SlideShare a Scribd company logo
1 of 16
Construction Management
1
Players
• Owner – owns project upon completion of
construction
– Private – owner owns land and pays for
construction of facility
• Able to accept/reject bids based on many
parameters including cost, quality, reputation
– Public – owner is government agency, public
pays for facility
• Very strict method of soliciting bids, accepting bids,
writing specs
2
• Design Professionals
– Architects, Engineers, design professionals
• Assist owner in developing plan for facility
• Make sure it is structurally sound
• Make sure all systems, utilities, facilities are
integrated into design
• Responsible for applying for and obtaining all
necessary permits
3
• Contractor
• Contracts to build project to the specs set
forth in the contract for a contracted price
– Contract will subcontract to specialty firms
– Subcontractors may subcontract further
• Project Management
– Acts as owners agent and works with
designers and contractors to insure high
quality and lower cost
4
Construction Project
• Has following characteristics
– Defined goal or objective
– Specific tasks not routinely performed
– Defined beginning and end
– Defined deliverables
– Resources being consumed
5
• To build a project on time and at cost need
a good map to get thru project
– Steps
• Establish project plan/objectives
• Do research into materials and design
• Design, estimate and schedule
• Present design to owner
• Analyze project for viability
• Adjust project plans as needed and go back to
beginning
6
• As the project progresses more
information is known and needs to be
considered
• Good early decisions provide significant
benefits. Ability to influence the project
costs decreases as the project is built
7
Construction Project Categories
• Residential
• Condos, town houses, apartments, single family
homes
• Owners may be development companies or
individual owners
• Fairly low tech
• Building Construction Projects
• Office buildings, large apartment buildings,
shopping malls, theaters
• Dependent on economy
• Designed by architects with engineering support
8
Construction Project Categories
• Heavy Construction
• Roads, bridges, dams, tunnels, water & waste
water systems
• Designed by engineers
• Usually public projects
• Industrial Projects
• Steel mills, petroleum refineries, chemical
processing plants, auto production facilities
• Specialized design and construction
• Limited companies do this work
9
Chronology
• Conceptual Planning
– Owner makes decisions on designers, site,
and project cost and schedule
– Iterative process – add in and delete items to
get desired final product
– Need to gather as much info as possible
• Rehab work uncovers many unknowns
– Permits are started and applications made
– Estimate +/- 25%, Schedule +/- month
10
Chronology
• Schematic Design
– Actual design begins
– Looking at method and materials to use
– Value engineering
– Begin setting up work packages
– Id long lead time items
– Preliminary estimate (+/- 10%) and schedule
are completed
11
Chronology
• Design Development
– Final design phase
– Make system choices based on cost and
schedule
– Prequalification process for bidders
– Contract documents and determination of
work packages – Woodrow Wilson Bridge
– Fair cost estimate and schedule developed
12
Chronology
• Construction
– Mobilization
– Milestones
– Substantial completion
– Punchlist items
– Project Close out
13
Project Risk
• Bid depends on amount of risk contractor is willing
to take
• Risks
– Project Site – Neighbors, Regulatory environment,
Subsurface conditions, Economic climate
– Project – complexity, planned technologies, degree of
finishes, materials, mechanical/electrical systems
– Process – Project funding, timetable, preconstruction
info, project unknowns
– Owner Org – sophistication, org structure, decision
making
• Contingency takes some of risk out
14
Contract Types
• Fixed Price (Lump Sum)
• Do work for a set price
• Must have an accurate estimate for bid
• Provides owner and contractor with a number
• Risk to contractor is great, to owner minimal
• Unit Price
• Price is per unit of each item. Price includes all
O&P
• Designer estimates quantities
15
Contract Types
• Cost Plus Fee
• Owner reimburses actual costs plus a fee to cover
O&P
• Good when scope of project is unclear
– GMP
• Owner knows max price for financing
• Clause provides a split of money if contract comes
in under budget
16

More Related Content

Similar to Construction Management Lesson - L1.pptx

Construction PROJECT MANAGEMENT
Construction PROJECT MANAGEMENTConstruction PROJECT MANAGEMENT
Construction PROJECT MANAGEMENTIrfan Ullah
 
Mohamed Salah Ibrahim
Mohamed Salah IbrahimMohamed Salah Ibrahim
Mohamed Salah IbrahimMohamed Salah
 
Construction Documents
Construction DocumentsConstruction Documents
Construction DocumentsAllan Berry
 
ZAKI Michael_CV 042014
ZAKI Michael_CV 042014ZAKI Michael_CV 042014
ZAKI Michael_CV 042014Michael Khalil
 
Advanced CM_04.09.2022.pptx
Advanced CM_04.09.2022.pptxAdvanced CM_04.09.2022.pptx
Advanced CM_04.09.2022.pptxSiharaGallage
 
Mohamed Mostafa Kamal Mohamed Elsahn 2016
Mohamed Mostafa Kamal Mohamed Elsahn 2016Mohamed Mostafa Kamal Mohamed Elsahn 2016
Mohamed Mostafa Kamal Mohamed Elsahn 2016Mohamed Elsahen
 
Complexity - Advanced Engineering Project Management
Complexity - Advanced Engineering Project ManagementComplexity - Advanced Engineering Project Management
Complexity - Advanced Engineering Project ManagementMDCSystems
 
Curriculum vitae of civil engineer for construction manager or Sr. project en...
Curriculum vitae of civil engineer for construction manager or Sr. project en...Curriculum vitae of civil engineer for construction manager or Sr. project en...
Curriculum vitae of civil engineer for construction manager or Sr. project en...Amir Mohammed
 
Updated Architecture Portfolio 2020
Updated Architecture Portfolio 2020Updated Architecture Portfolio 2020
Updated Architecture Portfolio 2020MTAF
 
Flow of construction project , stakeholders , WBS (work breakdown structure)
Flow of construction project , stakeholders , WBS (work breakdown structure)Flow of construction project , stakeholders , WBS (work breakdown structure)
Flow of construction project , stakeholders , WBS (work breakdown structure)SHREYASKUMAR PATEL
 
Project management
Project managementProject management
Project managementBenjamin Tan
 
Architectural Project Planning
Architectural Project PlanningArchitectural Project Planning
Architectural Project PlanningIndovance Inc
 

Similar to Construction Management Lesson - L1.pptx (20)

Construction PROJECT MANAGEMENT
Construction PROJECT MANAGEMENTConstruction PROJECT MANAGEMENT
Construction PROJECT MANAGEMENT
 
Mohamed Salah Ibrahim
Mohamed Salah IbrahimMohamed Salah Ibrahim
Mohamed Salah Ibrahim
 
Construction Documents
Construction DocumentsConstruction Documents
Construction Documents
 
PEEM 4.pptx
PEEM 4.pptxPEEM 4.pptx
PEEM 4.pptx
 
ZAKI Michael_CV 042014
ZAKI Michael_CV 042014ZAKI Michael_CV 042014
ZAKI Michael_CV 042014
 
Advanced CM_04.09.2022.pptx
Advanced CM_04.09.2022.pptxAdvanced CM_04.09.2022.pptx
Advanced CM_04.09.2022.pptx
 
Mohamed Mostafa Kamal Mohamed Elsahn 2016
Mohamed Mostafa Kamal Mohamed Elsahn 2016Mohamed Mostafa Kamal Mohamed Elsahn 2016
Mohamed Mostafa Kamal Mohamed Elsahn 2016
 
Complexity - Advanced Engineering Project Management
Complexity - Advanced Engineering Project ManagementComplexity - Advanced Engineering Project Management
Complexity - Advanced Engineering Project Management
 
Project management
Project managementProject management
Project management
 
Contracting strategies for_terminal_construction
Contracting strategies for_terminal_constructionContracting strategies for_terminal_construction
Contracting strategies for_terminal_construction
 
Contracting strategies for_terminal_construction
Contracting strategies for_terminal_constructionContracting strategies for_terminal_construction
Contracting strategies for_terminal_construction
 
PEEM 2.pptx
PEEM 2.pptxPEEM 2.pptx
PEEM 2.pptx
 
Final pp1
Final pp1Final pp1
Final pp1
 
PEEM 1.pptx
PEEM 1.pptxPEEM 1.pptx
PEEM 1.pptx
 
Curriculum vitae of civil engineer for construction manager or Sr. project en...
Curriculum vitae of civil engineer for construction manager or Sr. project en...Curriculum vitae of civil engineer for construction manager or Sr. project en...
Curriculum vitae of civil engineer for construction manager or Sr. project en...
 
Project planning and control
Project planning and controlProject planning and control
Project planning and control
 
Updated Architecture Portfolio 2020
Updated Architecture Portfolio 2020Updated Architecture Portfolio 2020
Updated Architecture Portfolio 2020
 
Flow of construction project , stakeholders , WBS (work breakdown structure)
Flow of construction project , stakeholders , WBS (work breakdown structure)Flow of construction project , stakeholders , WBS (work breakdown structure)
Flow of construction project , stakeholders , WBS (work breakdown structure)
 
Project management
Project managementProject management
Project management
 
Architectural Project Planning
Architectural Project PlanningArchitectural Project Planning
Architectural Project Planning
 

Recently uploaded

Churning of Butter, Factors affecting .
Churning of Butter, Factors affecting  .Churning of Butter, Factors affecting  .
Churning of Butter, Factors affecting .Satyam Kumar
 
Biology for Computer Engineers Course Handout.pptx
Biology for Computer Engineers Course Handout.pptxBiology for Computer Engineers Course Handout.pptx
Biology for Computer Engineers Course Handout.pptxDeepakSakkari2
 
chaitra-1.pptx fake news detection using machine learning
chaitra-1.pptx  fake news detection using machine learningchaitra-1.pptx  fake news detection using machine learning
chaitra-1.pptx fake news detection using machine learningmisbanausheenparvam
 
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICSAPPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICSKurinjimalarL3
 
What are the advantages and disadvantages of membrane structures.pptx
What are the advantages and disadvantages of membrane structures.pptxWhat are the advantages and disadvantages of membrane structures.pptx
What are the advantages and disadvantages of membrane structures.pptxwendy cai
 
Sachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
Sachpazis Costas: Geotechnical Engineering: A student's Perspective IntroductionSachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
Sachpazis Costas: Geotechnical Engineering: A student's Perspective IntroductionDr.Costas Sachpazis
 
Software and Systems Engineering Standards: Verification and Validation of Sy...
Software and Systems Engineering Standards: Verification and Validation of Sy...Software and Systems Engineering Standards: Verification and Validation of Sy...
Software and Systems Engineering Standards: Verification and Validation of Sy...VICTOR MAESTRE RAMIREZ
 
Call Us ≽ 8377877756 ≼ Call Girls In Shastri Nagar (Delhi)
Call Us ≽ 8377877756 ≼ Call Girls In Shastri Nagar (Delhi)Call Us ≽ 8377877756 ≼ Call Girls In Shastri Nagar (Delhi)
Call Us ≽ 8377877756 ≼ Call Girls In Shastri Nagar (Delhi)dollysharma2066
 
Introduction to Microprocesso programming and interfacing.pptx
Introduction to Microprocesso programming and interfacing.pptxIntroduction to Microprocesso programming and interfacing.pptx
Introduction to Microprocesso programming and interfacing.pptxvipinkmenon1
 
Introduction-To-Agricultural-Surveillance-Rover.pptx
Introduction-To-Agricultural-Surveillance-Rover.pptxIntroduction-To-Agricultural-Surveillance-Rover.pptx
Introduction-To-Agricultural-Surveillance-Rover.pptxk795866
 
CCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdf
CCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdfCCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdf
CCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdfAsst.prof M.Gokilavani
 
VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...
VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...
VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...VICTOR MAESTRE RAMIREZ
 
power system scada applications and uses
power system scada applications and usespower system scada applications and uses
power system scada applications and usesDevarapalliHaritha
 
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort service
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort serviceGurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort service
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort servicejennyeacort
 
IVE Industry Focused Event - Defence Sector 2024
IVE Industry Focused Event - Defence Sector 2024IVE Industry Focused Event - Defence Sector 2024
IVE Industry Focused Event - Defence Sector 2024Mark Billinghurst
 
Artificial-Intelligence-in-Electronics (K).pptx
Artificial-Intelligence-in-Electronics (K).pptxArtificial-Intelligence-in-Electronics (K).pptx
Artificial-Intelligence-in-Electronics (K).pptxbritheesh05
 
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...Soham Mondal
 
Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024hassan khalil
 

Recently uploaded (20)

Churning of Butter, Factors affecting .
Churning of Butter, Factors affecting  .Churning of Butter, Factors affecting  .
Churning of Butter, Factors affecting .
 
Biology for Computer Engineers Course Handout.pptx
Biology for Computer Engineers Course Handout.pptxBiology for Computer Engineers Course Handout.pptx
Biology for Computer Engineers Course Handout.pptx
 
chaitra-1.pptx fake news detection using machine learning
chaitra-1.pptx  fake news detection using machine learningchaitra-1.pptx  fake news detection using machine learning
chaitra-1.pptx fake news detection using machine learning
 
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICSAPPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
 
What are the advantages and disadvantages of membrane structures.pptx
What are the advantages and disadvantages of membrane structures.pptxWhat are the advantages and disadvantages of membrane structures.pptx
What are the advantages and disadvantages of membrane structures.pptx
 
Sachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
Sachpazis Costas: Geotechnical Engineering: A student's Perspective IntroductionSachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
Sachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
 
Software and Systems Engineering Standards: Verification and Validation of Sy...
Software and Systems Engineering Standards: Verification and Validation of Sy...Software and Systems Engineering Standards: Verification and Validation of Sy...
Software and Systems Engineering Standards: Verification and Validation of Sy...
 
Call Us ≽ 8377877756 ≼ Call Girls In Shastri Nagar (Delhi)
Call Us ≽ 8377877756 ≼ Call Girls In Shastri Nagar (Delhi)Call Us ≽ 8377877756 ≼ Call Girls In Shastri Nagar (Delhi)
Call Us ≽ 8377877756 ≼ Call Girls In Shastri Nagar (Delhi)
 
Introduction to Microprocesso programming and interfacing.pptx
Introduction to Microprocesso programming and interfacing.pptxIntroduction to Microprocesso programming and interfacing.pptx
Introduction to Microprocesso programming and interfacing.pptx
 
Introduction-To-Agricultural-Surveillance-Rover.pptx
Introduction-To-Agricultural-Surveillance-Rover.pptxIntroduction-To-Agricultural-Surveillance-Rover.pptx
Introduction-To-Agricultural-Surveillance-Rover.pptx
 
CCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdf
CCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdfCCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdf
CCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdf
 
VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...
VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...
VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...
 
power system scada applications and uses
power system scada applications and usespower system scada applications and uses
power system scada applications and uses
 
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort service
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort serviceGurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort service
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort service
 
🔝9953056974🔝!!-YOUNG call girls in Rajendra Nagar Escort rvice Shot 2000 nigh...
🔝9953056974🔝!!-YOUNG call girls in Rajendra Nagar Escort rvice Shot 2000 nigh...🔝9953056974🔝!!-YOUNG call girls in Rajendra Nagar Escort rvice Shot 2000 nigh...
🔝9953056974🔝!!-YOUNG call girls in Rajendra Nagar Escort rvice Shot 2000 nigh...
 
Exploring_Network_Security_with_JA3_by_Rakesh Seal.pptx
Exploring_Network_Security_with_JA3_by_Rakesh Seal.pptxExploring_Network_Security_with_JA3_by_Rakesh Seal.pptx
Exploring_Network_Security_with_JA3_by_Rakesh Seal.pptx
 
IVE Industry Focused Event - Defence Sector 2024
IVE Industry Focused Event - Defence Sector 2024IVE Industry Focused Event - Defence Sector 2024
IVE Industry Focused Event - Defence Sector 2024
 
Artificial-Intelligence-in-Electronics (K).pptx
Artificial-Intelligence-in-Electronics (K).pptxArtificial-Intelligence-in-Electronics (K).pptx
Artificial-Intelligence-in-Electronics (K).pptx
 
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
 
Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024
 

Construction Management Lesson - L1.pptx

  • 2. Players • Owner – owns project upon completion of construction – Private – owner owns land and pays for construction of facility • Able to accept/reject bids based on many parameters including cost, quality, reputation – Public – owner is government agency, public pays for facility • Very strict method of soliciting bids, accepting bids, writing specs 2
  • 3. • Design Professionals – Architects, Engineers, design professionals • Assist owner in developing plan for facility • Make sure it is structurally sound • Make sure all systems, utilities, facilities are integrated into design • Responsible for applying for and obtaining all necessary permits 3
  • 4. • Contractor • Contracts to build project to the specs set forth in the contract for a contracted price – Contract will subcontract to specialty firms – Subcontractors may subcontract further • Project Management – Acts as owners agent and works with designers and contractors to insure high quality and lower cost 4
  • 5. Construction Project • Has following characteristics – Defined goal or objective – Specific tasks not routinely performed – Defined beginning and end – Defined deliverables – Resources being consumed 5
  • 6. • To build a project on time and at cost need a good map to get thru project – Steps • Establish project plan/objectives • Do research into materials and design • Design, estimate and schedule • Present design to owner • Analyze project for viability • Adjust project plans as needed and go back to beginning 6
  • 7. • As the project progresses more information is known and needs to be considered • Good early decisions provide significant benefits. Ability to influence the project costs decreases as the project is built 7
  • 8. Construction Project Categories • Residential • Condos, town houses, apartments, single family homes • Owners may be development companies or individual owners • Fairly low tech • Building Construction Projects • Office buildings, large apartment buildings, shopping malls, theaters • Dependent on economy • Designed by architects with engineering support 8
  • 9. Construction Project Categories • Heavy Construction • Roads, bridges, dams, tunnels, water & waste water systems • Designed by engineers • Usually public projects • Industrial Projects • Steel mills, petroleum refineries, chemical processing plants, auto production facilities • Specialized design and construction • Limited companies do this work 9
  • 10. Chronology • Conceptual Planning – Owner makes decisions on designers, site, and project cost and schedule – Iterative process – add in and delete items to get desired final product – Need to gather as much info as possible • Rehab work uncovers many unknowns – Permits are started and applications made – Estimate +/- 25%, Schedule +/- month 10
  • 11. Chronology • Schematic Design – Actual design begins – Looking at method and materials to use – Value engineering – Begin setting up work packages – Id long lead time items – Preliminary estimate (+/- 10%) and schedule are completed 11
  • 12. Chronology • Design Development – Final design phase – Make system choices based on cost and schedule – Prequalification process for bidders – Contract documents and determination of work packages – Woodrow Wilson Bridge – Fair cost estimate and schedule developed 12
  • 13. Chronology • Construction – Mobilization – Milestones – Substantial completion – Punchlist items – Project Close out 13
  • 14. Project Risk • Bid depends on amount of risk contractor is willing to take • Risks – Project Site – Neighbors, Regulatory environment, Subsurface conditions, Economic climate – Project – complexity, planned technologies, degree of finishes, materials, mechanical/electrical systems – Process – Project funding, timetable, preconstruction info, project unknowns – Owner Org – sophistication, org structure, decision making • Contingency takes some of risk out 14
  • 15. Contract Types • Fixed Price (Lump Sum) • Do work for a set price • Must have an accurate estimate for bid • Provides owner and contractor with a number • Risk to contractor is great, to owner minimal • Unit Price • Price is per unit of each item. Price includes all O&P • Designer estimates quantities 15
  • 16. Contract Types • Cost Plus Fee • Owner reimburses actual costs plus a fee to cover O&P • Good when scope of project is unclear – GMP • Owner knows max price for financing • Clause provides a split of money if contract comes in under budget 16