2. PROBLEM ISSUE
Some activities must be done first before doing the next activity
Delay in some activity may cause delay in overall schedule
Need to Finish the project faster than normal time
3. METHODS
CRITICAL PATH METHOD (CPM)
Was develop by Dupond Company in 1950’s
Algorithm for scheduling a set of project
activities
Deterministic concept is used
Cost optimization is given prime importance
PROGRAM EVALUATION REVIEW
TECHNIQUE (PERT)
Tool for planning
Probabilistic
Assumed cost varies directly with time
model concept is used
Time is the controlling factor
5. ALTERNATIVE COURSE OF ACTION
Minimum Project Completion
Time (Using Normal Time)
Results by WinQsb software,
there are 32 critical paths and
project finished on 390 days
6. ALTERNATIVE COURSE OF ACTION
Gant Chart
Results by WinQsb software
Activities 1,2,3,4,5,6,7 are critical
activities and slack time is zero
7. ALTERNATIVE COURSE OF ACTION
CPM
Results by WinQsb software
Project completion in 365 days will
cost additional 2,364,353 Rials
8. ALTERNATIVE COURSE OF ACTION
PERT
Results by WinQsb software
Project completion in 364.67 days is
and have 384 critical paths
9. ALTERNATIVE COURSE OF ACTION
PERT
Results by WinQsb software
the maximum probability
completion
365 days 53.49%
370 days 84.14%
380 days 99.80%
10. KEY SUCCESS OF FACTOR
Right planning (Critical activity crashing )
On time scheduling
Control of project
Money
12. RECOMMENDATION
In doing CPM there will be some additional cost, makes sure that the budget is ready
PERT shows us the probability of achieving the target, make sure to choose one that is feasible