2. Which of the following statements is true about the change
control board?
A. A change control board is a group responsible for reviewing
and approving or rejecting changes to the project.
B. The change control board is responsible for tracking change
status to ensure all approved changes are correctly
implemented.
C. The change control board should not include the project
team to ensure objective decisions are made.
D. Every change should be analyzed and approved by the
change control board before being implemented.
HINT: Remember the concept of change control board.
QUESTION
3. The correct answer is A.
Every change request needs to be either approved or rejected by
a responsible individual or a change control board when required.
Depending on the complexity of the specific project or contract
requirements, some of changes may be approved by individuals,
while other changes may need to be considered by the change
control board, including relevant stakeholders before making
decisions. The change control board is a formally chartered group
responsible for reviewing, evaluating, approving, deferring, or
rejecting changes to the project and for recording and
communicating such decisions. The project team is responsible
for implementing and tracking approved change requests to
ensure they are correctly implemented.
ANSWER
4. All our questions are updated to the latest
A Guide to the Project Management Body of Knowledge (PMBOK® Guide)
standard.