SlideShare a Scribd company logo
1 of 21
Download to read offline
MANUFACTURING PROCESS OF 500 MW TURBO GENERTOR STATOR
WINDING BAR
HARSHIT AGARWAL
08070105022
AT BHEL HARIDWAR
INTRODUCTIONINTRODUCTION
In 1956 India took a major step towards the establishment of its heavy engineering industry when BHEL, the
first heavy electrical Manufacturing unit of the country was set up at Bhopal.
BHEL's Heavy Electrical Equipment Plant (HEEP) was set up in technical collaboration with USSR, for the
manufacturing of power plantequipment.
In 1976, BHEL entered into a collaboration agreement with M/sKraftwerkUnion, AG of Germany for
design, manufacturing, erection and commissioning of large size steam turbines.
More than 40 percent of the country's electrical energy is generated from the power equipment
supplied by BHEL,Haridwar.
MANUFACTURING BLOCKS:
.
BLOCK I:ELECTRICAL MACHINE BLOCK, IS DESIGNED TO
MANUFACTURING OF TURBOGENERATORS
BLOCK II: FABRICATION BLOCK
BLOCK III: TURBINE BLADE BLOCK
BLOCK IV: COIL & INSULATION MANUFACTURING &
APPARATUS & CONTROL GEAR MANUFACTURING BLOCK
BLOCK V: FEEDER BLOCK AND KNOWN AS FABRICATION AND FORGE BLOCK
BLOCK VI: STAMPING AND DIES MANUFACTURING BLOCK
BLOCK VII: WOODWORKING BLOCK
BLOCK VIII: HEAT EXCHANGER BLOCK, IS DESIGNED TO MANUFACTURE HEAT EXCHANGER
UNIT FOR STEAM TURBINES.
COIL & INSULATION MANUFACTURING SHOP (BLOCK-IV)
Block-4 is a feeder block for insulating items, winding with class-B Bituminous insulation
and sheet metal components for all the products of Block-1 i.e. Turbo-generators, Hydro-
generators, A.C. and D.C. machines
There are three BAYS in this block each bay manufactures stator bars and coils for
different machines
BAY-I: Bar winding shop:manufacturing of stator winding bars of generator
BAY-II:Manufacturing of heavy duty generator stator bars with New CNC M/c
BAY-III: Insulation detail shop:Manufacturing of hard insulation & machining of hares insulation part
(GlassTextolite) such as packing, washer, insulation box, wedges etc
Bar Shop:This shop is meant for manufacturing of stator winding coils of turbo-generator and hydro
generator
Layout of CIM, Block-IV
Sections in Block IV
1) Assembly Section
It is equipped with small size
• Drilling machines
• Welding sets
• Hydraulic testing equipment for manufacturing turbo-
generator mechanical assemblies.
2) Stator Bar Winding Section
It is equipped with
• Conductor cutting, insulation and transposition section.
• Stack consolidation section, forming and lug brazing
sections.
• Insulation taping sections with automatic taping facilities
in air-conditioned
3) Impregnation Section
It is equipped with
• Impregnation tank
• Ovens for impregnation of DC pole coils.
4) Armature Winding, Rotor coil and Stator bar Section
It is equipped with
• Conductors cutting.
• U- bending and terminal conductor cutting machines.
• Semi-automatic winding machine.
• Planking, boat pulling and diamond pulling machine.
• Insulation and pressing of AC coils.
5) Insulation Section
It is equipped with
• Small size lathes.
• Milling and radial drilling machines.
• Jet cutting saw.
• Electrical ovens & Hydraulic presses.
• Plastic Molding Section
Types of Generators
The generator may be classified based upon the cooling system used in the generators such as:THRI, TARI,
THDI, THDD, THDF, THFF, and THW
Stands for type of
generator
• T- Turbo Generator
• H- Hydro Generator
Stands for the cooling
media for Rotor
• H- Hydrogen gas
• A- Air
Stands for the type of
cooling for Rotor
• R- Radial
• D- Direct
• F- Forced
• I- Indirect
Stands for type of cooling
for Stator
• I- Indirect
• D- Direct
• F- Forced
Stands for cooling media
used for Stator coil
• W- Water
It is quite difficult (rather impossible) to manufacture, handle and wind in the stator slot of generator of
higher generation capacity because of its bigger size and heavy weight. That is why we make coil in two
parts. One part its bottom part of coil called bottom or lower bar and other part of coil is called top bar or
upper bar.
Why do we call it bar?
Set Type Upper Ordinary Upper Terminal Lower Ordinary Lower Terminal Total Bars No. of Bus
Bars
500MW THDF 42 6 42 6 96 6
210MW THW 54 6 54 6 120 9
250MW THRI 48 12 48 12 120 9
No. of Bars in current products
Poor Resin orMicalasticinsulation system
In this type of insulation the bond content in the resin is 5 – 7% and insulating material is prepared with
accelerator treatment. The temperature control need is not required. The insulating material is applied on
job and then same is impregnated (fully dipped) in the resin.
Resin System:
Rich Resin or Thermo-reactive insulation system:
In this type of insulation system the bond content in resin is 35 – 37 %. The raw materials are ready to use
and require preservation and working on temperature 20 – 25
0
C. Its shelf life is one year when kept at a
temperature of 20
0
C which could be increased when kept at temperature of 5
0
C.
INSULATION CLASSIFICATION:
Class YClass Y
• Upto90 °C
• Cotton, Silk, or Paper.
Class AClass A
• Upto105 °C
• ReinforcedClass-Y materials with impregnated varnish.
Class EClass E
• Upto120 °C
• Cotton lamination & Paper lamination.
Class BClass B
• Upto130 °C
• Inorganic material is hardened with adhesives.
Class FClass F
• Upto150 °C
• Class-B materials that are upgraded with adhesives.
Class HClass H
• Upto180 °C
• Made of inorganic material glued with silicone resin.
Class CClass C
• > 180 °CUpto220 °C
• Made of 100% inorganic material
Transposition
Transposition means changing/shifting of position of each conductor in active core (slot) part.
• After cutting the required number of conductors
• The conductors are arranged on the comb in staggered manner and then bends are given to the
conductors with the help of bending die at required distance.
• Then the conductors are taken out from the comb and die and placed with their ends in a line and
transposition is carried out.
• This process is repeated for making another half of the bar which would be mirror image of the first half.
• The two halves of the bar are overlapped over each other and a spacer is placed between the two halves.
Need of transposition.
1. To reduce eddy current losses.
2. Equalize the voltage generator.
3. To minimize skin effect of ac current.
Transposition is done in two ways:
Half Pitch Transposition:In this transposition, the first conductor at one end of the bar becomes the last
conductor at the other end of the bar.
Full Pitch Transposition:In this method of transposition, the first conductor at one end of the bar becomes
the last conductor in the mid of the bar and then again becomes the first conductor at the other end of the
bar.
Testing
Tan δ test:
• This test is carried out to ensure the healthiness of dielectric (Insulation) i.e. dense or rare & measured the
capacitance loss.
• Bar will act as capacitor when it is laid in the stator of the generator.
• SchearingBridge which works on the principle of wheat-stone bridge is used to find the unknown capacitance of
the bar.
• For good efficiency, capacitance of the bar should be high but we never approach pure capacitance.
• Bar is wrapped with aluminum to make the bar conductive throughout the outer surface of the bar. The two
conducting material i.e. the aluminum sheet and the conductors of the bar act as two plates of the capacitor
and the insulation on the bar act as dielectric medium for the capacitor thus the capacitance is found.
• Of angle of deviation due to impurity in the insulation is obtained from the formula:C4 * R4 * 10^-4 = tan δ
H.V. Test:
• Each bar is tested momentary at high voltage increased gradually to three times higher than rated voltage.
• This test is also known as insulation test because this test is performed to check the insulation of the bar.
• For 500 MW the working voltage of the bar is 64.5 KV & for 210 MW the working voltage of the bar is 63 KV.
• In this test the bar which is already wrapped with aluminum is used.
• High voltage is applied to the bar using auto-transformer and it is increased in steps according to the working
voltage of the generator. If the insulation is weak the bar will puncture at the place of weaker insulation.
• If any of the bar fails this test i.e. bar is punctured at any point then the bar is sent back for re-insulation and all
the processes are repeated again
2-Pole machine with the following features:
Direct cooling of stator winding with water.
Direct hydrogen cooling for rotor.
Micalasticinsulation system.
Spring mounted core housing for effective transmission of vibrations.
Brushless Excitation system.
Vertical hydrogen coolers
500 MW Turbo generators at a glance
Important dimensions & weights:
Heaviest lift of generator stator : 255 Tons
Rotor weight : 68 Tons
Overall stator dimensions [L*B*H] : 8.83m*4.lm*4.02m
Rotor dimensions(Dia. and length) : 1.15m and 12.11m
Total weight of turbo generator : 428 Tons
Salient technical data:
Rated output: 588 MVA , 500 MW
Terminal voltage: 21 KV
Rated stator current: 16 KA
Rated frequency: 50 Hz
Rated power factor: 0.85 Lag
Efficiency: 98.55%
Picture Of Bars
THANK YOUTHANK YOU

More Related Content

What's hot

500 MW synchronous generator rotor construction report
500 MW synchronous generator rotor construction report500 MW synchronous generator rotor construction report
500 MW synchronous generator rotor construction reportSumit Singh
 
Manfacturing of turbo generators at BHEL
Manfacturing of turbo generators at BHELManfacturing of turbo generators at BHEL
Manfacturing of turbo generators at BHELPrabhu Raj
 
Fluxtrol AlphaForm Moldable Magnetic Flux Concentrators
Fluxtrol AlphaForm Moldable Magnetic Flux ConcentratorsFluxtrol AlphaForm Moldable Magnetic Flux Concentrators
Fluxtrol AlphaForm Moldable Magnetic Flux ConcentratorsFluxtrol Inc.
 
Gurtej bhel electrical report-at-bhel-haridwar-1
Gurtej bhel electrical report-at-bhel-haridwar-1Gurtej bhel electrical report-at-bhel-haridwar-1
Gurtej bhel electrical report-at-bhel-haridwar-1Gurtej Rai
 
Complete Rolling Mill & Equipment Manufacturer ---Hani Tech
Complete Rolling Mill & Equipment Manufacturer ---Hani TechComplete Rolling Mill & Equipment Manufacturer ---Hani Tech
Complete Rolling Mill & Equipment Manufacturer ---Hani TechKerri Zhang
 
Sharjah exhibition tube mill ppt
Sharjah exhibition tube mill pptSharjah exhibition tube mill ppt
Sharjah exhibition tube mill pptnirtube
 
Wire rod rolling mill
Wire rod rolling millWire rod rolling mill
Wire rod rolling millZhangKerri
 
Transpower Switchgear Industries, Mumbai, Electrical Products
Transpower Switchgear Industries, Mumbai, Electrical ProductsTranspower Switchgear Industries, Mumbai, Electrical Products
Transpower Switchgear Industries, Mumbai, Electrical ProductsIndiaMART InterMESH Limited
 
Auger Monster (JWC Environmental) - Modular Headworks System _ Ingles
Auger Monster (JWC Environmental) - Modular Headworks System _ InglesAuger Monster (JWC Environmental) - Modular Headworks System _ Ingles
Auger Monster (JWC Environmental) - Modular Headworks System _ InglesVibropac
 
Industrial training report
Industrial training report Industrial training report
Industrial training report Pritam Samanta
 
Smaw welding machine -adorwelding-supergen-320
Smaw welding machine -adorwelding-supergen-320Smaw welding machine -adorwelding-supergen-320
Smaw welding machine -adorwelding-supergen-320Nucleosys Tech
 
Longwall mining[1]
Longwall mining[1]Longwall mining[1]
Longwall mining[1]munashechikuni1
 
Siemens Steam Turbines 2MW-250MW
Siemens Steam Turbines 2MW-250MWSiemens Steam Turbines 2MW-250MW
Siemens Steam Turbines 2MW-250MWWim Van Den Mosselaer
 

What's hot (20)

500 MW synchronous generator rotor construction report
500 MW synchronous generator rotor construction report500 MW synchronous generator rotor construction report
500 MW synchronous generator rotor construction report
 
Manfacturing of turbo generators at BHEL
Manfacturing of turbo generators at BHELManfacturing of turbo generators at BHEL
Manfacturing of turbo generators at BHEL
 
Fluxtrol AlphaForm Moldable Magnetic Flux Concentrators
Fluxtrol AlphaForm Moldable Magnetic Flux ConcentratorsFluxtrol AlphaForm Moldable Magnetic Flux Concentrators
Fluxtrol AlphaForm Moldable Magnetic Flux Concentrators
 
Hot metal ladle
Hot metal ladleHot metal ladle
Hot metal ladle
 
Shashi
ShashiShashi
Shashi
 
Gurtej bhel electrical report-at-bhel-haridwar-1
Gurtej bhel electrical report-at-bhel-haridwar-1Gurtej bhel electrical report-at-bhel-haridwar-1
Gurtej bhel electrical report-at-bhel-haridwar-1
 
Lance carriage & guiding system
Lance carriage & guiding systemLance carriage & guiding system
Lance carriage & guiding system
 
Complete Rolling Mill & Equipment Manufacturer ---Hani Tech
Complete Rolling Mill & Equipment Manufacturer ---Hani TechComplete Rolling Mill & Equipment Manufacturer ---Hani Tech
Complete Rolling Mill & Equipment Manufacturer ---Hani Tech
 
WRM & BM
WRM & BMWRM & BM
WRM & BM
 
Sharjah exhibition tube mill ppt
Sharjah exhibition tube mill pptSharjah exhibition tube mill ppt
Sharjah exhibition tube mill ppt
 
Pneumatic Feeder Air Feeder
Pneumatic Feeder Air FeederPneumatic Feeder Air Feeder
Pneumatic Feeder Air Feeder
 
Wire rod rolling mill
Wire rod rolling millWire rod rolling mill
Wire rod rolling mill
 
Transpower Switchgear Industries, Mumbai, Electrical Products
Transpower Switchgear Industries, Mumbai, Electrical ProductsTranspower Switchgear Industries, Mumbai, Electrical Products
Transpower Switchgear Industries, Mumbai, Electrical Products
 
Auger Monster (JWC Environmental) - Modular Headworks System _ Ingles
Auger Monster (JWC Environmental) - Modular Headworks System _ InglesAuger Monster (JWC Environmental) - Modular Headworks System _ Ingles
Auger Monster (JWC Environmental) - Modular Headworks System _ Ingles
 
Industrial training report
Industrial training report Industrial training report
Industrial training report
 
Innovative Technology for Steel Melt Shop
Innovative Technology for Steel Melt ShopInnovative Technology for Steel Melt Shop
Innovative Technology for Steel Melt Shop
 
Smaw welding machine -adorwelding-supergen-320
Smaw welding machine -adorwelding-supergen-320Smaw welding machine -adorwelding-supergen-320
Smaw welding machine -adorwelding-supergen-320
 
Longwall mining[1]
Longwall mining[1]Longwall mining[1]
Longwall mining[1]
 
Rolling mills
Rolling millsRolling mills
Rolling mills
 
Siemens Steam Turbines 2MW-250MW
Siemens Steam Turbines 2MW-250MWSiemens Steam Turbines 2MW-250MW
Siemens Steam Turbines 2MW-250MW
 

Viewers also liked

Generator protection
Generator protectionGenerator protection
Generator protectionSumeet Ratnawat
 
A.C GENERATOR
A.C GENERATORA.C GENERATOR
A.C GENERATORRubby Sharma
 
F:\Ac Generator Ppt
F:\Ac Generator PptF:\Ac Generator Ppt
F:\Ac Generator PptJunrellC
 
12th CBSE Physics Project AC Generator
12th CBSE Physics Project AC Generator12th CBSE Physics Project AC Generator
12th CBSE Physics Project AC GeneratorAshwin Francis
 
Protection Of Generator
Protection Of GeneratorProtection Of Generator
Protection Of GeneratorRahuldey1991
 
Physics Investigatory Project Class 12
Physics Investigatory Project Class 12Physics Investigatory Project Class 12
Physics Investigatory Project Class 12Self-employed
 
LinkedIn SlideShare: Knowledge, Well-Presented
LinkedIn SlideShare: Knowledge, Well-PresentedLinkedIn SlideShare: Knowledge, Well-Presented
LinkedIn SlideShare: Knowledge, Well-PresentedSlideShare
 

Viewers also liked (9)

Generator protection
Generator protectionGenerator protection
Generator protection
 
A.C GENERATOR
A.C GENERATORA.C GENERATOR
A.C GENERATOR
 
F:\Ac Generator Ppt
F:\Ac Generator PptF:\Ac Generator Ppt
F:\Ac Generator Ppt
 
Generators
GeneratorsGenerators
Generators
 
dc Generator Ppt
dc Generator Pptdc Generator Ppt
dc Generator Ppt
 
12th CBSE Physics Project AC Generator
12th CBSE Physics Project AC Generator12th CBSE Physics Project AC Generator
12th CBSE Physics Project AC Generator
 
Protection Of Generator
Protection Of GeneratorProtection Of Generator
Protection Of Generator
 
Physics Investigatory Project Class 12
Physics Investigatory Project Class 12Physics Investigatory Project Class 12
Physics Investigatory Project Class 12
 
LinkedIn SlideShare: Knowledge, Well-Presented
LinkedIn SlideShare: Knowledge, Well-PresentedLinkedIn SlideShare: Knowledge, Well-Presented
LinkedIn SlideShare: Knowledge, Well-Presented
 

Similar to Manufacturing Process of 500 MW Turbo Generator Stator Winding Bar

MANUFACTURING PROCESS OF 600 MW TURBO GENERTOR STATOR WINDING BAR
MANUFACTURING PROCESS OF 600 MW TURBO GENERTOR STATOR WINDING BAR MANUFACTURING PROCESS OF 600 MW TURBO GENERTOR STATOR WINDING BAR
MANUFACTURING PROCESS OF 600 MW TURBO GENERTOR STATOR WINDING BAR Shubham Kulshreshtha
 
Manufacturing process of 500/600MW stator winding bar
Manufacturing process of 500/600MW stator winding barManufacturing process of 500/600MW stator winding bar
Manufacturing process of 500/600MW stator winding barAvinash Kumar
 
Repairing of kiln shell crack
Repairing of kiln shell crackRepairing of kiln shell crack
Repairing of kiln shell crackmkpq pasha
 
Repairing of kiln shell crack
Repairing of kiln shell crackRepairing of kiln shell crack
Repairing of kiln shell crackmkpq pasha
 
Bus Ducts or Hollow conductors
Bus Ducts or Hollow conductorsBus Ducts or Hollow conductors
Bus Ducts or Hollow conductorsAjay Meena
 
Profile of the saravana global energy ltd
Profile of the saravana global energy ltdProfile of the saravana global energy ltd
Profile of the saravana global energy ltdKumar TS
 
Presentation-GEMCO
Presentation-GEMCOPresentation-GEMCO
Presentation-GEMCODipen Shome
 
Manufacturing of Large Electrical Machine
Manufacturing of Large Electrical MachineManufacturing of Large Electrical Machine
Manufacturing of Large Electrical MachineVAIBHAV SINGH
 
REPORT (1)
REPORT (1)REPORT (1)
REPORT (1)Raj290394
 
TELK Industrial Visit Report
TELK Industrial Visit ReportTELK Industrial Visit Report
TELK Industrial Visit ReportVaisakh Shanmughan
 
PROJECT ON STUDY OF COMMUNICATION PROBLEM IN ABB DRIVE - Copy
PROJECT ON  STUDY OF COMMUNICATION PROBLEM IN ABB DRIVE - CopyPROJECT ON  STUDY OF COMMUNICATION PROBLEM IN ABB DRIVE - Copy
PROJECT ON STUDY OF COMMUNICATION PROBLEM IN ABB DRIVE - CopyAmanraj Singh Padan
 
Traction machine shed
Traction machine shedTraction machine shed
Traction machine shedNeeraj Kumar
 
Industrial training ppt bhel bhopal
Industrial training ppt bhel bhopalIndustrial training ppt bhel bhopal
Industrial training ppt bhel bhopalPRAVEENKUMARSINGH87
 
Tbea vocatinal training
Tbea vocatinal trainingTbea vocatinal training
Tbea vocatinal trainingDeep Shah
 
8-step-by-step-processes.9772018.pptx
8-step-by-step-processes.9772018.pptx8-step-by-step-processes.9772018.pptx
8-step-by-step-processes.9772018.pptxPTD QUYCOCTU
 
8 step-by-step processes of manufacturing of electrical cable
8 step-by-step processes of manufacturing of electrical cable8 step-by-step processes of manufacturing of electrical cable
8 step-by-step processes of manufacturing of electrical cableDevanshVarma1
 
Transformer ppt
Transformer pptTransformer ppt
Transformer pptRakesh Gurjar
 
Bhel vocational training
Bhel vocational trainingBhel vocational training
Bhel vocational trainingRajeev Kumar
 
Sub Station Training Program
Sub Station Training ProgramSub Station Training Program
Sub Station Training ProgramArul Balan
 

Similar to Manufacturing Process of 500 MW Turbo Generator Stator Winding Bar (20)

MANUFACTURING PROCESS OF 600 MW TURBO GENERTOR STATOR WINDING BAR
MANUFACTURING PROCESS OF 600 MW TURBO GENERTOR STATOR WINDING BAR MANUFACTURING PROCESS OF 600 MW TURBO GENERTOR STATOR WINDING BAR
MANUFACTURING PROCESS OF 600 MW TURBO GENERTOR STATOR WINDING BAR
 
Manufacturing process of 500/600MW stator winding bar
Manufacturing process of 500/600MW stator winding barManufacturing process of 500/600MW stator winding bar
Manufacturing process of 500/600MW stator winding bar
 
Repairing of kiln shell crack
Repairing of kiln shell crackRepairing of kiln shell crack
Repairing of kiln shell crack
 
Repairing of kiln shell crack
Repairing of kiln shell crackRepairing of kiln shell crack
Repairing of kiln shell crack
 
Bus Ducts or Hollow conductors
Bus Ducts or Hollow conductorsBus Ducts or Hollow conductors
Bus Ducts or Hollow conductors
 
Profile of the saravana global energy ltd
Profile of the saravana global energy ltdProfile of the saravana global energy ltd
Profile of the saravana global energy ltd
 
Presentation-GEMCO
Presentation-GEMCOPresentation-GEMCO
Presentation-GEMCO
 
Manufacturing of Large Electrical Machine
Manufacturing of Large Electrical MachineManufacturing of Large Electrical Machine
Manufacturing of Large Electrical Machine
 
Seminar report
Seminar reportSeminar report
Seminar report
 
REPORT (1)
REPORT (1)REPORT (1)
REPORT (1)
 
TELK Industrial Visit Report
TELK Industrial Visit ReportTELK Industrial Visit Report
TELK Industrial Visit Report
 
PROJECT ON STUDY OF COMMUNICATION PROBLEM IN ABB DRIVE - Copy
PROJECT ON  STUDY OF COMMUNICATION PROBLEM IN ABB DRIVE - CopyPROJECT ON  STUDY OF COMMUNICATION PROBLEM IN ABB DRIVE - Copy
PROJECT ON STUDY OF COMMUNICATION PROBLEM IN ABB DRIVE - Copy
 
Traction machine shed
Traction machine shedTraction machine shed
Traction machine shed
 
Industrial training ppt bhel bhopal
Industrial training ppt bhel bhopalIndustrial training ppt bhel bhopal
Industrial training ppt bhel bhopal
 
Tbea vocatinal training
Tbea vocatinal trainingTbea vocatinal training
Tbea vocatinal training
 
8-step-by-step-processes.9772018.pptx
8-step-by-step-processes.9772018.pptx8-step-by-step-processes.9772018.pptx
8-step-by-step-processes.9772018.pptx
 
8 step-by-step processes of manufacturing of electrical cable
8 step-by-step processes of manufacturing of electrical cable8 step-by-step processes of manufacturing of electrical cable
8 step-by-step processes of manufacturing of electrical cable
 
Transformer ppt
Transformer pptTransformer ppt
Transformer ppt
 
Bhel vocational training
Bhel vocational trainingBhel vocational training
Bhel vocational training
 
Sub Station Training Program
Sub Station Training ProgramSub Station Training Program
Sub Station Training Program
 

More from k,l polytechnic roorkee

More from k,l polytechnic roorkee (13)

33/11 KV SUBSTATION
33/11 KV SUBSTATION33/11 KV SUBSTATION
33/11 KV SUBSTATION
 
Ntpc 131113070238-phpapp02
Ntpc 131113070238-phpapp02Ntpc 131113070238-phpapp02
Ntpc 131113070238-phpapp02
 
220kV Grid Transmission Substation vt report
220kV Grid Transmission Substation vt report220kV Grid Transmission Substation vt report
220kV Grid Transmission Substation vt report
 
33 kv substation vt report
33 kv substation vt report33 kv substation vt report
33 kv substation vt report
 
Bhel turbine_shop_block-3
 Bhel turbine_shop_block-3 Bhel turbine_shop_block-3
Bhel turbine_shop_block-3
 
electronic communication
electronic communicationelectronic communication
electronic communication
 
TURBO GENERATOR
TURBO GENERATORTURBO GENERATOR
TURBO GENERATOR
 
BHEL HARIDWAR VOCATIONAL TRAINING REPORT
BHEL HARIDWAR VOCATIONAL TRAINING REPORTBHEL HARIDWAR VOCATIONAL TRAINING REPORT
BHEL HARIDWAR VOCATIONAL TRAINING REPORT
 
Summer traNING
Summer traNINGSummer traNING
Summer traNING
 
Bhelparamjeet 121106032837-phpapp02 1-
Bhelparamjeet 121106032837-phpapp02 1-Bhelparamjeet 121106032837-phpapp02 1-
Bhelparamjeet 121106032837-phpapp02 1-
 
Apresentationonturbogeneratorandexcitor 1312012333
Apresentationonturbogeneratorandexcitor 1312012333Apresentationonturbogeneratorandexcitor 1312012333
Apresentationonturbogeneratorandexcitor 1312012333
 
Acelectricalgeneratorsasope 120408063101-phpapp01 (1)
Acelectricalgeneratorsasope 120408063101-phpapp01 (1)Acelectricalgeneratorsasope 120408063101-phpapp01 (1)
Acelectricalgeneratorsasope 120408063101-phpapp01 (1)
 
Bhel training report
Bhel training reportBhel training report
Bhel training report
 

Recently uploaded

AMERICAN LANGUAGE HUB_Level2_Student'sBook_Answerkey.pdf
AMERICAN LANGUAGE HUB_Level2_Student'sBook_Answerkey.pdfAMERICAN LANGUAGE HUB_Level2_Student'sBook_Answerkey.pdf
AMERICAN LANGUAGE HUB_Level2_Student'sBook_Answerkey.pdfphamnguyenenglishnb
 
Influencing policy (training slides from Fast Track Impact)
Influencing policy (training slides from Fast Track Impact)Influencing policy (training slides from Fast Track Impact)
Influencing policy (training slides from Fast Track Impact)Mark Reed
 
Field Attribute Index Feature in Odoo 17
Field Attribute Index Feature in Odoo 17Field Attribute Index Feature in Odoo 17
Field Attribute Index Feature in Odoo 17Celine George
 
call girls in Kamla Market (DELHI) 🔝 >༒9953330565🔝 genuine Escort Service 🔝✔️✔️
call girls in Kamla Market (DELHI) 🔝 >༒9953330565🔝 genuine Escort Service 🔝✔️✔️call girls in Kamla Market (DELHI) 🔝 >༒9953330565🔝 genuine Escort Service 🔝✔️✔️
call girls in Kamla Market (DELHI) 🔝 >༒9953330565🔝 genuine Escort Service 🔝✔️✔️9953056974 Low Rate Call Girls In Saket, Delhi NCR
 
Introduction to ArtificiaI Intelligence in Higher Education
Introduction to ArtificiaI Intelligence in Higher EducationIntroduction to ArtificiaI Intelligence in Higher Education
Introduction to ArtificiaI Intelligence in Higher Educationpboyjonauth
 
How to Configure Email Server in Odoo 17
How to Configure Email Server in Odoo 17How to Configure Email Server in Odoo 17
How to Configure Email Server in Odoo 17Celine George
 
ECONOMIC CONTEXT - LONG FORM TV DRAMA - PPT
ECONOMIC CONTEXT - LONG FORM TV DRAMA - PPTECONOMIC CONTEXT - LONG FORM TV DRAMA - PPT
ECONOMIC CONTEXT - LONG FORM TV DRAMA - PPTiammrhaywood
 
HỌC TỐT TIẾNG ANH 11 THEO CHƯƠNG TRÌNH GLOBAL SUCCESS ĐÁP ÁN CHI TIẾT - CẢ NĂ...
HỌC TỐT TIẾNG ANH 11 THEO CHƯƠNG TRÌNH GLOBAL SUCCESS ĐÁP ÁN CHI TIẾT - CẢ NĂ...HỌC TỐT TIẾNG ANH 11 THEO CHƯƠNG TRÌNH GLOBAL SUCCESS ĐÁP ÁN CHI TIẾT - CẢ NĂ...
HỌC TỐT TIẾNG ANH 11 THEO CHƯƠNG TRÌNH GLOBAL SUCCESS ĐÁP ÁN CHI TIẾT - CẢ NĂ...Nguyen Thanh Tu Collection
 
ENGLISH 7_Q4_LESSON 2_ Employing a Variety of Strategies for Effective Interp...
ENGLISH 7_Q4_LESSON 2_ Employing a Variety of Strategies for Effective Interp...ENGLISH 7_Q4_LESSON 2_ Employing a Variety of Strategies for Effective Interp...
ENGLISH 7_Q4_LESSON 2_ Employing a Variety of Strategies for Effective Interp...JhezDiaz1
 
ECONOMIC CONTEXT - PAPER 1 Q3: NEWSPAPERS.pptx
ECONOMIC CONTEXT - PAPER 1 Q3: NEWSPAPERS.pptxECONOMIC CONTEXT - PAPER 1 Q3: NEWSPAPERS.pptx
ECONOMIC CONTEXT - PAPER 1 Q3: NEWSPAPERS.pptxiammrhaywood
 
Like-prefer-love -hate+verb+ing & silent letters & citizenship text.pdf
Like-prefer-love -hate+verb+ing & silent letters & citizenship text.pdfLike-prefer-love -hate+verb+ing & silent letters & citizenship text.pdf
Like-prefer-love -hate+verb+ing & silent letters & citizenship text.pdfMr Bounab Samir
 
What is Model Inheritance in Odoo 17 ERP
What is Model Inheritance in Odoo 17 ERPWhat is Model Inheritance in Odoo 17 ERP
What is Model Inheritance in Odoo 17 ERPCeline George
 
Employee wellbeing at the workplace.pptx
Employee wellbeing at the workplace.pptxEmployee wellbeing at the workplace.pptx
Employee wellbeing at the workplace.pptxNirmalaLoungPoorunde1
 
Hierarchy of management that covers different levels of management
Hierarchy of management that covers different levels of managementHierarchy of management that covers different levels of management
Hierarchy of management that covers different levels of managementmkooblal
 
EPANDING THE CONTENT OF AN OUTLINE using notes.pptx
EPANDING THE CONTENT OF AN OUTLINE using notes.pptxEPANDING THE CONTENT OF AN OUTLINE using notes.pptx
EPANDING THE CONTENT OF AN OUTLINE using notes.pptxRaymartEstabillo3
 
Types of Journalistic Writing Grade 8.pptx
Types of Journalistic Writing Grade 8.pptxTypes of Journalistic Writing Grade 8.pptx
Types of Journalistic Writing Grade 8.pptxEyham Joco
 

Recently uploaded (20)

9953330565 Low Rate Call Girls In Rohini Delhi NCR
9953330565 Low Rate Call Girls In Rohini  Delhi NCR9953330565 Low Rate Call Girls In Rohini  Delhi NCR
9953330565 Low Rate Call Girls In Rohini Delhi NCR
 
AMERICAN LANGUAGE HUB_Level2_Student'sBook_Answerkey.pdf
AMERICAN LANGUAGE HUB_Level2_Student'sBook_Answerkey.pdfAMERICAN LANGUAGE HUB_Level2_Student'sBook_Answerkey.pdf
AMERICAN LANGUAGE HUB_Level2_Student'sBook_Answerkey.pdf
 
Influencing policy (training slides from Fast Track Impact)
Influencing policy (training slides from Fast Track Impact)Influencing policy (training slides from Fast Track Impact)
Influencing policy (training slides from Fast Track Impact)
 
Field Attribute Index Feature in Odoo 17
Field Attribute Index Feature in Odoo 17Field Attribute Index Feature in Odoo 17
Field Attribute Index Feature in Odoo 17
 
call girls in Kamla Market (DELHI) 🔝 >༒9953330565🔝 genuine Escort Service 🔝✔️✔️
call girls in Kamla Market (DELHI) 🔝 >༒9953330565🔝 genuine Escort Service 🔝✔️✔️call girls in Kamla Market (DELHI) 🔝 >༒9953330565🔝 genuine Escort Service 🔝✔️✔️
call girls in Kamla Market (DELHI) 🔝 >༒9953330565🔝 genuine Escort Service 🔝✔️✔️
 
Introduction to ArtificiaI Intelligence in Higher Education
Introduction to ArtificiaI Intelligence in Higher EducationIntroduction to ArtificiaI Intelligence in Higher Education
Introduction to ArtificiaI Intelligence in Higher Education
 
How to Configure Email Server in Odoo 17
How to Configure Email Server in Odoo 17How to Configure Email Server in Odoo 17
How to Configure Email Server in Odoo 17
 
ECONOMIC CONTEXT - LONG FORM TV DRAMA - PPT
ECONOMIC CONTEXT - LONG FORM TV DRAMA - PPTECONOMIC CONTEXT - LONG FORM TV DRAMA - PPT
ECONOMIC CONTEXT - LONG FORM TV DRAMA - PPT
 
HỌC TỐT TIẾNG ANH 11 THEO CHƯƠNG TRÌNH GLOBAL SUCCESS ĐÁP ÁN CHI TIẾT - CẢ NĂ...
HỌC TỐT TIẾNG ANH 11 THEO CHƯƠNG TRÌNH GLOBAL SUCCESS ĐÁP ÁN CHI TIẾT - CẢ NĂ...HỌC TỐT TIẾNG ANH 11 THEO CHƯƠNG TRÌNH GLOBAL SUCCESS ĐÁP ÁN CHI TIẾT - CẢ NĂ...
HỌC TỐT TIẾNG ANH 11 THEO CHƯƠNG TRÌNH GLOBAL SUCCESS ĐÁP ÁN CHI TIẾT - CẢ NĂ...
 
ENGLISH 7_Q4_LESSON 2_ Employing a Variety of Strategies for Effective Interp...
ENGLISH 7_Q4_LESSON 2_ Employing a Variety of Strategies for Effective Interp...ENGLISH 7_Q4_LESSON 2_ Employing a Variety of Strategies for Effective Interp...
ENGLISH 7_Q4_LESSON 2_ Employing a Variety of Strategies for Effective Interp...
 
ECONOMIC CONTEXT - PAPER 1 Q3: NEWSPAPERS.pptx
ECONOMIC CONTEXT - PAPER 1 Q3: NEWSPAPERS.pptxECONOMIC CONTEXT - PAPER 1 Q3: NEWSPAPERS.pptx
ECONOMIC CONTEXT - PAPER 1 Q3: NEWSPAPERS.pptx
 
Rapple "Scholarly Communications and the Sustainable Development Goals"
Rapple "Scholarly Communications and the Sustainable Development Goals"Rapple "Scholarly Communications and the Sustainable Development Goals"
Rapple "Scholarly Communications and the Sustainable Development Goals"
 
Like-prefer-love -hate+verb+ing & silent letters & citizenship text.pdf
Like-prefer-love -hate+verb+ing & silent letters & citizenship text.pdfLike-prefer-love -hate+verb+ing & silent letters & citizenship text.pdf
Like-prefer-love -hate+verb+ing & silent letters & citizenship text.pdf
 
What is Model Inheritance in Odoo 17 ERP
What is Model Inheritance in Odoo 17 ERPWhat is Model Inheritance in Odoo 17 ERP
What is Model Inheritance in Odoo 17 ERP
 
Employee wellbeing at the workplace.pptx
Employee wellbeing at the workplace.pptxEmployee wellbeing at the workplace.pptx
Employee wellbeing at the workplace.pptx
 
TataKelola dan KamSiber Kecerdasan Buatan v022.pdf
TataKelola dan KamSiber Kecerdasan Buatan v022.pdfTataKelola dan KamSiber Kecerdasan Buatan v022.pdf
TataKelola dan KamSiber Kecerdasan Buatan v022.pdf
 
Hierarchy of management that covers different levels of management
Hierarchy of management that covers different levels of managementHierarchy of management that covers different levels of management
Hierarchy of management that covers different levels of management
 
EPANDING THE CONTENT OF AN OUTLINE using notes.pptx
EPANDING THE CONTENT OF AN OUTLINE using notes.pptxEPANDING THE CONTENT OF AN OUTLINE using notes.pptx
EPANDING THE CONTENT OF AN OUTLINE using notes.pptx
 
Types of Journalistic Writing Grade 8.pptx
Types of Journalistic Writing Grade 8.pptxTypes of Journalistic Writing Grade 8.pptx
Types of Journalistic Writing Grade 8.pptx
 
Raw materials used in Herbal Cosmetics.pptx
Raw materials used in Herbal Cosmetics.pptxRaw materials used in Herbal Cosmetics.pptx
Raw materials used in Herbal Cosmetics.pptx
 

Manufacturing Process of 500 MW Turbo Generator Stator Winding Bar

  • 1. MANUFACTURING PROCESS OF 500 MW TURBO GENERTOR STATOR WINDING BAR HARSHIT AGARWAL 08070105022 AT BHEL HARIDWAR
  • 2. INTRODUCTIONINTRODUCTION In 1956 India took a major step towards the establishment of its heavy engineering industry when BHEL, the first heavy electrical Manufacturing unit of the country was set up at Bhopal. BHEL's Heavy Electrical Equipment Plant (HEEP) was set up in technical collaboration with USSR, for the manufacturing of power plantequipment. In 1976, BHEL entered into a collaboration agreement with M/sKraftwerkUnion, AG of Germany for design, manufacturing, erection and commissioning of large size steam turbines. More than 40 percent of the country's electrical energy is generated from the power equipment supplied by BHEL,Haridwar.
  • 3. MANUFACTURING BLOCKS: . BLOCK I:ELECTRICAL MACHINE BLOCK, IS DESIGNED TO MANUFACTURING OF TURBOGENERATORS BLOCK II: FABRICATION BLOCK BLOCK III: TURBINE BLADE BLOCK BLOCK IV: COIL & INSULATION MANUFACTURING & APPARATUS & CONTROL GEAR MANUFACTURING BLOCK BLOCK V: FEEDER BLOCK AND KNOWN AS FABRICATION AND FORGE BLOCK BLOCK VI: STAMPING AND DIES MANUFACTURING BLOCK BLOCK VII: WOODWORKING BLOCK BLOCK VIII: HEAT EXCHANGER BLOCK, IS DESIGNED TO MANUFACTURE HEAT EXCHANGER UNIT FOR STEAM TURBINES.
  • 4. COIL & INSULATION MANUFACTURING SHOP (BLOCK-IV) Block-4 is a feeder block for insulating items, winding with class-B Bituminous insulation and sheet metal components for all the products of Block-1 i.e. Turbo-generators, Hydro- generators, A.C. and D.C. machines There are three BAYS in this block each bay manufactures stator bars and coils for different machines
  • 5. BAY-I: Bar winding shop:manufacturing of stator winding bars of generator BAY-II:Manufacturing of heavy duty generator stator bars with New CNC M/c BAY-III: Insulation detail shop:Manufacturing of hard insulation & machining of hares insulation part (GlassTextolite) such as packing, washer, insulation box, wedges etc Bar Shop:This shop is meant for manufacturing of stator winding coils of turbo-generator and hydro generator
  • 6. Layout of CIM, Block-IV
  • 7. Sections in Block IV 1) Assembly Section It is equipped with small size • Drilling machines • Welding sets • Hydraulic testing equipment for manufacturing turbo- generator mechanical assemblies. 2) Stator Bar Winding Section It is equipped with • Conductor cutting, insulation and transposition section. • Stack consolidation section, forming and lug brazing sections. • Insulation taping sections with automatic taping facilities in air-conditioned 3) Impregnation Section It is equipped with • Impregnation tank • Ovens for impregnation of DC pole coils.
  • 8. 4) Armature Winding, Rotor coil and Stator bar Section It is equipped with • Conductors cutting. • U- bending and terminal conductor cutting machines. • Semi-automatic winding machine. • Planking, boat pulling and diamond pulling machine. • Insulation and pressing of AC coils. 5) Insulation Section It is equipped with • Small size lathes. • Milling and radial drilling machines. • Jet cutting saw. • Electrical ovens & Hydraulic presses. • Plastic Molding Section
  • 9. Types of Generators The generator may be classified based upon the cooling system used in the generators such as:THRI, TARI, THDI, THDD, THDF, THFF, and THW Stands for type of generator • T- Turbo Generator • H- Hydro Generator Stands for the cooling media for Rotor • H- Hydrogen gas • A- Air Stands for the type of cooling for Rotor • R- Radial • D- Direct • F- Forced • I- Indirect Stands for type of cooling for Stator • I- Indirect • D- Direct • F- Forced Stands for cooling media used for Stator coil • W- Water
  • 10. It is quite difficult (rather impossible) to manufacture, handle and wind in the stator slot of generator of higher generation capacity because of its bigger size and heavy weight. That is why we make coil in two parts. One part its bottom part of coil called bottom or lower bar and other part of coil is called top bar or upper bar. Why do we call it bar?
  • 11. Set Type Upper Ordinary Upper Terminal Lower Ordinary Lower Terminal Total Bars No. of Bus Bars 500MW THDF 42 6 42 6 96 6 210MW THW 54 6 54 6 120 9 250MW THRI 48 12 48 12 120 9 No. of Bars in current products
  • 12. Poor Resin orMicalasticinsulation system In this type of insulation the bond content in the resin is 5 – 7% and insulating material is prepared with accelerator treatment. The temperature control need is not required. The insulating material is applied on job and then same is impregnated (fully dipped) in the resin. Resin System: Rich Resin or Thermo-reactive insulation system: In this type of insulation system the bond content in resin is 35 – 37 %. The raw materials are ready to use and require preservation and working on temperature 20 – 25 0 C. Its shelf life is one year when kept at a temperature of 20 0 C which could be increased when kept at temperature of 5 0 C.
  • 13. INSULATION CLASSIFICATION: Class YClass Y • Upto90 °C • Cotton, Silk, or Paper. Class AClass A • Upto105 °C • ReinforcedClass-Y materials with impregnated varnish. Class EClass E • Upto120 °C • Cotton lamination & Paper lamination. Class BClass B • Upto130 °C • Inorganic material is hardened with adhesives. Class FClass F • Upto150 °C • Class-B materials that are upgraded with adhesives. Class HClass H • Upto180 °C • Made of inorganic material glued with silicone resin. Class CClass C • > 180 °CUpto220 °C • Made of 100% inorganic material
  • 14. Transposition Transposition means changing/shifting of position of each conductor in active core (slot) part. • After cutting the required number of conductors • The conductors are arranged on the comb in staggered manner and then bends are given to the conductors with the help of bending die at required distance. • Then the conductors are taken out from the comb and die and placed with their ends in a line and transposition is carried out. • This process is repeated for making another half of the bar which would be mirror image of the first half. • The two halves of the bar are overlapped over each other and a spacer is placed between the two halves.
  • 15. Need of transposition. 1. To reduce eddy current losses. 2. Equalize the voltage generator. 3. To minimize skin effect of ac current. Transposition is done in two ways: Half Pitch Transposition:In this transposition, the first conductor at one end of the bar becomes the last conductor at the other end of the bar. Full Pitch Transposition:In this method of transposition, the first conductor at one end of the bar becomes the last conductor in the mid of the bar and then again becomes the first conductor at the other end of the bar.
  • 16. Testing Tan δ test: • This test is carried out to ensure the healthiness of dielectric (Insulation) i.e. dense or rare & measured the capacitance loss. • Bar will act as capacitor when it is laid in the stator of the generator. • SchearingBridge which works on the principle of wheat-stone bridge is used to find the unknown capacitance of the bar. • For good efficiency, capacitance of the bar should be high but we never approach pure capacitance. • Bar is wrapped with aluminum to make the bar conductive throughout the outer surface of the bar. The two conducting material i.e. the aluminum sheet and the conductors of the bar act as two plates of the capacitor and the insulation on the bar act as dielectric medium for the capacitor thus the capacitance is found. • Of angle of deviation due to impurity in the insulation is obtained from the formula:C4 * R4 * 10^-4 = tan δ
  • 17. H.V. Test: • Each bar is tested momentary at high voltage increased gradually to three times higher than rated voltage. • This test is also known as insulation test because this test is performed to check the insulation of the bar. • For 500 MW the working voltage of the bar is 64.5 KV & for 210 MW the working voltage of the bar is 63 KV. • In this test the bar which is already wrapped with aluminum is used. • High voltage is applied to the bar using auto-transformer and it is increased in steps according to the working voltage of the generator. If the insulation is weak the bar will puncture at the place of weaker insulation. • If any of the bar fails this test i.e. bar is punctured at any point then the bar is sent back for re-insulation and all the processes are repeated again
  • 18. 2-Pole machine with the following features: Direct cooling of stator winding with water. Direct hydrogen cooling for rotor. Micalasticinsulation system. Spring mounted core housing for effective transmission of vibrations. Brushless Excitation system. Vertical hydrogen coolers 500 MW Turbo generators at a glance
  • 19. Important dimensions & weights: Heaviest lift of generator stator : 255 Tons Rotor weight : 68 Tons Overall stator dimensions [L*B*H] : 8.83m*4.lm*4.02m Rotor dimensions(Dia. and length) : 1.15m and 12.11m Total weight of turbo generator : 428 Tons Salient technical data: Rated output: 588 MVA , 500 MW Terminal voltage: 21 KV Rated stator current: 16 KA Rated frequency: 50 Hz Rated power factor: 0.85 Lag Efficiency: 98.55%