SlideShare a Scribd company logo
1 of 12
Download to read offline
PMI-002   11/5           11/6/03                    9:20           AM       Page   12




          EA R N ED VA L U E PR O JEC T MA N                                                                                   A G EMEN T
          METH O D A N D EX TEN S IO N S
                                                                                         FRANK T. ANBARI, PHD, P M P P ro ject M a n a g emen t P ro g ra m, Dep a rtmen t o f M a n a g emen t S cien ce,
                                                                                         S ch o o l o f B u s in es s a n d P u blic M a n a g emen t, T h e G eo rg e W a s h in g to n U n iv ers ity ,
                                                                                         21 1 5 G S treet N W , W a s h in g to n , DC 2005 2 U S A




                                                                                        Introduction
                                                                                                he earned value project management method is a powerful tool that sup-
                                     ABS TRAC T
            The earned value project management
            method integrates three critical elements
            of     project     management:         scope
                                                                                        T       ports the management of project scope, time, and cost. It allows the calcu-
                                                                                                lation of cost and schedule variances and performance indices, and
                                                                                        forecasts of project cost and schedule at completion. It provides early indications
            management, cost management, and time                                       of ex pected project results b ased on project performance and highlights the pos-
            management. It req uires the periodic                                       sib le need for corrective action. A s such, it allows the project manager and proj-
            monitoring of actual ex penditures and                                      ect team to adjust project strategy and to mak e trade-offs b ased on project
            physical scope accomplishments, and
                                                                                        ob jectives, actual project performance, and trends, as well as the environment in
            allows calculation of cost and schedule
            variances, along with performance indices.                                  which the project is b eing conducted.
            It allows forecasting of project cost and                                         T he method uses cost and value as the common measures of project per-
            schedule at completion and highlights the                                   formance for b oth cost and schedule parameters. It allows the measurement of
            possib le need for corrective action.                                       cost and value in dollars, hours, work er day s, or any other similar unit.
            This paper shows the major aspects of the
                                                                                              T his paper shows the major aspects of the earned value method, presents
            earned value method and presents graph-
            ical tools for assessing project perform-                                   graphical tools that enhance its effectiveness, and provides useful simplifications
            ance trends. It provides logical ex tensions                                and logical ex tensions of this important project management method.
            and useful simplifications to enhance the
            effective application of this important                                     B a ck g round
            method in project management.
                                                                                        A b asic form of the earned value analy sis project management method ( often
            Keywords: earned value method (E V M );                                     referred to as E V A or E V M ) can b e traced b ack to industrial engineers on the fac-
            earned value management system                                              tory floor in the late 1 8 0 0 s ( F leming & K oppelman, 2 0 0 0 ; K im, 2 0 0 0 ) . A round
            (E V M S ); cost variance (C V ); schedule                                  1 9 6 7 , E V M was introduced b y agencies of the U .S . federal government as an inte-
            variance (S V ); cost performance index                                     gral part of the cost/ schedule control sy stems criteria ( C / S C S C ) and was used in
            ( C P I) ; schedule perf ormance index
                                                                                        large acq uisition programs. E V M has b een widely and successfully used in proj-
            (S P I); critical ratio (C R ); cost estimate at
            completion (E A C ); time estimate at com-                                  ects associated with the U .S . federal government, with much less reported use in
            pletion (TE A C )                                                           private industry . U se of E V M in private industry and support b y popular project
                                                                                        management software pack ages have b een limited b ut have rapidly grown in
            © 2 0 0 3 b y the P roject M anagement Institute                            recent y ears.
            V ol. 3 4 , N o. 4 , 1 2 -2 3 , IS S N 8 7 5 6 -9 7 2 8 / 0 3                      T o encourage wider use of E V M in the private sector, the U .S . federal govern-
                                                                                        ment decided to discard C / S C S C b y the end of 1 9 9 6 and turned toward a more
                                                                                        flex ib le earned value management sy stem ( E V M S ) , also called the earned value
                                                                                        project management sy stem ( E V P M S ) . P roject M anagement Institute’s A Guide to
                                                                                        th e P rojec t M a n a g em en t B ody of K n ow ledg e ( P M B O K ® Guide) ( P roject M anagement
                                                                                        Institute, 2 0 0 0 ) provided the simplified E V M terminology and formulas.


          12 • Project Management Journal December 2003
PMI-002   11/5     11/6/03           9:20   AM    Page       13




                There has been a high degree of                    • A c tual c o s t (A C ): This is the cumula-                          this work package is EV = $ 20,000 x
          EVM acceptance among current and                         tive AC spent to a given point in time                                  1.00 = $ 20,000. W ork package 1.2 has
          past users of the method. They tend                      to accomplish an activity, work pack-                                   a total budget of $ 4 0,000 and is 5 0%
          to agree that EVM can improve cost,                      age, or project and to earn the related                                 complete as of the status date.
          schedule, and technical performance                      value. This was previously called the                                   Therefore, the earned value for this
          of their projects. EVM nonusers indi-                    actual cost of work performed                                           work package is EV = $ 4 0,000 x 0.5 0 =
          cate that the method is hard to use,                     (ACW P). Figure 2 illustrates a project                                 $ 20,000. The earned value for the
          that it applies primarily to federal                     in which the planned value as of the                                    entire project is EV = $ 20,000 +
          projects, and that they do not need it                   project status date is PV = $ 5 0,000 and                               $ 20,000 = $ 4 0,000.
          (Fleming & Koppelman, 2000;                              the actual cost is AC = $ 60,000.                                             The preceding formula converts
          Kim, 2000).                                                                                                                      project accomplishments from physi-
                This paper simplifies EVM and                                                                                              cal units of measure, e.g., cubic yards
          shows its applicability to public and                    C o st                             Planned                              of concrete, linear feet of cable, percent
                                                                   ($ 0 0 0 )                       V alu e (PV )
          private sector projects, regardless of                                                                         Budget At         complete, milestones achieved, or
          siz e. The paper uses the simplified ter-                                                                     C o m p letio n    deliverables completed, to financial
                                                                     60                                                     (BAC )
          minology and provides graphical                            50                                                                    units of measure. These financial
                                                                                A c tu al C o s t
          tools, extensions, and applications of                                     (A C )                                                measurements of value can be in dol-
                                                                                                       S tatu s D ate
          EVM to enhance the use and effective-                                                                                            lars (or any other currency), labor
                                                                                                                        T im e
          ness of this important project manage-                                                                                           hours, work hours, worker days, or any
          ment method.                                                                                                                     other similar quantity that can be used
                                                                   F igure 2 . Planned Value and A c tual C o s t                          as a common measurement of the
          EVM Key Components                                                                                                               value and cost associated with project
          EVM uses the following project param-                    • E ar ned value (E V): This is the cumu-                               work. Figure 3 illustrates the above
          eters to evaluate project performance:                   lative earned value for the work com-                                   project, in which the total budget at
          • Planned value (PV): This is the time-                  pleted up to a point in time. It                                        completion is B AC = $ 100,000, the
          phased budget baseline (Figure 1). It is                 represents the amount budgeted for                                      planned value as of the status date is
          the approved budget for accomplish-                      performing the work that was accom-                                     PV = $ 5 0,000, the actual cost is AC =
          ing the activity, work package, or proj-                 plished by a given point in time. This                                  $ 60,000, and the earned value is EV =
          ect related to the schedule. It can be                   was previously called the budgeted                                      $ 4 0,000. These are the main basic enti-
          viewed as the value to be earned as a                    cost of work performed (B CW P). To                                     ties in EVM.
          function of project work accomplish-                     obtain EV for an item, multiply its
          ments up to a given point in time. This                  total budget by its completed propor-                                   P erformance Measurement
          graph of cumulative PV is often                          tion. Table 1 shows the work break-                                     Cost performance is determined by
          referred to as the S-curve (because,                     down structure (W B S) of a project with                                comparing the EV to the AC of the
          with a little imagination, it looks like                 a total budget of $ 100,000. W ork pack-                                activity, work package, or project.
          the letter S, or as an abbreviation of the               age 1.1 has a total budget of $ 20,000                                  Schedule performance is determined
          Spending-curve). This was previously                     and is 100% complete as of the status                                   by comparing the EV to the PV. This
          called the budgeted cost of work                         date. Therefore, the earned value for                                   can be accomplished by calculating the
          scheduled (B CW S).

          • B udg et at c o m p letio n (B A C ): This is                                                                           ($ 0 0 0 )
          the total budget baseline for the activi-
          ty, work package, or project (Figure 1).                                                                                        Budget       % C o m p lete       E a rn ed
                                                                       P ro jec t
          It is the highest value of PV and the last                                                                                                                         V a lue
                                                                                              P h a se1
          point on the cumulative PV curve.
                                                                                                  W o rk Pac k ag e 1 .1                    20               100                20
                                                                                                  W o rk Pac k ag e 1 .2                    40               50                 20
                                                                                                  ........
          C o st
                            Planned                                                           P h a se2
                          v alu e (PV )           Budget At
                                                 C o m p letio n                                  W o rk Pac k ag e 2 .1                    ...
                                                     (BAC )
                                                                                                  W o rk Pac k ag e 2 .2                    ...
                                                                                                  ........                                  ...
                                                                                           ........                                         ...
                                                 T im e
                                                                       T o ta l                                                            100                                 40
          F igure 1 . Planned Value and Budget
          at C o m p letio n                                       T ab le 1 . W BS , Budget, % C o m p lete, and E ar ned Value



                                                                                                                                           December 2003 Project Management Journal • 13
PMI-002   11/5        11/6/03                  9:20      AM   Page   14




                                                                                    PV R ate = $100,000 / 40                                              For the above project, SVP =
          Cost                             Planned
                                                                           = $2,500 per week                                                          -$10,000 / $50,000 = -20 %. This
          ($000)                          Value (PV)                                TV = -$10,000 / $2,500 =                                          means that the project is 20%
                                                               Budget At
                                                              Completion   -4 weeks                                                                   behind schedule.
            60                                                  (BAC)
            50
            40
                   Actual Cost                                                 TV measurement also can be per-
                      (AC)          E arned    Status date
                                 Value (E V)                               formed and reported graphically. This                                                          40




                                                                                                                                                      CV and S V ($000)
                                                              Time         is accomplished by drawing a hori-                                                             20             G ood

                                                                           zontal line from the intersection of                                                            0
                                                                                                                                                                                    SV
          Figure 3 . Planned Value, Actual Cost and                        the EV curve with the status date to the                                                       -20            Poor
                                                                                                                                                                                    CV
          Earned Value
                                                                           PV curve and reading the distance on                                                           -40
          variances, the variance percentages,                             the horizontal time axis (Fleming &
                                                                                                                                                                                         Time
          and the performance indices at the                               Koppelman, 2000), as shown in
          desired levels of the WBS. It is interest-                       Figure 4.
          ing to note that these comparisons are                               In the above formulas, 0 indicates                                     Figure 5 . CV and SV G raph
          made to the EV, rather than to the                               that performance is on target. A posi-                                         H owever, it may be appropriate
          baseline PV.                                                     tive value indicates good perform-                                         to use EV rather than PV in the
               It is important to synchronize the                          ance. A negative value indicates poor                                      denominator of this formula (J. J.
          status date for data in the analysis. This                       performance.                                                               Moder in Cleland & King, 1988). The
          can be accomplished by using the con-                                                                                                       SVP based on the earned value
          cept of accrued cost, which includes                                                                                                        (SVev% or SVPev) would be defined
          expenditures made but not yet reflect-                                                                                                      as: SVPev = SV / EV. For the above
          ed in the financial system, to accom-                            Cost                             Planned                                   project, SVPev = -$10,000 / $40,000 =
                                                                           ($000)                          Value (PV)
          plish work up to the status date.                                                                                               Budget At   -25%. This indicates that the project is
                                                                                                                                         Completion
                                                                             60                                                            (BAC)      25% behind schedule.
                                                                             50                                 SV = -10      CV = -20
          Variances                                                          40
                                                                                    Actual Cost
          The following formulas are used to cal-                                      (AC)          E arned    Status date
                                                                                                  Value (E V)
          culate the variances, generally based                                                                                      Time
                                                                                                                                                                           4
          on cumulative data, also called incep-
                                                                                                                                                                           2             G ood
                                                                                                                                                       TV (W eek s)




          tion-to-date data and project-to-date                            Figure 4 . Variances                                                                            0
          data (Figure 4, using the data from the
                                                                                                                                                                          -2              Poor
          above project):                                                  G raph ical D isplays
                                                                                                                                                                          -4        TV
               The cost variance (CV) is a meas-                           G raphs of variances over time provide
          ure of the budgetary conformance of                              valuable indicators of trends in project                                                                      Time
          actual cost of work performed: CV =                              performance and of the impact of any
          EV – AC. For the above project, CV =                             corrective actions (Figures 5 and 6).                                      Figure 6 . T V G raph
          $40,000 – $60,000 = -$20,000.
               The schedule variance (SV) is a                             Variance Percentages                                                            SVPev is consistent with the for-
          measure of the conformance of actual                             The following formulas are used to                                         mula for CVP. It points out that SV
          progress to the schedule: S V = EV – PV.                         calculate the variance percentages,                                        occurred while accomplishing EV.
          For the above project, SV = $40,000 –                            generally based on cumulative data                                         Therefore, it may be a better indicator
          $50,000 = -$10,000.                                              (Figure 4, using the data from the                                         of project schedule status, as shown
               T ime variance: The average AC per                          above project):                                                            later in the calculation of the time esti-
          time period is often called the spend                                The cost variance percent (CV% or                                      mate at completion (TEAC).
          rate or burn rate. Similarly, the average                        CVP) is a measure of the budgetary                                              In the above formulas, 0 indicates
          PV per time period can be called the                             conformance of actual cost of work                                         that performance is on target. A posi-
          planned        accomplishment        rate,                       performed: CVP = CV / EV. For the                                          tive value indicates good perform-
          planned value rate, or the PV rate. It is                        above project, CVP = -$20,000 /                                            ance. A negative value indicates poor
          defined as the baseline BAC divided by                           $40,000 = -50%, which indicates that                                       performance.
          the baseline schedule at completion                              the project is 50% over budget.
          (SAC). As a formula, PV R ate = BAC /                                The schedule variance percent                                          Performance Indices
          SAC. Thus, SV can be translated into                             (SV% or SVP) is a measure of the con-                                      The following formulas are used to cal-
          time units by dividing SV by the PV                              formance of actual progress to the                                         culate the performance indices, general-
          R ate. The result is the SV in time units                        schedule. The following formula has                                        ly based on cumulative data (Figure 4,
          or the TV. As a formula, T V = SV / PV                           been generally used to calculate it                                        using the data from the above project):
          R ate. If the above project were sched-                          (Project Management Institute, 2000):                                           The cost performance index (CPI)
          uled for forty weeks, then:                                      S VP = SV / PV.                                                            is a measure of the budgetary confor-


          14 • Project Management Journal December 2003
PMI-002   11/5    11/6/03     9:20   AM   Page   15




          mance of actual cost of work per-                                                        ures of project performance and to
          formed: CPI = EV / AC. For the above                         1.4                         quantify the “ traffic light approach.”
          project, CPI = $40,000 / $60,000 =                           1.2               Good      We can include the line that indicates




                                                        CPI and SPI
          0.67.                                                        1.0                         on target performance with the area
               The schedule performance index                          .8 0      SPI     Poor      that indicates good performance and
          (SPI) is a measure of the conformance                        .60       CPI               use the color green to indicate on tar-
          of actual progress to the schedule: SPI                                                  get and good (better than target) per-
                                                                                         Time
          = EV / PV. For the above project, SPI =                                                  formance. We can break the poor
          $40,000 / $50,000 = 0.80.                                                                performance area into two and use
                                                       Figure 7 . CPI and SPI Graph
               Performance indices can be                                                          the color yellow to indicate somewhat
          thought of as efficiency ratios. In the      SPI being close to target, or, if one of    below target performance, and the
          above formulas, 1.00 indicates that          these indices suggests poor perform-        color red to indicate poor perform-
          performance is efficient and on target.      ance, the other must be indicating          ance. It is important for the organiza-
          More than 1.00 indicates excellent,          good performance. This allows some          tion to carefully establish meaningful
          highly efficient performance, and less       trade-offs to reach the desired project     thresholds, acceptable tolerances, or
          than 1.00 indicates poor, inefficient        goals.                                      critical limits for action on project
          performance.                                      A CR of more than 1.00 indicates       performance. This helps ensure that
               The inverse of the formulas given       that the overall project performance is     when action is needed, it is highlight-
          above has also been used (Anbari,            excellent. This may result from both        ed, and when action is not needed,
          1980; Egan, 1982; Cioffi, 2002;              the CPI and SPI being better than tar-      tampering and micromanagement are
          Webster, 2002). This facilitates use of      get, or, if one of these indices is indi-   minimized.
          the indices in forecasting. Using the        cating poor performance, the other               For example, performance indices
          inverse definition, the CPI for the          must be indicating outstanding per-         and critical ratios of 1.00 or above can
          above project would be $60,000 /             formance. This allows extensive trade-      be considered green; performance
          $40,000 = 1.50, indicating that the          offs to reach the desired project goals.    indices and critical ratios equal to or
          project is running 50% over budget.               A CR of less than 1.00 indicates       greater than 0.80, but less than 1.00,
          Completion of the project would be           that the overall project performance is     can be considered yellow; and per-
          forecasted at $150,000, if performance       poor. This may result from both the         formance indices below 0.80 can be
          continues at this rate. Similarly, the SPI   CPI and SPI being worse than target,        considered red. In this paper, a black
          would be $50,000 / $40,000 = 1.25,           or, if one of these indices suggests        and white chart depicting this concept
          indicating the project is running 25%        good performance, the other must be         is shown in Figure 9, and is called the
          behind schedule. The project would be        indicating extremely poor perform-          target performance chart. It can be pro-
          forecasted to take 25% longer than the       ance. This limits the use of effective      duced in color and may also be nick-
          original schedule, with completion at        trade-offs, and highlights significant      named the rainbow chart.
          1.25 x 40 weeks = 50 weeks, if per-          difficulty in attempting to reach the            O ther colors can also be added.
          formance continues at this rate. These       desired project goals.                      For example, orange or amber can be
          forecasts are discussed in more detail            A graph of the critical ratio over     used between yellow and red, or in the
          in the forecasting section of this paper.    time provides a quick indicator of          yellow area to indicate that the item in
               Graphs of performance indices           trends in the overall project perform-      trouble has been previously reviewed.
          over time provide valuable indicators        ance, and of the impact of any correc-      Blue can be used to indicate the super-
          of trends in project performance and         tive actions. These graphs may be very      stars— items with performance indices
          the impact of any corrective actions.        effective in project reviews (Figure 8).    above 1.20, for example (Figure 9).
          These graphs can be very effective in                                                    Some may say that such superstar
          project reviews (Figure 7).                                                              items must have had inflated baseline
                                                                                                   budgets and schedules. However, there
                                                                      1.4
          The Critical Ratio                                                            Good
                                                                                                   may be important lessons to be
                                                                      1.2
          The critical ratio (CR) is the product of                                                learned from these items in terms of
                                                                      1.0
                                                       CR




          CPI and SPI (Anbari, 2001; L ewis,                                                       estimating, budgeting, performance
                                                                      .8 0               Poor
          2001). It can also be called the cost-                                                   management, and cost control.
                                                                      .60
          schedule index (CSI) (Barr, 1996;                                     CR                 Reallocation       of     organizational
          Meredith & Mantel, 2000). It is used as                                       Time       resources may be another outcome
          an indicator of the overall project                                                      from such analyses (L ewis, 2001).
          health: CR = CPI x SPI. For the above        Figure 8 . CR Graph                              An activity, work package, or proj-
          project, CR = 0.67 x 0.80 = 0.53.                                                        ect should be carefully reviewed when
               A CR of 1.00 indicates that the         Q uantifying the Traffic L ight A pproach   it enters the yellow zone, with the
          overall project performance is on tar-       Graphs of CPI, SPI, and CR can be           intent of finding the root cause(s) of
          get. This may result from both CPI and       used to further highlight these meas-       performance or planning problems


                                                                                                   December 2003 Project Management Journal • 15
PMI-002   11/5                     11/6/03   9:20   AM      Page       16




          and eliminating them. When an item                                affecting the activity, work package, or    ciencies observed to date will prevail to
          in the red zone is reviewed, this should                          project, a new ETC needs to be devel-       completion, the EAC3 is the sum of
          generally be a status report on                                   oped; EAC1 is the sum of the cumula-        the cumulative AC plus the original
          action(s) taken or not taken when that                            tive AC plus the ETC. As a formula,         budget for the remaining work (BAC –
          item was in the yellow zone. When an                              EAC1 = AC + ETC. For the example            EV), modified by a performance factor,
          item enters the blue zone, it also                                project used in this paper, EAC1 =          which is usually the cumulative CPI.
          would be appropriate to review it, to                             $60,000 + ETC. This applies where           As a formula, EAC3 = AC + (BAC – EV)
          obtain information on the root                                    ETC is developed for the remaining          / CPI. For the above project:
          cause(s) of the super performance, and                            work. EAC1 may also be called the                EAC3 = $60,000 + ($100,000 –
          incorporate the lessons learned into                              revised cost estimate (RCE), latest         $40,000) / 0.67
          future work.                                                      revised estimate (LRE), or current                      = $60,000 + $60,000 / 0.67
                                                                            working estimate (CWE).                                 = $60,000 + $90,000
                                                                                 Using the above assumption, the                    = $150,000
                                                                            ETC for the remainder of the activity,                The above formula can be
                             1.4
                                                                            work package, or project usually is         simplified as follows:
          CPI, SPI, and CR




                                                         Super Stars
                             1.2
                                                            G ood           developed using various cost estimat-            EAC3 = AC + (BAC – EV) / CPI
                             1.0
                                                           Caution          ing methods. Because the work already                   = AC + BAC / CPI – EV / CPI
                             .80
                                              SPI                           is in progress, a detailed, bottom-up                   = AC + BAC / CPI – AC
                             .60              CPI           Poor
                                              CR
                                                                            cost estimate for the remaining work is                 = BAC / CPI
                                                                 Time       common in this case.                             Thus:
                                                                                 When current analysis shows that                 EAC3 = BAC / CPI
          Figure 9 . Target Performance Chart                               past performance is not a good predic-           The definition of EAC3 can there-
                                                                            tor of future performance, that prob-       fore be simplified to equal the original
          Forecasting                                                       lems or opportunities which affected        BAC divided by the CPI. For the above
          Project management is primarily con-                              performance in the past will not occur      project, EAC3 = $100,000 / 0.67 =
          cerned with decisions affecting the                               in the future, and that future perform-     $150,000. EAC3 may also be called the
          future. Therefore, forecasting and pre-                           ance will parallel the original plan, the   statistical estimate at completion
          diction are extremely important                                   EAC2 is the sum of the cumulative AC        (EACstat), the mathematical estimate at
          aspects of project management. EVM is                             plus the original budget for the            completion (EACmath), or simply the
          particularly useful in forecasting the                            remaining work (BAC – EV): EAC2 =           cost at completion (CAC).
          cost and time of the project at comple-                           AC + BAC – EV. For the above project,            Using the above assumption, the
          tion, based on actual performance up                              EAC2 = $60,000 + $100,000 – $40,000         estimated cost to complete the remain-
          to any given point in the project.                                = $120,000.                                 der of the activity, work package, or
                                                                                 The above formula can be simpli-       project is the original budget for the
          Forecasting of Cost at Completion                                 fied as follows:                            remaining work divided by the CPI. As
          The EAC may also be called cost esti-                                  EAC2 = AC + BAC – EV                   a formula, ETC = (BAC – EV) / CPI.
          mate at completion (CEAC). The esti-                                          = BAC + (AC – EV)               This may be called statistical estimate
          mated cost to complete the remainder                                          = BAC – (EV – AC)               to complete (ETCstat) or the mathe-
          of the project is usually called the esti-                                    = BAC – CV                      matical      estimate   to    complete
          mate to complete (ETC). Both can be                                    Thus:                                  (ETCmath).
          developed using various cost estimat-                                         EAC2 = BAC – CV                      A graph of the EAC over time
          ing methods or calculated mathemati-                                   The definition of EAC2 can there-      provides a valuable indicator of
          cally using EVM.                                                  fore be simplified to equal the original    trends in project cost performance
               EACs may differ based on the                                 baseline BAC minus the CV. For the          and the impact of any corrective
          assumptions made about future per-                                above project, EAC2 = $100,000 – (-         actions. This graph can be particular-
          formance. The PMBOK® Guide (Project                               $20,000) = $100,000 + $20,000 =             ly effective in project reviews. Figure
          Management Institute, 2000) provides                              $120,000.                                   10 shows a graph of EAC for the
          three such estimates, based on three                                   Using the above assumption, the        example project used in this paper,
          different assumptions. In this section,                           ETC for the remainder of the activity,      using the above assumption.
          these estimates are reviewed, simpli-                             work package, or project is the original
          fied and enhanced. They are given a                               budget for the remaining work (BAC –        Additional Forecasts of Cost
          sequential subscript to differentiate                             EV).                                        at Completion
          among them.                                                            When current analysis shows that       Other assumptions can be made about
               When current analysis shows that                             past performance is a good predictor        future performance and may result in
          the assumptions underlying the origi-                             of future performance, that perform-        different estimates at completion. In
          nal estimate are flawed, or no longer                             ance to date will continue into the         this section, other assumptions and
          applicable due to changed conditions                              future, and that efficiencies or ineffi-    the resulting EACs are presented. They


          16 • Project Management Journal December 2003
PMI-002   11/5               11/6/03   9:20   AM   Page    17




                                                                it acknowledges that cost management        higher than the original baseline BAC.
                       160                                      and schedule management are insepa-         As a formula, EAC6 > > BAC. This esti-
                                        EAC
                       140                                      rable (Kerzner, 2001). As examples:         mate is generally not quantified, but is
                                                   Poor         Project schedules can be crashed at an      referred to by project team members
          EAC ($000)




                       120
                                                          BAC
                       100                                      additional cost, or less skilled            with statements such as: “If you think
                       80                          Good         resources may be used on the project,       this is bad, wait till you see the next
                       60                                       which may reduce the cost and possi-        report! Y ou ain’t seen nothing yet! ” or
                                                                bly extend the duration.                    “The cost is going sky high. If this
                                                    Time             The assumption implied by the          project ever finishes, it would be a
                                                                above formula is that if the activity,      miracle! ”
          Figure 10. EAC Graph
                                                                work package, or project were behind             This case may result from delaying
          are given a continuing sequential sub-                schedule, additional cost would be          corrective action and believing for too
          script to differentiate among them.                   incurred to bring the project back on       long that the actual cost at completion
               In some organizations, it is com-                schedule, through the use of overtime,      somehow would end up close to the
          mon to state that the activity, work                  additional resources, expediting ship-      original baseline BAC, regardless of
          package, or project will meet the orig-               ments, and similar actions. On the          prior poor performance. Higher costs,
          inal targets upon completion, regard-                 other hand, if the activity, work pack-     lower levels of accomplishment, and
          less of prior performance. This                       age, or project were ahead of schedule,     inefficient spending patterns become
          frequently occurs early in the project                opportunities for significant cost sav-     practically irreversible and the project’s
          when prior performance has been                       ings may be pursued, although they          fate is sealed. Statistics of challenged
          poor. The EAC4 would be the original                  may require more time as a result of        and failed projects testify that this case
          baseline BAC. As a formula, EAC4 =                    using resources that are fewer in num-      is much more common than we would
          BAC. Statements such as the following                 ber, less experienced, and/or less          like to believe.
          may be heard: “We had some mobi-                      skilled. Additional time may also be
          lization problems, but we took care of                required to find better prices for equip-                           EACs
          them. We expect the project to finish                 ment and material, negotiate better                       160
          on schedule and on budget.” or “The                   contract terms, use more economical                       140
                                                                                                            EACs ($000)


          original specs were unclear. So we                    shipping methods, or take similar                         120                  Poor
                                                                                                                                                      BAC
          took additional time to clarify them.                 actions. This formula may provide a                       100

          We are planning to meet project tar-                  better indication of estimated cost at                    80                   Good
          gets at this time.”                                   completion, when adherence to a                           60
               The above statements should be                   schedule is critical to the organization.
                                                                                                                                                 Time
          challenged firmly, with a response                         Using the earlier definition of CR
          such as: “What we hear you say is that                = CPI x SPI, and further defining EAC5
                                                                                                            Figure 11. EACs Graph
          future performance will be so much                    or EACs as the EAC adjusted for sched-
          better than the original plan and will                ule performance, the above formula               The Standish Group conducted
          make up for prior cost overruns (and                  can be restated as follows: EAC5 =          surveys and interviews to explore what
          delays). So far, we have not performed                EACs = BAC / CR. For the above proj-        causes information technology (IT)
          to the original plan and would like to                ect, EAC5 = EACs = $100,000 / 0.53 =        software development projects to be
          know how this superior performance                    $187,500.                                   challenged and why these projects fail.
          will be achieved.”                                         Using the above assumption, the        These studies classified projects into
               EAC 4      is   rarely  achieved.                ETC for the remainder of the activity,      three types:
          Unmanaged projects do not fix them-                   work package, or project is the original         Successful: The project is complet-
          selves. They only tend to overrun                     budget for the remaining work divided       ed on time and on budget, with all fea-
          their budgets, fall behind their sched-               by the CR: (BAC – EV) / CR. This may        tures and functions as originally
          ules, and often miss other scope and                  be called the ETC adjusted for schedule     specified;
          quality targets.                                      performance (ETCs). A graph of the               Challenged: The project is com-
               Heinze (1996) provides the follow-               EACs over time provides a valuable          pleted and operational but is over
          ing additional formula for calculating                indicator of trends in project cost per-    budget, beyond the time estimate, and
          the EAC: EAC = BAC / CPI x SPI.                       formance and the impact of any cor-         offers fewer features and functions
          Fleming & Koppelman (2000) provide                    rective actions. This graph can be very     than initially specified;
          a similar formula and support it by                   effective in project reviews. Figure 11          Failed: The project is canceled
          indicating that there is a human ten-                 shows a graph of EACs for the example       before completion.
          dency to get back on schedule, even if                project used in this paper, using the            The Standish Group study con-
          that requires more resources for the                  above assumption.                           ducted in 1994 and published in 1995
          same work. The above formula may be                        A case that is not often mentioned     (The Standish Group, 1995) had a
          mathematically questionable. However,                 occurs when the EAC6 is substantially       total sample of 365 respondents repre-


                                                                                                            December 2003 Project Management Journal • 17
PMI-002   11/5          11/6/03      9:20   AM     Page      18




          senting 8,380 projects. The results of                       A graph of the VAC over time pro-     weeks, meaning that the cumulative AT
          that research showed that 16% of IT                     vides a valuable indicator of trends in    is 20 weeks. Therefore: TEAC1 = 20 +
          projects were successful, 53% were                      project cost performance and the           TETC weeks. In this case, TETC needs
          challenged,     and    31%     failed.                  impact of any corrective actions. This     to be developed for the remaining
          Comparisons to subsequent studies                       graph can be effective in project          work. TEAC1 may also be called the
          are shown in Table 2 (The Standish                      reviews. Figure 12 shows a VAC graph       revised schedule or current schedule.
          Group, 1999):                                           for the example project used in this            When current analysis shows that
                                                                  paper, using the above assumption.         past schedule performance is not a
                                                                                                             good predictor of future schedule per-
           Y ear of Study   Successful   Challenged   F ailed
                                                                  Completion Time Forecasting                formance, that problems or opportuni-
               19 9 4         16%           53 %      3 1%
                                                                  EVM has not been widely used to esti-      ties    which      affected    schedule
               19 9 6         27 %          33%       40%
                                                                  mate the total time at completion,         performance in the past will not occur
               19 9 8         26%           46%       28%
                                                                  total project duration, or schedule for    in the future, and that future schedule
          Table 2. Project Resolution H Istory                    an activity, work package, or project      performance will parallel the original
                                                                  based on actual performance up to a        plan, TEAC2 is the sum of the cumula-
               The Treasury Board of Canada                       given point in the project. However,       tive AT plus the original scheduled
          Secretariat (2000–2002) supported                       using assumptions and logic similar to     time for the remaining work. This can
          findings of The Standish Group, indi-                   those discussed above, the project’s       be simplified to the original baseline
          cated similarities to results of reviews                time estimate at completion (TEAC)         SAC minus the TV (Fleming &
          of Canadian government IT projects                      and time variance at completion            Koppelman, 2000). As a formula,
          and presented a framework for the                       (TVAC) can be calculated based on the      TEAC2 = SAC – TV. For the above proj-
          management of these projects.                           baseline schedule at completion (SAC)      ect, TEAC2 = 40 – (-4) = 40 + 4 = 44
               A survey of IT projects by Sauer                   and actual performance up to any           weeks.
          and Cuthbertson (2002) covered vari-                    given point in the project (Anbari,             The above is the total estimated
          ous industry sectors and government                     2001 and 2002).                            schedule duration that would have
          in the United Kingdom, and had a                                                                   been obtained using the critical path
          usable sample size of 565 projects. It                                                             method (CPM) or the program evalua-
          showed that 5% of all projects were                                  40
                                                                                                             tion and review technique (PERT), if
          reported to have been abandoned                                      20                  Good      the schedule slippage of four weeks
                                                                  VAC ($000)




          prior to or during implementation,                                   0                             were on the critical path.
          55% of projects exceeded budget, 27%                                 -20
                                                                                                                  When current analysis shows that
                                                                                                   Poor
          came in exactly on budget, and 8%                                    -40
                                                                                                             past schedule performance is a good
          came in below budget. Performance,                                             VAC                 predictor of future schedule perform-
          measured by attainment of initially                                                      Time      ance, that performance to date will
          agreed upon specifications, averaged                                                               continue into the future, and that
          above 80%. Across the whole sample,                     Figure 12. VAC Graph                       schedule efficiencies, or inefficiencies,
          56% delivered 90% to 99% of the                                                                    observed to date will prevail to com-
          specifications, approximately 20% of                         In this section, various time esti-   pletion, TEAC3 is the sum of the
          projects delivered less than 80% of the                 mates are presented and given a            cumulative AT plus the original sched-
          specifications, and a sprinkling of proj-               sequential subscript to differentiate      uled time for the remaining work,
          ects exceeded the specifications.                       among them, following the same pat-        modified by the cumulative SPI. This
                                                                  tern used previously for the cost esti-    can be simplified to the original base-
          Variance at Completion:                                 mate at completion.                        line SAC divided by the SPI. As a for-
          The variance at completion (VAC)                             When current analysis shows that      mula, TEAC3 = SAC / SPI. For the
          gives an indication of the estimated                    assumptions underlying the original        above project, TEAC3 = 40 / 0.80 = 50
          cost underrun or overrun at the com-                    time estimate were flawed or no longer     weeks.
          pletion of the project. As a formula,                   applicable due to changed conditions            The above example indicates that
          VAC = BAC – EAC. For the above proj-                    affecting the activity, work package, or   the project is estimated to be complet-
          ect, using BAC = 100,000 and EAC3 =                     project, a new schedule, duration esti-    ed 25% behind schedule: (40 weeks –
          150,000, VAC = 100,000 – 150,000 =                      mate, or time estimate to complete         50 weeks) / 40 weeks = -10 weeks / 40
          -50,000.                                                (TETC) needs to be developed, and the      weeks = -0.25 = -25%.
               In the above equation, 0 indi-                     TEAC1 is the sum of the cumulative AT           A graph of the TEAC over time
          cates that the project is forecasted to                 plus the TETC. As a formula, TEAC1 =       provides a valuable indicator of
          be completed on budget. A positive                      AT + TETC.                                 trends in project schedule perform-
          value indicates a forecasted under-                          The example project used in this      ance and the impact of any corrective
          run. A negative value indicates a                       paper has an original baseline SAC of      actions. This graph can be effective in
          forecasted overrun.                                     40 weeks, and its status date is 20        project reviews. Figure 13 shows a


          18 • Project Management Journal December 2003
PMI-002   11/5                 11/6/03   9:20    AM   Page    19




          graph of TEAC, for the example proj-                     prices for equipment and material,          of prior poor performance. Longer
          ect used in this paper, using the above                  negotiate better contract terms using       durations, lower levels of accomplish-
          assumption.                                              more economical shipping methods,           ment, and inefficient schedule achieve-
                                                                   and similar actions. On the other           ment patterns become practically
                                                                   hand, if an activity, work package, or      irreversible, and the project’s fate is
                          52              TEAC                     project were running below budget,          sealed. Statistics of challenged and
                          48                                       opportunities for reducing completion       failed projects testify that this case is
           TEAC (Weeks)




                          44                          Poor         time, reducing cycle time, and expedit-     much more common than we would
                                                             SAC
                          40                                       ing time to market may be pursued,          like to believe, as previously discussed
                          36                          Good         although they may incur more cost.          in the development of EAC6.
                          32                                       This may be accomplished through the
                                                                   use of overtime, additional resources,
                                                       Time                                                                     70      TEACc
                                                                   and expediting shipments.
                                                                                                                                60
                                                                         D efining TEAC5 or TEACc as the




                                                                                                                TEACc (Weeks)
          Figure 13. TEAC Graph
                                                                                                                                50               Poor
                                                                   TEAC adjusted for cost performance,                                                  SAC
                                                                                                                                40
               In some organizations, it is com-                   the following formula would reflect
                                                                                                                                30               Good
          mon to state that the activity, work                     the above assumption: TEAC5 =
                                                                                                                                20
          package, or project will be on schedule                  TEACc = SAC / CR. For the above proj-
          upon completion, regardless of prior                     ect, TEAC5 = TEACc = 40 / 0.53 = 75                                              Time
          performance. This frequently occurs                      weeks. This formula may provide a bet-
          early in the project, when prior sched-                  ter indication of estimated time at         Figure 14. TEACc Graph
          ule performance has been poor. The                       completion, when adherence to budg-
          TEAC4 would be the original baseline                     et is critical to the organization. TEAC5        Time variance at completion: The
          SAC. As a formula, TEAC4 = SAC.                          may also be called the time estimate at     TVAC gives an indication of the esti-
          Statements similar to those mentioned                    completion adjusted for cost perform-       mated amount of time that the project
          earlier in the cost discussion may be                    ance (TEACc).                               will be completed ahead or behind
          heard. In some disciplines, such as                            A graph of TEACc over time pro-       schedule: TVAC = SAC – TEAC. For the
          software development, it is common                       vides a valuable indicator of trends in     above project, using SAC = 40 and
          to conclude these statements saying,                     project schedule performance and the        TEAC3 = 50: TVAC = 40 – 50 = -10
          “We’ll catch up during the testing                       impact of any corrective actions. This      weeks.
          phase!” Several modifiers to the word                    graph can be very effective in project           In the above equation, 0 indicates
          “test” have been developed, which may                    reviews. Figure 14 shows a graph of         that the project is expected to be com-
          increase the likelihood of catching up.                  TEACc, for the example project used         pleted on schedule. A positive value
          They include: alpha test, beta test, user                in this paper, using the above              indicates that the project is expected to
          test, stress test, acceptance test, and                  assumption.                                 be completed ahead of schedule. A
          parallel test. Such statements should                          A case that is not mentioned          negative value indicates that the proj-
          be challenged firmly, with a response                    often occurs when the TEAC6 is sub-         ect is expected to be completed behind
          similar to that mentioned earlier in the                 stantially higher than the original         schedule.
          cost discussion.                                         baseline SAC. As a formula, TEAC6 > >            A graph of TVAC over time pro-
               TEAC4 is rarely achieved. Again,                    SAC. This estimate is generally not         vides a valuable indicator of trends
          unmanaged projects do not fix them-                      quantified, but is referred to by proj-     in project schedule performance and
          selves. They only tend to fall behind                    ect team members with statements            the impact of any corrective actions.
          their schedules, overrun their budgets,                  similar to those mentioned earlier in       This graph can be effective in project
          and often miss other scope and quality                   the cost discussion. At times, this case    reviews. Figure 15 shows a graph of
          targets.                                                 occurs in the later phases of a project,    TVAC, for the example project used
               Recalling that cost performance                     when team members have no other             in this paper, using the above
          and schedule performance are insepa-                     planned assignments, and the organi-        assumption.
          rable, the assumption can be made                        zation is “right sizing.” Q uality prob-
          that if an activity, work package, or                    lems       become        apparent,    and   CPM, PERT, and EVM
          project were running over budget,                        additional time is requested to fix var-    As mentioned above in the develop-
          additional time may be needed to                         ious problems. Sometimes a lot of           ment of TEAC2, an underlying
          bring the project back on budget. This                   additional time is needed.                  assumption of the CPM and the PERT
          may be accomplished by reducing                                Again, this case may result from      is that future performance will parallel
          resources applied to the project, using                  delaying corrective action and believ-      the original plan, unless changes are
          fewer paid resources, many of which                      ing for too long that the project would     made to the original plan time, logic,
          are less experienced and less skilled,                   somehow be completed close to the           or cost.
          taking additional time to find better                    original baseline schedule, regardless           The example project used in this


                                                                                                               December 2003 Project Management Journal • 19
PMI-002   11/5                 11/6/03   9:20   AM   Page    20




          paper has an original baseline SAC of                   meetings. Both mathematical forecasts           % Complete = $40,000 / $100,000
          40 weeks. With a status date of 20                      and subjective forecasts would be                             = 0.40 = 40%
          weeks, TV = -4 weeks. If TV represented                 included in project performance                 % Spent = $60,000 / $100,000
          a schedule slippage of 4 weeks on the                   reports. This effort highlights perform-                 = 0.60 = 60%
          critical path, CPM and PERT would esti-                 ance deviations for work area man-              CPI = % Complete / % Spent
          mate a completion time of 44 weeks.                     agers, encourages them to consider                   = 40 / 60 = 0.67
          This is the same as: TEAC2 = SAC – TV                   appropriate, timely actions, and incor-         The above allows a further
          = 40 – (-4) = 40 + 4 = 44 weeks.                        porates their close, detailed knowledge         simplification
                                                                  of performance in their areas, which            (Slemaker, 1985) of the EAC3:
                                                                  may not be evident from the reported                 EAC3 = BAC / CPI
                                                                  values. At a minimum, this effort may                       = BAC / (% Complete /
                         10                                       help avoid surprises and arguments                           % Spent)
          TVAC (Weeks)




                         5                           Good
                                                                  over the numbers during project                             = (BAC x % Spent) /
                         0                                        review meetings.                                            % Complete
                         -5                          Poor              Forecasting in project manage-                         = AC / % Complete
                         -10               TVAC                   ment may well be a self-defeating               Thus: EAC3 = AC / % Complete
                                                      Time        prophecy, and that may be good for              The definition of EAC3 can be fur-
                                                                  the organization. Large deviations usu-    ther simplified to the AC divided by
                                                                  ally attract management’s attention        the percent complete. For the above
          Figure 15. TVAC Graph
                                                                  and result in corrective action. Small     project, EAC3 = $60,000 / 0.40 =
               CPM and PERT initially assume                      deviations are usually left alone. By      $150,000.
          that problems or opportunities that                     quantifying and highlighting such               Similarly, the TEAC3 can be sim-
          affected performance in the past will                   deviations, EVM helps focus manage-        plified to: TEAC3 = AT / % Complete.
          not occur in the future and that past                   ment’s interest on projects or work        The example project used in this paper
          performance is not a good predictor of                  packages that need the most attention.     has an original baseline SAC of 40
          future performance.                                     As a result, EVM supports effective        weeks, and the status date is 20 weeks,
               The assumption generally associ-                   management of projects and work            which means that the cumulative AT is
          ated with EVM is that past perform-                     packages collectively and enhances         20 weeks. Therefore: TEAC3 = 20 / 0.40
          ance is a good predictor of future                      management of the enterprise’s project     = 50 weeks.
          performance, that performance to date                   portfolio (Anbari, 1983). Forecasting           Similarly, the following is derived
          will continue into the future, and that                 using these techniques provides a uni-     (Anbari, 1980):
          efficiencies or inefficiencies observed                 form approach to project reviews,                    CPI = % Complete / % Spent
          to date will prevail to completion.                     building confidence in the project out-                  = (Actual Production /
          Therefore, the EAC3 is generally asso-                  come as time progresses. Changing                           Total Scope) /
          ciated with EVM. Similarly, the TEAC3                   project evaluation methods during the                       (Actual Cost /
          can be associated with EVM.                             project duration can result in no                           Total Budget)
          Therefore: TEAC3 = SAC / SPI = 40 /                     meaningful data for decision-making.                     = (Actual Production /
          0.80 = 50 weeks.                                                                                                    Total Scope) x
               Which of the above forecasts will                  Further Ex tensions, Issues                                 (Total Budget /
          materialize depends greatly on deci-                    and Applications                                            Actual Cost)
          sions and actions taken by the project                                                                           = (Total Budget /
          manager, the project team, and the                      Extensions                                                  Total Scope) x
          organization. Some like to add luck to                  Using the above definitions, the fol-                       (Actual Production /
          the factors affecting project outcomes.                 lowing is derived (Slemaker, 1985):                         Actual Cost)
          Others observe that good luck tends to                       % Complete = EV / BAC                               = (Total Budget /
          be directly associated with better plan-                     % Spent = AC / BAC                                     Total Scope) /
          ning and better decisions.                                   Taking the ratio of the above two                      (Actual Cost /
                                                                       formulas                                               Actual Production)
          Project Forecasting                                          (Anbari, 1980):                                     = Planned Unit Cost /
          It is advisable to ask work package                          % Complete / % Spent                                   Actual Unit Cost
          managers, project leaders, and func-                         = (EV / BAC) / (AC / BAC)                  Thus: CPI = Planned Unit Cost /
          tional managers to review cost and                           = EV / AC                                              Actual Unit Cost
          schedule mathematical forecasts and                          = CPI                                      The additional formulas devel-
          to provide their own subjective fore-                        Thus:                                 oped in this section provide a more
          casts for their own work areas in                            CPI = % Complete / % Spent            intuitive understanding of CPI based
          advance of issuing project performance                       For the example project used in       on information readily available in
          reports and conducting project review                   this paper:                                many organizations. The first formula


          20 • Project Management Journal December 2003
PMI-002   11/5    11/6/03    9:20   AM   Page   21




          for CPI uses information widely            ble, collecting 50% of the contract         centage of the value associated with
          known in project environments, and         price for each of these items.              the milestone based on subjective esti-
          the second formula for CPI uses infor-          The 0/100 rule can also be used.       mates. When the predefined, tangible
          mation widely known in production          This rule specifies that the value is       criteria for the milestone are met, the
          environments:                              earned only when the item is complet-       balance of the value associated with
                  CPI = % Complete / % Spent         ed and is usually used in work pack-        the milestone is earned (Fleming &
                  CPI = Planned Unit Cost /          ages having a short duration (Kerzner,      Koppelman, 2000). These approaches
          Actual Unit Cost                           2001). This rule can also be called the     may help alleviate the “95% complete
                                                     weighted milestone method, where the        and stays there forever” syndrome.
          Issues in the Determination of             value is earned only when the mile-              For level of effort items such as
          Percent Complete                           stone is physically completed, and one      project management, customer sup-
          Determination of the percent complete      or more milestones are planned in           port, and other support work during a
          or proportion complete of an activity,     each performance-reporting period           given period of time in a project, the
          work package, or project is a necessary    (Fleming & Koppelman, 2000).                effort itself is the end product.
          but challenging task in many organiza-     Contractors may consider the 0/100          Therefore, the earned value can be con-
          tions. This task becomes even more         rule harsh. When a contractor is paid       sidered to be equal to the effort
          demanding when dealing with new,           based on this rule, it is reasonable to     applied or the actual cost.
          emerging, or softer technology proj-       expect that the contractor will strive to
          ects, such as telecommunications, soft-    have a very detailed WBS that breaks        Applications
          ware development, architectural or         the project down to as many items as        EVM provides project managers and
          engineering design, and research and       possible, so that completion of item(s)     the organization with triggers or early
          development.                               can be shown regularly and payment          warning signals that allow them to take
               Alternatives to using the percent     can be authorized.                          timely actions in response to indicators
          complete to determine physical                  Other alternatives for determining     of poor performance and enhance the
          accomplishments have been used. The        physical accomplishments can be             opportunities for project success. Such
          50/50 rule specifies that 50% of an        used. For example, the 10/90 rule,          indicators have been found to be reli-
          item’s budget is recorded at the time      20/80 rule, and 25/75 rule acknowl-         able as early as 15% into a project.
          that the work is scheduled to begin,       edge that to start a work package, a cer-   Better planning and resource allocation
          and the remaining 50% is recorded          tain amount of preparation and              associated with the early periods of a
          when the work is scheduled to be com-      mobilization are needed. Therefore,         project might be the cause of this relia-
          pleted. If the project had a large num-    10%, 20%, or 25% of the value would         bility (Fleming & Koppelman, 2000).
          ber of items, the distortion from the      be considered earned when the work is            EVM can be used for progress pay-
          50/50 rule would be minimal                started, and the remaining amount           ments to contractors based on the EV
          (Kerzner, 2001), because these items       would be earned when the work is            of contracted or outsourced work.
          would be at various stages of comple-      completed. If the work package were         Because such contractual arrangements
          tion. This allows us to calculate PV.      front-end loaded, as might be the case      create legal and financial obligations, it
          Similarly, to calculate EV, 50% of an      with certain equipment acquisitions,        is important to consider the method
          item’s budget is recorded when the         then the inverse of these rules might be    specified for evaluating progress. The
          work begins, and the remaining 50% is      appropriate. For example, the 75/25         previously discussed alternatives for
          recorded when the work is completed.       rule might specify that 75% of the          determination of percent complete
          To make the 50/50 rule work success-       value would be considered earned            should be carefully considered and
          fully, the project should be broken        when the equipment is delivered, and        negotiated to achieve a fair and equi-
          down into very detailed, short-span        the remaining amount is earned when         table environment that encourages suc-
          work       packages     (Fleming      &    installation, testing, and commission-      cessful accomplishment of contracted
          Koppelman, 2000).                          ing are completed.                          or outsourced project items.
               The 50/50 rule is a common prac-           The percent complete method can             For long-term projects, it may be
          tice in a number of contractual            be used with a buffer that sets a ceiling   appropriate to consider incorporating
          arrangements, such as those for home       of about 80% or 90% upon reported           the time value of money and time-dis-
          repair. Half of the contract price is      completion. A work package may earn         counted cash flows into EVM. Inflation
          paid up front, and the remaining bal-      only up to the specified percent ceiling    can be explicitly considered in EVM,
          ance is paid upon completion of the        based on subjective estimates. When         and the inflation variance (IV) can be
          work. It should be noted that when         the work package is 100% complete,          calculated (Farid & Karshenas, 1988).
          the 50/50 rule is used in a contractual    the balance is earned. A variation of       However, these considerations add
          arrangement and the contractor is          this approach is using a combination        complexity to the method and may be
          paid based on this rule, it is reason-     of the percent complete and a mile-         justifiable only for very long-term proj-
          able to expect that the contractor will    stone gate. A work package may earn         ects or in very high inflation periods or
          tend to start as many items as possi-      only up to a maximum specified per-         economies.


                                                                                                 December 2003 Project Management Journal • 21
PMI-002   11/5     11/6/03     9:20    AM   Page   22




               An organization may elect to                    0.67 = $150,000                        Analysis          Method        [ CD-ROM] .
          apply EVM uniformly to all of its proj-             EAC3 = AC / % Complete = 60,000 /       Proceedings of the Project Management
          ects, or only to projects exceeding its             0.40 = $150,000                         Institute 2 0 0 1 Seminars & Symp osium,
          own thresholds for cost and schedule                VAC = BAC - EAC = $100,000 -            N ovember 1-10, 2001, N ashville, TN ,
          reporting and control. EVM can be                    $150,000 = -$50,000                    USA. N ewtown Square, PA: Project
          applied to projects of various types and                                                    Management Institute.
          sizes in the public and private sectors.            EAC5 = EACs = BAC / CR = $100,000/            Anbari, F.T. (2002). Q uantitativ e
          It can be applied at various levels of a            0.53 = $187,500                         Methods for Project Management, Second
          project’s WBS and to various cost com-                                                      Edition. N ew York, N Y: International
          ponents, such as labor, material and                TEAC3 = SAC / SPI = 40 weeks /          Institute for Learning.
          subcontractors.                                     0.80 = 50 weeks                               Barr, Z . (1996). Earned Value
                                                              TEAC3 = AT / % Complete = 20 /          Analysis: A Case Study. PM N etwork , X
          Comprehensive Example                               0.40 = 50 weeks                         (12), 31-37.
          A project has a baseline BAC of                     TVAC = SAC – TEAC = 40 weeks –                Cioffi, D. F. (2002). Managing
          $100,000 and a baseline SAC of 40                   50 weeks = -10 weeks                    Project Integration. Vienna, VA:
          weeks. The baseline indicates that by                                                       Management Concepts.
          the end of week 20, the project is              Conclusion                                        Cleland, D.I., & King, W.R.
          planned to be 50% complete. At the              EVM helps focus management’s inter-         (Editors). (1988). Project Management
          end of week 20, it is reported that 40%         est on projects that need most atten-       H andb ook , (2nd. Ed.). N ew York, N Y:
          of the project work has been complet-           tion and may aid the prioritization and     Van N ostrand Reinhold.
          ed at a cost of $60,000. Using the EVM          emphasis management gives projects                Egan, Jr., D.S. (1982). The
          method:                                         within a portfolio, enhancing the           Performance Index: Combining Cost
                    BAC = $100,000                        enterprise’s project portfolio manage-      and Production Data to Show How
                    SAC = 40 weeks                        ment. EVM provides important infor-         Good (or Bad) Your Project Really Is!!
                                                          mation for project or work package          Proceedings of the 7 . Internet W orld
                   PV = 50% x $100,000                    decision-making. Its wider acceptance       C ongress on Project Management, 1982,
                      = $50,000                           and effectiveness may depend on bet-        Copenhagen, Denmark, PROJEKT-
                   AC = $60,000                           ter understanding of its capabilities.      PLAN ,        The      Danish        Project
                   EV = 40% x $100,000                    Simplification of EVM calculations,         Management Society, The Danish
                      = $40,000                           use of graphical tools to enhance           Technical Press, Denmark, 355-364.
                   AT = 20 weeks                          understanding of performance trends,              Farid, F., & Karshenas, S.
             Therefore:                                   and successful application of EVM in        (N ovember, 1988). Cost/Schedule
              % Complete = EV / BAC                       industry are important factors for the      Control Systems Criteria Under
              = $40,000 / $100,000 = 40%                  growth and effective use of this valu-      Inflation. Project Management Journal,
              % Spent = AC / BAC = $60,000 /              able method in project management.          X IX (5), 23-29.
               $100,000 = 60%                                                                               Fleming, Q.W., & Koppelman, J.M.
                                                          References                                  (2000).        E arned     V alue     Project
               CV = EV – AC = $40,000 –                   Anbari, F.T. (1980). An Operating           Management, (2nd Ed.). N ewtown
               $60,000 = -$20,000                         Management Control System for Large         Square, PA: Project Management
               SV = EV – PV = $40,000 –                   Scale Projects. Unpublished paper pre-      Institute.
               $50,000 = -$10,000                         sented at The Decision Sciences Institute         Heinze,       K.     (1996).      C ost
                                                          N inth Annual Meeting, N ortheast           Management of C ap ital Projects. N ew
               PV Rate = BAC / SAC = $100,000 /           R egional C onference, Philadelphia, PA.    York: Marcel Dekker, Inc.
               40 weeks = $2,500 per week                 Sponsored by the N ortheast Decision              Kerzner, H. (2001). Project
               TV = SV / PV Rate = - $10,000 /            Sciences Institute.                         Management: A Systems Ap p roach to
               $2,500 per week = -4 weeks                      Anbari, F.T. (1983). An Operating      Planning, Scheduling, and C ontrolling,
                                                          System for Forecasting Project Cost at      (7th Ed.). N ew York, N Y: John Wiley &
               CPI = EV / AC = $40,000 /                  Completion. Unpublished paper pre-          Sons.
               $60,000 = 0.67                             sented at The Third International                 Kim, E.H. (2000). A Study on the
               CPI = % Complete /                         Symp osium on F orecasting, Philadelphia,   E ffectiv e Imp lementation of E arned V alue
               % Spent = 40% / 60% = 0.67                 PA. Abstract in Program sponsored by        Management Methodology, Unpublished
               SPI = EV / PV = $40,000 /                  The International Institute of              doctoral dissertation. The George
               $50,000 = 0.80                             Forecasters in collaboration with the       Washington University, Washington,
                                                          Wharton School, University of               DC.
               CR = CPI x SPI = 0.67 x 0.80               Pennsylvania, Philadelphia, PA.                   Lewis, J.P. (2001). Project Planning,
               = 0.53                                          Anbari, F. T. (2001). Applications     Scheduling, & C ontrol: A H ands-On
               EAC3 = BAC / CPI = $100,000 /              and Extensions of the Earned Value          Guide to Bringing Projects In On Time


          22 • Project Management Journal December 2003
Eva[1]

More Related Content

What's hot

Front-End Loading in the Oil and Gas Industry
Front-End Loading in the Oil and Gas IndustryFront-End Loading in the Oil and Gas Industry
Front-End Loading in the Oil and Gas IndustryDavid Pires
 
Zieger.alfred
Zieger.alfredZieger.alfred
Zieger.alfredNASAPMC
 
Dwayne Davis resume June 2016
Dwayne Davis resume June 2016Dwayne Davis resume June 2016
Dwayne Davis resume June 2016Dwayne Davis
 
J.S. Daniel paper for practical checklist of schedule
J.S. Daniel paper for practical checklist of scheduleJ.S. Daniel paper for practical checklist of schedule
J.S. Daniel paper for practical checklist of scheduleJ.S. Daniel
 
Dlpks Cwmf Technical Briefing
Dlpks Cwmf Technical BriefingDlpks Cwmf Technical Briefing
Dlpks Cwmf Technical Briefingjoregan
 
J.S. Daniel presentation on planning
J.S. Daniel presentation on planningJ.S. Daniel presentation on planning
J.S. Daniel presentation on planningJ.S. Daniel
 
Improvement of construction labor productivity in chambal region
Improvement of construction labor productivity in chambal regionImprovement of construction labor productivity in chambal region
Improvement of construction labor productivity in chambal regioneSAT Publishing House
 
Delay Disruption & EOT Flyer
Delay Disruption & EOT FlyerDelay Disruption & EOT Flyer
Delay Disruption & EOT FlyerGarry Macdonald
 
Planning and Scheduling Construction Projects using Primavera Software A Case...
Planning and Scheduling Construction Projects using Primavera Software A Case...Planning and Scheduling Construction Projects using Primavera Software A Case...
Planning and Scheduling Construction Projects using Primavera Software A Case...ijtsrd
 
CV04.16.16 P. McAlpine
CV04.16.16  P. McAlpineCV04.16.16  P. McAlpine
CV04.16.16 P. McAlpinePenny McAlpine
 
Esker.linda
Esker.lindaEsker.linda
Esker.lindaNASAPMC
 
J.S. Daniel paper for presentation cost management
J.S. Daniel paper for presentation cost managementJ.S. Daniel paper for presentation cost management
J.S. Daniel paper for presentation cost managementJ.S. Daniel
 
Application of Earned Value Method and Delay Analysis on Construction Project...
Application of Earned Value Method and Delay Analysis on Construction Project...Application of Earned Value Method and Delay Analysis on Construction Project...
Application of Earned Value Method and Delay Analysis on Construction Project...IRJET Journal
 

What's hot (17)

Front-End Loading in the Oil and Gas Industry
Front-End Loading in the Oil and Gas IndustryFront-End Loading in the Oil and Gas Industry
Front-End Loading in the Oil and Gas Industry
 
Zieger.alfred
Zieger.alfredZieger.alfred
Zieger.alfred
 
S curve1
S curve1S curve1
S curve1
 
CCP Technical Paper and Application
CCP Technical Paper and ApplicationCCP Technical Paper and Application
CCP Technical Paper and Application
 
Dwayne Davis resume June 2016
Dwayne Davis resume June 2016Dwayne Davis resume June 2016
Dwayne Davis resume June 2016
 
J.S. Daniel paper for practical checklist of schedule
J.S. Daniel paper for practical checklist of scheduleJ.S. Daniel paper for practical checklist of schedule
J.S. Daniel paper for practical checklist of schedule
 
Dlpks Cwmf Technical Briefing
Dlpks Cwmf Technical BriefingDlpks Cwmf Technical Briefing
Dlpks Cwmf Technical Briefing
 
113 2 pdri
113 2 pdri113 2 pdri
113 2 pdri
 
J.S. Daniel presentation on planning
J.S. Daniel presentation on planningJ.S. Daniel presentation on planning
J.S. Daniel presentation on planning
 
Improvement of construction labor productivity in chambal region
Improvement of construction labor productivity in chambal regionImprovement of construction labor productivity in chambal region
Improvement of construction labor productivity in chambal region
 
Delay Disruption & EOT Flyer
Delay Disruption & EOT FlyerDelay Disruption & EOT Flyer
Delay Disruption & EOT Flyer
 
Planning and Scheduling Construction Projects using Primavera Software A Case...
Planning and Scheduling Construction Projects using Primavera Software A Case...Planning and Scheduling Construction Projects using Primavera Software A Case...
Planning and Scheduling Construction Projects using Primavera Software A Case...
 
CV04.16.16 P. McAlpine
CV04.16.16  P. McAlpineCV04.16.16  P. McAlpine
CV04.16.16 P. McAlpine
 
Esker.linda
Esker.lindaEsker.linda
Esker.linda
 
J.S. Daniel paper for presentation cost management
J.S. Daniel paper for presentation cost managementJ.S. Daniel paper for presentation cost management
J.S. Daniel paper for presentation cost management
 
David Fitzsimmons Resume
David Fitzsimmons ResumeDavid Fitzsimmons Resume
David Fitzsimmons Resume
 
Application of Earned Value Method and Delay Analysis on Construction Project...
Application of Earned Value Method and Delay Analysis on Construction Project...Application of Earned Value Method and Delay Analysis on Construction Project...
Application of Earned Value Method and Delay Analysis on Construction Project...
 

Similar to Eva[1]

iEVM (Integrated Earned Value Management) An approach for integrating quality...
iEVM (Integrated Earned Value Management) An approach for integrating quality...iEVM (Integrated Earned Value Management) An approach for integrating quality...
iEVM (Integrated Earned Value Management) An approach for integrating quality...IRJET Journal
 
Cost Analysis of Road Construction Project by Earned Value Analysis using Pri...
Cost Analysis of Road Construction Project by Earned Value Analysis using Pri...Cost Analysis of Road Construction Project by Earned Value Analysis using Pri...
Cost Analysis of Road Construction Project by Earned Value Analysis using Pri...IRJET Journal
 
Improving Project Performance in the DOE
Improving Project Performance in the DOEImproving Project Performance in the DOE
Improving Project Performance in the DOEGlen Alleman
 
Tracking a Typical Apartment Construction using Earned Value Management
Tracking a Typical Apartment Construction using Earned Value ManagementTracking a Typical Apartment Construction using Earned Value Management
Tracking a Typical Apartment Construction using Earned Value ManagementIRJET Journal
 
Performance Evaluation of Construction Projects by EVM Method, Using Primaver...
Performance Evaluation of Construction Projects by EVM Method, Using Primaver...Performance Evaluation of Construction Projects by EVM Method, Using Primaver...
Performance Evaluation of Construction Projects by EVM Method, Using Primaver...Mohammad Lemar ZALMAİ
 
Polynomial Function and Fuzzy Inference for Evaluating the Project Performanc...
Polynomial Function and Fuzzy Inference for Evaluating the Project Performanc...Polynomial Function and Fuzzy Inference for Evaluating the Project Performanc...
Polynomial Function and Fuzzy Inference for Evaluating the Project Performanc...IJERA Editor
 
Improving DOE Project Performance Using the DOD Integrated Master Plan
Improving DOE Project Performance Using the DOD Integrated Master PlanImproving DOE Project Performance Using the DOD Integrated Master Plan
Improving DOE Project Performance Using the DOD Integrated Master PlanGlen Alleman
 
IRJET- Value Management
IRJET- Value ManagementIRJET- Value Management
IRJET- Value ManagementIRJET Journal
 
IRJET- The Application of Value Engineering to Highway Projects and Programs
IRJET- The Application of Value Engineering to Highway Projects and ProgramsIRJET- The Application of Value Engineering to Highway Projects and Programs
IRJET- The Application of Value Engineering to Highway Projects and ProgramsIRJET Journal
 
PROJECT MANAGEMENT _PPT_VIS
PROJECT MANAGEMENT _PPT_VISPROJECT MANAGEMENT _PPT_VIS
PROJECT MANAGEMENT _PPT_VIStpvishnu1
 
Performance Evaluation of Construction Projects by EVM Method, Using Primaver...
Performance Evaluation of Construction Projects by EVM Method, Using Primaver...Performance Evaluation of Construction Projects by EVM Method, Using Primaver...
Performance Evaluation of Construction Projects by EVM Method, Using Primaver...Mohammad Lemar ZALMAİ
 
Construction Management Techniques to Complete the Project within Time Period...
Construction Management Techniques to Complete the Project within Time Period...Construction Management Techniques to Complete the Project within Time Period...
Construction Management Techniques to Complete the Project within Time Period...IRJET Journal
 
C:\documents and settings\ckampschulte\desktop\in sync risk range analysis
C:\documents and settings\ckampschulte\desktop\in sync risk range analysisC:\documents and settings\ckampschulte\desktop\in sync risk range analysis
C:\documents and settings\ckampschulte\desktop\in sync risk range analysisInSync Conference
 
Impact of Rework on Cost and Schedule
Impact of Rework on Cost and ScheduleImpact of Rework on Cost and Schedule
Impact of Rework on Cost and Scheduleskalema34
 
Strategies for successful engineering management
Strategies for successful engineering managementStrategies for successful engineering management
Strategies for successful engineering managementCarla Fair-Wright
 
projectmanagement-141108102434-conversion-gate01-converted.pptx
projectmanagement-141108102434-conversion-gate01-converted.pptxprojectmanagement-141108102434-conversion-gate01-converted.pptx
projectmanagement-141108102434-conversion-gate01-converted.pptxChandrasen Sharma
 
Project Implementation.pdf
Project Implementation.pdfProject Implementation.pdf
Project Implementation.pdfssuserc0e4e0
 

Similar to Eva[1] (20)

iEVM (Integrated Earned Value Management) An approach for integrating quality...
iEVM (Integrated Earned Value Management) An approach for integrating quality...iEVM (Integrated Earned Value Management) An approach for integrating quality...
iEVM (Integrated Earned Value Management) An approach for integrating quality...
 
Cost Analysis of Road Construction Project by Earned Value Analysis using Pri...
Cost Analysis of Road Construction Project by Earned Value Analysis using Pri...Cost Analysis of Road Construction Project by Earned Value Analysis using Pri...
Cost Analysis of Road Construction Project by Earned Value Analysis using Pri...
 
Improving Project Performance in the DOE
Improving Project Performance in the DOEImproving Project Performance in the DOE
Improving Project Performance in the DOE
 
Tracking a Typical Apartment Construction using Earned Value Management
Tracking a Typical Apartment Construction using Earned Value ManagementTracking a Typical Apartment Construction using Earned Value Management
Tracking a Typical Apartment Construction using Earned Value Management
 
Performance Evaluation of Construction Projects by EVM Method, Using Primaver...
Performance Evaluation of Construction Projects by EVM Method, Using Primaver...Performance Evaluation of Construction Projects by EVM Method, Using Primaver...
Performance Evaluation of Construction Projects by EVM Method, Using Primaver...
 
Polynomial Function and Fuzzy Inference for Evaluating the Project Performanc...
Polynomial Function and Fuzzy Inference for Evaluating the Project Performanc...Polynomial Function and Fuzzy Inference for Evaluating the Project Performanc...
Polynomial Function and Fuzzy Inference for Evaluating the Project Performanc...
 
Improving DOE Project Performance Using the DOD Integrated Master Plan
Improving DOE Project Performance Using the DOD Integrated Master PlanImproving DOE Project Performance Using the DOD Integrated Master Plan
Improving DOE Project Performance Using the DOD Integrated Master Plan
 
IRJET- Value Management
IRJET- Value ManagementIRJET- Value Management
IRJET- Value Management
 
COST CONTROL AND TRACKING OF A BUILDING BY EARNED VALUE METHOD
COST CONTROL AND TRACKING OF A BUILDING BY EARNED VALUE METHODCOST CONTROL AND TRACKING OF A BUILDING BY EARNED VALUE METHOD
COST CONTROL AND TRACKING OF A BUILDING BY EARNED VALUE METHOD
 
IRJET- The Application of Value Engineering to Highway Projects and Programs
IRJET- The Application of Value Engineering to Highway Projects and ProgramsIRJET- The Application of Value Engineering to Highway Projects and Programs
IRJET- The Application of Value Engineering to Highway Projects and Programs
 
PROJECT MANAGEMENT _PPT_VIS
PROJECT MANAGEMENT _PPT_VISPROJECT MANAGEMENT _PPT_VIS
PROJECT MANAGEMENT _PPT_VIS
 
CCP_SEC3_Planning and Scheduling
CCP_SEC3_Planning and SchedulingCCP_SEC3_Planning and Scheduling
CCP_SEC3_Planning and Scheduling
 
Performance Evaluation of Construction Projects by EVM Method, Using Primaver...
Performance Evaluation of Construction Projects by EVM Method, Using Primaver...Performance Evaluation of Construction Projects by EVM Method, Using Primaver...
Performance Evaluation of Construction Projects by EVM Method, Using Primaver...
 
Construction Management Techniques to Complete the Project within Time Period...
Construction Management Techniques to Complete the Project within Time Period...Construction Management Techniques to Complete the Project within Time Period...
Construction Management Techniques to Complete the Project within Time Period...
 
C:\documents and settings\ckampschulte\desktop\in sync risk range analysis
C:\documents and settings\ckampschulte\desktop\in sync risk range analysisC:\documents and settings\ckampschulte\desktop\in sync risk range analysis
C:\documents and settings\ckampschulte\desktop\in sync risk range analysis
 
Impact of Rework on Cost and Schedule
Impact of Rework on Cost and ScheduleImpact of Rework on Cost and Schedule
Impact of Rework on Cost and Schedule
 
Strategies for successful engineering management
Strategies for successful engineering managementStrategies for successful engineering management
Strategies for successful engineering management
 
projectmanagement-141108102434-conversion-gate01-converted.pptx
projectmanagement-141108102434-conversion-gate01-converted.pptxprojectmanagement-141108102434-conversion-gate01-converted.pptx
projectmanagement-141108102434-conversion-gate01-converted.pptx
 
Unit 2.pptx
Unit 2.pptxUnit 2.pptx
Unit 2.pptx
 
Project Implementation.pdf
Project Implementation.pdfProject Implementation.pdf
Project Implementation.pdf
 

More from Eduardo Alves

Auditoria de-contratos
Auditoria de-contratosAuditoria de-contratos
Auditoria de-contratosEduardo Alves
 
Eudaiminia na etic nociomano
Eudaiminia na etic nociomanoEudaiminia na etic nociomano
Eudaiminia na etic nociomanoEduardo Alves
 
383 aula 11_mapeamento_do_fluxo_de_valor
383 aula 11_mapeamento_do_fluxo_de_valor383 aula 11_mapeamento_do_fluxo_de_valor
383 aula 11_mapeamento_do_fluxo_de_valorEduardo Alves
 
Como medir produtividade entac
Como medir produtividade   entacComo medir produtividade   entac
Como medir produtividade entacEduardo Alves
 
O que significa ph d abd
O que significa ph d abdO que significa ph d abd
O que significa ph d abdEduardo Alves
 
06 projeto-churrasco-dos-sonhos-gerando-a-eap-gráfica-guia-03
06 projeto-churrasco-dos-sonhos-gerando-a-eap-gráfica-guia-0306 projeto-churrasco-dos-sonhos-gerando-a-eap-gráfica-guia-03
06 projeto-churrasco-dos-sonhos-gerando-a-eap-gráfica-guia-03Eduardo Alves
 
Calendário lunar 2012
Calendário lunar 2012Calendário lunar 2012
Calendário lunar 2012Eduardo Alves
 

More from Eduardo Alves (17)

Teste hip facil
Teste hip facilTeste hip facil
Teste hip facil
 
Livro qfd
Livro qfdLivro qfd
Livro qfd
 
Auditoria de-contratos
Auditoria de-contratosAuditoria de-contratos
Auditoria de-contratos
 
Eudaiminia na etic nociomano
Eudaiminia na etic nociomanoEudaiminia na etic nociomano
Eudaiminia na etic nociomano
 
383 aula 11_mapeamento_do_fluxo_de_valor
383 aula 11_mapeamento_do_fluxo_de_valor383 aula 11_mapeamento_do_fluxo_de_valor
383 aula 11_mapeamento_do_fluxo_de_valor
 
Apresentacao cpm
Apresentacao cpmApresentacao cpm
Apresentacao cpm
 
Como medir produtividade entac
Como medir produtividade   entacComo medir produtividade   entac
Como medir produtividade entac
 
Wbs
WbsWbs
Wbs
 
O que significa ph d abd
O que significa ph d abdO que significa ph d abd
O que significa ph d abd
 
06 projeto-churrasco-dos-sonhos-gerando-a-eap-gráfica-guia-03
06 projeto-churrasco-dos-sonhos-gerando-a-eap-gráfica-guia-0306 projeto-churrasco-dos-sonhos-gerando-a-eap-gráfica-guia-03
06 projeto-churrasco-dos-sonhos-gerando-a-eap-gráfica-guia-03
 
Calendário lunar 2012
Calendário lunar 2012Calendário lunar 2012
Calendário lunar 2012
 
Hemograma2
Hemograma2Hemograma2
Hemograma2
 
Hemograma2
Hemograma2Hemograma2
Hemograma2
 
Hemograma2
Hemograma2Hemograma2
Hemograma2
 
Hemograma2
Hemograma2Hemograma2
Hemograma2
 
(Eva) in the cost
(Eva) in the cost(Eva) in the cost
(Eva) in the cost
 
5. cost estimation
5. cost estimation5. cost estimation
5. cost estimation
 

Recently uploaded

Insurers' journeys to build a mastery in the IoT usage
Insurers' journeys to build a mastery in the IoT usageInsurers' journeys to build a mastery in the IoT usage
Insurers' journeys to build a mastery in the IoT usageMatteo Carbone
 
Mondelez State of Snacking and Future Trends 2023
Mondelez State of Snacking and Future Trends 2023Mondelez State of Snacking and Future Trends 2023
Mondelez State of Snacking and Future Trends 2023Neil Kimberley
 
Monte Carlo simulation : Simulation using MCSM
Monte Carlo simulation : Simulation using MCSMMonte Carlo simulation : Simulation using MCSM
Monte Carlo simulation : Simulation using MCSMRavindra Nath Shukla
 
Keppel Ltd. 1Q 2024 Business Update Presentation Slides
Keppel Ltd. 1Q 2024 Business Update  Presentation SlidesKeppel Ltd. 1Q 2024 Business Update  Presentation Slides
Keppel Ltd. 1Q 2024 Business Update Presentation SlidesKeppelCorporation
 
Intro to BCG's Carbon Emissions Benchmark_vF.pdf
Intro to BCG's Carbon Emissions Benchmark_vF.pdfIntro to BCG's Carbon Emissions Benchmark_vF.pdf
Intro to BCG's Carbon Emissions Benchmark_vF.pdfpollardmorgan
 
VIP Call Girl Jamshedpur Aashi 8250192130 Independent Escort Service Jamshedpur
VIP Call Girl Jamshedpur Aashi 8250192130 Independent Escort Service JamshedpurVIP Call Girl Jamshedpur Aashi 8250192130 Independent Escort Service Jamshedpur
VIP Call Girl Jamshedpur Aashi 8250192130 Independent Escort Service JamshedpurSuhani Kapoor
 
VIP Kolkata Call Girl Howrah 👉 8250192130 Available With Room
VIP Kolkata Call Girl Howrah 👉 8250192130  Available With RoomVIP Kolkata Call Girl Howrah 👉 8250192130  Available With Room
VIP Kolkata Call Girl Howrah 👉 8250192130 Available With Roomdivyansh0kumar0
 
Vip Dewas Call Girls #9907093804 Contact Number Escorts Service Dewas
Vip Dewas Call Girls #9907093804 Contact Number Escorts Service DewasVip Dewas Call Girls #9907093804 Contact Number Escorts Service Dewas
Vip Dewas Call Girls #9907093804 Contact Number Escorts Service Dewasmakika9823
 
Lucknow 💋 Escorts in Lucknow - 450+ Call Girl Cash Payment 8923113531 Neha Th...
Lucknow 💋 Escorts in Lucknow - 450+ Call Girl Cash Payment 8923113531 Neha Th...Lucknow 💋 Escorts in Lucknow - 450+ Call Girl Cash Payment 8923113531 Neha Th...
Lucknow 💋 Escorts in Lucknow - 450+ Call Girl Cash Payment 8923113531 Neha Th...anilsa9823
 
Call Girls Pune Just Call 9907093804 Top Class Call Girl Service Available
Call Girls Pune Just Call 9907093804 Top Class Call Girl Service AvailableCall Girls Pune Just Call 9907093804 Top Class Call Girl Service Available
Call Girls Pune Just Call 9907093804 Top Class Call Girl Service AvailableDipal Arora
 
VIP Call Girls Pune Kirti 8617697112 Independent Escort Service Pune
VIP Call Girls Pune Kirti 8617697112 Independent Escort Service PuneVIP Call Girls Pune Kirti 8617697112 Independent Escort Service Pune
VIP Call Girls Pune Kirti 8617697112 Independent Escort Service PuneCall girls in Ahmedabad High profile
 
Lowrate Call Girls In Sector 18 Noida ❤️8860477959 Escorts 100% Genuine Servi...
Lowrate Call Girls In Sector 18 Noida ❤️8860477959 Escorts 100% Genuine Servi...Lowrate Call Girls In Sector 18 Noida ❤️8860477959 Escorts 100% Genuine Servi...
Lowrate Call Girls In Sector 18 Noida ❤️8860477959 Escorts 100% Genuine Servi...lizamodels9
 
Tech Startup Growth Hacking 101 - Basics on Growth Marketing
Tech Startup Growth Hacking 101  - Basics on Growth MarketingTech Startup Growth Hacking 101  - Basics on Growth Marketing
Tech Startup Growth Hacking 101 - Basics on Growth MarketingShawn Pang
 
Progress Report - Oracle Database Analyst Summit
Progress  Report - Oracle Database Analyst SummitProgress  Report - Oracle Database Analyst Summit
Progress Report - Oracle Database Analyst SummitHolger Mueller
 
Regression analysis: Simple Linear Regression Multiple Linear Regression
Regression analysis:  Simple Linear Regression Multiple Linear RegressionRegression analysis:  Simple Linear Regression Multiple Linear Regression
Regression analysis: Simple Linear Regression Multiple Linear RegressionRavindra Nath Shukla
 
BEST Call Girls In Greater Noida ✨ 9773824855 ✨ Escorts Service In Delhi Ncr,
BEST Call Girls In Greater Noida ✨ 9773824855 ✨ Escorts Service In Delhi Ncr,BEST Call Girls In Greater Noida ✨ 9773824855 ✨ Escorts Service In Delhi Ncr,
BEST Call Girls In Greater Noida ✨ 9773824855 ✨ Escorts Service In Delhi Ncr,noida100girls
 
0183760ssssssssssssssssssssssssssss00101011 (27).pdf
0183760ssssssssssssssssssssssssssss00101011 (27).pdf0183760ssssssssssssssssssssssssssss00101011 (27).pdf
0183760ssssssssssssssssssssssssssss00101011 (27).pdfRenandantas16
 
Non Text Magic Studio Magic Design for Presentations L&P.pptx
Non Text Magic Studio Magic Design for Presentations L&P.pptxNon Text Magic Studio Magic Design for Presentations L&P.pptx
Non Text Magic Studio Magic Design for Presentations L&P.pptxAbhayThakur200703
 
Pharma Works Profile of Karan Communications
Pharma Works Profile of Karan CommunicationsPharma Works Profile of Karan Communications
Pharma Works Profile of Karan Communicationskarancommunications
 

Recently uploaded (20)

Insurers' journeys to build a mastery in the IoT usage
Insurers' journeys to build a mastery in the IoT usageInsurers' journeys to build a mastery in the IoT usage
Insurers' journeys to build a mastery in the IoT usage
 
Mondelez State of Snacking and Future Trends 2023
Mondelez State of Snacking and Future Trends 2023Mondelez State of Snacking and Future Trends 2023
Mondelez State of Snacking and Future Trends 2023
 
Monte Carlo simulation : Simulation using MCSM
Monte Carlo simulation : Simulation using MCSMMonte Carlo simulation : Simulation using MCSM
Monte Carlo simulation : Simulation using MCSM
 
Keppel Ltd. 1Q 2024 Business Update Presentation Slides
Keppel Ltd. 1Q 2024 Business Update  Presentation SlidesKeppel Ltd. 1Q 2024 Business Update  Presentation Slides
Keppel Ltd. 1Q 2024 Business Update Presentation Slides
 
Intro to BCG's Carbon Emissions Benchmark_vF.pdf
Intro to BCG's Carbon Emissions Benchmark_vF.pdfIntro to BCG's Carbon Emissions Benchmark_vF.pdf
Intro to BCG's Carbon Emissions Benchmark_vF.pdf
 
VIP Call Girl Jamshedpur Aashi 8250192130 Independent Escort Service Jamshedpur
VIP Call Girl Jamshedpur Aashi 8250192130 Independent Escort Service JamshedpurVIP Call Girl Jamshedpur Aashi 8250192130 Independent Escort Service Jamshedpur
VIP Call Girl Jamshedpur Aashi 8250192130 Independent Escort Service Jamshedpur
 
VIP Kolkata Call Girl Howrah 👉 8250192130 Available With Room
VIP Kolkata Call Girl Howrah 👉 8250192130  Available With RoomVIP Kolkata Call Girl Howrah 👉 8250192130  Available With Room
VIP Kolkata Call Girl Howrah 👉 8250192130 Available With Room
 
Vip Dewas Call Girls #9907093804 Contact Number Escorts Service Dewas
Vip Dewas Call Girls #9907093804 Contact Number Escorts Service DewasVip Dewas Call Girls #9907093804 Contact Number Escorts Service Dewas
Vip Dewas Call Girls #9907093804 Contact Number Escorts Service Dewas
 
Lucknow 💋 Escorts in Lucknow - 450+ Call Girl Cash Payment 8923113531 Neha Th...
Lucknow 💋 Escorts in Lucknow - 450+ Call Girl Cash Payment 8923113531 Neha Th...Lucknow 💋 Escorts in Lucknow - 450+ Call Girl Cash Payment 8923113531 Neha Th...
Lucknow 💋 Escorts in Lucknow - 450+ Call Girl Cash Payment 8923113531 Neha Th...
 
Call Girls Pune Just Call 9907093804 Top Class Call Girl Service Available
Call Girls Pune Just Call 9907093804 Top Class Call Girl Service AvailableCall Girls Pune Just Call 9907093804 Top Class Call Girl Service Available
Call Girls Pune Just Call 9907093804 Top Class Call Girl Service Available
 
VIP Call Girls Pune Kirti 8617697112 Independent Escort Service Pune
VIP Call Girls Pune Kirti 8617697112 Independent Escort Service PuneVIP Call Girls Pune Kirti 8617697112 Independent Escort Service Pune
VIP Call Girls Pune Kirti 8617697112 Independent Escort Service Pune
 
Lowrate Call Girls In Sector 18 Noida ❤️8860477959 Escorts 100% Genuine Servi...
Lowrate Call Girls In Sector 18 Noida ❤️8860477959 Escorts 100% Genuine Servi...Lowrate Call Girls In Sector 18 Noida ❤️8860477959 Escorts 100% Genuine Servi...
Lowrate Call Girls In Sector 18 Noida ❤️8860477959 Escorts 100% Genuine Servi...
 
KestrelPro Flyer Japan IT Week 2024 (English)
KestrelPro Flyer Japan IT Week 2024 (English)KestrelPro Flyer Japan IT Week 2024 (English)
KestrelPro Flyer Japan IT Week 2024 (English)
 
Tech Startup Growth Hacking 101 - Basics on Growth Marketing
Tech Startup Growth Hacking 101  - Basics on Growth MarketingTech Startup Growth Hacking 101  - Basics on Growth Marketing
Tech Startup Growth Hacking 101 - Basics on Growth Marketing
 
Progress Report - Oracle Database Analyst Summit
Progress  Report - Oracle Database Analyst SummitProgress  Report - Oracle Database Analyst Summit
Progress Report - Oracle Database Analyst Summit
 
Regression analysis: Simple Linear Regression Multiple Linear Regression
Regression analysis:  Simple Linear Regression Multiple Linear RegressionRegression analysis:  Simple Linear Regression Multiple Linear Regression
Regression analysis: Simple Linear Regression Multiple Linear Regression
 
BEST Call Girls In Greater Noida ✨ 9773824855 ✨ Escorts Service In Delhi Ncr,
BEST Call Girls In Greater Noida ✨ 9773824855 ✨ Escorts Service In Delhi Ncr,BEST Call Girls In Greater Noida ✨ 9773824855 ✨ Escorts Service In Delhi Ncr,
BEST Call Girls In Greater Noida ✨ 9773824855 ✨ Escorts Service In Delhi Ncr,
 
0183760ssssssssssssssssssssssssssss00101011 (27).pdf
0183760ssssssssssssssssssssssssssss00101011 (27).pdf0183760ssssssssssssssssssssssssssss00101011 (27).pdf
0183760ssssssssssssssssssssssssssss00101011 (27).pdf
 
Non Text Magic Studio Magic Design for Presentations L&P.pptx
Non Text Magic Studio Magic Design for Presentations L&P.pptxNon Text Magic Studio Magic Design for Presentations L&P.pptx
Non Text Magic Studio Magic Design for Presentations L&P.pptx
 
Pharma Works Profile of Karan Communications
Pharma Works Profile of Karan CommunicationsPharma Works Profile of Karan Communications
Pharma Works Profile of Karan Communications
 

Eva[1]

  • 1. PMI-002 11/5 11/6/03 9:20 AM Page 12 EA R N ED VA L U E PR O JEC T MA N A G EMEN T METH O D A N D EX TEN S IO N S FRANK T. ANBARI, PHD, P M P P ro ject M a n a g emen t P ro g ra m, Dep a rtmen t o f M a n a g emen t S cien ce, S ch o o l o f B u s in es s a n d P u blic M a n a g emen t, T h e G eo rg e W a s h in g to n U n iv ers ity , 21 1 5 G S treet N W , W a s h in g to n , DC 2005 2 U S A Introduction he earned value project management method is a powerful tool that sup- ABS TRAC T The earned value project management method integrates three critical elements of project management: scope T ports the management of project scope, time, and cost. It allows the calcu- lation of cost and schedule variances and performance indices, and forecasts of project cost and schedule at completion. It provides early indications management, cost management, and time of ex pected project results b ased on project performance and highlights the pos- management. It req uires the periodic sib le need for corrective action. A s such, it allows the project manager and proj- monitoring of actual ex penditures and ect team to adjust project strategy and to mak e trade-offs b ased on project physical scope accomplishments, and ob jectives, actual project performance, and trends, as well as the environment in allows calculation of cost and schedule variances, along with performance indices. which the project is b eing conducted. It allows forecasting of project cost and T he method uses cost and value as the common measures of project per- schedule at completion and highlights the formance for b oth cost and schedule parameters. It allows the measurement of possib le need for corrective action. cost and value in dollars, hours, work er day s, or any other similar unit. This paper shows the major aspects of the T his paper shows the major aspects of the earned value method, presents earned value method and presents graph- ical tools for assessing project perform- graphical tools that enhance its effectiveness, and provides useful simplifications ance trends. It provides logical ex tensions and logical ex tensions of this important project management method. and useful simplifications to enhance the effective application of this important B a ck g round method in project management. A b asic form of the earned value analy sis project management method ( often Keywords: earned value method (E V M ); referred to as E V A or E V M ) can b e traced b ack to industrial engineers on the fac- earned value management system tory floor in the late 1 8 0 0 s ( F leming & K oppelman, 2 0 0 0 ; K im, 2 0 0 0 ) . A round (E V M S ); cost variance (C V ); schedule 1 9 6 7 , E V M was introduced b y agencies of the U .S . federal government as an inte- variance (S V ); cost performance index gral part of the cost/ schedule control sy stems criteria ( C / S C S C ) and was used in ( C P I) ; schedule perf ormance index large acq uisition programs. E V M has b een widely and successfully used in proj- (S P I); critical ratio (C R ); cost estimate at completion (E A C ); time estimate at com- ects associated with the U .S . federal government, with much less reported use in pletion (TE A C ) private industry . U se of E V M in private industry and support b y popular project management software pack ages have b een limited b ut have rapidly grown in © 2 0 0 3 b y the P roject M anagement Institute recent y ears. V ol. 3 4 , N o. 4 , 1 2 -2 3 , IS S N 8 7 5 6 -9 7 2 8 / 0 3 T o encourage wider use of E V M in the private sector, the U .S . federal govern- ment decided to discard C / S C S C b y the end of 1 9 9 6 and turned toward a more flex ib le earned value management sy stem ( E V M S ) , also called the earned value project management sy stem ( E V P M S ) . P roject M anagement Institute’s A Guide to th e P rojec t M a n a g em en t B ody of K n ow ledg e ( P M B O K ® Guide) ( P roject M anagement Institute, 2 0 0 0 ) provided the simplified E V M terminology and formulas. 12 • Project Management Journal December 2003
  • 2. PMI-002 11/5 11/6/03 9:20 AM Page 13 There has been a high degree of • A c tual c o s t (A C ): This is the cumula- this work package is EV = $ 20,000 x EVM acceptance among current and tive AC spent to a given point in time 1.00 = $ 20,000. W ork package 1.2 has past users of the method. They tend to accomplish an activity, work pack- a total budget of $ 4 0,000 and is 5 0% to agree that EVM can improve cost, age, or project and to earn the related complete as of the status date. schedule, and technical performance value. This was previously called the Therefore, the earned value for this of their projects. EVM nonusers indi- actual cost of work performed work package is EV = $ 4 0,000 x 0.5 0 = cate that the method is hard to use, (ACW P). Figure 2 illustrates a project $ 20,000. The earned value for the that it applies primarily to federal in which the planned value as of the entire project is EV = $ 20,000 + projects, and that they do not need it project status date is PV = $ 5 0,000 and $ 20,000 = $ 4 0,000. (Fleming & Koppelman, 2000; the actual cost is AC = $ 60,000. The preceding formula converts Kim, 2000). project accomplishments from physi- This paper simplifies EVM and cal units of measure, e.g., cubic yards shows its applicability to public and C o st Planned of concrete, linear feet of cable, percent ($ 0 0 0 ) V alu e (PV ) private sector projects, regardless of Budget At complete, milestones achieved, or siz e. The paper uses the simplified ter- C o m p letio n deliverables completed, to financial 60 (BAC ) minology and provides graphical 50 units of measure. These financial A c tu al C o s t tools, extensions, and applications of (A C ) measurements of value can be in dol- S tatu s D ate EVM to enhance the use and effective- lars (or any other currency), labor T im e ness of this important project manage- hours, work hours, worker days, or any ment method. other similar quantity that can be used F igure 2 . Planned Value and A c tual C o s t as a common measurement of the EVM Key Components value and cost associated with project EVM uses the following project param- • E ar ned value (E V): This is the cumu- work. Figure 3 illustrates the above eters to evaluate project performance: lative earned value for the work com- project, in which the total budget at • Planned value (PV): This is the time- pleted up to a point in time. It completion is B AC = $ 100,000, the phased budget baseline (Figure 1). It is represents the amount budgeted for planned value as of the status date is the approved budget for accomplish- performing the work that was accom- PV = $ 5 0,000, the actual cost is AC = ing the activity, work package, or proj- plished by a given point in time. This $ 60,000, and the earned value is EV = ect related to the schedule. It can be was previously called the budgeted $ 4 0,000. These are the main basic enti- viewed as the value to be earned as a cost of work performed (B CW P). To ties in EVM. function of project work accomplish- obtain EV for an item, multiply its ments up to a given point in time. This total budget by its completed propor- P erformance Measurement graph of cumulative PV is often tion. Table 1 shows the work break- Cost performance is determined by referred to as the S-curve (because, down structure (W B S) of a project with comparing the EV to the AC of the with a little imagination, it looks like a total budget of $ 100,000. W ork pack- activity, work package, or project. the letter S, or as an abbreviation of the age 1.1 has a total budget of $ 20,000 Schedule performance is determined Spending-curve). This was previously and is 100% complete as of the status by comparing the EV to the PV. This called the budgeted cost of work date. Therefore, the earned value for can be accomplished by calculating the scheduled (B CW S). • B udg et at c o m p letio n (B A C ): This is ($ 0 0 0 ) the total budget baseline for the activi- ty, work package, or project (Figure 1). Budget % C o m p lete E a rn ed P ro jec t It is the highest value of PV and the last V a lue P h a se1 point on the cumulative PV curve. W o rk Pac k ag e 1 .1 20 100 20 W o rk Pac k ag e 1 .2 40 50 20 ........ C o st Planned P h a se2 v alu e (PV ) Budget At C o m p letio n W o rk Pac k ag e 2 .1 ... (BAC ) W o rk Pac k ag e 2 .2 ... ........ ... ........ ... T im e T o ta l 100 40 F igure 1 . Planned Value and Budget at C o m p letio n T ab le 1 . W BS , Budget, % C o m p lete, and E ar ned Value December 2003 Project Management Journal • 13
  • 3. PMI-002 11/5 11/6/03 9:20 AM Page 14 PV R ate = $100,000 / 40 For the above project, SVP = Cost Planned = $2,500 per week -$10,000 / $50,000 = -20 %. This ($000) Value (PV) TV = -$10,000 / $2,500 = means that the project is 20% Budget At Completion -4 weeks behind schedule. 60 (BAC) 50 40 Actual Cost TV measurement also can be per- (AC) E arned Status date Value (E V) formed and reported graphically. This 40 CV and S V ($000) Time is accomplished by drawing a hori- 20 G ood zontal line from the intersection of 0 SV Figure 3 . Planned Value, Actual Cost and the EV curve with the status date to the -20 Poor CV Earned Value PV curve and reading the distance on -40 variances, the variance percentages, the horizontal time axis (Fleming & Time and the performance indices at the Koppelman, 2000), as shown in desired levels of the WBS. It is interest- Figure 4. ing to note that these comparisons are In the above formulas, 0 indicates Figure 5 . CV and SV G raph made to the EV, rather than to the that performance is on target. A posi- H owever, it may be appropriate baseline PV. tive value indicates good perform- to use EV rather than PV in the It is important to synchronize the ance. A negative value indicates poor denominator of this formula (J. J. status date for data in the analysis. This performance. Moder in Cleland & King, 1988). The can be accomplished by using the con- SVP based on the earned value cept of accrued cost, which includes (SVev% or SVPev) would be defined expenditures made but not yet reflect- as: SVPev = SV / EV. For the above ed in the financial system, to accom- Cost Planned project, SVPev = -$10,000 / $40,000 = ($000) Value (PV) plish work up to the status date. Budget At -25%. This indicates that the project is Completion 60 (BAC) 25% behind schedule. 50 SV = -10 CV = -20 Variances 40 Actual Cost The following formulas are used to cal- (AC) E arned Status date Value (E V) culate the variances, generally based Time 4 on cumulative data, also called incep- 2 G ood TV (W eek s) tion-to-date data and project-to-date Figure 4 . Variances 0 data (Figure 4, using the data from the -2 Poor above project): G raph ical D isplays -4 TV The cost variance (CV) is a meas- G raphs of variances over time provide ure of the budgetary conformance of valuable indicators of trends in project Time actual cost of work performed: CV = performance and of the impact of any EV – AC. For the above project, CV = corrective actions (Figures 5 and 6). Figure 6 . T V G raph $40,000 – $60,000 = -$20,000. The schedule variance (SV) is a Variance Percentages SVPev is consistent with the for- measure of the conformance of actual The following formulas are used to mula for CVP. It points out that SV progress to the schedule: S V = EV – PV. calculate the variance percentages, occurred while accomplishing EV. For the above project, SV = $40,000 – generally based on cumulative data Therefore, it may be a better indicator $50,000 = -$10,000. (Figure 4, using the data from the of project schedule status, as shown T ime variance: The average AC per above project): later in the calculation of the time esti- time period is often called the spend The cost variance percent (CV% or mate at completion (TEAC). rate or burn rate. Similarly, the average CVP) is a measure of the budgetary In the above formulas, 0 indicates PV per time period can be called the conformance of actual cost of work that performance is on target. A posi- planned accomplishment rate, performed: CVP = CV / EV. For the tive value indicates good perform- planned value rate, or the PV rate. It is above project, CVP = -$20,000 / ance. A negative value indicates poor defined as the baseline BAC divided by $40,000 = -50%, which indicates that performance. the baseline schedule at completion the project is 50% over budget. (SAC). As a formula, PV R ate = BAC / The schedule variance percent Performance Indices SAC. Thus, SV can be translated into (SV% or SVP) is a measure of the con- The following formulas are used to cal- time units by dividing SV by the PV formance of actual progress to the culate the performance indices, general- R ate. The result is the SV in time units schedule. The following formula has ly based on cumulative data (Figure 4, or the TV. As a formula, T V = SV / PV been generally used to calculate it using the data from the above project): R ate. If the above project were sched- (Project Management Institute, 2000): The cost performance index (CPI) uled for forty weeks, then: S VP = SV / PV. is a measure of the budgetary confor- 14 • Project Management Journal December 2003
  • 4. PMI-002 11/5 11/6/03 9:20 AM Page 15 mance of actual cost of work per- ures of project performance and to formed: CPI = EV / AC. For the above 1.4 quantify the “ traffic light approach.” project, CPI = $40,000 / $60,000 = 1.2 Good We can include the line that indicates CPI and SPI 0.67. 1.0 on target performance with the area The schedule performance index .8 0 SPI Poor that indicates good performance and (SPI) is a measure of the conformance .60 CPI use the color green to indicate on tar- of actual progress to the schedule: SPI get and good (better than target) per- Time = EV / PV. For the above project, SPI = formance. We can break the poor $40,000 / $50,000 = 0.80. performance area into two and use Figure 7 . CPI and SPI Graph Performance indices can be the color yellow to indicate somewhat thought of as efficiency ratios. In the SPI being close to target, or, if one of below target performance, and the above formulas, 1.00 indicates that these indices suggests poor perform- color red to indicate poor perform- performance is efficient and on target. ance, the other must be indicating ance. It is important for the organiza- More than 1.00 indicates excellent, good performance. This allows some tion to carefully establish meaningful highly efficient performance, and less trade-offs to reach the desired project thresholds, acceptable tolerances, or than 1.00 indicates poor, inefficient goals. critical limits for action on project performance. A CR of more than 1.00 indicates performance. This helps ensure that The inverse of the formulas given that the overall project performance is when action is needed, it is highlight- above has also been used (Anbari, excellent. This may result from both ed, and when action is not needed, 1980; Egan, 1982; Cioffi, 2002; the CPI and SPI being better than tar- tampering and micromanagement are Webster, 2002). This facilitates use of get, or, if one of these indices is indi- minimized. the indices in forecasting. Using the cating poor performance, the other For example, performance indices inverse definition, the CPI for the must be indicating outstanding per- and critical ratios of 1.00 or above can above project would be $60,000 / formance. This allows extensive trade- be considered green; performance $40,000 = 1.50, indicating that the offs to reach the desired project goals. indices and critical ratios equal to or project is running 50% over budget. A CR of less than 1.00 indicates greater than 0.80, but less than 1.00, Completion of the project would be that the overall project performance is can be considered yellow; and per- forecasted at $150,000, if performance poor. This may result from both the formance indices below 0.80 can be continues at this rate. Similarly, the SPI CPI and SPI being worse than target, considered red. In this paper, a black would be $50,000 / $40,000 = 1.25, or, if one of these indices suggests and white chart depicting this concept indicating the project is running 25% good performance, the other must be is shown in Figure 9, and is called the behind schedule. The project would be indicating extremely poor perform- target performance chart. It can be pro- forecasted to take 25% longer than the ance. This limits the use of effective duced in color and may also be nick- original schedule, with completion at trade-offs, and highlights significant named the rainbow chart. 1.25 x 40 weeks = 50 weeks, if per- difficulty in attempting to reach the O ther colors can also be added. formance continues at this rate. These desired project goals. For example, orange or amber can be forecasts are discussed in more detail A graph of the critical ratio over used between yellow and red, or in the in the forecasting section of this paper. time provides a quick indicator of yellow area to indicate that the item in Graphs of performance indices trends in the overall project perform- trouble has been previously reviewed. over time provide valuable indicators ance, and of the impact of any correc- Blue can be used to indicate the super- of trends in project performance and tive actions. These graphs may be very stars— items with performance indices the impact of any corrective actions. effective in project reviews (Figure 8). above 1.20, for example (Figure 9). These graphs can be very effective in Some may say that such superstar project reviews (Figure 7). items must have had inflated baseline budgets and schedules. However, there 1.4 The Critical Ratio Good may be important lessons to be 1.2 The critical ratio (CR) is the product of learned from these items in terms of 1.0 CR CPI and SPI (Anbari, 2001; L ewis, estimating, budgeting, performance .8 0 Poor 2001). It can also be called the cost- management, and cost control. .60 schedule index (CSI) (Barr, 1996; CR Reallocation of organizational Meredith & Mantel, 2000). It is used as Time resources may be another outcome an indicator of the overall project from such analyses (L ewis, 2001). health: CR = CPI x SPI. For the above Figure 8 . CR Graph An activity, work package, or proj- project, CR = 0.67 x 0.80 = 0.53. ect should be carefully reviewed when A CR of 1.00 indicates that the Q uantifying the Traffic L ight A pproach it enters the yellow zone, with the overall project performance is on tar- Graphs of CPI, SPI, and CR can be intent of finding the root cause(s) of get. This may result from both CPI and used to further highlight these meas- performance or planning problems December 2003 Project Management Journal • 15
  • 5. PMI-002 11/5 11/6/03 9:20 AM Page 16 and eliminating them. When an item affecting the activity, work package, or ciencies observed to date will prevail to in the red zone is reviewed, this should project, a new ETC needs to be devel- completion, the EAC3 is the sum of generally be a status report on oped; EAC1 is the sum of the cumula- the cumulative AC plus the original action(s) taken or not taken when that tive AC plus the ETC. As a formula, budget for the remaining work (BAC – item was in the yellow zone. When an EAC1 = AC + ETC. For the example EV), modified by a performance factor, item enters the blue zone, it also project used in this paper, EAC1 = which is usually the cumulative CPI. would be appropriate to review it, to $60,000 + ETC. This applies where As a formula, EAC3 = AC + (BAC – EV) obtain information on the root ETC is developed for the remaining / CPI. For the above project: cause(s) of the super performance, and work. EAC1 may also be called the EAC3 = $60,000 + ($100,000 – incorporate the lessons learned into revised cost estimate (RCE), latest $40,000) / 0.67 future work. revised estimate (LRE), or current = $60,000 + $60,000 / 0.67 working estimate (CWE). = $60,000 + $90,000 Using the above assumption, the = $150,000 ETC for the remainder of the activity, The above formula can be 1.4 work package, or project usually is simplified as follows: CPI, SPI, and CR Super Stars 1.2 G ood developed using various cost estimat- EAC3 = AC + (BAC – EV) / CPI 1.0 Caution ing methods. Because the work already = AC + BAC / CPI – EV / CPI .80 SPI is in progress, a detailed, bottom-up = AC + BAC / CPI – AC .60 CPI Poor CR cost estimate for the remaining work is = BAC / CPI Time common in this case. Thus: When current analysis shows that EAC3 = BAC / CPI Figure 9 . Target Performance Chart past performance is not a good predic- The definition of EAC3 can there- tor of future performance, that prob- fore be simplified to equal the original Forecasting lems or opportunities which affected BAC divided by the CPI. For the above Project management is primarily con- performance in the past will not occur project, EAC3 = $100,000 / 0.67 = cerned with decisions affecting the in the future, and that future perform- $150,000. EAC3 may also be called the future. Therefore, forecasting and pre- ance will parallel the original plan, the statistical estimate at completion diction are extremely important EAC2 is the sum of the cumulative AC (EACstat), the mathematical estimate at aspects of project management. EVM is plus the original budget for the completion (EACmath), or simply the particularly useful in forecasting the remaining work (BAC – EV): EAC2 = cost at completion (CAC). cost and time of the project at comple- AC + BAC – EV. For the above project, Using the above assumption, the tion, based on actual performance up EAC2 = $60,000 + $100,000 – $40,000 estimated cost to complete the remain- to any given point in the project. = $120,000. der of the activity, work package, or The above formula can be simpli- project is the original budget for the Forecasting of Cost at Completion fied as follows: remaining work divided by the CPI. As The EAC may also be called cost esti- EAC2 = AC + BAC – EV a formula, ETC = (BAC – EV) / CPI. mate at completion (CEAC). The esti- = BAC + (AC – EV) This may be called statistical estimate mated cost to complete the remainder = BAC – (EV – AC) to complete (ETCstat) or the mathe- of the project is usually called the esti- = BAC – CV matical estimate to complete mate to complete (ETC). Both can be Thus: (ETCmath). developed using various cost estimat- EAC2 = BAC – CV A graph of the EAC over time ing methods or calculated mathemati- The definition of EAC2 can there- provides a valuable indicator of cally using EVM. fore be simplified to equal the original trends in project cost performance EACs may differ based on the baseline BAC minus the CV. For the and the impact of any corrective assumptions made about future per- above project, EAC2 = $100,000 – (- actions. This graph can be particular- formance. The PMBOK® Guide (Project $20,000) = $100,000 + $20,000 = ly effective in project reviews. Figure Management Institute, 2000) provides $120,000. 10 shows a graph of EAC for the three such estimates, based on three Using the above assumption, the example project used in this paper, different assumptions. In this section, ETC for the remainder of the activity, using the above assumption. these estimates are reviewed, simpli- work package, or project is the original fied and enhanced. They are given a budget for the remaining work (BAC – Additional Forecasts of Cost sequential subscript to differentiate EV). at Completion among them. When current analysis shows that Other assumptions can be made about When current analysis shows that past performance is a good predictor future performance and may result in the assumptions underlying the origi- of future performance, that perform- different estimates at completion. In nal estimate are flawed, or no longer ance to date will continue into the this section, other assumptions and applicable due to changed conditions future, and that efficiencies or ineffi- the resulting EACs are presented. They 16 • Project Management Journal December 2003
  • 6. PMI-002 11/5 11/6/03 9:20 AM Page 17 it acknowledges that cost management higher than the original baseline BAC. 160 and schedule management are insepa- As a formula, EAC6 > > BAC. This esti- EAC 140 rable (Kerzner, 2001). As examples: mate is generally not quantified, but is Poor Project schedules can be crashed at an referred to by project team members EAC ($000) 120 BAC 100 additional cost, or less skilled with statements such as: “If you think 80 Good resources may be used on the project, this is bad, wait till you see the next 60 which may reduce the cost and possi- report! Y ou ain’t seen nothing yet! ” or bly extend the duration. “The cost is going sky high. If this Time The assumption implied by the project ever finishes, it would be a above formula is that if the activity, miracle! ” Figure 10. EAC Graph work package, or project were behind This case may result from delaying are given a continuing sequential sub- schedule, additional cost would be corrective action and believing for too script to differentiate among them. incurred to bring the project back on long that the actual cost at completion In some organizations, it is com- schedule, through the use of overtime, somehow would end up close to the mon to state that the activity, work additional resources, expediting ship- original baseline BAC, regardless of package, or project will meet the orig- ments, and similar actions. On the prior poor performance. Higher costs, inal targets upon completion, regard- other hand, if the activity, work pack- lower levels of accomplishment, and less of prior performance. This age, or project were ahead of schedule, inefficient spending patterns become frequently occurs early in the project opportunities for significant cost sav- practically irreversible and the project’s when prior performance has been ings may be pursued, although they fate is sealed. Statistics of challenged poor. The EAC4 would be the original may require more time as a result of and failed projects testify that this case baseline BAC. As a formula, EAC4 = using resources that are fewer in num- is much more common than we would BAC. Statements such as the following ber, less experienced, and/or less like to believe. may be heard: “We had some mobi- skilled. Additional time may also be lization problems, but we took care of required to find better prices for equip- EACs them. We expect the project to finish ment and material, negotiate better 160 on schedule and on budget.” or “The contract terms, use more economical 140 EACs ($000) original specs were unclear. So we shipping methods, or take similar 120 Poor BAC took additional time to clarify them. actions. This formula may provide a 100 We are planning to meet project tar- better indication of estimated cost at 80 Good gets at this time.” completion, when adherence to a 60 The above statements should be schedule is critical to the organization. Time challenged firmly, with a response Using the earlier definition of CR such as: “What we hear you say is that = CPI x SPI, and further defining EAC5 Figure 11. EACs Graph future performance will be so much or EACs as the EAC adjusted for sched- better than the original plan and will ule performance, the above formula The Standish Group conducted make up for prior cost overruns (and can be restated as follows: EAC5 = surveys and interviews to explore what delays). So far, we have not performed EACs = BAC / CR. For the above proj- causes information technology (IT) to the original plan and would like to ect, EAC5 = EACs = $100,000 / 0.53 = software development projects to be know how this superior performance $187,500. challenged and why these projects fail. will be achieved.” Using the above assumption, the These studies classified projects into EAC 4 is rarely achieved. ETC for the remainder of the activity, three types: Unmanaged projects do not fix them- work package, or project is the original Successful: The project is complet- selves. They only tend to overrun budget for the remaining work divided ed on time and on budget, with all fea- their budgets, fall behind their sched- by the CR: (BAC – EV) / CR. This may tures and functions as originally ules, and often miss other scope and be called the ETC adjusted for schedule specified; quality targets. performance (ETCs). A graph of the Challenged: The project is com- Heinze (1996) provides the follow- EACs over time provides a valuable pleted and operational but is over ing additional formula for calculating indicator of trends in project cost per- budget, beyond the time estimate, and the EAC: EAC = BAC / CPI x SPI. formance and the impact of any cor- offers fewer features and functions Fleming & Koppelman (2000) provide rective actions. This graph can be very than initially specified; a similar formula and support it by effective in project reviews. Figure 11 Failed: The project is canceled indicating that there is a human ten- shows a graph of EACs for the example before completion. dency to get back on schedule, even if project used in this paper, using the The Standish Group study con- that requires more resources for the above assumption. ducted in 1994 and published in 1995 same work. The above formula may be A case that is not often mentioned (The Standish Group, 1995) had a mathematically questionable. However, occurs when the EAC6 is substantially total sample of 365 respondents repre- December 2003 Project Management Journal • 17
  • 7. PMI-002 11/5 11/6/03 9:20 AM Page 18 senting 8,380 projects. The results of A graph of the VAC over time pro- weeks, meaning that the cumulative AT that research showed that 16% of IT vides a valuable indicator of trends in is 20 weeks. Therefore: TEAC1 = 20 + projects were successful, 53% were project cost performance and the TETC weeks. In this case, TETC needs challenged, and 31% failed. impact of any corrective actions. This to be developed for the remaining Comparisons to subsequent studies graph can be effective in project work. TEAC1 may also be called the are shown in Table 2 (The Standish reviews. Figure 12 shows a VAC graph revised schedule or current schedule. Group, 1999): for the example project used in this When current analysis shows that paper, using the above assumption. past schedule performance is not a good predictor of future schedule per- Y ear of Study Successful Challenged F ailed Completion Time Forecasting formance, that problems or opportuni- 19 9 4 16% 53 % 3 1% EVM has not been widely used to esti- ties which affected schedule 19 9 6 27 % 33% 40% mate the total time at completion, performance in the past will not occur 19 9 8 26% 46% 28% total project duration, or schedule for in the future, and that future schedule Table 2. Project Resolution H Istory an activity, work package, or project performance will parallel the original based on actual performance up to a plan, TEAC2 is the sum of the cumula- The Treasury Board of Canada given point in the project. However, tive AT plus the original scheduled Secretariat (2000–2002) supported using assumptions and logic similar to time for the remaining work. This can findings of The Standish Group, indi- those discussed above, the project’s be simplified to the original baseline cated similarities to results of reviews time estimate at completion (TEAC) SAC minus the TV (Fleming & of Canadian government IT projects and time variance at completion Koppelman, 2000). As a formula, and presented a framework for the (TVAC) can be calculated based on the TEAC2 = SAC – TV. For the above proj- management of these projects. baseline schedule at completion (SAC) ect, TEAC2 = 40 – (-4) = 40 + 4 = 44 A survey of IT projects by Sauer and actual performance up to any weeks. and Cuthbertson (2002) covered vari- given point in the project (Anbari, The above is the total estimated ous industry sectors and government 2001 and 2002). schedule duration that would have in the United Kingdom, and had a been obtained using the critical path usable sample size of 565 projects. It method (CPM) or the program evalua- showed that 5% of all projects were 40 tion and review technique (PERT), if reported to have been abandoned 20 Good the schedule slippage of four weeks VAC ($000) prior to or during implementation, 0 were on the critical path. 55% of projects exceeded budget, 27% -20 When current analysis shows that Poor came in exactly on budget, and 8% -40 past schedule performance is a good came in below budget. Performance, VAC predictor of future schedule perform- measured by attainment of initially Time ance, that performance to date will agreed upon specifications, averaged continue into the future, and that above 80%. Across the whole sample, Figure 12. VAC Graph schedule efficiencies, or inefficiencies, 56% delivered 90% to 99% of the observed to date will prevail to com- specifications, approximately 20% of In this section, various time esti- pletion, TEAC3 is the sum of the projects delivered less than 80% of the mates are presented and given a cumulative AT plus the original sched- specifications, and a sprinkling of proj- sequential subscript to differentiate uled time for the remaining work, ects exceeded the specifications. among them, following the same pat- modified by the cumulative SPI. This tern used previously for the cost esti- can be simplified to the original base- Variance at Completion: mate at completion. line SAC divided by the SPI. As a for- The variance at completion (VAC) When current analysis shows that mula, TEAC3 = SAC / SPI. For the gives an indication of the estimated assumptions underlying the original above project, TEAC3 = 40 / 0.80 = 50 cost underrun or overrun at the com- time estimate were flawed or no longer weeks. pletion of the project. As a formula, applicable due to changed conditions The above example indicates that VAC = BAC – EAC. For the above proj- affecting the activity, work package, or the project is estimated to be complet- ect, using BAC = 100,000 and EAC3 = project, a new schedule, duration esti- ed 25% behind schedule: (40 weeks – 150,000, VAC = 100,000 – 150,000 = mate, or time estimate to complete 50 weeks) / 40 weeks = -10 weeks / 40 -50,000. (TETC) needs to be developed, and the weeks = -0.25 = -25%. In the above equation, 0 indi- TEAC1 is the sum of the cumulative AT A graph of the TEAC over time cates that the project is forecasted to plus the TETC. As a formula, TEAC1 = provides a valuable indicator of be completed on budget. A positive AT + TETC. trends in project schedule perform- value indicates a forecasted under- The example project used in this ance and the impact of any corrective run. A negative value indicates a paper has an original baseline SAC of actions. This graph can be effective in forecasted overrun. 40 weeks, and its status date is 20 project reviews. Figure 13 shows a 18 • Project Management Journal December 2003
  • 8. PMI-002 11/5 11/6/03 9:20 AM Page 19 graph of TEAC, for the example proj- prices for equipment and material, of prior poor performance. Longer ect used in this paper, using the above negotiate better contract terms using durations, lower levels of accomplish- assumption. more economical shipping methods, ment, and inefficient schedule achieve- and similar actions. On the other ment patterns become practically hand, if an activity, work package, or irreversible, and the project’s fate is 52 TEAC project were running below budget, sealed. Statistics of challenged and 48 opportunities for reducing completion failed projects testify that this case is TEAC (Weeks) 44 Poor time, reducing cycle time, and expedit- much more common than we would SAC 40 ing time to market may be pursued, like to believe, as previously discussed 36 Good although they may incur more cost. in the development of EAC6. 32 This may be accomplished through the use of overtime, additional resources, Time 70 TEACc and expediting shipments. 60 D efining TEAC5 or TEACc as the TEACc (Weeks) Figure 13. TEAC Graph 50 Poor TEAC adjusted for cost performance, SAC 40 In some organizations, it is com- the following formula would reflect 30 Good mon to state that the activity, work the above assumption: TEAC5 = 20 package, or project will be on schedule TEACc = SAC / CR. For the above proj- upon completion, regardless of prior ect, TEAC5 = TEACc = 40 / 0.53 = 75 Time performance. This frequently occurs weeks. This formula may provide a bet- early in the project, when prior sched- ter indication of estimated time at Figure 14. TEACc Graph ule performance has been poor. The completion, when adherence to budg- TEAC4 would be the original baseline et is critical to the organization. TEAC5 Time variance at completion: The SAC. As a formula, TEAC4 = SAC. may also be called the time estimate at TVAC gives an indication of the esti- Statements similar to those mentioned completion adjusted for cost perform- mated amount of time that the project earlier in the cost discussion may be ance (TEACc). will be completed ahead or behind heard. In some disciplines, such as A graph of TEACc over time pro- schedule: TVAC = SAC – TEAC. For the software development, it is common vides a valuable indicator of trends in above project, using SAC = 40 and to conclude these statements saying, project schedule performance and the TEAC3 = 50: TVAC = 40 – 50 = -10 “We’ll catch up during the testing impact of any corrective actions. This weeks. phase!” Several modifiers to the word graph can be very effective in project In the above equation, 0 indicates “test” have been developed, which may reviews. Figure 14 shows a graph of that the project is expected to be com- increase the likelihood of catching up. TEACc, for the example project used pleted on schedule. A positive value They include: alpha test, beta test, user in this paper, using the above indicates that the project is expected to test, stress test, acceptance test, and assumption. be completed ahead of schedule. A parallel test. Such statements should A case that is not mentioned negative value indicates that the proj- be challenged firmly, with a response often occurs when the TEAC6 is sub- ect is expected to be completed behind similar to that mentioned earlier in the stantially higher than the original schedule. cost discussion. baseline SAC. As a formula, TEAC6 > > A graph of TVAC over time pro- TEAC4 is rarely achieved. Again, SAC. This estimate is generally not vides a valuable indicator of trends unmanaged projects do not fix them- quantified, but is referred to by proj- in project schedule performance and selves. They only tend to fall behind ect team members with statements the impact of any corrective actions. their schedules, overrun their budgets, similar to those mentioned earlier in This graph can be effective in project and often miss other scope and quality the cost discussion. At times, this case reviews. Figure 15 shows a graph of targets. occurs in the later phases of a project, TVAC, for the example project used Recalling that cost performance when team members have no other in this paper, using the above and schedule performance are insepa- planned assignments, and the organi- assumption. rable, the assumption can be made zation is “right sizing.” Q uality prob- that if an activity, work package, or lems become apparent, and CPM, PERT, and EVM project were running over budget, additional time is requested to fix var- As mentioned above in the develop- additional time may be needed to ious problems. Sometimes a lot of ment of TEAC2, an underlying bring the project back on budget. This additional time is needed. assumption of the CPM and the PERT may be accomplished by reducing Again, this case may result from is that future performance will parallel resources applied to the project, using delaying corrective action and believ- the original plan, unless changes are fewer paid resources, many of which ing for too long that the project would made to the original plan time, logic, are less experienced and less skilled, somehow be completed close to the or cost. taking additional time to find better original baseline schedule, regardless The example project used in this December 2003 Project Management Journal • 19
  • 9. PMI-002 11/5 11/6/03 9:20 AM Page 20 paper has an original baseline SAC of meetings. Both mathematical forecasts % Complete = $40,000 / $100,000 40 weeks. With a status date of 20 and subjective forecasts would be = 0.40 = 40% weeks, TV = -4 weeks. If TV represented included in project performance % Spent = $60,000 / $100,000 a schedule slippage of 4 weeks on the reports. This effort highlights perform- = 0.60 = 60% critical path, CPM and PERT would esti- ance deviations for work area man- CPI = % Complete / % Spent mate a completion time of 44 weeks. agers, encourages them to consider = 40 / 60 = 0.67 This is the same as: TEAC2 = SAC – TV appropriate, timely actions, and incor- The above allows a further = 40 – (-4) = 40 + 4 = 44 weeks. porates their close, detailed knowledge simplification of performance in their areas, which (Slemaker, 1985) of the EAC3: may not be evident from the reported EAC3 = BAC / CPI values. At a minimum, this effort may = BAC / (% Complete / 10 help avoid surprises and arguments % Spent) TVAC (Weeks) 5 Good over the numbers during project = (BAC x % Spent) / 0 review meetings. % Complete -5 Poor Forecasting in project manage- = AC / % Complete -10 TVAC ment may well be a self-defeating Thus: EAC3 = AC / % Complete Time prophecy, and that may be good for The definition of EAC3 can be fur- the organization. Large deviations usu- ther simplified to the AC divided by ally attract management’s attention the percent complete. For the above Figure 15. TVAC Graph and result in corrective action. Small project, EAC3 = $60,000 / 0.40 = CPM and PERT initially assume deviations are usually left alone. By $150,000. that problems or opportunities that quantifying and highlighting such Similarly, the TEAC3 can be sim- affected performance in the past will deviations, EVM helps focus manage- plified to: TEAC3 = AT / % Complete. not occur in the future and that past ment’s interest on projects or work The example project used in this paper performance is not a good predictor of packages that need the most attention. has an original baseline SAC of 40 future performance. As a result, EVM supports effective weeks, and the status date is 20 weeks, The assumption generally associ- management of projects and work which means that the cumulative AT is ated with EVM is that past perform- packages collectively and enhances 20 weeks. Therefore: TEAC3 = 20 / 0.40 ance is a good predictor of future management of the enterprise’s project = 50 weeks. performance, that performance to date portfolio (Anbari, 1983). Forecasting Similarly, the following is derived will continue into the future, and that using these techniques provides a uni- (Anbari, 1980): efficiencies or inefficiencies observed form approach to project reviews, CPI = % Complete / % Spent to date will prevail to completion. building confidence in the project out- = (Actual Production / Therefore, the EAC3 is generally asso- come as time progresses. Changing Total Scope) / ciated with EVM. Similarly, the TEAC3 project evaluation methods during the (Actual Cost / can be associated with EVM. project duration can result in no Total Budget) Therefore: TEAC3 = SAC / SPI = 40 / meaningful data for decision-making. = (Actual Production / 0.80 = 50 weeks. Total Scope) x Which of the above forecasts will Further Ex tensions, Issues (Total Budget / materialize depends greatly on deci- and Applications Actual Cost) sions and actions taken by the project = (Total Budget / manager, the project team, and the Extensions Total Scope) x organization. Some like to add luck to Using the above definitions, the fol- (Actual Production / the factors affecting project outcomes. lowing is derived (Slemaker, 1985): Actual Cost) Others observe that good luck tends to % Complete = EV / BAC = (Total Budget / be directly associated with better plan- % Spent = AC / BAC Total Scope) / ning and better decisions. Taking the ratio of the above two (Actual Cost / formulas Actual Production) Project Forecasting (Anbari, 1980): = Planned Unit Cost / It is advisable to ask work package % Complete / % Spent Actual Unit Cost managers, project leaders, and func- = (EV / BAC) / (AC / BAC) Thus: CPI = Planned Unit Cost / tional managers to review cost and = EV / AC Actual Unit Cost schedule mathematical forecasts and = CPI The additional formulas devel- to provide their own subjective fore- Thus: oped in this section provide a more casts for their own work areas in CPI = % Complete / % Spent intuitive understanding of CPI based advance of issuing project performance For the example project used in on information readily available in reports and conducting project review this paper: many organizations. The first formula 20 • Project Management Journal December 2003
  • 10. PMI-002 11/5 11/6/03 9:20 AM Page 21 for CPI uses information widely ble, collecting 50% of the contract centage of the value associated with known in project environments, and price for each of these items. the milestone based on subjective esti- the second formula for CPI uses infor- The 0/100 rule can also be used. mates. When the predefined, tangible mation widely known in production This rule specifies that the value is criteria for the milestone are met, the environments: earned only when the item is complet- balance of the value associated with CPI = % Complete / % Spent ed and is usually used in work pack- the milestone is earned (Fleming & CPI = Planned Unit Cost / ages having a short duration (Kerzner, Koppelman, 2000). These approaches Actual Unit Cost 2001). This rule can also be called the may help alleviate the “95% complete weighted milestone method, where the and stays there forever” syndrome. Issues in the Determination of value is earned only when the mile- For level of effort items such as Percent Complete stone is physically completed, and one project management, customer sup- Determination of the percent complete or more milestones are planned in port, and other support work during a or proportion complete of an activity, each performance-reporting period given period of time in a project, the work package, or project is a necessary (Fleming & Koppelman, 2000). effort itself is the end product. but challenging task in many organiza- Contractors may consider the 0/100 Therefore, the earned value can be con- tions. This task becomes even more rule harsh. When a contractor is paid sidered to be equal to the effort demanding when dealing with new, based on this rule, it is reasonable to applied or the actual cost. emerging, or softer technology proj- expect that the contractor will strive to ects, such as telecommunications, soft- have a very detailed WBS that breaks Applications ware development, architectural or the project down to as many items as EVM provides project managers and engineering design, and research and possible, so that completion of item(s) the organization with triggers or early development. can be shown regularly and payment warning signals that allow them to take Alternatives to using the percent can be authorized. timely actions in response to indicators complete to determine physical Other alternatives for determining of poor performance and enhance the accomplishments have been used. The physical accomplishments can be opportunities for project success. Such 50/50 rule specifies that 50% of an used. For example, the 10/90 rule, indicators have been found to be reli- item’s budget is recorded at the time 20/80 rule, and 25/75 rule acknowl- able as early as 15% into a project. that the work is scheduled to begin, edge that to start a work package, a cer- Better planning and resource allocation and the remaining 50% is recorded tain amount of preparation and associated with the early periods of a when the work is scheduled to be com- mobilization are needed. Therefore, project might be the cause of this relia- pleted. If the project had a large num- 10%, 20%, or 25% of the value would bility (Fleming & Koppelman, 2000). ber of items, the distortion from the be considered earned when the work is EVM can be used for progress pay- 50/50 rule would be minimal started, and the remaining amount ments to contractors based on the EV (Kerzner, 2001), because these items would be earned when the work is of contracted or outsourced work. would be at various stages of comple- completed. If the work package were Because such contractual arrangements tion. This allows us to calculate PV. front-end loaded, as might be the case create legal and financial obligations, it Similarly, to calculate EV, 50% of an with certain equipment acquisitions, is important to consider the method item’s budget is recorded when the then the inverse of these rules might be specified for evaluating progress. The work begins, and the remaining 50% is appropriate. For example, the 75/25 previously discussed alternatives for recorded when the work is completed. rule might specify that 75% of the determination of percent complete To make the 50/50 rule work success- value would be considered earned should be carefully considered and fully, the project should be broken when the equipment is delivered, and negotiated to achieve a fair and equi- down into very detailed, short-span the remaining amount is earned when table environment that encourages suc- work packages (Fleming & installation, testing, and commission- cessful accomplishment of contracted Koppelman, 2000). ing are completed. or outsourced project items. The 50/50 rule is a common prac- The percent complete method can For long-term projects, it may be tice in a number of contractual be used with a buffer that sets a ceiling appropriate to consider incorporating arrangements, such as those for home of about 80% or 90% upon reported the time value of money and time-dis- repair. Half of the contract price is completion. A work package may earn counted cash flows into EVM. Inflation paid up front, and the remaining bal- only up to the specified percent ceiling can be explicitly considered in EVM, ance is paid upon completion of the based on subjective estimates. When and the inflation variance (IV) can be work. It should be noted that when the work package is 100% complete, calculated (Farid & Karshenas, 1988). the 50/50 rule is used in a contractual the balance is earned. A variation of However, these considerations add arrangement and the contractor is this approach is using a combination complexity to the method and may be paid based on this rule, it is reason- of the percent complete and a mile- justifiable only for very long-term proj- able to expect that the contractor will stone gate. A work package may earn ects or in very high inflation periods or tend to start as many items as possi- only up to a maximum specified per- economies. December 2003 Project Management Journal • 21
  • 11. PMI-002 11/5 11/6/03 9:20 AM Page 22 An organization may elect to 0.67 = $150,000 Analysis Method [ CD-ROM] . apply EVM uniformly to all of its proj- EAC3 = AC / % Complete = 60,000 / Proceedings of the Project Management ects, or only to projects exceeding its 0.40 = $150,000 Institute 2 0 0 1 Seminars & Symp osium, own thresholds for cost and schedule VAC = BAC - EAC = $100,000 - N ovember 1-10, 2001, N ashville, TN , reporting and control. EVM can be $150,000 = -$50,000 USA. N ewtown Square, PA: Project applied to projects of various types and Management Institute. sizes in the public and private sectors. EAC5 = EACs = BAC / CR = $100,000/ Anbari, F.T. (2002). Q uantitativ e It can be applied at various levels of a 0.53 = $187,500 Methods for Project Management, Second project’s WBS and to various cost com- Edition. N ew York, N Y: International ponents, such as labor, material and TEAC3 = SAC / SPI = 40 weeks / Institute for Learning. subcontractors. 0.80 = 50 weeks Barr, Z . (1996). Earned Value TEAC3 = AT / % Complete = 20 / Analysis: A Case Study. PM N etwork , X Comprehensive Example 0.40 = 50 weeks (12), 31-37. A project has a baseline BAC of TVAC = SAC – TEAC = 40 weeks – Cioffi, D. F. (2002). Managing $100,000 and a baseline SAC of 40 50 weeks = -10 weeks Project Integration. Vienna, VA: weeks. The baseline indicates that by Management Concepts. the end of week 20, the project is Conclusion Cleland, D.I., & King, W.R. planned to be 50% complete. At the EVM helps focus management’s inter- (Editors). (1988). Project Management end of week 20, it is reported that 40% est on projects that need most atten- H andb ook , (2nd. Ed.). N ew York, N Y: of the project work has been complet- tion and may aid the prioritization and Van N ostrand Reinhold. ed at a cost of $60,000. Using the EVM emphasis management gives projects Egan, Jr., D.S. (1982). The method: within a portfolio, enhancing the Performance Index: Combining Cost BAC = $100,000 enterprise’s project portfolio manage- and Production Data to Show How SAC = 40 weeks ment. EVM provides important infor- Good (or Bad) Your Project Really Is!! mation for project or work package Proceedings of the 7 . Internet W orld PV = 50% x $100,000 decision-making. Its wider acceptance C ongress on Project Management, 1982, = $50,000 and effectiveness may depend on bet- Copenhagen, Denmark, PROJEKT- AC = $60,000 ter understanding of its capabilities. PLAN , The Danish Project EV = 40% x $100,000 Simplification of EVM calculations, Management Society, The Danish = $40,000 use of graphical tools to enhance Technical Press, Denmark, 355-364. AT = 20 weeks understanding of performance trends, Farid, F., & Karshenas, S. Therefore: and successful application of EVM in (N ovember, 1988). Cost/Schedule % Complete = EV / BAC industry are important factors for the Control Systems Criteria Under = $40,000 / $100,000 = 40% growth and effective use of this valu- Inflation. Project Management Journal, % Spent = AC / BAC = $60,000 / able method in project management. X IX (5), 23-29. $100,000 = 60% Fleming, Q.W., & Koppelman, J.M. References (2000). E arned V alue Project CV = EV – AC = $40,000 – Anbari, F.T. (1980). An Operating Management, (2nd Ed.). N ewtown $60,000 = -$20,000 Management Control System for Large Square, PA: Project Management SV = EV – PV = $40,000 – Scale Projects. Unpublished paper pre- Institute. $50,000 = -$10,000 sented at The Decision Sciences Institute Heinze, K. (1996). C ost N inth Annual Meeting, N ortheast Management of C ap ital Projects. N ew PV Rate = BAC / SAC = $100,000 / R egional C onference, Philadelphia, PA. York: Marcel Dekker, Inc. 40 weeks = $2,500 per week Sponsored by the N ortheast Decision Kerzner, H. (2001). Project TV = SV / PV Rate = - $10,000 / Sciences Institute. Management: A Systems Ap p roach to $2,500 per week = -4 weeks Anbari, F.T. (1983). An Operating Planning, Scheduling, and C ontrolling, System for Forecasting Project Cost at (7th Ed.). N ew York, N Y: John Wiley & CPI = EV / AC = $40,000 / Completion. Unpublished paper pre- Sons. $60,000 = 0.67 sented at The Third International Kim, E.H. (2000). A Study on the CPI = % Complete / Symp osium on F orecasting, Philadelphia, E ffectiv e Imp lementation of E arned V alue % Spent = 40% / 60% = 0.67 PA. Abstract in Program sponsored by Management Methodology, Unpublished SPI = EV / PV = $40,000 / The International Institute of doctoral dissertation. The George $50,000 = 0.80 Forecasters in collaboration with the Washington University, Washington, Wharton School, University of DC. CR = CPI x SPI = 0.67 x 0.80 Pennsylvania, Philadelphia, PA. Lewis, J.P. (2001). Project Planning, = 0.53 Anbari, F. T. (2001). Applications Scheduling, & C ontrol: A H ands-On EAC3 = BAC / CPI = $100,000 / and Extensions of the Earned Value Guide to Bringing Projects In On Time 22 • Project Management Journal December 2003