Construction Management
Players
• Owner – owns project upon completion of
construction
– Private – owner owns land and pays for
construction of facility
• Able to accept/reject bids based on many
parameters including cost, quality, reputation
– Public – owner is government agency, public
pays for facility
• Very strict method of soliciting bids, accepting bids,
writing specs
• Design Professionals
– Architects, Engineers, design professionals
• Assist owner in developing plan for facility
• Make sure it is structurally sound
• Make sure all systems, utilities, facilities are
integrated into design
• Responsible for applying for and obtaining all
necessary permits
• Contractor
• Contracts to build project to the specs set
forth in the contract for a contracted price
– Contract will subcontract to specialty firms
– Subcontractors may subcontract further
• Project Management
– Acts as owners agent and works with
designers and contractors to insure high
quality and lower cost
Construction Project
• Has following characteristics
– Defined goal or objective
– Specific tasks not routinely performed
– Defined beginning and end
– Defined deliverables
– Resources being consumed
• To build a project on time and at cost need
a good map to get thru project
– Steps
• Establish project plan/objectives
• Do research into materials and design
• Design, estimate and schedule
• Present design to owner
• Analyze project for viability
• Adjust project plans as needed and go back to
beginning
• As the project progresses more
information is known and needs to be
considered
• Good early decisions provide significant
benefits. Ability to influence the project
costs decreases as the project is built
Construction Project Categories
• Residential
• Condos, town houses, apartments, single family
homes
• Owners may be development companies or
individual owners
• Fairly low tech
• Building Construction Projects
• Office buildings, large apartment buildings,
shopping malls, theaters
• Dependent on economy
• Designed by architects with engineering support
Construction Project Categories
• Heavy Construction
• Roads, bridges, dams, tunnels, water & waste
water systems
• Designed by engineers
• Usually public projects
• Industrial Projects
• Steel mills, petroleum refineries, chemical
processing plants, auto production facilities
• Specialized design and construction
• Limited companies do this work
Chronology
• Conceptual Planning
– Owner makes decisions on designers, site,
and project cost and schedule
– Iterative process – add in and delete items to
get desired final product
– Need to gather as much info as possible
• Rehab work uncovers many unknowns
– Permits are started and applications made
– Estimate +/- 25%, Schedule +/- month
Chronology
• Schematic Design
– Actual design begins
– Looking at method and materials to use
– Value engineering
– Begin setting up work packages
– Id long lead time items
– Preliminary estimate (+/- 10%) and schedule
are completed
Chronology
• Design Development
– Final design phase
– Make system choices based on cost and
schedule
– Prequalification process for bidders
– Contract documents and determination of
work packages – Woodrow Wilson Bridge
– Fair cost estimate and schedule developed
Chronology
• Construction
– Mobilization
– Milestones
– Substantial completion
– Punchlist items
– Project Close out
Project Risk
• Bid depends on amount of risk contractor is willing
to take
• Risks
– Project Site – Neighbors, Regulatory environment,
Subsurface conditions, Economic climate
– Project – complexity, planned technologies, degree of
finishes, materials, mechanical/electrical systems
– Process – Project funding, timetable, preconstruction
info, project unknowns
– Owner Org – sophistication, org structure, decision
making
• Contingency takes some of risk out
Contract Types
• Fixed Price (Lump Sum)
• Do work for a set price
• Must have an accurate estimate for bid
• Provides owner and contractor with a number
• Risk to contractor is great, to owner minimal
• Unit Price
• Price is per unit of each item. Price includes all
O&P
• Designer estimates quantities
Contract Types
• Cost Plus Fee
• Owner reimburses actual costs plus a fee to cover
O&P
• Good when scope of project is unclear
– GMP
• Owner knows max price for financing
• Clause provides a split of money if contract comes
in under budget

More Related Content

Similar to Construction Management - L1 (1).ppt

Architectural Project Planning
Architectural Project PlanningArchitectural Project Planning
Architectural Project PlanningIndovance Inc
 
Mohamed Mostafa Kamal Mohamed Elsahn 2016
Mohamed Mostafa Kamal Mohamed Elsahn 2016Mohamed Mostafa Kamal Mohamed Elsahn 2016
Mohamed Mostafa Kamal Mohamed Elsahn 2016Mohamed Elsahen
 
Construction Documents
Construction DocumentsConstruction Documents
Construction DocumentsAllan Berry
 
Effective Engineering Management in EPC Industry
Effective Engineering Management in EPC IndustryEffective Engineering Management in EPC Industry
Effective Engineering Management in EPC IndustryPMI Chennai Chapter
 
Construction PROJECT MANAGEMENT
Construction PROJECT MANAGEMENTConstruction PROJECT MANAGEMENT
Construction PROJECT MANAGEMENTIrfan Ullah
 
Time & Schedule, Submittals, Site visits, Testing and Inspection
Time & Schedule, Submittals, Site visits, Testing and InspectionTime & Schedule, Submittals, Site visits, Testing and Inspection
Time & Schedule, Submittals, Site visits, Testing and InspectionGalala University
 
Curriculum vitae of civil engineer for construction manager or Sr. project en...
Curriculum vitae of civil engineer for construction manager or Sr. project en...Curriculum vitae of civil engineer for construction manager or Sr. project en...
Curriculum vitae of civil engineer for construction manager or Sr. project en...Amir Mohammed
 
Om lect 07 (r3-jul 11)_basics of project management_mms-bharti_sies
Om lect 07 (r3-jul 11)_basics of project management_mms-bharti_siesOm lect 07 (r3-jul 11)_basics of project management_mms-bharti_sies
Om lect 07 (r3-jul 11)_basics of project management_mms-bharti_siesvideoaakash15
 
Updated Architecture Portfolio 2020
Updated Architecture Portfolio 2020Updated Architecture Portfolio 2020
Updated Architecture Portfolio 2020MTAF
 
ZAKI Michael_CV 042014
ZAKI Michael_CV 042014ZAKI Michael_CV 042014
ZAKI Michael_CV 042014Michael Khalil
 
Len Bettencourt-Resume Oct 2016
Len Bettencourt-Resume Oct 2016Len Bettencourt-Resume Oct 2016
Len Bettencourt-Resume Oct 2016Len Bettencourt
 

Similar to Construction Management - L1 (1).ppt (20)

Architectural Project Planning
Architectural Project PlanningArchitectural Project Planning
Architectural Project Planning
 
Mohamed Mostafa Kamal Mohamed Elsahn 2016
Mohamed Mostafa Kamal Mohamed Elsahn 2016Mohamed Mostafa Kamal Mohamed Elsahn 2016
Mohamed Mostafa Kamal Mohamed Elsahn 2016
 
Final pp1
Final pp1Final pp1
Final pp1
 
Construction Documents
Construction DocumentsConstruction Documents
Construction Documents
 
Effective Engineering Management in EPC Industry
Effective Engineering Management in EPC IndustryEffective Engineering Management in EPC Industry
Effective Engineering Management in EPC Industry
 
Construction PROJECT MANAGEMENT
Construction PROJECT MANAGEMENTConstruction PROJECT MANAGEMENT
Construction PROJECT MANAGEMENT
 
SANPPT
SANPPTSANPPT
SANPPT
 
CV-Sounder
CV-SounderCV-Sounder
CV-Sounder
 
Time & Schedule, Submittals, Site visits, Testing and Inspection
Time & Schedule, Submittals, Site visits, Testing and InspectionTime & Schedule, Submittals, Site visits, Testing and Inspection
Time & Schedule, Submittals, Site visits, Testing and Inspection
 
Curriculum vitae of civil engineer for construction manager or Sr. project en...
Curriculum vitae of civil engineer for construction manager or Sr. project en...Curriculum vitae of civil engineer for construction manager or Sr. project en...
Curriculum vitae of civil engineer for construction manager or Sr. project en...
 
PEEM 1.pptx
PEEM 1.pptxPEEM 1.pptx
PEEM 1.pptx
 
CV
CVCV
CV
 
Introduction to pm
Introduction to pmIntroduction to pm
Introduction to pm
 
Ddg architecture
Ddg architectureDdg architecture
Ddg architecture
 
Om lect 07 (r3-jul 11)_basics of project management_mms-bharti_sies
Om lect 07 (r3-jul 11)_basics of project management_mms-bharti_siesOm lect 07 (r3-jul 11)_basics of project management_mms-bharti_sies
Om lect 07 (r3-jul 11)_basics of project management_mms-bharti_sies
 
Project Engineer
Project EngineerProject Engineer
Project Engineer
 
Updated Architecture Portfolio 2020
Updated Architecture Portfolio 2020Updated Architecture Portfolio 2020
Updated Architecture Portfolio 2020
 
ZAKI Michael_CV 042014
ZAKI Michael_CV 042014ZAKI Michael_CV 042014
ZAKI Michael_CV 042014
 
PEEM 2.pptx
PEEM 2.pptxPEEM 2.pptx
PEEM 2.pptx
 
Len Bettencourt-Resume Oct 2016
Len Bettencourt-Resume Oct 2016Len Bettencourt-Resume Oct 2016
Len Bettencourt-Resume Oct 2016
 

Recently uploaded

Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur High Profile
 
Booking open Available Pune Call Girls Koregaon Park 6297143586 Call Hot Ind...
Booking open Available Pune Call Girls Koregaon Park  6297143586 Call Hot Ind...Booking open Available Pune Call Girls Koregaon Park  6297143586 Call Hot Ind...
Booking open Available Pune Call Girls Koregaon Park 6297143586 Call Hot Ind...Call Girls in Nagpur High Profile
 
(TARA) Talegaon Dabhade Call Girls Just Call 7001035870 [ Cash on Delivery ] ...
(TARA) Talegaon Dabhade Call Girls Just Call 7001035870 [ Cash on Delivery ] ...(TARA) Talegaon Dabhade Call Girls Just Call 7001035870 [ Cash on Delivery ] ...
(TARA) Talegaon Dabhade Call Girls Just Call 7001035870 [ Cash on Delivery ] ...ranjana rawat
 
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINEMANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINESIVASHANKAR N
 
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...ranjana rawat
 
UNIT-III FMM. DIMENSIONAL ANALYSIS
UNIT-III FMM.        DIMENSIONAL ANALYSISUNIT-III FMM.        DIMENSIONAL ANALYSIS
UNIT-III FMM. DIMENSIONAL ANALYSISrknatarajan
 
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...Soham Mondal
 
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escortsranjana rawat
 
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICSAPPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICSKurinjimalarL3
 
IMPLICATIONS OF THE ABOVE HOLISTIC UNDERSTANDING OF HARMONY ON PROFESSIONAL E...
IMPLICATIONS OF THE ABOVE HOLISTIC UNDERSTANDING OF HARMONY ON PROFESSIONAL E...IMPLICATIONS OF THE ABOVE HOLISTIC UNDERSTANDING OF HARMONY ON PROFESSIONAL E...
IMPLICATIONS OF THE ABOVE HOLISTIC UNDERSTANDING OF HARMONY ON PROFESSIONAL E...RajaP95
 
College Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service NashikCollege Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service NashikCall Girls in Nagpur High Profile
 
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130Suhani Kapoor
 
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escortsranjana rawat
 
SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )Tsuyoshi Horigome
 
Software Development Life Cycle By Team Orange (Dept. of Pharmacy)
Software Development Life Cycle By  Team Orange (Dept. of Pharmacy)Software Development Life Cycle By  Team Orange (Dept. of Pharmacy)
Software Development Life Cycle By Team Orange (Dept. of Pharmacy)Suman Mia
 
Coefficient of Thermal Expansion and their Importance.pptx
Coefficient of Thermal Expansion and their Importance.pptxCoefficient of Thermal Expansion and their Importance.pptx
Coefficient of Thermal Expansion and their Importance.pptxAsutosh Ranjan
 
HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICS
HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICSHARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICS
HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICSRajkumarAkumalla
 
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...Dr.Costas Sachpazis
 

Recently uploaded (20)

Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
 
Booking open Available Pune Call Girls Koregaon Park 6297143586 Call Hot Ind...
Booking open Available Pune Call Girls Koregaon Park  6297143586 Call Hot Ind...Booking open Available Pune Call Girls Koregaon Park  6297143586 Call Hot Ind...
Booking open Available Pune Call Girls Koregaon Park 6297143586 Call Hot Ind...
 
(TARA) Talegaon Dabhade Call Girls Just Call 7001035870 [ Cash on Delivery ] ...
(TARA) Talegaon Dabhade Call Girls Just Call 7001035870 [ Cash on Delivery ] ...(TARA) Talegaon Dabhade Call Girls Just Call 7001035870 [ Cash on Delivery ] ...
(TARA) Talegaon Dabhade Call Girls Just Call 7001035870 [ Cash on Delivery ] ...
 
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINEMANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
 
Call Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCR
Call Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCRCall Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCR
Call Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCR
 
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
 
UNIT-III FMM. DIMENSIONAL ANALYSIS
UNIT-III FMM.        DIMENSIONAL ANALYSISUNIT-III FMM.        DIMENSIONAL ANALYSIS
UNIT-III FMM. DIMENSIONAL ANALYSIS
 
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
 
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
 
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICSAPPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
 
IMPLICATIONS OF THE ABOVE HOLISTIC UNDERSTANDING OF HARMONY ON PROFESSIONAL E...
IMPLICATIONS OF THE ABOVE HOLISTIC UNDERSTANDING OF HARMONY ON PROFESSIONAL E...IMPLICATIONS OF THE ABOVE HOLISTIC UNDERSTANDING OF HARMONY ON PROFESSIONAL E...
IMPLICATIONS OF THE ABOVE HOLISTIC UNDERSTANDING OF HARMONY ON PROFESSIONAL E...
 
College Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service NashikCollege Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
 
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
 
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
 
SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )
 
Software Development Life Cycle By Team Orange (Dept. of Pharmacy)
Software Development Life Cycle By  Team Orange (Dept. of Pharmacy)Software Development Life Cycle By  Team Orange (Dept. of Pharmacy)
Software Development Life Cycle By Team Orange (Dept. of Pharmacy)
 
Coefficient of Thermal Expansion and their Importance.pptx
Coefficient of Thermal Expansion and their Importance.pptxCoefficient of Thermal Expansion and their Importance.pptx
Coefficient of Thermal Expansion and their Importance.pptx
 
9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf
9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf
9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf
 
HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICS
HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICSHARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICS
HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICS
 
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
 

Construction Management - L1 (1).ppt

  • 2. Players • Owner – owns project upon completion of construction – Private – owner owns land and pays for construction of facility • Able to accept/reject bids based on many parameters including cost, quality, reputation – Public – owner is government agency, public pays for facility • Very strict method of soliciting bids, accepting bids, writing specs
  • 3. • Design Professionals – Architects, Engineers, design professionals • Assist owner in developing plan for facility • Make sure it is structurally sound • Make sure all systems, utilities, facilities are integrated into design • Responsible for applying for and obtaining all necessary permits
  • 4. • Contractor • Contracts to build project to the specs set forth in the contract for a contracted price – Contract will subcontract to specialty firms – Subcontractors may subcontract further • Project Management – Acts as owners agent and works with designers and contractors to insure high quality and lower cost
  • 5. Construction Project • Has following characteristics – Defined goal or objective – Specific tasks not routinely performed – Defined beginning and end – Defined deliverables – Resources being consumed
  • 6. • To build a project on time and at cost need a good map to get thru project – Steps • Establish project plan/objectives • Do research into materials and design • Design, estimate and schedule • Present design to owner • Analyze project for viability • Adjust project plans as needed and go back to beginning
  • 7. • As the project progresses more information is known and needs to be considered • Good early decisions provide significant benefits. Ability to influence the project costs decreases as the project is built
  • 8. Construction Project Categories • Residential • Condos, town houses, apartments, single family homes • Owners may be development companies or individual owners • Fairly low tech • Building Construction Projects • Office buildings, large apartment buildings, shopping malls, theaters • Dependent on economy • Designed by architects with engineering support
  • 9. Construction Project Categories • Heavy Construction • Roads, bridges, dams, tunnels, water & waste water systems • Designed by engineers • Usually public projects • Industrial Projects • Steel mills, petroleum refineries, chemical processing plants, auto production facilities • Specialized design and construction • Limited companies do this work
  • 10. Chronology • Conceptual Planning – Owner makes decisions on designers, site, and project cost and schedule – Iterative process – add in and delete items to get desired final product – Need to gather as much info as possible • Rehab work uncovers many unknowns – Permits are started and applications made – Estimate +/- 25%, Schedule +/- month
  • 11. Chronology • Schematic Design – Actual design begins – Looking at method and materials to use – Value engineering – Begin setting up work packages – Id long lead time items – Preliminary estimate (+/- 10%) and schedule are completed
  • 12. Chronology • Design Development – Final design phase – Make system choices based on cost and schedule – Prequalification process for bidders – Contract documents and determination of work packages – Woodrow Wilson Bridge – Fair cost estimate and schedule developed
  • 13. Chronology • Construction – Mobilization – Milestones – Substantial completion – Punchlist items – Project Close out
  • 14. Project Risk • Bid depends on amount of risk contractor is willing to take • Risks – Project Site – Neighbors, Regulatory environment, Subsurface conditions, Economic climate – Project – complexity, planned technologies, degree of finishes, materials, mechanical/electrical systems – Process – Project funding, timetable, preconstruction info, project unknowns – Owner Org – sophistication, org structure, decision making • Contingency takes some of risk out
  • 15. Contract Types • Fixed Price (Lump Sum) • Do work for a set price • Must have an accurate estimate for bid • Provides owner and contractor with a number • Risk to contractor is great, to owner minimal • Unit Price • Price is per unit of each item. Price includes all O&P • Designer estimates quantities
  • 16. Contract Types • Cost Plus Fee • Owner reimburses actual costs plus a fee to cover O&P • Good when scope of project is unclear – GMP • Owner knows max price for financing • Clause provides a split of money if contract comes in under budget