SlideShare a Scribd company logo
1 of 25
Managing a major organizational change: Lessons learned about coping with homogeneous internal teams and globally diverse external partners.  Academy of Management Management Consulting  Division - 2011 5th International Conference VU University, Amsterdam, the Netherlands Dr. Joseph B. Baugh, PMP Baugh Group LTD Capella University
Dr. Joseph B. Baugh, PMP Program Manager/Project Manager Consultant Technical Trainer Project Management [PMP] Information Security [CISSP, CISM] Faculty Member Three learning institutions Undergrad to doctoral courses Multiple learning milieus Brick-and-mortar Online Hybrid Managing a Change Initiative: MCD 2011 5th International Conference - Amsterdam  © 2011 Joseph B. Baugh 2
Agenda Planning for the project Key project constraints Developing the study Lessons learned  The survey The interviews Conclusion What did it all mean? Managing a Change Initiative: MCD 2011 5th International Conference - Amsterdam  3 © 2011 Joseph B. Baugh
Project Rationale Literally hundreds of applications Legacy systems across multiple platforms Spreadsheets Databases None were interconnected Very inefficient No one “trusted” the numbers No real-time budget data The time had come to change Managing a Change Initiative: MCD 2011 5th International Conference - Amsterdam  © 2011 Joseph B. Baugh 4
Project Planning Examine business processes Identify key internal resources [SMEs] Develop Requests for Proposal [RFPs] ERP system software evaluations Implementation partners Board Funding Approval Project Implementation Post-project activities Managing a Change Initiative: MCD 2011 5th International Conference - Amsterdam  © 2011 Joseph B. Baugh 5
Key Project Constraints Time was the key constraint Aggressive timeline was driven by: Fall Overhaul Schedule Delay in Board Approval Resource Availability Internal resources External consultants Scope was not defined as well as originally thought Managing a Change Initiative: MCD 2011 5th International Conference - Amsterdam  © 2011 Joseph B. Baugh 6
Project Issues Schedule Driven Issues Conflicting demands Resource contention Structural Issues Planning & Training Understanding Business Requirements Geographical and Cultural Barriers Diverse perceptions of results Led to the study described in the paper Managing a Change Initiative: MCD 2011 5th International Conference - Amsterdam  © 2011 Joseph B. Baugh 7
Project Team Structure Managing a Change Initiative: MCD 2011 5th International Conference - Amsterdam  © 2011 Joseph B. Baugh 8
Understanding Business Requirements  Managing a Change Initiative: MCD 2011 5th International Conference - Amsterdam  © 2011 Joseph B. Baugh 9
Lessons Learned: The Survey Qualitative survey of project stakeholders QDAS analysis yielded eight primary themes Pre-project preparation Resource availability Setting expectations Organizing the project Communications Testing Training Post-project issues Managing a Change Initiative: MCD 2011 5th International Conference - Amsterdam  © 2011 Joseph B. Baugh 10
Pre-Project Preparations Fully understand internal business processes before trying to explain them to contractors Review & redefine business processes early on to flesh out RFP Bring in consultants, if necessary, to develop a more complete RFP specification Don’t assume that anything is included in scope unless it is explicitly identified in the RFP Identify & send client team members to ERP training prior to project start Managing a Change Initiative: MCD 2011 5th International Conference - Amsterdam  © 2011 Joseph B. Baugh 11
Resource Availability Identify internal team members early Functional managers must support resource commitment to the project Backfill for critical internal resources Interview individual consultants to ensure appropriate experience levels Check references & experience Don’t let vendor “bait-&-switch” consultants Managing a Change Initiative: MCD 2011 5th International Conference - Amsterdam  © 2011 Joseph B. Baugh 12
Setting Expectations	 Set a reasonable timeline, 8 months is very aggressive for a complex project Don’t let salesmen dictate timelines Manage senior management & user expectations from the start Don’t start project immediately after funding approval, take time to interview & approve consultants Have key business unit owners & employees sign off on their contributions, such as user acceptance testing Managing a Change Initiative: MCD 2011 5th International Conference - Amsterdam  © 2011 Joseph B. Baugh 13
Organizing the Project Authorize one Project Manager to run the project  Better responsibility & accountability Break up large modules into two or more teams Don’t let consultants control the project plan, create one that works for the organization Follow a sound software development methodology Co-locate the project team Ensure that project team members are dedicated to the project Managing a Change Initiative: MCD 2011 5th International Conference - Amsterdam  © 2011 Joseph B. Baugh 14
Communications Go beyond status reports Develop & implement a full communications plan Ensure that the team leads and their Contractors are talking Share information across teams via periodic meetings Resolve conflicts & personnel issues early Share information with all employees Regular internal communications Company intranet site Managing a Change Initiative: MCD 2011 5th International Conference - Amsterdam  © 2011 Joseph B. Baugh 15
Testing Test, test, test, then test some more Convert legacy data first Enhances unit testing as new module configurations are finalized Test valid data with appropriate roles & authorizations Complete and approve integration testing BEFORE Go-Live Managing a Change Initiative: MCD 2011 5th International Conference - Amsterdam  © 2011 Joseph B. Baugh 16
Training Establish a dedicated training team Identify training needs early on Input valid data & configurations into training environment as soon as possible Train employees on the new system as soon as possible Raise satisfaction levels Raise user comfort levels Manage user expectations Managing a Change Initiative: MCD 2011 5th International Conference - Amsterdam  © 2011 Joseph B. Baugh 17
Post-Project Issues Include post-project support as part of implementation RFP Identify post-project training needs as part of the project plan Managing a Change Initiative: MCD 2011 5th International Conference - Amsterdam  © 2011 Joseph B. Baugh 18
Lessons Learned: The Interviews Purposeful sampling of key project personnel The interview protocol Looking behind What worked well? What didn’t work well? Looking ahead  What to try on a future project? QDAS analysis identified the top five tactics in each category Managing a Change Initiative: MCD 2011 5th International Conference - Amsterdam  © 2011 Joseph B. Baugh 19
What Worked Well? Daily standup status reports by team leads Central location for project team Using collaborative software Conference and video calls Timely examination of scope Plan revision Managing a Change Initiative: MCD 2011 5th International Conference - Amsterdam  © 2011 Joseph B. Baugh 20
What Didn’t Work Well?  Ill-defined business requirements Attendance at project team meetings Organizational structure of project staff Reporting on deliverables ERP specific training for project team members Managing a Change Initiative: MCD 2011 5th International Conference - Amsterdam  © 2011 Joseph B. Baugh 21
What to Try on Future Project? Gain earlier full support from senior management Make IT personnel part of the project team Provide IT with user support training early Require key stakeholders to attend major project team meetings Manage the action items better in team meetings Provide better training for all stakeholders including the users Managing a Change Initiative: MCD 2011 5th International Conference - Amsterdam  © 2011 Joseph B. Baugh 22
Conclusion The project team overcame many concerns to meet an aggressive timeline and complete the project for the Fall Overhaul Diverse perceptions of project success led to the study to find lessons learned related to planning, preparation, communications, and implementation Lessons learned came from two primary sets of sources: Surveys & Interviews Managing a Change Initiative: MCD 2011 5th International Conference - Amsterdam  23 © 2011 Joseph B. Baugh
Conclusion Management consultants can apply the lessons learned to assist their clients with:  Defining initial problems Seeking effective solutions Supporting development of RFPs Influencing Senior Management & Boards of Directors Educating clients on roles & responsibilities in successful organizational change initiatives Managing a Change Initiative: MCD 2011 5th International Conference - Amsterdam  24 © 2011 Joseph B. Baugh
Questions Managing a Change Initiative: MCD 2011 5th International Conference - Amsterdam  25 © 2011 Joseph B. Baugh drjoe(at)baughgroup.com

More Related Content

What's hot

Project initiation topic 2.7_the project manager
Project initiation topic 2.7_the project managerProject initiation topic 2.7_the project manager
Project initiation topic 2.7_the project managerRudreshSamant
 
Introduction to project management
Introduction to project managementIntroduction to project management
Introduction to project managementDhani Ahmad
 
2. characteristics of a projec
2. characteristics of a projec2. characteristics of a projec
2. characteristics of a projecDr. Johnson Mavole
 
Webinar: An introduction to the Symphony Software Foundation project life cycle
Webinar: An introduction to the Symphony Software Foundation project life cycleWebinar: An introduction to the Symphony Software Foundation project life cycle
Webinar: An introduction to the Symphony Software Foundation project life cycleSymphony Software Foundation
 
Creating the project charter
Creating the project charterCreating the project charter
Creating the project charterbadrux
 
Infographic Slide: What is Project Management?
Infographic Slide: What is Project Management?Infographic Slide: What is Project Management?
Infographic Slide: What is Project Management?OneDeskApp
 
Infrastructure Project Manager
Infrastructure Project ManagerInfrastructure Project Manager
Infrastructure Project Managergaryclough
 
Chapter 1 Modern Project Management
Chapter 1 Modern Project ManagementChapter 1 Modern Project Management
Chapter 1 Modern Project ManagementKristina Badec
 
ICT4GOV project management_2
ICT4GOV project management_2ICT4GOV project management_2
ICT4GOV project management_2John Macasio
 
Project management Framework
Project management FrameworkProject management Framework
Project management Frameworknewbie2009
 
An Introduction to Project Management
An Introduction to Project Management An Introduction to Project Management
An Introduction to Project Management Krishna Kant
 
PMP Certification Chapter one Summary of PMBOK
PMP Certification Chapter one Summary of PMBOKPMP Certification Chapter one Summary of PMBOK
PMP Certification Chapter one Summary of PMBOKskiltful
 
Chap01 introduction to project management
Chap01 introduction to project managementChap01 introduction to project management
Chap01 introduction to project managementDhani Ahmad
 
PMP Exam Prep_sample slides
PMP Exam Prep_sample slidesPMP Exam Prep_sample slides
PMP Exam Prep_sample slidesWilber Tuttleman
 

What's hot (19)

Project initiation topic 2.7_the project manager
Project initiation topic 2.7_the project managerProject initiation topic 2.7_the project manager
Project initiation topic 2.7_the project manager
 
Introduction to project management
Introduction to project managementIntroduction to project management
Introduction to project management
 
2. characteristics of a projec
2. characteristics of a projec2. characteristics of a projec
2. characteristics of a projec
 
Webinar: An introduction to the Symphony Software Foundation project life cycle
Webinar: An introduction to the Symphony Software Foundation project life cycleWebinar: An introduction to the Symphony Software Foundation project life cycle
Webinar: An introduction to the Symphony Software Foundation project life cycle
 
Lec#1
Lec#1Lec#1
Lec#1
 
Ch05
Ch05Ch05
Ch05
 
Creating the project charter
Creating the project charterCreating the project charter
Creating the project charter
 
Infographic Slide: What is Project Management?
Infographic Slide: What is Project Management?Infographic Slide: What is Project Management?
Infographic Slide: What is Project Management?
 
Infrastructure Project Manager
Infrastructure Project ManagerInfrastructure Project Manager
Infrastructure Project Manager
 
Chapter 1 Modern Project Management
Chapter 1 Modern Project ManagementChapter 1 Modern Project Management
Chapter 1 Modern Project Management
 
ICT4GOV project management_2
ICT4GOV project management_2ICT4GOV project management_2
ICT4GOV project management_2
 
Project management Framework
Project management FrameworkProject management Framework
Project management Framework
 
An Introduction to Project Management
An Introduction to Project Management An Introduction to Project Management
An Introduction to Project Management
 
PMP Certification Chapter one Summary of PMBOK
PMP Certification Chapter one Summary of PMBOKPMP Certification Chapter one Summary of PMBOK
PMP Certification Chapter one Summary of PMBOK
 
Chap01 introduction to project management
Chap01 introduction to project managementChap01 introduction to project management
Chap01 introduction to project management
 
Chapter 2
Chapter 2Chapter 2
Chapter 2
 
Activites and Time Planning
Activites and Time PlanningActivites and Time Planning
Activites and Time Planning
 
PMP Exam Prep_sample slides
PMP Exam Prep_sample slidesPMP Exam Prep_sample slides
PMP Exam Prep_sample slides
 
Pm chapter 7
Pm chapter 7Pm chapter 7
Pm chapter 7
 

Viewers also liked

Opal case study 57 estonia
Opal case study 57 estoniaOpal case study 57 estonia
Opal case study 57 estoniaOPAL2010
 
culture of domino's and pizza hut
 culture of domino's and pizza hut culture of domino's and pizza hut
culture of domino's and pizza hutdivyanshi dayalani
 
Total quality management (tqm)
Total quality management (tqm)Total quality management (tqm)
Total quality management (tqm)Management
 
Veet case study team saltrose_mica
Veet case study team saltrose_micaVeet case study team saltrose_mica
Veet case study team saltrose_micaSatyaprem Upadhyay
 
The Lantus Name Development Case Study
The Lantus Name Development Case StudyThe Lantus Name Development Case Study
The Lantus Name Development Case StudyBill Smith
 
Sanket Kubal MCD PPT
Sanket Kubal MCD PPTSanket Kubal MCD PPT
Sanket Kubal MCD PPTSanket Kubal
 
Case study on success story of suzuki in india
Case study on success story of suzuki in indiaCase study on success story of suzuki in india
Case study on success story of suzuki in indiaProjects Kart
 
A PROJECT REPORT ON “THE LEADERSHIP STORY OF MARUTI SUZUKI”
A PROJECT REPORT ON “THE LEADERSHIP STORY OF  MARUTI SUZUKI”A PROJECT REPORT ON “THE LEADERSHIP STORY OF  MARUTI SUZUKI”
A PROJECT REPORT ON “THE LEADERSHIP STORY OF MARUTI SUZUKI”jitendrasangle
 
Domino’s Pizza - PPT
Domino’s Pizza - PPTDomino’s Pizza - PPT
Domino’s Pizza - PPTTaher S B
 
Dove Beauty Case Study
Dove Beauty Case StudyDove Beauty Case Study
Dove Beauty Case StudyElyse Schaefer
 
Management of Change
Management of ChangeManagement of Change
Management of ChangeISAAC Jayant
 
organisation development (case study of british airways )
organisation development (case study of british airways )organisation development (case study of british airways )
organisation development (case study of british airways )Gurparvesh kaur
 
tata profile
tata profiletata profile
tata profileeceavi
 
Change Management in the organization
Change Management in the organizationChange Management in the organization
Change Management in the organizationJayashree Prabhu
 

Viewers also liked (20)

Presentation1
Presentation1Presentation1
Presentation1
 
Chetna
ChetnaChetna
Chetna
 
McDonald's Term Paper
McDonald's Term PaperMcDonald's Term Paper
McDonald's Term Paper
 
Opal case study 57 estonia
Opal case study 57 estoniaOpal case study 57 estonia
Opal case study 57 estonia
 
culture of domino's and pizza hut
 culture of domino's and pizza hut culture of domino's and pizza hut
culture of domino's and pizza hut
 
Total quality management (tqm)
Total quality management (tqm)Total quality management (tqm)
Total quality management (tqm)
 
dominos Pizza
dominos Pizzadominos Pizza
dominos Pizza
 
Veet case study team saltrose_mica
Veet case study team saltrose_micaVeet case study team saltrose_mica
Veet case study team saltrose_mica
 
The Lantus Name Development Case Study
The Lantus Name Development Case StudyThe Lantus Name Development Case Study
The Lantus Name Development Case Study
 
Sanket Kubal MCD PPT
Sanket Kubal MCD PPTSanket Kubal MCD PPT
Sanket Kubal MCD PPT
 
Case study on success story of suzuki in india
Case study on success story of suzuki in indiaCase study on success story of suzuki in india
Case study on success story of suzuki in india
 
A PROJECT REPORT ON “THE LEADERSHIP STORY OF MARUTI SUZUKI”
A PROJECT REPORT ON “THE LEADERSHIP STORY OF  MARUTI SUZUKI”A PROJECT REPORT ON “THE LEADERSHIP STORY OF  MARUTI SUZUKI”
A PROJECT REPORT ON “THE LEADERSHIP STORY OF MARUTI SUZUKI”
 
Domino’s Pizza - PPT
Domino’s Pizza - PPTDomino’s Pizza - PPT
Domino’s Pizza - PPT
 
Introduction of domino pdf
Introduction of domino pdfIntroduction of domino pdf
Introduction of domino pdf
 
Dove Beauty Case Study
Dove Beauty Case StudyDove Beauty Case Study
Dove Beauty Case Study
 
Management of Change
Management of ChangeManagement of Change
Management of Change
 
Tata vs cyrus
Tata vs cyrusTata vs cyrus
Tata vs cyrus
 
organisation development (case study of british airways )
organisation development (case study of british airways )organisation development (case study of british airways )
organisation development (case study of british airways )
 
tata profile
tata profiletata profile
tata profile
 
Change Management in the organization
Change Management in the organizationChange Management in the organization
Change Management in the organization
 

Similar to Managing A Major Organizational Change

PMP Muzette Charles_Sp2019_Week2_Chapter4_5
PMP Muzette Charles_Sp2019_Week2_Chapter4_5PMP Muzette Charles_Sp2019_Week2_Chapter4_5
PMP Muzette Charles_Sp2019_Week2_Chapter4_5Muzette Charles, PMP
 
PMP Training - 01 introduction to framework
PMP Training - 01 introduction to frameworkPMP Training - 01 introduction to framework
PMP Training - 01 introduction to frameworkejlp12
 
Chapter 3 Lecture Slides
Chapter 3 Lecture SlidesChapter 3 Lecture Slides
Chapter 3 Lecture Slidesdotesch
 
Vcs platform verhaal final
Vcs platform verhaal finalVcs platform verhaal final
Vcs platform verhaal finalNeZtslide
 
Chap 4.0 Project integration management Overview
Chap 4.0 Project integration management OverviewChap 4.0 Project integration management Overview
Chap 4.0 Project integration management OverviewAnand Bobade
 
20240130_UNIUD_Book Presentation_Applying Lean Project Management_(LMA).pptx
20240130_UNIUD_Book Presentation_Applying Lean Project Management_(LMA).pptx20240130_UNIUD_Book Presentation_Applying Lean Project Management_(LMA).pptx
20240130_UNIUD_Book Presentation_Applying Lean Project Management_(LMA).pptxirrosennen
 
Pmp Questions Complete
Pmp Questions CompletePmp Questions Complete
Pmp Questions CompleteKareemBullard1
 
Lec 08 project scope_management
Lec 08 project scope_managementLec 08 project scope_management
Lec 08 project scope_managementSAJID ALI RUK
 
project analysis and management for the masters students.
project analysis and management for the masters students.project analysis and management for the masters students.
project analysis and management for the masters students.abuzertaju
 
Chapter 4(1) system development life .ppt
Chapter 4(1) system development life .pptChapter 4(1) system development life .ppt
Chapter 4(1) system development life .pptDoaaRezk5
 
Project Management 101
Project Management 101Project Management 101
Project Management 101Ryan Campbell
 

Similar to Managing A Major Organizational Change (20)

PMP Muzette Charles_Sp2019_Week2_Chapter4_5
PMP Muzette Charles_Sp2019_Week2_Chapter4_5PMP Muzette Charles_Sp2019_Week2_Chapter4_5
PMP Muzette Charles_Sp2019_Week2_Chapter4_5
 
CAPM Week 2 Chapter 4
CAPM Week 2 Chapter 4CAPM Week 2 Chapter 4
CAPM Week 2 Chapter 4
 
PMP Training - 01 introduction to framework
PMP Training - 01 introduction to frameworkPMP Training - 01 introduction to framework
PMP Training - 01 introduction to framework
 
Chapter 3 Lecture Slides
Chapter 3 Lecture SlidesChapter 3 Lecture Slides
Chapter 3 Lecture Slides
 
ch04.ppt
ch04.pptch04.ppt
ch04.ppt
 
Vcs platform verhaal final
Vcs platform verhaal finalVcs platform verhaal final
Vcs platform verhaal final
 
Section 1: introduction
Section 1: introductionSection 1: introduction
Section 1: introduction
 
Section 1: introduction
Section 1: introductionSection 1: introduction
Section 1: introduction
 
Resume Al Cleverley 2016
Resume Al Cleverley 2016Resume Al Cleverley 2016
Resume Al Cleverley 2016
 
Chap 4.0 Project integration management Overview
Chap 4.0 Project integration management OverviewChap 4.0 Project integration management Overview
Chap 4.0 Project integration management Overview
 
20240130_UNIUD_Book Presentation_Applying Lean Project Management_(LMA).pptx
20240130_UNIUD_Book Presentation_Applying Lean Project Management_(LMA).pptx20240130_UNIUD_Book Presentation_Applying Lean Project Management_(LMA).pptx
20240130_UNIUD_Book Presentation_Applying Lean Project Management_(LMA).pptx
 
Project Implementation
Project ImplementationProject Implementation
Project Implementation
 
Pmp Questions Complete
Pmp Questions CompletePmp Questions Complete
Pmp Questions Complete
 
Lec 08 project scope_management
Lec 08 project scope_managementLec 08 project scope_management
Lec 08 project scope_management
 
project analysis and management for the masters students.
project analysis and management for the masters students.project analysis and management for the masters students.
project analysis and management for the masters students.
 
Project Management Framework
Project Management FrameworkProject Management Framework
Project Management Framework
 
Chapter 3
Chapter 3Chapter 3
Chapter 3
 
Pm chapter 7...
Pm chapter 7...Pm chapter 7...
Pm chapter 7...
 
Chapter 4(1) system development life .ppt
Chapter 4(1) system development life .pptChapter 4(1) system development life .ppt
Chapter 4(1) system development life .ppt
 
Project Management 101
Project Management 101Project Management 101
Project Management 101
 

Recently uploaded

PEMATANG SIANTAR 0851/8063/4797 JUAL OBAT ABORSI CYTOTEC PEMATANG SIANTAR
PEMATANG SIANTAR 0851/8063/4797 JUAL OBAT ABORSI CYTOTEC PEMATANG SIANTARPEMATANG SIANTAR 0851/8063/4797 JUAL OBAT ABORSI CYTOTEC PEMATANG SIANTAR
PEMATANG SIANTAR 0851/8063/4797 JUAL OBAT ABORSI CYTOTEC PEMATANG SIANTARdoktercalysta
 
5 Brilliant Ways To Buy Verified Payoneer Accounts In 2024
5 Brilliant Ways To Buy Verified Payoneer Accounts In 20245 Brilliant Ways To Buy Verified Payoneer Accounts In 2024
5 Brilliant Ways To Buy Verified Payoneer Accounts In 2024https://localsmmshop.com/
 
NewBase 17 May 2024 Energy News issue - 1725 by Khaled Al Awadi_compresse...
NewBase   17 May  2024  Energy News issue - 1725 by Khaled Al Awadi_compresse...NewBase   17 May  2024  Energy News issue - 1725 by Khaled Al Awadi_compresse...
NewBase 17 May 2024 Energy News issue - 1725 by Khaled Al Awadi_compresse...Khaled Al Awadi
 
Toyota Kata Coaching for Agile Teams & Transformations
Toyota Kata Coaching for Agile Teams & TransformationsToyota Kata Coaching for Agile Teams & Transformations
Toyota Kata Coaching for Agile Teams & TransformationsStefan Wolpers
 
Stages of Startup Funding - An Explainer
Stages of Startup Funding - An ExplainerStages of Startup Funding - An Explainer
Stages of Startup Funding - An ExplainerAlejandro Cremades
 
wagamamaLab presentation @MIT 20240509 IRODORI
wagamamaLab presentation @MIT 20240509 IRODORIwagamamaLab presentation @MIT 20240509 IRODORI
wagamamaLab presentation @MIT 20240509 IRODORIIRODORI inc.
 
How to refresh to be fit for the future world
How to refresh to be fit for the future worldHow to refresh to be fit for the future world
How to refresh to be fit for the future worldChris Skinner
 
stock price prediction using machine learning
stock price prediction using machine learningstock price prediction using machine learning
stock price prediction using machine learninggauravwankar27
 
hyundai capital 2023 consolidated financial statements
hyundai capital 2023 consolidated financial statementshyundai capital 2023 consolidated financial statements
hyundai capital 2023 consolidated financial statementsirhcs
 
Creating an Income Statement with Forecasts: A Simple Guide and Free Excel Te...
Creating an Income Statement with Forecasts: A Simple Guide and Free Excel Te...Creating an Income Statement with Forecasts: A Simple Guide and Free Excel Te...
Creating an Income Statement with Forecasts: A Simple Guide and Free Excel Te...Aurelien Domont, MBA
 
PitchBook’s Guide to VC Funding for Startups
PitchBook’s Guide to VC Funding for StartupsPitchBook’s Guide to VC Funding for Startups
PitchBook’s Guide to VC Funding for StartupsAlejandro Cremades
 
Abortion pills in Muscut<Oman(+27737758557) Cytotec available.inn Kuwait City.
Abortion pills in Muscut<Oman(+27737758557) Cytotec available.inn Kuwait City.Abortion pills in Muscut<Oman(+27737758557) Cytotec available.inn Kuwait City.
Abortion pills in Muscut<Oman(+27737758557) Cytotec available.inn Kuwait City.daisycvs
 
Hyundai capital 2024 1q Earnings release
Hyundai capital 2024 1q Earnings releaseHyundai capital 2024 1q Earnings release
Hyundai capital 2024 1q Earnings releaseirhcs
 
MichaelStarkes_UncutGemsProjectSummary.pdf
MichaelStarkes_UncutGemsProjectSummary.pdfMichaelStarkes_UncutGemsProjectSummary.pdf
MichaelStarkes_UncutGemsProjectSummary.pdfmstarkes24
 
Presentation4 (2) survey responses clearly labelled
Presentation4 (2) survey responses clearly labelledPresentation4 (2) survey responses clearly labelled
Presentation4 (2) survey responses clearly labelledCaitlinCummins3
 
Global Internal Audit Standards 2024.pdf
Global Internal Audit Standards 2024.pdfGlobal Internal Audit Standards 2024.pdf
Global Internal Audit Standards 2024.pdfAmer Morgan
 
Creative Ideas for Interactive Team Presentations
Creative Ideas for Interactive Team PresentationsCreative Ideas for Interactive Team Presentations
Creative Ideas for Interactive Team PresentationsSlidesAI
 
What is paper chromatography, principal, procedure,types, diagram, advantages...
What is paper chromatography, principal, procedure,types, diagram, advantages...What is paper chromatography, principal, procedure,types, diagram, advantages...
What is paper chromatography, principal, procedure,types, diagram, advantages...srcw2322l101
 

Recently uploaded (20)

PEMATANG SIANTAR 0851/8063/4797 JUAL OBAT ABORSI CYTOTEC PEMATANG SIANTAR
PEMATANG SIANTAR 0851/8063/4797 JUAL OBAT ABORSI CYTOTEC PEMATANG SIANTARPEMATANG SIANTAR 0851/8063/4797 JUAL OBAT ABORSI CYTOTEC PEMATANG SIANTAR
PEMATANG SIANTAR 0851/8063/4797 JUAL OBAT ABORSI CYTOTEC PEMATANG SIANTAR
 
5 Brilliant Ways To Buy Verified Payoneer Accounts In 2024
5 Brilliant Ways To Buy Verified Payoneer Accounts In 20245 Brilliant Ways To Buy Verified Payoneer Accounts In 2024
5 Brilliant Ways To Buy Verified Payoneer Accounts In 2024
 
NewBase 17 May 2024 Energy News issue - 1725 by Khaled Al Awadi_compresse...
NewBase   17 May  2024  Energy News issue - 1725 by Khaled Al Awadi_compresse...NewBase   17 May  2024  Energy News issue - 1725 by Khaled Al Awadi_compresse...
NewBase 17 May 2024 Energy News issue - 1725 by Khaled Al Awadi_compresse...
 
Toyota Kata Coaching for Agile Teams & Transformations
Toyota Kata Coaching for Agile Teams & TransformationsToyota Kata Coaching for Agile Teams & Transformations
Toyota Kata Coaching for Agile Teams & Transformations
 
Stages of Startup Funding - An Explainer
Stages of Startup Funding - An ExplainerStages of Startup Funding - An Explainer
Stages of Startup Funding - An Explainer
 
wagamamaLab presentation @MIT 20240509 IRODORI
wagamamaLab presentation @MIT 20240509 IRODORIwagamamaLab presentation @MIT 20240509 IRODORI
wagamamaLab presentation @MIT 20240509 IRODORI
 
WAM Corporate Presentation May 2024_w.pdf
WAM Corporate Presentation May 2024_w.pdfWAM Corporate Presentation May 2024_w.pdf
WAM Corporate Presentation May 2024_w.pdf
 
How to refresh to be fit for the future world
How to refresh to be fit for the future worldHow to refresh to be fit for the future world
How to refresh to be fit for the future world
 
stock price prediction using machine learning
stock price prediction using machine learningstock price prediction using machine learning
stock price prediction using machine learning
 
hyundai capital 2023 consolidated financial statements
hyundai capital 2023 consolidated financial statementshyundai capital 2023 consolidated financial statements
hyundai capital 2023 consolidated financial statements
 
Creating an Income Statement with Forecasts: A Simple Guide and Free Excel Te...
Creating an Income Statement with Forecasts: A Simple Guide and Free Excel Te...Creating an Income Statement with Forecasts: A Simple Guide and Free Excel Te...
Creating an Income Statement with Forecasts: A Simple Guide and Free Excel Te...
 
PitchBook’s Guide to VC Funding for Startups
PitchBook’s Guide to VC Funding for StartupsPitchBook’s Guide to VC Funding for Startups
PitchBook’s Guide to VC Funding for Startups
 
Abortion pills in Muscut<Oman(+27737758557) Cytotec available.inn Kuwait City.
Abortion pills in Muscut<Oman(+27737758557) Cytotec available.inn Kuwait City.Abortion pills in Muscut<Oman(+27737758557) Cytotec available.inn Kuwait City.
Abortion pills in Muscut<Oman(+27737758557) Cytotec available.inn Kuwait City.
 
(推特)Twitter账号批发(自助购买网址🎉top233.com🎉)
(推特)Twitter账号批发(自助购买网址🎉top233.com🎉)(推特)Twitter账号批发(自助购买网址🎉top233.com🎉)
(推特)Twitter账号批发(自助购买网址🎉top233.com🎉)
 
Hyundai capital 2024 1q Earnings release
Hyundai capital 2024 1q Earnings releaseHyundai capital 2024 1q Earnings release
Hyundai capital 2024 1q Earnings release
 
MichaelStarkes_UncutGemsProjectSummary.pdf
MichaelStarkes_UncutGemsProjectSummary.pdfMichaelStarkes_UncutGemsProjectSummary.pdf
MichaelStarkes_UncutGemsProjectSummary.pdf
 
Presentation4 (2) survey responses clearly labelled
Presentation4 (2) survey responses clearly labelledPresentation4 (2) survey responses clearly labelled
Presentation4 (2) survey responses clearly labelled
 
Global Internal Audit Standards 2024.pdf
Global Internal Audit Standards 2024.pdfGlobal Internal Audit Standards 2024.pdf
Global Internal Audit Standards 2024.pdf
 
Creative Ideas for Interactive Team Presentations
Creative Ideas for Interactive Team PresentationsCreative Ideas for Interactive Team Presentations
Creative Ideas for Interactive Team Presentations
 
What is paper chromatography, principal, procedure,types, diagram, advantages...
What is paper chromatography, principal, procedure,types, diagram, advantages...What is paper chromatography, principal, procedure,types, diagram, advantages...
What is paper chromatography, principal, procedure,types, diagram, advantages...
 

Managing A Major Organizational Change

  • 1. Managing a major organizational change: Lessons learned about coping with homogeneous internal teams and globally diverse external partners. Academy of Management Management Consulting Division - 2011 5th International Conference VU University, Amsterdam, the Netherlands Dr. Joseph B. Baugh, PMP Baugh Group LTD Capella University
  • 2. Dr. Joseph B. Baugh, PMP Program Manager/Project Manager Consultant Technical Trainer Project Management [PMP] Information Security [CISSP, CISM] Faculty Member Three learning institutions Undergrad to doctoral courses Multiple learning milieus Brick-and-mortar Online Hybrid Managing a Change Initiative: MCD 2011 5th International Conference - Amsterdam © 2011 Joseph B. Baugh 2
  • 3. Agenda Planning for the project Key project constraints Developing the study Lessons learned The survey The interviews Conclusion What did it all mean? Managing a Change Initiative: MCD 2011 5th International Conference - Amsterdam 3 © 2011 Joseph B. Baugh
  • 4. Project Rationale Literally hundreds of applications Legacy systems across multiple platforms Spreadsheets Databases None were interconnected Very inefficient No one “trusted” the numbers No real-time budget data The time had come to change Managing a Change Initiative: MCD 2011 5th International Conference - Amsterdam © 2011 Joseph B. Baugh 4
  • 5. Project Planning Examine business processes Identify key internal resources [SMEs] Develop Requests for Proposal [RFPs] ERP system software evaluations Implementation partners Board Funding Approval Project Implementation Post-project activities Managing a Change Initiative: MCD 2011 5th International Conference - Amsterdam © 2011 Joseph B. Baugh 5
  • 6. Key Project Constraints Time was the key constraint Aggressive timeline was driven by: Fall Overhaul Schedule Delay in Board Approval Resource Availability Internal resources External consultants Scope was not defined as well as originally thought Managing a Change Initiative: MCD 2011 5th International Conference - Amsterdam © 2011 Joseph B. Baugh 6
  • 7. Project Issues Schedule Driven Issues Conflicting demands Resource contention Structural Issues Planning & Training Understanding Business Requirements Geographical and Cultural Barriers Diverse perceptions of results Led to the study described in the paper Managing a Change Initiative: MCD 2011 5th International Conference - Amsterdam © 2011 Joseph B. Baugh 7
  • 8. Project Team Structure Managing a Change Initiative: MCD 2011 5th International Conference - Amsterdam © 2011 Joseph B. Baugh 8
  • 9. Understanding Business Requirements Managing a Change Initiative: MCD 2011 5th International Conference - Amsterdam © 2011 Joseph B. Baugh 9
  • 10. Lessons Learned: The Survey Qualitative survey of project stakeholders QDAS analysis yielded eight primary themes Pre-project preparation Resource availability Setting expectations Organizing the project Communications Testing Training Post-project issues Managing a Change Initiative: MCD 2011 5th International Conference - Amsterdam © 2011 Joseph B. Baugh 10
  • 11. Pre-Project Preparations Fully understand internal business processes before trying to explain them to contractors Review & redefine business processes early on to flesh out RFP Bring in consultants, if necessary, to develop a more complete RFP specification Don’t assume that anything is included in scope unless it is explicitly identified in the RFP Identify & send client team members to ERP training prior to project start Managing a Change Initiative: MCD 2011 5th International Conference - Amsterdam © 2011 Joseph B. Baugh 11
  • 12. Resource Availability Identify internal team members early Functional managers must support resource commitment to the project Backfill for critical internal resources Interview individual consultants to ensure appropriate experience levels Check references & experience Don’t let vendor “bait-&-switch” consultants Managing a Change Initiative: MCD 2011 5th International Conference - Amsterdam © 2011 Joseph B. Baugh 12
  • 13. Setting Expectations Set a reasonable timeline, 8 months is very aggressive for a complex project Don’t let salesmen dictate timelines Manage senior management & user expectations from the start Don’t start project immediately after funding approval, take time to interview & approve consultants Have key business unit owners & employees sign off on their contributions, such as user acceptance testing Managing a Change Initiative: MCD 2011 5th International Conference - Amsterdam © 2011 Joseph B. Baugh 13
  • 14. Organizing the Project Authorize one Project Manager to run the project Better responsibility & accountability Break up large modules into two or more teams Don’t let consultants control the project plan, create one that works for the organization Follow a sound software development methodology Co-locate the project team Ensure that project team members are dedicated to the project Managing a Change Initiative: MCD 2011 5th International Conference - Amsterdam © 2011 Joseph B. Baugh 14
  • 15. Communications Go beyond status reports Develop & implement a full communications plan Ensure that the team leads and their Contractors are talking Share information across teams via periodic meetings Resolve conflicts & personnel issues early Share information with all employees Regular internal communications Company intranet site Managing a Change Initiative: MCD 2011 5th International Conference - Amsterdam © 2011 Joseph B. Baugh 15
  • 16. Testing Test, test, test, then test some more Convert legacy data first Enhances unit testing as new module configurations are finalized Test valid data with appropriate roles & authorizations Complete and approve integration testing BEFORE Go-Live Managing a Change Initiative: MCD 2011 5th International Conference - Amsterdam © 2011 Joseph B. Baugh 16
  • 17. Training Establish a dedicated training team Identify training needs early on Input valid data & configurations into training environment as soon as possible Train employees on the new system as soon as possible Raise satisfaction levels Raise user comfort levels Manage user expectations Managing a Change Initiative: MCD 2011 5th International Conference - Amsterdam © 2011 Joseph B. Baugh 17
  • 18. Post-Project Issues Include post-project support as part of implementation RFP Identify post-project training needs as part of the project plan Managing a Change Initiative: MCD 2011 5th International Conference - Amsterdam © 2011 Joseph B. Baugh 18
  • 19. Lessons Learned: The Interviews Purposeful sampling of key project personnel The interview protocol Looking behind What worked well? What didn’t work well? Looking ahead What to try on a future project? QDAS analysis identified the top five tactics in each category Managing a Change Initiative: MCD 2011 5th International Conference - Amsterdam © 2011 Joseph B. Baugh 19
  • 20. What Worked Well? Daily standup status reports by team leads Central location for project team Using collaborative software Conference and video calls Timely examination of scope Plan revision Managing a Change Initiative: MCD 2011 5th International Conference - Amsterdam © 2011 Joseph B. Baugh 20
  • 21. What Didn’t Work Well? Ill-defined business requirements Attendance at project team meetings Organizational structure of project staff Reporting on deliverables ERP specific training for project team members Managing a Change Initiative: MCD 2011 5th International Conference - Amsterdam © 2011 Joseph B. Baugh 21
  • 22. What to Try on Future Project? Gain earlier full support from senior management Make IT personnel part of the project team Provide IT with user support training early Require key stakeholders to attend major project team meetings Manage the action items better in team meetings Provide better training for all stakeholders including the users Managing a Change Initiative: MCD 2011 5th International Conference - Amsterdam © 2011 Joseph B. Baugh 22
  • 23. Conclusion The project team overcame many concerns to meet an aggressive timeline and complete the project for the Fall Overhaul Diverse perceptions of project success led to the study to find lessons learned related to planning, preparation, communications, and implementation Lessons learned came from two primary sets of sources: Surveys & Interviews Managing a Change Initiative: MCD 2011 5th International Conference - Amsterdam 23 © 2011 Joseph B. Baugh
  • 24. Conclusion Management consultants can apply the lessons learned to assist their clients with: Defining initial problems Seeking effective solutions Supporting development of RFPs Influencing Senior Management & Boards of Directors Educating clients on roles & responsibilities in successful organizational change initiatives Managing a Change Initiative: MCD 2011 5th International Conference - Amsterdam 24 © 2011 Joseph B. Baugh
  • 25. Questions Managing a Change Initiative: MCD 2011 5th International Conference - Amsterdam 25 © 2011 Joseph B. Baugh drjoe(at)baughgroup.com