SlideShare a Scribd company logo
15th
June to 18th
June 2015
Power House
4 PowerHouse
Introduction: A substation is a part of an electrical generation, transmission and
distribution system. Substations transform voltage from high to low
or reverse or any of several other important functions. Electric power may flow
through several substations between generating plant and consumer and its voltage
may change in several steps.
A substation has a step up transformer which increase the voltage while decreasing
the current while a step down transformer decrease the voltage while increasing the
current for domestic and commercial distribution .The word substation comes from
the days before the distribution system became a grid. The first substation were
connected to only one power station, where the generators were housed and were
subsidiaries of that power station.
6 KV. Distribution System in Sealdah Area
Sealdah Power House LT Distribution system
5 PowerHouse
In SEALDAH POWERHOUSEthe control is divided into two sections.
i. The Low Tension section
ii. The High Tension section
 The main components of the Power House :
 Switch Gear
 Transformers (300KVA. & 500 KVA.)
 Isolator
 Bus Bar
 Bus Coupler
 Circuit breakers (Air circuit breakers on L.T. side & vacuumcircuit breakers on
H.T. side)
 Relays (Earth Fault Relay & Over CurrentRelay)
 Hooter / Alarm
The components are described in brief fromthe power housebellow.
 Switch Gear: It is a
combination of electrical
disconnect switches, fuses
and circuit breakers used to
control, protect and isolate
electrical equipment.
This switchgear is
connected to the incoming
supply from CESC. There
are two connections
available (one kept for
emergency). Incoming Switch Gear
The connections are coupled together by a Bus coupler and then sent to the
Transformers for further step down of voltage, as required. If any fault occurs
upstream (i.e., in supply side), this switchgear immediately disconnects from
6 PowerHouse
the supply thereby preventing further spreading of fault and hence keeping
alive the essential railway operations.
 Step down transformer: A transformer is a device that transfers electric
energy from one circuit to another circuit through
inductively coupled conductors---the transformers coil---a varying current in
the first or primary winding creates a varying magnetic flux in the transformer
core and thus a varying magnetic field through the secondary winding. This
varying magnetic field induces a varying electromotive force (EMF) or voltage
in the secondary winding. This effect is called mutual induction.
If a load is connected to the secondary, an electric current will flow in the
secondary winding and electrical energy will be transferred from the primary
circuit through the transformer to the load. In an ideal transformer ,the
induced voltage (Vs) in the secondary winding is proportion to primary voltage
(Vp) and is given by the ratio of the number of turns in the secondary(Ns) to
the number of turns in primary(Np) as follows,
Vs/ Vp = Ns/ Np
By appropriate selection of the ratio of turns, a transformer thus allows an
alternating current voltage to be “stepped up” by making Ns greater than Np
or “stepped down” by making Ns less than Np.
In the vast majority of transformers, the winding are coils wound around a
ferromagnetic core, air-core transformers being a notable exception.
In SEALDAH POWER HOUSE two transformers are used, two 300 KVA and
another 500 KVA.
Two 300 KVA transformers are connected in parallel.
A spare 500 KVA transformer is kept for backup.
7 PowerHouse
300 KVA. Transformer in Sealdah Power House
500 KVA. Transformer in Sealdah Power House
8 PowerHouse
 500 KVA. Transformer ratings :
 Isolator: In electrical engineering, an isolator switch is used to make sure that
an electrical circuit can be completely de-energised for serviceor maintenance.
Such switches are often found in electrical distribution and industrial
applications where machinery must have its source of driving power removed
for adjustment or repair. High voltage isolation switches are used in electrical
substations to allow isolation of apparatus such as circuit breakers transformer
and transmission lines for maintenance.
C Serial No. 1581/D7-08
Maker AUTOMATIC ELECTRIC GROUP
KVA. 500 KVA.
Voltage At No Load H.V: 6000 V. ; L.V: 415 V.
Amperes H.V: 48.11 A. ; L.V: 695.62 A.
Phases H.V: 3 ; L.V: 3
Type of cooling Oil Natural Cooling
Frequency 50 C/S
Impedance voltage 4.37 %
Vector Group Ref. Dy11
Core and Wedge 1140 kg.
Weight of oil 451 kg.
Total weight 2105 kg.
Oil amount 530 liters
Maximum temperature rise in oil 45 degree
9 PowerHouse
 Bus Bar: In electrical power distribution, a bus
bar is a metallic strip (or bus) that conducts
electricity within a distribution board or
substation.
Its main purpose is to conduct a substancial
current of electricity and not to function as a
structural member. It is a wide and thick strip of
metal generally copper wich carry high voltage
power. The bus bars are used instead oc wire to
reduce the transmission losses.
Bus Bar in the Control Panel
 Bus coupler: Bus coupler provides electrical
isolation bus by employing coupling
transformers and fault isolation resistors. The
Bus couplers contain two isolation resistors (one
per wire) and an isolation transformer (with a
ratio one to the square root of two). The
purpose of bus coupler is to prevent a short on a
single stub from shorting the main data bus. The
buses of two different voltage levels cannot be
connected in series. So, bus coupler is used to
join the buses of different voltage level.
Bus Coupler
 Protective Relays: A relay is fault sensing device. Many relay use an
electromagnet to operate a switching mechanism mechanically, but other
operating principles are also used. Relays are used where it is necessary to
control a circuit by a low-power signal (with complete electrical isolation
between control and controlled circuit) or where several circuits must be
controlled by one.
10 PowerHouse
The first relays were used in long distance telegraph circuits, repeating the
signal coming from one circuit and re-transmitting it to another. Relays were
extensively used in telephone exchanges and early computers to perform
logical operations.
A type of relay that can handle the high
power required to directly control an
electric motor is called a conductor. Solid-
state relays control power circuits with no
moving parts, instead using a
semiconductor device to perform
switching. Relays with calibrated operating
characteristics and sometimes multiple
operating coils are used to protect
electrical circuits fromoverload or faults; in
modern electric power systems these
functions are performed by digital
instruments still called ‘Protective Relays’.
Protective Relay
The Relays used in Sealdah Power Houseare of mainly two types,
 Over CurrentRelay
 Earth Fault Relay
 The Relay specification (Based on one sample on HT. panel):
Over Current Relay Earth Fault Relay
Model No. CDG31EG001SBCH Model No. CDG31EG001SBCH
Serial no. - 130954160621011 Serial no. - 130954160621011
C.T. SEC : 5 AMPS;2.5-10 Amps. C.T. SEC : 5 AMPS;1-4 Amps.
Frequency : 50 Hz. Frequency : 50 Hz.
11 PowerHouse
 Oil Circuit Breaker (O.C.B.): The oil in OCB’s serves two purposes. It
insulates between the phases and the ground, and it provides the medium for
the extinguishing of arc. When electric arc is drawn under oil, the arc vaporises
the oil and creates a large bubble that surrounds the arc. The gas inside the
bubble is around 80%hydrogen, which impairs ionisation. The decomposition
of oil into gas requires energy that comes from the heat generated by the arc.
The oil surrounding the bubble conducts the heat away from the arc and thus
also contributes to deionisation of the arc.
Oil Circuit Breaker
 The Oil Circuit Breaker specification (Based on one sample on the LT.
panel of 1 no. PF. Substation):
Sl. No. 2K2132
Type HN2T
Normal current 400 A.
Service voltage 415 V.
Design frequency 50 Hz.
Breaking capacity 25 MVA.
Trip coil rating 5 A.
Calibration 100/200 %
12 PowerHouse
C.T. ratio 800/5
 Air Circuit Breaker (A.C.B.): The working principle of this breaker is rather
different from those in any other types of circuit breakers. The main aim of all
kind of circuit breaker is to prevent the reestablishment of arcing after current
zero by creating a situation where in the contact gap will withstand the system
recovery voltage. The air circuit breaker does the same but in different
manner. For interrupting arc it creates an arc voltage in excess of the supply
voltage. Arc voltage is defined as the minimum voltage required maintaining
the arc. This circuit breaker increases the arc voltage by mainly three different
ways,
i. It may increase the arc
voltage by cooling the arc
plasma. As the
temperature of arc plasma
is decreased, the mobility
of the particle in arc
plasma is reduced, hence
more voltage gradient is
required to maintain the
arc.
ii. It may increase the arc
voltage by lengthening the
arc path. As the length of
arc path is increased, the
resistance of the path is
increased, and hence to
maintain the same arc
current more voltage is
required to be applied
across the arc path. That
means arc voltage is
increased.
iii. Splitting up the arc into a
number of series arcs also
increases the arc voltage. Various internal parts of an Air Circuit Breaker
13 PowerHouse
 The Air Circuit Breaker specification (Based on one sample on LT.
panel):
 Rated Characteristics:
 Substation of PF. No. 1: The 6 KV. high voltage is transmitted to the 1 no.
platform of Sealdah rail station from the power house and stepped down to
415 v. (Phase to phase) by a 300 KVA. transformer situated in the substation.
The 415 V. supply is then distributed to the entire Sealdah station, all the
platforms, the offices, ticket counters, train boards, digital clock,
announcement speakers and all of the lights and fans of Sealdah Main and
South both sections are run by this supply.
 The Diesel Engine-Alternator arrangement situated at substation of PF.
No. 1:
There is a diesel engine coupled with a alternator in the 1 no. platform
substation for delivering power when main power is not available means at the
Maker PULSER
Frame LH800 DM1T3P
Sl. No. Y606183
IEC-947-2 IS:13947 (PART-2)
Utilization category 8
In 400A.
ITH @40 degree C. 800A.
ICS & ICU 50 Ka.
ICW 50 Ka., 1sec.
Power Factor 0.25
Ui=1000VUe=415V Frequency : 50/60HZ
U/V 40 AC
14 PowerHouse
time of load shading. This alternator produce 3 phase 415 V and make run the
essential systems of Sealdah Station at the time of load shading.
The Diesel Engine and Alternator arrangement at PF. No. 1 Substation
15 PowerHouse

More Related Content

What's hot

PPt on 220 kV substation
PPt on 220 kV substationPPt on 220 kV substation
PPt on 220 kV substationIshank Ranjan
 
Substations
SubstationsSubstations
Substations
itfakash
 
400/220 kV SCADA controlled gis based TRANSMISSION SUBSTATION
400/220 kV SCADA controlled gis based TRANSMISSION SUBSTATION400/220 kV SCADA controlled gis based TRANSMISSION SUBSTATION
400/220 kV SCADA controlled gis based TRANSMISSION SUBSTATION
Power System Operation
 
33 kv substation vt report
33 kv substation vt report33 kv substation vt report
33 kv substation vt report
k,l polytechnic roorkee
 
220 kv Sub-station Summer Training ppt
220 kv Sub-station Summer Training ppt220 kv Sub-station Summer Training ppt
220 kv Sub-station Summer Training ppt
Shubham Patel
 
Impacts of Distributed Generation on Power Quality
Impacts of Distributed Generation on Power QualityImpacts of Distributed Generation on Power Quality
Impacts of Distributed Generation on Power Quality
Parth Patel
 
DISTRIBUTION SYSTEM OPERATION AND CONTROL
DISTRIBUTION SYSTEM OPERATION AND CONTROLDISTRIBUTION SYSTEM OPERATION AND CONTROL
DISTRIBUTION SYSTEM OPERATION AND CONTROL
yohannes feleke
 
132 33kv substation documentation
132 33kv substation documentation132 33kv substation documentation
132 33kv substation documentation
Rajashekar Gurrala
 
Electrical substations: 132 KV
Electrical substations: 132 KV Electrical substations: 132 KV
Electrical substations: 132 KV
Girish Gupta
 
Report on 220kv substation at Jassure
Report on 220kv substation at JassureReport on 220kv substation at Jassure
Report on 220kv substation at Jassure
Shuvam Pathania
 
Electric substation
Electric substation Electric substation
Electric substation
ANNU KUMAR
 
Visit to 400 kV substation, Hadala
Visit to 400 kV substation, HadalaVisit to 400 kV substation, Hadala
Visit to 400 kV substation, Hadala
Nandan Desai
 
132 kv gss summer training report from CPWD vidhyadar nagar jaipur
132 kv gss summer training report from CPWD vidhyadar nagar jaipur132 kv gss summer training report from CPWD vidhyadar nagar jaipur
132 kv gss summer training report from CPWD vidhyadar nagar jaipur
ramesh kumawat
 
Electrical substation (grid station)
Electrical substation (grid station)Electrical substation (grid station)
Electrical substation (grid station)
Sufi Nouman Riaz
 
Unit1 8
Unit1 8Unit1 8
Unit1 8
budashow1
 
Stability test of transformer
Stability test of transformerStability test of transformer
Stability test of transformer
Santu Mondal
 
Transmission Line
Transmission LineTransmission Line
Transmission Line
PRITAM DEBNATH
 
Training at 132 kv substation
Training at 132 kv substation Training at 132 kv substation
Training at 132 kv substation
Tejveer Choudhary
 
Ppt of 132kv gss sitapura jaipur
Ppt of 132kv gss sitapura jaipurPpt of 132kv gss sitapura jaipur
Ppt of 132kv gss sitapura jaipur
kishankky
 
substation 220 kv
substation 220 kv substation 220 kv
substation 220 kv
student
 

What's hot (20)

PPt on 220 kV substation
PPt on 220 kV substationPPt on 220 kV substation
PPt on 220 kV substation
 
Substations
SubstationsSubstations
Substations
 
400/220 kV SCADA controlled gis based TRANSMISSION SUBSTATION
400/220 kV SCADA controlled gis based TRANSMISSION SUBSTATION400/220 kV SCADA controlled gis based TRANSMISSION SUBSTATION
400/220 kV SCADA controlled gis based TRANSMISSION SUBSTATION
 
33 kv substation vt report
33 kv substation vt report33 kv substation vt report
33 kv substation vt report
 
220 kv Sub-station Summer Training ppt
220 kv Sub-station Summer Training ppt220 kv Sub-station Summer Training ppt
220 kv Sub-station Summer Training ppt
 
Impacts of Distributed Generation on Power Quality
Impacts of Distributed Generation on Power QualityImpacts of Distributed Generation on Power Quality
Impacts of Distributed Generation on Power Quality
 
DISTRIBUTION SYSTEM OPERATION AND CONTROL
DISTRIBUTION SYSTEM OPERATION AND CONTROLDISTRIBUTION SYSTEM OPERATION AND CONTROL
DISTRIBUTION SYSTEM OPERATION AND CONTROL
 
132 33kv substation documentation
132 33kv substation documentation132 33kv substation documentation
132 33kv substation documentation
 
Electrical substations: 132 KV
Electrical substations: 132 KV Electrical substations: 132 KV
Electrical substations: 132 KV
 
Report on 220kv substation at Jassure
Report on 220kv substation at JassureReport on 220kv substation at Jassure
Report on 220kv substation at Jassure
 
Electric substation
Electric substation Electric substation
Electric substation
 
Visit to 400 kV substation, Hadala
Visit to 400 kV substation, HadalaVisit to 400 kV substation, Hadala
Visit to 400 kV substation, Hadala
 
132 kv gss summer training report from CPWD vidhyadar nagar jaipur
132 kv gss summer training report from CPWD vidhyadar nagar jaipur132 kv gss summer training report from CPWD vidhyadar nagar jaipur
132 kv gss summer training report from CPWD vidhyadar nagar jaipur
 
Electrical substation (grid station)
Electrical substation (grid station)Electrical substation (grid station)
Electrical substation (grid station)
 
Unit1 8
Unit1 8Unit1 8
Unit1 8
 
Stability test of transformer
Stability test of transformerStability test of transformer
Stability test of transformer
 
Transmission Line
Transmission LineTransmission Line
Transmission Line
 
Training at 132 kv substation
Training at 132 kv substation Training at 132 kv substation
Training at 132 kv substation
 
Ppt of 132kv gss sitapura jaipur
Ppt of 132kv gss sitapura jaipurPpt of 132kv gss sitapura jaipur
Ppt of 132kv gss sitapura jaipur
 
substation 220 kv
substation 220 kv substation 220 kv
substation 220 kv
 

Viewers also liked

Realtime Utility Engineers - SOQ
Realtime Utility Engineers - SOQRealtime Utility Engineers - SOQ
Realtime Utility Engineers - SOQ
Tim_Barnett
 
Week 1 electrical basics ii
Week 1 electrical basics iiWeek 1 electrical basics ii
Week 1 electrical basics ii
Craig Kielb
 
Powerhouse SD Install (11-01-2012)
Powerhouse SD Install (11-01-2012)Powerhouse SD Install (11-01-2012)
Powerhouse SD Install (11-01-2012)Anthony Protasiuk
 
Understanding How Solar Power Works
Understanding How Solar Power WorksUnderstanding How Solar Power Works
Understanding How Solar Power Works
EnergyMaxOut
 
Powerhouse Presentation
Powerhouse PresentationPowerhouse Presentation
Powerhouse Presentationwacotao
 
4th yer ppt
4th yer  ppt4th yer  ppt
4th yer ppt
Yogesh Thakur
 
Photovoltaic Systems- Chpater 4
Photovoltaic Systems- Chpater 4Photovoltaic Systems- Chpater 4
Photovoltaic Systems- Chpater 4rvb1019
 
Electrical basics
Electrical basicsElectrical basics
Electrical basics
Ganesh Kumar
 
Basics of electrical engineering
Basics of electrical engineeringBasics of electrical engineering
Basics of electrical engineering
Nishkam Dhiman
 

Viewers also liked (11)

Realtime Utility Engineers - SOQ
Realtime Utility Engineers - SOQRealtime Utility Engineers - SOQ
Realtime Utility Engineers - SOQ
 
Week 1 electrical basics ii
Week 1 electrical basics iiWeek 1 electrical basics ii
Week 1 electrical basics ii
 
Powerhouse SD Install (11-01-2012)
Powerhouse SD Install (11-01-2012)Powerhouse SD Install (11-01-2012)
Powerhouse SD Install (11-01-2012)
 
Understanding How Solar Power Works
Understanding How Solar Power WorksUnderstanding How Solar Power Works
Understanding How Solar Power Works
 
Powerhouse Presentation
Powerhouse PresentationPowerhouse Presentation
Powerhouse Presentation
 
4th yer ppt
4th yer  ppt4th yer  ppt
4th yer ppt
 
Photovoltaic Systems- Chpater 4
Photovoltaic Systems- Chpater 4Photovoltaic Systems- Chpater 4
Photovoltaic Systems- Chpater 4
 
Dc Principal
Dc PrincipalDc Principal
Dc Principal
 
Electrical basics
Electrical basicsElectrical basics
Electrical basics
 
Basics of electrical engineering
Basics of electrical engineeringBasics of electrical engineering
Basics of electrical engineering
 
Solar Energy
Solar EnergySolar Energy
Solar Energy
 

Similar to Vocational Training Report ( Sealdah Power House)

Gss ppt by kanhaiya
Gss ppt  by kanhaiyaGss ppt  by kanhaiya
Gss ppt by kanhaiya
imkanhaiyalal
 
project report on plc based load sharing
project report on plc based load sharingproject report on plc based load sharing
project report on plc based load sharing
Vivek Arun
 
Sub station training
Sub station trainingSub station training
Sub station training
Durga Prasad, IES
 
Lab manual psd v sem experiment no 7
Lab manual psd v sem experiment no 7Lab manual psd v sem experiment no 7
Lab manual psd v sem experiment no 7Sachin Airan
 
"high tension generator", "high tension","tension generator", "generator", ...
"high tension generator",  "high tension","tension generator",  "generator", ..."high tension generator",  "high tension","tension generator",  "generator", ...
"high tension generator", "high tension","tension generator", "generator", ...Prem Murti
 
substation internship report
substation internship report substation internship report
substation internship report
Arun Thapa
 
Substation
SubstationSubstation
Indusrtrial training ppt (1).pptx
Indusrtrial training ppt (1).pptxIndusrtrial training ppt (1).pptx
Indusrtrial training ppt (1).pptx
SNEHAKANWAR1
 
Uttar pradesh power corporation limited
Uttar pradesh power corporation limitedUttar pradesh power corporation limited
Uttar pradesh power corporation limited
VSRAGHU
 
5 power house
5 power house5 power house
5 power house
Arighna Dalal
 
Design of substation
Design of substationDesign of substation
Design of substation
SayanSarkar55
 
grid sub-station training Report
grid sub-station training Report grid sub-station training Report
grid sub-station training Report
ravi kant
 
132 KV Grid Station Intern ship training report
132 KV Grid Station Intern ship training report132 KV Grid Station Intern ship training report
132 KV Grid Station Intern ship training report
Muntazir Mehdi
 
132 gss ppt
132 gss ppt132 gss ppt
132 gss ppt
hunk143
 
Summer Training presentation on 132/33 KV sub-station Minto park, Allahabad
Summer Training presentation on 132/33 KV sub-station Minto park, AllahabadSummer Training presentation on 132/33 KV sub-station Minto park, Allahabad
Summer Training presentation on 132/33 KV sub-station Minto park, Allahabad
Sudhir Cement Industries Pvt. Ltd. Meerut
 
Ppt on 132 kv gss by ashok khoja
Ppt on  132 kv gss  by ashok khojaPpt on  132 kv gss  by ashok khoja
Ppt on 132 kv gss by ashok khojaASHOK KHOJA
 
Presentation 2014
Presentation 2014Presentation 2014
Presentation 2014
pinki199319
 
Equipments in switchyard and its protection
Equipments in switchyard and its protectionEquipments in switchyard and its protection
Equipments in switchyard and its protectionJayashree Behera
 
Summer Training Report Ntpc barh (ajeet)
Summer Training Report Ntpc barh (ajeet)Summer Training Report Ntpc barh (ajeet)
Summer Training Report Ntpc barh (ajeet)
Ajeet Chaurasia
 

Similar to Vocational Training Report ( Sealdah Power House) (20)

Gss ppt by kanhaiya
Gss ppt  by kanhaiyaGss ppt  by kanhaiya
Gss ppt by kanhaiya
 
project report on plc based load sharing
project report on plc based load sharingproject report on plc based load sharing
project report on plc based load sharing
 
Sub station training
Sub station trainingSub station training
Sub station training
 
Lab manual psd v sem experiment no 7
Lab manual psd v sem experiment no 7Lab manual psd v sem experiment no 7
Lab manual psd v sem experiment no 7
 
"high tension generator", "high tension","tension generator", "generator", ...
"high tension generator",  "high tension","tension generator",  "generator", ..."high tension generator",  "high tension","tension generator",  "generator", ...
"high tension generator", "high tension","tension generator", "generator", ...
 
substation internship report
substation internship report substation internship report
substation internship report
 
Substation
SubstationSubstation
Substation
 
Indusrtrial training ppt (1).pptx
Indusrtrial training ppt (1).pptxIndusrtrial training ppt (1).pptx
Indusrtrial training ppt (1).pptx
 
Uttar pradesh power corporation limited
Uttar pradesh power corporation limitedUttar pradesh power corporation limited
Uttar pradesh power corporation limited
 
5 power house
5 power house5 power house
5 power house
 
Design of substation
Design of substationDesign of substation
Design of substation
 
grid sub-station training Report
grid sub-station training Report grid sub-station training Report
grid sub-station training Report
 
132 KV Grid Station Intern ship training report
132 KV Grid Station Intern ship training report132 KV Grid Station Intern ship training report
132 KV Grid Station Intern ship training report
 
132 gss ppt
132 gss ppt132 gss ppt
132 gss ppt
 
Summer Training presentation on 132/33 KV sub-station Minto park, Allahabad
Summer Training presentation on 132/33 KV sub-station Minto park, AllahabadSummer Training presentation on 132/33 KV sub-station Minto park, Allahabad
Summer Training presentation on 132/33 KV sub-station Minto park, Allahabad
 
Ppt on 132 kv gss by ashok khoja
Ppt on  132 kv gss  by ashok khojaPpt on  132 kv gss  by ashok khoja
Ppt on 132 kv gss by ashok khoja
 
electronic componets
electronic componetselectronic componets
electronic componets
 
Presentation 2014
Presentation 2014Presentation 2014
Presentation 2014
 
Equipments in switchyard and its protection
Equipments in switchyard and its protectionEquipments in switchyard and its protection
Equipments in switchyard and its protection
 
Summer Training Report Ntpc barh (ajeet)
Summer Training Report Ntpc barh (ajeet)Summer Training Report Ntpc barh (ajeet)
Summer Training Report Ntpc barh (ajeet)
 

Recently uploaded

Accelerate your Kubernetes clusters with Varnish Caching
Accelerate your Kubernetes clusters with Varnish CachingAccelerate your Kubernetes clusters with Varnish Caching
Accelerate your Kubernetes clusters with Varnish Caching
Thijs Feryn
 
Slack (or Teams) Automation for Bonterra Impact Management (fka Social Soluti...
Slack (or Teams) Automation for Bonterra Impact Management (fka Social Soluti...Slack (or Teams) Automation for Bonterra Impact Management (fka Social Soluti...
Slack (or Teams) Automation for Bonterra Impact Management (fka Social Soluti...
Jeffrey Haguewood
 
Assuring Contact Center Experiences for Your Customers With ThousandEyes
Assuring Contact Center Experiences for Your Customers With ThousandEyesAssuring Contact Center Experiences for Your Customers With ThousandEyes
Assuring Contact Center Experiences for Your Customers With ThousandEyes
ThousandEyes
 
Kubernetes & AI - Beauty and the Beast !?! @KCD Istanbul 2024
Kubernetes & AI - Beauty and the Beast !?! @KCD Istanbul 2024Kubernetes & AI - Beauty and the Beast !?! @KCD Istanbul 2024
Kubernetes & AI - Beauty and the Beast !?! @KCD Istanbul 2024
Tobias Schneck
 
Unsubscribed: Combat Subscription Fatigue With a Membership Mentality by Head...
Unsubscribed: Combat Subscription Fatigue With a Membership Mentality by Head...Unsubscribed: Combat Subscription Fatigue With a Membership Mentality by Head...
Unsubscribed: Combat Subscription Fatigue With a Membership Mentality by Head...
Product School
 
Leading Change strategies and insights for effective change management pdf 1.pdf
Leading Change strategies and insights for effective change management pdf 1.pdfLeading Change strategies and insights for effective change management pdf 1.pdf
Leading Change strategies and insights for effective change management pdf 1.pdf
OnBoard
 
Neuro-symbolic is not enough, we need neuro-*semantic*
Neuro-symbolic is not enough, we need neuro-*semantic*Neuro-symbolic is not enough, we need neuro-*semantic*
Neuro-symbolic is not enough, we need neuro-*semantic*
Frank van Harmelen
 
FIDO Alliance Osaka Seminar: Passkeys at Amazon.pdf
FIDO Alliance Osaka Seminar: Passkeys at Amazon.pdfFIDO Alliance Osaka Seminar: Passkeys at Amazon.pdf
FIDO Alliance Osaka Seminar: Passkeys at Amazon.pdf
FIDO Alliance
 
From Siloed Products to Connected Ecosystem: Building a Sustainable and Scala...
From Siloed Products to Connected Ecosystem: Building a Sustainable and Scala...From Siloed Products to Connected Ecosystem: Building a Sustainable and Scala...
From Siloed Products to Connected Ecosystem: Building a Sustainable and Scala...
Product School
 
FIDO Alliance Osaka Seminar: FIDO Security Aspects.pdf
FIDO Alliance Osaka Seminar: FIDO Security Aspects.pdfFIDO Alliance Osaka Seminar: FIDO Security Aspects.pdf
FIDO Alliance Osaka Seminar: FIDO Security Aspects.pdf
FIDO Alliance
 
JMeter webinar - integration with InfluxDB and Grafana
JMeter webinar - integration with InfluxDB and GrafanaJMeter webinar - integration with InfluxDB and Grafana
JMeter webinar - integration with InfluxDB and Grafana
RTTS
 
Generating a custom Ruby SDK for your web service or Rails API using Smithy
Generating a custom Ruby SDK for your web service or Rails API using SmithyGenerating a custom Ruby SDK for your web service or Rails API using Smithy
Generating a custom Ruby SDK for your web service or Rails API using Smithy
g2nightmarescribd
 
Elevating Tactical DDD Patterns Through Object Calisthenics
Elevating Tactical DDD Patterns Through Object CalisthenicsElevating Tactical DDD Patterns Through Object Calisthenics
Elevating Tactical DDD Patterns Through Object Calisthenics
Dorra BARTAGUIZ
 
DevOps and Testing slides at DASA Connect
DevOps and Testing slides at DASA ConnectDevOps and Testing slides at DASA Connect
DevOps and Testing slides at DASA Connect
Kari Kakkonen
 
UiPath Test Automation using UiPath Test Suite series, part 3
UiPath Test Automation using UiPath Test Suite series, part 3UiPath Test Automation using UiPath Test Suite series, part 3
UiPath Test Automation using UiPath Test Suite series, part 3
DianaGray10
 
Mission to Decommission: Importance of Decommissioning Products to Increase E...
Mission to Decommission: Importance of Decommissioning Products to Increase E...Mission to Decommission: Importance of Decommissioning Products to Increase E...
Mission to Decommission: Importance of Decommissioning Products to Increase E...
Product School
 
Designing Great Products: The Power of Design and Leadership by Chief Designe...
Designing Great Products: The Power of Design and Leadership by Chief Designe...Designing Great Products: The Power of Design and Leadership by Chief Designe...
Designing Great Products: The Power of Design and Leadership by Chief Designe...
Product School
 
Essentials of Automations: Optimizing FME Workflows with Parameters
Essentials of Automations: Optimizing FME Workflows with ParametersEssentials of Automations: Optimizing FME Workflows with Parameters
Essentials of Automations: Optimizing FME Workflows with Parameters
Safe Software
 
Smart TV Buyer Insights Survey 2024 by 91mobiles.pdf
Smart TV Buyer Insights Survey 2024 by 91mobiles.pdfSmart TV Buyer Insights Survey 2024 by 91mobiles.pdf
Smart TV Buyer Insights Survey 2024 by 91mobiles.pdf
91mobiles
 
GraphRAG is All You need? LLM & Knowledge Graph
GraphRAG is All You need? LLM & Knowledge GraphGraphRAG is All You need? LLM & Knowledge Graph
GraphRAG is All You need? LLM & Knowledge Graph
Guy Korland
 

Recently uploaded (20)

Accelerate your Kubernetes clusters with Varnish Caching
Accelerate your Kubernetes clusters with Varnish CachingAccelerate your Kubernetes clusters with Varnish Caching
Accelerate your Kubernetes clusters with Varnish Caching
 
Slack (or Teams) Automation for Bonterra Impact Management (fka Social Soluti...
Slack (or Teams) Automation for Bonterra Impact Management (fka Social Soluti...Slack (or Teams) Automation for Bonterra Impact Management (fka Social Soluti...
Slack (or Teams) Automation for Bonterra Impact Management (fka Social Soluti...
 
Assuring Contact Center Experiences for Your Customers With ThousandEyes
Assuring Contact Center Experiences for Your Customers With ThousandEyesAssuring Contact Center Experiences for Your Customers With ThousandEyes
Assuring Contact Center Experiences for Your Customers With ThousandEyes
 
Kubernetes & AI - Beauty and the Beast !?! @KCD Istanbul 2024
Kubernetes & AI - Beauty and the Beast !?! @KCD Istanbul 2024Kubernetes & AI - Beauty and the Beast !?! @KCD Istanbul 2024
Kubernetes & AI - Beauty and the Beast !?! @KCD Istanbul 2024
 
Unsubscribed: Combat Subscription Fatigue With a Membership Mentality by Head...
Unsubscribed: Combat Subscription Fatigue With a Membership Mentality by Head...Unsubscribed: Combat Subscription Fatigue With a Membership Mentality by Head...
Unsubscribed: Combat Subscription Fatigue With a Membership Mentality by Head...
 
Leading Change strategies and insights for effective change management pdf 1.pdf
Leading Change strategies and insights for effective change management pdf 1.pdfLeading Change strategies and insights for effective change management pdf 1.pdf
Leading Change strategies and insights for effective change management pdf 1.pdf
 
Neuro-symbolic is not enough, we need neuro-*semantic*
Neuro-symbolic is not enough, we need neuro-*semantic*Neuro-symbolic is not enough, we need neuro-*semantic*
Neuro-symbolic is not enough, we need neuro-*semantic*
 
FIDO Alliance Osaka Seminar: Passkeys at Amazon.pdf
FIDO Alliance Osaka Seminar: Passkeys at Amazon.pdfFIDO Alliance Osaka Seminar: Passkeys at Amazon.pdf
FIDO Alliance Osaka Seminar: Passkeys at Amazon.pdf
 
From Siloed Products to Connected Ecosystem: Building a Sustainable and Scala...
From Siloed Products to Connected Ecosystem: Building a Sustainable and Scala...From Siloed Products to Connected Ecosystem: Building a Sustainable and Scala...
From Siloed Products to Connected Ecosystem: Building a Sustainable and Scala...
 
FIDO Alliance Osaka Seminar: FIDO Security Aspects.pdf
FIDO Alliance Osaka Seminar: FIDO Security Aspects.pdfFIDO Alliance Osaka Seminar: FIDO Security Aspects.pdf
FIDO Alliance Osaka Seminar: FIDO Security Aspects.pdf
 
JMeter webinar - integration with InfluxDB and Grafana
JMeter webinar - integration with InfluxDB and GrafanaJMeter webinar - integration with InfluxDB and Grafana
JMeter webinar - integration with InfluxDB and Grafana
 
Generating a custom Ruby SDK for your web service or Rails API using Smithy
Generating a custom Ruby SDK for your web service or Rails API using SmithyGenerating a custom Ruby SDK for your web service or Rails API using Smithy
Generating a custom Ruby SDK for your web service or Rails API using Smithy
 
Elevating Tactical DDD Patterns Through Object Calisthenics
Elevating Tactical DDD Patterns Through Object CalisthenicsElevating Tactical DDD Patterns Through Object Calisthenics
Elevating Tactical DDD Patterns Through Object Calisthenics
 
DevOps and Testing slides at DASA Connect
DevOps and Testing slides at DASA ConnectDevOps and Testing slides at DASA Connect
DevOps and Testing slides at DASA Connect
 
UiPath Test Automation using UiPath Test Suite series, part 3
UiPath Test Automation using UiPath Test Suite series, part 3UiPath Test Automation using UiPath Test Suite series, part 3
UiPath Test Automation using UiPath Test Suite series, part 3
 
Mission to Decommission: Importance of Decommissioning Products to Increase E...
Mission to Decommission: Importance of Decommissioning Products to Increase E...Mission to Decommission: Importance of Decommissioning Products to Increase E...
Mission to Decommission: Importance of Decommissioning Products to Increase E...
 
Designing Great Products: The Power of Design and Leadership by Chief Designe...
Designing Great Products: The Power of Design and Leadership by Chief Designe...Designing Great Products: The Power of Design and Leadership by Chief Designe...
Designing Great Products: The Power of Design and Leadership by Chief Designe...
 
Essentials of Automations: Optimizing FME Workflows with Parameters
Essentials of Automations: Optimizing FME Workflows with ParametersEssentials of Automations: Optimizing FME Workflows with Parameters
Essentials of Automations: Optimizing FME Workflows with Parameters
 
Smart TV Buyer Insights Survey 2024 by 91mobiles.pdf
Smart TV Buyer Insights Survey 2024 by 91mobiles.pdfSmart TV Buyer Insights Survey 2024 by 91mobiles.pdf
Smart TV Buyer Insights Survey 2024 by 91mobiles.pdf
 
GraphRAG is All You need? LLM & Knowledge Graph
GraphRAG is All You need? LLM & Knowledge GraphGraphRAG is All You need? LLM & Knowledge Graph
GraphRAG is All You need? LLM & Knowledge Graph
 

Vocational Training Report ( Sealdah Power House)

  • 1. 15th June to 18th June 2015 Power House
  • 2. 4 PowerHouse Introduction: A substation is a part of an electrical generation, transmission and distribution system. Substations transform voltage from high to low or reverse or any of several other important functions. Electric power may flow through several substations between generating plant and consumer and its voltage may change in several steps. A substation has a step up transformer which increase the voltage while decreasing the current while a step down transformer decrease the voltage while increasing the current for domestic and commercial distribution .The word substation comes from the days before the distribution system became a grid. The first substation were connected to only one power station, where the generators were housed and were subsidiaries of that power station. 6 KV. Distribution System in Sealdah Area Sealdah Power House LT Distribution system
  • 3. 5 PowerHouse In SEALDAH POWERHOUSEthe control is divided into two sections. i. The Low Tension section ii. The High Tension section  The main components of the Power House :  Switch Gear  Transformers (300KVA. & 500 KVA.)  Isolator  Bus Bar  Bus Coupler  Circuit breakers (Air circuit breakers on L.T. side & vacuumcircuit breakers on H.T. side)  Relays (Earth Fault Relay & Over CurrentRelay)  Hooter / Alarm The components are described in brief fromthe power housebellow.  Switch Gear: It is a combination of electrical disconnect switches, fuses and circuit breakers used to control, protect and isolate electrical equipment. This switchgear is connected to the incoming supply from CESC. There are two connections available (one kept for emergency). Incoming Switch Gear The connections are coupled together by a Bus coupler and then sent to the Transformers for further step down of voltage, as required. If any fault occurs upstream (i.e., in supply side), this switchgear immediately disconnects from
  • 4. 6 PowerHouse the supply thereby preventing further spreading of fault and hence keeping alive the essential railway operations.  Step down transformer: A transformer is a device that transfers electric energy from one circuit to another circuit through inductively coupled conductors---the transformers coil---a varying current in the first or primary winding creates a varying magnetic flux in the transformer core and thus a varying magnetic field through the secondary winding. This varying magnetic field induces a varying electromotive force (EMF) or voltage in the secondary winding. This effect is called mutual induction. If a load is connected to the secondary, an electric current will flow in the secondary winding and electrical energy will be transferred from the primary circuit through the transformer to the load. In an ideal transformer ,the induced voltage (Vs) in the secondary winding is proportion to primary voltage (Vp) and is given by the ratio of the number of turns in the secondary(Ns) to the number of turns in primary(Np) as follows, Vs/ Vp = Ns/ Np By appropriate selection of the ratio of turns, a transformer thus allows an alternating current voltage to be “stepped up” by making Ns greater than Np or “stepped down” by making Ns less than Np. In the vast majority of transformers, the winding are coils wound around a ferromagnetic core, air-core transformers being a notable exception. In SEALDAH POWER HOUSE two transformers are used, two 300 KVA and another 500 KVA. Two 300 KVA transformers are connected in parallel. A spare 500 KVA transformer is kept for backup.
  • 5. 7 PowerHouse 300 KVA. Transformer in Sealdah Power House 500 KVA. Transformer in Sealdah Power House
  • 6. 8 PowerHouse  500 KVA. Transformer ratings :  Isolator: In electrical engineering, an isolator switch is used to make sure that an electrical circuit can be completely de-energised for serviceor maintenance. Such switches are often found in electrical distribution and industrial applications where machinery must have its source of driving power removed for adjustment or repair. High voltage isolation switches are used in electrical substations to allow isolation of apparatus such as circuit breakers transformer and transmission lines for maintenance. C Serial No. 1581/D7-08 Maker AUTOMATIC ELECTRIC GROUP KVA. 500 KVA. Voltage At No Load H.V: 6000 V. ; L.V: 415 V. Amperes H.V: 48.11 A. ; L.V: 695.62 A. Phases H.V: 3 ; L.V: 3 Type of cooling Oil Natural Cooling Frequency 50 C/S Impedance voltage 4.37 % Vector Group Ref. Dy11 Core and Wedge 1140 kg. Weight of oil 451 kg. Total weight 2105 kg. Oil amount 530 liters Maximum temperature rise in oil 45 degree
  • 7. 9 PowerHouse  Bus Bar: In electrical power distribution, a bus bar is a metallic strip (or bus) that conducts electricity within a distribution board or substation. Its main purpose is to conduct a substancial current of electricity and not to function as a structural member. It is a wide and thick strip of metal generally copper wich carry high voltage power. The bus bars are used instead oc wire to reduce the transmission losses. Bus Bar in the Control Panel  Bus coupler: Bus coupler provides electrical isolation bus by employing coupling transformers and fault isolation resistors. The Bus couplers contain two isolation resistors (one per wire) and an isolation transformer (with a ratio one to the square root of two). The purpose of bus coupler is to prevent a short on a single stub from shorting the main data bus. The buses of two different voltage levels cannot be connected in series. So, bus coupler is used to join the buses of different voltage level. Bus Coupler  Protective Relays: A relay is fault sensing device. Many relay use an electromagnet to operate a switching mechanism mechanically, but other operating principles are also used. Relays are used where it is necessary to control a circuit by a low-power signal (with complete electrical isolation between control and controlled circuit) or where several circuits must be controlled by one.
  • 8. 10 PowerHouse The first relays were used in long distance telegraph circuits, repeating the signal coming from one circuit and re-transmitting it to another. Relays were extensively used in telephone exchanges and early computers to perform logical operations. A type of relay that can handle the high power required to directly control an electric motor is called a conductor. Solid- state relays control power circuits with no moving parts, instead using a semiconductor device to perform switching. Relays with calibrated operating characteristics and sometimes multiple operating coils are used to protect electrical circuits fromoverload or faults; in modern electric power systems these functions are performed by digital instruments still called ‘Protective Relays’. Protective Relay The Relays used in Sealdah Power Houseare of mainly two types,  Over CurrentRelay  Earth Fault Relay  The Relay specification (Based on one sample on HT. panel): Over Current Relay Earth Fault Relay Model No. CDG31EG001SBCH Model No. CDG31EG001SBCH Serial no. - 130954160621011 Serial no. - 130954160621011 C.T. SEC : 5 AMPS;2.5-10 Amps. C.T. SEC : 5 AMPS;1-4 Amps. Frequency : 50 Hz. Frequency : 50 Hz.
  • 9. 11 PowerHouse  Oil Circuit Breaker (O.C.B.): The oil in OCB’s serves two purposes. It insulates between the phases and the ground, and it provides the medium for the extinguishing of arc. When electric arc is drawn under oil, the arc vaporises the oil and creates a large bubble that surrounds the arc. The gas inside the bubble is around 80%hydrogen, which impairs ionisation. The decomposition of oil into gas requires energy that comes from the heat generated by the arc. The oil surrounding the bubble conducts the heat away from the arc and thus also contributes to deionisation of the arc. Oil Circuit Breaker  The Oil Circuit Breaker specification (Based on one sample on the LT. panel of 1 no. PF. Substation): Sl. No. 2K2132 Type HN2T Normal current 400 A. Service voltage 415 V. Design frequency 50 Hz. Breaking capacity 25 MVA. Trip coil rating 5 A. Calibration 100/200 %
  • 10. 12 PowerHouse C.T. ratio 800/5  Air Circuit Breaker (A.C.B.): The working principle of this breaker is rather different from those in any other types of circuit breakers. The main aim of all kind of circuit breaker is to prevent the reestablishment of arcing after current zero by creating a situation where in the contact gap will withstand the system recovery voltage. The air circuit breaker does the same but in different manner. For interrupting arc it creates an arc voltage in excess of the supply voltage. Arc voltage is defined as the minimum voltage required maintaining the arc. This circuit breaker increases the arc voltage by mainly three different ways, i. It may increase the arc voltage by cooling the arc plasma. As the temperature of arc plasma is decreased, the mobility of the particle in arc plasma is reduced, hence more voltage gradient is required to maintain the arc. ii. It may increase the arc voltage by lengthening the arc path. As the length of arc path is increased, the resistance of the path is increased, and hence to maintain the same arc current more voltage is required to be applied across the arc path. That means arc voltage is increased. iii. Splitting up the arc into a number of series arcs also increases the arc voltage. Various internal parts of an Air Circuit Breaker
  • 11. 13 PowerHouse  The Air Circuit Breaker specification (Based on one sample on LT. panel):  Rated Characteristics:  Substation of PF. No. 1: The 6 KV. high voltage is transmitted to the 1 no. platform of Sealdah rail station from the power house and stepped down to 415 v. (Phase to phase) by a 300 KVA. transformer situated in the substation. The 415 V. supply is then distributed to the entire Sealdah station, all the platforms, the offices, ticket counters, train boards, digital clock, announcement speakers and all of the lights and fans of Sealdah Main and South both sections are run by this supply.  The Diesel Engine-Alternator arrangement situated at substation of PF. No. 1: There is a diesel engine coupled with a alternator in the 1 no. platform substation for delivering power when main power is not available means at the Maker PULSER Frame LH800 DM1T3P Sl. No. Y606183 IEC-947-2 IS:13947 (PART-2) Utilization category 8 In 400A. ITH @40 degree C. 800A. ICS & ICU 50 Ka. ICW 50 Ka., 1sec. Power Factor 0.25 Ui=1000VUe=415V Frequency : 50/60HZ U/V 40 AC
  • 12. 14 PowerHouse time of load shading. This alternator produce 3 phase 415 V and make run the essential systems of Sealdah Station at the time of load shading. The Diesel Engine and Alternator arrangement at PF. No. 1 Substation