SlideShare a Scribd company logo
1 of 11
-Super Lightweight Tank-
A Risk Management Case Study in
Mass Reduction
AN INOVATIVE DISTRIBUTED PROJECT CONTROL
APPROACH : A CASE STUDY OF THE CASSINI MIS
Presented by Yulhendri Saputra & Marcel Bernadi
 Introduction
 Problem Issues
 Environmental Scanning
 Alternatives Course of Actions
 Key Success Factors
 Selection of Best Alternatives
 Recommendation
INTRODUCTION
 Originally. Congress approved funding for a joint program composed of a
Comet Rendezvous/Asteroid Flyby (CRAF) mission and the Cassini mission.
 The program was authorized with the stipulation that it would be canceled if
original cost estimates were exceeded.
 In response, Jet Propulsion Laboratory (JPL) chose to implement a classical
earned-value system for controlling schedule and cost.
 In 1990, after purchasing a full-featured commercialoff-the-shelf (COTS)
project management system, the project hired 20 schedulers and planners to
implement a full) integrated network schedule.
 The system was based on classic program evaluation and review technique
(PERT) concepts (developed in 1958) and the Cost/Schedule Control System
Criteria (C/SCSC) formalized by the U.S. Department of Defense in 1967.
 A large expenditure was made for training at all project levels. By late 199 1 ,
CRAF/Cassini project managers observed somt: trends with the entire project
control process: This refereed c a s e study article w a s accepted January
1996.
ENVIRONMENTAL SCANNING
 The COTS project management system process countered JPL's effort to
having decision making shifted to lower levels in the organization.
 Considering the large expenditure for project control, no corresponding
improvement was made with regard to communication between the
different project elements.
 The COTS project management system was not viewed as an easy-to-use
tool.
 The COTS project management system did not provide a straightforward
method for addressing uncertainty.
PROBLEM ISSUES
"Network-based techniques as planning tools do not consider the issue of
uncertainty in identifying tasks and the relationship among tasks in the network"
(Morad and Vorster, 1993).
 
"A network models only one set of schedule options at any given time"
(Mathews, 1993).
"The current approach to planning and controlling complex projects has
traditionally been to eliminate mcertainty and change from our projects, or at
ieast treat them as if change will not occur7' (Archibald and Lichtenburg, 1994).
"Older packages emphasize the critical path method, which can be very clumsy
when scheduling people. Classic approaches tend to be expensive and roo!ed
in legacy technologies" (Wood, 1995). In short, the project found that the
cleanliness of theory (PERT, CISCSC) was no match for the clutter of reality.
ALTERNATIVE COURSE OF ACTION
1. CPM and PERT
Network-based techniques as planning tools do not consider the issue of uncertainty in
identifying tasks and the relationship among tasks in the network"
 
Eliminate uncertainty and change from our projects, or treat them as if no change
Older packages emphasize the critical path method, which can be very clumsy. In short,
the project found that the cleanliness of theory was no match for the clutter of reality.
2. CMlS
• All project products have to be someone's deliverable (Del) and another's receivable
• Once a deliverer and receiver reach an agreement on the need t
• Each Reciving and Delivery agreement
• Any person on the project is able to determine a Rec/Dells status at any given time
KEY SUCCES FACTOR
The value of this approach became immediately apparent:
I. The CMIS schedule control module facilitated and increased communication. It also
highlighted where communication between project elements was deficient. Product
specification and delivery schedule disputes were easily identified, problems were
quickly addressed. and schedule confusion vanished.
2. Schedule tracking and statusing became virtually effortless. The project implemented
an automated statusing system that polled receivers on a weekly basis about whether
they had received their agreed-to deliveries for that week. Receiver responses to the
messages were automatically compiled and summarized in weekly metric reports to
management. In addition, on-line statusing within CMIS was provided.
3. The single-database design allowed current project-level schedule reports to be
generated at any time.
4. CMIS reduced centralized project control costs to less than 0.25% of the total project
budget. The workforce of planners/schedulers dropped from
20 people to an operations staff of 3 . This yielded a savings of greater than 60 work-
years over the project's development phase.
SELECTION OF BEST ALTERNATIVES
CMIS Schedule Control Module Planning Reports and Metrics.
•Before CMIS implementation, many seasoned managers expected that the simple level
of formality (that is, requiring technical managers to input only the product's
name, source, destination, and delivery date) would not be beneficial. This perception
changed dramatically when only 3 of the initial 1,200 products submitted to the CMIS
database had matching receiver and deliverer information. Moreover, technical
managers quickly recognized that CMIS allowed them to formalize their external delivery
commitments without limiting their ability to modify their internal schedules to best meet
their delivery commitments.
•The reconciliation process found holes in the plan where needed products were not
being supplied or were being supplied but not needed. The process also uncovered
many occurrences of product delivery dates that were much later than those needed by
receivers.
•CMIS provides metrics for tracking the level of reconciliation at the project. system. and
subsystem levels.
•
RecIDel metrics are reviewed weekly by the project manager and his staff. Lack of a
reconciled plan immediately draws management attention.
Recommendation
• For large research and development projects, effective cost and schedule control is
possible without incurring the large costs associated with centralized project control
systems.
• An effective cost/schedule management information system for all levels of
management can be built by focusing on satisfying the requirements of first-line
managers and lead engineers. Such an approach removes the inherent noise in
management reports
created by planning and control staffs.
•
An effective way to deal with schedule uncertainty is to simplify the project control
approach to focus on the areas where schedule uncertainty has the greatest impacts
(that is, the interfaces between receivers and deliverers).
Thank you
Ref :
Tuman, John, "It's Time to Re-engineer Project Management." PM Network, 7: 1 (January 1993),
pp. 40-4 1 .
Morad, Ayman A., and Michael C. Vorster, "Network-based Versus A 1-Based Techniques in
Project Planning." Project Management Journal, 24: 1 (March 1993), p. 25.
Mathews, Mark D., "Introducing Networks to an In-Progress Project." Project Management Journal,
24:2 (June 1993), p. 9. Archibald, Russell D., and Lichtenburg Steen, "Uncertainty and Change
Require a New Management Model." PAM NETwork, 7:5 (May 1994), pp. 6-10.
Wood, Lamont, "Project Management Perfect Harmony.“ nformation Week,No. 526 (May 8, 1995),
pp. 42-54.
Thank you
1.Please elaborate the different between
PERT project evaluation review technique VS
CPM critical path method ,CMIS contstruction
management information system ?
2.What are the benefit and disadvantages of
using PERT/CPM/CMIS ?

More Related Content

Similar to 6 An Innovative Distributed Project Control

A Synergistic Approach To Information Systems Project Management
A Synergistic Approach To Information Systems Project ManagementA Synergistic Approach To Information Systems Project Management
A Synergistic Approach To Information Systems Project ManagementJoe Osborn
 
London Ambulance Problems
London Ambulance ProblemsLondon Ambulance Problems
London Ambulance ProblemsKennyBHS
 
The sustainable management of remote construction projects
The sustainable management of remote construction projectsThe sustainable management of remote construction projects
The sustainable management of remote construction projectsBhzad Sidawi
 
Facility Location in Logistic Network Design Using Soft Computing Opimization...
Facility Location in Logistic Network Design Using Soft Computing Opimization...Facility Location in Logistic Network Design Using Soft Computing Opimization...
Facility Location in Logistic Network Design Using Soft Computing Opimization...AIRCC Publishing Corporation
 
FACILITY LOCATION IN LOGISTIC NETWORK DESIGN USING SOFT COMPUTING OPTIMIZATIO...
FACILITY LOCATION IN LOGISTIC NETWORK DESIGN USING SOFT COMPUTING OPTIMIZATIO...FACILITY LOCATION IN LOGISTIC NETWORK DESIGN USING SOFT COMPUTING OPTIMIZATIO...
FACILITY LOCATION IN LOGISTIC NETWORK DESIGN USING SOFT COMPUTING OPTIMIZATIO...ijcsit
 
I0313048051
I0313048051I0313048051
I0313048051theijes
 
TOOLS OF EDUCATIONAL MANAGEMENT-8615
TOOLS OF EDUCATIONAL MANAGEMENT-8615TOOLS OF EDUCATIONAL MANAGEMENT-8615
TOOLS OF EDUCATIONAL MANAGEMENT-8615EqraBaig
 
OR PERT CPM AND JOB SCHEDULING
OR PERT CPM AND JOB SCHEDULINGOR PERT CPM AND JOB SCHEDULING
OR PERT CPM AND JOB SCHEDULINGJignesh Kariya
 
Scheduling coordination and control of projects
Scheduling coordination and control of projects Scheduling coordination and control of projects
Scheduling coordination and control of projects Somashekar S.M
 
STUDY AND IMPLEMENTATION OF LAST PLANNER SYSTEM (LPS) IN CONSTRUCTION PROJECTS
STUDY AND IMPLEMENTATION OF LAST PLANNER SYSTEM (LPS) IN CONSTRUCTION PROJECTSSTUDY AND IMPLEMENTATION OF LAST PLANNER SYSTEM (LPS) IN CONSTRUCTION PROJECTS
STUDY AND IMPLEMENTATION OF LAST PLANNER SYSTEM (LPS) IN CONSTRUCTION PROJECTSIRJET Journal
 
Planning And Scheduling Construction For Decades
Planning And Scheduling Construction For DecadesPlanning And Scheduling Construction For Decades
Planning And Scheduling Construction For DecadesBeth Hall
 
London Ambulance Services (LAS) In a state of Emergency
London Ambulance Services (LAS) In a state of EmergencyLondon Ambulance Services (LAS) In a state of Emergency
London Ambulance Services (LAS) In a state of EmergencyMonzer Osama Alchikh WARAK
 
Construction project management
Construction project managementConstruction project management
Construction project managementsaif hasan
 
OPTIMIZED RESOURCE PROVISIONING METHOD FOR COMPUTATIONAL GRID
OPTIMIZED RESOURCE PROVISIONING METHOD FOR COMPUTATIONAL GRID OPTIMIZED RESOURCE PROVISIONING METHOD FOR COMPUTATIONAL GRID
OPTIMIZED RESOURCE PROVISIONING METHOD FOR COMPUTATIONAL GRID ijgca
 
Optimized Resource Provisioning Method for Computational Grid
Optimized Resource Provisioning Method for Computational GridOptimized Resource Provisioning Method for Computational Grid
Optimized Resource Provisioning Method for Computational Gridijgca
 
A Case Study On Applying Lean Construction To Concrete
A Case Study On Applying Lean Construction To ConcreteA Case Study On Applying Lean Construction To Concrete
A Case Study On Applying Lean Construction To ConcreteDawn Cook
 
3.Tools and Techniques of Project Management.pdf
3.Tools and Techniques of Project Management.pdf3.Tools and Techniques of Project Management.pdf
3.Tools and Techniques of Project Management.pdfShoDp
 
Project management
Project managementProject management
Project managementtwilight89
 
Chapter 5-Project Management.pptx
Chapter 5-Project Management.pptxChapter 5-Project Management.pptx
Chapter 5-Project Management.pptxBahredinAbdella1
 
Modul 06 penentuan durasi kegiatan
Modul 06 penentuan durasi kegiatanModul 06 penentuan durasi kegiatan
Modul 06 penentuan durasi kegiatanmelchioreq
 

Similar to 6 An Innovative Distributed Project Control (20)

A Synergistic Approach To Information Systems Project Management
A Synergistic Approach To Information Systems Project ManagementA Synergistic Approach To Information Systems Project Management
A Synergistic Approach To Information Systems Project Management
 
London Ambulance Problems
London Ambulance ProblemsLondon Ambulance Problems
London Ambulance Problems
 
The sustainable management of remote construction projects
The sustainable management of remote construction projectsThe sustainable management of remote construction projects
The sustainable management of remote construction projects
 
Facility Location in Logistic Network Design Using Soft Computing Opimization...
Facility Location in Logistic Network Design Using Soft Computing Opimization...Facility Location in Logistic Network Design Using Soft Computing Opimization...
Facility Location in Logistic Network Design Using Soft Computing Opimization...
 
FACILITY LOCATION IN LOGISTIC NETWORK DESIGN USING SOFT COMPUTING OPTIMIZATIO...
FACILITY LOCATION IN LOGISTIC NETWORK DESIGN USING SOFT COMPUTING OPTIMIZATIO...FACILITY LOCATION IN LOGISTIC NETWORK DESIGN USING SOFT COMPUTING OPTIMIZATIO...
FACILITY LOCATION IN LOGISTIC NETWORK DESIGN USING SOFT COMPUTING OPTIMIZATIO...
 
I0313048051
I0313048051I0313048051
I0313048051
 
TOOLS OF EDUCATIONAL MANAGEMENT-8615
TOOLS OF EDUCATIONAL MANAGEMENT-8615TOOLS OF EDUCATIONAL MANAGEMENT-8615
TOOLS OF EDUCATIONAL MANAGEMENT-8615
 
OR PERT CPM AND JOB SCHEDULING
OR PERT CPM AND JOB SCHEDULINGOR PERT CPM AND JOB SCHEDULING
OR PERT CPM AND JOB SCHEDULING
 
Scheduling coordination and control of projects
Scheduling coordination and control of projects Scheduling coordination and control of projects
Scheduling coordination and control of projects
 
STUDY AND IMPLEMENTATION OF LAST PLANNER SYSTEM (LPS) IN CONSTRUCTION PROJECTS
STUDY AND IMPLEMENTATION OF LAST PLANNER SYSTEM (LPS) IN CONSTRUCTION PROJECTSSTUDY AND IMPLEMENTATION OF LAST PLANNER SYSTEM (LPS) IN CONSTRUCTION PROJECTS
STUDY AND IMPLEMENTATION OF LAST PLANNER SYSTEM (LPS) IN CONSTRUCTION PROJECTS
 
Planning And Scheduling Construction For Decades
Planning And Scheduling Construction For DecadesPlanning And Scheduling Construction For Decades
Planning And Scheduling Construction For Decades
 
London Ambulance Services (LAS) In a state of Emergency
London Ambulance Services (LAS) In a state of EmergencyLondon Ambulance Services (LAS) In a state of Emergency
London Ambulance Services (LAS) In a state of Emergency
 
Construction project management
Construction project managementConstruction project management
Construction project management
 
OPTIMIZED RESOURCE PROVISIONING METHOD FOR COMPUTATIONAL GRID
OPTIMIZED RESOURCE PROVISIONING METHOD FOR COMPUTATIONAL GRID OPTIMIZED RESOURCE PROVISIONING METHOD FOR COMPUTATIONAL GRID
OPTIMIZED RESOURCE PROVISIONING METHOD FOR COMPUTATIONAL GRID
 
Optimized Resource Provisioning Method for Computational Grid
Optimized Resource Provisioning Method for Computational GridOptimized Resource Provisioning Method for Computational Grid
Optimized Resource Provisioning Method for Computational Grid
 
A Case Study On Applying Lean Construction To Concrete
A Case Study On Applying Lean Construction To ConcreteA Case Study On Applying Lean Construction To Concrete
A Case Study On Applying Lean Construction To Concrete
 
3.Tools and Techniques of Project Management.pdf
3.Tools and Techniques of Project Management.pdf3.Tools and Techniques of Project Management.pdf
3.Tools and Techniques of Project Management.pdf
 
Project management
Project managementProject management
Project management
 
Chapter 5-Project Management.pptx
Chapter 5-Project Management.pptxChapter 5-Project Management.pptx
Chapter 5-Project Management.pptx
 
Modul 06 penentuan durasi kegiatan
Modul 06 penentuan durasi kegiatanModul 06 penentuan durasi kegiatan
Modul 06 penentuan durasi kegiatan
 

More from pmb25

4 Super Lightweight Tank - Risk Management
4 Super Lightweight Tank - Risk Management4 Super Lightweight Tank - Risk Management
4 Super Lightweight Tank - Risk Managementpmb25
 
5 Application of Project Scheduling System for Construction Supply Chain Mana...
5 Application of Project Scheduling System for Construction Supply Chain Mana...5 Application of Project Scheduling System for Construction Supply Chain Mana...
5 Application of Project Scheduling System for Construction Supply Chain Mana...pmb25
 
7 Ave Maria Nursing Home Audit
7 Ave Maria Nursing Home Audit7 Ave Maria Nursing Home Audit
7 Ave Maria Nursing Home Auditpmb25
 
6 monitoring and evaluation
6 monitoring and evaluation6 monitoring and evaluation
6 monitoring and evaluationpmb25
 
7 the identity project : Audit Case
7 the identity project : Audit Case7 the identity project : Audit Case
7 the identity project : Audit Casepmb25
 
5 project scheduling in agriculture of stabilization 300 hectares grape gard...
5 project scheduling in agriculture of stabilization 300  hectares grape gard...5 project scheduling in agriculture of stabilization 300  hectares grape gard...
5 project scheduling in agriculture of stabilization 300 hectares grape gard...pmb25
 
4 risk analysis in oil and gas projects
4 risk analysis in oil and gas projects4 risk analysis in oil and gas projects
4 risk analysis in oil and gas projectspmb25
 
3 Dart Risk Management Case Study
3 Dart Risk Management Case Study 3 Dart Risk Management Case Study
3 Dart Risk Management Case Study pmb25
 
6 A Guide to Project Management Auditing Assessment and Recommendation
6 A Guide to Project Management Auditing Assessment and Recommendation6 A Guide to Project Management Auditing Assessment and Recommendation
6 A Guide to Project Management Auditing Assessment and Recommendationpmb25
 
5 Design and Monitoring of Shellfish Restoration Projects
5 Design and Monitoring of Shellfish Restoration Projects5 Design and Monitoring of Shellfish Restoration Projects
5 Design and Monitoring of Shellfish Restoration Projectspmb25
 
4 an activity analysis of project scheduling problem a case study 1
4 an activity analysis of project scheduling problem   a case study 14 an activity analysis of project scheduling problem   a case study 1
4 an activity analysis of project scheduling problem a case study 1pmb25
 
Project Management Effectiveness in organizational Conditions
Project Management Effectiveness in organizational ConditionsProject Management Effectiveness in organizational Conditions
Project Management Effectiveness in organizational Conditionspmb25
 
Organizational Structure and Cross Cultural Management
Organizational Structure and Cross Cultural ManagementOrganizational Structure and Cross Cultural Management
Organizational Structure and Cross Cultural Managementpmb25
 
Advancing Project Management in Learning Organization
Advancing Project Management in Learning Organization Advancing Project Management in Learning Organization
Advancing Project Management in Learning Organization pmb25
 
Restoring legitimacy in order to remain sustainable
Restoring legitimacy in order to remain sustainableRestoring legitimacy in order to remain sustainable
Restoring legitimacy in order to remain sustainablepmb25
 
Dealing with conflict in project management
Dealing with conflict in project managementDealing with conflict in project management
Dealing with conflict in project managementpmb25
 

More from pmb25 (16)

4 Super Lightweight Tank - Risk Management
4 Super Lightweight Tank - Risk Management4 Super Lightweight Tank - Risk Management
4 Super Lightweight Tank - Risk Management
 
5 Application of Project Scheduling System for Construction Supply Chain Mana...
5 Application of Project Scheduling System for Construction Supply Chain Mana...5 Application of Project Scheduling System for Construction Supply Chain Mana...
5 Application of Project Scheduling System for Construction Supply Chain Mana...
 
7 Ave Maria Nursing Home Audit
7 Ave Maria Nursing Home Audit7 Ave Maria Nursing Home Audit
7 Ave Maria Nursing Home Audit
 
6 monitoring and evaluation
6 monitoring and evaluation6 monitoring and evaluation
6 monitoring and evaluation
 
7 the identity project : Audit Case
7 the identity project : Audit Case7 the identity project : Audit Case
7 the identity project : Audit Case
 
5 project scheduling in agriculture of stabilization 300 hectares grape gard...
5 project scheduling in agriculture of stabilization 300  hectares grape gard...5 project scheduling in agriculture of stabilization 300  hectares grape gard...
5 project scheduling in agriculture of stabilization 300 hectares grape gard...
 
4 risk analysis in oil and gas projects
4 risk analysis in oil and gas projects4 risk analysis in oil and gas projects
4 risk analysis in oil and gas projects
 
3 Dart Risk Management Case Study
3 Dart Risk Management Case Study 3 Dart Risk Management Case Study
3 Dart Risk Management Case Study
 
6 A Guide to Project Management Auditing Assessment and Recommendation
6 A Guide to Project Management Auditing Assessment and Recommendation6 A Guide to Project Management Auditing Assessment and Recommendation
6 A Guide to Project Management Auditing Assessment and Recommendation
 
5 Design and Monitoring of Shellfish Restoration Projects
5 Design and Monitoring of Shellfish Restoration Projects5 Design and Monitoring of Shellfish Restoration Projects
5 Design and Monitoring of Shellfish Restoration Projects
 
4 an activity analysis of project scheduling problem a case study 1
4 an activity analysis of project scheduling problem   a case study 14 an activity analysis of project scheduling problem   a case study 1
4 an activity analysis of project scheduling problem a case study 1
 
Project Management Effectiveness in organizational Conditions
Project Management Effectiveness in organizational ConditionsProject Management Effectiveness in organizational Conditions
Project Management Effectiveness in organizational Conditions
 
Organizational Structure and Cross Cultural Management
Organizational Structure and Cross Cultural ManagementOrganizational Structure and Cross Cultural Management
Organizational Structure and Cross Cultural Management
 
Advancing Project Management in Learning Organization
Advancing Project Management in Learning Organization Advancing Project Management in Learning Organization
Advancing Project Management in Learning Organization
 
Restoring legitimacy in order to remain sustainable
Restoring legitimacy in order to remain sustainableRestoring legitimacy in order to remain sustainable
Restoring legitimacy in order to remain sustainable
 
Dealing with conflict in project management
Dealing with conflict in project managementDealing with conflict in project management
Dealing with conflict in project management
 

Recently uploaded

Measures of Central Tendency: Mean, Median and Mode
Measures of Central Tendency: Mean, Median and ModeMeasures of Central Tendency: Mean, Median and Mode
Measures of Central Tendency: Mean, Median and ModeThiyagu K
 
Accessible design: Minimum effort, maximum impact
Accessible design: Minimum effort, maximum impactAccessible design: Minimum effort, maximum impact
Accessible design: Minimum effort, maximum impactdawncurless
 
Introduction to AI in Higher Education_draft.pptx
Introduction to AI in Higher Education_draft.pptxIntroduction to AI in Higher Education_draft.pptx
Introduction to AI in Higher Education_draft.pptxpboyjonauth
 
Introduction to ArtificiaI Intelligence in Higher Education
Introduction to ArtificiaI Intelligence in Higher EducationIntroduction to ArtificiaI Intelligence in Higher Education
Introduction to ArtificiaI Intelligence in Higher Educationpboyjonauth
 
microwave assisted reaction. General introduction
microwave assisted reaction. General introductionmicrowave assisted reaction. General introduction
microwave assisted reaction. General introductionMaksud Ahmed
 
Grant Readiness 101 TechSoup and Remy Consulting
Grant Readiness 101 TechSoup and Remy ConsultingGrant Readiness 101 TechSoup and Remy Consulting
Grant Readiness 101 TechSoup and Remy ConsultingTechSoup
 
Organic Name Reactions for the students and aspirants of Chemistry12th.pptx
Organic Name Reactions  for the students and aspirants of Chemistry12th.pptxOrganic Name Reactions  for the students and aspirants of Chemistry12th.pptx
Organic Name Reactions for the students and aspirants of Chemistry12th.pptxVS Mahajan Coaching Centre
 
The Most Excellent Way | 1 Corinthians 13
The Most Excellent Way | 1 Corinthians 13The Most Excellent Way | 1 Corinthians 13
The Most Excellent Way | 1 Corinthians 13Steve Thomason
 
Call Girls in Dwarka Mor Delhi Contact Us 9654467111
Call Girls in Dwarka Mor Delhi Contact Us 9654467111Call Girls in Dwarka Mor Delhi Contact Us 9654467111
Call Girls in Dwarka Mor Delhi Contact Us 9654467111Sapana Sha
 
Paris 2024 Olympic Geographies - an activity
Paris 2024 Olympic Geographies - an activityParis 2024 Olympic Geographies - an activity
Paris 2024 Olympic Geographies - an activityGeoBlogs
 
Mastering the Unannounced Regulatory Inspection
Mastering the Unannounced Regulatory InspectionMastering the Unannounced Regulatory Inspection
Mastering the Unannounced Regulatory InspectionSafetyChain Software
 
Alper Gobel In Media Res Media Component
Alper Gobel In Media Res Media ComponentAlper Gobel In Media Res Media Component
Alper Gobel In Media Res Media ComponentInMediaRes1
 
Incoming and Outgoing Shipments in 1 STEP Using Odoo 17
Incoming and Outgoing Shipments in 1 STEP Using Odoo 17Incoming and Outgoing Shipments in 1 STEP Using Odoo 17
Incoming and Outgoing Shipments in 1 STEP Using Odoo 17Celine George
 
Sanyam Choudhary Chemistry practical.pdf
Sanyam Choudhary Chemistry practical.pdfSanyam Choudhary Chemistry practical.pdf
Sanyam Choudhary Chemistry practical.pdfsanyamsingh5019
 
Software Engineering Methodologies (overview)
Software Engineering Methodologies (overview)Software Engineering Methodologies (overview)
Software Engineering Methodologies (overview)eniolaolutunde
 
Contemporary philippine arts from the regions_PPT_Module_12 [Autosaved] (1).pptx
Contemporary philippine arts from the regions_PPT_Module_12 [Autosaved] (1).pptxContemporary philippine arts from the regions_PPT_Module_12 [Autosaved] (1).pptx
Contemporary philippine arts from the regions_PPT_Module_12 [Autosaved] (1).pptxRoyAbrique
 
Employee wellbeing at the workplace.pptx
Employee wellbeing at the workplace.pptxEmployee wellbeing at the workplace.pptx
Employee wellbeing at the workplace.pptxNirmalaLoungPoorunde1
 

Recently uploaded (20)

Measures of Central Tendency: Mean, Median and Mode
Measures of Central Tendency: Mean, Median and ModeMeasures of Central Tendency: Mean, Median and Mode
Measures of Central Tendency: Mean, Median and Mode
 
TataKelola dan KamSiber Kecerdasan Buatan v022.pdf
TataKelola dan KamSiber Kecerdasan Buatan v022.pdfTataKelola dan KamSiber Kecerdasan Buatan v022.pdf
TataKelola dan KamSiber Kecerdasan Buatan v022.pdf
 
Accessible design: Minimum effort, maximum impact
Accessible design: Minimum effort, maximum impactAccessible design: Minimum effort, maximum impact
Accessible design: Minimum effort, maximum impact
 
Introduction to AI in Higher Education_draft.pptx
Introduction to AI in Higher Education_draft.pptxIntroduction to AI in Higher Education_draft.pptx
Introduction to AI in Higher Education_draft.pptx
 
Introduction to ArtificiaI Intelligence in Higher Education
Introduction to ArtificiaI Intelligence in Higher EducationIntroduction to ArtificiaI Intelligence in Higher Education
Introduction to ArtificiaI Intelligence in Higher Education
 
microwave assisted reaction. General introduction
microwave assisted reaction. General introductionmicrowave assisted reaction. General introduction
microwave assisted reaction. General introduction
 
Grant Readiness 101 TechSoup and Remy Consulting
Grant Readiness 101 TechSoup and Remy ConsultingGrant Readiness 101 TechSoup and Remy Consulting
Grant Readiness 101 TechSoup and Remy Consulting
 
Organic Name Reactions for the students and aspirants of Chemistry12th.pptx
Organic Name Reactions  for the students and aspirants of Chemistry12th.pptxOrganic Name Reactions  for the students and aspirants of Chemistry12th.pptx
Organic Name Reactions for the students and aspirants of Chemistry12th.pptx
 
Model Call Girl in Tilak Nagar Delhi reach out to us at 🔝9953056974🔝
Model Call Girl in Tilak Nagar Delhi reach out to us at 🔝9953056974🔝Model Call Girl in Tilak Nagar Delhi reach out to us at 🔝9953056974🔝
Model Call Girl in Tilak Nagar Delhi reach out to us at 🔝9953056974🔝
 
The Most Excellent Way | 1 Corinthians 13
The Most Excellent Way | 1 Corinthians 13The Most Excellent Way | 1 Corinthians 13
The Most Excellent Way | 1 Corinthians 13
 
Call Girls in Dwarka Mor Delhi Contact Us 9654467111
Call Girls in Dwarka Mor Delhi Contact Us 9654467111Call Girls in Dwarka Mor Delhi Contact Us 9654467111
Call Girls in Dwarka Mor Delhi Contact Us 9654467111
 
Código Creativo y Arte de Software | Unidad 1
Código Creativo y Arte de Software | Unidad 1Código Creativo y Arte de Software | Unidad 1
Código Creativo y Arte de Software | Unidad 1
 
Paris 2024 Olympic Geographies - an activity
Paris 2024 Olympic Geographies - an activityParis 2024 Olympic Geographies - an activity
Paris 2024 Olympic Geographies - an activity
 
Mastering the Unannounced Regulatory Inspection
Mastering the Unannounced Regulatory InspectionMastering the Unannounced Regulatory Inspection
Mastering the Unannounced Regulatory Inspection
 
Alper Gobel In Media Res Media Component
Alper Gobel In Media Res Media ComponentAlper Gobel In Media Res Media Component
Alper Gobel In Media Res Media Component
 
Incoming and Outgoing Shipments in 1 STEP Using Odoo 17
Incoming and Outgoing Shipments in 1 STEP Using Odoo 17Incoming and Outgoing Shipments in 1 STEP Using Odoo 17
Incoming and Outgoing Shipments in 1 STEP Using Odoo 17
 
Sanyam Choudhary Chemistry practical.pdf
Sanyam Choudhary Chemistry practical.pdfSanyam Choudhary Chemistry practical.pdf
Sanyam Choudhary Chemistry practical.pdf
 
Software Engineering Methodologies (overview)
Software Engineering Methodologies (overview)Software Engineering Methodologies (overview)
Software Engineering Methodologies (overview)
 
Contemporary philippine arts from the regions_PPT_Module_12 [Autosaved] (1).pptx
Contemporary philippine arts from the regions_PPT_Module_12 [Autosaved] (1).pptxContemporary philippine arts from the regions_PPT_Module_12 [Autosaved] (1).pptx
Contemporary philippine arts from the regions_PPT_Module_12 [Autosaved] (1).pptx
 
Employee wellbeing at the workplace.pptx
Employee wellbeing at the workplace.pptxEmployee wellbeing at the workplace.pptx
Employee wellbeing at the workplace.pptx
 

6 An Innovative Distributed Project Control

  • 1. -Super Lightweight Tank- A Risk Management Case Study in Mass Reduction AN INOVATIVE DISTRIBUTED PROJECT CONTROL APPROACH : A CASE STUDY OF THE CASSINI MIS Presented by Yulhendri Saputra & Marcel Bernadi
  • 2.  Introduction  Problem Issues  Environmental Scanning  Alternatives Course of Actions  Key Success Factors  Selection of Best Alternatives  Recommendation
  • 3. INTRODUCTION  Originally. Congress approved funding for a joint program composed of a Comet Rendezvous/Asteroid Flyby (CRAF) mission and the Cassini mission.  The program was authorized with the stipulation that it would be canceled if original cost estimates were exceeded.  In response, Jet Propulsion Laboratory (JPL) chose to implement a classical earned-value system for controlling schedule and cost.  In 1990, after purchasing a full-featured commercialoff-the-shelf (COTS) project management system, the project hired 20 schedulers and planners to implement a full) integrated network schedule.  The system was based on classic program evaluation and review technique (PERT) concepts (developed in 1958) and the Cost/Schedule Control System Criteria (C/SCSC) formalized by the U.S. Department of Defense in 1967.  A large expenditure was made for training at all project levels. By late 199 1 , CRAF/Cassini project managers observed somt: trends with the entire project control process: This refereed c a s e study article w a s accepted January 1996.
  • 4. ENVIRONMENTAL SCANNING  The COTS project management system process countered JPL's effort to having decision making shifted to lower levels in the organization.  Considering the large expenditure for project control, no corresponding improvement was made with regard to communication between the different project elements.  The COTS project management system was not viewed as an easy-to-use tool.  The COTS project management system did not provide a straightforward method for addressing uncertainty.
  • 5. PROBLEM ISSUES "Network-based techniques as planning tools do not consider the issue of uncertainty in identifying tasks and the relationship among tasks in the network" (Morad and Vorster, 1993).   "A network models only one set of schedule options at any given time" (Mathews, 1993). "The current approach to planning and controlling complex projects has traditionally been to eliminate mcertainty and change from our projects, or at ieast treat them as if change will not occur7' (Archibald and Lichtenburg, 1994). "Older packages emphasize the critical path method, which can be very clumsy when scheduling people. Classic approaches tend to be expensive and roo!ed in legacy technologies" (Wood, 1995). In short, the project found that the cleanliness of theory (PERT, CISCSC) was no match for the clutter of reality.
  • 6. ALTERNATIVE COURSE OF ACTION 1. CPM and PERT Network-based techniques as planning tools do not consider the issue of uncertainty in identifying tasks and the relationship among tasks in the network"   Eliminate uncertainty and change from our projects, or treat them as if no change Older packages emphasize the critical path method, which can be very clumsy. In short, the project found that the cleanliness of theory was no match for the clutter of reality. 2. CMlS • All project products have to be someone's deliverable (Del) and another's receivable • Once a deliverer and receiver reach an agreement on the need t • Each Reciving and Delivery agreement • Any person on the project is able to determine a Rec/Dells status at any given time
  • 7. KEY SUCCES FACTOR The value of this approach became immediately apparent: I. The CMIS schedule control module facilitated and increased communication. It also highlighted where communication between project elements was deficient. Product specification and delivery schedule disputes were easily identified, problems were quickly addressed. and schedule confusion vanished. 2. Schedule tracking and statusing became virtually effortless. The project implemented an automated statusing system that polled receivers on a weekly basis about whether they had received their agreed-to deliveries for that week. Receiver responses to the messages were automatically compiled and summarized in weekly metric reports to management. In addition, on-line statusing within CMIS was provided. 3. The single-database design allowed current project-level schedule reports to be generated at any time. 4. CMIS reduced centralized project control costs to less than 0.25% of the total project budget. The workforce of planners/schedulers dropped from 20 people to an operations staff of 3 . This yielded a savings of greater than 60 work- years over the project's development phase.
  • 8. SELECTION OF BEST ALTERNATIVES CMIS Schedule Control Module Planning Reports and Metrics. •Before CMIS implementation, many seasoned managers expected that the simple level of formality (that is, requiring technical managers to input only the product's name, source, destination, and delivery date) would not be beneficial. This perception changed dramatically when only 3 of the initial 1,200 products submitted to the CMIS database had matching receiver and deliverer information. Moreover, technical managers quickly recognized that CMIS allowed them to formalize their external delivery commitments without limiting their ability to modify their internal schedules to best meet their delivery commitments. •The reconciliation process found holes in the plan where needed products were not being supplied or were being supplied but not needed. The process also uncovered many occurrences of product delivery dates that were much later than those needed by receivers. •CMIS provides metrics for tracking the level of reconciliation at the project. system. and subsystem levels. • RecIDel metrics are reviewed weekly by the project manager and his staff. Lack of a reconciled plan immediately draws management attention.
  • 9. Recommendation • For large research and development projects, effective cost and schedule control is possible without incurring the large costs associated with centralized project control systems. • An effective cost/schedule management information system for all levels of management can be built by focusing on satisfying the requirements of first-line managers and lead engineers. Such an approach removes the inherent noise in management reports created by planning and control staffs. • An effective way to deal with schedule uncertainty is to simplify the project control approach to focus on the areas where schedule uncertainty has the greatest impacts (that is, the interfaces between receivers and deliverers).
  • 10. Thank you Ref : Tuman, John, "It's Time to Re-engineer Project Management." PM Network, 7: 1 (January 1993), pp. 40-4 1 . Morad, Ayman A., and Michael C. Vorster, "Network-based Versus A 1-Based Techniques in Project Planning." Project Management Journal, 24: 1 (March 1993), p. 25. Mathews, Mark D., "Introducing Networks to an In-Progress Project." Project Management Journal, 24:2 (June 1993), p. 9. Archibald, Russell D., and Lichtenburg Steen, "Uncertainty and Change Require a New Management Model." PAM NETwork, 7:5 (May 1994), pp. 6-10. Wood, Lamont, "Project Management Perfect Harmony.“ nformation Week,No. 526 (May 8, 1995), pp. 42-54.
  • 11. Thank you 1.Please elaborate the different between PERT project evaluation review technique VS CPM critical path method ,CMIS contstruction management information system ? 2.What are the benefit and disadvantages of using PERT/CPM/CMIS ?