This document summarizes the process of moving a datacenter from an old converted kitchen space to a new dedicated facility over a 4 day period. Key aspects of the move included 3 years of planning, virtualizing servers, upgrading storage and networking, and improving disaster recovery capabilities. The move improved stability, reduced power outages and failures, separated test and production systems, and enabled remote management. It established an effective disaster recovery plan and provided a flexible computing environment to support the organization's move to a new headquarters location with minimal business disruption.