2. Which of the following statements is true about the change control board?
A. A change control board is a group responsible for reviewing and approving or rejecting
changes to the project.
B. The change control board is responsible for tracking change status to ensure all
approved changes are correctly implemented.
C. The change control board should not include the project team to ensure objective
decisions are made.
D. Every change should be analyzed and approved by the change control board before
being implemented.
HINT: Remember the concept of change control board.
QUESTION:
3. The correct answer is A
Every change request needs to be either approved or rejected by a responsible individual or a
change control board when required. Depending on the complexity of the specific project or
contract requirements, some of changes may be approved by individuals, while other changes
may need to be considered by the change control board, including relevant stakeholders
before making decisions. The change control board is a formally chartered group responsible
for reviewing, evaluating, approving, deferring, or rejecting changes to the project and for
recording and communicating such decisions. The project team is responsible for
implementing and tracking approved change requests to ensure they are correctly
implemented.
ANSWER:
4. All our questions are updated to the latest A Guide to the Project Management Body of Knowledge
(PMBOK® Guide) standard.