hospital management system project report.pdf
 
Design For Accessibility: Getting it right from the start
Design For Accessibility: Getting it right from the startDesign For Accessibility: Getting it right from the start
Design For Accessibility: Getting it right from the start
 
Convergence of Robotics and Gen AI offers excellent opportunities for Entrepr...
Convergence of Robotics and Gen AI offers excellent opportunities for Entrepr...Convergence of Robotics and Gen AI offers excellent opportunities for Entrepr...
Convergence of Robotics and Gen AI offers excellent opportunities for Entrepr...
 
Path loss model, OKUMURA Model, Hata Model
Path loss model, OKUMURA Model, Hata ModelPath loss model, OKUMURA Model, Hata Model
Path loss model, OKUMURA Model, Hata Model
 
Cara Menggugurkan Sperma Yang Masuk Rahim Biyar Tidak Hamil
Cara Menggugurkan Sperma Yang Masuk Rahim Biyar Tidak HamilCara Menggugurkan Sperma Yang Masuk Rahim Biyar Tidak Hamil
Cara Menggugurkan Sperma Yang Masuk Rahim Biyar Tidak Hamil
 
UNIT 4 PTRP final Convergence in probability.pptx
UNIT 4 PTRP final Convergence in probability.pptxUNIT 4 PTRP final Convergence in probability.pptx
UNIT 4 PTRP final Convergence in probability.pptx
 
Integrated Test Rig For HTFE-25 - Neometrix
Integrated Test Rig For HTFE-25 - NeometrixIntegrated Test Rig For HTFE-25 - Neometrix
Integrated Test Rig For HTFE-25 - Neometrix
 
Computer Graphics Introduction To Curves
Computer Graphics Introduction To CurvesComputer Graphics Introduction To Curves
Computer Graphics Introduction To Curves
 
fitting shop and tools used in fitting shop .ppt
fitting shop and tools used in fitting shop .pptfitting shop and tools used in fitting shop .ppt
fitting shop and tools used in fitting shop .ppt
 

2024.03.07 PICA Armor Rock_Rev. 05 (Live Doc.)_CPY.pdf

  • 1. ©JGC Indonesia ©JGC Indonesia Sumbawa LNG Terminal & Regas Facility Project PICA | ARMOR ROCK SUPPLY (Live Doc.) (Problem, Identification & Corrective Action) Sumbawa, 07 March 2024 Rev. 05 @ws
  • 2. ©JGC Indonesia K. AMNT MINING QUARRY AT A GLANCE 26
  • 3. ©JGC Indonesia K.1 ARM0R ROCK LAB. RESULT 27 Conclusion: Armor rock from AMNT mining area has been tested at Sucofindo and comply with approved project specification.
  • 4. ©JGC Indonesia K.2 ARM0R ROCK DUMPING LOCATION 28 Conclusion: Armor rock from AMNT mining area will be dumped out to dumping location at AMNT Regas area (Laydown E – 2010 m2 approx.).
  • 5. ©JGC Indonesia K.3 ARM0R ROCK DUMPING LOCATION JOIN SURVEY 29 Conclusion: AMNT, CPY, CTR (JGC/PDP) conducted join survey on 29 February 2024 and all parties confirmed and agreed with the proposed armor rock dumping area.
  • 6. ©JGC Indonesia K.4 AMNT - CHANGE MANAGEMENT PLAN 30 Conclusion: Change Management Plan (CMP) has been approved by AMNT authority and CTR is allowed to use armor rock from mining area.
  • 7. ©JGC Indonesia K.5. CONTRACTOR READINESS 31 Checklist: ✓ Authority to Work (ATW) → Approved ✓ Excavator → Available ✓ Tower Lamp → Available ✓ Operator Shelter → Available ✓ Site Preparation → Done ✓ HDPE Pipe Shifting → Done K.5.1 Laydown-E Readiness
  • 8. ©JGC Indonesia K.5. CONTRACTOR READINESS 32 ✓ Escort Driver #1 - Day Shift K.5.2 Manpower ✓ Escort Driver #2 - Night Shift Superintendent: ✓ Harly Maulana HSSE: ✓ Sulthana Caesa Adiya (Day Shift) ✓ Matari Intan Pranata (Night Shift) Spotter: ✓ Tuslihun (Day Shift) ✓ Arifin (Day Shift) ✓ Mafud (Night Shift) ✓ Widiyatmoko (Night Shift)
  • 9. ©JGC Indonesia K.5. CONTRACTOR READINESS 33 Checklist: ✓ Escort vehicle (1 unit) ✓ Escort board : “Escort Vehicle” and “Over Size” Type (1 unit). K.5.3 Escort Vehicle & Board
  • 10. ©JGC Indonesia K.6 SCHEDULE 34 K.6.1 Armor Rock Delivery Schedule Date Time Location Activity Remark 8 March 2024 07:00 am Pondok CWA 02 Section 6 Pre-Safety Briefing All required CTR’s manpower shall attend to this location i.e., SI, HSSE, Escort Driver, Spotter. 08:00 am - Finish AMNT Mining to LNG Regas area (Vice versa) 1st Delivery of Armor Rock Material CTR to be assisted by AMNT Escort team for day shift (3 (three) first trips) and night shift (3 (three) first trips). Agreed Completion Date Day shift: 07:00 am - 04:00 pm Night shift: 07:00 pm - 04:00 am AMNT Mining to LNG Regas area (Vice versa) Delivery of Armor Rock Material ADT to be escorted by CTR with CPY approval and guidance. Table-K.6.1. Armor Rock Delivery Schedule
  • 11. ©JGC Indonesia K.7 FIRST MEETING POINT 35 K.7.1 Pondok CWA 02 Section 6
  • 12. ©JGC Indonesia L. CONTRACTOR COUNTERMEASURES #2 36 No. Description/Summary Action by Due Date Remar ks A CONSTRUCTION (CONST) 1 AMNT, JGC and PDP have conducted join survey to the proposed armor rock dumping area on 29 February 2024. As supported by CPY, the armor rock quarry will be located at AMNT mining area. ALL Info CLOSE 2 AMNT informed that 7 meter wide along the west toe slope shall be free from any activity and will be utilized for shotcrete Contractor. CPY Info CLOSE 3 AMNT confirmed to use three (3) ADT to transporting armor rock from AMNT loading point to AMNT dumping point. CPY ASAP Open 4 AMNT will apply two shift (day and night shift) delivery with 2 trips for each shift. The total ADT delivery are 12 trips/day. CPY ASAP Open 5 CTR will provide 1 (one) escort car for every armor rock delivery (3 ADT for each trip). → Day shift JGC: Neksen (G-LV04) | NV 8467 | DK 8656 DJ → Night shift PDP: Muhtar (G-LV04) | NV 8609 | F 8867 HT CTR/PDP Continue Open 6 CPY will ensure the availability of armor rock acid test to AMNT mining and inform the result to CTR later on. → CTR/PDP in-progress for acid testing of armor rock (1 week duration approx). → Continue CPY 1 March 2024 12 March 2024 Open 7 CTR to mobilize excavator to the dumping area and shifting the existing HDPE pipe to west area (near to the toe slope). → CTR has mobilized excavator to laydown E and in progress for shifting HDPE pipe. → This activity is completed. CTR/PDP 1 March 2024 2 March 2024 6 March 2024 Open CLOSE 8 CTR to provide lamp tower at dumping area for night shift purpose. → CTR to mobilize tower lamp on 6 March 2024. → This activity is completed. CTR 1 March 2024 3 March 2024 6 March 2024 Open CLOSE
  • 13. ©JGC Indonesia L. CONTRACTOR COUNTERMEASURES #2 37 No. Description/Summary Action by Due Date Remarks A CONSTRUCTION (CONST) 9 CPY informed that currently the permit and CMP (Change Management Plan) are being reviewed internally and it is expected the 1st armor rock delivery can be proceed on 4-5 March 2024. → AMNT inform that the permit/CMP had been approved by KTT on 2 March 2024. CPY 4-5 March 2024 2 March 2024 Open CLOSE 10 Related to armor rock acid test, CTR also request to CPY to provide rock specimen with 250-300 mm diameter. <Post Meeting Notes> CPY confirmed and CTR is allowed to picking up the rock material at MMA AMNT Office. → CTR had picking up the armor rock specimen on 1 March 2024 at MMA AMNT office. CPY 29 February 2024 1 March 2024 Open CLOSE 11 Split of Work & Supply: ▪ Armor Rock Transportation from AMNT Shift Change Shelter Pondok CWA 02 Section 6 area to AMNT Regas Dumping area → AMNT Mining ▪ Armor Rock screening and selection work → CTR ▪ Armor Rock Transportation from AMNT Regas Dumping area to Causeway area. → CTR ALL ASAP Open 12 CPY to provide armor rock with minimum weight of 200 kg/pcs or 600 mm diameter. CPY ASAP Open 13 In case in this proposed dumping area are fully occupied, CTR will utilize the other AMNT laydown area. ALL Info CLOSE
  • 14. ©JGC Indonesia L. CONTRACTOR COUNTERMEASURES #2 38 No. Description/Summary Action by Due Date Remarks A CONSTRUCTION (CONST) 14 CTR to prepare ATW for shifting HDPE pipe and armor rock screening at AMNT dumping area (Laydown E). → ATW is now being reviewed by CPY → ATW for day shift had been approved by CPY on 2 March 2024. CTR/PDP 1 March 2024 2 March 2024 Continue Open 15 CTR to provide shelter for personnel rest area.→ This activity is completed. CTR/PDP 2 March 2024 3 March 2024 6 March 2024 Open CLOSE 16 MAR for armor rock doc. No. V-31M0-001-A-426 Rev. 2 has been submitted to CPY with approval code B. CTR/PDP Info CLOSE 17 CTR to mobilize related heavy equipment to AMNT dumping area → Excavator and stone breaker. → As of 5 March 2024, CTR has mobilized excavator to Laydown E. Stone braker to be provided by CTR immediately. → Continue for mobilization stone breaker CTR/PDP 4 March 2024 2 March 2024 3 March 2024 6 March 2024 Continue Open 18 Safety briefing to be conducted at Shift Change area at 07:00 am (Sumbawa time) for escorter and spotter. → This activity was postponed due to new underground facility at around Gate2A is still under construction and will be tentatively opened on 6 March 2024. → Resume on 8 March 2024 at Pondok CWA 02 Section 6. ALL 3 March 2024 6 March 2024 8 March 2024 Open 19 CTR to be assisted by AMNT Escort team for day shift (3 trips) and night shift (3 trips). CPY 8 March 2024 Open