SlideShare a Scribd company logo
Project – PML3_US_EHVL_02
Heightening and conversion of existing
220 kV & 132 kV Overhead line
infringing Metro Rail alignment of Pune
Metro Line III
Project Synopsis
Contract No.: PML3_US_EHLV_02
Authority: Pune Metropolitan Region Development Authority
Employer PITCMRL, PUNE
Completion Period: 240 days from LOA ( Package B,C & D - 180 days)
(Package E & F – 240 Days)
LOA Date 15 th March 2022
Contract Value INR 1,10,80,08,369 ( Rs.110.80 Crs) excluding GST
Contractor Rahul Cables Pvt. Ltd.
Bank Guarantee INR 11,08,00,837.00 valid up to 30.06.2025
Contractual Completion
Date
10 th November 2022
Anticipated Completion
Date
30.06.2023
Sailent features of the Project
 The project is for heightening & conversion of existing 220 kV & 132 kV overhead lines which are infringing the Metro
Rail alignment of Pune Metro Line 3 Project to Underground Cable.
 The project work consist of total five packages
 Package 1 – 220 kV S/c Chinchwad – Hinjewadi line between Location No.159 to 163
 Package 2 – 220 kV D/c Chinchwad – Parvati (PRM) line between Location No.16 to 20 Heightening with Monopole
 Package 3 – 132 kV D/C Rahatani – Varasagan line between location No.11 to 16
 Package 4 – 132 kV S/C NCL – Rahatani line between Location No.33 to 38
 Package 5 – 132 kV D/c Chinchwad – Ganeshkhind Line between Loacation 1 to 7 Conversion of OH to UG Cable
 The line is passing through highly traffic zone and the lot of utilities are passing through the proposed cable route.
 In all the heightening works ( Package 1 to 3) monopoles are proposed in the same power corridor and for execution,
outage is must for Monopole erection and stringing work and also utmost safety measures to adhered.
 ROW will play a vital role in this project. As the Monopole designs are unique, change in the position of tower may lead
to change in the type of Monopole and it is time taking process for the new type pole from its design to manufacturing.
Scope of work – Line wise
S No Line name Monopole
(Nos)
UG Cable
(Kms)
Remarks
01 220 kV S/c Chinchwad -
Hinjewadi
4 Nil Tower Nos.160, 161,161A &
162
02 220 kV D/c Chinchwad –
Parvati Flagship
3 Nil Tower Nos.17, 17A & 18
03 132 kV D/c Rahatani –
Varasgan
3 Nil Tower Nos. 13, 14 & 15
04 132 kV S/c NCL - Rahatni 1 1.288 CTT proposed at Tower
No.34A ( Near Vidyanchal
School)
05 132 kV D/c Chinchwad -
Ganeshkhind
1 1.582 CTT proposed at Tower
No.6 (YASHDA premises)
Supply Status (Monopole)
Sl
No
Description Unit Req. Qty Supplied Balance Remarks
1
220 kV S/c
Chinchwad -
Hinjewadi
Nos 4 3 1 Tower No.160 on hold due to
ROW
2
220 kV D/c
Chinchwad – Parvati
Flagship
Nos 3 3 Nil
3
132 kV D/c Rahatani
–Varasgan
Nos 3 - 3 Manufacturing clearance
awaited from client
4 132 kV S/c NCL -
Rahatni
Nos 1 - 1 Design verification u/p at
MSETCL, Mumbai
5 132 kV D/c
Chinchwad -
Ganeshkhind
Nos 1 - 1 Design verification u/p at
MSETCL, Mumbai
Supply Status (Cable)
Sl
No
Description Unit Req. Qty Supplied Balance Remarks
1 132 kV S/c NCL -
Rahatni
Kms 7.8 -
First lot of cable drums in
transit
2
132 kV D/c
Chinchwad -
Ganeshkhind
Kms 9.5 -
First lot cable drums in transit
Physical Completion Plan – Monopole works
Activity Anticipated Qty Progress till date Bal Plan
Jan Feb Mar April May
Foundation (Nos)
P-1 4 P-1 - P-1 4 P-1 - P-1 2 P-1 2 P-1 - P-1 -
P-2 3 P-2 1 P-2 2 P-2 - P-2 1 P-2 1 P-2 - P-2 -
P-3 3 P-3 - P-3 3 P-3 - P-3 - P-3 1 P-3 2 P-3 -
P-4 1 P-4 - P-4 1 P-4 - P-4 - P-4 1 P-4 - P-4 -
P-5 1 P-5 - P-5 1 P-5 - P-5 - P-5 - P-5 1 P-5 -
Erection ( Nos)
P-1 4 P-1 - P-1 4 P-1 - P-1 - P-1 2 P-1 1 P-1 1
P-2 3 P-2 - P-2 3 P-2 - P-2 1 P-2 1 P-2 1 P-2 -
P-3 3 P-3 - P-3 3 P-3 - P-3 - P-3 - P-3 1 P-3 2
P-4 1 P-4 - P-4 1 P-4 - P-4 - P-4 - P-4 1 P-4 -
P-5 1 P-5 - P-5 1 P-5 - P-5 - P-5 - P-5 - P-5 1
Stringing ( Kms)
P-1 2.46
P-1 - P-1 2.46
P-1 - P-1 - P-1 - P-1 - P-1 2.46
P-2 1.28
P-2 - P-2 1.28
P-2 - P-2 - P-2 - P-2 1.28 P-2 -
P-3 1.35
P-3 - P-3 1.35
P-3 - P-3 - P-3 - P-3 - P-3 1.35
Physical Completion Plan ( UG Cable works)
Description Anticipated
Qty
Progress till
date
Bal as on
date
Plan
Jan Feb Mar April May Jun
Cable laying ( Sections)
P4 3 P4 - P4 3 P4 - P4 1 P4 1 P4 1 P4 - P4 -
P5 3 P5 - P5 3 P5 - P5 - P5 1 P5 1 P5 1 P5 -
Joint Bay construction
P4 4 P4 - P4 6 P4 - P4 - P4 2 P4 2 P4 - P4 -
P5 4 P5 - P5 6 P5 - P5 - P5 1 P5 3 P5 - P5 -
OET Foundation
P4 6 P4 - P4 6 P4 - P4 - P4 - P4 6 P4 - P4 -
P5 6 P5 - P5 6 P5 - P5 - P5 - P5 - P5 6 P5 -
Jointing (JB wise)
P4 4 P4 - P4 6 P4 - P4 - P4 - P4 2 P4 2 P4 -
P5 4 P5 - P5 6 P5 - P5 - P5 - P5 - P5 2 P5 2
Termination
P4 24 P4 - P4 24 P4 - P4 - P4 - P4 - P4 12 P4 -
P5 24 P5 - P5 24 P5 - P5 - P5 - P5 - P5 - P5 12
Challenges and Action Plan
Challenges
 ROW clearance of Monopole locations - Package –B
(160, 162)
 ROW clearance of Monopole locations - Package –C
(17A)
 ROW clearance of Monopole locations -Package –D
(13,14 & 15 )
 Monopole design Approval – Package E & F
 NHAI approval Package – D
 EI permission
 Finalization of cable route & CTT –Package F
Action Plan
 Coordination with MSETCL/PMRDA/PITCMRL to
resolve ROW by this week of Location Nos 17A, 160
& 162.
 Package D – Coordination with collector office to
resolve ROW . PMRDA Scope
 Monpole Design approval – Under process at
MSETCL Corporate office
 RCPL will submit the proposal after ROW clearance
 EI permission – In coordination with MSETCL, RCPL
will file the on line application this week
Challenges and Action Plan
Challenges
 Finalization of Gantry (NCL)
 SLD preparation and its approval
Action Plan
 NCL gantry yet to finalize MSETCL. Coordination
with MSETCL to finalize by month end
 SLD – RCPL has to submit the SLD for both lines
after cable route approval.
Site Photos - Execution
Site Photos - Execution
Site Photos – Execution
Site Photos – Execution
Site Photos - Safety
Site Photos - Safety
Site Photos - Safety
Site Photos - Safety
Site Photos – client visit
Thank you

More Related Content

Similar to Project Review Meeting - 14.02.23.ppt

Stockley Xmas 14 - Possession Workshop 25092014
Stockley Xmas 14 - Possession Workshop 25092014Stockley Xmas 14 - Possession Workshop 25092014
Stockley Xmas 14 - Possession Workshop 25092014Thomas Ingrey
 
Vasanth_Electrical Engineer_CV_new
Vasanth_Electrical Engineer_CV_newVasanth_Electrical Engineer_CV_new
Vasanth_Electrical Engineer_CV_newvasanth morais
 
Review of PH-16 With CRB.pptx
Review of PH-16 With CRB.pptxReview of PH-16 With CRB.pptx
Review of PH-16 With CRB.pptx
MayankGandhi51
 
NACE CP LEVEL II ENGINEER
NACE CP LEVEL II ENGINEERNACE CP LEVEL II ENGINEER
NACE CP LEVEL II ENGINEER
RAMA SAMY
 
Cv Piping Engineer
Cv Piping EngineerCv Piping Engineer
Cv Piping Engineer
Padmanabh Dhobale
 
CV-_SDhiman_27-04-2016
CV-_SDhiman_27-04-2016CV-_SDhiman_27-04-2016
CV-_SDhiman_27-04-2016Subhash Dhiman
 
CV_Rolando M. Garcia_Feb 2016
CV_Rolando M. Garcia_Feb 2016CV_Rolando M. Garcia_Feb 2016
CV_Rolando M. Garcia_Feb 2016Rolando Garcia
 
RAMASAMY (NACE CERTIFIED CP LEVEL II ENGINEER)
RAMASAMY  (NACE CERTIFIED   CP LEVEL II ENGINEER)RAMASAMY  (NACE CERTIFIED   CP LEVEL II ENGINEER)
RAMASAMY (NACE CERTIFIED CP LEVEL II ENGINEER)
RAMA SAMY
 
CV-SC-Shaukat Mahmood Khan(5306) January 08,2017
CV-SC-Shaukat Mahmood Khan(5306) January 08,2017CV-SC-Shaukat Mahmood Khan(5306) January 08,2017
CV-SC-Shaukat Mahmood Khan(5306) January 08,2017Shaukat Mahmood Khan
 
RAMASAMY NACE CP LEVEL II ENGINEER
RAMASAMY NACE CP LEVEL II ENGINEERRAMASAMY NACE CP LEVEL II ENGINEER
RAMASAMY NACE CP LEVEL II ENGINEER
RAMA SAMY
 
cvPaoloAguzziNov16
cvPaoloAguzziNov16cvPaoloAguzziNov16
cvPaoloAguzziNov16Paolo Aguzzi
 
Cv paoloaguzzinov16
Cv paoloaguzzinov16Cv paoloaguzzinov16
Cv paoloaguzzinov16
Paolo Aguzzi
 

Similar to Project Review Meeting - 14.02.23.ppt (20)

Stockley Xmas 14 - Possession Workshop 25092014
Stockley Xmas 14 - Possession Workshop 25092014Stockley Xmas 14 - Possession Workshop 25092014
Stockley Xmas 14 - Possession Workshop 25092014
 
Vasanth_Electrical Engineer_CV_new
Vasanth_Electrical Engineer_CV_newVasanth_Electrical Engineer_CV_new
Vasanth_Electrical Engineer_CV_new
 
ramakant_23.9.2016 (1)
ramakant_23.9.2016 (1)ramakant_23.9.2016 (1)
ramakant_23.9.2016 (1)
 
MIG CV (Mar 2016)
MIG CV (Mar 2016)MIG CV (Mar 2016)
MIG CV (Mar 2016)
 
RSR LATEST TRESUME
RSR LATEST TRESUMERSR LATEST TRESUME
RSR LATEST TRESUME
 
Review of PH-16 With CRB.pptx
Review of PH-16 With CRB.pptxReview of PH-16 With CRB.pptx
Review of PH-16 With CRB.pptx
 
CV Solar
CV SolarCV Solar
CV Solar
 
CV-Priono_Update
CV-Priono_UpdateCV-Priono_Update
CV-Priono_Update
 
Atchiraju Batchu_CV (1)
Atchiraju Batchu_CV (1)Atchiraju Batchu_CV (1)
Atchiraju Batchu_CV (1)
 
RS Resume
RS ResumeRS Resume
RS Resume
 
NACE CP LEVEL II ENGINEER
NACE CP LEVEL II ENGINEERNACE CP LEVEL II ENGINEER
NACE CP LEVEL II ENGINEER
 
Cv Piping Engineer
Cv Piping EngineerCv Piping Engineer
Cv Piping Engineer
 
CV-_SDhiman_27-04-2016
CV-_SDhiman_27-04-2016CV-_SDhiman_27-04-2016
CV-_SDhiman_27-04-2016
 
CV_Rolando M. Garcia_Feb 2016
CV_Rolando M. Garcia_Feb 2016CV_Rolando M. Garcia_Feb 2016
CV_Rolando M. Garcia_Feb 2016
 
RAMASAMY (NACE CERTIFIED CP LEVEL II ENGINEER)
RAMASAMY  (NACE CERTIFIED   CP LEVEL II ENGINEER)RAMASAMY  (NACE CERTIFIED   CP LEVEL II ENGINEER)
RAMASAMY (NACE CERTIFIED CP LEVEL II ENGINEER)
 
CV-SC-Shaukat Mahmood Khan(5306) January 08,2017
CV-SC-Shaukat Mahmood Khan(5306) January 08,2017CV-SC-Shaukat Mahmood Khan(5306) January 08,2017
CV-SC-Shaukat Mahmood Khan(5306) January 08,2017
 
RAMASAMY NACE CP LEVEL II ENGINEER
RAMASAMY NACE CP LEVEL II ENGINEERRAMASAMY NACE CP LEVEL II ENGINEER
RAMASAMY NACE CP LEVEL II ENGINEER
 
cvPaoloAguzziNov16
cvPaoloAguzziNov16cvPaoloAguzziNov16
cvPaoloAguzziNov16
 
Cv paoloaguzzinov16
Cv paoloaguzzinov16Cv paoloaguzzinov16
Cv paoloaguzzinov16
 
CV_SIG_DES_MG_Dastagir 07_11_2016
CV_SIG_DES_MG_Dastagir 07_11_2016CV_SIG_DES_MG_Dastagir 07_11_2016
CV_SIG_DES_MG_Dastagir 07_11_2016
 

Recently uploaded

Unbalanced Three Phase Systems and circuits.pptx
Unbalanced Three Phase Systems and circuits.pptxUnbalanced Three Phase Systems and circuits.pptx
Unbalanced Three Phase Systems and circuits.pptx
ChristineTorrepenida1
 
DESIGN A COTTON SEED SEPARATION MACHINE.docx
DESIGN A COTTON SEED SEPARATION MACHINE.docxDESIGN A COTTON SEED SEPARATION MACHINE.docx
DESIGN A COTTON SEED SEPARATION MACHINE.docx
FluxPrime1
 
一比一原版(UofT毕业证)多伦多大学毕业证成绩单如何办理
一比一原版(UofT毕业证)多伦多大学毕业证成绩单如何办理一比一原版(UofT毕业证)多伦多大学毕业证成绩单如何办理
一比一原版(UofT毕业证)多伦多大学毕业证成绩单如何办理
ydteq
 
Design and Analysis of Algorithms-DP,Backtracking,Graphs,B&B
Design and Analysis of Algorithms-DP,Backtracking,Graphs,B&BDesign and Analysis of Algorithms-DP,Backtracking,Graphs,B&B
Design and Analysis of Algorithms-DP,Backtracking,Graphs,B&B
Sreedhar Chowdam
 
Planning Of Procurement o different goods and services
Planning Of Procurement o different goods and servicesPlanning Of Procurement o different goods and services
Planning Of Procurement o different goods and services
JoytuBarua2
 
Heap Sort (SS).ppt FOR ENGINEERING GRADUATES, BCA, MCA, MTECH, BSC STUDENTS
Heap Sort (SS).ppt FOR ENGINEERING GRADUATES, BCA, MCA, MTECH, BSC STUDENTSHeap Sort (SS).ppt FOR ENGINEERING GRADUATES, BCA, MCA, MTECH, BSC STUDENTS
Heap Sort (SS).ppt FOR ENGINEERING GRADUATES, BCA, MCA, MTECH, BSC STUDENTS
Soumen Santra
 
Hierarchical Digital Twin of a Naval Power System
Hierarchical Digital Twin of a Naval Power SystemHierarchical Digital Twin of a Naval Power System
Hierarchical Digital Twin of a Naval Power System
Kerry Sado
 
Investor-Presentation-Q1FY2024 investor presentation document.pptx
Investor-Presentation-Q1FY2024 investor presentation document.pptxInvestor-Presentation-Q1FY2024 investor presentation document.pptx
Investor-Presentation-Q1FY2024 investor presentation document.pptx
AmarGB2
 
DfMAy 2024 - key insights and contributions
DfMAy 2024 - key insights and contributionsDfMAy 2024 - key insights and contributions
DfMAy 2024 - key insights and contributions
gestioneergodomus
 
ML for identifying fraud using open blockchain data.pptx
ML for identifying fraud using open blockchain data.pptxML for identifying fraud using open blockchain data.pptx
ML for identifying fraud using open blockchain data.pptx
Vijay Dialani, PhD
 
Student information management system project report ii.pdf
Student information management system project report ii.pdfStudent information management system project report ii.pdf
Student information management system project report ii.pdf
Kamal Acharya
 
一比一原版(SFU毕业证)西蒙菲莎大学毕业证成绩单如何办理
一比一原版(SFU毕业证)西蒙菲莎大学毕业证成绩单如何办理一比一原版(SFU毕业证)西蒙菲莎大学毕业证成绩单如何办理
一比一原版(SFU毕业证)西蒙菲莎大学毕业证成绩单如何办理
bakpo1
 
Cosmetic shop management system project report.pdf
Cosmetic shop management system project report.pdfCosmetic shop management system project report.pdf
Cosmetic shop management system project report.pdf
Kamal Acharya
 
6th International Conference on Machine Learning & Applications (CMLA 2024)
6th International Conference on Machine Learning & Applications (CMLA 2024)6th International Conference on Machine Learning & Applications (CMLA 2024)
6th International Conference on Machine Learning & Applications (CMLA 2024)
ClaraZara1
 
weather web application report.pdf
weather web application report.pdfweather web application report.pdf
weather web application report.pdf
Pratik Pawar
 
AP LAB PPT.pdf ap lab ppt no title specific
AP LAB PPT.pdf ap lab ppt no title specificAP LAB PPT.pdf ap lab ppt no title specific
AP LAB PPT.pdf ap lab ppt no title specific
BrazilAccount1
 
AKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdf
AKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdfAKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdf
AKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdf
SamSarthak3
 
RAT: Retrieval Augmented Thoughts Elicit Context-Aware Reasoning in Long-Hori...
RAT: Retrieval Augmented Thoughts Elicit Context-Aware Reasoning in Long-Hori...RAT: Retrieval Augmented Thoughts Elicit Context-Aware Reasoning in Long-Hori...
RAT: Retrieval Augmented Thoughts Elicit Context-Aware Reasoning in Long-Hori...
thanhdowork
 
Industrial Training at Shahjalal Fertilizer Company Limited (SFCL)
Industrial Training at Shahjalal Fertilizer Company Limited (SFCL)Industrial Training at Shahjalal Fertilizer Company Limited (SFCL)
Industrial Training at Shahjalal Fertilizer Company Limited (SFCL)
MdTanvirMahtab2
 
NUMERICAL SIMULATIONS OF HEAT AND MASS TRANSFER IN CONDENSING HEAT EXCHANGERS...
NUMERICAL SIMULATIONS OF HEAT AND MASS TRANSFER IN CONDENSING HEAT EXCHANGERS...NUMERICAL SIMULATIONS OF HEAT AND MASS TRANSFER IN CONDENSING HEAT EXCHANGERS...
NUMERICAL SIMULATIONS OF HEAT AND MASS TRANSFER IN CONDENSING HEAT EXCHANGERS...
ssuser7dcef0
 

Recently uploaded (20)

Unbalanced Three Phase Systems and circuits.pptx
Unbalanced Three Phase Systems and circuits.pptxUnbalanced Three Phase Systems and circuits.pptx
Unbalanced Three Phase Systems and circuits.pptx
 
DESIGN A COTTON SEED SEPARATION MACHINE.docx
DESIGN A COTTON SEED SEPARATION MACHINE.docxDESIGN A COTTON SEED SEPARATION MACHINE.docx
DESIGN A COTTON SEED SEPARATION MACHINE.docx
 
一比一原版(UofT毕业证)多伦多大学毕业证成绩单如何办理
一比一原版(UofT毕业证)多伦多大学毕业证成绩单如何办理一比一原版(UofT毕业证)多伦多大学毕业证成绩单如何办理
一比一原版(UofT毕业证)多伦多大学毕业证成绩单如何办理
 
Design and Analysis of Algorithms-DP,Backtracking,Graphs,B&B
Design and Analysis of Algorithms-DP,Backtracking,Graphs,B&BDesign and Analysis of Algorithms-DP,Backtracking,Graphs,B&B
Design and Analysis of Algorithms-DP,Backtracking,Graphs,B&B
 
Planning Of Procurement o different goods and services
Planning Of Procurement o different goods and servicesPlanning Of Procurement o different goods and services
Planning Of Procurement o different goods and services
 
Heap Sort (SS).ppt FOR ENGINEERING GRADUATES, BCA, MCA, MTECH, BSC STUDENTS
Heap Sort (SS).ppt FOR ENGINEERING GRADUATES, BCA, MCA, MTECH, BSC STUDENTSHeap Sort (SS).ppt FOR ENGINEERING GRADUATES, BCA, MCA, MTECH, BSC STUDENTS
Heap Sort (SS).ppt FOR ENGINEERING GRADUATES, BCA, MCA, MTECH, BSC STUDENTS
 
Hierarchical Digital Twin of a Naval Power System
Hierarchical Digital Twin of a Naval Power SystemHierarchical Digital Twin of a Naval Power System
Hierarchical Digital Twin of a Naval Power System
 
Investor-Presentation-Q1FY2024 investor presentation document.pptx
Investor-Presentation-Q1FY2024 investor presentation document.pptxInvestor-Presentation-Q1FY2024 investor presentation document.pptx
Investor-Presentation-Q1FY2024 investor presentation document.pptx
 
DfMAy 2024 - key insights and contributions
DfMAy 2024 - key insights and contributionsDfMAy 2024 - key insights and contributions
DfMAy 2024 - key insights and contributions
 
ML for identifying fraud using open blockchain data.pptx
ML for identifying fraud using open blockchain data.pptxML for identifying fraud using open blockchain data.pptx
ML for identifying fraud using open blockchain data.pptx
 
Student information management system project report ii.pdf
Student information management system project report ii.pdfStudent information management system project report ii.pdf
Student information management system project report ii.pdf
 
一比一原版(SFU毕业证)西蒙菲莎大学毕业证成绩单如何办理
一比一原版(SFU毕业证)西蒙菲莎大学毕业证成绩单如何办理一比一原版(SFU毕业证)西蒙菲莎大学毕业证成绩单如何办理
一比一原版(SFU毕业证)西蒙菲莎大学毕业证成绩单如何办理
 
Cosmetic shop management system project report.pdf
Cosmetic shop management system project report.pdfCosmetic shop management system project report.pdf
Cosmetic shop management system project report.pdf
 
6th International Conference on Machine Learning & Applications (CMLA 2024)
6th International Conference on Machine Learning & Applications (CMLA 2024)6th International Conference on Machine Learning & Applications (CMLA 2024)
6th International Conference on Machine Learning & Applications (CMLA 2024)
 
weather web application report.pdf
weather web application report.pdfweather web application report.pdf
weather web application report.pdf
 
AP LAB PPT.pdf ap lab ppt no title specific
AP LAB PPT.pdf ap lab ppt no title specificAP LAB PPT.pdf ap lab ppt no title specific
AP LAB PPT.pdf ap lab ppt no title specific
 
AKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdf
AKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdfAKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdf
AKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdf
 
RAT: Retrieval Augmented Thoughts Elicit Context-Aware Reasoning in Long-Hori...
RAT: Retrieval Augmented Thoughts Elicit Context-Aware Reasoning in Long-Hori...RAT: Retrieval Augmented Thoughts Elicit Context-Aware Reasoning in Long-Hori...
RAT: Retrieval Augmented Thoughts Elicit Context-Aware Reasoning in Long-Hori...
 
Industrial Training at Shahjalal Fertilizer Company Limited (SFCL)
Industrial Training at Shahjalal Fertilizer Company Limited (SFCL)Industrial Training at Shahjalal Fertilizer Company Limited (SFCL)
Industrial Training at Shahjalal Fertilizer Company Limited (SFCL)
 
NUMERICAL SIMULATIONS OF HEAT AND MASS TRANSFER IN CONDENSING HEAT EXCHANGERS...
NUMERICAL SIMULATIONS OF HEAT AND MASS TRANSFER IN CONDENSING HEAT EXCHANGERS...NUMERICAL SIMULATIONS OF HEAT AND MASS TRANSFER IN CONDENSING HEAT EXCHANGERS...
NUMERICAL SIMULATIONS OF HEAT AND MASS TRANSFER IN CONDENSING HEAT EXCHANGERS...
 

Project Review Meeting - 14.02.23.ppt

  • 1. Project – PML3_US_EHVL_02 Heightening and conversion of existing 220 kV & 132 kV Overhead line infringing Metro Rail alignment of Pune Metro Line III
  • 2. Project Synopsis Contract No.: PML3_US_EHLV_02 Authority: Pune Metropolitan Region Development Authority Employer PITCMRL, PUNE Completion Period: 240 days from LOA ( Package B,C & D - 180 days) (Package E & F – 240 Days) LOA Date 15 th March 2022 Contract Value INR 1,10,80,08,369 ( Rs.110.80 Crs) excluding GST Contractor Rahul Cables Pvt. Ltd. Bank Guarantee INR 11,08,00,837.00 valid up to 30.06.2025 Contractual Completion Date 10 th November 2022 Anticipated Completion Date 30.06.2023
  • 3. Sailent features of the Project  The project is for heightening & conversion of existing 220 kV & 132 kV overhead lines which are infringing the Metro Rail alignment of Pune Metro Line 3 Project to Underground Cable.  The project work consist of total five packages  Package 1 – 220 kV S/c Chinchwad – Hinjewadi line between Location No.159 to 163  Package 2 – 220 kV D/c Chinchwad – Parvati (PRM) line between Location No.16 to 20 Heightening with Monopole  Package 3 – 132 kV D/C Rahatani – Varasagan line between location No.11 to 16  Package 4 – 132 kV S/C NCL – Rahatani line between Location No.33 to 38  Package 5 – 132 kV D/c Chinchwad – Ganeshkhind Line between Loacation 1 to 7 Conversion of OH to UG Cable  The line is passing through highly traffic zone and the lot of utilities are passing through the proposed cable route.  In all the heightening works ( Package 1 to 3) monopoles are proposed in the same power corridor and for execution, outage is must for Monopole erection and stringing work and also utmost safety measures to adhered.  ROW will play a vital role in this project. As the Monopole designs are unique, change in the position of tower may lead to change in the type of Monopole and it is time taking process for the new type pole from its design to manufacturing.
  • 4. Scope of work – Line wise S No Line name Monopole (Nos) UG Cable (Kms) Remarks 01 220 kV S/c Chinchwad - Hinjewadi 4 Nil Tower Nos.160, 161,161A & 162 02 220 kV D/c Chinchwad – Parvati Flagship 3 Nil Tower Nos.17, 17A & 18 03 132 kV D/c Rahatani – Varasgan 3 Nil Tower Nos. 13, 14 & 15 04 132 kV S/c NCL - Rahatni 1 1.288 CTT proposed at Tower No.34A ( Near Vidyanchal School) 05 132 kV D/c Chinchwad - Ganeshkhind 1 1.582 CTT proposed at Tower No.6 (YASHDA premises)
  • 5. Supply Status (Monopole) Sl No Description Unit Req. Qty Supplied Balance Remarks 1 220 kV S/c Chinchwad - Hinjewadi Nos 4 3 1 Tower No.160 on hold due to ROW 2 220 kV D/c Chinchwad – Parvati Flagship Nos 3 3 Nil 3 132 kV D/c Rahatani –Varasgan Nos 3 - 3 Manufacturing clearance awaited from client 4 132 kV S/c NCL - Rahatni Nos 1 - 1 Design verification u/p at MSETCL, Mumbai 5 132 kV D/c Chinchwad - Ganeshkhind Nos 1 - 1 Design verification u/p at MSETCL, Mumbai
  • 6. Supply Status (Cable) Sl No Description Unit Req. Qty Supplied Balance Remarks 1 132 kV S/c NCL - Rahatni Kms 7.8 - First lot of cable drums in transit 2 132 kV D/c Chinchwad - Ganeshkhind Kms 9.5 - First lot cable drums in transit
  • 7. Physical Completion Plan – Monopole works Activity Anticipated Qty Progress till date Bal Plan Jan Feb Mar April May Foundation (Nos) P-1 4 P-1 - P-1 4 P-1 - P-1 2 P-1 2 P-1 - P-1 - P-2 3 P-2 1 P-2 2 P-2 - P-2 1 P-2 1 P-2 - P-2 - P-3 3 P-3 - P-3 3 P-3 - P-3 - P-3 1 P-3 2 P-3 - P-4 1 P-4 - P-4 1 P-4 - P-4 - P-4 1 P-4 - P-4 - P-5 1 P-5 - P-5 1 P-5 - P-5 - P-5 - P-5 1 P-5 - Erection ( Nos) P-1 4 P-1 - P-1 4 P-1 - P-1 - P-1 2 P-1 1 P-1 1 P-2 3 P-2 - P-2 3 P-2 - P-2 1 P-2 1 P-2 1 P-2 - P-3 3 P-3 - P-3 3 P-3 - P-3 - P-3 - P-3 1 P-3 2 P-4 1 P-4 - P-4 1 P-4 - P-4 - P-4 - P-4 1 P-4 - P-5 1 P-5 - P-5 1 P-5 - P-5 - P-5 - P-5 - P-5 1 Stringing ( Kms) P-1 2.46 P-1 - P-1 2.46 P-1 - P-1 - P-1 - P-1 - P-1 2.46 P-2 1.28 P-2 - P-2 1.28 P-2 - P-2 - P-2 - P-2 1.28 P-2 - P-3 1.35 P-3 - P-3 1.35 P-3 - P-3 - P-3 - P-3 - P-3 1.35
  • 8. Physical Completion Plan ( UG Cable works) Description Anticipated Qty Progress till date Bal as on date Plan Jan Feb Mar April May Jun Cable laying ( Sections) P4 3 P4 - P4 3 P4 - P4 1 P4 1 P4 1 P4 - P4 - P5 3 P5 - P5 3 P5 - P5 - P5 1 P5 1 P5 1 P5 - Joint Bay construction P4 4 P4 - P4 6 P4 - P4 - P4 2 P4 2 P4 - P4 - P5 4 P5 - P5 6 P5 - P5 - P5 1 P5 3 P5 - P5 - OET Foundation P4 6 P4 - P4 6 P4 - P4 - P4 - P4 6 P4 - P4 - P5 6 P5 - P5 6 P5 - P5 - P5 - P5 - P5 6 P5 - Jointing (JB wise) P4 4 P4 - P4 6 P4 - P4 - P4 - P4 2 P4 2 P4 - P5 4 P5 - P5 6 P5 - P5 - P5 - P5 - P5 2 P5 2 Termination P4 24 P4 - P4 24 P4 - P4 - P4 - P4 - P4 12 P4 - P5 24 P5 - P5 24 P5 - P5 - P5 - P5 - P5 - P5 12
  • 9. Challenges and Action Plan Challenges  ROW clearance of Monopole locations - Package –B (160, 162)  ROW clearance of Monopole locations - Package –C (17A)  ROW clearance of Monopole locations -Package –D (13,14 & 15 )  Monopole design Approval – Package E & F  NHAI approval Package – D  EI permission  Finalization of cable route & CTT –Package F Action Plan  Coordination with MSETCL/PMRDA/PITCMRL to resolve ROW by this week of Location Nos 17A, 160 & 162.  Package D – Coordination with collector office to resolve ROW . PMRDA Scope  Monpole Design approval – Under process at MSETCL Corporate office  RCPL will submit the proposal after ROW clearance  EI permission – In coordination with MSETCL, RCPL will file the on line application this week
  • 10. Challenges and Action Plan Challenges  Finalization of Gantry (NCL)  SLD preparation and its approval Action Plan  NCL gantry yet to finalize MSETCL. Coordination with MSETCL to finalize by month end  SLD – RCPL has to submit the SLD for both lines after cable route approval.
  • 11. Site Photos - Execution
  • 12. Site Photos - Execution
  • 13. Site Photos – Execution
  • 14. Site Photos – Execution
  • 15. Site Photos - Safety
  • 16. Site Photos - Safety Site Photos - Safety
  • 17. Site Photos - Safety
  • 18. Site Photos – client visit