SlideShare a Scribd company logo
1 of 21
MANUFACTURING PROCESS OF 600 MW
TURBO GENERTOR STATOR WINDING
BAR
Presented By: Shubham Kulshreshtha(1301421092)
SRMS College of engineering & technology,
Bareilly
BHEL HARIDWAR
INTRODUCTION
In 1956 India took a major step towards the establishment of its
heavy engineering industry when BHEL, the first heavy electrical
Manufacturing unit of the country was set up at Bhopal.
BHEL's Heavy Electrical Equipment Plant (HEEP) was set up
in technical collaboration with USSR, for the manufacturing of
power plant equipment.
In 1976, BHEL entered into a collaboration agreement with
M/s Kraftwerk Union, AG of Germany for design,
manufacturing, erection and commissioning of large size
steam turbines.
More than 40 percent of the country's electrical energy is
generated from the power equipment supplied by BHEL,
Haridwar.
MANUFACTURING BLOCKS:
.
BLOCK I: ELECTRICAL MACHINE BLOCK, IS DESIGNED TO
MANUFACTURING OF TURBOGENERATORS
BLOCK II: FABRICATION BLOCK
BLOCK III: TURBINE BLADE BLOCK
BLOCK IV: COIL & INSULATION MANUFACTURING &
APPARATUS & CONTROL GEAR MANUFACTURING
BLOCK
BLOCK V: FEEDER BLOCK AND KNOWN AS FABRICATION
AND FORGE BLOCK
BLOCK VI: STAMPING AND DIES MANUFACTURING BLOCK
BLOCK VII: WOODWORKING BLOCK
BLOCK VIII: HEAT EXCHANGER BLOCK, IS DESIGNED TO
MANUFACTURE HEAT EXCHANGER UNIT FOR
STEAM TURBINES.
COIL & INSULATION MANUFACTURING
SHOP (BLOCK-IV)
Block-4 is a feeder block for insulating items,
winding with class-B Bituminous insulation and sheet
metal components for all the products of Block-1 i.e.
Turbo-generators, Hydro-generators, A.C. and D.C.
machines
There are three BAYS in this block each bay
manufactures stator bars and coils for different
machines
BAY-I: Bar winding shop: manufacturing of stator winding
bars of generator
BAY-II: Manufacturing of heavy duty generator stator bars
with New CNC M/c
BAY-III: Insulation detail shop: Manufacturing of hard
insulation & machining of hares insulation part (Glass Textolite)
such as packing, washer, insulation box, wedges etc
Bar Shop: This shop is meant for manufacturing of stator
winding coils of turbo-generator and hydro generator
Layout of CIM, Block-IV
Sections in Block IV
1) Assembly Section
It is equipped with small size
• Drilling machines
• Welding sets
• Hydraulic testing equipment
for manufacturing turbo-
generator mechanical
assemblies.
2) Stator Bar Winding Section
It is equipped with
•Conductor cutting, insulation and
transposition section.
•Stack consolidation section,
forming and lug brazing sections.
•Insulation taping sections with
automatic taping facilities in air-
conditioned
3) Impregnation Section
It is equipped with
• Impregnation tank
• Ovens for impregnation of DC pole coils.
4) Armature Winding, Rotor coil and Stator bar Section
It is equipped with
• Conductors cutting.
• U- bending and terminal conductor cutting machines.
• Semi-automatic winding machine.
• Planking, boat pulling and diamond pulling machine.
• Insulation and pressing of AC coils.
5) Insulation Section
It is equipped with
• Small size lathes.
• Milling and radial drilling machines.
• Jet cutting saw.
• Electrical ovens & Hydraulic presses.
•Plastic Molding Section
Types of Generators
The generator may be classified based upon the cooling
system used in the generators such as: THRI, TARI, THDI,
THDD, THDF, THFF, and THW
Stands for type
of generator
• T- Turbo
Generator
• H- Hydro
Generator
Stands for the
cooling media
for Rotor
• H- Hydrogen
gas
• A- Air
Stands for the
type of cooling
for Rotor
• R- Radial
• D- Direct
• F- Forced
• I- Indirect
Stands for type
of cooling for
Stator
• I- Indirect
• D- Direct
• F- Forced
Stands for
cooling media
used for Stator
coil
• W- Water
It is quite difficult (rather impossible) to manufacture, handle
and wind in the stator slot of generator of higher generation
capacity because of its bigger size and heavy weight. That is
why we make coil in two parts. One part its bottom part of coil
called bottom or lower bar and other part of coil is called top
bar or upper bar.
Why do we call it bar?
Set Type Upper
Ordinary
Upper
Terminal
Lower
Ordinary
Lower
Terminal
Total
Bars
No. of
Bus
Bars
500MW
THDF
42 6 42 6 96 6
210MW
THW
54 6 54 6 120 9
250MW
THRI
48 12 48 12 120 9
No. of Bars in current products
 Poor Resin or Micalastic insulation system
In this type of insulation the bond content in the resin is 5 – 7%
and insulating material is prepared with accelerator treatment.
The temperature control need is not required. The insulating
material is applied on job and then same is impregnated (fully
dipped) in the resin.
Resin System:
 Rich Resin or Thermo-reactive insulation system:
In this type of insulation system the bond content in resin is
35 – 37 %. The raw materials are ready to use and require
preservation and working on temperature 20 – 250C. Its shelf
life is one year when kept at a temperature of 200C which
could be increased when kept at temperature of 50C.
INSULATION CLASSIFICATION:
Class
Y
• Upto 90 °C
• Cotton, Silk, or Paper.
Class
A
• Upto 105 °C
• Reinforced Class-Y materials with impregnated varnish.
Class
E
• Upto 120 °C
• Cotton lamination & Paper lamination.
Class
B
• Upto 130 °C
• Inorganic material is hardened with adhesives.
Class
F
• Upto 150 °C
• Class-B materials that are upgraded with adhesives.
Class
H
• Upto 180 °C
• Made of inorganic material glued with silicone resin.
Class
C
• > 180 °C Upto 220 °C
• Made of 100% inorganic material
Transposition
Transposition means changing/shifting of position of each
conductor in active core (slot) part.
•After cutting the required number of conductors
•The conductors are arranged on the comb in staggered
manner and then bends are given to the conductors with the
help of bending die at required distance.
•Then the conductors are taken out from the comb and die and
placed with their ends in a line and transposition is carried out.
•This process is repeated for making another half of the bar
which would be mirror image of the first half.
•The two halves of the bar are overlapped over each other and
a spacer is placed between the two halves.
Need of transposition.
1. To reduce eddy current losses.
2. Equalize the voltage generator.
3. To minimize skin effect of ac current.
Transposition is done in two ways:
Half Pitch Transposition: In this transposition, the first
conductor at one end of the bar becomes the last conductor at
the other end of the bar.
Full Pitch Transposition: In this method of transposition, the
first conductor at one end of the bar becomes the last
conductor in the mid of the bar and then again becomes the
first conductor at the other end of the bar.
Testing
Tan δ test:
•This test is carried out to ensure the healthiness of dielectric
(Insulation) i.e. dense or rare & measured the capacitance loss.
•Bar will act as capacitor when it is laid in the stator of the
generator.
•Schearing Bridge which works on the principle of wheat-stone
bridge is used to find the unknown capacitance of the bar.
•For good efficiency, capacitance of the bar should be high but we
never approach pure capacitance.
•Bar is wrapped with aluminum to make the bar conductive
throughout the outer surface of the bar. The two conducting
material i.e. the aluminum sheet and the conductors of the bar act
as two plates of the capacitor and the insulation on the bar act as
dielectric medium for the capacitor thus the capacitance is found.
•Of angle of deviation due to impurity in the insulation is obtained
from the formula: C4 * R4 * 10^-4 = tan δ
H.V. Test:
•Each bar is tested momentary at high voltage increased gradually
to three times higher than rated voltage.
•This test is also known as insulation test because this test is
performed to check the insulation of the bar.
•For 600 MW the working voltage of the bar is 64.5 KV & for 210
MW the working voltage of the bar is 63 KV.
•In this test the bar which is already wrapped with aluminum is
used.
•High voltage is applied to the bar using auto-transformer and it is
increased in steps according to the working voltage of the
generator. If the insulation is weak the bar will puncture at the
place of weaker insulation.
•If any of the bar fails this test i.e. bar is punctured at any point
then the bar is sent back for re-insulation and all the processes
are repeated again
2-Pole machine with the following features:
Direct cooling of stator winding with water.
Direct hydrogen cooling for rotor.
Micalastic insulation system.
Spring mounted core housing for effective transmission of
vibrations.
Brushless Excitation system.
Vertical hydrogen coolers
600 MW Turbo generators at a glance
Important dimensions & weights:
Heaviest lift of generator stator : 255 Tons
Rotor weight : 68 Tons
Overall stator dimensions [L*B*H] : 8.83m*4.lm*4.02m
Rotor dimensions(Dia. and length) : 1.15m and 12.11m
Total weight of turbo generator : 428 Tons
Salient technical data:
Rated output: 588 MVA , 600 MW
Terminal voltage: 21 KV
Rated stator current: 16 KA
Rated frequency: 50 Hz
Rated power factor: 0.85 Lag
Efficiency: 98.55%
Picture Of Bars
THANK YOU

More Related Content

What's hot

Gurtej bhel electrical report-at-bhel-haridwar-1
Gurtej bhel electrical report-at-bhel-haridwar-1Gurtej bhel electrical report-at-bhel-haridwar-1
Gurtej bhel electrical report-at-bhel-haridwar-1Gurtej Rai
 
Fluxtrol AlphaForm Moldable Magnetic Flux Concentrators
Fluxtrol AlphaForm Moldable Magnetic Flux ConcentratorsFluxtrol AlphaForm Moldable Magnetic Flux Concentrators
Fluxtrol AlphaForm Moldable Magnetic Flux ConcentratorsFluxtrol Inc.
 
Gallery of Fluxtrol Magnetic Flux Concentrators
Gallery of Fluxtrol Magnetic Flux ConcentratorsGallery of Fluxtrol Magnetic Flux Concentrators
Gallery of Fluxtrol Magnetic Flux ConcentratorsFluxtrol Inc.
 
MAGNETIC FLUX CONTROL IN INDUCTION INSTALLATIONS
MAGNETIC FLUX CONTROL IN INDUCTION INSTALLATIONSMAGNETIC FLUX CONTROL IN INDUCTION INSTALLATIONS
MAGNETIC FLUX CONTROL IN INDUCTION INSTALLATIONSFluxtrol Inc.
 
Rautomead Newsletter issue 03
Rautomead Newsletter issue 03 Rautomead Newsletter issue 03
Rautomead Newsletter issue 03 Rautomead Limited
 
Optimization Potential of Induction Heating Systems by Stefan Schubotz and Ha...
Optimization Potential of Induction Heating Systems by Stefan Schubotz and Ha...Optimization Potential of Induction Heating Systems by Stefan Schubotz and Ha...
Optimization Potential of Induction Heating Systems by Stefan Schubotz and Ha...Fluxtrol Inc.
 
iron and steel plant
iron and steel plantiron and steel plant
iron and steel plantKumar Gaurav
 
Repairing of kiln shell crack
Repairing of kiln shell crackRepairing of kiln shell crack
Repairing of kiln shell crackmkpq pasha
 
Recognizing and Eliminating Flux Concentrator Failures
Recognizing and Eliminating Flux Concentrator FailuresRecognizing and Eliminating Flux Concentrator Failures
Recognizing and Eliminating Flux Concentrator FailuresFluxtrol Inc.
 
Airframe Maintenance and Repair
Airframe Maintenance and RepairAirframe Maintenance and Repair
Airframe Maintenance and RepairDeepanBooramurthy
 
SUMMER TRAINING
SUMMER TRAININGSUMMER TRAINING
SUMMER TRAININGAnu Gupta
 
INDUCTION HARDENING by Jeevan B M
INDUCTION HARDENING by Jeevan B M INDUCTION HARDENING by Jeevan B M
INDUCTION HARDENING by Jeevan B M Jeevan B M
 
Specification and Use of a Flux Concentrator
Specification and Use of a Flux ConcentratorSpecification and Use of a Flux Concentrator
Specification and Use of a Flux ConcentratorFluxtrol Inc.
 
Cg distribution-transformers
Cg distribution-transformersCg distribution-transformers
Cg distribution-transformersprevrtljivac
 
Hot Hydroforging of Lightweight Bilateral Gears and Hollow Products
Hot Hydroforging of Lightweight Bilateral Gears and Hollow ProductsHot Hydroforging of Lightweight Bilateral Gears and Hollow Products
Hot Hydroforging of Lightweight Bilateral Gears and Hollow ProductsFluxtrol Inc.
 
Increasing Inductor Lifetime by Predicting Coil Copper Temperatures Presentation
Increasing Inductor Lifetime by Predicting Coil Copper Temperatures PresentationIncreasing Inductor Lifetime by Predicting Coil Copper Temperatures Presentation
Increasing Inductor Lifetime by Predicting Coil Copper Temperatures PresentationFluxtrol Inc.
 

What's hot (20)

Gurtej bhel electrical report-at-bhel-haridwar-1
Gurtej bhel electrical report-at-bhel-haridwar-1Gurtej bhel electrical report-at-bhel-haridwar-1
Gurtej bhel electrical report-at-bhel-haridwar-1
 
Fluxtrol AlphaForm Moldable Magnetic Flux Concentrators
Fluxtrol AlphaForm Moldable Magnetic Flux ConcentratorsFluxtrol AlphaForm Moldable Magnetic Flux Concentrators
Fluxtrol AlphaForm Moldable Magnetic Flux Concentrators
 
Gallery of Fluxtrol Magnetic Flux Concentrators
Gallery of Fluxtrol Magnetic Flux ConcentratorsGallery of Fluxtrol Magnetic Flux Concentrators
Gallery of Fluxtrol Magnetic Flux Concentrators
 
MAGNETIC FLUX CONTROL IN INDUCTION INSTALLATIONS
MAGNETIC FLUX CONTROL IN INDUCTION INSTALLATIONSMAGNETIC FLUX CONTROL IN INDUCTION INSTALLATIONS
MAGNETIC FLUX CONTROL IN INDUCTION INSTALLATIONS
 
Rautomead Newsletter issue 03
Rautomead Newsletter issue 03 Rautomead Newsletter issue 03
Rautomead Newsletter issue 03
 
REPORT (1)
REPORT (1)REPORT (1)
REPORT (1)
 
heat treatment
heat treatmentheat treatment
heat treatment
 
Optimization Potential of Induction Heating Systems by Stefan Schubotz and Ha...
Optimization Potential of Induction Heating Systems by Stefan Schubotz and Ha...Optimization Potential of Induction Heating Systems by Stefan Schubotz and Ha...
Optimization Potential of Induction Heating Systems by Stefan Schubotz and Ha...
 
iron and steel plant
iron and steel plantiron and steel plant
iron and steel plant
 
Repairing of kiln shell crack
Repairing of kiln shell crackRepairing of kiln shell crack
Repairing of kiln shell crack
 
Recognizing and Eliminating Flux Concentrator Failures
Recognizing and Eliminating Flux Concentrator FailuresRecognizing and Eliminating Flux Concentrator Failures
Recognizing and Eliminating Flux Concentrator Failures
 
Airframe Maintenance and Repair
Airframe Maintenance and RepairAirframe Maintenance and Repair
Airframe Maintenance and Repair
 
Composite repair
Composite repairComposite repair
Composite repair
 
SUMMER TRAINING
SUMMER TRAININGSUMMER TRAINING
SUMMER TRAINING
 
INDUCTION HARDENING by Jeevan B M
INDUCTION HARDENING by Jeevan B M INDUCTION HARDENING by Jeevan B M
INDUCTION HARDENING by Jeevan B M
 
Specification and Use of a Flux Concentrator
Specification and Use of a Flux ConcentratorSpecification and Use of a Flux Concentrator
Specification and Use of a Flux Concentrator
 
Cg distribution-transformers
Cg distribution-transformersCg distribution-transformers
Cg distribution-transformers
 
Hot Hydroforging of Lightweight Bilateral Gears and Hollow Products
Hot Hydroforging of Lightweight Bilateral Gears and Hollow ProductsHot Hydroforging of Lightweight Bilateral Gears and Hollow Products
Hot Hydroforging of Lightweight Bilateral Gears and Hollow Products
 
Increasing Inductor Lifetime by Predicting Coil Copper Temperatures Presentation
Increasing Inductor Lifetime by Predicting Coil Copper Temperatures PresentationIncreasing Inductor Lifetime by Predicting Coil Copper Temperatures Presentation
Increasing Inductor Lifetime by Predicting Coil Copper Temperatures Presentation
 
Case hardening
Case hardeningCase hardening
Case hardening
 

Viewers also liked

Computer basics--basic comp-oper
Computer basics--basic comp-operComputer basics--basic comp-oper
Computer basics--basic comp-operNidhi Khandelwal
 
20620041 electrical-motors
20620041 electrical-motors20620041 electrical-motors
20620041 electrical-motorsDodda Haralu
 
Three Phase Ac Winding Calculation
Three Phase Ac Winding CalculationThree Phase Ac Winding Calculation
Three Phase Ac Winding Calculationzlatkodo
 
Basic Computer Operation And Troubleshooting
Basic  Computer  Operation And  TroubleshootingBasic  Computer  Operation And  Troubleshooting
Basic Computer Operation And TroubleshootingPraveen Sudarsan
 
F:\Ac Generator Ppt
F:\Ac Generator PptF:\Ac Generator Ppt
F:\Ac Generator PptJunrellC
 
Induction Synchronous Motor
Induction Synchronous MotorInduction Synchronous Motor
Induction Synchronous MotorShahzad Khalil
 

Viewers also liked (11)

Computer basics--basic comp-oper
Computer basics--basic comp-operComputer basics--basic comp-oper
Computer basics--basic comp-oper
 
Ac motor winding
Ac motor windingAc motor winding
Ac motor winding
 
20620041 electrical-motors
20620041 electrical-motors20620041 electrical-motors
20620041 electrical-motors
 
Three Phase Ac Winding Calculation
Three Phase Ac Winding CalculationThree Phase Ac Winding Calculation
Three Phase Ac Winding Calculation
 
Basic Computer Operation
Basic Computer OperationBasic Computer Operation
Basic Computer Operation
 
Basic Computer Operation And Troubleshooting
Basic  Computer  Operation And  TroubleshootingBasic  Computer  Operation And  Troubleshooting
Basic Computer Operation And Troubleshooting
 
F:\Ac Generator Ppt
F:\Ac Generator PptF:\Ac Generator Ppt
F:\Ac Generator Ppt
 
AC MOTORS
AC MOTORSAC MOTORS
AC MOTORS
 
Induction Synchronous Motor
Induction Synchronous MotorInduction Synchronous Motor
Induction Synchronous Motor
 
Induction motor
Induction motorInduction motor
Induction motor
 
Slideshare ppt
Slideshare pptSlideshare ppt
Slideshare ppt
 

Similar to MANUFACTURING PROCESS OF 600 MW TURBO GENERTOR STATOR WINDING BAR

MANUFACTURING PROCESS OF STATOR BAR; 600 MW TURBO GENERATOR
MANUFACTURING PROCESS OF STATOR BAR; 600 MW TURBO GENERATORMANUFACTURING PROCESS OF STATOR BAR; 600 MW TURBO GENERATOR
MANUFACTURING PROCESS OF STATOR BAR; 600 MW TURBO GENERATORAnurag Verma
 
Manufacturing process of 500/600MW stator winding bar
Manufacturing process of 500/600MW stator winding barManufacturing process of 500/600MW stator winding bar
Manufacturing process of 500/600MW stator winding barAvinash Kumar
 
Manfacturing of turbo generators at BHEL
Manfacturing of turbo generators at BHELManfacturing of turbo generators at BHEL
Manfacturing of turbo generators at BHELPrabhu Raj
 
Welding of Joints.pdf
Welding of Joints.pdfWelding of Joints.pdf
Welding of Joints.pdfTVijayaGowri
 
Circuit Breaker: Part 2
Circuit Breaker: Part 2Circuit Breaker: Part 2
Circuit Breaker: Part 2Dr. Rohit Babu
 
Manufacturing of Large Electrical Machine
Manufacturing of Large Electrical MachineManufacturing of Large Electrical Machine
Manufacturing of Large Electrical MachineVAIBHAV SINGH
 
Condition monitoring of rotating electrical machines
Condition monitoring of rotating electrical machinesCondition monitoring of rotating electrical machines
Condition monitoring of rotating electrical machinesAnkit Basera
 
Bus Ducts or Hollow conductors
Bus Ducts or Hollow conductorsBus Ducts or Hollow conductors
Bus Ducts or Hollow conductorsAjay Meena
 
Ramendra summer training presentation
Ramendra summer training presentationRamendra summer training presentation
Ramendra summer training presentationRamendra Dhiman
 
Protection & switchgear
Protection & switchgear   Protection & switchgear
Protection & switchgear johny renoald
 
Traction distribution
Traction distribution Traction distribution
Traction distribution Amit Kumar
 
Transformer Designing
Transformer Designing Transformer Designing
Transformer Designing Praveen Sharma
 

Similar to MANUFACTURING PROCESS OF 600 MW TURBO GENERTOR STATOR WINDING BAR (20)

Harshitagarwal 111109034529-phpapp02
Harshitagarwal 111109034529-phpapp02Harshitagarwal 111109034529-phpapp02
Harshitagarwal 111109034529-phpapp02
 
MANUFACTURING PROCESS OF STATOR BAR; 600 MW TURBO GENERATOR
MANUFACTURING PROCESS OF STATOR BAR; 600 MW TURBO GENERATORMANUFACTURING PROCESS OF STATOR BAR; 600 MW TURBO GENERATOR
MANUFACTURING PROCESS OF STATOR BAR; 600 MW TURBO GENERATOR
 
Harshit agarwal
Harshit agarwalHarshit agarwal
Harshit agarwal
 
Manufacturing process of 500/600MW stator winding bar
Manufacturing process of 500/600MW stator winding barManufacturing process of 500/600MW stator winding bar
Manufacturing process of 500/600MW stator winding bar
 
Manfacturing of turbo generators at BHEL
Manfacturing of turbo generators at BHELManfacturing of turbo generators at BHEL
Manfacturing of turbo generators at BHEL
 
Welding of Joints.pdf
Welding of Joints.pdfWelding of Joints.pdf
Welding of Joints.pdf
 
Shashi
ShashiShashi
Shashi
 
BHEL Trainning Report
BHEL Trainning ReportBHEL Trainning Report
BHEL Trainning Report
 
TELK Industrial Visit Report
TELK Industrial Visit ReportTELK Industrial Visit Report
TELK Industrial Visit Report
 
Circuit Breaker: Part 2
Circuit Breaker: Part 2Circuit Breaker: Part 2
Circuit Breaker: Part 2
 
Seminar report
Seminar reportSeminar report
Seminar report
 
Manufacturing of Large Electrical Machine
Manufacturing of Large Electrical MachineManufacturing of Large Electrical Machine
Manufacturing of Large Electrical Machine
 
Condition monitoring of rotating electrical machines
Condition monitoring of rotating electrical machinesCondition monitoring of rotating electrical machines
Condition monitoring of rotating electrical machines
 
Bus Ducts or Hollow conductors
Bus Ducts or Hollow conductorsBus Ducts or Hollow conductors
Bus Ducts or Hollow conductors
 
ALTERNATOR DESIGN
ALTERNATOR DESIGNALTERNATOR DESIGN
ALTERNATOR DESIGN
 
Ramendra summer training presentation
Ramendra summer training presentationRamendra summer training presentation
Ramendra summer training presentation
 
Protection & switchgear
Protection & switchgear   Protection & switchgear
Protection & switchgear
 
COMPANY PROFILE
COMPANY PROFILECOMPANY PROFILE
COMPANY PROFILE
 
Traction distribution
Traction distribution Traction distribution
Traction distribution
 
Transformer Designing
Transformer Designing Transformer Designing
Transformer Designing
 

Recently uploaded

(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...ranjana rawat
 
Extrusion Processes and Their Limitations
Extrusion Processes and Their LimitationsExtrusion Processes and Their Limitations
Extrusion Processes and Their Limitations120cr0395
 
SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )Tsuyoshi Horigome
 
High Profile Call Girls Dahisar Arpita 9907093804 Independent Escort Service ...
High Profile Call Girls Dahisar Arpita 9907093804 Independent Escort Service ...High Profile Call Girls Dahisar Arpita 9907093804 Independent Escort Service ...
High Profile Call Girls Dahisar Arpita 9907093804 Independent Escort Service ...Call girls in Ahmedabad High profile
 
Microscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptxMicroscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptxpurnimasatapathy1234
 
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...ranjana rawat
 
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICSAPPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICSKurinjimalarL3
 
HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICS
HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICSHARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICS
HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICSRajkumarAkumalla
 
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur High Profile
 
IMPLICATIONS OF THE ABOVE HOLISTIC UNDERSTANDING OF HARMONY ON PROFESSIONAL E...
IMPLICATIONS OF THE ABOVE HOLISTIC UNDERSTANDING OF HARMONY ON PROFESSIONAL E...IMPLICATIONS OF THE ABOVE HOLISTIC UNDERSTANDING OF HARMONY ON PROFESSIONAL E...
IMPLICATIONS OF THE ABOVE HOLISTIC UNDERSTANDING OF HARMONY ON PROFESSIONAL E...RajaP95
 
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLSMANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLSSIVASHANKAR N
 
Processing & Properties of Floor and Wall Tiles.pptx
Processing & Properties of Floor and Wall Tiles.pptxProcessing & Properties of Floor and Wall Tiles.pptx
Processing & Properties of Floor and Wall Tiles.pptxpranjaldaimarysona
 
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...Soham Mondal
 
the ladakh protest in leh ladakh 2024 sonam wangchuk.pptx
the ladakh protest in leh ladakh 2024 sonam wangchuk.pptxthe ladakh protest in leh ladakh 2024 sonam wangchuk.pptx
the ladakh protest in leh ladakh 2024 sonam wangchuk.pptxhumanexperienceaaa
 
Porous Ceramics seminar and technical writing
Porous Ceramics seminar and technical writingPorous Ceramics seminar and technical writing
Porous Ceramics seminar and technical writingrakeshbaidya232001
 
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escortsranjana rawat
 
Introduction and different types of Ethernet.pptx
Introduction and different types of Ethernet.pptxIntroduction and different types of Ethernet.pptx
Introduction and different types of Ethernet.pptxupamatechverse
 
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur High Profile
 
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...ranjana rawat
 

Recently uploaded (20)

DJARUM4D - SLOT GACOR ONLINE | SLOT DEMO ONLINE
DJARUM4D - SLOT GACOR ONLINE | SLOT DEMO ONLINEDJARUM4D - SLOT GACOR ONLINE | SLOT DEMO ONLINE
DJARUM4D - SLOT GACOR ONLINE | SLOT DEMO ONLINE
 
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
 
Extrusion Processes and Their Limitations
Extrusion Processes and Their LimitationsExtrusion Processes and Their Limitations
Extrusion Processes and Their Limitations
 
SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )
 
High Profile Call Girls Dahisar Arpita 9907093804 Independent Escort Service ...
High Profile Call Girls Dahisar Arpita 9907093804 Independent Escort Service ...High Profile Call Girls Dahisar Arpita 9907093804 Independent Escort Service ...
High Profile Call Girls Dahisar Arpita 9907093804 Independent Escort Service ...
 
Microscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptxMicroscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptx
 
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...
 
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICSAPPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
 
HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICS
HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICSHARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICS
HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICS
 
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
 
IMPLICATIONS OF THE ABOVE HOLISTIC UNDERSTANDING OF HARMONY ON PROFESSIONAL E...
IMPLICATIONS OF THE ABOVE HOLISTIC UNDERSTANDING OF HARMONY ON PROFESSIONAL E...IMPLICATIONS OF THE ABOVE HOLISTIC UNDERSTANDING OF HARMONY ON PROFESSIONAL E...
IMPLICATIONS OF THE ABOVE HOLISTIC UNDERSTANDING OF HARMONY ON PROFESSIONAL E...
 
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLSMANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
 
Processing & Properties of Floor and Wall Tiles.pptx
Processing & Properties of Floor and Wall Tiles.pptxProcessing & Properties of Floor and Wall Tiles.pptx
Processing & Properties of Floor and Wall Tiles.pptx
 
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
 
the ladakh protest in leh ladakh 2024 sonam wangchuk.pptx
the ladakh protest in leh ladakh 2024 sonam wangchuk.pptxthe ladakh protest in leh ladakh 2024 sonam wangchuk.pptx
the ladakh protest in leh ladakh 2024 sonam wangchuk.pptx
 
Porous Ceramics seminar and technical writing
Porous Ceramics seminar and technical writingPorous Ceramics seminar and technical writing
Porous Ceramics seminar and technical writing
 
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
 
Introduction and different types of Ethernet.pptx
Introduction and different types of Ethernet.pptxIntroduction and different types of Ethernet.pptx
Introduction and different types of Ethernet.pptx
 
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
 
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
 

MANUFACTURING PROCESS OF 600 MW TURBO GENERTOR STATOR WINDING BAR

  • 1. MANUFACTURING PROCESS OF 600 MW TURBO GENERTOR STATOR WINDING BAR Presented By: Shubham Kulshreshtha(1301421092) SRMS College of engineering & technology, Bareilly BHEL HARIDWAR
  • 2. INTRODUCTION In 1956 India took a major step towards the establishment of its heavy engineering industry when BHEL, the first heavy electrical Manufacturing unit of the country was set up at Bhopal. BHEL's Heavy Electrical Equipment Plant (HEEP) was set up in technical collaboration with USSR, for the manufacturing of power plant equipment. In 1976, BHEL entered into a collaboration agreement with M/s Kraftwerk Union, AG of Germany for design, manufacturing, erection and commissioning of large size steam turbines. More than 40 percent of the country's electrical energy is generated from the power equipment supplied by BHEL, Haridwar.
  • 3. MANUFACTURING BLOCKS: . BLOCK I: ELECTRICAL MACHINE BLOCK, IS DESIGNED TO MANUFACTURING OF TURBOGENERATORS BLOCK II: FABRICATION BLOCK BLOCK III: TURBINE BLADE BLOCK BLOCK IV: COIL & INSULATION MANUFACTURING & APPARATUS & CONTROL GEAR MANUFACTURING BLOCK BLOCK V: FEEDER BLOCK AND KNOWN AS FABRICATION AND FORGE BLOCK BLOCK VI: STAMPING AND DIES MANUFACTURING BLOCK BLOCK VII: WOODWORKING BLOCK BLOCK VIII: HEAT EXCHANGER BLOCK, IS DESIGNED TO MANUFACTURE HEAT EXCHANGER UNIT FOR STEAM TURBINES.
  • 4. COIL & INSULATION MANUFACTURING SHOP (BLOCK-IV) Block-4 is a feeder block for insulating items, winding with class-B Bituminous insulation and sheet metal components for all the products of Block-1 i.e. Turbo-generators, Hydro-generators, A.C. and D.C. machines There are three BAYS in this block each bay manufactures stator bars and coils for different machines
  • 5. BAY-I: Bar winding shop: manufacturing of stator winding bars of generator BAY-II: Manufacturing of heavy duty generator stator bars with New CNC M/c BAY-III: Insulation detail shop: Manufacturing of hard insulation & machining of hares insulation part (Glass Textolite) such as packing, washer, insulation box, wedges etc Bar Shop: This shop is meant for manufacturing of stator winding coils of turbo-generator and hydro generator
  • 6. Layout of CIM, Block-IV
  • 7. Sections in Block IV 1) Assembly Section It is equipped with small size • Drilling machines • Welding sets • Hydraulic testing equipment for manufacturing turbo- generator mechanical assemblies. 2) Stator Bar Winding Section It is equipped with •Conductor cutting, insulation and transposition section. •Stack consolidation section, forming and lug brazing sections. •Insulation taping sections with automatic taping facilities in air- conditioned 3) Impregnation Section It is equipped with • Impregnation tank • Ovens for impregnation of DC pole coils.
  • 8. 4) Armature Winding, Rotor coil and Stator bar Section It is equipped with • Conductors cutting. • U- bending and terminal conductor cutting machines. • Semi-automatic winding machine. • Planking, boat pulling and diamond pulling machine. • Insulation and pressing of AC coils. 5) Insulation Section It is equipped with • Small size lathes. • Milling and radial drilling machines. • Jet cutting saw. • Electrical ovens & Hydraulic presses. •Plastic Molding Section
  • 9. Types of Generators The generator may be classified based upon the cooling system used in the generators such as: THRI, TARI, THDI, THDD, THDF, THFF, and THW Stands for type of generator • T- Turbo Generator • H- Hydro Generator Stands for the cooling media for Rotor • H- Hydrogen gas • A- Air Stands for the type of cooling for Rotor • R- Radial • D- Direct • F- Forced • I- Indirect Stands for type of cooling for Stator • I- Indirect • D- Direct • F- Forced Stands for cooling media used for Stator coil • W- Water
  • 10. It is quite difficult (rather impossible) to manufacture, handle and wind in the stator slot of generator of higher generation capacity because of its bigger size and heavy weight. That is why we make coil in two parts. One part its bottom part of coil called bottom or lower bar and other part of coil is called top bar or upper bar. Why do we call it bar?
  • 11. Set Type Upper Ordinary Upper Terminal Lower Ordinary Lower Terminal Total Bars No. of Bus Bars 500MW THDF 42 6 42 6 96 6 210MW THW 54 6 54 6 120 9 250MW THRI 48 12 48 12 120 9 No. of Bars in current products
  • 12.  Poor Resin or Micalastic insulation system In this type of insulation the bond content in the resin is 5 – 7% and insulating material is prepared with accelerator treatment. The temperature control need is not required. The insulating material is applied on job and then same is impregnated (fully dipped) in the resin. Resin System:  Rich Resin or Thermo-reactive insulation system: In this type of insulation system the bond content in resin is 35 – 37 %. The raw materials are ready to use and require preservation and working on temperature 20 – 250C. Its shelf life is one year when kept at a temperature of 200C which could be increased when kept at temperature of 50C.
  • 13. INSULATION CLASSIFICATION: Class Y • Upto 90 °C • Cotton, Silk, or Paper. Class A • Upto 105 °C • Reinforced Class-Y materials with impregnated varnish. Class E • Upto 120 °C • Cotton lamination & Paper lamination. Class B • Upto 130 °C • Inorganic material is hardened with adhesives. Class F • Upto 150 °C • Class-B materials that are upgraded with adhesives. Class H • Upto 180 °C • Made of inorganic material glued with silicone resin. Class C • > 180 °C Upto 220 °C • Made of 100% inorganic material
  • 14. Transposition Transposition means changing/shifting of position of each conductor in active core (slot) part. •After cutting the required number of conductors •The conductors are arranged on the comb in staggered manner and then bends are given to the conductors with the help of bending die at required distance. •Then the conductors are taken out from the comb and die and placed with their ends in a line and transposition is carried out. •This process is repeated for making another half of the bar which would be mirror image of the first half. •The two halves of the bar are overlapped over each other and a spacer is placed between the two halves.
  • 15. Need of transposition. 1. To reduce eddy current losses. 2. Equalize the voltage generator. 3. To minimize skin effect of ac current. Transposition is done in two ways: Half Pitch Transposition: In this transposition, the first conductor at one end of the bar becomes the last conductor at the other end of the bar. Full Pitch Transposition: In this method of transposition, the first conductor at one end of the bar becomes the last conductor in the mid of the bar and then again becomes the first conductor at the other end of the bar.
  • 16. Testing Tan δ test: •This test is carried out to ensure the healthiness of dielectric (Insulation) i.e. dense or rare & measured the capacitance loss. •Bar will act as capacitor when it is laid in the stator of the generator. •Schearing Bridge which works on the principle of wheat-stone bridge is used to find the unknown capacitance of the bar. •For good efficiency, capacitance of the bar should be high but we never approach pure capacitance. •Bar is wrapped with aluminum to make the bar conductive throughout the outer surface of the bar. The two conducting material i.e. the aluminum sheet and the conductors of the bar act as two plates of the capacitor and the insulation on the bar act as dielectric medium for the capacitor thus the capacitance is found. •Of angle of deviation due to impurity in the insulation is obtained from the formula: C4 * R4 * 10^-4 = tan δ
  • 17. H.V. Test: •Each bar is tested momentary at high voltage increased gradually to three times higher than rated voltage. •This test is also known as insulation test because this test is performed to check the insulation of the bar. •For 600 MW the working voltage of the bar is 64.5 KV & for 210 MW the working voltage of the bar is 63 KV. •In this test the bar which is already wrapped with aluminum is used. •High voltage is applied to the bar using auto-transformer and it is increased in steps according to the working voltage of the generator. If the insulation is weak the bar will puncture at the place of weaker insulation. •If any of the bar fails this test i.e. bar is punctured at any point then the bar is sent back for re-insulation and all the processes are repeated again
  • 18. 2-Pole machine with the following features: Direct cooling of stator winding with water. Direct hydrogen cooling for rotor. Micalastic insulation system. Spring mounted core housing for effective transmission of vibrations. Brushless Excitation system. Vertical hydrogen coolers 600 MW Turbo generators at a glance
  • 19. Important dimensions & weights: Heaviest lift of generator stator : 255 Tons Rotor weight : 68 Tons Overall stator dimensions [L*B*H] : 8.83m*4.lm*4.02m Rotor dimensions(Dia. and length) : 1.15m and 12.11m Total weight of turbo generator : 428 Tons Salient technical data: Rated output: 588 MVA , 600 MW Terminal voltage: 21 KV Rated stator current: 16 KA Rated frequency: 50 Hz Rated power factor: 0.85 Lag Efficiency: 98.55%