SlideShare a Scribd company logo
1 of 22
Conduct Procurements
Conduct Procurements
Coincides with PMBOK 12.2
Process Group and Knowledge Area Mapping
Knowledge Areas Initiating Planning Process Group Executing Process Group Monitoring and Controlling Process Group Closing Process Group
4. Project Integration
Management
4.1 Develop Project Charter
4.2 Develop Project Management
Plan
4.3 Direct and Manage Project Work
4.4 Manage Project Knowledge
4.5 Monitor and Control Project Work
4.6 Perform Integrated Change Control
4.7 Close Project or Phase
5. Project Scope
Management
5.1 Plan Scope Management
5.2 Collect Requirements
5.3 Define Scope
5.4 Create WBS
5.5 Validate Scope
5.6 Control Scope
6. Project Schedule
Management
6.1 Plan Schedule Management
6.2 Define Activities
6.3 Sequence Activities
6.4 Estimate Activity Durations
6.5 Develop Schedule
6.6 Control Schedule
7. Project Cost Management
7.1 Plan Cost Management
7.2 Estimate Costs
7.3 Determine Budget
7.4 Control Costs
8. Project Quality
Management
8.1 Plan Quality Management 8.2 Manage Quality 8.3 Control Quality
9. Project Resource
Management
9.1 Plan Resource Management
9.2 Estimate Activity Resources
9.3 Acquire Resources
9.4 Develop Team
9.5 Manage Team
9.6 Control Resources
10. Project Communications
Management
10.1 Plan Communications
Management
10.2 Manage Communications 10.3 Monitor Communications
11. Project Risk
Management
11.1 Plan Risk Management
11.2 Identify Risks
11.3 Perform Qualitative Risk Analysis
11.4 Perform Quantitative Risk
Analysis
11.5 Plan Risk Responses
11.6 Implement Risk Responses 11.7 Monitor Risks
12. Project Procurement
Management
12.1 Plan Procurement Management 12.2 Conduct Procurements 12.3 Control Procurements
13. Project Stakeholder
Management
13.1 Identify Stakeholders 13.2 Plan Stakeholder Engagement
13.3 Manage Stakeholder
Engagement
13.4 Monitor Stakeholder Engagement
What is it?
Conduct Procurements is the process of obtaining seller responses,
selecting a seller, and awarding a contract.
Why?
The key benefit of this process is that it selects a qualified seller and
implements the legal agreement for delivery. The end results of the
process are the established agreements including formal contracts.
Conduct Procurements
Coincides with PMBOK 12.2
Inputs Tools & Techniques Outputs
1. Project management plan
• Scope management plan
• Requirements management plan
• Communications management
plan
• Risk management plan
• Procurement management plan
• Configuration management plan
• Cost baseline
2. Project documents
• Lessons learned register
• Project schedule
• Requirements
• documentation
• Risk register
• Stakeholder register
3. Procurement documentation
4. Seller proposals
5. Enterprise environmental factors
6. Organizational process assets
1. Expert judgment
2. Advertising
3. Bidder conferences
4. Data analysis
• Proposal evaluation
5. Interpersonal and team skills
• Negotiation
1. Selected sellers
2. Agreements
3. Change requests
4. Project management plan updates
• Requirements management plan
• Quality management plan
• Communications management plan
• Risk management plan
• Procurement management plan
• Scope baseline
• Schedule baseline
• Cost baseline
5. Project documents updates
• Lessons learned register
• Requirements documentation
• Requirements traceability matrix
• Resource calendars
• Risk register
• Stakeholder register
6. Organizational process assets updates
Inputs, Tools & Techniques, Outputs
Conduct Procurements Coincides with PMBOK 12.2
12.2 Conduct
Procurements
Project
Management
Plan
• Lessons learned register
• Project schedule
• Requirements
• documentation
• Risk register
• Stakeholder register
• Sellers proposals
Project
Documents
• Lessons learned register
• Requirements documentation
• Requirements traceability matrix
• Resource calendars
• Risk register
• Stakeholder register
• Scope management plan
• Requirements management plan
• Communications management plan
• Risk management plan
• Procurement management plan
• Configuration management plan
• Cost baseline
Project
Documents
• Change Requests
• Requirements management plan
• Quality management plan
• Communications management plan
• Risk management plan
• Procurement management plan
• Scope baseline
• Schedule baseline
• Cost baseline
Project
Management
Plan
Enterprise/Orga
nization • Organizational process assets
• Selected Sellers• Enterprise organizational factors
• Organizational process assets
Conduct Procurements
Coincides with PMBOK 12.2
Enterprise/Orga
nization
Procurement
Documentation
Sellers
12.3 Control
Procurements
4.6 Perform
Integrated
Change Control
4.1 Develop
Project Charter
4.5 Monitor and
Control Project
Work
4.7 Close
Project or
Phase
6.5 Develop
Schedule
7.3 Determine
Budget
9.6 Control
Resources
12.3 Control
Procurements
13.1 Identify
Stakeholders
13.1 Identify
Stakeholders
• Agreements
Conduct Procurements - Inputs
Coincides with PMBOK 12.2
Project Management Plan
Project management plan components include:
• Scope management plan
• Requirements management plan
• Communications management plan
• Risk management plan
• Procurement management plan
• Configuration management plan
• Cost baseline
Project Documents
Project documents that should be considered as inputs for this process include:
• Lessons learned register
• Project schedule
• Requirements documentation
• Risk register
• Stakeholder register
Conduct Procurements - Inputs
Coincides with PMBOK 12.2
Procurement Documentation
Procurement documentation provides a written record used in reaching the legal
agreement, and may include older documents predating the current project.
Procurement documentation can include:
• Bid Documents
• Procurement statement of work
• Independent cost estimates
• Source selection criteria
Conduct Procurements - Inputs
Coincides with PMBOK 12.2
Seller Proposals
• Seller proposals, prepared in response to a procurement document package, form
the basic information that will be used by an evaluation body to select one or more
successful bidders (sellers).
• The evaluation body reviews each submitted proposal according to the source
selection criteria and selects the seller that can best satisfy the buying
organization’s requirements.
Conduct Procurements - Inputs
Coincides with PMBOK 12.2
Enterprise Environmental Factors
The enterprise environmental factors that can influence the Conduct Procurements
Process include:
• Local laws and regulations regarding procurements
• Local laws and regulations ensuring that the major procurements involve local
sellers
• External economic environment constraining procurement processes
• Marketplace conditions
• Information on relevant past experience with sellers, both good and bad
• Prior agreements already in place
• Contract management systems
Conduct Procurements - Inputs
Coincides with PMBOK 12.2
Organizational Process Assets
The organizational process assets that can influence the Conduct Procurements
process include but are not limited to:
• List of preferred sellers that have been prequalified
• Organizational policies that influence the selection of a seller
• Specific organizational templates or guidelines that will determine the way
agreements are drafted and built
• Financial policies and procedures regarding invoicing and payment processes.
Conduct Procurements - Inputs
Coincides with PMBOK 12.2
Expert Judgement
Expertise should be considered from individuals or groups with specialized knowledge
or training in the following topics:
• Proposal evaluation
• Technical or subject matter
• Relevant functional areas such as finance, engineering, design, development,
supply chain management, etc.
• Industry regulatory environment
• Laws, regulations, and compliance requirements
• Negotiation
Conduct Procurements – Tools & Techniques
Coincides with PMBOK 12.2
Advertising
Advertising is communicating with users or potential users of a product,
service, or result. Existing lists of potential sellers often can be expanded by
placing advertisements in general circulation publications such as selected
newspapers or in specialty trade publications. Most government jurisdictions
require public advertising or online posting of pending government contracts.
Conduct Procurements – Tools & Techniques
Coincides with PMBOK 12.2
Bidder Conferences
Bidder conferences (also called contractor conferences, vendor conferences,
and pre-bid conferences) are meetings between the buyer and prospective
sellers prior to proposal submittal. They are used to ensure that all prospective
bidders have a clear and common understanding of the procurement and no
bidders receive preferential treatment.
Conduct Procurements – Tools & Techniques
Coincides with PMBOK 12.2
Data Analysis
A data analysis technique that can be used for this process includes but is not
limited to proposal evaluation. Proposals are evaluated to ensure they are
complete and respond in full to the bid documents, procurement statement of
work, source selection criteria, and any other documents that went out in the
bid package.
Conduct Procurements – Tools & Techniques
Coincides with PMBOK 12.2
Interpersonal and Team Skills
• Interpersonal and team skills that can be used for this process include negotiation.
• Negotiation is a discussion aimed at reaching an agreement. Procurement
negotiation clarifies the structure, rights, and obligations of the parties and other
terms of the purchases so that mutual agreement can be reached prior to signing
the contract.
• The negotiation should be led by a member of the procurement team that has the
authority to sign contracts.
Conduct Procurements – Tools & Techniques
Coincides with PMBOK 12.2
Selected Sellers
• The selected sellers are those who have been judged to be in a competitive
range based on the outcome of the proposal or bid evaluation.
• Final approval of complex, high-value, high-risk procurements will generally
require organizational senior management approval prior to award.
Conduct Procurements – Outputs
Coincides with PMBOK 12.2
Agreements
A contract is a mutually binding agreement that obligates the seller to provide the specified
products, services, or results; obligates the buyer to compensate the seller; and represents a
legal relationship that is subject to remedy in the courts. The major components in an
agreement document may include:
Conduct Procurements – Outputs
Coincides with PMBOK 12.2
• Incentives and penalties
• Insurance and performance bonds
• Subordinate subcontractor approvals
• General terms and conditions
• Change request handling
• Termination clause and alternative dispute
resolution mechanisms
• Procurement statement of work or major
deliverables
• Schedule, milestones, or date by which a schedule
is required
• Performance reporting
• Pricing and payment terms
• Inspection, quality, and acceptance criteria
• Warranty and future product support
Change Requests
Change requests to the project management plan, its subsidiary plans,
and other components are processed for review and disposition through
the Perform Integrated Change Control process
Conduct Procurements – Outputs
Coincides with PMBOK 12.2
Project Management Plan Updates
Any change to the project management plan goes through the organization’s change control
process via a change request. Components of the project management plan that may require
a change request for the project management plan include:
• Requirements management plan
• Quality management plan
• Communications management plan
• Risk management plan
• Procurement management plan
• Scope baseline
• Schedule baseline
• Cost baseline
Conduct Procurements – Outputs
Coincides with PMBOK 12.2
Project Document Updates
Project documents that may be updated as a result of carrying out this process include:
• Lessons learned register
• Requirements documentation
• Requirements traceability matrix
• Resource calendars
• Risk register
• Stakeholder register
Conduct Procurements – Outputs
Coincides with PMBOK 12.2
Organizational Process Assets Updates
Elements of the organizational process assets that can be updated as a result of the
Conduct Procurements process can include:
• Listings of prospective and prequalified sellers
• Information on relevant experience with sellers, both good and bad.
Conduct Procurements – Outputs
Coincides with PMBOK 12.2

More Related Content

What's hot

Project Procurement Management
 Project Procurement Management  Project Procurement Management
Project Procurement Management Serdar Temiz
 
What is the difference between procurement and purchasing
What is the difference between procurement and purchasingWhat is the difference between procurement and purchasing
What is the difference between procurement and purchasingleadershipmgtservice
 
Procurement Mgmt Supplement1
Procurement Mgmt Supplement1Procurement Mgmt Supplement1
Procurement Mgmt Supplement1zfr71
 
VENDOR PROCESS DEVELOPMENT
VENDOR PROCESS DEVELOPMENTVENDOR PROCESS DEVELOPMENT
VENDOR PROCESS DEVELOPMENTSWAPAN KUMAR ROY
 
Project management procurement
Project management  procurementProject management  procurement
Project management procurementMalcolm Peart
 
Introduction to procurement
Introduction to procurementIntroduction to procurement
Introduction to procurementVj NiroSh
 
Basic procurement principle lect.1
Basic procurement principle lect.1Basic procurement principle lect.1
Basic procurement principle lect.1AMOS MIYUDA
 
Types of procurement solicitations and types of contracts
Types of procurement solicitations and types of contractsTypes of procurement solicitations and types of contracts
Types of procurement solicitations and types of contractsProColombia
 
Section 01 Procurement Fundamentals
Section 01 Procurement FundamentalsSection 01 Procurement Fundamentals
Section 01 Procurement FundamentalsAvik Munshi
 
Purchasing, Procurement, Vendor, Contract and RFP Process Management with Sha...
Purchasing, Procurement, Vendor, Contract and RFP Process Management with Sha...Purchasing, Procurement, Vendor, Contract and RFP Process Management with Sha...
Purchasing, Procurement, Vendor, Contract and RFP Process Management with Sha...Optimus BT
 
Contract management.ppt
Contract management.pptContract management.ppt
Contract management.pptMUST
 
Overview to contract management
Overview to contract managementOverview to contract management
Overview to contract managementPriyesh Nair
 
Purchasing and Procurement management
Purchasing and Procurement managementPurchasing and Procurement management
Purchasing and Procurement managementFarouk Nasser
 
Project Procurement Management PMBOK 5
Project Procurement Management PMBOK 5Project Procurement Management PMBOK 5
Project Procurement Management PMBOK 5pankajsh10
 
Chap 12.3 Control Procurement
Chap 12.3 Control ProcurementChap 12.3 Control Procurement
Chap 12.3 Control ProcurementAnand Bobade
 
Effective Contract Management
Effective Contract ManagementEffective Contract Management
Effective Contract ManagementDr Gordon Murray
 

What's hot (20)

Project Procurement Management
 Project Procurement Management  Project Procurement Management
Project Procurement Management
 
What is the difference between procurement and purchasing
What is the difference between procurement and purchasingWhat is the difference between procurement and purchasing
What is the difference between procurement and purchasing
 
Procurement Mgmt Supplement1
Procurement Mgmt Supplement1Procurement Mgmt Supplement1
Procurement Mgmt Supplement1
 
Contract Management
Contract Management Contract Management
Contract Management
 
Contract management general
Contract management generalContract management general
Contract management general
 
VENDOR PROCESS DEVELOPMENT
VENDOR PROCESS DEVELOPMENTVENDOR PROCESS DEVELOPMENT
VENDOR PROCESS DEVELOPMENT
 
Project management procurement
Project management  procurementProject management  procurement
Project management procurement
 
Introduction to procurement
Introduction to procurementIntroduction to procurement
Introduction to procurement
 
Basic procurement principle lect.1
Basic procurement principle lect.1Basic procurement principle lect.1
Basic procurement principle lect.1
 
Types of procurement solicitations and types of contracts
Types of procurement solicitations and types of contractsTypes of procurement solicitations and types of contracts
Types of procurement solicitations and types of contracts
 
Section 01 Procurement Fundamentals
Section 01 Procurement FundamentalsSection 01 Procurement Fundamentals
Section 01 Procurement Fundamentals
 
Purchasing, Procurement, Vendor, Contract and RFP Process Management with Sha...
Purchasing, Procurement, Vendor, Contract and RFP Process Management with Sha...Purchasing, Procurement, Vendor, Contract and RFP Process Management with Sha...
Purchasing, Procurement, Vendor, Contract and RFP Process Management with Sha...
 
Contract management.ppt
Contract management.pptContract management.ppt
Contract management.ppt
 
Overview to contract management
Overview to contract managementOverview to contract management
Overview to contract management
 
Purchasing and Procurement management
Purchasing and Procurement managementPurchasing and Procurement management
Purchasing and Procurement management
 
Project Procurement Management PMBOK 5
Project Procurement Management PMBOK 5Project Procurement Management PMBOK 5
Project Procurement Management PMBOK 5
 
Chap 12.3 Control Procurement
Chap 12.3 Control ProcurementChap 12.3 Control Procurement
Chap 12.3 Control Procurement
 
11- PMP Training - Procurement Management
11- PMP Training - Procurement Management 11- PMP Training - Procurement Management
11- PMP Training - Procurement Management
 
Effective Contract Management
Effective Contract ManagementEffective Contract Management
Effective Contract Management
 
The four-supply-chain-enablers
The four-supply-chain-enablersThe four-supply-chain-enablers
The four-supply-chain-enablers
 

Similar to 12.2 Conduct Procurements

12.3 Control Procurements
12.3 Control Procurements12.3 Control Procurements
12.3 Control ProcurementsDavidMcLachlan1
 
Topic 7 - Project Scope Management.pdf
Topic 7 - Project Scope Management.pdfTopic 7 - Project Scope Management.pdf
Topic 7 - Project Scope Management.pdfHuyNguyen657394
 
13.1 Identify Stakeholders
13.1 Identify Stakeholders13.1 Identify Stakeholders
13.1 Identify StakeholdersDavidMcLachlan1
 
7.1 Plan Cost Management
7.1 Plan Cost Management7.1 Plan Cost Management
7.1 Plan Cost ManagementDavidMcLachlan1
 
10.2 Manage Communication
10.2 Manage Communication10.2 Manage Communication
10.2 Manage CommunicationDavidMcLachlan1
 
10.3 Monitor Communication
10.3 Monitor Communication10.3 Monitor Communication
10.3 Monitor CommunicationDavidMcLachlan1
 
10.1 Plan Communication Management
10.1 Plan Communication Management10.1 Plan Communication Management
10.1 Plan Communication ManagementDavidMcLachlan1
 
10.1 Plan Communication Management
10.1 Plan Communication Management10.1 Plan Communication Management
10.1 Plan Communication ManagementDavidMcLachlan1
 
Undestand PMBok 5th, Section 4
Undestand PMBok 5th, Section 4Undestand PMBok 5th, Section 4
Undestand PMBok 5th, Section 4Amr Miqdadi
 
The Art Of Project Management
The Art Of Project ManagementThe Art Of Project Management
The Art Of Project Managementhatemk
 
L1-Project Integration Management.pdf
L1-Project Integration Management.pdfL1-Project Integration Management.pdf
L1-Project Integration Management.pdfMUST
 
Executing the Project (1).pdf
Executing the Project (1).pdfExecuting the Project (1).pdf
Executing the Project (1).pdfAkshithKota
 
Online PMP Training Material for PMP Exam - Integration Management Knowledge ...
Online PMP Training Material for PMP Exam - Integration Management Knowledge ...Online PMP Training Material for PMP Exam - Integration Management Knowledge ...
Online PMP Training Material for PMP Exam - Integration Management Knowledge ...GlobalSkillup
 

Similar to 12.2 Conduct Procurements (20)

12.3 Control Procurements
12.3 Control Procurements12.3 Control Procurements
12.3 Control Procurements
 
Topic 7 - Project Scope Management.pdf
Topic 7 - Project Scope Management.pdfTopic 7 - Project Scope Management.pdf
Topic 7 - Project Scope Management.pdf
 
05 project scope management
05 project scope management05 project scope management
05 project scope management
 
05 project scope management
05 project scope management05 project scope management
05 project scope management
 
Pmp scope chapter 5
Pmp scope chapter 5Pmp scope chapter 5
Pmp scope chapter 5
 
11.2 Identify Risks
11.2 Identify Risks11.2 Identify Risks
11.2 Identify Risks
 
13.1 Identify Stakeholders
13.1 Identify Stakeholders13.1 Identify Stakeholders
13.1 Identify Stakeholders
 
7.1 Plan Cost Management
7.1 Plan Cost Management7.1 Plan Cost Management
7.1 Plan Cost Management
 
10.2 Manage Communication
10.2 Manage Communication10.2 Manage Communication
10.2 Manage Communication
 
PMP PMBok 5th ch 5 scope management
PMP PMBok 5th ch 5 scope managementPMP PMBok 5th ch 5 scope management
PMP PMBok 5th ch 5 scope management
 
PMP PMBOK5 Ch4 integration management
PMP PMBOK5 Ch4 integration managementPMP PMBOK5 Ch4 integration management
PMP PMBOK5 Ch4 integration management
 
PMP-Scope Management area
PMP-Scope Management areaPMP-Scope Management area
PMP-Scope Management area
 
10.3 Monitor Communication
10.3 Monitor Communication10.3 Monitor Communication
10.3 Monitor Communication
 
10.1 Plan Communication Management
10.1 Plan Communication Management10.1 Plan Communication Management
10.1 Plan Communication Management
 
10.1 Plan Communication Management
10.1 Plan Communication Management10.1 Plan Communication Management
10.1 Plan Communication Management
 
Undestand PMBok 5th, Section 4
Undestand PMBok 5th, Section 4Undestand PMBok 5th, Section 4
Undestand PMBok 5th, Section 4
 
The Art Of Project Management
The Art Of Project ManagementThe Art Of Project Management
The Art Of Project Management
 
L1-Project Integration Management.pdf
L1-Project Integration Management.pdfL1-Project Integration Management.pdf
L1-Project Integration Management.pdf
 
Executing the Project (1).pdf
Executing the Project (1).pdfExecuting the Project (1).pdf
Executing the Project (1).pdf
 
Online PMP Training Material for PMP Exam - Integration Management Knowledge ...
Online PMP Training Material for PMP Exam - Integration Management Knowledge ...Online PMP Training Material for PMP Exam - Integration Management Knowledge ...
Online PMP Training Material for PMP Exam - Integration Management Knowledge ...
 

More from DavidMcLachlan1

12.1 Procurement Contracts
12.1 Procurement Contracts12.1 Procurement Contracts
12.1 Procurement ContractsDavidMcLachlan1
 
5.1 Plan Scope Management
5.1 Plan Scope Management5.1 Plan Scope Management
5.1 Plan Scope ManagementDavidMcLachlan1
 
4.4 Manage Project Knowledge
4.4 Manage Project Knowledge4.4 Manage Project Knowledge
4.4 Manage Project KnowledgeDavidMcLachlan1
 
Project Cost Forecasting Techniques with EAC, ETC, VAC, TCPI
Project Cost Forecasting Techniques with EAC, ETC, VAC, TCPIProject Cost Forecasting Techniques with EAC, ETC, VAC, TCPI
Project Cost Forecasting Techniques with EAC, ETC, VAC, TCPIDavidMcLachlan1
 
Scenario - Project Management Processes | 2 of 2
Scenario - Project Management Processes | 2 of 2Scenario - Project Management Processes | 2 of 2
Scenario - Project Management Processes | 2 of 2DavidMcLachlan1
 
Scenario - Project Management Processes | 1 of 2
Scenario - Project Management Processes | 1 of 2Scenario - Project Management Processes | 1 of 2
Scenario - Project Management Processes | 1 of 2DavidMcLachlan1
 
Scenario - The Project Management Environment
Scenario - The Project Management EnvironmentScenario - The Project Management Environment
Scenario - The Project Management EnvironmentDavidMcLachlan1
 
Agile Scenarios - Delivering an Agile Environment
Agile Scenarios - Delivering an Agile EnvironmentAgile Scenarios - Delivering an Agile Environment
Agile Scenarios - Delivering an Agile EnvironmentDavidMcLachlan1
 
Agile Scenarios - Core Practices
Agile Scenarios - Core PracticesAgile Scenarios - Core Practices
Agile Scenarios - Core PracticesDavidMcLachlan1
 
Agile Core Practices - Rolling Wave Planning
Agile Core Practices - Rolling Wave PlanningAgile Core Practices - Rolling Wave Planning
Agile Core Practices - Rolling Wave PlanningDavidMcLachlan1
 
6.0 Auxiliary Agile and Lean Frameworks
6.0 Auxiliary Agile and Lean Frameworks6.0 Auxiliary Agile and Lean Frameworks
6.0 Auxiliary Agile and Lean FrameworksDavidMcLachlan1
 
5.0 Core Agile and Lean Frameworks
5.0 Core Agile and Lean Frameworks5.0 Core Agile and Lean Frameworks
5.0 Core Agile and Lean FrameworksDavidMcLachlan1
 
7.0 Delivering in an Agile Environment
7.0 Delivering in an Agile Environment7.0 Delivering in an Agile Environment
7.0 Delivering in an Agile EnvironmentDavidMcLachlan1
 
4.0 The Agile Core Practices
4.0 The Agile Core Practices4.0 The Agile Core Practices
4.0 The Agile Core PracticesDavidMcLachlan1
 
3.0 The Agile Manifesto and Clarifying principles
3.0 The Agile Manifesto and Clarifying principles3.0 The Agile Manifesto and Clarifying principles
3.0 The Agile Manifesto and Clarifying principlesDavidMcLachlan1
 
2.0 The Differences Between Agile and Waterfall, Incremental, Iterative and H...
2.0 The Differences Between Agile and Waterfall, Incremental, Iterative and H...2.0 The Differences Between Agile and Waterfall, Incremental, Iterative and H...
2.0 The Differences Between Agile and Waterfall, Incremental, Iterative and H...DavidMcLachlan1
 

More from DavidMcLachlan1 (20)

9.5 Manage Team
9.5 Manage Team9.5 Manage Team
9.5 Manage Team
 
12.1 Procurement Contracts
12.1 Procurement Contracts12.1 Procurement Contracts
12.1 Procurement Contracts
 
6.5 Develop Schedule
6.5 Develop Schedule6.5 Develop Schedule
6.5 Develop Schedule
 
5.1 Plan Scope Management
5.1 Plan Scope Management5.1 Plan Scope Management
5.1 Plan Scope Management
 
4.4 Manage Project Knowledge
4.4 Manage Project Knowledge4.4 Manage Project Knowledge
4.4 Manage Project Knowledge
 
Project Cost Forecasting Techniques with EAC, ETC, VAC, TCPI
Project Cost Forecasting Techniques with EAC, ETC, VAC, TCPIProject Cost Forecasting Techniques with EAC, ETC, VAC, TCPI
Project Cost Forecasting Techniques with EAC, ETC, VAC, TCPI
 
Scenario - Project Management Processes | 2 of 2
Scenario - Project Management Processes | 2 of 2Scenario - Project Management Processes | 2 of 2
Scenario - Project Management Processes | 2 of 2
 
Scenario - Project Management Processes | 1 of 2
Scenario - Project Management Processes | 1 of 2Scenario - Project Management Processes | 1 of 2
Scenario - Project Management Processes | 1 of 2
 
Scenario - The Project Management Environment
Scenario - The Project Management EnvironmentScenario - The Project Management Environment
Scenario - The Project Management Environment
 
Agile Scenarios - Delivering an Agile Environment
Agile Scenarios - Delivering an Agile EnvironmentAgile Scenarios - Delivering an Agile Environment
Agile Scenarios - Delivering an Agile Environment
 
Agile Scenarios - Core Practices
Agile Scenarios - Core PracticesAgile Scenarios - Core Practices
Agile Scenarios - Core Practices
 
Agile Core Practices - Rolling Wave Planning
Agile Core Practices - Rolling Wave PlanningAgile Core Practices - Rolling Wave Planning
Agile Core Practices - Rolling Wave Planning
 
6.0 Auxiliary Agile and Lean Frameworks
6.0 Auxiliary Agile and Lean Frameworks6.0 Auxiliary Agile and Lean Frameworks
6.0 Auxiliary Agile and Lean Frameworks
 
5.0 Core Agile and Lean Frameworks
5.0 Core Agile and Lean Frameworks5.0 Core Agile and Lean Frameworks
5.0 Core Agile and Lean Frameworks
 
7.0 Delivering in an Agile Environment
7.0 Delivering in an Agile Environment7.0 Delivering in an Agile Environment
7.0 Delivering in an Agile Environment
 
4.0 The Agile Core Practices
4.0 The Agile Core Practices4.0 The Agile Core Practices
4.0 The Agile Core Practices
 
3.0 The Agile Manifesto and Clarifying principles
3.0 The Agile Manifesto and Clarifying principles3.0 The Agile Manifesto and Clarifying principles
3.0 The Agile Manifesto and Clarifying principles
 
2.0 The Differences Between Agile and Waterfall, Incremental, Iterative and H...
2.0 The Differences Between Agile and Waterfall, Incremental, Iterative and H...2.0 The Differences Between Agile and Waterfall, Incremental, Iterative and H...
2.0 The Differences Between Agile and Waterfall, Incremental, Iterative and H...
 
7.4 Control Costs
7.4 Control Costs7.4 Control Costs
7.4 Control Costs
 
7.3 Determine Budget
7.3 Determine Budget7.3 Determine Budget
7.3 Determine Budget
 

Recently uploaded

ENG 5 Q4 WEEk 1 DAY 1 Restate sentences heard in one’s own words. Use appropr...
ENG 5 Q4 WEEk 1 DAY 1 Restate sentences heard in one’s own words. Use appropr...ENG 5 Q4 WEEk 1 DAY 1 Restate sentences heard in one’s own words. Use appropr...
ENG 5 Q4 WEEk 1 DAY 1 Restate sentences heard in one’s own words. Use appropr...JojoEDelaCruz
 
Activity 2-unit 2-update 2024. English translation
Activity 2-unit 2-update 2024. English translationActivity 2-unit 2-update 2024. English translation
Activity 2-unit 2-update 2024. English translationRosabel UA
 
AUDIENCE THEORY -CULTIVATION THEORY - GERBNER.pptx
AUDIENCE THEORY -CULTIVATION THEORY -  GERBNER.pptxAUDIENCE THEORY -CULTIVATION THEORY -  GERBNER.pptx
AUDIENCE THEORY -CULTIVATION THEORY - GERBNER.pptxiammrhaywood
 
GRADE 4 - SUMMATIVE TEST QUARTER 4 ALL SUBJECTS
GRADE 4 - SUMMATIVE TEST QUARTER 4 ALL SUBJECTSGRADE 4 - SUMMATIVE TEST QUARTER 4 ALL SUBJECTS
GRADE 4 - SUMMATIVE TEST QUARTER 4 ALL SUBJECTSJoshuaGantuangco2
 
Karra SKD Conference Presentation Revised.pptx
Karra SKD Conference Presentation Revised.pptxKarra SKD Conference Presentation Revised.pptx
Karra SKD Conference Presentation Revised.pptxAshokKarra1
 
Active Learning Strategies (in short ALS).pdf
Active Learning Strategies (in short ALS).pdfActive Learning Strategies (in short ALS).pdf
Active Learning Strategies (in short ALS).pdfPatidar M
 
Daily Lesson Plan in Mathematics Quarter 4
Daily Lesson Plan in Mathematics Quarter 4Daily Lesson Plan in Mathematics Quarter 4
Daily Lesson Plan in Mathematics Quarter 4JOYLYNSAMANIEGO
 
Transaction Management in Database Management System
Transaction Management in Database Management SystemTransaction Management in Database Management System
Transaction Management in Database Management SystemChristalin Nelson
 
4.16.24 21st Century Movements for Black Lives.pptx
4.16.24 21st Century Movements for Black Lives.pptx4.16.24 21st Century Movements for Black Lives.pptx
4.16.24 21st Century Movements for Black Lives.pptxmary850239
 
How to Add Barcode on PDF Report in Odoo 17
How to Add Barcode on PDF Report in Odoo 17How to Add Barcode on PDF Report in Odoo 17
How to Add Barcode on PDF Report in Odoo 17Celine George
 
MULTIDISCIPLINRY NATURE OF THE ENVIRONMENTAL STUDIES.pptx
MULTIDISCIPLINRY NATURE OF THE ENVIRONMENTAL STUDIES.pptxMULTIDISCIPLINRY NATURE OF THE ENVIRONMENTAL STUDIES.pptx
MULTIDISCIPLINRY NATURE OF THE ENVIRONMENTAL STUDIES.pptxAnupkumar Sharma
 
Grade 9 Quarter 4 Dll Grade 9 Quarter 4 DLL.pdf
Grade 9 Quarter 4 Dll Grade 9 Quarter 4 DLL.pdfGrade 9 Quarter 4 Dll Grade 9 Quarter 4 DLL.pdf
Grade 9 Quarter 4 Dll Grade 9 Quarter 4 DLL.pdfJemuel Francisco
 
Field Attribute Index Feature in Odoo 17
Field Attribute Index Feature in Odoo 17Field Attribute Index Feature in Odoo 17
Field Attribute Index Feature in Odoo 17Celine George
 
Difference Between Search & Browse Methods in Odoo 17
Difference Between Search & Browse Methods in Odoo 17Difference Between Search & Browse Methods in Odoo 17
Difference Between Search & Browse Methods in Odoo 17Celine George
 
THEORIES OF ORGANIZATION-PUBLIC ADMINISTRATION
THEORIES OF ORGANIZATION-PUBLIC ADMINISTRATIONTHEORIES OF ORGANIZATION-PUBLIC ADMINISTRATION
THEORIES OF ORGANIZATION-PUBLIC ADMINISTRATIONHumphrey A Beña
 
Visit to a blind student's school🧑‍🦯🧑‍🦯(community medicine)
Visit to a blind student's school🧑‍🦯🧑‍🦯(community medicine)Visit to a blind student's school🧑‍🦯🧑‍🦯(community medicine)
Visit to a blind student's school🧑‍🦯🧑‍🦯(community medicine)lakshayb543
 

Recently uploaded (20)

FINALS_OF_LEFT_ON_C'N_EL_DORADO_2024.pptx
FINALS_OF_LEFT_ON_C'N_EL_DORADO_2024.pptxFINALS_OF_LEFT_ON_C'N_EL_DORADO_2024.pptx
FINALS_OF_LEFT_ON_C'N_EL_DORADO_2024.pptx
 
ENG 5 Q4 WEEk 1 DAY 1 Restate sentences heard in one’s own words. Use appropr...
ENG 5 Q4 WEEk 1 DAY 1 Restate sentences heard in one’s own words. Use appropr...ENG 5 Q4 WEEk 1 DAY 1 Restate sentences heard in one’s own words. Use appropr...
ENG 5 Q4 WEEk 1 DAY 1 Restate sentences heard in one’s own words. Use appropr...
 
Activity 2-unit 2-update 2024. English translation
Activity 2-unit 2-update 2024. English translationActivity 2-unit 2-update 2024. English translation
Activity 2-unit 2-update 2024. English translation
 
YOUVE_GOT_EMAIL_PRELIMS_EL_DORADO_2024.pptx
YOUVE_GOT_EMAIL_PRELIMS_EL_DORADO_2024.pptxYOUVE_GOT_EMAIL_PRELIMS_EL_DORADO_2024.pptx
YOUVE_GOT_EMAIL_PRELIMS_EL_DORADO_2024.pptx
 
Raw materials used in Herbal Cosmetics.pptx
Raw materials used in Herbal Cosmetics.pptxRaw materials used in Herbal Cosmetics.pptx
Raw materials used in Herbal Cosmetics.pptx
 
LEFT_ON_C'N_ PRELIMS_EL_DORADO_2024.pptx
LEFT_ON_C'N_ PRELIMS_EL_DORADO_2024.pptxLEFT_ON_C'N_ PRELIMS_EL_DORADO_2024.pptx
LEFT_ON_C'N_ PRELIMS_EL_DORADO_2024.pptx
 
AUDIENCE THEORY -CULTIVATION THEORY - GERBNER.pptx
AUDIENCE THEORY -CULTIVATION THEORY -  GERBNER.pptxAUDIENCE THEORY -CULTIVATION THEORY -  GERBNER.pptx
AUDIENCE THEORY -CULTIVATION THEORY - GERBNER.pptx
 
GRADE 4 - SUMMATIVE TEST QUARTER 4 ALL SUBJECTS
GRADE 4 - SUMMATIVE TEST QUARTER 4 ALL SUBJECTSGRADE 4 - SUMMATIVE TEST QUARTER 4 ALL SUBJECTS
GRADE 4 - SUMMATIVE TEST QUARTER 4 ALL SUBJECTS
 
Karra SKD Conference Presentation Revised.pptx
Karra SKD Conference Presentation Revised.pptxKarra SKD Conference Presentation Revised.pptx
Karra SKD Conference Presentation Revised.pptx
 
Active Learning Strategies (in short ALS).pdf
Active Learning Strategies (in short ALS).pdfActive Learning Strategies (in short ALS).pdf
Active Learning Strategies (in short ALS).pdf
 
Daily Lesson Plan in Mathematics Quarter 4
Daily Lesson Plan in Mathematics Quarter 4Daily Lesson Plan in Mathematics Quarter 4
Daily Lesson Plan in Mathematics Quarter 4
 
Transaction Management in Database Management System
Transaction Management in Database Management SystemTransaction Management in Database Management System
Transaction Management in Database Management System
 
4.16.24 21st Century Movements for Black Lives.pptx
4.16.24 21st Century Movements for Black Lives.pptx4.16.24 21st Century Movements for Black Lives.pptx
4.16.24 21st Century Movements for Black Lives.pptx
 
How to Add Barcode on PDF Report in Odoo 17
How to Add Barcode on PDF Report in Odoo 17How to Add Barcode on PDF Report in Odoo 17
How to Add Barcode on PDF Report in Odoo 17
 
MULTIDISCIPLINRY NATURE OF THE ENVIRONMENTAL STUDIES.pptx
MULTIDISCIPLINRY NATURE OF THE ENVIRONMENTAL STUDIES.pptxMULTIDISCIPLINRY NATURE OF THE ENVIRONMENTAL STUDIES.pptx
MULTIDISCIPLINRY NATURE OF THE ENVIRONMENTAL STUDIES.pptx
 
Grade 9 Quarter 4 Dll Grade 9 Quarter 4 DLL.pdf
Grade 9 Quarter 4 Dll Grade 9 Quarter 4 DLL.pdfGrade 9 Quarter 4 Dll Grade 9 Quarter 4 DLL.pdf
Grade 9 Quarter 4 Dll Grade 9 Quarter 4 DLL.pdf
 
Field Attribute Index Feature in Odoo 17
Field Attribute Index Feature in Odoo 17Field Attribute Index Feature in Odoo 17
Field Attribute Index Feature in Odoo 17
 
Difference Between Search & Browse Methods in Odoo 17
Difference Between Search & Browse Methods in Odoo 17Difference Between Search & Browse Methods in Odoo 17
Difference Between Search & Browse Methods in Odoo 17
 
THEORIES OF ORGANIZATION-PUBLIC ADMINISTRATION
THEORIES OF ORGANIZATION-PUBLIC ADMINISTRATIONTHEORIES OF ORGANIZATION-PUBLIC ADMINISTRATION
THEORIES OF ORGANIZATION-PUBLIC ADMINISTRATION
 
Visit to a blind student's school🧑‍🦯🧑‍🦯(community medicine)
Visit to a blind student's school🧑‍🦯🧑‍🦯(community medicine)Visit to a blind student's school🧑‍🦯🧑‍🦯(community medicine)
Visit to a blind student's school🧑‍🦯🧑‍🦯(community medicine)
 

12.2 Conduct Procurements

  • 2. Conduct Procurements Coincides with PMBOK 12.2 Process Group and Knowledge Area Mapping Knowledge Areas Initiating Planning Process Group Executing Process Group Monitoring and Controlling Process Group Closing Process Group 4. Project Integration Management 4.1 Develop Project Charter 4.2 Develop Project Management Plan 4.3 Direct and Manage Project Work 4.4 Manage Project Knowledge 4.5 Monitor and Control Project Work 4.6 Perform Integrated Change Control 4.7 Close Project or Phase 5. Project Scope Management 5.1 Plan Scope Management 5.2 Collect Requirements 5.3 Define Scope 5.4 Create WBS 5.5 Validate Scope 5.6 Control Scope 6. Project Schedule Management 6.1 Plan Schedule Management 6.2 Define Activities 6.3 Sequence Activities 6.4 Estimate Activity Durations 6.5 Develop Schedule 6.6 Control Schedule 7. Project Cost Management 7.1 Plan Cost Management 7.2 Estimate Costs 7.3 Determine Budget 7.4 Control Costs 8. Project Quality Management 8.1 Plan Quality Management 8.2 Manage Quality 8.3 Control Quality 9. Project Resource Management 9.1 Plan Resource Management 9.2 Estimate Activity Resources 9.3 Acquire Resources 9.4 Develop Team 9.5 Manage Team 9.6 Control Resources 10. Project Communications Management 10.1 Plan Communications Management 10.2 Manage Communications 10.3 Monitor Communications 11. Project Risk Management 11.1 Plan Risk Management 11.2 Identify Risks 11.3 Perform Qualitative Risk Analysis 11.4 Perform Quantitative Risk Analysis 11.5 Plan Risk Responses 11.6 Implement Risk Responses 11.7 Monitor Risks 12. Project Procurement Management 12.1 Plan Procurement Management 12.2 Conduct Procurements 12.3 Control Procurements 13. Project Stakeholder Management 13.1 Identify Stakeholders 13.2 Plan Stakeholder Engagement 13.3 Manage Stakeholder Engagement 13.4 Monitor Stakeholder Engagement
  • 3. What is it? Conduct Procurements is the process of obtaining seller responses, selecting a seller, and awarding a contract. Why? The key benefit of this process is that it selects a qualified seller and implements the legal agreement for delivery. The end results of the process are the established agreements including formal contracts. Conduct Procurements Coincides with PMBOK 12.2
  • 4. Inputs Tools & Techniques Outputs 1. Project management plan • Scope management plan • Requirements management plan • Communications management plan • Risk management plan • Procurement management plan • Configuration management plan • Cost baseline 2. Project documents • Lessons learned register • Project schedule • Requirements • documentation • Risk register • Stakeholder register 3. Procurement documentation 4. Seller proposals 5. Enterprise environmental factors 6. Organizational process assets 1. Expert judgment 2. Advertising 3. Bidder conferences 4. Data analysis • Proposal evaluation 5. Interpersonal and team skills • Negotiation 1. Selected sellers 2. Agreements 3. Change requests 4. Project management plan updates • Requirements management plan • Quality management plan • Communications management plan • Risk management plan • Procurement management plan • Scope baseline • Schedule baseline • Cost baseline 5. Project documents updates • Lessons learned register • Requirements documentation • Requirements traceability matrix • Resource calendars • Risk register • Stakeholder register 6. Organizational process assets updates Inputs, Tools & Techniques, Outputs Conduct Procurements Coincides with PMBOK 12.2
  • 5. 12.2 Conduct Procurements Project Management Plan • Lessons learned register • Project schedule • Requirements • documentation • Risk register • Stakeholder register • Sellers proposals Project Documents • Lessons learned register • Requirements documentation • Requirements traceability matrix • Resource calendars • Risk register • Stakeholder register • Scope management plan • Requirements management plan • Communications management plan • Risk management plan • Procurement management plan • Configuration management plan • Cost baseline Project Documents • Change Requests • Requirements management plan • Quality management plan • Communications management plan • Risk management plan • Procurement management plan • Scope baseline • Schedule baseline • Cost baseline Project Management Plan Enterprise/Orga nization • Organizational process assets • Selected Sellers• Enterprise organizational factors • Organizational process assets Conduct Procurements Coincides with PMBOK 12.2 Enterprise/Orga nization Procurement Documentation Sellers 12.3 Control Procurements 4.6 Perform Integrated Change Control 4.1 Develop Project Charter 4.5 Monitor and Control Project Work 4.7 Close Project or Phase 6.5 Develop Schedule 7.3 Determine Budget 9.6 Control Resources 12.3 Control Procurements 13.1 Identify Stakeholders 13.1 Identify Stakeholders • Agreements
  • 6. Conduct Procurements - Inputs Coincides with PMBOK 12.2 Project Management Plan Project management plan components include: • Scope management plan • Requirements management plan • Communications management plan • Risk management plan • Procurement management plan • Configuration management plan • Cost baseline
  • 7. Project Documents Project documents that should be considered as inputs for this process include: • Lessons learned register • Project schedule • Requirements documentation • Risk register • Stakeholder register Conduct Procurements - Inputs Coincides with PMBOK 12.2
  • 8. Procurement Documentation Procurement documentation provides a written record used in reaching the legal agreement, and may include older documents predating the current project. Procurement documentation can include: • Bid Documents • Procurement statement of work • Independent cost estimates • Source selection criteria Conduct Procurements - Inputs Coincides with PMBOK 12.2
  • 9. Seller Proposals • Seller proposals, prepared in response to a procurement document package, form the basic information that will be used by an evaluation body to select one or more successful bidders (sellers). • The evaluation body reviews each submitted proposal according to the source selection criteria and selects the seller that can best satisfy the buying organization’s requirements. Conduct Procurements - Inputs Coincides with PMBOK 12.2
  • 10. Enterprise Environmental Factors The enterprise environmental factors that can influence the Conduct Procurements Process include: • Local laws and regulations regarding procurements • Local laws and regulations ensuring that the major procurements involve local sellers • External economic environment constraining procurement processes • Marketplace conditions • Information on relevant past experience with sellers, both good and bad • Prior agreements already in place • Contract management systems Conduct Procurements - Inputs Coincides with PMBOK 12.2
  • 11. Organizational Process Assets The organizational process assets that can influence the Conduct Procurements process include but are not limited to: • List of preferred sellers that have been prequalified • Organizational policies that influence the selection of a seller • Specific organizational templates or guidelines that will determine the way agreements are drafted and built • Financial policies and procedures regarding invoicing and payment processes. Conduct Procurements - Inputs Coincides with PMBOK 12.2
  • 12. Expert Judgement Expertise should be considered from individuals or groups with specialized knowledge or training in the following topics: • Proposal evaluation • Technical or subject matter • Relevant functional areas such as finance, engineering, design, development, supply chain management, etc. • Industry regulatory environment • Laws, regulations, and compliance requirements • Negotiation Conduct Procurements – Tools & Techniques Coincides with PMBOK 12.2
  • 13. Advertising Advertising is communicating with users or potential users of a product, service, or result. Existing lists of potential sellers often can be expanded by placing advertisements in general circulation publications such as selected newspapers or in specialty trade publications. Most government jurisdictions require public advertising or online posting of pending government contracts. Conduct Procurements – Tools & Techniques Coincides with PMBOK 12.2
  • 14. Bidder Conferences Bidder conferences (also called contractor conferences, vendor conferences, and pre-bid conferences) are meetings between the buyer and prospective sellers prior to proposal submittal. They are used to ensure that all prospective bidders have a clear and common understanding of the procurement and no bidders receive preferential treatment. Conduct Procurements – Tools & Techniques Coincides with PMBOK 12.2
  • 15. Data Analysis A data analysis technique that can be used for this process includes but is not limited to proposal evaluation. Proposals are evaluated to ensure they are complete and respond in full to the bid documents, procurement statement of work, source selection criteria, and any other documents that went out in the bid package. Conduct Procurements – Tools & Techniques Coincides with PMBOK 12.2
  • 16. Interpersonal and Team Skills • Interpersonal and team skills that can be used for this process include negotiation. • Negotiation is a discussion aimed at reaching an agreement. Procurement negotiation clarifies the structure, rights, and obligations of the parties and other terms of the purchases so that mutual agreement can be reached prior to signing the contract. • The negotiation should be led by a member of the procurement team that has the authority to sign contracts. Conduct Procurements – Tools & Techniques Coincides with PMBOK 12.2
  • 17. Selected Sellers • The selected sellers are those who have been judged to be in a competitive range based on the outcome of the proposal or bid evaluation. • Final approval of complex, high-value, high-risk procurements will generally require organizational senior management approval prior to award. Conduct Procurements – Outputs Coincides with PMBOK 12.2
  • 18. Agreements A contract is a mutually binding agreement that obligates the seller to provide the specified products, services, or results; obligates the buyer to compensate the seller; and represents a legal relationship that is subject to remedy in the courts. The major components in an agreement document may include: Conduct Procurements – Outputs Coincides with PMBOK 12.2 • Incentives and penalties • Insurance and performance bonds • Subordinate subcontractor approvals • General terms and conditions • Change request handling • Termination clause and alternative dispute resolution mechanisms • Procurement statement of work or major deliverables • Schedule, milestones, or date by which a schedule is required • Performance reporting • Pricing and payment terms • Inspection, quality, and acceptance criteria • Warranty and future product support
  • 19. Change Requests Change requests to the project management plan, its subsidiary plans, and other components are processed for review and disposition through the Perform Integrated Change Control process Conduct Procurements – Outputs Coincides with PMBOK 12.2
  • 20. Project Management Plan Updates Any change to the project management plan goes through the organization’s change control process via a change request. Components of the project management plan that may require a change request for the project management plan include: • Requirements management plan • Quality management plan • Communications management plan • Risk management plan • Procurement management plan • Scope baseline • Schedule baseline • Cost baseline Conduct Procurements – Outputs Coincides with PMBOK 12.2
  • 21. Project Document Updates Project documents that may be updated as a result of carrying out this process include: • Lessons learned register • Requirements documentation • Requirements traceability matrix • Resource calendars • Risk register • Stakeholder register Conduct Procurements – Outputs Coincides with PMBOK 12.2
  • 22. Organizational Process Assets Updates Elements of the organizational process assets that can be updated as a result of the Conduct Procurements process can include: • Listings of prospective and prequalified sellers • Information on relevant experience with sellers, both good and bad. Conduct Procurements – Outputs Coincides with PMBOK 12.2

Editor's Notes

  1. This process is performed periodically throughout the project as needed.
  2. Scope management plan - The scope management plan describes how the overall scope of work will be managed, including the scope performed by sellers. Requirements management plan - The requirements management plan describes how requirements will be analyzed, documented, and managed. The requirements management plan may include how sellers will manage the requirements they are under agreement to satisfy. Communications management plan - The communications management plan describes how communications between buyers and sellers will be conducted. Risk management plan - The risk management plan is a component of the project management plan and describes how risk management activities will be structured and performed for the project. Procurement management plan - The procurement management plan contains the activities to be undertaken during the Conduct Procurements process. Configuration management plan - The configuration management plan defines those items that are configurable, those items that require formal change control, and the process for controlling changes to such items. It includes formats and processes for how sellers will provide configuration management in a way that is consistent with the buyer’s approach. Cost baseline - The cost baseline includes the budget for the procurement as well as costs associated with managing the procurement process and sellers.
  3. Lessons learned register - Lessons learned earlier in the project with regard to conducting procurements can be applied to later phases in the project to improve the efficiency of this process. Project schedule - The project schedule identifies the start and end dates of project activities, including procurement activities. It also defines when contractor deliverables are due. Requirements documentation - Requirements documentation may include: Technical requirements the seller is required to satisfy, and Requirements with contractual and legal implications that may include health, safety, security, performance, environmental, insurance, intellectual property rights, equal employment opportunity, licenses, permits, and other nontechnical requirements. Risk register - Each approved seller comes with its own unique set of risks, depending on the seller’s organization, the duration of the contract, the external environment, the project delivery method, the type of contracting vehicle chosen, and the final agreed-upon price. Stakeholder register - This document contains all of the details about the identified stakeholders.
  4. Bid documents - Procurement documents include the RFI, RFP, RFQ, or other documents sent to sellers so they can develop a bid response. Procurement statement of work - The procurement statement of work (SOW) provides sellers with a clearly stated set of goals, requirements, and outcomes from which they can provide a quantifiable response. Independent cost estimates - Independent cost estimates are developed either internally or by using external resources and provide a reasonableness check against the proposals submitted by bidders. Source selection criteria - These criteria describe how bidder proposals will be evaluated, including evaluation criteria and weights.
  5. If the seller is going to submit a price proposal, good practice is to require that it be separate from the technical proposal.
  6. Final document language reflects all agreements reached. Negotiation concludes with a signed contract document or other formal agreement that can be executed by both buyer and seller. The project manager and other members of the project management team may be present during negotiation to provide assistance as needed.
  7. Requirements management plan - There may be changes to project requirements due to changes identified by sellers. Quality management plan - Sellers may offer alternative quality standards or alternative solutions that impact the quality approaches defined in the quality management plan. Communications management plan - As sellers are hired, the communications management plan is updated to incorporate their communications needs and approaches. Risk management plan - Each agreement and seller has its own set of risks that may require updates to the risk management plan. Specific risks are incorporated into the risk register. Procurement management plan - Updates may be required depending on the results of the contracting and negotiations processes. Scope baseline - The project WBS and deliverables documented in the scope baseline are considered when performing procurement activities. Any one or all of these may change during the procurement process. Schedule baseline - If there are delivery changes created by sellers that impact overall project schedule performance, the baseline schedule may need to be updated and approved to reflect the current expectations. Cost baseline - Contractor and materials prices can change frequently during the delivery of a project. These changes can occur because of fluctuating materials and labor prices created by the external economic environment and need to be incorporated into the cost baseline.
  8. Lessons learned register - The lessons learned register is updated with information on challenges encountered while conducting procurements and how they could have been avoided as well as approaches that worked well. Requirements documentation - Requirements documentation may include: Technical requirements that the seller is required to satisfy, and Requirements with contractual and legal implications that may include health, safety, security, performance, environmental, insurance, intellectual property rights, equal employment opportunity, licenses, permits, and other nontechnical requirements. Requirements traceability matrix - As sellers are incorporated into the project’s plan, the requirements register and the traceability matrix may change depending on the capabilities of the specific seller. Resource calendars - Schedule resource calendars may need to be updated depending on the availabilities of the sellers. Risk register - Each approved seller comes with its own unique set of risks, depending on the seller’s organization, the duration of the contract, the external environment, the project delivery method, the type of contracting vehicle chosen, and the final agreed-upon price. Stakeholder register. - This document contains all the details about the identified stakeholders. The stakeholder register is updated as agreements are made with specific sellers.