SlideShare a Scribd company logo
1 of 18
Plan Risk Management
Plan Risk Management
Coincides with PMBOK 11.1
Process Group and Knowledge Area Mapping
Knowledge Areas Initiating Planning Process Group Executing Process Group Monitoring and Controlling Process Group Closing Process Group
4. Project Integration
Management
4.1 Develop Project Charter
4.2 Develop Project Management
Plan
4.3 Direct and Manage Project Work
4.4 Manage Project Knowledge
4.5 Monitor and Control Project Work
4.6 Perform Integrated Change Control
4.7 Close Project or Phase
5. Project Scope
Management
5.1 Plan Scope Management
5.2 Collect Requirements
5.3 Define Scope
5.4 Create WBS
5.5 Validate Scope
5.6 Control Scope
6. Project Schedule
Management
6.1 Plan Schedule Management
6.2 Define Activities
6.3 Sequence Activities
6.4 Estimate Activity Durations
6.5 Develop Schedule
6.6 Control Schedule
7. Project Cost Management
7.1 Plan Cost Management
7.2 Estimate Costs
7.3 Determine Budget
7.4 Control Costs
8. Project Quality
Management
8.1 Plan Quality Management 8.2 Manage Quality 8.3 Control Quality
9. Project Resource
Management
9.1 Plan Resource Management
9.2 Estimate Activity Resources
9.3 Acquire Resources
9.4 Develop Team
9.5 Manage Team
9.6 Control Resources
10. Project Communications
Management
10.1 Plan Communications
Management
10.2 Manage Communications 10.3 Monitor Communications
11. Project Risk
Management
11.1 Plan Risk Management
11.2 Identify Risks
11.3 Perform Qualitative Risk Analysis
11.4 Perform Quantitative Risk
Analysis
11.5 Plan Risk Responses
11.6 Implement Risk Responses 11.7 Monitor Risks
12. Project Procurement
Management
12.1 Plan Procurement Management 12.2 Conduct Procurements 12.3 Control Procurements
13. Project Stakeholder
Management
13.1 Identify Stakeholders 13.2 Plan Stakeholder Engagement
13.3 Manage Stakeholder
Engagement
13.4 Monitor Stakeholder Engagement
What is it?
Plan Risk Management is the process of defining how to conduct risk
management activities for a project.
Why?
The key benefit of this process is that it ensures that the degree, type,
and visibility of risk management are proportionate to both risks and
the importance of the project to the organization and other
stakeholders.
Plan Risk Management
Coincides with PMBOK 11.1
Overview
• The Plan Risk Management process should begin when a project is conceived and
should be completed early in the project.
• It may be necessary to revisit this process later in the project life cycle, for example
at a major phase change, or if the project scope changes significantly, or if a
subsequent review of risk management effectiveness determines that the Project
Risk Management process requires modification.
Coincides with PMBOK 11.1
Plan Risk Management
Plan Risk Management
Coincides with PMBOK 11.1
Inputs Tools & Techniques Outputs
1. Project charter
2. Project management plan
• All components
3. Project documents
• Stakeholder register
4. Enterprise environmental
factors
5. Organizational process
assets
1. Expert judgment
2. Data analysis
• Stakeholder analysis
3. Meetings
1. Risk management
plan
Inputs, Tools & Techniques, Outputs
Plan Risk Management
Coincides with PMBOK 11.1
11.1 Plan Risk
Management
Project
Management
Plan
Enterprise/Orga
nization
4.1 Develop
Project Charter
• Risk management plan
• All components
• Enterprise environmental factors
• Organizational process assets
• Project charter
Project
Documents
• Stakeholder register
Project
Management
Plan
Plan Risk Management - Inputs
Coincides with PMBOK 11.1
Project Charter
The project charter documents the high-level project description and
boundaries, high- level requirements, and risks.
Plan Risk Management - Inputs
Coincides with PMBOK 11.1
Project Management Plan
In planning Project Risk Management, all approved subsidiary
management plans should be taken into consideration in order to make
the risk management plan consistent with them. The methodology
outlined in other project management plan components might influence
the Plan Risk Management process.
Plan Risk Management - Inputs
Coincides with PMBOK 11.1
Project Documents
Project documents that can be considered as inputs for this process
include but are not limited to the stakeholder register. The stakeholder
register contains details of the project’s stakeholders and provides an
overview of their project roles and their attitude toward risk on this
project.
Coincides with PMBOK 11.1
Enterprise Environmental Factors
The enterprise environmental factors that can influence the Plan Risk
Management process include but are not limited to overall risk
thresholds set by the organization or key stakeholders.
Plan Risk Management - Inputs
Coincides with PMBOK 11.1
Organisational Process Assets
The organizational process assets that can influence the Plan Risk Management
process include:
• Organizational risk policy
• Risk categories, possibly organized into a risk breakdown structure
• Common definitions of risk concepts and terms
• Risk statement formats
• Templates for the risk management plan, risk register, and risk report
• Roles and responsibilities
• Authority levels for decision making
• Lessons learned repository from previous similar projects.
Plan Risk Management - Inputs
Plan Risk Management – Tools & Techniques
Coincides with PMBOK 11.1
Expert Judgment
Expertise should be considered from individuals or groups with specialized knowledge
or training in the following topics:
• Familiarity with the organization’s approach to managing risk, including enterprise
risk management where this is performed
• Tailoring risk management to the specific needs of a project
• Types of risk that are likely to be encountered on projects in the same area
Plan Risk Management – Tools & Techniques
Coincides with PMBOK 11.1
Data Analysis
Data analysis techniques that can be used for this process includes but
are not limited to a stakeholder analysis to determine the risk appetite of
project stakeholders.
Coincides with PMBOK 11.1
Meetings
Plan Risk Management – Tools & Techniques
The risk management plan may be developed as part of the project kick-off meeting or
a specific planning meeting may be held. Attendees may include the project manager,
selected project team members, key stakeholders, or team members who are
responsible to manage the risk management process on the project.
Plans for conducting risk management activities are defined in these meetings and
documented in the risk management plan.
Plan Risk Management - Outputs
Coincides with PMBOK 11.1
Risk Management Plan
The risk management plan is a component of the project management plan that
describes how risk management activities will be structured and performed. The risk
management plan may include some or all the following elements:
• Risk strategy
• Methodology
• Roles and responsibilities
• Funding
• Timing
• Tracking
• Risk categories
• Stakeholder risk appetite
• Definitions of risk probability and
impacts
• Probability and impact matrix
• Reporting Formats
Plan Risk Management - Outputs
Coincides with PMBOK 11.1
Risk Management Plan – Risk Categories
A common way to structure risk
categories is with a risk
breakdown structure (RBS),
which is a hierarchical
representation of potential
sources of risk. An RBS helps the
project team consider the full
range of sources from which
individual project risks may
arise.
Example of
Risk
Breakdown
Structure
Plan Risk Management - Outputs
Coincides with PMBOK 11.1
Risk Management Plan – Definitions of risk probability and impacts
Definitions of risk probability
and impact levels are specific
to the project context and
reflect the risk appetite and
thresholds of the organization
and key stakeholders. Example
provides an example of
definitions of probability and
impacts against three project
objectives.
Example of Definitions of risk probability and impacts
Plan Risk Management - Outputs
Coincides with PMBOK 11.1
Risk Management Plan – Probability and Impact Matrix
Opportunities and threats are
represented in a common
probability and impact matrix
using positive definitions of
impact for opportunities and
negative impact definitions for
threats. An example
probability and impact matrix
is presented, which also
shows a possible numeric risk
scoring scheme.
Example of Probability and Impact Matrix

More Related Content

What's hot

11.6 Implement Risk Responses
11.6 Implement Risk Responses11.6 Implement Risk Responses
11.6 Implement Risk ResponsesDavidMcLachlan1
 
Project risk management
Project risk managementProject risk management
Project risk managementDewang Agrawal
 
Projectriskmanagement pmbok5
Projectriskmanagement pmbok5Projectriskmanagement pmbok5
Projectriskmanagement pmbok5Dhamo daran
 
Risk strategies presentation
Risk strategies presentationRisk strategies presentation
Risk strategies presentationRaven Morgan
 
11.5 Plan Risk Responses
11.5 Plan Risk Responses11.5 Plan Risk Responses
11.5 Plan Risk ResponsesDavidMcLachlan1
 
Risk Management Lifecycle PowerPoint Presentation Slides
Risk Management Lifecycle PowerPoint Presentation Slides Risk Management Lifecycle PowerPoint Presentation Slides
Risk Management Lifecycle PowerPoint Presentation Slides SlideTeam
 
Risk Management Knowledge Area
Risk Management Knowledge AreaRisk Management Knowledge Area
Risk Management Knowledge AreaJoshua Render
 
Risk management presentation
Risk management presentationRisk management presentation
Risk management presentationabpeters82
 
Risk Management Best Practices
Risk Management Best PracticesRisk Management Best Practices
Risk Management Best PracticesPMILebanonChapter
 
Episode 25 : Project Risk Management
Episode 25 :  Project Risk ManagementEpisode 25 :  Project Risk Management
Episode 25 : Project Risk ManagementSAJJAD KHUDHUR ABBAS
 
PMP PMBOK 5th Ch 11 Project Risk Management
PMP PMBOK 5th Ch 11 Project Risk ManagementPMP PMBOK 5th Ch 11 Project Risk Management
PMP PMBOK 5th Ch 11 Project Risk ManagementAbdullah Ahmed, PMP, RMP
 
Project Risk Management - PMBOK6
Project Risk Management - PMBOK6Project Risk Management - PMBOK6
Project Risk Management - PMBOK6Agus Suhanto
 
Introduction To Risk Management Powerpoint Presentation Slides
Introduction To Risk Management Powerpoint Presentation SlidesIntroduction To Risk Management Powerpoint Presentation Slides
Introduction To Risk Management Powerpoint Presentation SlidesSlideTeam
 

What's hot (20)

11.6 Implement Risk Responses
11.6 Implement Risk Responses11.6 Implement Risk Responses
11.6 Implement Risk Responses
 
Project risk management
Project risk managementProject risk management
Project risk management
 
Projectriskmanagement pmbok5
Projectriskmanagement pmbok5Projectriskmanagement pmbok5
Projectriskmanagement pmbok5
 
Risk strategies presentation
Risk strategies presentationRisk strategies presentation
Risk strategies presentation
 
11.5 Plan Risk Responses
11.5 Plan Risk Responses11.5 Plan Risk Responses
11.5 Plan Risk Responses
 
Risk Management Lifecycle PowerPoint Presentation Slides
Risk Management Lifecycle PowerPoint Presentation Slides Risk Management Lifecycle PowerPoint Presentation Slides
Risk Management Lifecycle PowerPoint Presentation Slides
 
10- PMP Training - Risk Management
10- PMP Training - Risk Management 10- PMP Training - Risk Management
10- PMP Training - Risk Management
 
Risk management
Risk managementRisk management
Risk management
 
Risk Management Knowledge Area
Risk Management Knowledge AreaRisk Management Knowledge Area
Risk Management Knowledge Area
 
Risk management presentation
Risk management presentationRisk management presentation
Risk management presentation
 
Risk Management Best Practices
Risk Management Best PracticesRisk Management Best Practices
Risk Management Best Practices
 
Episode 25 : Project Risk Management
Episode 25 :  Project Risk ManagementEpisode 25 :  Project Risk Management
Episode 25 : Project Risk Management
 
PMP PMBOK 5th Ch 11 Project Risk Management
PMP PMBOK 5th Ch 11 Project Risk ManagementPMP PMBOK 5th Ch 11 Project Risk Management
PMP PMBOK 5th Ch 11 Project Risk Management
 
Project Risk Management - PMBOK6
Project Risk Management - PMBOK6Project Risk Management - PMBOK6
Project Risk Management - PMBOK6
 
Risk management
Risk managementRisk management
Risk management
 
PMP_Project Risk Management
PMP_Project Risk ManagementPMP_Project Risk Management
PMP_Project Risk Management
 
Project risk management
Project risk managementProject risk management
Project risk management
 
Risk management
Risk managementRisk management
Risk management
 
Introduction To Risk Management Powerpoint Presentation Slides
Introduction To Risk Management Powerpoint Presentation SlidesIntroduction To Risk Management Powerpoint Presentation Slides
Introduction To Risk Management Powerpoint Presentation Slides
 
Risk management
Risk managementRisk management
Risk management
 

Similar to 11.1 Plan Risk Management

11.0 Project Risk Management Overview
11.0 Project Risk Management Overview11.0 Project Risk Management Overview
11.0 Project Risk Management OverviewDavidMcLachlan1
 
11.3 Perform Qualitative Risk Analysis
11.3 Perform Qualitative Risk Analysis11.3 Perform Qualitative Risk Analysis
11.3 Perform Qualitative Risk AnalysisDavidMcLachlan1
 
7.1 Plan Cost Management
7.1 Plan Cost Management7.1 Plan Cost Management
7.1 Plan Cost ManagementDavidMcLachlan1
 
Plan risk management
Plan risk management Plan risk management
Plan risk management Shereef Sabri
 
5.1 Plan Scope Management
5.1 Plan Scope Management5.1 Plan Scope Management
5.1 Plan Scope ManagementDavidMcLachlan1
 
7.0 project,-planning-and-management
7.0 project,-planning-and-management7.0 project,-planning-and-management
7.0 project,-planning-and-managementsinger manjeet gupta
 
Organizational project maturity model (opm3)
Organizational project maturity model (opm3)Organizational project maturity model (opm3)
Organizational project maturity model (opm3)Daniele Pinto
 
9.1 Plan Resource Management
9.1 Plan Resource Management9.1 Plan Resource Management
9.1 Plan Resource ManagementDavidMcLachlan1
 
Topic 6 - Project Integration Management.pdf
Topic 6 - Project Integration Management.pdfTopic 6 - Project Integration Management.pdf
Topic 6 - Project Integration Management.pdfHuyNguyen657394
 
Planning process group
Planning process groupPlanning process group
Planning process groupMudassir Iqbal
 
13.0 Project Stakeholder Management Overview
13.0 Project Stakeholder Management Overview13.0 Project Stakeholder Management Overview
13.0 Project Stakeholder Management OverviewDavidMcLachlan1
 
13.2 Plan Stakeholder Engagement
13.2 Plan Stakeholder Engagement13.2 Plan Stakeholder Engagement
13.2 Plan Stakeholder EngagementDavidMcLachlan1
 
PMBoK ed.5 brief overview
PMBoK ed.5 brief overviewPMBoK ed.5 brief overview
PMBoK ed.5 brief overviewOleksiy Rudenko
 
PMP as per PMBOK 6
PMP as per PMBOK 6PMP as per PMBOK 6
PMP as per PMBOK 6Amit Gupta
 
Lecture 07: Project Management Fundamentals Project Organization and Integr...
Lecture 07: Project Management Fundamentals Project Organization and Integr...Lecture 07: Project Management Fundamentals Project Organization and Integr...
Lecture 07: Project Management Fundamentals Project Organization and Integr...Fida Karim 🇵🇰
 

Similar to 11.1 Plan Risk Management (20)

11.0 Project Risk Management Overview
11.0 Project Risk Management Overview11.0 Project Risk Management Overview
11.0 Project Risk Management Overview
 
11.3 Perform Qualitative Risk Analysis
11.3 Perform Qualitative Risk Analysis11.3 Perform Qualitative Risk Analysis
11.3 Perform Qualitative Risk Analysis
 
11.2 Identify Risks
11.2 Identify Risks11.2 Identify Risks
11.2 Identify Risks
 
7.1 Plan Cost Management
7.1 Plan Cost Management7.1 Plan Cost Management
7.1 Plan Cost Management
 
Plan risk management
Plan risk management Plan risk management
Plan risk management
 
11.7 Monitor Risks
11.7 Monitor Risks11.7 Monitor Risks
11.7 Monitor Risks
 
5.1 Plan Scope Management
5.1 Plan Scope Management5.1 Plan Scope Management
5.1 Plan Scope Management
 
7.0 project,-planning-and-management
7.0 project,-planning-and-management7.0 project,-planning-and-management
7.0 project,-planning-and-management
 
Organizational project maturity model (opm3)
Organizational project maturity model (opm3)Organizational project maturity model (opm3)
Organizational project maturity model (opm3)
 
9.1 Plan Resource Management
9.1 Plan Resource Management9.1 Plan Resource Management
9.1 Plan Resource Management
 
Topic 6 - Project Integration Management.pdf
Topic 6 - Project Integration Management.pdfTopic 6 - Project Integration Management.pdf
Topic 6 - Project Integration Management.pdf
 
041006-Program Management PMI NB - PMI Logo
041006-Program Management PMI NB - PMI Logo041006-Program Management PMI NB - PMI Logo
041006-Program Management PMI NB - PMI Logo
 
Planning process group
Planning process groupPlanning process group
Planning process group
 
13.0 Project Stakeholder Management Overview
13.0 Project Stakeholder Management Overview13.0 Project Stakeholder Management Overview
13.0 Project Stakeholder Management Overview
 
13.2 Plan Stakeholder Engagement
13.2 Plan Stakeholder Engagement13.2 Plan Stakeholder Engagement
13.2 Plan Stakeholder Engagement
 
PMBoK ed.5 brief overview
PMBoK ed.5 brief overviewPMBoK ed.5 brief overview
PMBoK ed.5 brief overview
 
Project managment 10
Project managment  10Project managment  10
Project managment 10
 
PMP as per PMBOK 6
PMP as per PMBOK 6PMP as per PMBOK 6
PMP as per PMBOK 6
 
Lecture 07: Project Management Fundamentals Project Organization and Integr...
Lecture 07: Project Management Fundamentals Project Organization and Integr...Lecture 07: Project Management Fundamentals Project Organization and Integr...
Lecture 07: Project Management Fundamentals Project Organization and Integr...
 
Pmi rmp-2020 - v6
Pmi rmp-2020 - v6Pmi rmp-2020 - v6
Pmi rmp-2020 - v6
 

More from DavidMcLachlan1

10.1 Plan Communication Management
10.1 Plan Communication Management10.1 Plan Communication Management
10.1 Plan Communication ManagementDavidMcLachlan1
 
12.1 Procurement Contracts
12.1 Procurement Contracts12.1 Procurement Contracts
12.1 Procurement ContractsDavidMcLachlan1
 
12.2 Conduct Procurements
12.2 Conduct Procurements12.2 Conduct Procurements
12.2 Conduct ProcurementsDavidMcLachlan1
 
12.3 Control Procurements
12.3 Control Procurements12.3 Control Procurements
12.3 Control ProcurementsDavidMcLachlan1
 
4.4 Manage Project Knowledge
4.4 Manage Project Knowledge4.4 Manage Project Knowledge
4.4 Manage Project KnowledgeDavidMcLachlan1
 
Project Cost Forecasting Techniques with EAC, ETC, VAC, TCPI
Project Cost Forecasting Techniques with EAC, ETC, VAC, TCPIProject Cost Forecasting Techniques with EAC, ETC, VAC, TCPI
Project Cost Forecasting Techniques with EAC, ETC, VAC, TCPIDavidMcLachlan1
 
Scenario - Project Management Processes | 2 of 2
Scenario - Project Management Processes | 2 of 2Scenario - Project Management Processes | 2 of 2
Scenario - Project Management Processes | 2 of 2DavidMcLachlan1
 
Scenario - Project Management Processes | 1 of 2
Scenario - Project Management Processes | 1 of 2Scenario - Project Management Processes | 1 of 2
Scenario - Project Management Processes | 1 of 2DavidMcLachlan1
 
Scenario - The Project Management Environment
Scenario - The Project Management EnvironmentScenario - The Project Management Environment
Scenario - The Project Management EnvironmentDavidMcLachlan1
 
Agile Scenarios - Delivering an Agile Environment
Agile Scenarios - Delivering an Agile EnvironmentAgile Scenarios - Delivering an Agile Environment
Agile Scenarios - Delivering an Agile EnvironmentDavidMcLachlan1
 
Agile Scenarios - Core Practices
Agile Scenarios - Core PracticesAgile Scenarios - Core Practices
Agile Scenarios - Core PracticesDavidMcLachlan1
 
Agile Core Practices - Rolling Wave Planning
Agile Core Practices - Rolling Wave PlanningAgile Core Practices - Rolling Wave Planning
Agile Core Practices - Rolling Wave PlanningDavidMcLachlan1
 
6.0 Auxiliary Agile and Lean Frameworks
6.0 Auxiliary Agile and Lean Frameworks6.0 Auxiliary Agile and Lean Frameworks
6.0 Auxiliary Agile and Lean FrameworksDavidMcLachlan1
 
5.0 Core Agile and Lean Frameworks
5.0 Core Agile and Lean Frameworks5.0 Core Agile and Lean Frameworks
5.0 Core Agile and Lean FrameworksDavidMcLachlan1
 
7.0 Delivering in an Agile Environment
7.0 Delivering in an Agile Environment7.0 Delivering in an Agile Environment
7.0 Delivering in an Agile EnvironmentDavidMcLachlan1
 
4.0 The Agile Core Practices
4.0 The Agile Core Practices4.0 The Agile Core Practices
4.0 The Agile Core PracticesDavidMcLachlan1
 
3.0 The Agile Manifesto and Clarifying principles
3.0 The Agile Manifesto and Clarifying principles3.0 The Agile Manifesto and Clarifying principles
3.0 The Agile Manifesto and Clarifying principlesDavidMcLachlan1
 
2.0 The Differences Between Agile and Waterfall, Incremental, Iterative and H...
2.0 The Differences Between Agile and Waterfall, Incremental, Iterative and H...2.0 The Differences Between Agile and Waterfall, Incremental, Iterative and H...
2.0 The Differences Between Agile and Waterfall, Incremental, Iterative and H...DavidMcLachlan1
 

More from DavidMcLachlan1 (20)

10.1 Plan Communication Management
10.1 Plan Communication Management10.1 Plan Communication Management
10.1 Plan Communication Management
 
9.5 Manage Team
9.5 Manage Team9.5 Manage Team
9.5 Manage Team
 
12.1 Procurement Contracts
12.1 Procurement Contracts12.1 Procurement Contracts
12.1 Procurement Contracts
 
12.2 Conduct Procurements
12.2 Conduct Procurements12.2 Conduct Procurements
12.2 Conduct Procurements
 
12.3 Control Procurements
12.3 Control Procurements12.3 Control Procurements
12.3 Control Procurements
 
6.5 Develop Schedule
6.5 Develop Schedule6.5 Develop Schedule
6.5 Develop Schedule
 
4.4 Manage Project Knowledge
4.4 Manage Project Knowledge4.4 Manage Project Knowledge
4.4 Manage Project Knowledge
 
Project Cost Forecasting Techniques with EAC, ETC, VAC, TCPI
Project Cost Forecasting Techniques with EAC, ETC, VAC, TCPIProject Cost Forecasting Techniques with EAC, ETC, VAC, TCPI
Project Cost Forecasting Techniques with EAC, ETC, VAC, TCPI
 
Scenario - Project Management Processes | 2 of 2
Scenario - Project Management Processes | 2 of 2Scenario - Project Management Processes | 2 of 2
Scenario - Project Management Processes | 2 of 2
 
Scenario - Project Management Processes | 1 of 2
Scenario - Project Management Processes | 1 of 2Scenario - Project Management Processes | 1 of 2
Scenario - Project Management Processes | 1 of 2
 
Scenario - The Project Management Environment
Scenario - The Project Management EnvironmentScenario - The Project Management Environment
Scenario - The Project Management Environment
 
Agile Scenarios - Delivering an Agile Environment
Agile Scenarios - Delivering an Agile EnvironmentAgile Scenarios - Delivering an Agile Environment
Agile Scenarios - Delivering an Agile Environment
 
Agile Scenarios - Core Practices
Agile Scenarios - Core PracticesAgile Scenarios - Core Practices
Agile Scenarios - Core Practices
 
Agile Core Practices - Rolling Wave Planning
Agile Core Practices - Rolling Wave PlanningAgile Core Practices - Rolling Wave Planning
Agile Core Practices - Rolling Wave Planning
 
6.0 Auxiliary Agile and Lean Frameworks
6.0 Auxiliary Agile and Lean Frameworks6.0 Auxiliary Agile and Lean Frameworks
6.0 Auxiliary Agile and Lean Frameworks
 
5.0 Core Agile and Lean Frameworks
5.0 Core Agile and Lean Frameworks5.0 Core Agile and Lean Frameworks
5.0 Core Agile and Lean Frameworks
 
7.0 Delivering in an Agile Environment
7.0 Delivering in an Agile Environment7.0 Delivering in an Agile Environment
7.0 Delivering in an Agile Environment
 
4.0 The Agile Core Practices
4.0 The Agile Core Practices4.0 The Agile Core Practices
4.0 The Agile Core Practices
 
3.0 The Agile Manifesto and Clarifying principles
3.0 The Agile Manifesto and Clarifying principles3.0 The Agile Manifesto and Clarifying principles
3.0 The Agile Manifesto and Clarifying principles
 
2.0 The Differences Between Agile and Waterfall, Incremental, Iterative and H...
2.0 The Differences Between Agile and Waterfall, Incremental, Iterative and H...2.0 The Differences Between Agile and Waterfall, Incremental, Iterative and H...
2.0 The Differences Between Agile and Waterfall, Incremental, Iterative and H...
 

Recently uploaded

Historical philosophical, theoretical, and legal foundations of special and i...
Historical philosophical, theoretical, and legal foundations of special and i...Historical philosophical, theoretical, and legal foundations of special and i...
Historical philosophical, theoretical, and legal foundations of special and i...jaredbarbolino94
 
Organic Name Reactions for the students and aspirants of Chemistry12th.pptx
Organic Name Reactions  for the students and aspirants of Chemistry12th.pptxOrganic Name Reactions  for the students and aspirants of Chemistry12th.pptx
Organic Name Reactions for the students and aspirants of Chemistry12th.pptxVS Mahajan Coaching Centre
 
“Oh GOSH! Reflecting on Hackteria's Collaborative Practices in a Global Do-It...
“Oh GOSH! Reflecting on Hackteria's Collaborative Practices in a Global Do-It...“Oh GOSH! Reflecting on Hackteria's Collaborative Practices in a Global Do-It...
“Oh GOSH! Reflecting on Hackteria's Collaborative Practices in a Global Do-It...Marc Dusseiller Dusjagr
 
ENGLISH 7_Q4_LESSON 2_ Employing a Variety of Strategies for Effective Interp...
ENGLISH 7_Q4_LESSON 2_ Employing a Variety of Strategies for Effective Interp...ENGLISH 7_Q4_LESSON 2_ Employing a Variety of Strategies for Effective Interp...
ENGLISH 7_Q4_LESSON 2_ Employing a Variety of Strategies for Effective Interp...JhezDiaz1
 
Crayon Activity Handout For the Crayon A
Crayon Activity Handout For the Crayon ACrayon Activity Handout For the Crayon A
Crayon Activity Handout For the Crayon AUnboundStockton
 
Difference Between Search & Browse Methods in Odoo 17
Difference Between Search & Browse Methods in Odoo 17Difference Between Search & Browse Methods in Odoo 17
Difference Between Search & Browse Methods in Odoo 17Celine George
 
Framing an Appropriate Research Question 6b9b26d93da94caf993c038d9efcdedb.pdf
Framing an Appropriate Research Question 6b9b26d93da94caf993c038d9efcdedb.pdfFraming an Appropriate Research Question 6b9b26d93da94caf993c038d9efcdedb.pdf
Framing an Appropriate Research Question 6b9b26d93da94caf993c038d9efcdedb.pdfUjwalaBharambe
 
Procuring digital preservation CAN be quick and painless with our new dynamic...
Procuring digital preservation CAN be quick and painless with our new dynamic...Procuring digital preservation CAN be quick and painless with our new dynamic...
Procuring digital preservation CAN be quick and painless with our new dynamic...Jisc
 
Pharmacognosy Flower 3. Compositae 2023.pdf
Pharmacognosy Flower 3. Compositae 2023.pdfPharmacognosy Flower 3. Compositae 2023.pdf
Pharmacognosy Flower 3. Compositae 2023.pdfMahmoud M. Sallam
 
CELL CYCLE Division Science 8 quarter IV.pptx
CELL CYCLE Division Science 8 quarter IV.pptxCELL CYCLE Division Science 8 quarter IV.pptx
CELL CYCLE Division Science 8 quarter IV.pptxJiesonDelaCerna
 
Like-prefer-love -hate+verb+ing & silent letters & citizenship text.pdf
Like-prefer-love -hate+verb+ing & silent letters & citizenship text.pdfLike-prefer-love -hate+verb+ing & silent letters & citizenship text.pdf
Like-prefer-love -hate+verb+ing & silent letters & citizenship text.pdfMr Bounab Samir
 
DATA STRUCTURE AND ALGORITHM for beginners
DATA STRUCTURE AND ALGORITHM for beginnersDATA STRUCTURE AND ALGORITHM for beginners
DATA STRUCTURE AND ALGORITHM for beginnersSabitha Banu
 
Gas measurement O2,Co2,& ph) 04/2024.pptx
Gas measurement O2,Co2,& ph) 04/2024.pptxGas measurement O2,Co2,& ph) 04/2024.pptx
Gas measurement O2,Co2,& ph) 04/2024.pptxDr.Ibrahim Hassaan
 
POINT- BIOCHEMISTRY SEM 2 ENZYMES UNIT 5.pptx
POINT- BIOCHEMISTRY SEM 2 ENZYMES UNIT 5.pptxPOINT- BIOCHEMISTRY SEM 2 ENZYMES UNIT 5.pptx
POINT- BIOCHEMISTRY SEM 2 ENZYMES UNIT 5.pptxSayali Powar
 
Full Stack Web Development Course for Beginners
Full Stack Web Development Course  for BeginnersFull Stack Web Development Course  for Beginners
Full Stack Web Development Course for BeginnersSabitha Banu
 
Capitol Tech U Doctoral Presentation - April 2024.pptx
Capitol Tech U Doctoral Presentation - April 2024.pptxCapitol Tech U Doctoral Presentation - April 2024.pptx
Capitol Tech U Doctoral Presentation - April 2024.pptxCapitolTechU
 
EPANDING THE CONTENT OF AN OUTLINE using notes.pptx
EPANDING THE CONTENT OF AN OUTLINE using notes.pptxEPANDING THE CONTENT OF AN OUTLINE using notes.pptx
EPANDING THE CONTENT OF AN OUTLINE using notes.pptxRaymartEstabillo3
 

Recently uploaded (20)

Historical philosophical, theoretical, and legal foundations of special and i...
Historical philosophical, theoretical, and legal foundations of special and i...Historical philosophical, theoretical, and legal foundations of special and i...
Historical philosophical, theoretical, and legal foundations of special and i...
 
Organic Name Reactions for the students and aspirants of Chemistry12th.pptx
Organic Name Reactions  for the students and aspirants of Chemistry12th.pptxOrganic Name Reactions  for the students and aspirants of Chemistry12th.pptx
Organic Name Reactions for the students and aspirants of Chemistry12th.pptx
 
“Oh GOSH! Reflecting on Hackteria's Collaborative Practices in a Global Do-It...
“Oh GOSH! Reflecting on Hackteria's Collaborative Practices in a Global Do-It...“Oh GOSH! Reflecting on Hackteria's Collaborative Practices in a Global Do-It...
“Oh GOSH! Reflecting on Hackteria's Collaborative Practices in a Global Do-It...
 
ENGLISH 7_Q4_LESSON 2_ Employing a Variety of Strategies for Effective Interp...
ENGLISH 7_Q4_LESSON 2_ Employing a Variety of Strategies for Effective Interp...ENGLISH 7_Q4_LESSON 2_ Employing a Variety of Strategies for Effective Interp...
ENGLISH 7_Q4_LESSON 2_ Employing a Variety of Strategies for Effective Interp...
 
Crayon Activity Handout For the Crayon A
Crayon Activity Handout For the Crayon ACrayon Activity Handout For the Crayon A
Crayon Activity Handout For the Crayon A
 
Difference Between Search & Browse Methods in Odoo 17
Difference Between Search & Browse Methods in Odoo 17Difference Between Search & Browse Methods in Odoo 17
Difference Between Search & Browse Methods in Odoo 17
 
Framing an Appropriate Research Question 6b9b26d93da94caf993c038d9efcdedb.pdf
Framing an Appropriate Research Question 6b9b26d93da94caf993c038d9efcdedb.pdfFraming an Appropriate Research Question 6b9b26d93da94caf993c038d9efcdedb.pdf
Framing an Appropriate Research Question 6b9b26d93da94caf993c038d9efcdedb.pdf
 
Model Call Girl in Bikash Puri Delhi reach out to us at 🔝9953056974🔝
Model Call Girl in Bikash Puri  Delhi reach out to us at 🔝9953056974🔝Model Call Girl in Bikash Puri  Delhi reach out to us at 🔝9953056974🔝
Model Call Girl in Bikash Puri Delhi reach out to us at 🔝9953056974🔝
 
Procuring digital preservation CAN be quick and painless with our new dynamic...
Procuring digital preservation CAN be quick and painless with our new dynamic...Procuring digital preservation CAN be quick and painless with our new dynamic...
Procuring digital preservation CAN be quick and painless with our new dynamic...
 
Pharmacognosy Flower 3. Compositae 2023.pdf
Pharmacognosy Flower 3. Compositae 2023.pdfPharmacognosy Flower 3. Compositae 2023.pdf
Pharmacognosy Flower 3. Compositae 2023.pdf
 
CELL CYCLE Division Science 8 quarter IV.pptx
CELL CYCLE Division Science 8 quarter IV.pptxCELL CYCLE Division Science 8 quarter IV.pptx
CELL CYCLE Division Science 8 quarter IV.pptx
 
Like-prefer-love -hate+verb+ing & silent letters & citizenship text.pdf
Like-prefer-love -hate+verb+ing & silent letters & citizenship text.pdfLike-prefer-love -hate+verb+ing & silent letters & citizenship text.pdf
Like-prefer-love -hate+verb+ing & silent letters & citizenship text.pdf
 
DATA STRUCTURE AND ALGORITHM for beginners
DATA STRUCTURE AND ALGORITHM for beginnersDATA STRUCTURE AND ALGORITHM for beginners
DATA STRUCTURE AND ALGORITHM for beginners
 
Gas measurement O2,Co2,& ph) 04/2024.pptx
Gas measurement O2,Co2,& ph) 04/2024.pptxGas measurement O2,Co2,& ph) 04/2024.pptx
Gas measurement O2,Co2,& ph) 04/2024.pptx
 
POINT- BIOCHEMISTRY SEM 2 ENZYMES UNIT 5.pptx
POINT- BIOCHEMISTRY SEM 2 ENZYMES UNIT 5.pptxPOINT- BIOCHEMISTRY SEM 2 ENZYMES UNIT 5.pptx
POINT- BIOCHEMISTRY SEM 2 ENZYMES UNIT 5.pptx
 
Full Stack Web Development Course for Beginners
Full Stack Web Development Course  for BeginnersFull Stack Web Development Course  for Beginners
Full Stack Web Development Course for Beginners
 
ESSENTIAL of (CS/IT/IS) class 06 (database)
ESSENTIAL of (CS/IT/IS) class 06 (database)ESSENTIAL of (CS/IT/IS) class 06 (database)
ESSENTIAL of (CS/IT/IS) class 06 (database)
 
OS-operating systems- ch04 (Threads) ...
OS-operating systems- ch04 (Threads) ...OS-operating systems- ch04 (Threads) ...
OS-operating systems- ch04 (Threads) ...
 
Capitol Tech U Doctoral Presentation - April 2024.pptx
Capitol Tech U Doctoral Presentation - April 2024.pptxCapitol Tech U Doctoral Presentation - April 2024.pptx
Capitol Tech U Doctoral Presentation - April 2024.pptx
 
EPANDING THE CONTENT OF AN OUTLINE using notes.pptx
EPANDING THE CONTENT OF AN OUTLINE using notes.pptxEPANDING THE CONTENT OF AN OUTLINE using notes.pptx
EPANDING THE CONTENT OF AN OUTLINE using notes.pptx
 

11.1 Plan Risk Management

  • 2. Plan Risk Management Coincides with PMBOK 11.1 Process Group and Knowledge Area Mapping Knowledge Areas Initiating Planning Process Group Executing Process Group Monitoring and Controlling Process Group Closing Process Group 4. Project Integration Management 4.1 Develop Project Charter 4.2 Develop Project Management Plan 4.3 Direct and Manage Project Work 4.4 Manage Project Knowledge 4.5 Monitor and Control Project Work 4.6 Perform Integrated Change Control 4.7 Close Project or Phase 5. Project Scope Management 5.1 Plan Scope Management 5.2 Collect Requirements 5.3 Define Scope 5.4 Create WBS 5.5 Validate Scope 5.6 Control Scope 6. Project Schedule Management 6.1 Plan Schedule Management 6.2 Define Activities 6.3 Sequence Activities 6.4 Estimate Activity Durations 6.5 Develop Schedule 6.6 Control Schedule 7. Project Cost Management 7.1 Plan Cost Management 7.2 Estimate Costs 7.3 Determine Budget 7.4 Control Costs 8. Project Quality Management 8.1 Plan Quality Management 8.2 Manage Quality 8.3 Control Quality 9. Project Resource Management 9.1 Plan Resource Management 9.2 Estimate Activity Resources 9.3 Acquire Resources 9.4 Develop Team 9.5 Manage Team 9.6 Control Resources 10. Project Communications Management 10.1 Plan Communications Management 10.2 Manage Communications 10.3 Monitor Communications 11. Project Risk Management 11.1 Plan Risk Management 11.2 Identify Risks 11.3 Perform Qualitative Risk Analysis 11.4 Perform Quantitative Risk Analysis 11.5 Plan Risk Responses 11.6 Implement Risk Responses 11.7 Monitor Risks 12. Project Procurement Management 12.1 Plan Procurement Management 12.2 Conduct Procurements 12.3 Control Procurements 13. Project Stakeholder Management 13.1 Identify Stakeholders 13.2 Plan Stakeholder Engagement 13.3 Manage Stakeholder Engagement 13.4 Monitor Stakeholder Engagement
  • 3. What is it? Plan Risk Management is the process of defining how to conduct risk management activities for a project. Why? The key benefit of this process is that it ensures that the degree, type, and visibility of risk management are proportionate to both risks and the importance of the project to the organization and other stakeholders. Plan Risk Management Coincides with PMBOK 11.1
  • 4. Overview • The Plan Risk Management process should begin when a project is conceived and should be completed early in the project. • It may be necessary to revisit this process later in the project life cycle, for example at a major phase change, or if the project scope changes significantly, or if a subsequent review of risk management effectiveness determines that the Project Risk Management process requires modification. Coincides with PMBOK 11.1 Plan Risk Management
  • 5. Plan Risk Management Coincides with PMBOK 11.1 Inputs Tools & Techniques Outputs 1. Project charter 2. Project management plan • All components 3. Project documents • Stakeholder register 4. Enterprise environmental factors 5. Organizational process assets 1. Expert judgment 2. Data analysis • Stakeholder analysis 3. Meetings 1. Risk management plan Inputs, Tools & Techniques, Outputs
  • 6. Plan Risk Management Coincides with PMBOK 11.1 11.1 Plan Risk Management Project Management Plan Enterprise/Orga nization 4.1 Develop Project Charter • Risk management plan • All components • Enterprise environmental factors • Organizational process assets • Project charter Project Documents • Stakeholder register Project Management Plan
  • 7. Plan Risk Management - Inputs Coincides with PMBOK 11.1 Project Charter The project charter documents the high-level project description and boundaries, high- level requirements, and risks.
  • 8. Plan Risk Management - Inputs Coincides with PMBOK 11.1 Project Management Plan In planning Project Risk Management, all approved subsidiary management plans should be taken into consideration in order to make the risk management plan consistent with them. The methodology outlined in other project management plan components might influence the Plan Risk Management process.
  • 9. Plan Risk Management - Inputs Coincides with PMBOK 11.1 Project Documents Project documents that can be considered as inputs for this process include but are not limited to the stakeholder register. The stakeholder register contains details of the project’s stakeholders and provides an overview of their project roles and their attitude toward risk on this project.
  • 10. Coincides with PMBOK 11.1 Enterprise Environmental Factors The enterprise environmental factors that can influence the Plan Risk Management process include but are not limited to overall risk thresholds set by the organization or key stakeholders. Plan Risk Management - Inputs
  • 11. Coincides with PMBOK 11.1 Organisational Process Assets The organizational process assets that can influence the Plan Risk Management process include: • Organizational risk policy • Risk categories, possibly organized into a risk breakdown structure • Common definitions of risk concepts and terms • Risk statement formats • Templates for the risk management plan, risk register, and risk report • Roles and responsibilities • Authority levels for decision making • Lessons learned repository from previous similar projects. Plan Risk Management - Inputs
  • 12. Plan Risk Management – Tools & Techniques Coincides with PMBOK 11.1 Expert Judgment Expertise should be considered from individuals or groups with specialized knowledge or training in the following topics: • Familiarity with the organization’s approach to managing risk, including enterprise risk management where this is performed • Tailoring risk management to the specific needs of a project • Types of risk that are likely to be encountered on projects in the same area
  • 13. Plan Risk Management – Tools & Techniques Coincides with PMBOK 11.1 Data Analysis Data analysis techniques that can be used for this process includes but are not limited to a stakeholder analysis to determine the risk appetite of project stakeholders.
  • 14. Coincides with PMBOK 11.1 Meetings Plan Risk Management – Tools & Techniques The risk management plan may be developed as part of the project kick-off meeting or a specific planning meeting may be held. Attendees may include the project manager, selected project team members, key stakeholders, or team members who are responsible to manage the risk management process on the project. Plans for conducting risk management activities are defined in these meetings and documented in the risk management plan.
  • 15. Plan Risk Management - Outputs Coincides with PMBOK 11.1 Risk Management Plan The risk management plan is a component of the project management plan that describes how risk management activities will be structured and performed. The risk management plan may include some or all the following elements: • Risk strategy • Methodology • Roles and responsibilities • Funding • Timing • Tracking • Risk categories • Stakeholder risk appetite • Definitions of risk probability and impacts • Probability and impact matrix • Reporting Formats
  • 16. Plan Risk Management - Outputs Coincides with PMBOK 11.1 Risk Management Plan – Risk Categories A common way to structure risk categories is with a risk breakdown structure (RBS), which is a hierarchical representation of potential sources of risk. An RBS helps the project team consider the full range of sources from which individual project risks may arise. Example of Risk Breakdown Structure
  • 17. Plan Risk Management - Outputs Coincides with PMBOK 11.1 Risk Management Plan – Definitions of risk probability and impacts Definitions of risk probability and impact levels are specific to the project context and reflect the risk appetite and thresholds of the organization and key stakeholders. Example provides an example of definitions of probability and impacts against three project objectives. Example of Definitions of risk probability and impacts
  • 18. Plan Risk Management - Outputs Coincides with PMBOK 11.1 Risk Management Plan – Probability and Impact Matrix Opportunities and threats are represented in a common probability and impact matrix using positive definitions of impact for opportunities and negative impact definitions for threats. An example probability and impact matrix is presented, which also shows a possible numeric risk scoring scheme. Example of Probability and Impact Matrix

Editor's Notes

  1. This process is performed once or at predefined points in the project.
  2. This is useful in determining roles and responsibilities for managing risk on the project, as well as setting risk thresholds for the project.
  3. Others outside the organization may also be invited, as needed, including customers, sellers, and regulators. A skilled facilitator can help participants remain focused on the task, agree on key aspects of the risk approach, identify and overcome sources of bias, and resolve any disagreements that may arise.
  4. Risk Strategy - Describes the general approach to managing risk on this project Methodology - Defines the specific approaches, tools, and data sources that will be used to perform risk management on the project. Roles and responsibilities - Defines the lead, support, and risk management team members for each type of activity described in the risk management plan, and clarifies their responsibilities. Funding - Identifies the funds needed to perform activities related to Project Risk Management. Establishes protocols for the application of contingency and management reserves. Timing - Defines when and how often the Project Risk Management processes will be performed throughout the project life cycle, and establishes risk management activities for inclusion into the project schedule. Risk Categories - Provide a means for grouping individual project risks. Stakeholder risk appetite - The risk appetites of key stakeholders on the project are recorded in the risk management plan, as they inform the details of the Plan Risk Management process. Definitions of risk probability and impacts - The project may generate specific definitions of probability that reflect risk appetite and thresholds of the organization and key stakeholders Probability impact matrix - Opportunities and threats are represented in a common probability and impact matrix using positive definitions of impact for opportunities and negative impact definitions for threats Reporting formats – Reporting formats define how the outcomes of the Project Risk Management process will be documented, analyzed, and communicated. Tracking - Tracking documents how risk activities will be recorded and how risk management processes will be audited.
  5. This can be useful when identifying risks or when categorizing identified risks. The organization may have a generic RBS to be used for all projects, or there may be several RBS frameworks for different types of projects, or the project may develop a tailored RBS. Where an RBS is not used, an organization may use a custom risk categorization framework, which may take the form of a simple list of categories or a structure based on project objectives.
  6. The project may generate specific definitions of probability and impact levels or it may start with general definitions provided by the organization. The number of levels reflects the degree of detail required for the Project Risk Management process, with more levels used for a more detailed risk approach (typically five levels), and fewer for a simple process (usually three) In Figure - These scales can be used to evaluate both threats and opportunities by interpreting the impact definitions as negative for threats (delay, additional cost, and performance shortfall) and positive for opportunities (reduced time or cost, and performance enhancement).
  7. Prioritization rules may be specified by the organization in advance of the project and be included in organizational process assets, or they may be tailored to the specific project Descriptive terms (such as very high, high, medium, low, and very low) or numeric values can be used for probability and impact. Where numeric values are used, these can be multiplied to give a probability-impact score for each risk, which allows the relative priority of individual risks to be evaluated within each priority level.