Page 2 SILVER ATENA 2014Ana Rodríguez - Ada Europe 2014
Contents
 Corporate Overview
 ERTMS - European Rail Traffic Management System
 RBC (Radio Block Centre)
 Conclusions and opportunities
Page 3 SILVER ATENA 2014Ana Rodríguez - Ada Europe 2014
 System Engineering
 Hardware Engineering
 RAMS Engineering
 Software Engineering
 System Consulting
 Technology Consulting
 Process Consulting
 HIL Test Systems
 Simulators
 Test Benches
 Electronic Control Units
 Development Tools
Safety-critical Electronic Systems Engineering
Engineering Consulting Products
In-house On-site
Corporate Overview
Service Porfolio
Page 4 SILVER ATENA 2014Ana Rodríguez - Ada Europe 2014
Corporate Overview
Silver Atena Group
Assystem is an Industrial Engineering company listed in NYSE Euro
next Paris.
Offices in 14 countries, employs approximately 11,100 people
worldwide and reported €871.4 M in revenue in 2013.
2013 Consolidated Revenue Up 1.8%
Page 5 SILVER ATENA 2014Ana Rodríguez - Ada Europe 2014
Corporate Overview
Quality – Standards – Memberships
Accreditations
 AS 9100C
(EN 9100:2009)
 DIN EN ISO 9001:2008
Industry Standards
 RTCA DO-160, DO-178B,
DO-248B & DO-254
 IEC 61508
 ISO 26262
 CENELEC
EN 50126, EN 50128 &
EN 50129
 BS IEC 60880-2:2000
 MISRA
 ECSS
Memberships
 Aerospace Cluster
 Cetren
 ECPE
 FlexRay
 Open-DO
 VDA
 ZAL
 Shitf2RAIL
Page 6 SILVER ATENA 2014Ana Rodríguez - Ada Europe 2014
Corporate Overview
Key Customers and Locations
Key Customer
Silver Atena Locations
Westinghouse Rail Systems
GE Aviation
Ultra Electronics
Goodrich
London Underground
Meggitt
Siemens
Alstom
Augusta Westlands
Hamilton Sundstrand
GE Transportation
BAE Systems
Airbus DS
Snecma
THALES Group
IAI
CAF
Eliop
BMW
Robert Bosch
Daimler
Audi
ZF Lenksysteme
Volkswagen
MTU Aero Engines
Airbus
EADS
Bombardier
Page 7 SILVER ATENA 2014Ana Rodríguez - Ada Europe 2014
Corporate Overview
Railways Competences
 Software Engineering, Hardware Engineering and Test Facilities
 RAMS (Reliability, Availability, Maintainability and Safety) Program
Safety Management: Safety Plan, Hazard Analysis, Preliminary
Hazard Analysis, Hazard Log, V&V reports Safety Case
Independent Safety Assessment
RAMS proven methodology (tool-set, methods and techniques)
 Safety Integrity Level (SIL): SIL 4, 3 and 2
 Consultancy on processes, products deployments, safety issues and
software technologies
 H2020 SHIFT²RAIL Innovation Program
On-board Train Integrity; Zero Field Testing; Formal Methods and
Standardisation for Smart Signalling Systems; Traffic
Management System
Page 8 SILVER ATENA 2014Ana Rodríguez - Ada Europe 2014
Contents
 Corporate Overview
 ERTMS - European Rail Traffic Management System
 RBC (Radio Block Centre)
 Conclusions and opportunities
Page 9 SILVER ATENA 2014Ana Rodríguez - Ada Europe 2014
ERTMS
European Rail Traffic Management System
 ERTMS aims to enable intelligent train traffic
management with interoperable driving
systems and optimise capacity, reliability and
minimise life-cycle cost
 European Train Control System
(ERTMS/ETCS) developed to establish
common standards for on-board systems,
connection/communication interfaces
between modules and the development of
common procedures
 Specifications of ERTMS/ETCS requirements
are public, and define the so-called kernel
and its interfaces with the ground
 … and now being deployed across Europe
Assist our clients in the development and prove of
ERTMS/ETCS equipments, which is intended to achieve this
interoperability with safety
Page 10 SILVER ATENA 2014Ana Rodríguez - Ada Europe 2014
ERTMS
ERTMS/ETCS
 The ERTMS/ETCS system provides the driver, in a standard format,
with all the information needed for optimum driving, constantly
controlling the effect of every action taken in terms of train safety,
and activating emergency braking should the train speed exceed
the maximum safety limits
 There are three levels of application
Page 11 SILVER ATENA 2014Ana Rodríguez - Ada Europe 2014
ERTMS
ERTMS/ETCS - Radio Block Centre
 Projects on Advance Traffic Management & Control Systems for a
new generation of signalling and control systems, building on
current ERTMS/ETCS
 Bombardier: Improvement of Rio de Janeiro commuter lines that
is the first ERTMS solution deployed in South America
 Siemens Rail Automation Division (former Invensys Rail
Dimetronic): Development of the Radio Block Centre (RBC),
ERTMS interoperability requirements for the data exchange
between the RBC and the on-board sub-system
 On the basis of the state of the infrastructure (free line, routes in
the stations, train speeds, slowdowns) and the position of the
train, the RBC transmits authorisation to proceed data to the
on-train unit, giving details of the free distance and the maximum
permitted speed at the point
Page 12 SILVER ATENA 2014Ana Rodríguez - Ada Europe 2014
Contents
 Corporate Overview
 ERTMS - European Rail Traffic Management System
 RBC (Radio Block Centre)
 Conclusions and opportunities
Page 13 SILVER ATENA 2014Ana Rodríguez - Ada Europe 2014
Radio Block Centre
ERTMS/ETCS level 2’s ground technology
 ERTMS/ETCS level 2’s ground
system comprises a RBC
central unit, installed in
specific central posts, from
which railway circulation is
managed and controlled
through the System of
Command and Control (SCC)
 The RBC continuously
transmits to every train, via
GSM-R radio, the speed and
the train distance, the
constraints imposed by the
track, and the position of the
trains
SCC © Cetren
Page 14 SILVER ATENA 2014Ana Rodríguez - Ada Europe 2014
Radio Block Centre
System Operation
©Siemens
 RBC: bi-directional continuous information by GSM-R Euro-radio (SIL4
Ada Software)
 CEC- Command and control of all the RBCs in a line
 JRU – black-box unit
 Maintenance Assistance Unit
 I/C Control equipment
 Local ERTMS Control, operator commands console
Page 15 SILVER ATENA 2014Ana Rodríguez - Ada Europe 2014
Radio Block Centre
Safety & Integrity Requirements
 ERTMS/ETCS – Baseline 3 - System Requirements Specification
 High integrity requirements for RBC data generation: maintaining
and assuring the accuracy, consistency and validity of data.
 RBC messages generation function: Safety Integrity Level 4 (SIL4)
 Strict life-cycle development to eliminate (minimize) threats to
data integrity
 Develop controls to eliminate
or reduce the probability or
severity of each hazard, to
lower the overall risk
Page 16 SILVER ATENA 2014Ana Rodríguez - Ada Europe 2014
Radio Block Centre
Safety & Integrity processes and techniques
 CENELEC standards
 Independent teams: Design& Development, V&V and safety
auditor (Independent Safety Assessment)
Page 17 SILVER ATENA 2014Ana Rodríguez - Ada Europe 2014
Radio Block Centre
Safety & Integrity Requirements
 RBC embedded software:
 Safety-critical Software (software which can directly create or
control a hazard).
 Software that provides information required for a safety-
related decision falls into the safety-critical category
 Designing for Safety SW is designing for minimum risk: Hazard
risk (likelihood and severity), risk of software defects, risk of
human operator errors, and other types of risk (such as
programmatic, cost, schedule, etc.)
 The RBC software is implemented in Ada95 Language:
 Ada is widely used for railways critical (SIL4 and SIL3)
developments
 Ada enforces good programming practices, makes bugs easier
for the compiler to find, and incorporates elements that make
the software easier to verify
Page 18 SILVER ATENA 2014Ana Rodríguez - Ada Europe 2014
Radio Block Centre
Safety & Integrity Requirements
 RBC embedded software:
 Safety-critical Software (software which can directly create or
control a hazard).
 Software that provides information required for a safety-
related decision falls into the safety-critical category
 Designing for Safety SW is designing for minimum risk: Hazard
risk (likelihood and severity), risk of software defects, risk of
human operator errors, and other types of risk (such as
programmatic, cost, schedule, etc.)
 The RBC software is implemented in Ada95 Language:
 Ada is widely used for railways critical (SIL4 and SIL3)
developments
 Ada enforces good programming practices, makes bugs easier
for the compiler to find, and incorporates elements that make
the software easier to verify
Page 19 SILVER ATENA 2014Ana Rodríguez - Ada Europe 2014
RBC
Safety Process – RAMS program
RAMS Engineering processes, tools and
techniques used to manage,
development and assessment of high-
integrity systems:
 Preliminary Hazard Analysis
 System Hazard Analysis
 System Safety Assessment
 Safety Case
 Independent Safety Assessment
Early risk appreciation
Quantitative measurements of reliability,
availability and maintainability through a
RAM program
CENELEC EN 50128
ISA recognized by Spanish Railway Authority
Page 20 SILVER ATENA 2014Ana Rodríguez - Ada Europe 2014
Radio Block Centre
V&V
 Design, specification and implementation of the RBC V&V Program
 Functional testing, integration and performance testing
Integration
V&V
Coding
Design
Requirements
Analysis
UML, RTSD,
Model Based Design
Ada, Assembler
Dynamic and Static Analysis
Code Inspection, Unit Test
SW/SW Integration, SW/HW
Integration
SIL4 Lifecycle
Modelling, UML, RTSA
Project Management Quality Management Risk Management Configuration Management
Page 21 SILVER ATENA 2014Ana Rodríguez - Ada Europe 2014
Radio Block Centre
RBC – SW & Validation Development
 Test Bench based on Silver-Atena testing product
 Simulation of Equipments interfacing RBC
 Messages logger
 Automatic test scenarios and scripts generation
Page 22 SILVER ATENA 2014Ana Rodríguez - Ada Europe 2014
Contents
 Corporate Overview
 ERTMS - European Rail Traffic Management System
 RBC (Radio Block Centre)
 Conclusions and opportunities
Page 23 SILVER ATENA 2014Ana Rodríguez - Ada Europe 2014
Radio Block Centre
Conclusion and opportunities
 Spain: ERTMS/ETMS largest
deployment in Europe
 Consolidated technologies and
capacities
 Good opportunities for Spanish railways
industry (AVE La Meca-Medina)
 New challenges for the deployment of
ERTMS/ETCS level 2 and 3
 Introduction of satellite assets for
improving safety at railway level
crossings
 Employ Satellite Communication and
Satellite Navigation in conjunction with
existing terrestrial assets/systems
Page 24 SILVER ATENA 2014Ana Rodríguez - Ada Europe 2014
Radio Block Centre
Conclusion and opportunities
 Ada Language and development
tools are commonly used for SIL4
and SIL3 projects
 Needs for improvement of safety
assurance processes, both
deployment and operations of the
train lines
The “safeness” and reliability
of a system depend on many
factors
Humans are involved in all
aspects of the process, quite
capable of subverting even
the “safest” of languages
Page 25 SILVER ATENA 2014Ana Rodríguez - Ada Europe 2014
Radio Block Centre
Conclusion and opportunities
 Expert report commissioned by the
Spanish government (June 2014)
 The cause of the crash was “excess
speed resulting from the driving
personnel’s failure to comply with
speed limit regulations”
 Adif, the state railway infrastructure
manager failed to install the kind of
technology that can automatically
slow down a train in the event of
human error.
 Recommendations: ERTMS signs
warning drivers and security
mechanisms to automatically slow
down speeding trains, a safer internal
communications system
The Santiago de
Compostela
derailment on July
2013: Europe’s worst
rail accident in recent
history.
Page 26 SILVER ATENA 2014Ana Rodríguez - Ada Europe 2014
Thank you for your attention!
Ana Rodríguez - Aerospace Business Unit Manager
ana.rodriguez@silver-atena.es
Ronda de Poniente 5, 28760 Tres Cantos, Madrid
Telf. +34 608754488
Engineering | Product| Consulting
www.silver-atena.com
www.assystem.com

More Related Content

What's hot

Maintenance, Repair & Overhaul (MRO)
Maintenance, Repair & Overhaul (MRO) Maintenance, Repair & Overhaul (MRO)
Maintenance, Repair & Overhaul (MRO)
Melissa Gannaway
 
The Essential European Fleet & Asset Management Update
The Essential European Fleet & Asset Management UpdateThe Essential European Fleet & Asset Management Update
The Essential European Fleet & Asset Management UpdateHitReach
 
IBM Maximo Asset Management Training - Asset and Work Management for Chang Sh...
IBM Maximo Asset Management Training - Asset and Work Management for Chang Sh...IBM Maximo Asset Management Training - Asset and Work Management for Chang Sh...
IBM Maximo Asset Management Training - Asset and Work Management for Chang Sh...
Duane Aritonang
 
Workshop INFOR EAM 14th Maintenance Management Conference Dubai, Dec 18/2008
Workshop INFOR EAM 14th Maintenance Management Conference Dubai, Dec 18/2008Workshop INFOR EAM 14th Maintenance Management Conference Dubai, Dec 18/2008
Workshop INFOR EAM 14th Maintenance Management Conference Dubai, Dec 18/2008
jcvd12
 
Nextgen tools for data migration in aviation
Nextgen tools for data migration in aviationNextgen tools for data migration in aviation
Nextgen tools for data migration in aviation
EXSYN Aviation Solutions
 
Boeing Case Study | e-enabled Advantage
Boeing Case Study | e-enabled AdvantageBoeing Case Study | e-enabled Advantage
Boeing Case Study | e-enabled Advantage
Adheesha Dharmakeerthi
 
IBM MAXIMO Online training
IBM MAXIMO Online trainingIBM MAXIMO Online training
IBM MAXIMO Online training
ParthaT1
 
Qbit Presentation
Qbit PresentationQbit Presentation
Qbit Presentationkumarrahul
 
IBM Maximo for Utilities
IBM Maximo for UtilitiesIBM Maximo for Utilities
IBM Maximo for Utilities
Vincent Kwon
 
Travel CaseStudy: HCLT helps a leading airline in asia reduce 25% of its IT cost
Travel CaseStudy: HCLT helps a leading airline in asia reduce 25% of its IT costTravel CaseStudy: HCLT helps a leading airline in asia reduce 25% of its IT cost
Travel CaseStudy: HCLT helps a leading airline in asia reduce 25% of its IT cost
HCL Technologies
 
IBM Maximo Asset Management solutions for the oil and gas industry
IBM Maximo Asset Management solutions for the oil and gas industryIBM Maximo Asset Management solutions for the oil and gas industry
IBM Maximo Asset Management solutions for the oil and gas industry
IBM Chemical Petroleum
 
aviation management information system
aviation management information systemaviation management information system
aviation management information systemAmit Kumar
 
Maximo Roadmap - September 2019
Maximo Roadmap - September 2019Maximo Roadmap - September 2019
Maximo Roadmap - September 2019
Bruno Portaluri
 
ME Article_ 5 req LAM p38-41 Charboneau paper (4pp)
ME Article_ 5 req LAM p38-41 Charboneau paper (4pp)ME Article_ 5 req LAM p38-41 Charboneau paper (4pp)
ME Article_ 5 req LAM p38-41 Charboneau paper (4pp)James (Jim) Charboneau
 
Maximo overview
Maximo overviewMaximo overview
Maximo overview
Dharani Dharan
 
Ramco - A Software for all Seasons
 Ramco - A Software for all Seasons Ramco - A Software for all Seasons
Ramco - A Software for all Seasons
Ramco Systems
 
How to successfully implement sap ami
How to successfully implement sap amiHow to successfully implement sap ami
How to successfully implement sap amirobgirvan
 
Simex avionics-profile
Simex avionics-profileSimex avionics-profile
Simex avionics-profile
Shamaz Khan
 
Maximo and a roadmap for your IoT journey
Maximo and a roadmap for your IoT journeyMaximo and a roadmap for your IoT journey
Maximo and a roadmap for your IoT journey
Helen Fisher
 
Using FMI (Functional Mock-up Interface) for MBSE at all steps of System Design
Using FMI (Functional Mock-up Interface) for MBSE at all steps of System DesignUsing FMI (Functional Mock-up Interface) for MBSE at all steps of System Design
Using FMI (Functional Mock-up Interface) for MBSE at all steps of System Design
Siemens PLM Software
 

What's hot (20)

Maintenance, Repair & Overhaul (MRO)
Maintenance, Repair & Overhaul (MRO) Maintenance, Repair & Overhaul (MRO)
Maintenance, Repair & Overhaul (MRO)
 
The Essential European Fleet & Asset Management Update
The Essential European Fleet & Asset Management UpdateThe Essential European Fleet & Asset Management Update
The Essential European Fleet & Asset Management Update
 
IBM Maximo Asset Management Training - Asset and Work Management for Chang Sh...
IBM Maximo Asset Management Training - Asset and Work Management for Chang Sh...IBM Maximo Asset Management Training - Asset and Work Management for Chang Sh...
IBM Maximo Asset Management Training - Asset and Work Management for Chang Sh...
 
Workshop INFOR EAM 14th Maintenance Management Conference Dubai, Dec 18/2008
Workshop INFOR EAM 14th Maintenance Management Conference Dubai, Dec 18/2008Workshop INFOR EAM 14th Maintenance Management Conference Dubai, Dec 18/2008
Workshop INFOR EAM 14th Maintenance Management Conference Dubai, Dec 18/2008
 
Nextgen tools for data migration in aviation
Nextgen tools for data migration in aviationNextgen tools for data migration in aviation
Nextgen tools for data migration in aviation
 
Boeing Case Study | e-enabled Advantage
Boeing Case Study | e-enabled AdvantageBoeing Case Study | e-enabled Advantage
Boeing Case Study | e-enabled Advantage
 
IBM MAXIMO Online training
IBM MAXIMO Online trainingIBM MAXIMO Online training
IBM MAXIMO Online training
 
Qbit Presentation
Qbit PresentationQbit Presentation
Qbit Presentation
 
IBM Maximo for Utilities
IBM Maximo for UtilitiesIBM Maximo for Utilities
IBM Maximo for Utilities
 
Travel CaseStudy: HCLT helps a leading airline in asia reduce 25% of its IT cost
Travel CaseStudy: HCLT helps a leading airline in asia reduce 25% of its IT costTravel CaseStudy: HCLT helps a leading airline in asia reduce 25% of its IT cost
Travel CaseStudy: HCLT helps a leading airline in asia reduce 25% of its IT cost
 
IBM Maximo Asset Management solutions for the oil and gas industry
IBM Maximo Asset Management solutions for the oil and gas industryIBM Maximo Asset Management solutions for the oil and gas industry
IBM Maximo Asset Management solutions for the oil and gas industry
 
aviation management information system
aviation management information systemaviation management information system
aviation management information system
 
Maximo Roadmap - September 2019
Maximo Roadmap - September 2019Maximo Roadmap - September 2019
Maximo Roadmap - September 2019
 
ME Article_ 5 req LAM p38-41 Charboneau paper (4pp)
ME Article_ 5 req LAM p38-41 Charboneau paper (4pp)ME Article_ 5 req LAM p38-41 Charboneau paper (4pp)
ME Article_ 5 req LAM p38-41 Charboneau paper (4pp)
 
Maximo overview
Maximo overviewMaximo overview
Maximo overview
 
Ramco - A Software for all Seasons
 Ramco - A Software for all Seasons Ramco - A Software for all Seasons
Ramco - A Software for all Seasons
 
How to successfully implement sap ami
How to successfully implement sap amiHow to successfully implement sap ami
How to successfully implement sap ami
 
Simex avionics-profile
Simex avionics-profileSimex avionics-profile
Simex avionics-profile
 
Maximo and a roadmap for your IoT journey
Maximo and a roadmap for your IoT journeyMaximo and a roadmap for your IoT journey
Maximo and a roadmap for your IoT journey
 
Using FMI (Functional Mock-up Interface) for MBSE at all steps of System Design
Using FMI (Functional Mock-up Interface) for MBSE at all steps of System DesignUsing FMI (Functional Mock-up Interface) for MBSE at all steps of System Design
Using FMI (Functional Mock-up Interface) for MBSE at all steps of System Design
 

Viewers also liked

Hospital Management System
Hospital Management SystemHospital Management System
Hospital Management System
Mohin Uddin Majumder (Sanofi Mohin)
 
Cbi company profile - 2014
Cbi   company profile - 2014Cbi   company profile - 2014
Cbi company profile - 2014Minh Minh
 
Detected por Natalia Sanroman
Detected por Natalia SanromanDetected por Natalia Sanroman
Detected por Natalia Sanroman
Natalia Sanroman
 
Jette Panduro slides
Jette Panduro slidesJette Panduro slides
Jette Panduro slides
koradk
 
Newtek IP Series 2016 czech version
Newtek IP Series 2016 czech versionNewtek IP Series 2016 czech version
Newtek IP Series 2016 czech version
Petr Krkavec
 
GURT Communique, December 2015
GURT Communique, December 2015GURT Communique, December 2015
GURT Communique, December 2015
GURT Resource Centre
 
ITpreneurs 2011 Store redesign
ITpreneurs 2011 Store redesignITpreneurs 2011 Store redesign
ITpreneurs 2011 Store redesign
Diogo Caldeira-Pires
 
BiGG SEA - Hızlı Başla, Temmuz 2015
BiGG SEA - Hızlı Başla, Temmuz 2015BiGG SEA - Hızlı Başla, Temmuz 2015
BiGG SEA - Hızlı Başla, Temmuz 2015
SUCOOL Incubation Center
 
Uno no es ninguno
Uno no es ningunoUno no es ninguno
Uno no es ninguno
tcrosalva
 
119500910 proiect-de-investitii
119500910 proiect-de-investitii119500910 proiect-de-investitii
119500910 proiect-de-investitiiCiuvaga Andrei
 
Gestione delle attività IT presso l’Aeroporto di Bologna - CMDBuild Day, 15 a...
Gestione delle attività IT presso l’Aeroporto di Bologna - CMDBuild Day, 15 a...Gestione delle attività IT presso l’Aeroporto di Bologna - CMDBuild Day, 15 a...
Gestione delle attività IT presso l’Aeroporto di Bologna - CMDBuild Day, 15 a...
CMDBuild org
 
Relevant Product Design Requires Keeping Up with Perpetual Change
Relevant Product Design Requires Keeping Up with Perpetual ChangeRelevant Product Design Requires Keeping Up with Perpetual Change
Relevant Product Design Requires Keeping Up with Perpetual Change
Cognizant
 
Escuela de Biología y Química Botánica por Victoria Cañar Vc
Escuela de Biología y Química Botánica por Victoria Cañar  VcEscuela de Biología y Química Botánica por Victoria Cañar  Vc
Escuela de Biología y Química Botánica por Victoria Cañar Vc
VickyFlow
 
La red de la Cantabria Net al descubierto
La red de la Cantabria Net al descubiertoLa red de la Cantabria Net al descubierto
La red de la Cantabria Net al descubierto
David Cristóbal
 
Mobiliario para aulas universitarias 2
Mobiliario para aulas universitarias 2Mobiliario para aulas universitarias 2
Mobiliario para aulas universitarias 2PANELSISTEM
 
LasNIC 10 Y 11 Normas Internacionales de Contabilidad 10 y 11
LasNIC 10 Y 11 Normas Internacionales de Contabilidad 10 y 11LasNIC 10 Y 11 Normas Internacionales de Contabilidad 10 y 11
LasNIC 10 Y 11 Normas Internacionales de Contabilidad 10 y 11Victor TiTo Quintanilla
 

Viewers also liked (20)

Hospital Management System
Hospital Management SystemHospital Management System
Hospital Management System
 
Cbi company profile - 2014
Cbi   company profile - 2014Cbi   company profile - 2014
Cbi company profile - 2014
 
Detected por Natalia Sanroman
Detected por Natalia SanromanDetected por Natalia Sanroman
Detected por Natalia Sanroman
 
Jette Panduro slides
Jette Panduro slidesJette Panduro slides
Jette Panduro slides
 
Newtek IP Series 2016 czech version
Newtek IP Series 2016 czech versionNewtek IP Series 2016 czech version
Newtek IP Series 2016 czech version
 
GURT Communique, December 2015
GURT Communique, December 2015GURT Communique, December 2015
GURT Communique, December 2015
 
ITpreneurs 2011 Store redesign
ITpreneurs 2011 Store redesignITpreneurs 2011 Store redesign
ITpreneurs 2011 Store redesign
 
BiGG SEA - Hızlı Başla, Temmuz 2015
BiGG SEA - Hızlı Başla, Temmuz 2015BiGG SEA - Hızlı Başla, Temmuz 2015
BiGG SEA - Hızlı Başla, Temmuz 2015
 
Uno no es ninguno
Uno no es ningunoUno no es ninguno
Uno no es ninguno
 
CV-2015
CV-2015CV-2015
CV-2015
 
119500910 proiect-de-investitii
119500910 proiect-de-investitii119500910 proiect-de-investitii
119500910 proiect-de-investitii
 
Gestione delle attività IT presso l’Aeroporto di Bologna - CMDBuild Day, 15 a...
Gestione delle attività IT presso l’Aeroporto di Bologna - CMDBuild Day, 15 a...Gestione delle attività IT presso l’Aeroporto di Bologna - CMDBuild Day, 15 a...
Gestione delle attività IT presso l’Aeroporto di Bologna - CMDBuild Day, 15 a...
 
Expo de compu de linux y w phone
Expo de compu de linux y w phoneExpo de compu de linux y w phone
Expo de compu de linux y w phone
 
last cv 2014
last cv 2014last cv 2014
last cv 2014
 
Relevant Product Design Requires Keeping Up with Perpetual Change
Relevant Product Design Requires Keeping Up with Perpetual ChangeRelevant Product Design Requires Keeping Up with Perpetual Change
Relevant Product Design Requires Keeping Up with Perpetual Change
 
Escuela de Biología y Química Botánica por Victoria Cañar Vc
Escuela de Biología y Química Botánica por Victoria Cañar  VcEscuela de Biología y Química Botánica por Victoria Cañar  Vc
Escuela de Biología y Química Botánica por Victoria Cañar Vc
 
La red de la Cantabria Net al descubierto
La red de la Cantabria Net al descubiertoLa red de la Cantabria Net al descubierto
La red de la Cantabria Net al descubierto
 
Mobiliario para aulas universitarias 2
Mobiliario para aulas universitarias 2Mobiliario para aulas universitarias 2
Mobiliario para aulas universitarias 2
 
Rogers1973b
Rogers1973bRogers1973b
Rogers1973b
 
LasNIC 10 Y 11 Normas Internacionales de Contabilidad 10 y 11
LasNIC 10 Y 11 Normas Internacionales de Contabilidad 10 y 11LasNIC 10 Y 11 Normas Internacionales de Contabilidad 10 y 11
LasNIC 10 Y 11 Normas Internacionales de Contabilidad 10 y 11
 

Similar to Critical software For the First European Rail Traffic Management System

Developing safety autonomous driving solutions based on the adaptive AUTOSAR ...
Developing safety autonomous driving solutions based on the adaptive AUTOSAR ...Developing safety autonomous driving solutions based on the adaptive AUTOSAR ...
Developing safety autonomous driving solutions based on the adaptive AUTOSAR ...
Andrei Kholodnyi
 
Innovation Solutions
Innovation SolutionsInnovation Solutions
Innovation Solutions
Railways and Harbours
 
Connecting vehicles, highways and telecommunications
Connecting vehicles, highways and telecommunicationsConnecting vehicles, highways and telecommunications
Connecting vehicles, highways and telecommunications
innovITS
 
Sesar swim master class best in class 2014 overview of the submissions
Sesar swim master class best in class 2014 overview of the submissionsSesar swim master class best in class 2014 overview of the submissions
Sesar swim master class best in class 2014 overview of the submissions
SESAR Joint Undertaking
 
Rep Presentation V4 13
Rep Presentation V4 13Rep Presentation V4 13
Rep Presentation V4 13lyndonroberts
 
Inter vehicle communication
Inter vehicle communicationInter vehicle communication
Inter vehicle communication
R prasad
 
Passenger Counting / People Counting Applications and Devices
Passenger Counting / People Counting Applications and DevicesPassenger Counting / People Counting Applications and Devices
Passenger Counting / People Counting Applications and Devices
Eurotech
 
Portfolio of Projects
Portfolio of ProjectsPortfolio of Projects
Portfolio of Projects
Daniele Pinto
 
9. PA DIM presentation.pdf
9. PA DIM presentation.pdf9. PA DIM presentation.pdf
Remedy IT Company presentation
Remedy IT Company presentationRemedy IT Company presentation
Remedy IT Company presentation
Remedy IT
 
Company Presentation RemedyIT
Company Presentation RemedyITCompany Presentation RemedyIT
Company Presentation RemedyITRemedy IT
 
ERTMS Solutions general company presentation
ERTMS Solutions general company presentationERTMS Solutions general company presentation
ERTMS Solutions general company presentation
ERTMS Solutions
 
CV-For-Thair 2
CV-For-Thair 2CV-For-Thair 2
CV-For-Thair 2tjust80
 
An OSGi Environment for FlexibleService Concepts - Detlef Kuck, Teamleader Te...
An OSGi Environment for FlexibleService Concepts - Detlef Kuck, Teamleader Te...An OSGi Environment for FlexibleService Concepts - Detlef Kuck, Teamleader Te...
An OSGi Environment for FlexibleService Concepts - Detlef Kuck, Teamleader Te...
mfrancis
 
Transsol Ltd
Transsol LtdTranssol Ltd
Transsol Ltd
smealing
 
End to End In-Vehicle Infotainment Test Solution - MaxEye Technologies
End to End In-Vehicle Infotainment Test Solution - MaxEye TechnologiesEnd to End In-Vehicle Infotainment Test Solution - MaxEye Technologies
End to End In-Vehicle Infotainment Test Solution - MaxEye Technologies
MaxEye Technologies Private Limited
 
vehicular communications
vehicular communicationsvehicular communications
vehicular communications
Saikiran Guduri
 
Yakaiah_Resume_9Yrs
Yakaiah_Resume_9YrsYakaiah_Resume_9Yrs
Yakaiah_Resume_9YrsYakaiah S
 
Seven_RAMS_Presentation_EN_04
Seven_RAMS_Presentation_EN_04Seven_RAMS_Presentation_EN_04
Seven_RAMS_Presentation_EN_04Marco Addino
 

Similar to Critical software For the First European Rail Traffic Management System (20)

Developing safety autonomous driving solutions based on the adaptive AUTOSAR ...
Developing safety autonomous driving solutions based on the adaptive AUTOSAR ...Developing safety autonomous driving solutions based on the adaptive AUTOSAR ...
Developing safety autonomous driving solutions based on the adaptive AUTOSAR ...
 
Innovation Solutions
Innovation SolutionsInnovation Solutions
Innovation Solutions
 
Connecting vehicles, highways and telecommunications
Connecting vehicles, highways and telecommunicationsConnecting vehicles, highways and telecommunications
Connecting vehicles, highways and telecommunications
 
Car liga ac
Car liga acCar liga ac
Car liga ac
 
Sesar swim master class best in class 2014 overview of the submissions
Sesar swim master class best in class 2014 overview of the submissionsSesar swim master class best in class 2014 overview of the submissions
Sesar swim master class best in class 2014 overview of the submissions
 
Rep Presentation V4 13
Rep Presentation V4 13Rep Presentation V4 13
Rep Presentation V4 13
 
Inter vehicle communication
Inter vehicle communicationInter vehicle communication
Inter vehicle communication
 
Passenger Counting / People Counting Applications and Devices
Passenger Counting / People Counting Applications and DevicesPassenger Counting / People Counting Applications and Devices
Passenger Counting / People Counting Applications and Devices
 
Portfolio of Projects
Portfolio of ProjectsPortfolio of Projects
Portfolio of Projects
 
9. PA DIM presentation.pdf
9. PA DIM presentation.pdf9. PA DIM presentation.pdf
9. PA DIM presentation.pdf
 
Remedy IT Company presentation
Remedy IT Company presentationRemedy IT Company presentation
Remedy IT Company presentation
 
Company Presentation RemedyIT
Company Presentation RemedyITCompany Presentation RemedyIT
Company Presentation RemedyIT
 
ERTMS Solutions general company presentation
ERTMS Solutions general company presentationERTMS Solutions general company presentation
ERTMS Solutions general company presentation
 
CV-For-Thair 2
CV-For-Thair 2CV-For-Thair 2
CV-For-Thair 2
 
An OSGi Environment for FlexibleService Concepts - Detlef Kuck, Teamleader Te...
An OSGi Environment for FlexibleService Concepts - Detlef Kuck, Teamleader Te...An OSGi Environment for FlexibleService Concepts - Detlef Kuck, Teamleader Te...
An OSGi Environment for FlexibleService Concepts - Detlef Kuck, Teamleader Te...
 
Transsol Ltd
Transsol LtdTranssol Ltd
Transsol Ltd
 
End to End In-Vehicle Infotainment Test Solution - MaxEye Technologies
End to End In-Vehicle Infotainment Test Solution - MaxEye TechnologiesEnd to End In-Vehicle Infotainment Test Solution - MaxEye Technologies
End to End In-Vehicle Infotainment Test Solution - MaxEye Technologies
 
vehicular communications
vehicular communicationsvehicular communications
vehicular communications
 
Yakaiah_Resume_9Yrs
Yakaiah_Resume_9YrsYakaiah_Resume_9Yrs
Yakaiah_Resume_9Yrs
 
Seven_RAMS_Presentation_EN_04
Seven_RAMS_Presentation_EN_04Seven_RAMS_Presentation_EN_04
Seven_RAMS_Presentation_EN_04
 

Recently uploaded

Final project report on grocery store management system..pdf
Final project report on grocery store management system..pdfFinal project report on grocery store management system..pdf
Final project report on grocery store management system..pdf
Kamal Acharya
 
Standard Reomte Control Interface - Neometrix
Standard Reomte Control Interface - NeometrixStandard Reomte Control Interface - Neometrix
Standard Reomte Control Interface - Neometrix
Neometrix_Engineering_Pvt_Ltd
 
CME397 Surface Engineering- Professional Elective
CME397 Surface Engineering- Professional ElectiveCME397 Surface Engineering- Professional Elective
CME397 Surface Engineering- Professional Elective
karthi keyan
 
一比一原版(SFU毕业证)西蒙菲莎大学毕业证成绩单如何办理
一比一原版(SFU毕业证)西蒙菲莎大学毕业证成绩单如何办理一比一原版(SFU毕业证)西蒙菲莎大学毕业证成绩单如何办理
一比一原版(SFU毕业证)西蒙菲莎大学毕业证成绩单如何办理
bakpo1
 
Top 10 Oil and Gas Projects in Saudi Arabia 2024.pdf
Top 10 Oil and Gas Projects in Saudi Arabia 2024.pdfTop 10 Oil and Gas Projects in Saudi Arabia 2024.pdf
Top 10 Oil and Gas Projects in Saudi Arabia 2024.pdf
Teleport Manpower Consultant
 
一比一原版(IIT毕业证)伊利诺伊理工大学毕业证成绩单专业办理
一比一原版(IIT毕业证)伊利诺伊理工大学毕业证成绩单专业办理一比一原版(IIT毕业证)伊利诺伊理工大学毕业证成绩单专业办理
一比一原版(IIT毕业证)伊利诺伊理工大学毕业证成绩单专业办理
zwunae
 
The Benefits and Techniques of Trenchless Pipe Repair.pdf
The Benefits and Techniques of Trenchless Pipe Repair.pdfThe Benefits and Techniques of Trenchless Pipe Repair.pdf
The Benefits and Techniques of Trenchless Pipe Repair.pdf
Pipe Restoration Solutions
 
ASME IX(9) 2007 Full Version .pdf
ASME IX(9)  2007 Full Version       .pdfASME IX(9)  2007 Full Version       .pdf
ASME IX(9) 2007 Full Version .pdf
AhmedHussein950959
 
power quality voltage fluctuation UNIT - I.pptx
power quality voltage fluctuation UNIT - I.pptxpower quality voltage fluctuation UNIT - I.pptx
power quality voltage fluctuation UNIT - I.pptx
ViniHema
 
Architectural Portfolio Sean Lockwood
Architectural Portfolio Sean LockwoodArchitectural Portfolio Sean Lockwood
Architectural Portfolio Sean Lockwood
seandesed
 
Hierarchical Digital Twin of a Naval Power System
Hierarchical Digital Twin of a Naval Power SystemHierarchical Digital Twin of a Naval Power System
Hierarchical Digital Twin of a Naval Power System
Kerry Sado
 
ML for identifying fraud using open blockchain data.pptx
ML for identifying fraud using open blockchain data.pptxML for identifying fraud using open blockchain data.pptx
ML for identifying fraud using open blockchain data.pptx
Vijay Dialani, PhD
 
NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...
NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...
NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...
Amil Baba Dawood bangali
 
MCQ Soil mechanics questions (Soil shear strength).pdf
MCQ Soil mechanics questions (Soil shear strength).pdfMCQ Soil mechanics questions (Soil shear strength).pdf
MCQ Soil mechanics questions (Soil shear strength).pdf
Osamah Alsalih
 
AKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdf
AKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdfAKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdf
AKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdf
SamSarthak3
 
block diagram and signal flow graph representation
block diagram and signal flow graph representationblock diagram and signal flow graph representation
block diagram and signal flow graph representation
Divya Somashekar
 
在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样
在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样
在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样
obonagu
 
Cosmetic shop management system project report.pdf
Cosmetic shop management system project report.pdfCosmetic shop management system project report.pdf
Cosmetic shop management system project report.pdf
Kamal Acharya
 
Runway Orientation Based on the Wind Rose Diagram.pptx
Runway Orientation Based on the Wind Rose Diagram.pptxRunway Orientation Based on the Wind Rose Diagram.pptx
Runway Orientation Based on the Wind Rose Diagram.pptx
SupreethSP4
 
Railway Signalling Principles Edition 3.pdf
Railway Signalling Principles Edition 3.pdfRailway Signalling Principles Edition 3.pdf
Railway Signalling Principles Edition 3.pdf
TeeVichai
 

Recently uploaded (20)

Final project report on grocery store management system..pdf
Final project report on grocery store management system..pdfFinal project report on grocery store management system..pdf
Final project report on grocery store management system..pdf
 
Standard Reomte Control Interface - Neometrix
Standard Reomte Control Interface - NeometrixStandard Reomte Control Interface - Neometrix
Standard Reomte Control Interface - Neometrix
 
CME397 Surface Engineering- Professional Elective
CME397 Surface Engineering- Professional ElectiveCME397 Surface Engineering- Professional Elective
CME397 Surface Engineering- Professional Elective
 
一比一原版(SFU毕业证)西蒙菲莎大学毕业证成绩单如何办理
一比一原版(SFU毕业证)西蒙菲莎大学毕业证成绩单如何办理一比一原版(SFU毕业证)西蒙菲莎大学毕业证成绩单如何办理
一比一原版(SFU毕业证)西蒙菲莎大学毕业证成绩单如何办理
 
Top 10 Oil and Gas Projects in Saudi Arabia 2024.pdf
Top 10 Oil and Gas Projects in Saudi Arabia 2024.pdfTop 10 Oil and Gas Projects in Saudi Arabia 2024.pdf
Top 10 Oil and Gas Projects in Saudi Arabia 2024.pdf
 
一比一原版(IIT毕业证)伊利诺伊理工大学毕业证成绩单专业办理
一比一原版(IIT毕业证)伊利诺伊理工大学毕业证成绩单专业办理一比一原版(IIT毕业证)伊利诺伊理工大学毕业证成绩单专业办理
一比一原版(IIT毕业证)伊利诺伊理工大学毕业证成绩单专业办理
 
The Benefits and Techniques of Trenchless Pipe Repair.pdf
The Benefits and Techniques of Trenchless Pipe Repair.pdfThe Benefits and Techniques of Trenchless Pipe Repair.pdf
The Benefits and Techniques of Trenchless Pipe Repair.pdf
 
ASME IX(9) 2007 Full Version .pdf
ASME IX(9)  2007 Full Version       .pdfASME IX(9)  2007 Full Version       .pdf
ASME IX(9) 2007 Full Version .pdf
 
power quality voltage fluctuation UNIT - I.pptx
power quality voltage fluctuation UNIT - I.pptxpower quality voltage fluctuation UNIT - I.pptx
power quality voltage fluctuation UNIT - I.pptx
 
Architectural Portfolio Sean Lockwood
Architectural Portfolio Sean LockwoodArchitectural Portfolio Sean Lockwood
Architectural Portfolio Sean Lockwood
 
Hierarchical Digital Twin of a Naval Power System
Hierarchical Digital Twin of a Naval Power SystemHierarchical Digital Twin of a Naval Power System
Hierarchical Digital Twin of a Naval Power System
 
ML for identifying fraud using open blockchain data.pptx
ML for identifying fraud using open blockchain data.pptxML for identifying fraud using open blockchain data.pptx
ML for identifying fraud using open blockchain data.pptx
 
NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...
NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...
NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...
 
MCQ Soil mechanics questions (Soil shear strength).pdf
MCQ Soil mechanics questions (Soil shear strength).pdfMCQ Soil mechanics questions (Soil shear strength).pdf
MCQ Soil mechanics questions (Soil shear strength).pdf
 
AKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdf
AKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdfAKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdf
AKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdf
 
block diagram and signal flow graph representation
block diagram and signal flow graph representationblock diagram and signal flow graph representation
block diagram and signal flow graph representation
 
在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样
在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样
在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样
 
Cosmetic shop management system project report.pdf
Cosmetic shop management system project report.pdfCosmetic shop management system project report.pdf
Cosmetic shop management system project report.pdf
 
Runway Orientation Based on the Wind Rose Diagram.pptx
Runway Orientation Based on the Wind Rose Diagram.pptxRunway Orientation Based on the Wind Rose Diagram.pptx
Runway Orientation Based on the Wind Rose Diagram.pptx
 
Railway Signalling Principles Edition 3.pdf
Railway Signalling Principles Edition 3.pdfRailway Signalling Principles Edition 3.pdf
Railway Signalling Principles Edition 3.pdf
 

Critical software For the First European Rail Traffic Management System

  • 1. Ada Europe 2014 Industrial Sessions: Ada in Railways Critical software For the First European Rail Traffic Management System Ana Rodríguez June 2014
  • 2. Page 2 SILVER ATENA 2014Ana Rodríguez - Ada Europe 2014 Contents  Corporate Overview  ERTMS - European Rail Traffic Management System  RBC (Radio Block Centre)  Conclusions and opportunities
  • 3. Page 3 SILVER ATENA 2014Ana Rodríguez - Ada Europe 2014  System Engineering  Hardware Engineering  RAMS Engineering  Software Engineering  System Consulting  Technology Consulting  Process Consulting  HIL Test Systems  Simulators  Test Benches  Electronic Control Units  Development Tools Safety-critical Electronic Systems Engineering Engineering Consulting Products In-house On-site Corporate Overview Service Porfolio
  • 4. Page 4 SILVER ATENA 2014Ana Rodríguez - Ada Europe 2014 Corporate Overview Silver Atena Group Assystem is an Industrial Engineering company listed in NYSE Euro next Paris. Offices in 14 countries, employs approximately 11,100 people worldwide and reported €871.4 M in revenue in 2013. 2013 Consolidated Revenue Up 1.8%
  • 5. Page 5 SILVER ATENA 2014Ana Rodríguez - Ada Europe 2014 Corporate Overview Quality – Standards – Memberships Accreditations  AS 9100C (EN 9100:2009)  DIN EN ISO 9001:2008 Industry Standards  RTCA DO-160, DO-178B, DO-248B & DO-254  IEC 61508  ISO 26262  CENELEC EN 50126, EN 50128 & EN 50129  BS IEC 60880-2:2000  MISRA  ECSS Memberships  Aerospace Cluster  Cetren  ECPE  FlexRay  Open-DO  VDA  ZAL  Shitf2RAIL
  • 6. Page 6 SILVER ATENA 2014Ana Rodríguez - Ada Europe 2014 Corporate Overview Key Customers and Locations Key Customer Silver Atena Locations Westinghouse Rail Systems GE Aviation Ultra Electronics Goodrich London Underground Meggitt Siemens Alstom Augusta Westlands Hamilton Sundstrand GE Transportation BAE Systems Airbus DS Snecma THALES Group IAI CAF Eliop BMW Robert Bosch Daimler Audi ZF Lenksysteme Volkswagen MTU Aero Engines Airbus EADS Bombardier
  • 7. Page 7 SILVER ATENA 2014Ana Rodríguez - Ada Europe 2014 Corporate Overview Railways Competences  Software Engineering, Hardware Engineering and Test Facilities  RAMS (Reliability, Availability, Maintainability and Safety) Program Safety Management: Safety Plan, Hazard Analysis, Preliminary Hazard Analysis, Hazard Log, V&V reports Safety Case Independent Safety Assessment RAMS proven methodology (tool-set, methods and techniques)  Safety Integrity Level (SIL): SIL 4, 3 and 2  Consultancy on processes, products deployments, safety issues and software technologies  H2020 SHIFT²RAIL Innovation Program On-board Train Integrity; Zero Field Testing; Formal Methods and Standardisation for Smart Signalling Systems; Traffic Management System
  • 8. Page 8 SILVER ATENA 2014Ana Rodríguez - Ada Europe 2014 Contents  Corporate Overview  ERTMS - European Rail Traffic Management System  RBC (Radio Block Centre)  Conclusions and opportunities
  • 9. Page 9 SILVER ATENA 2014Ana Rodríguez - Ada Europe 2014 ERTMS European Rail Traffic Management System  ERTMS aims to enable intelligent train traffic management with interoperable driving systems and optimise capacity, reliability and minimise life-cycle cost  European Train Control System (ERTMS/ETCS) developed to establish common standards for on-board systems, connection/communication interfaces between modules and the development of common procedures  Specifications of ERTMS/ETCS requirements are public, and define the so-called kernel and its interfaces with the ground  … and now being deployed across Europe Assist our clients in the development and prove of ERTMS/ETCS equipments, which is intended to achieve this interoperability with safety
  • 10. Page 10 SILVER ATENA 2014Ana Rodríguez - Ada Europe 2014 ERTMS ERTMS/ETCS  The ERTMS/ETCS system provides the driver, in a standard format, with all the information needed for optimum driving, constantly controlling the effect of every action taken in terms of train safety, and activating emergency braking should the train speed exceed the maximum safety limits  There are three levels of application
  • 11. Page 11 SILVER ATENA 2014Ana Rodríguez - Ada Europe 2014 ERTMS ERTMS/ETCS - Radio Block Centre  Projects on Advance Traffic Management & Control Systems for a new generation of signalling and control systems, building on current ERTMS/ETCS  Bombardier: Improvement of Rio de Janeiro commuter lines that is the first ERTMS solution deployed in South America  Siemens Rail Automation Division (former Invensys Rail Dimetronic): Development of the Radio Block Centre (RBC), ERTMS interoperability requirements for the data exchange between the RBC and the on-board sub-system  On the basis of the state of the infrastructure (free line, routes in the stations, train speeds, slowdowns) and the position of the train, the RBC transmits authorisation to proceed data to the on-train unit, giving details of the free distance and the maximum permitted speed at the point
  • 12. Page 12 SILVER ATENA 2014Ana Rodríguez - Ada Europe 2014 Contents  Corporate Overview  ERTMS - European Rail Traffic Management System  RBC (Radio Block Centre)  Conclusions and opportunities
  • 13. Page 13 SILVER ATENA 2014Ana Rodríguez - Ada Europe 2014 Radio Block Centre ERTMS/ETCS level 2’s ground technology  ERTMS/ETCS level 2’s ground system comprises a RBC central unit, installed in specific central posts, from which railway circulation is managed and controlled through the System of Command and Control (SCC)  The RBC continuously transmits to every train, via GSM-R radio, the speed and the train distance, the constraints imposed by the track, and the position of the trains SCC © Cetren
  • 14. Page 14 SILVER ATENA 2014Ana Rodríguez - Ada Europe 2014 Radio Block Centre System Operation ©Siemens  RBC: bi-directional continuous information by GSM-R Euro-radio (SIL4 Ada Software)  CEC- Command and control of all the RBCs in a line  JRU – black-box unit  Maintenance Assistance Unit  I/C Control equipment  Local ERTMS Control, operator commands console
  • 15. Page 15 SILVER ATENA 2014Ana Rodríguez - Ada Europe 2014 Radio Block Centre Safety & Integrity Requirements  ERTMS/ETCS – Baseline 3 - System Requirements Specification  High integrity requirements for RBC data generation: maintaining and assuring the accuracy, consistency and validity of data.  RBC messages generation function: Safety Integrity Level 4 (SIL4)  Strict life-cycle development to eliminate (minimize) threats to data integrity  Develop controls to eliminate or reduce the probability or severity of each hazard, to lower the overall risk
  • 16. Page 16 SILVER ATENA 2014Ana Rodríguez - Ada Europe 2014 Radio Block Centre Safety & Integrity processes and techniques  CENELEC standards  Independent teams: Design& Development, V&V and safety auditor (Independent Safety Assessment)
  • 17. Page 17 SILVER ATENA 2014Ana Rodríguez - Ada Europe 2014 Radio Block Centre Safety & Integrity Requirements  RBC embedded software:  Safety-critical Software (software which can directly create or control a hazard).  Software that provides information required for a safety- related decision falls into the safety-critical category  Designing for Safety SW is designing for minimum risk: Hazard risk (likelihood and severity), risk of software defects, risk of human operator errors, and other types of risk (such as programmatic, cost, schedule, etc.)  The RBC software is implemented in Ada95 Language:  Ada is widely used for railways critical (SIL4 and SIL3) developments  Ada enforces good programming practices, makes bugs easier for the compiler to find, and incorporates elements that make the software easier to verify
  • 18. Page 18 SILVER ATENA 2014Ana Rodríguez - Ada Europe 2014 Radio Block Centre Safety & Integrity Requirements  RBC embedded software:  Safety-critical Software (software which can directly create or control a hazard).  Software that provides information required for a safety- related decision falls into the safety-critical category  Designing for Safety SW is designing for minimum risk: Hazard risk (likelihood and severity), risk of software defects, risk of human operator errors, and other types of risk (such as programmatic, cost, schedule, etc.)  The RBC software is implemented in Ada95 Language:  Ada is widely used for railways critical (SIL4 and SIL3) developments  Ada enforces good programming practices, makes bugs easier for the compiler to find, and incorporates elements that make the software easier to verify
  • 19. Page 19 SILVER ATENA 2014Ana Rodríguez - Ada Europe 2014 RBC Safety Process – RAMS program RAMS Engineering processes, tools and techniques used to manage, development and assessment of high- integrity systems:  Preliminary Hazard Analysis  System Hazard Analysis  System Safety Assessment  Safety Case  Independent Safety Assessment Early risk appreciation Quantitative measurements of reliability, availability and maintainability through a RAM program CENELEC EN 50128 ISA recognized by Spanish Railway Authority
  • 20. Page 20 SILVER ATENA 2014Ana Rodríguez - Ada Europe 2014 Radio Block Centre V&V  Design, specification and implementation of the RBC V&V Program  Functional testing, integration and performance testing Integration V&V Coding Design Requirements Analysis UML, RTSD, Model Based Design Ada, Assembler Dynamic and Static Analysis Code Inspection, Unit Test SW/SW Integration, SW/HW Integration SIL4 Lifecycle Modelling, UML, RTSA Project Management Quality Management Risk Management Configuration Management
  • 21. Page 21 SILVER ATENA 2014Ana Rodríguez - Ada Europe 2014 Radio Block Centre RBC – SW & Validation Development  Test Bench based on Silver-Atena testing product  Simulation of Equipments interfacing RBC  Messages logger  Automatic test scenarios and scripts generation
  • 22. Page 22 SILVER ATENA 2014Ana Rodríguez - Ada Europe 2014 Contents  Corporate Overview  ERTMS - European Rail Traffic Management System  RBC (Radio Block Centre)  Conclusions and opportunities
  • 23. Page 23 SILVER ATENA 2014Ana Rodríguez - Ada Europe 2014 Radio Block Centre Conclusion and opportunities  Spain: ERTMS/ETMS largest deployment in Europe  Consolidated technologies and capacities  Good opportunities for Spanish railways industry (AVE La Meca-Medina)  New challenges for the deployment of ERTMS/ETCS level 2 and 3  Introduction of satellite assets for improving safety at railway level crossings  Employ Satellite Communication and Satellite Navigation in conjunction with existing terrestrial assets/systems
  • 24. Page 24 SILVER ATENA 2014Ana Rodríguez - Ada Europe 2014 Radio Block Centre Conclusion and opportunities  Ada Language and development tools are commonly used for SIL4 and SIL3 projects  Needs for improvement of safety assurance processes, both deployment and operations of the train lines The “safeness” and reliability of a system depend on many factors Humans are involved in all aspects of the process, quite capable of subverting even the “safest” of languages
  • 25. Page 25 SILVER ATENA 2014Ana Rodríguez - Ada Europe 2014 Radio Block Centre Conclusion and opportunities  Expert report commissioned by the Spanish government (June 2014)  The cause of the crash was “excess speed resulting from the driving personnel’s failure to comply with speed limit regulations”  Adif, the state railway infrastructure manager failed to install the kind of technology that can automatically slow down a train in the event of human error.  Recommendations: ERTMS signs warning drivers and security mechanisms to automatically slow down speeding trains, a safer internal communications system The Santiago de Compostela derailment on July 2013: Europe’s worst rail accident in recent history.
  • 26. Page 26 SILVER ATENA 2014Ana Rodríguez - Ada Europe 2014 Thank you for your attention! Ana Rodríguez - Aerospace Business Unit Manager ana.rodriguez@silver-atena.es Ronda de Poniente 5, 28760 Tres Cantos, Madrid Telf. +34 608754488 Engineering | Product| Consulting www.silver-atena.com www.assystem.com