SlideShare a Scribd company logo
1 of 22
Download to read offline
KYAMBOGO UNIVERSITY
FOURTH-YEAR PROJECT REPORT
TOPIC:
CONSTRUCTION-RELATED REWORK AND ITS IMPACT ON
COST AND SCHEDULE: A CASE STUDY, KAMPALA CAPITAL
CITY AUTHORITY
BY
KALEMA SOLOMON WASAJJA
REG NO: 17/U/8331/ECE/PE
SUPERVISOR
ACHIRE MICHAEL WEST (GMUIPE)
JULY, 2022
SUMMARY OF THE PRESENTATION
• Introduction
• Statement of the problem
• Objectives
• Conceptual framework
• Methodology used
• Result and Discussion
• Conclusions and Recommendations
INTRODUCTION
Globally, in Ukraine’s construction industry, there is a trend of rework being
accepted as an integral part of construction activities (Trach et al, 2019).
On the African continent, studies have shown that all the elements of the building
had a direct bearing on an increase in the final cost of the project because of
rework (Oyewobi 2010).
In Uganda, Rework has been known to contribute to waste and value losses in
building design and construction (Kakitahi et al. 2013), and it has been considered
one of the key factors responsible for the cost and schedule overruns in
construction projects.
INTRODUCTION CONT….
Rework has been linked to waste and value loss in building design and construction
in Uganda (Kakitahi et al. 2013), and it has been identified as one of the primary
causes of cost and schedule overruns in building projects.
Alinaitwe (2014) also demonstrated that design omissions, poor workmanship, and
insufficient contractor supervision could be blamed for construction-related rework,
with consequences ranging from project schedule creep to client directives that
altered the scope of the task, coupled with client payment delays and site handover
delays.
The aim of this study, therefore, is to identify and evaluate the critical factors that
bring about rework and how it affects construction Cost and Schedule based on the
KIIDP2 project in KCCA.
Many economies rely heavily on the building industry. In Uganda, the sector accounts for more
than 12% of the country's GDP and has grown steadily over the years (Alinaitwe, 2021). The
sector has made significant strides in terms of capacity development and performance
enhancement (Joseph et al, 2018).
Despite its positive potential, the sector confronts significant barriers in failing to properly
transform investment opportunities into employment creation and national productivity
(Ntungire, 2018).One of the pertinent issues causing this is 'rework.’
It has an impact on time, cost, quality, and practically every other project success criterion
(Rezahoseini, et al, 2019). Rework is linked with higher expenses, while being responsible for
Schedule overruns and delays.
However, little is known about the history, causality and consequently, its impact on
Construction Schedule and Cost. Accordingly, the study attempted to undertake a
comprehensive assessment of past studies by various authors in order to evaluate the primary
consequences of rework on construction cost and schedule on the KIIDP2 project in KCCA
STATEMENT OF PROBLEM
OBJECTIVES OF THE STUDY
• General Objective
To investigate the impact of construction-related Rework on cost and schedule.
• Specific objectives
(i) To identify the causes of Rework on construction projects.
(ii) To ascertain the effects of Rework on construction cost and schedule.
(iii)To propose strategies on how to minimize the impact of Rework on Cost and
schedule
CONCEPTUAL FRAMEWORK
Conceptual framework; by the researcher
Research Approach
A mixed method paradigm (quantitative and qualitative research approaches) in
examining the impact of Rework on Construction Cost and Schedule was adopted.
Research Design
A descriptive design was used to collect current data and establish the relationship
between variables.
Study Area
The study was carried out within Kampala Capital City Authority located in central
Uganda.
Study Population
From a study population of 47 and using Morgan’s tables, a sample size of 42
respondents was considered.
METHODOLOGY SLIDES
Study tools
Questionnaires- this was the main tool for the study, arranged on a 5-Linkert scale.
Questionnaires were administered to all participants.
Interview Guides- semi-structured guides was prepared and administered to the
respondents.
Data Tools Quality
The tools were tested for:
Validity-using Face Validity and Content Validity tests
Reliability-using SPSS to test for Cronbach’s Alpha values
These tools were considered valid and reliable with 0.7+ score.
• DATA COLLECTION INSTRUMENTS
DATA PROCESSING AND ANALYSIS
QUANTITATIVE
Raw data was entered into SPSS ver. 23 for analysis. Descriptive and Inferential
statistics tests were done. Hypotheses testing, correlations and regressions were used
to ascertain the relationship between variables. Results are presented in tables,
figures, and descriptive statements.
QUALITATIVE
Data from interviews were edited into meaningful opinions from participants. These
were categorized into leading themes. Content analysis was done and results were
presented in statements
RESULTS AND DISCUSSION
Response Rate of respondents
Out of 42 questionnaires distributed to the respondents, 39 responded, giving a response rate of 92%.
Background Information of the Respondents
This information was necessary to guarantee that the study's sample was representative had a similar
distribution of respondents by attributes to the population from which it was selected.
Background of respondents Cont..
15 (38.5%) respondents had a Master's degree, 21 (53.8 %) held a Bachelor's degree, and 3 (7.7 %) held a Diploma. This demonstrates that
the majority of research participants were appropriately informed
30 (76.9 %) had worked for a period of 5 – 10 years, 6 (15.4 %) had worked for a period of (11-16 years), leaving 3 (7.7 %) had worked for
a time of fewer than 5 years.
This means that the majority of respondents have been working within the industry and on this project long enough to contribute
meaningful information to the research.
DISCUSSION OF RESULTS.
Validation of questionnaires
Cronbach's alpha with the help of SPSS was deployed to assess the questionnaire's reliability from
the following equation;
where C = the average inter-item covariance, v = the average variance and N = the number of items
The obtained Cronbach’s Alpha value of 0.964 shows an excellent level of internal consistency in the questionnaire.
Cronbach's Alpha
Cronbach's Alpha Based on
Standardized Items
Number of Items
0.964 0.965 33
Objective No.1 Analysis of the causes of Rework on construction sites;
The scores were assigned for each factor as perceived by the respondents and were used for statistical
analysis, the factors were examined and ranked in terms of their impact using the Relative Importance
Index. S/N Causes of Rework on Construction Sites RII Rank
1 Insufficient briefing 0.744 12
2 Inadequate understanding of the construction process 0.754 10
3 Inadequate funds for site investigations 0.744 12
4 Changes because of change in officials 0.646 21
5 Lack of funding allocated for consultation 0.738 14
6 Communication breakdown with design consultants (architects/engineers) 0.795 4
7 Payment of low fees for preparing contract documentation 0.641 22
8 Mistakes in contract documents 0.779 7
9 Items missing from the contract documents 0.826 2
10 Poor coordination of design 0.774 9
11 Inadequate skill sets for completing the specified assignment 0.718 18
12 Inadequate time to produce bidding documents 0.687 20
13 Tender being incomplete at the time of bidding 0.785 6
14 Insufficient client briefing to produce comprehensive contract document 0.723 17
15 Workers being given unclear instructions. 0.779 7
16 Specification non-compliance 0.841 1
17 Having few trained supervisors on site 0.795 4
18 Scarcity of trained labour 0.728 16
19 Inadequate trained labourers 0.708 19
20 Insufficient supervisor-to-foreman-to-tradesmen ratios 0.733 15
21 Faulty construction 0.805 3
22 Carelessness resulting into damage to other works 0.754 10
Where:
W - is the weight given
to each factor by the
respondents and
ranges from 0 to 39,
X is the largest weight
(i.e., 39 in this case)
and; N - is the total
number of people that
responded.
Objective No.2: Effect of rework on project cost and schedule.
Based on the values of numerous independent variables (causes of rework), multiple
regression was used to estimate the value of the dependent variable (cost and/or
schedule).
Multiple regression allows for the determination of the model's overall fit (variance
explained) as well as the proportionate contribution of each predictor to the project
cost and schedule.
From multiple regression analysis, an equation of the form below was obtained
(Hanson, 2002);
where 𝑦 is the project cost or project schedule variable, 𝛽0 + 𝛽1𝑥1 + 𝛽2𝑥2 + ⋯ +
𝛽𝑛𝑥𝑛 is the deterministic portion of the model; in this case 𝑥𝑛 the causes of cost and
schedule overruns and 𝛽𝑛 the beta values, and 𝜀 is the random error.
Table: Showing Model Summary on the significance of Rework on Cost
Table: Showing Model Summary for the significance of Rework on schedule
• Rework accounted for an 8.95% variance in the construction cost increase.
• Rework accounted for an 8.0% variance in the construction Schedule increase.
Model R R Square Adjusted R Square Std. Error of the Estimate Durbin-Watson
1 0.946a 0.0895 0.0857 6.96698 1.516
a. Predictors: (Constant), Carelessness resulting into damage to other works, Tender being incomplete at the time of bidding, Workers being given unclear
instructions., Having few trained supervisors on site, Communication breakdown with design consultants (architects/engineers), Inadequate time to produce
bidding documents, Faulty construction, Items missing from the contract documents, Specification non-compliance, Mistakes in contract documents
b. Dependent Variable: Percentage Increase in Project Cost
Model R R Square Adjusted R Square Std. Error of the Estimate Durbin-Watson
1 0.900a 0.0809 0.0741 9.18350 1.966
a. Predictors: (Constant), Carelessness resulting into damage to other works, Tender being incomplete at the time of bidding, Workers being given unclear
instructions., Having few trained supervisors on site, Communication breakdown with design consultants (architects/engineers), Inadequate time to produce
bidding documents, Faulty construction, Items missing from the contract documents, Specification non-compliance, Mistakes in contract documents
b. Dependent Variable: Percentage Increase in project Schedule
Statistical Significance
The tables below show the ANOVA table from the regression analysis. The F-ratio was used to test whether the overall
regression model was a good fit for the data. The table shows that the causes of rework are statistically significant in
predicting the overall increase in project cost, F(10, 28) = 23.847, p < 0.001, and overall increase in the project schedule,
F(10, 28) = 11.881, p < 0.001 indicating that the regression model was a good fit for the data.
Table: Regression Model Fit for percentage cost increase with rework Table: Regression Model Fit for percentage Schedule increase with rework
ANOVAa
Model
Sum of
Squares
df
Mean
Square
F Sig.
1
Regression 11579.939 10 1157.994 23.857 0.000b
Residual 1359.086 28 48.539
Total 12939.025 38
a. Dependent Variable: Percentage Increase in Project Cost
b. Predictors: (Constant), Carelessness resulting into damage to other works, Tender being
incomplete at the time of bidding, Workers being given unclear instructions, Having few
trained supervisors on site, Communication breakdown with design consultants
(architects/engineers), Inadequate time to produce bidding documents, Faulty construction,
Items missing from the contract documents, Specification non-compliance, Mistakes in
contract documents.
ANOVAa
Model Sum of Squares df Mean Square F Sig.
1
Regression 10020.267 10 1002.027 11.881 0.000b
Residual 2361.425 28 84.337
Total 12381.692 38
a. Dependent Variable: Percentage Increase in project time
b. Predictors: (Constant), Carelessness resulting into damage to other works, Tender being
incomplete at the time of bidding, Workers being given unclear instructions., Having few
trained supervisors on site, Communication breakdown with design consultants
(architects/engineers), Inadequate time to produce bidding documents, Faulty construction,
Items missing from the contract documents, Specification non-compliance, Mistakes in contract
documents.
Objective 3: Strategies to minimize Rework on cost and schedule
The Relative Importance Index (RII) was calculated and the identified causes were ranked as per the responses in the
table below. The most notable solutions were identified to be;
S/N Measures taken to reduce rework on Cost and schedule RII Rank
1 Using sufficient and capable human resource 0.882 2
2 Sufficient supervision 0.887 1
3
Developing effective communication between project
participants
0.872 3
4
Continuous monitoring before and throughout work
implementation of work
0.867 4
5 Involving the client 0.815 8
6 Using effective planning and scheduling 0.867 4
7 Using qualified suppliers 0.764 11
8 Tracking and documenting rework incidents 0.810 10
9 Identifying the root cause of rework in detail 0.826 6
10 Developing options and actions to reduce reworking 0.821 7
11 Quantifying the cost and time effect of rework on project delivery 0.815 8
Where:
W - is the weight given to
each factor by the
respondents and ranges
from 0 to 39,
X is the largest weight
(i.e., 39 in this case) and;
N - is the total number of
people that responded.
The study also elicited independent suggestions from the respondents on how to mitigate the
cost and schedule impact of rework and these are as below.
➢Developing work programmes
➢getting an in-depth cause and solutions to the problem other than basing on assumptions
➢Proper Project conceptualization and adequate planning
➢Public projects should actively engage the stakeholders at the planning stage
➢Investing in Quality Control and Quality Assurance
➢Ensuring that work is done as per specifications, and drawings and also maintaining quality.
➢Proper planning of works
➢Adherence to documentation and permissions
➢Incorporating value engineering into all kinds of construction projects
CONCLUSIONS AND RECOMMENDATIONS
Conclusions
Close attention should be given to Contractor related rework causes as they were seen to be the heaviest
contributor to the negative effects.
There is a need for prior knowledge of rework during construction can help projects save money and time.
KCCA should know that the costs for building projects end up becoming very high because of the
complexities resulting from Rework.
Various methods can be deployed to help reduce the negative impacts of Rework on construction projects
and all project participants should be aware of these and know how to utilise them.
Recommendations
The project team should always have strategies for detecting Rework and be able to put in place mitigation
measures to mitigate rework.
Parties responsible for rework should bear the cost. This prevents unnecessary costs for the client and keeps
everyone on top of their game.
There is a need to allocate more supervisory resources like a “clerk of works” on projects to closely monitor
the implementation of the project.
REFERENCES
Trach, R., & Pawluk, K. (2019). CAUSES OF REWORK IN CONSTRUCTION PROJECTS IN UKRAINE. Pan
Polska, 63.
Kakitahi, Alinaitwe (2016) Impact of construction-related rework on selected Ugandan public projects, Journal of
Engineering Design and Technology.
Alinaitwe, H. (2014). A COMPARISON OF CONSTRUCTION-RELATED REWORK IN UGANDAAND
MOZAMBIQUE. Journal of Construction Project Management and Innovation, 775-776.
Ntungire, E. C. (2018, December). Construction and public procurement in Uganda. Boston: United Nations
University.
Rezahoseini, A., Noori, S., & Ghannadpour, S. F. (2019). Reducing rework and increasing the quality of the civil
project, through Total Quality Management (TQM), by using the concept of Building Information Modelling
(BIM). Journal of Industrial and Systems Engineering, 3.
Joseph Stables, G. O. (2018, November 18). Uganda Construction Capacity Preliminary Assessment: Key Findings
and Recommendations. Infrastructure for Cities and Economic Development, p.6.
END

More Related Content

Similar to Impact of Rework on Cost and Schedule

Cost _ Time Control in Construction Projects- Part -3.pdf
Cost _ Time Control in Construction Projects- Part -3.pdfCost _ Time Control in Construction Projects- Part -3.pdf
Cost _ Time Control in Construction Projects- Part -3.pdfYohannesBizuneheWeld
 
Salam_2007_Time_and_cost_overruns_on_PhD.pdf
Salam_2007_Time_and_cost_overruns_on_PhD.pdfSalam_2007_Time_and_cost_overruns_on_PhD.pdf
Salam_2007_Time_and_cost_overruns_on_PhD.pdfKarthikeyanP288430
 
Study of Lean construction tools for Workflow Improvement -A Review
Study of Lean construction tools for Workflow Improvement -A ReviewStudy of Lean construction tools for Workflow Improvement -A Review
Study of Lean construction tools for Workflow Improvement -A ReviewIRJET Journal
 
Causes of delay and cost overruns in construction of groundwater projects in ...
Causes of delay and cost overruns in construction of groundwater projects in ...Causes of delay and cost overruns in construction of groundwater projects in ...
Causes of delay and cost overruns in construction of groundwater projects in ...Charles Abraham Scheck
 
STUDY AND ANALYSIS OF CONCRETE STRENGTH PARAMETERS USING VETIVER GRASS ASH AS...
STUDY AND ANALYSIS OF CONCRETE STRENGTH PARAMETERS USING VETIVER GRASS ASH AS...STUDY AND ANALYSIS OF CONCRETE STRENGTH PARAMETERS USING VETIVER GRASS ASH AS...
STUDY AND ANALYSIS OF CONCRETE STRENGTH PARAMETERS USING VETIVER GRASS ASH AS...Vamsi Kovalam
 
IRJET- A Study on Factors Affecting Estimation of Construction Project : Conc...
IRJET- A Study on Factors Affecting Estimation of Construction Project : Conc...IRJET- A Study on Factors Affecting Estimation of Construction Project : Conc...
IRJET- A Study on Factors Affecting Estimation of Construction Project : Conc...IRJET Journal
 
Delay Analysis in EPC Projects using Ishikawa Diagram
Delay Analysis in EPC Projects using Ishikawa DiagramDelay Analysis in EPC Projects using Ishikawa Diagram
Delay Analysis in EPC Projects using Ishikawa DiagramIJAEMSJORNAL
 
IRJET- Development of a Neural Network based Model for Construction Proje...
IRJET-  	  Development of a Neural Network based Model for Construction Proje...IRJET-  	  Development of a Neural Network based Model for Construction Proje...
IRJET- Development of a Neural Network based Model for Construction Proje...IRJET Journal
 
Statistical Methods for Construction Delay Analysis
Statistical Methods for Construction Delay Analysis Statistical Methods for Construction Delay Analysis
Statistical Methods for Construction Delay Analysis IOSR Journals
 
An empirical study on key determinants of construction Delay
An empirical study on key determinants of construction DelayAn empirical study on key determinants of construction Delay
An empirical study on key determinants of construction DelayIRJET Journal
 
Towards Innovate Methods of Construction Cost Management and Control
Towards Innovate Methods of Construction Cost Management and ControlTowards Innovate Methods of Construction Cost Management and Control
Towards Innovate Methods of Construction Cost Management and Controlcivej
 
Towards Innovate Methods of Construction Cost Management and Control
Towards Innovate Methods of Construction Cost Management and ControlTowards Innovate Methods of Construction Cost Management and Control
Towards Innovate Methods of Construction Cost Management and Controlcivejjour
 
Application of value engineering in construction
Application of value engineering in constructionApplication of value engineering in construction
Application of value engineering in constructionDr Ezzat Mansour
 
Project Performance Analysis And Delivery Methods - Quantitative Analysis
Project Performance Analysis And Delivery Methods - Quantitative AnalysisProject Performance Analysis And Delivery Methods - Quantitative Analysis
Project Performance Analysis And Delivery Methods - Quantitative AnalysisSeta Ohanesian, PMP, LEED AP
 
IRJET - Investigating the Effectiveness of Construction Practices in Dela...
IRJET -  	  Investigating the Effectiveness of Construction Practices in Dela...IRJET -  	  Investigating the Effectiveness of Construction Practices in Dela...
IRJET - Investigating the Effectiveness of Construction Practices in Dela...IRJET Journal
 
Factors affecting Quality of construction projects in India region
Factors affecting Quality of construction projects in India regionFactors affecting Quality of construction projects in India region
Factors affecting Quality of construction projects in India regionAyush khandelwal
 
Multivariate approach to benchmarking quality prediction parameters in buildi...
Multivariate approach to benchmarking quality prediction parameters in buildi...Multivariate approach to benchmarking quality prediction parameters in buildi...
Multivariate approach to benchmarking quality prediction parameters in buildi...Alexander Decker
 
IRJET- A Study on Factors Affecting Estimation of Construction Project : Conc...
IRJET- A Study on Factors Affecting Estimation of Construction Project : Conc...IRJET- A Study on Factors Affecting Estimation of Construction Project : Conc...
IRJET- A Study on Factors Affecting Estimation of Construction Project : Conc...IRJET Journal
 
IRJET- A Review Paper on Lean Management in Construction Sites
IRJET-  	  A Review Paper on Lean Management in Construction SitesIRJET-  	  A Review Paper on Lean Management in Construction Sites
IRJET- A Review Paper on Lean Management in Construction SitesIRJET Journal
 

Similar to Impact of Rework on Cost and Schedule (20)

Cost _ Time Control in Construction Projects- Part -3.pdf
Cost _ Time Control in Construction Projects- Part -3.pdfCost _ Time Control in Construction Projects- Part -3.pdf
Cost _ Time Control in Construction Projects- Part -3.pdf
 
Salam_2007_Time_and_cost_overruns_on_PhD.pdf
Salam_2007_Time_and_cost_overruns_on_PhD.pdfSalam_2007_Time_and_cost_overruns_on_PhD.pdf
Salam_2007_Time_and_cost_overruns_on_PhD.pdf
 
Study of Lean construction tools for Workflow Improvement -A Review
Study of Lean construction tools for Workflow Improvement -A ReviewStudy of Lean construction tools for Workflow Improvement -A Review
Study of Lean construction tools for Workflow Improvement -A Review
 
Causes of delay and cost overruns in construction of groundwater projects in ...
Causes of delay and cost overruns in construction of groundwater projects in ...Causes of delay and cost overruns in construction of groundwater projects in ...
Causes of delay and cost overruns in construction of groundwater projects in ...
 
STUDY AND ANALYSIS OF CONCRETE STRENGTH PARAMETERS USING VETIVER GRASS ASH AS...
STUDY AND ANALYSIS OF CONCRETE STRENGTH PARAMETERS USING VETIVER GRASS ASH AS...STUDY AND ANALYSIS OF CONCRETE STRENGTH PARAMETERS USING VETIVER GRASS ASH AS...
STUDY AND ANALYSIS OF CONCRETE STRENGTH PARAMETERS USING VETIVER GRASS ASH AS...
 
IRJET- A Study on Factors Affecting Estimation of Construction Project : Conc...
IRJET- A Study on Factors Affecting Estimation of Construction Project : Conc...IRJET- A Study on Factors Affecting Estimation of Construction Project : Conc...
IRJET- A Study on Factors Affecting Estimation of Construction Project : Conc...
 
Delay Analysis in EPC Projects using Ishikawa Diagram
Delay Analysis in EPC Projects using Ishikawa DiagramDelay Analysis in EPC Projects using Ishikawa Diagram
Delay Analysis in EPC Projects using Ishikawa Diagram
 
ppt final final.pptx
ppt final final.pptxppt final final.pptx
ppt final final.pptx
 
IRJET- Development of a Neural Network based Model for Construction Proje...
IRJET-  	  Development of a Neural Network based Model for Construction Proje...IRJET-  	  Development of a Neural Network based Model for Construction Proje...
IRJET- Development of a Neural Network based Model for Construction Proje...
 
Statistical Methods for Construction Delay Analysis
Statistical Methods for Construction Delay Analysis Statistical Methods for Construction Delay Analysis
Statistical Methods for Construction Delay Analysis
 
An empirical study on key determinants of construction Delay
An empirical study on key determinants of construction DelayAn empirical study on key determinants of construction Delay
An empirical study on key determinants of construction Delay
 
Towards Innovate Methods of Construction Cost Management and Control
Towards Innovate Methods of Construction Cost Management and ControlTowards Innovate Methods of Construction Cost Management and Control
Towards Innovate Methods of Construction Cost Management and Control
 
Towards Innovate Methods of Construction Cost Management and Control
Towards Innovate Methods of Construction Cost Management and ControlTowards Innovate Methods of Construction Cost Management and Control
Towards Innovate Methods of Construction Cost Management and Control
 
Application of value engineering in construction
Application of value engineering in constructionApplication of value engineering in construction
Application of value engineering in construction
 
Project Performance Analysis And Delivery Methods - Quantitative Analysis
Project Performance Analysis And Delivery Methods - Quantitative AnalysisProject Performance Analysis And Delivery Methods - Quantitative Analysis
Project Performance Analysis And Delivery Methods - Quantitative Analysis
 
IRJET - Investigating the Effectiveness of Construction Practices in Dela...
IRJET -  	  Investigating the Effectiveness of Construction Practices in Dela...IRJET -  	  Investigating the Effectiveness of Construction Practices in Dela...
IRJET - Investigating the Effectiveness of Construction Practices in Dela...
 
Factors affecting Quality of construction projects in India region
Factors affecting Quality of construction projects in India regionFactors affecting Quality of construction projects in India region
Factors affecting Quality of construction projects in India region
 
Multivariate approach to benchmarking quality prediction parameters in buildi...
Multivariate approach to benchmarking quality prediction parameters in buildi...Multivariate approach to benchmarking quality prediction parameters in buildi...
Multivariate approach to benchmarking quality prediction parameters in buildi...
 
IRJET- A Study on Factors Affecting Estimation of Construction Project : Conc...
IRJET- A Study on Factors Affecting Estimation of Construction Project : Conc...IRJET- A Study on Factors Affecting Estimation of Construction Project : Conc...
IRJET- A Study on Factors Affecting Estimation of Construction Project : Conc...
 
IRJET- A Review Paper on Lean Management in Construction Sites
IRJET-  	  A Review Paper on Lean Management in Construction SitesIRJET-  	  A Review Paper on Lean Management in Construction Sites
IRJET- A Review Paper on Lean Management in Construction Sites
 

Recently uploaded

Worksharing and 3D Modeling with Revit.pptx
Worksharing and 3D Modeling with Revit.pptxWorksharing and 3D Modeling with Revit.pptx
Worksharing and 3D Modeling with Revit.pptxMustafa Ahmed
 
Danikor Product Catalog- Screw Feeder.pdf
Danikor Product Catalog- Screw Feeder.pdfDanikor Product Catalog- Screw Feeder.pdf
Danikor Product Catalog- Screw Feeder.pdfthietkevietthinh
 
Computer Graphics Introduction To Curves
Computer Graphics Introduction To CurvesComputer Graphics Introduction To Curves
Computer Graphics Introduction To CurvesChandrakantDivate1
 
Electromagnetic relays used for power system .pptx
Electromagnetic relays used for power system .pptxElectromagnetic relays used for power system .pptx
Electromagnetic relays used for power system .pptxNANDHAKUMARA10
 
Hospital management system project report.pdf
Hospital management system project report.pdfHospital management system project report.pdf
Hospital management system project report.pdfKamal Acharya
 
Path loss model, OKUMURA Model, Hata Model
Path loss model, OKUMURA Model, Hata ModelPath loss model, OKUMURA Model, Hata Model
Path loss model, OKUMURA Model, Hata ModelDrAjayKumarYadav4
 
Basic Electronics for diploma students as per technical education Kerala Syll...
Basic Electronics for diploma students as per technical education Kerala Syll...Basic Electronics for diploma students as per technical education Kerala Syll...
Basic Electronics for diploma students as per technical education Kerala Syll...ppkakm
 
COST-EFFETIVE and Energy Efficient BUILDINGS ptx
COST-EFFETIVE  and Energy Efficient BUILDINGS ptxCOST-EFFETIVE  and Energy Efficient BUILDINGS ptx
COST-EFFETIVE and Energy Efficient BUILDINGS ptxJIT KUMAR GUPTA
 
Augmented Reality (AR) with Augin Software.pptx
Augmented Reality (AR) with Augin Software.pptxAugmented Reality (AR) with Augin Software.pptx
Augmented Reality (AR) with Augin Software.pptxMustafa Ahmed
 
8086 Microprocessor Architecture: 16-bit microprocessor
8086 Microprocessor Architecture: 16-bit microprocessor8086 Microprocessor Architecture: 16-bit microprocessor
8086 Microprocessor Architecture: 16-bit microprocessorAshwiniTodkar4
 
Standard vs Custom Battery Packs - Decoding the Power Play
Standard vs Custom Battery Packs - Decoding the Power PlayStandard vs Custom Battery Packs - Decoding the Power Play
Standard vs Custom Battery Packs - Decoding the Power PlayEpec Engineered Technologies
 
Online food ordering system project report.pdf
Online food ordering system project report.pdfOnline food ordering system project report.pdf
Online food ordering system project report.pdfKamal Acharya
 
Ground Improvement Technique: Earth Reinforcement
Ground Improvement Technique: Earth ReinforcementGround Improvement Technique: Earth Reinforcement
Ground Improvement Technique: Earth ReinforcementDr. Deepak Mudgal
 
Theory of Time 2024 (Universal Theory for Everything)
Theory of Time 2024 (Universal Theory for Everything)Theory of Time 2024 (Universal Theory for Everything)
Theory of Time 2024 (Universal Theory for Everything)Ramkumar k
 
NO1 Top No1 Amil Baba In Azad Kashmir, Kashmir Black Magic Specialist Expert ...
NO1 Top No1 Amil Baba In Azad Kashmir, Kashmir Black Magic Specialist Expert ...NO1 Top No1 Amil Baba In Azad Kashmir, Kashmir Black Magic Specialist Expert ...
NO1 Top No1 Amil Baba In Azad Kashmir, Kashmir Black Magic Specialist Expert ...Amil baba
 
PE 459 LECTURE 2- natural gas basic concepts and properties
PE 459 LECTURE 2- natural gas basic concepts and propertiesPE 459 LECTURE 2- natural gas basic concepts and properties
PE 459 LECTURE 2- natural gas basic concepts and propertiessarkmank1
 
Cybercrimes in the Darknet and Their Detections: A Comprehensive Analysis and...
Cybercrimes in the Darknet and Their Detections: A Comprehensive Analysis and...Cybercrimes in the Darknet and Their Detections: A Comprehensive Analysis and...
Cybercrimes in the Darknet and Their Detections: A Comprehensive Analysis and...dannyijwest
 
8th International Conference on Soft Computing, Mathematics and Control (SMC ...
8th International Conference on Soft Computing, Mathematics and Control (SMC ...8th International Conference on Soft Computing, Mathematics and Control (SMC ...
8th International Conference on Soft Computing, Mathematics and Control (SMC ...josephjonse
 
Introduction to Artificial Intelligence ( AI)
Introduction to Artificial Intelligence ( AI)Introduction to Artificial Intelligence ( AI)
Introduction to Artificial Intelligence ( AI)ChandrakantDivate1
 

Recently uploaded (20)

Worksharing and 3D Modeling with Revit.pptx
Worksharing and 3D Modeling with Revit.pptxWorksharing and 3D Modeling with Revit.pptx
Worksharing and 3D Modeling with Revit.pptx
 
Danikor Product Catalog- Screw Feeder.pdf
Danikor Product Catalog- Screw Feeder.pdfDanikor Product Catalog- Screw Feeder.pdf
Danikor Product Catalog- Screw Feeder.pdf
 
Computer Graphics Introduction To Curves
Computer Graphics Introduction To CurvesComputer Graphics Introduction To Curves
Computer Graphics Introduction To Curves
 
Electromagnetic relays used for power system .pptx
Electromagnetic relays used for power system .pptxElectromagnetic relays used for power system .pptx
Electromagnetic relays used for power system .pptx
 
Hospital management system project report.pdf
Hospital management system project report.pdfHospital management system project report.pdf
Hospital management system project report.pdf
 
Path loss model, OKUMURA Model, Hata Model
Path loss model, OKUMURA Model, Hata ModelPath loss model, OKUMURA Model, Hata Model
Path loss model, OKUMURA Model, Hata Model
 
Basic Electronics for diploma students as per technical education Kerala Syll...
Basic Electronics for diploma students as per technical education Kerala Syll...Basic Electronics for diploma students as per technical education Kerala Syll...
Basic Electronics for diploma students as per technical education Kerala Syll...
 
COST-EFFETIVE and Energy Efficient BUILDINGS ptx
COST-EFFETIVE  and Energy Efficient BUILDINGS ptxCOST-EFFETIVE  and Energy Efficient BUILDINGS ptx
COST-EFFETIVE and Energy Efficient BUILDINGS ptx
 
Augmented Reality (AR) with Augin Software.pptx
Augmented Reality (AR) with Augin Software.pptxAugmented Reality (AR) with Augin Software.pptx
Augmented Reality (AR) with Augin Software.pptx
 
8086 Microprocessor Architecture: 16-bit microprocessor
8086 Microprocessor Architecture: 16-bit microprocessor8086 Microprocessor Architecture: 16-bit microprocessor
8086 Microprocessor Architecture: 16-bit microprocessor
 
Standard vs Custom Battery Packs - Decoding the Power Play
Standard vs Custom Battery Packs - Decoding the Power PlayStandard vs Custom Battery Packs - Decoding the Power Play
Standard vs Custom Battery Packs - Decoding the Power Play
 
Online food ordering system project report.pdf
Online food ordering system project report.pdfOnline food ordering system project report.pdf
Online food ordering system project report.pdf
 
Ground Improvement Technique: Earth Reinforcement
Ground Improvement Technique: Earth ReinforcementGround Improvement Technique: Earth Reinforcement
Ground Improvement Technique: Earth Reinforcement
 
Theory of Time 2024 (Universal Theory for Everything)
Theory of Time 2024 (Universal Theory for Everything)Theory of Time 2024 (Universal Theory for Everything)
Theory of Time 2024 (Universal Theory for Everything)
 
Cara Menggugurkan Sperma Yang Masuk Rahim Biyar Tidak Hamil
Cara Menggugurkan Sperma Yang Masuk Rahim Biyar Tidak HamilCara Menggugurkan Sperma Yang Masuk Rahim Biyar Tidak Hamil
Cara Menggugurkan Sperma Yang Masuk Rahim Biyar Tidak Hamil
 
NO1 Top No1 Amil Baba In Azad Kashmir, Kashmir Black Magic Specialist Expert ...
NO1 Top No1 Amil Baba In Azad Kashmir, Kashmir Black Magic Specialist Expert ...NO1 Top No1 Amil Baba In Azad Kashmir, Kashmir Black Magic Specialist Expert ...
NO1 Top No1 Amil Baba In Azad Kashmir, Kashmir Black Magic Specialist Expert ...
 
PE 459 LECTURE 2- natural gas basic concepts and properties
PE 459 LECTURE 2- natural gas basic concepts and propertiesPE 459 LECTURE 2- natural gas basic concepts and properties
PE 459 LECTURE 2- natural gas basic concepts and properties
 
Cybercrimes in the Darknet and Their Detections: A Comprehensive Analysis and...
Cybercrimes in the Darknet and Their Detections: A Comprehensive Analysis and...Cybercrimes in the Darknet and Their Detections: A Comprehensive Analysis and...
Cybercrimes in the Darknet and Their Detections: A Comprehensive Analysis and...
 
8th International Conference on Soft Computing, Mathematics and Control (SMC ...
8th International Conference on Soft Computing, Mathematics and Control (SMC ...8th International Conference on Soft Computing, Mathematics and Control (SMC ...
8th International Conference on Soft Computing, Mathematics and Control (SMC ...
 
Introduction to Artificial Intelligence ( AI)
Introduction to Artificial Intelligence ( AI)Introduction to Artificial Intelligence ( AI)
Introduction to Artificial Intelligence ( AI)
 

Impact of Rework on Cost and Schedule

  • 1. KYAMBOGO UNIVERSITY FOURTH-YEAR PROJECT REPORT TOPIC: CONSTRUCTION-RELATED REWORK AND ITS IMPACT ON COST AND SCHEDULE: A CASE STUDY, KAMPALA CAPITAL CITY AUTHORITY BY KALEMA SOLOMON WASAJJA REG NO: 17/U/8331/ECE/PE SUPERVISOR ACHIRE MICHAEL WEST (GMUIPE) JULY, 2022
  • 2. SUMMARY OF THE PRESENTATION • Introduction • Statement of the problem • Objectives • Conceptual framework • Methodology used • Result and Discussion • Conclusions and Recommendations
  • 3. INTRODUCTION Globally, in Ukraine’s construction industry, there is a trend of rework being accepted as an integral part of construction activities (Trach et al, 2019). On the African continent, studies have shown that all the elements of the building had a direct bearing on an increase in the final cost of the project because of rework (Oyewobi 2010). In Uganda, Rework has been known to contribute to waste and value losses in building design and construction (Kakitahi et al. 2013), and it has been considered one of the key factors responsible for the cost and schedule overruns in construction projects.
  • 4. INTRODUCTION CONT…. Rework has been linked to waste and value loss in building design and construction in Uganda (Kakitahi et al. 2013), and it has been identified as one of the primary causes of cost and schedule overruns in building projects. Alinaitwe (2014) also demonstrated that design omissions, poor workmanship, and insufficient contractor supervision could be blamed for construction-related rework, with consequences ranging from project schedule creep to client directives that altered the scope of the task, coupled with client payment delays and site handover delays. The aim of this study, therefore, is to identify and evaluate the critical factors that bring about rework and how it affects construction Cost and Schedule based on the KIIDP2 project in KCCA.
  • 5. Many economies rely heavily on the building industry. In Uganda, the sector accounts for more than 12% of the country's GDP and has grown steadily over the years (Alinaitwe, 2021). The sector has made significant strides in terms of capacity development and performance enhancement (Joseph et al, 2018). Despite its positive potential, the sector confronts significant barriers in failing to properly transform investment opportunities into employment creation and national productivity (Ntungire, 2018).One of the pertinent issues causing this is 'rework.’ It has an impact on time, cost, quality, and practically every other project success criterion (Rezahoseini, et al, 2019). Rework is linked with higher expenses, while being responsible for Schedule overruns and delays. However, little is known about the history, causality and consequently, its impact on Construction Schedule and Cost. Accordingly, the study attempted to undertake a comprehensive assessment of past studies by various authors in order to evaluate the primary consequences of rework on construction cost and schedule on the KIIDP2 project in KCCA STATEMENT OF PROBLEM
  • 6. OBJECTIVES OF THE STUDY • General Objective To investigate the impact of construction-related Rework on cost and schedule. • Specific objectives (i) To identify the causes of Rework on construction projects. (ii) To ascertain the effects of Rework on construction cost and schedule. (iii)To propose strategies on how to minimize the impact of Rework on Cost and schedule
  • 8. Research Approach A mixed method paradigm (quantitative and qualitative research approaches) in examining the impact of Rework on Construction Cost and Schedule was adopted. Research Design A descriptive design was used to collect current data and establish the relationship between variables. Study Area The study was carried out within Kampala Capital City Authority located in central Uganda. Study Population From a study population of 47 and using Morgan’s tables, a sample size of 42 respondents was considered. METHODOLOGY SLIDES
  • 9. Study tools Questionnaires- this was the main tool for the study, arranged on a 5-Linkert scale. Questionnaires were administered to all participants. Interview Guides- semi-structured guides was prepared and administered to the respondents. Data Tools Quality The tools were tested for: Validity-using Face Validity and Content Validity tests Reliability-using SPSS to test for Cronbach’s Alpha values These tools were considered valid and reliable with 0.7+ score. • DATA COLLECTION INSTRUMENTS
  • 10. DATA PROCESSING AND ANALYSIS QUANTITATIVE Raw data was entered into SPSS ver. 23 for analysis. Descriptive and Inferential statistics tests were done. Hypotheses testing, correlations and regressions were used to ascertain the relationship between variables. Results are presented in tables, figures, and descriptive statements. QUALITATIVE Data from interviews were edited into meaningful opinions from participants. These were categorized into leading themes. Content analysis was done and results were presented in statements
  • 11. RESULTS AND DISCUSSION Response Rate of respondents Out of 42 questionnaires distributed to the respondents, 39 responded, giving a response rate of 92%. Background Information of the Respondents This information was necessary to guarantee that the study's sample was representative had a similar distribution of respondents by attributes to the population from which it was selected.
  • 12. Background of respondents Cont.. 15 (38.5%) respondents had a Master's degree, 21 (53.8 %) held a Bachelor's degree, and 3 (7.7 %) held a Diploma. This demonstrates that the majority of research participants were appropriately informed 30 (76.9 %) had worked for a period of 5 – 10 years, 6 (15.4 %) had worked for a period of (11-16 years), leaving 3 (7.7 %) had worked for a time of fewer than 5 years. This means that the majority of respondents have been working within the industry and on this project long enough to contribute meaningful information to the research.
  • 13. DISCUSSION OF RESULTS. Validation of questionnaires Cronbach's alpha with the help of SPSS was deployed to assess the questionnaire's reliability from the following equation; where C = the average inter-item covariance, v = the average variance and N = the number of items The obtained Cronbach’s Alpha value of 0.964 shows an excellent level of internal consistency in the questionnaire. Cronbach's Alpha Cronbach's Alpha Based on Standardized Items Number of Items 0.964 0.965 33
  • 14. Objective No.1 Analysis of the causes of Rework on construction sites; The scores were assigned for each factor as perceived by the respondents and were used for statistical analysis, the factors were examined and ranked in terms of their impact using the Relative Importance Index. S/N Causes of Rework on Construction Sites RII Rank 1 Insufficient briefing 0.744 12 2 Inadequate understanding of the construction process 0.754 10 3 Inadequate funds for site investigations 0.744 12 4 Changes because of change in officials 0.646 21 5 Lack of funding allocated for consultation 0.738 14 6 Communication breakdown with design consultants (architects/engineers) 0.795 4 7 Payment of low fees for preparing contract documentation 0.641 22 8 Mistakes in contract documents 0.779 7 9 Items missing from the contract documents 0.826 2 10 Poor coordination of design 0.774 9 11 Inadequate skill sets for completing the specified assignment 0.718 18 12 Inadequate time to produce bidding documents 0.687 20 13 Tender being incomplete at the time of bidding 0.785 6 14 Insufficient client briefing to produce comprehensive contract document 0.723 17 15 Workers being given unclear instructions. 0.779 7 16 Specification non-compliance 0.841 1 17 Having few trained supervisors on site 0.795 4 18 Scarcity of trained labour 0.728 16 19 Inadequate trained labourers 0.708 19 20 Insufficient supervisor-to-foreman-to-tradesmen ratios 0.733 15 21 Faulty construction 0.805 3 22 Carelessness resulting into damage to other works 0.754 10 Where: W - is the weight given to each factor by the respondents and ranges from 0 to 39, X is the largest weight (i.e., 39 in this case) and; N - is the total number of people that responded.
  • 15. Objective No.2: Effect of rework on project cost and schedule. Based on the values of numerous independent variables (causes of rework), multiple regression was used to estimate the value of the dependent variable (cost and/or schedule). Multiple regression allows for the determination of the model's overall fit (variance explained) as well as the proportionate contribution of each predictor to the project cost and schedule. From multiple regression analysis, an equation of the form below was obtained (Hanson, 2002); where 𝑦 is the project cost or project schedule variable, 𝛽0 + 𝛽1𝑥1 + 𝛽2𝑥2 + ⋯ + 𝛽𝑛𝑥𝑛 is the deterministic portion of the model; in this case 𝑥𝑛 the causes of cost and schedule overruns and 𝛽𝑛 the beta values, and 𝜀 is the random error.
  • 16. Table: Showing Model Summary on the significance of Rework on Cost Table: Showing Model Summary for the significance of Rework on schedule • Rework accounted for an 8.95% variance in the construction cost increase. • Rework accounted for an 8.0% variance in the construction Schedule increase. Model R R Square Adjusted R Square Std. Error of the Estimate Durbin-Watson 1 0.946a 0.0895 0.0857 6.96698 1.516 a. Predictors: (Constant), Carelessness resulting into damage to other works, Tender being incomplete at the time of bidding, Workers being given unclear instructions., Having few trained supervisors on site, Communication breakdown with design consultants (architects/engineers), Inadequate time to produce bidding documents, Faulty construction, Items missing from the contract documents, Specification non-compliance, Mistakes in contract documents b. Dependent Variable: Percentage Increase in Project Cost Model R R Square Adjusted R Square Std. Error of the Estimate Durbin-Watson 1 0.900a 0.0809 0.0741 9.18350 1.966 a. Predictors: (Constant), Carelessness resulting into damage to other works, Tender being incomplete at the time of bidding, Workers being given unclear instructions., Having few trained supervisors on site, Communication breakdown with design consultants (architects/engineers), Inadequate time to produce bidding documents, Faulty construction, Items missing from the contract documents, Specification non-compliance, Mistakes in contract documents b. Dependent Variable: Percentage Increase in project Schedule
  • 17. Statistical Significance The tables below show the ANOVA table from the regression analysis. The F-ratio was used to test whether the overall regression model was a good fit for the data. The table shows that the causes of rework are statistically significant in predicting the overall increase in project cost, F(10, 28) = 23.847, p < 0.001, and overall increase in the project schedule, F(10, 28) = 11.881, p < 0.001 indicating that the regression model was a good fit for the data. Table: Regression Model Fit for percentage cost increase with rework Table: Regression Model Fit for percentage Schedule increase with rework ANOVAa Model Sum of Squares df Mean Square F Sig. 1 Regression 11579.939 10 1157.994 23.857 0.000b Residual 1359.086 28 48.539 Total 12939.025 38 a. Dependent Variable: Percentage Increase in Project Cost b. Predictors: (Constant), Carelessness resulting into damage to other works, Tender being incomplete at the time of bidding, Workers being given unclear instructions, Having few trained supervisors on site, Communication breakdown with design consultants (architects/engineers), Inadequate time to produce bidding documents, Faulty construction, Items missing from the contract documents, Specification non-compliance, Mistakes in contract documents. ANOVAa Model Sum of Squares df Mean Square F Sig. 1 Regression 10020.267 10 1002.027 11.881 0.000b Residual 2361.425 28 84.337 Total 12381.692 38 a. Dependent Variable: Percentage Increase in project time b. Predictors: (Constant), Carelessness resulting into damage to other works, Tender being incomplete at the time of bidding, Workers being given unclear instructions., Having few trained supervisors on site, Communication breakdown with design consultants (architects/engineers), Inadequate time to produce bidding documents, Faulty construction, Items missing from the contract documents, Specification non-compliance, Mistakes in contract documents.
  • 18. Objective 3: Strategies to minimize Rework on cost and schedule The Relative Importance Index (RII) was calculated and the identified causes were ranked as per the responses in the table below. The most notable solutions were identified to be; S/N Measures taken to reduce rework on Cost and schedule RII Rank 1 Using sufficient and capable human resource 0.882 2 2 Sufficient supervision 0.887 1 3 Developing effective communication between project participants 0.872 3 4 Continuous monitoring before and throughout work implementation of work 0.867 4 5 Involving the client 0.815 8 6 Using effective planning and scheduling 0.867 4 7 Using qualified suppliers 0.764 11 8 Tracking and documenting rework incidents 0.810 10 9 Identifying the root cause of rework in detail 0.826 6 10 Developing options and actions to reduce reworking 0.821 7 11 Quantifying the cost and time effect of rework on project delivery 0.815 8 Where: W - is the weight given to each factor by the respondents and ranges from 0 to 39, X is the largest weight (i.e., 39 in this case) and; N - is the total number of people that responded.
  • 19. The study also elicited independent suggestions from the respondents on how to mitigate the cost and schedule impact of rework and these are as below. ➢Developing work programmes ➢getting an in-depth cause and solutions to the problem other than basing on assumptions ➢Proper Project conceptualization and adequate planning ➢Public projects should actively engage the stakeholders at the planning stage ➢Investing in Quality Control and Quality Assurance ➢Ensuring that work is done as per specifications, and drawings and also maintaining quality. ➢Proper planning of works ➢Adherence to documentation and permissions ➢Incorporating value engineering into all kinds of construction projects
  • 20. CONCLUSIONS AND RECOMMENDATIONS Conclusions Close attention should be given to Contractor related rework causes as they were seen to be the heaviest contributor to the negative effects. There is a need for prior knowledge of rework during construction can help projects save money and time. KCCA should know that the costs for building projects end up becoming very high because of the complexities resulting from Rework. Various methods can be deployed to help reduce the negative impacts of Rework on construction projects and all project participants should be aware of these and know how to utilise them. Recommendations The project team should always have strategies for detecting Rework and be able to put in place mitigation measures to mitigate rework. Parties responsible for rework should bear the cost. This prevents unnecessary costs for the client and keeps everyone on top of their game. There is a need to allocate more supervisory resources like a “clerk of works” on projects to closely monitor the implementation of the project.
  • 21. REFERENCES Trach, R., & Pawluk, K. (2019). CAUSES OF REWORK IN CONSTRUCTION PROJECTS IN UKRAINE. Pan Polska, 63. Kakitahi, Alinaitwe (2016) Impact of construction-related rework on selected Ugandan public projects, Journal of Engineering Design and Technology. Alinaitwe, H. (2014). A COMPARISON OF CONSTRUCTION-RELATED REWORK IN UGANDAAND MOZAMBIQUE. Journal of Construction Project Management and Innovation, 775-776. Ntungire, E. C. (2018, December). Construction and public procurement in Uganda. Boston: United Nations University. Rezahoseini, A., Noori, S., & Ghannadpour, S. F. (2019). Reducing rework and increasing the quality of the civil project, through Total Quality Management (TQM), by using the concept of Building Information Modelling (BIM). Journal of Industrial and Systems Engineering, 3. Joseph Stables, G. O. (2018, November 18). Uganda Construction Capacity Preliminary Assessment: Key Findings and Recommendations. Infrastructure for Cities and Economic Development, p.6.
  • 22. END