SlideShare a Scribd company logo
1 of 16
Project Costs Go Up: the Question is Why? NASA Project Management Challenge Long Beach, CA Feb 9 – 10, 2011 Rod Zieger Manager, Project Support Office Jet Propulsion Laboratory, California Institute of Technology Used with permission
Content ,[object Object],[object Object],[object Object],[object Object],[object Object],[object Object]
What We Have Learned (1) ,[object Object],[object Object],[object Object],[object Object],[object Object]
What We Have Learned (2) ,[object Object],[object Object],[object Object],[object Object],[object Object],[object Object],[object Object]
Pre-Phase A & Proposals Phase A Phase B Phase C Phase D Authorization Commitment MCR/ Downselect PDR  Phase E SIR CDR  SRR/MDR/ Selection Preliminary estimates remembered by sponsors as commitments L Costs Go Up Anywhere in the Lifecycle Optimistic assumptions  Incomplete requirements Requirements creep without funding creep Increased knowledge and detail in cost estimates Contractors bids exceed assumptions Test failures LV Delays Increased understanding of technical difficulty Schedule delays anytime are major cost drivers Scope doesn’t match resources New technical problems discovered (S/C, LV, etc) Management inexperience with projects of similar complexity
Cost Increases are Not New !! This is a copy of an original Werner Gruhl chart from April 19, 1988
Costs Go Up With Schedule Delays Example FY 1 FY 2 FY 5 FY 4 FY 3 FY 7 FY 6 FY 8 Δ   Cost, % / mo 0.6 Baseline Plan 14 Δ   L, mo 5 Δ   Cost,  % 3 11 0 0 1.3 1.4 19 15 0 (this is based on a real project that had 4 significant delays from the baseline plan) 15 1.1 17 PDR B C/D E L C/D E L PDR B C/D E L C/D E E L TOTAL Project Cost, $M 290 280 235 205 175 L Schedule Delay Due to Funding Delay More Schedule Delay Due to Funding Delay Schedule Delay Due to Tech Problems & Contractor Capability Schedule Delay Due to Launch Vehicle
Generic Causes:   Costs Went Up From Delays (1) ,[object Object],[object Object],[object Object],[object Object],[object Object]
Generic Causes:   Costs Went Up From Delays (2) ,[object Object],[object Object],[object Object],[object Object],[object Object]
Risk Imbalances Lead to Cost Increases Desirable Characteristics Cost Risks Enormous Science Breakthrough Innovative Mission Concept High Decadal Survey Ranking High NASA Strategic Priority Exciting to Public Advances State of the Art World-Class PI  Advocate Risks Not Well Understood Few Acceptable Descopes Requirements Not Well Defined Inheritance Several Years Old New Mission/  System Architecture New Operating Environments Scope Mismatch to Cost & Schedule New Technology Breakthrough No Experience With This Kind of Mission
Implementation Problems Are Big Cost Drivers Phase C Phase D Commitment PDR  SIR CDR  L (more)   New driving requirements mandated  (fewer) Start implementation before design complete  - Build to redlines, then re-build - Order wrong parts, then re-order Costs of trades open at PDR Infrastructure not available on time due to schedule slip by other projects  Known threats against the budget not included in the baseline - Known threats consume reserves, inadequate reserves remain to cover new unknown-unknowns Environmental test failure requires redesign New technology not ready, requires redesign Not identifying impending schedule slips in time for efficient replan Contractor capabilities not adequate to deliver  Hardware failure during I&T requires redesign Partner performance shortfalls  Launch vehicle readiness slips
What Would Help: At the Start ,[object Object],[object Object],[object Object],[object Object],[object Object],[object Object],[object Object],[object Object],[object Object],[object Object]
What Would Help: Formulation ,[object Object],[object Object],[object Object],[object Object],[object Object],[object Object],[object Object],[object Object],[object Object],[object Object],[object Object],[object Object]
What Would Help: Implementation ,[object Object],[object Object],[object Object],[object Object],[object Object],[object Object],[object Object],[object Object],[object Object],[object Object],[object Object]
What Would Help: The Soft Stuff ,[object Object],[object Object],[object Object],[object Object],[object Object],[object Object],[object Object],[object Object]
[object Object],[object Object],[object Object],[object Object],[object Object],[object Object],[object Object],Summary

More Related Content

What's hot

Costello kenneth
Costello kennethCostello kenneth
Costello kenneth
NASAPMC
 
Backup darren elliott
Backup darren elliottBackup darren elliott
Backup darren elliott
NASAPMC
 
Cole ready aim fire impact!- status impact analysis - nasa
Cole   ready aim fire impact!- status impact analysis - nasaCole   ready aim fire impact!- status impact analysis - nasa
Cole ready aim fire impact!- status impact analysis - nasa
NASAPMC
 
Armstrong
ArmstrongArmstrong
Armstrong
NASAPMC
 
Matt.gonzales
Matt.gonzalesMatt.gonzales
Matt.gonzales
NASAPMC
 
Stefanini.trinh
Stefanini.trinhStefanini.trinh
Stefanini.trinh
NASAPMC
 
Rider.stephen
Rider.stephenRider.stephen
Rider.stephen
NASAPMC
 
Dan galorath
Dan galorathDan galorath
Dan galorath
NASAPMC
 
Osterkamp jeff
Osterkamp jeffOsterkamp jeff
Osterkamp jeff
NASAPMC
 
Thomas.coonce
Thomas.coonceThomas.coonce
Thomas.coonce
NASAPMC
 
Geyer.m.sasaki.c
Geyer.m.sasaki.cGeyer.m.sasaki.c
Geyer.m.sasaki.c
NASAPMC
 
Hughitt brian
Hughitt brianHughitt brian
Hughitt brian
NASAPMC
 
Jenks.ken
Jenks.kenJenks.ken
Jenks.ken
NASAPMC
 
Dezfuli youngblood
Dezfuli youngbloodDezfuli youngblood
Dezfuli youngblood
NASAPMC
 

What's hot (20)

Symons
SymonsSymons
Symons
 
Costello kenneth
Costello kennethCostello kenneth
Costello kenneth
 
Backup darren elliott
Backup darren elliottBackup darren elliott
Backup darren elliott
 
Cole ready aim fire impact!- status impact analysis - nasa
Cole   ready aim fire impact!- status impact analysis - nasaCole   ready aim fire impact!- status impact analysis - nasa
Cole ready aim fire impact!- status impact analysis - nasa
 
Risk Management Processes from Jerry Klanac
Risk Management Processes from Jerry KlanacRisk Management Processes from Jerry Klanac
Risk Management Processes from Jerry Klanac
 
A Suite Of Tools For Technology Assessment
A Suite Of Tools For Technology AssessmentA Suite Of Tools For Technology Assessment
A Suite Of Tools For Technology Assessment
 
Armstrong
ArmstrongArmstrong
Armstrong
 
Matt.gonzales
Matt.gonzalesMatt.gonzales
Matt.gonzales
 
Stefanini.trinh
Stefanini.trinhStefanini.trinh
Stefanini.trinh
 
Rider.stephen
Rider.stephenRider.stephen
Rider.stephen
 
Cure for cost and schedule growth
Cure for cost and schedule growthCure for cost and schedule growth
Cure for cost and schedule growth
 
Dan galorath
Dan galorathDan galorath
Dan galorath
 
Osterkamp jeff
Osterkamp jeffOsterkamp jeff
Osterkamp jeff
 
Risk Modeling and Analysis (Mitigating the Planning Fallacy)
Risk Modeling and Analysis (Mitigating the Planning Fallacy)Risk Modeling and Analysis (Mitigating the Planning Fallacy)
Risk Modeling and Analysis (Mitigating the Planning Fallacy)
 
Thomas.coonce
Thomas.coonceThomas.coonce
Thomas.coonce
 
Geyer.m.sasaki.c
Geyer.m.sasaki.cGeyer.m.sasaki.c
Geyer.m.sasaki.c
 
WBS is Paramount
WBS is ParamountWBS is Paramount
WBS is Paramount
 
Hughitt brian
Hughitt brianHughitt brian
Hughitt brian
 
Jenks.ken
Jenks.kenJenks.ken
Jenks.ken
 
Dezfuli youngblood
Dezfuli youngbloodDezfuli youngblood
Dezfuli youngblood
 

Viewers also liked

Alfred mecum
Alfred mecumAlfred mecum
Alfred mecum
NASAPMC
 
Rovinsky final
Rovinsky finalRovinsky final
Rovinsky final
NASAPMC
 
Leonard.matthew
Leonard.matthewLeonard.matthew
Leonard.matthew
NASAPMC
 
J marinaro jmay
J marinaro jmayJ marinaro jmay
J marinaro jmay
NASAPMC
 
Maturo.a.midgett.j
Maturo.a.midgett.jMaturo.a.midgett.j
Maturo.a.midgett.j
NASAPMC
 
Baniszewski.john
Baniszewski.johnBaniszewski.john
Baniszewski.john
NASAPMC
 
Taylor.randall
Taylor.randallTaylor.randall
Taylor.randall
NASAPMC
 

Viewers also liked (7)

Alfred mecum
Alfred mecumAlfred mecum
Alfred mecum
 
Rovinsky final
Rovinsky finalRovinsky final
Rovinsky final
 
Leonard.matthew
Leonard.matthewLeonard.matthew
Leonard.matthew
 
J marinaro jmay
J marinaro jmayJ marinaro jmay
J marinaro jmay
 
Maturo.a.midgett.j
Maturo.a.midgett.jMaturo.a.midgett.j
Maturo.a.midgett.j
 
Baniszewski.john
Baniszewski.johnBaniszewski.john
Baniszewski.john
 
Taylor.randall
Taylor.randallTaylor.randall
Taylor.randall
 

Similar to Zieger.alfred

Barley newhouse
Barley newhouseBarley newhouse
Barley newhouse
NASAPMC
 
Cassidy.jim
Cassidy.jimCassidy.jim
Cassidy.jim
NASAPMC
 
Backup jim cassidy
Backup jim cassidyBackup jim cassidy
Backup jim cassidy
NASAPMC
 
Goodwin, John MULTIPURPOSE RESUME
Goodwin, John MULTIPURPOSE RESUMEGoodwin, John MULTIPURPOSE RESUME
Goodwin, John MULTIPURPOSE RESUME
John Goodwin
 
Successfully Achieving And Delivering Results Through Rigorous Project Select...
Successfully Achieving And Delivering ResultsThrough Rigorous Project Select...Successfully Achieving And Delivering ResultsThrough Rigorous Project Select...
Successfully Achieving And Delivering Results Through Rigorous Project Select...
shawncarner
 

Similar to Zieger.alfred (20)

Opportunity framing
Opportunity framingOpportunity framing
Opportunity framing
 
2 a. project auditing
2 a. project auditing2 a. project auditing
2 a. project auditing
 
PPTX Corporate Project Presentation FEL in New Energies 2023.ppsx
PPTX Corporate   Project Presentation FEL in  New Energies 2023.ppsxPPTX Corporate   Project Presentation FEL in  New Energies 2023.ppsx
PPTX Corporate Project Presentation FEL in New Energies 2023.ppsx
 
Barley newhouse
Barley newhouseBarley newhouse
Barley newhouse
 
Architecture presentation 9
Architecture presentation 9Architecture presentation 9
Architecture presentation 9
 
Pmwg.110603
Pmwg.110603Pmwg.110603
Pmwg.110603
 
Cassidy.jim
Cassidy.jimCassidy.jim
Cassidy.jim
 
Pharmaceutical Project Management Checklist
Pharmaceutical Project Management ChecklistPharmaceutical Project Management Checklist
Pharmaceutical Project Management Checklist
 
Phil Welker Commissioning
Phil Welker CommissioningPhil Welker Commissioning
Phil Welker Commissioning
 
Project management (A Basic Approach)
Project management (A Basic Approach)Project management (A Basic Approach)
Project management (A Basic Approach)
 
Backup jim cassidy
Backup jim cassidyBackup jim cassidy
Backup jim cassidy
 
Moldova ICT Summit 2011 - Pentalog's presentation in Project Management section.
Moldova ICT Summit 2011 - Pentalog's presentation in Project Management section.Moldova ICT Summit 2011 - Pentalog's presentation in Project Management section.
Moldova ICT Summit 2011 - Pentalog's presentation in Project Management section.
 
Building Energy Efficiency Metrics: From Title 24 to EUI
Building Energy Efficiency Metrics: From Title 24 to EUIBuilding Energy Efficiency Metrics: From Title 24 to EUI
Building Energy Efficiency Metrics: From Title 24 to EUI
 
Goodwin, John MULTIPURPOSE RESUME
Goodwin, John MULTIPURPOSE RESUMEGoodwin, John MULTIPURPOSE RESUME
Goodwin, John MULTIPURPOSE RESUME
 
Phase gate review development model august 8 2017 - dave litwiller
Phase gate review development model   august 8 2017 - dave litwillerPhase gate review development model   august 8 2017 - dave litwiller
Phase gate review development model august 8 2017 - dave litwiller
 
Pl Pr3
Pl Pr3Pl Pr3
Pl Pr3
 
Baskaren Accomplishments Summary
Baskaren Accomplishments SummaryBaskaren Accomplishments Summary
Baskaren Accomplishments Summary
 
Successfully Achieving And Delivering Results Through Rigorous Project Select...
Successfully Achieving And Delivering ResultsThrough Rigorous Project Select...Successfully Achieving And Delivering ResultsThrough Rigorous Project Select...
Successfully Achieving And Delivering Results Through Rigorous Project Select...
 
PPRPreparationGuide
PPRPreparationGuidePPRPreparationGuide
PPRPreparationGuide
 
Pmicos 2011 Ppt Schedule Componentsr Raf Rev
Pmicos 2011 Ppt Schedule Componentsr Raf RevPmicos 2011 Ppt Schedule Componentsr Raf Rev
Pmicos 2011 Ppt Schedule Componentsr Raf Rev
 

More from NASAPMC

Bejmuk bo
Bejmuk boBejmuk bo
Bejmuk bo
NASAPMC
 
Baniszewski john
Baniszewski johnBaniszewski john
Baniszewski john
NASAPMC
 
Yew manson
Yew mansonYew manson
Yew manson
NASAPMC
 
Wood frank
Wood frankWood frank
Wood frank
NASAPMC
 
Wood frank
Wood frankWood frank
Wood frank
NASAPMC
 
Wessen randi (cd)
Wessen randi (cd)Wessen randi (cd)
Wessen randi (cd)
NASAPMC
 
Vellinga joe
Vellinga joeVellinga joe
Vellinga joe
NASAPMC
 
Trahan stuart
Trahan stuartTrahan stuart
Trahan stuart
NASAPMC
 
Stock gahm
Stock gahmStock gahm
Stock gahm
NASAPMC
 
Snow lee
Snow leeSnow lee
Snow lee
NASAPMC
 
Smalley sandra
Smalley sandraSmalley sandra
Smalley sandra
NASAPMC
 
Seftas krage
Seftas krageSeftas krage
Seftas krage
NASAPMC
 
Sampietro marco
Sampietro marcoSampietro marco
Sampietro marco
NASAPMC
 
Rudolphi mike
Rudolphi mikeRudolphi mike
Rudolphi mike
NASAPMC
 
Roberts karlene
Roberts karleneRoberts karlene
Roberts karlene
NASAPMC
 
Rackley mike
Rackley mikeRackley mike
Rackley mike
NASAPMC
 
Paradis william
Paradis williamParadis william
Paradis william
NASAPMC
 
O'keefe william
O'keefe williamO'keefe william
O'keefe william
NASAPMC
 
Muller ralf
Muller ralfMuller ralf
Muller ralf
NASAPMC
 
Mulenburg jerry
Mulenburg jerryMulenburg jerry
Mulenburg jerry
NASAPMC
 

More from NASAPMC (20)

Bejmuk bo
Bejmuk boBejmuk bo
Bejmuk bo
 
Baniszewski john
Baniszewski johnBaniszewski john
Baniszewski john
 
Yew manson
Yew mansonYew manson
Yew manson
 
Wood frank
Wood frankWood frank
Wood frank
 
Wood frank
Wood frankWood frank
Wood frank
 
Wessen randi (cd)
Wessen randi (cd)Wessen randi (cd)
Wessen randi (cd)
 
Vellinga joe
Vellinga joeVellinga joe
Vellinga joe
 
Trahan stuart
Trahan stuartTrahan stuart
Trahan stuart
 
Stock gahm
Stock gahmStock gahm
Stock gahm
 
Snow lee
Snow leeSnow lee
Snow lee
 
Smalley sandra
Smalley sandraSmalley sandra
Smalley sandra
 
Seftas krage
Seftas krageSeftas krage
Seftas krage
 
Sampietro marco
Sampietro marcoSampietro marco
Sampietro marco
 
Rudolphi mike
Rudolphi mikeRudolphi mike
Rudolphi mike
 
Roberts karlene
Roberts karleneRoberts karlene
Roberts karlene
 
Rackley mike
Rackley mikeRackley mike
Rackley mike
 
Paradis william
Paradis williamParadis william
Paradis william
 
O'keefe william
O'keefe williamO'keefe william
O'keefe william
 
Muller ralf
Muller ralfMuller ralf
Muller ralf
 
Mulenburg jerry
Mulenburg jerryMulenburg jerry
Mulenburg jerry
 

Recently uploaded

The basics of sentences session 3pptx.pptx
The basics of sentences session 3pptx.pptxThe basics of sentences session 3pptx.pptx
The basics of sentences session 3pptx.pptx
heathfieldcps1
 
Jual Obat Aborsi Hongkong ( Asli No.1 ) 085657271886 Obat Penggugur Kandungan...
Jual Obat Aborsi Hongkong ( Asli No.1 ) 085657271886 Obat Penggugur Kandungan...Jual Obat Aborsi Hongkong ( Asli No.1 ) 085657271886 Obat Penggugur Kandungan...
Jual Obat Aborsi Hongkong ( Asli No.1 ) 085657271886 Obat Penggugur Kandungan...
ZurliaSoop
 

Recently uploaded (20)

REMIFENTANIL: An Ultra short acting opioid.pptx
REMIFENTANIL: An Ultra short acting opioid.pptxREMIFENTANIL: An Ultra short acting opioid.pptx
REMIFENTANIL: An Ultra short acting opioid.pptx
 
COMMUNICATING NEGATIVE NEWS - APPROACHES .pptx
COMMUNICATING NEGATIVE NEWS - APPROACHES .pptxCOMMUNICATING NEGATIVE NEWS - APPROACHES .pptx
COMMUNICATING NEGATIVE NEWS - APPROACHES .pptx
 
Graduate Outcomes Presentation Slides - English
Graduate Outcomes Presentation Slides - EnglishGraduate Outcomes Presentation Slides - English
Graduate Outcomes Presentation Slides - English
 
TỔNG ÔN TẬP THI VÀO LỚP 10 MÔN TIẾNG ANH NĂM HỌC 2023 - 2024 CÓ ĐÁP ÁN (NGỮ Â...
TỔNG ÔN TẬP THI VÀO LỚP 10 MÔN TIẾNG ANH NĂM HỌC 2023 - 2024 CÓ ĐÁP ÁN (NGỮ Â...TỔNG ÔN TẬP THI VÀO LỚP 10 MÔN TIẾNG ANH NĂM HỌC 2023 - 2024 CÓ ĐÁP ÁN (NGỮ Â...
TỔNG ÔN TẬP THI VÀO LỚP 10 MÔN TIẾNG ANH NĂM HỌC 2023 - 2024 CÓ ĐÁP ÁN (NGỮ Â...
 
Sensory_Experience_and_Emotional_Resonance_in_Gabriel_Okaras_The_Piano_and_Th...
Sensory_Experience_and_Emotional_Resonance_in_Gabriel_Okaras_The_Piano_and_Th...Sensory_Experience_and_Emotional_Resonance_in_Gabriel_Okaras_The_Piano_and_Th...
Sensory_Experience_and_Emotional_Resonance_in_Gabriel_Okaras_The_Piano_and_Th...
 
On_Translating_a_Tamil_Poem_by_A_K_Ramanujan.pptx
On_Translating_a_Tamil_Poem_by_A_K_Ramanujan.pptxOn_Translating_a_Tamil_Poem_by_A_K_Ramanujan.pptx
On_Translating_a_Tamil_Poem_by_A_K_Ramanujan.pptx
 
Plant propagation: Sexual and Asexual propapagation.pptx
Plant propagation: Sexual and Asexual propapagation.pptxPlant propagation: Sexual and Asexual propapagation.pptx
Plant propagation: Sexual and Asexual propapagation.pptx
 
How to Create and Manage Wizard in Odoo 17
How to Create and Manage Wizard in Odoo 17How to Create and Manage Wizard in Odoo 17
How to Create and Manage Wizard in Odoo 17
 
This PowerPoint helps students to consider the concept of infinity.
This PowerPoint helps students to consider the concept of infinity.This PowerPoint helps students to consider the concept of infinity.
This PowerPoint helps students to consider the concept of infinity.
 
The basics of sentences session 3pptx.pptx
The basics of sentences session 3pptx.pptxThe basics of sentences session 3pptx.pptx
The basics of sentences session 3pptx.pptx
 
How to Give a Domain for a Field in Odoo 17
How to Give a Domain for a Field in Odoo 17How to Give a Domain for a Field in Odoo 17
How to Give a Domain for a Field in Odoo 17
 
Unit 3 Emotional Intelligence and Spiritual Intelligence.pdf
Unit 3 Emotional Intelligence and Spiritual Intelligence.pdfUnit 3 Emotional Intelligence and Spiritual Intelligence.pdf
Unit 3 Emotional Intelligence and Spiritual Intelligence.pdf
 
How to setup Pycharm environment for Odoo 17.pptx
How to setup Pycharm environment for Odoo 17.pptxHow to setup Pycharm environment for Odoo 17.pptx
How to setup Pycharm environment for Odoo 17.pptx
 
General Principles of Intellectual Property: Concepts of Intellectual Proper...
General Principles of Intellectual Property: Concepts of Intellectual  Proper...General Principles of Intellectual Property: Concepts of Intellectual  Proper...
General Principles of Intellectual Property: Concepts of Intellectual Proper...
 
Accessible Digital Futures project (20/03/2024)
Accessible Digital Futures project (20/03/2024)Accessible Digital Futures project (20/03/2024)
Accessible Digital Futures project (20/03/2024)
 
2024-NATIONAL-LEARNING-CAMP-AND-OTHER.pptx
2024-NATIONAL-LEARNING-CAMP-AND-OTHER.pptx2024-NATIONAL-LEARNING-CAMP-AND-OTHER.pptx
2024-NATIONAL-LEARNING-CAMP-AND-OTHER.pptx
 
Jual Obat Aborsi Hongkong ( Asli No.1 ) 085657271886 Obat Penggugur Kandungan...
Jual Obat Aborsi Hongkong ( Asli No.1 ) 085657271886 Obat Penggugur Kandungan...Jual Obat Aborsi Hongkong ( Asli No.1 ) 085657271886 Obat Penggugur Kandungan...
Jual Obat Aborsi Hongkong ( Asli No.1 ) 085657271886 Obat Penggugur Kandungan...
 
How to Add New Custom Addons Path in Odoo 17
How to Add New Custom Addons Path in Odoo 17How to Add New Custom Addons Path in Odoo 17
How to Add New Custom Addons Path in Odoo 17
 
How to Manage Global Discount in Odoo 17 POS
How to Manage Global Discount in Odoo 17 POSHow to Manage Global Discount in Odoo 17 POS
How to Manage Global Discount in Odoo 17 POS
 
SOC 101 Demonstration of Learning Presentation
SOC 101 Demonstration of Learning PresentationSOC 101 Demonstration of Learning Presentation
SOC 101 Demonstration of Learning Presentation
 

Zieger.alfred

  • 1. Project Costs Go Up: the Question is Why? NASA Project Management Challenge Long Beach, CA Feb 9 – 10, 2011 Rod Zieger Manager, Project Support Office Jet Propulsion Laboratory, California Institute of Technology Used with permission
  • 2.
  • 3.
  • 4.
  • 5. Pre-Phase A & Proposals Phase A Phase B Phase C Phase D Authorization Commitment MCR/ Downselect PDR Phase E SIR CDR SRR/MDR/ Selection Preliminary estimates remembered by sponsors as commitments L Costs Go Up Anywhere in the Lifecycle Optimistic assumptions Incomplete requirements Requirements creep without funding creep Increased knowledge and detail in cost estimates Contractors bids exceed assumptions Test failures LV Delays Increased understanding of technical difficulty Schedule delays anytime are major cost drivers Scope doesn’t match resources New technical problems discovered (S/C, LV, etc) Management inexperience with projects of similar complexity
  • 6. Cost Increases are Not New !! This is a copy of an original Werner Gruhl chart from April 19, 1988
  • 7. Costs Go Up With Schedule Delays Example FY 1 FY 2 FY 5 FY 4 FY 3 FY 7 FY 6 FY 8 Δ Cost, % / mo 0.6 Baseline Plan 14 Δ L, mo 5 Δ Cost, % 3 11 0 0 1.3 1.4 19 15 0 (this is based on a real project that had 4 significant delays from the baseline plan) 15 1.1 17 PDR B C/D E L C/D E L PDR B C/D E L C/D E E L TOTAL Project Cost, $M 290 280 235 205 175 L Schedule Delay Due to Funding Delay More Schedule Delay Due to Funding Delay Schedule Delay Due to Tech Problems & Contractor Capability Schedule Delay Due to Launch Vehicle
  • 8.
  • 9.
  • 10. Risk Imbalances Lead to Cost Increases Desirable Characteristics Cost Risks Enormous Science Breakthrough Innovative Mission Concept High Decadal Survey Ranking High NASA Strategic Priority Exciting to Public Advances State of the Art World-Class PI Advocate Risks Not Well Understood Few Acceptable Descopes Requirements Not Well Defined Inheritance Several Years Old New Mission/ System Architecture New Operating Environments Scope Mismatch to Cost & Schedule New Technology Breakthrough No Experience With This Kind of Mission
  • 11. Implementation Problems Are Big Cost Drivers Phase C Phase D Commitment PDR SIR CDR L (more) New driving requirements mandated (fewer) Start implementation before design complete - Build to redlines, then re-build - Order wrong parts, then re-order Costs of trades open at PDR Infrastructure not available on time due to schedule slip by other projects Known threats against the budget not included in the baseline - Known threats consume reserves, inadequate reserves remain to cover new unknown-unknowns Environmental test failure requires redesign New technology not ready, requires redesign Not identifying impending schedule slips in time for efficient replan Contractor capabilities not adequate to deliver Hardware failure during I&T requires redesign Partner performance shortfalls Launch vehicle readiness slips
  • 12.
  • 13.
  • 14.
  • 15.
  • 16.