SlideShare a Scribd company logo
1 of 7
Download to read offline
International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056
Volume: 07 Issue: 01 | Jan 2020 www.irjet.net p-ISSN: 2395-0072
© 2020, IRJET | Impact Factor value: 7.34 | ISO 9001:2008 Certified Journal | Page 1794
GEO- Mining Based Reliability Assessment of Continuous Surface
Miners–A Critical Review
Hemant Sharad Pande1, Dr. Manish. D. Uttarwar2, Prof. M.S. Tiwari3
1Chief Manager (Mining), Gevra Area, S.E.C.L
2Professor (On Lien), Department of Mining Engineering, R C E R T, Chandrapur
3Associate Professor, Ramdeobaba College of Engineering & Management
---------------------------------------------------------------------***----------------------------------------------------------------------
Abstract -At present the demand of coal is more than
1000MT in spite of more focus by Govt. on solar and other
non conventional source of energy. The new perspective
requires systematic operational planning and strict
operational control of capital intensive machine. The
proactive approach of equipment reliability assessment
will be beneficial for surface coal mines. The quantitivly
production paradigm is now shifting towards
qualitatively. The conventional methods of coal extraction
in surface mining does not sustained with qualitative
aspect. The application of Surface Miners minimizes the
mining activities up to a limited extent. Due to wide
application and adoptability in surface coal mining, it
shows that Surface miner is a proved technology can
beneficial in different aspects. if its reliability and
productivity parameters are handled with due diligence.
The surface miner equipment handled the required
gigantic and qualitative coal target. This technology is
used as hallmark for selective mining. At present, Out of
422 Approximately 150 Surface Miners of different make
and capacity are operated in India at different sectors.
Appropriate use of technology fulfills techno-safe,
economical and quality requirements along with
avoidance strategy of blasting and crushing. Ability of
surface miner to operate and cut coal effectively is limited
to strength of coal. Update knowledge of coal
characteristics and machine interactions utmost necessary
for gigantic production and smooth operation. For best
utilization of this technology, it is required to predict
surface miner reliabilities on basis of geo mining
parameter. GEVRA OCP is world’s third highest coal
producing mine, the yearly production target is 45 MT and
subsequently increases up to 70 MT in next three years.
Eleven numbers of surface miners are used as a part of
systematic method of coal production along with Pay-
loader & surface trucks. The Overburden handling uses
Shovel-Dumper combination. Reliability assessment and
evaluation of surface miner by Weibull analysis is detailed
in this paper. Break down details of sub parts & whole of
surface miner in three years is used in this study. Output
element of this study is line fit plot & probability of failure
of different subparts. Performance of the Surface miner
are assessed through comparative evaluation of line fit
plot & geo mining parameters. Probability of failure is
helpful to design proactive maintenance strategy in
advance. Due to compatibility & adoptability in
production growth, there may be future scope of
application in different mines so the reliability analyses of
these equipments are to be studied.
Key Words: Reliability, Weibull Analysis, Reliability
Evaluation, Reliability Assessment, Surface miner.
1. INTRODUCTION
India’s two-third commercial energy mainly comes from
coal and will be increased in subsequent years. The
difference between demand and supply needs to cope up
through reforming the process of coal production and
technology adopted. There are various reasons related to
government strategies, which hinder the coal production
and appropriate measures required to boost up coal
production. Opencast mines share almost four-fifth of
total coal production in India so boost up the opencast
mines production is a prime target for coal Industry.
Govt. strategies also enforce to improve efficiency of the
coal sectors in level of international standards. The
output norms of capital intensive machines reviewed
and become comparable with international levels.
Incredible pressure on Coal Company wants boost up the
opencast production have become thrust areas.
Reliability related with better utilizations of human
resource and capital investment. Better equipment
reliability is a choice and reliability analysis at initial
operational stage is essential to verify the reliability of
the same equipment for further deployment Reliability
analysis of mining equipment is helpful to estimate the
failure patterns. In this study the sub-parts of Surface
miner is integrated to evaluate the actual equipment
reliability. A case study of surface miners presented in
this paper to evaluate reliability as an early operating
reliability.
1.1 Glimpses of Gevra Opencast Mine
The coal block of the project consist thick coal bench and
strike direction is NW-SE to E-W in major part of the
block. The average stripping ratio in this OCP is 1.3 along
with thickness range 117 -174 m and seam gradient is
40 to 90 Surface miners are used for coal production, the
slope angle of coal bench is of 600 to 750. Mainly 42
cum shovel- 240 Te dumper combinations with large
diametric deep hole drills of 20 meters depth and 381
mm diameter are used for OB handling. The slope angle
International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056
Volume: 07 Issue: 01 | Jan 2020 www.irjet.net p-ISSN: 2395-0072
© 2020, IRJET | Impact Factor value: 7.34 | ISO 9001:2008 Certified Journal | Page 1795
of coal bench is of 600 to 750. In the year 2019 the coal
and OB production targets 45 million tons and 58 million
cubic meters respectively. It is expected to be the slated
at a production target of 70 million tons in forthcoming
years. To meet the gigantic target, A number of high
capacity capital intensive mining machineries used that
needs to reliable. Reliability is a performance indicator
of overall equipment condition.
1.2 Technical description of Surface Miner
under study
The quality production management in opencast mine
due to layers of shale, & stone bands has become a
difficult task. The application of Surface Miners was
extended for coal mining in the year 1999. The design
concept for the surface miner is based on the milling
principal. Deployment of the Surface Miner technology
largely succeeded and to increase the quality coal
production along with minimizing terminal effect of
mining. At present in every mega project of Coal India,
maximum coal production is obtained by this
technology. The technology is not only contributed as
mass production technology but also produce
appropriate size of fragmentation that is the emergent
need of today. In Gevra OCP there are 12 numbers of
surface miners for coal production which are of different
make but Wirtgen Surface Miner 2200 SM was
considered in this study. The technical specifications are
been mentioned below:
Table 1- Technical & Operating Parameters of SM
Figure- 1: Overview of Surface Miner
2. RELIABILITY OF SURFACE MINERS’
Productivity is major concern even in hired Surface
Miner or departmental surface miner. The evaluation &
prediction of reliability of surface miner was considered
the geo-mining parameter of coal. With this emergent
issue some field observations and data study are being
carried out with respect to operation of Surface Miner
taken under study. The study of failure pattern is
immense importance as the prevailing stiff targets of
coal overcome by maintaining High equipment
reliability, which may come from providing good
operational environmental conditions. The classification
of miners as milling type, bucket wheel type and
ranging-shearer-drum type on basis of cutting drum,
choice is decided on the required capacity and geo
mining parameter of cutting strata. The evaluation of
reliability of Surface miner is been studied in this paper
and the methodology of the same is been developed.
Mainly the methodologies applied for reliability
estimations are Stress Analysis, Reliability Predictions
(MTBF: Mean Time Between Failures), FMCA ( Failures
Mode and Effect Analysis) & FMECA ( Failures Mode
Effects and Criticality Analysis).The flow chart reliability
evaluation of 2200 SM through Weibull analysis. The
breakdown data of the machine has been acquired from
the daily record data base of the component. From the
OEM specifications and manuals, the specific life of the
major assemblies and its sub-assemblies can be
acquired. From the obtained results the probability of
occurrence of error in data selecting for components
failure, uncertainty is evaluated. Even a minor failure of
the selected components leads to system failure and
system operation breakdown and this is the case study
of this research.
Working width` 2.20 m
Max. cutting depth 0.35 m
Engine power 811 PS
Weight 51 t
Cutting drum drive Mechanical
Number of crawlers 4
Travel drive Hydraulic
Working width` 2.20 m
Max. cutting depth 0.35 m
Engine power 811 PS
Weight 51 t
Cutting drum drive Mechanical
Number of crawlers 4
Travel drive Hydraulic
International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056
Volume: 07 Issue: 01 | Jan 2020 www.irjet.net p-ISSN: 2395-0072
© 2020, IRJET | Impact Factor value: 7.34 | ISO 9001:2008 Certified Journal | Page 1796
Figure -2: Flow chart of study work
.
Operating failure data collected from routine day wise
data base. Intercalation pebbles & shale-sandstone
bands other adversely impact on machine health.
Reliability aspects of the equipment play important role
for forecast of sub parts failure .On the basis of reliability
forecast appropriate pro active maintenance scheduled
and minimize the cost. The 2200 SM surface miner is
selected for this study. Weibull analysis is used for a
method for reliability evaluation. The Weibull formula
for two parameter distribution is
R(x) = e (-(x/α) ^β) ; for x>0
Where “β” is the shape parameter,
“α” is the characteristics life
“x” is the time to failure.
The Bernard’s approximation formula for
calculating Median rank is
F (t) = (i-0.3)/ (n+0.4)
Where “i” is the corresponding rank of the data
“n” is the total number of samples
Weibull Analysis is beneficial in ascertain the failure
probability; the output of this analysis is easier line fit
plots. The two defining parameters of the Weibull line
are the shape parameter β, and the characteristic life α.
The Weibull distribution’s easily approximate an
exponential, a normal or a skewed distribution in Excel
and not required more upgraded software.
3. DATA ANALYSIS
In this case study, the Average compressive strength,
Tensile strength, Shear strength & Average density of
three consecutive years has been collected from
borehole logs and correlated with machine reliability.
The geo mining parameter of the coal for the selected
years is computed separately and is depicted in the
Table given below. As can be observed from the data
given above, the major breakdowns in Surface Miner are
attributed to high engine temperatures, hydraulic
Cylinder leakages, idler cracking, drive pump failures,
coupling failures, main control panel, water sprinklers,
lighting, engine firing and air-conditioning unit. The
Table given below shows the coal production from
surface miner, breakdown hours, maintenance hours,
idle hours and working hours in percentage for the
Surface Miner Model SM 2200/3800
Table 3- Geo mining matrix
Table 4- Year wise production and breakdown details
4. OUTPUT OF WEIBULL ANALYSIS
Figure -3: Year – 1 Overall Breakdown
Figure- 4: Year –2 Overall Breakdown
Year
Avg
Compressive
strength
Avg Tensile
strength
Avg shear
strength Avg density
2013-
14 8.50642857 0.626428571 1.519285714 1.527142857
2014-
15 17.3117949 0.506410256 1.203846154 1.444102564
2015-
16 15.8763895 0.739216152 0.948764846 1.527102138
Year Production Breakdown hour
2013-14 3842800 2200.5
2014-15 3867600 2168.5
2015-16 3873200 2173
Field data base
collection
Time to Failure Weibull Analysis
Interpretation by
Weibull plot
Reliability prediction
at diff. hours
Correlation with geo
mining parameters
Geo-mining
reliability
Component & its
relation identification
International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056
Volume: 07 Issue: 01 | Jan 2020 www.irjet.net p-ISSN: 2395-0072
© 2020, IRJET | Impact Factor value: 7.34 | ISO 9001:2008 Certified Journal | Page 1797
Figure -5: Year –3 Overall Breakdown
4.1 Analysis of Weibull plots
In the line plots blue colored line represents the
available reliability and red color line represents
predicted reliability. From the line plot of 1st year over
all breakdowns, it can be observed that the predicted
reliability of 1st year follows almost same path all along
the year except mild increasing trend of actual reliability
in the middle. At final quarter of the year actual
reliability follows same pattern while predicted
reliability is in increasing trend .From the line plot of
2nd year overall breakdown, it can be observed that the
predicted reliability of 2nd year follows straight line
path throughout the year while actual reliability is lower
at the initial phase of the year & after that follows
increasing trend up to some extent till higher than
predicted reliability. At the final quarter of year actual
reliability is slightly lower than predicted reliability and
again increasing trend.
From the line fit plot of Year 3 overall breakdown it can
be observed that at some particular operating hours the
predicted reliability line is lower compared to available
reliability line which clearly show that the reliability of
the machine is much better than the predicted reliability.
The main cause for this condition to occur is the
scheduled maintenance and mini shutdown system
which means the maintenance carried out at some
particular interval of time.
4.2 Reliability study of surface miner by using
Weibull analysis:
Table -5:Reliability study of surface miner by using
weibull analysis
4.3 Reliability analysis of surface miner under
the given geo-mining conditions
This section depicted to establish a relation between
selected year wise associated reliability estimates of
surface miner and geo-mining parameters of coal. The
following observation established after comparative
analysis of the reliability graphical plots of the surface
miners with the selected three years and selected geo-
mining parameters. In this paper only two intervals of
1000 hours and 2000 hours are taken under study in
selected three years.
1-It can be primarily established that the reliability of
the surface miners decreases after a certain initial hours
of deployment with the increasing compressive strength
of the coal material to be handled.
2 -It can be primarily established that the reliability of
the surface miners decreases after a certain initial hours
of deployment with the increasing tensile strength of the
coal material to be handled
3-It can be primarily established that the reliability of
the surface miners decreases after a certain initial hours
of deployment with the increasing shear strength of the
coal material to be handled
Year Year 1 Year 2 Year 3
CYCLE Reliability Reliability Reliability
100 0.986068992 1 1
200 0.966491752 1 1
500 0.895663704 0.999999933 1
1000 0.765136741 0.999995674 1
2000 0.521856309 0.99972067 0.999999992
5000 0.122132088 0.933311539 0.999918873
10000 0.006046543 0.011600464 0.913017417
20000 4.07665E-06 0 0
30000 8.73357E-10 0 0
40000 8.06022E-14 0 0
50000 0 0 0
60000 0 0 0
International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056
Volume: 07 Issue: 01 | Jan 2020 www.irjet.net p-ISSN: 2395-0072
© 2020, IRJET | Impact Factor value: 7.34 | ISO 9001:2008 Certified Journal | Page 1798
4.4 Reliability impact of compressive strength
Figure -6: Compressive strength Vs Reliability at 1000
Hrs
Figure-7: Compressive strength Vs Reliability at 2000
Hrs
4.5 Reliability impact of shear strength
Figure-8: Shear strength Vs Reliability at 1000 Hrs
Figure-9: Shear strength Vs Reliability at 2000 Hrs
4.6 Reliability impact of Tensile strength
Figure-10: Tensile strength Vs Reliability at 1000 Hrs
Figure-11: Tensile strength Vs Reliability at 2000 Hrs
International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056
Volume: 07 Issue: 01 | Jan 2020 www.irjet.net p-ISSN: 2395-0072
© 2020, IRJET | Impact Factor value: 7.34 | ISO 9001:2008 Certified Journal | Page 1799
4.7 Graph between yearly reliability and
working hours for all the 3 years:
Figure-12: Reliability verses working hours
4.8 Observations
Reliability graph in the year 2013-14 follows drastically
down trend at initial hours of deployment up to 2000
hrs. Reliability graph in the year 2014-15 follows
straight line path during initial hours of deployment up
to 2000 hrs. of working. Reliability graph in the year
2015-16 follows straight line path at initial hours of
deployment up to 5000 hrs. Finally it shows that
Reliability has a correlation with working hours & the
geo mining characteristics of coal. Both are the prime
factors that are responsible for variation in Reliability of
surface miner.
4.9 Final Inference
Geo-mining parameters during the period of the study
under different coal characteristics were analyzed
individually and it was found that the reason of
breakdowns were common except it was noted that the
frequency of electrical problem is higher which required
the review of the system from the point of view of
original equipment manufacturer (OEM). The
preparedness for pro-active maintenance strategy to
improve the Reliability of machine is an essential
function to be looked into. Operational failure will be
minimized by way of provision for maintenance strategy
formulation with regard to deployment of the surface
miner.
5. CONCLUSIONS AND SUGGESTED FUTURE
WORK
Different geo mining parameters during deployment of
surface miner machine were considered primarily in this
study. All the major heads of breakdowns were identified
& they were analyzed by regression method of Weibull
including the maintenance strategy of surface miner. In
this study the importance of operational parameters
were highlighted. The relations between all the
operational parameters of surface miner machine and
the mechanical reliability, which was calculated by
Weibull analysis were developed and that are found
useful to find out the predicted reliability at different
phases of machine with respect to geo mining
parameters .The study was aimed at improving the
reliability of surface miner technology by identifying
major thrust hold categories of breakdowns at different
known geo mining parameters. The studies of various
parameters including the breakdowns of the machine
were found useful to identify the areas of concern from
the operational point of view as well as from machine
design point of view. The study also focused on
possibility of few design changes from the OEM point of
view. The major inferences which were derived from this
research work are discussed in the following section.
5.1 Suggested maintenance strategy
The study suggested some of the areas as critical areas
including the breakdown areas in the machine. The
impact of all the breakdown reasons of all the electrical
and mechanical nature during the study period was
identified and Reliability of the machine was studied.
Definitely the breakdown reasons are responsible for
reduction of the reliability of the machine but the study
was done to find out the greatest impact factor to
suggest improvement in maintenance strategy of the
machine. The following point should be considered
during formulation of maintenance strategy:
1. A reliability review team will be trained in each mine.
2. Reliability review interval should be decided on basis
of planned machine deployment strategy.
3. A three tier maintenance strategy should be
developed.
4. Safety parameters of machine are also considered as
input parameter during reliability analysis.
5.2 Suggested Deployment strategy
In future, a number of surface miners are planned to be
deployed in this mega project as the target of the project
is going to be doubled in the coming years. This study
undertaken thus provides a guideline for predicted
deployment with respect to the reliability as well as the
productivity of the given surface miner.
5.3 Suggested future work
The studies of some of the important geo-mining
parameters of surface miner were considered in this
research study. In future the other parameters such as
wear & tear of cutting picks, impact of deeper cut on
machine reliability can suggest new relationship to find
out the better way for improving reliability. The study of
different make of surface miners deployed in other
minerals can also be useful in strengthening the
established relationship between different parameters
which are suggested in this study.
International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056
Volume: 07 Issue: 01 | Jan 2020 www.irjet.net p-ISSN: 2395-0072
© 2020, IRJET | Impact Factor value: 7.34 | ISO 9001:2008 Certified Journal | Page 1800
5.4 Recommendations for the effective
utilization of the surface miner
1. Operational reliability can be improvised by
planning activities like “campaign” strategy,
whereby a “mini-shutdowns” are programmed at
regular intervals to perform all necessary
maintenance and inspections.
2. On line machine diagnostics and down time
minimizing techniques can enhance reliability of the
machine.
3. Immediate action to be taken for frequently
impacting breakdowns. Proper scientific layout, face
availability can help reduce idle/waiting time to a
greater extent.
ACKNOWLEDGEMENT
The work proposed in this paper forms a part of the Post
Graduate study of the first author. The author expresses
his thankfulness towards the supervisors of the study
and department of mining engineering, RCERT
Chandrapur for providing varied facilities. The
permission and subsequent field support from Gevra
OCP, S.E.C.L. is deeply acknowledged with thanks. The
view expressed in this paper is those of authors and not
necessarily of the organizations they represent nor of
the sector under study.
REFERENCES
[1] WIRTGEN(1984).WRITGEN INFORMATION/IW-
2/84-22/5/84
[2] Wiilliam W. Dorner (1999), Using Microsoft
Excel for Weibull Analysis,
http://www.qualitydigest.com/pdfs/weibull.xls
[3] Coal India Limited, www.cil.nic.in

More Related Content

Similar to Reliability assessment of surface miners using Weibull analysis

Study of Influence of Tool Nose Radius on Surface Roughness and Material Remo...
Study of Influence of Tool Nose Radius on Surface Roughness and Material Remo...Study of Influence of Tool Nose Radius on Surface Roughness and Material Remo...
Study of Influence of Tool Nose Radius on Surface Roughness and Material Remo...IRJET Journal
 
IRJET - Fabrication of Four Way Machining by using Scotch Yoke Mechanism
IRJET - Fabrication of Four Way Machining by using Scotch Yoke MechanismIRJET - Fabrication of Four Way Machining by using Scotch Yoke Mechanism
IRJET - Fabrication of Four Way Machining by using Scotch Yoke MechanismIRJET Journal
 
AN INVESTIGATION ON MINE OVERBURDEN DUMP SLOPE STABILITY
AN INVESTIGATION ON MINE OVERBURDEN DUMP SLOPE STABILITYAN INVESTIGATION ON MINE OVERBURDEN DUMP SLOPE STABILITY
AN INVESTIGATION ON MINE OVERBURDEN DUMP SLOPE STABILITYIRJET Journal
 
A Theoretical Study on Strata Behaviour and Ground Control in Coal Mines
A Theoretical Study on Strata Behaviour and Ground Control in Coal MinesA Theoretical Study on Strata Behaviour and Ground Control in Coal Mines
A Theoretical Study on Strata Behaviour and Ground Control in Coal MinesIRJET Journal
 
IRJET- Characteristic and Failure Analysis of Frp Composite Tank used for Sod...
IRJET- Characteristic and Failure Analysis of Frp Composite Tank used for Sod...IRJET- Characteristic and Failure Analysis of Frp Composite Tank used for Sod...
IRJET- Characteristic and Failure Analysis of Frp Composite Tank used for Sod...IRJET Journal
 
IRJET- Multi-Objective Optimization of Machining Parameters by using Response...
IRJET- Multi-Objective Optimization of Machining Parameters by using Response...IRJET- Multi-Objective Optimization of Machining Parameters by using Response...
IRJET- Multi-Objective Optimization of Machining Parameters by using Response...IRJET Journal
 
Increase the Life of Bend Pulley Lagging of HL-3 Conveyor using TQM
Increase the Life of Bend Pulley Lagging of HL-3 Conveyor using TQMIncrease the Life of Bend Pulley Lagging of HL-3 Conveyor using TQM
Increase the Life of Bend Pulley Lagging of HL-3 Conveyor using TQMIRJET Journal
 
IRJET- Simulation of Structural Vibration Controlled System using Semi Active...
IRJET- Simulation of Structural Vibration Controlled System using Semi Active...IRJET- Simulation of Structural Vibration Controlled System using Semi Active...
IRJET- Simulation of Structural Vibration Controlled System using Semi Active...IRJET Journal
 
IRJET- To Study the Impact of Crumb Rubber on Young’s Modulus of Concrete
IRJET- To Study the Impact of Crumb Rubber on Young’s Modulus of ConcreteIRJET- To Study the Impact of Crumb Rubber on Young’s Modulus of Concrete
IRJET- To Study the Impact of Crumb Rubber on Young’s Modulus of ConcreteIRJET Journal
 
Prashant_rai_Mech8 yrs final
Prashant_rai_Mech8 yrs finalPrashant_rai_Mech8 yrs final
Prashant_rai_Mech8 yrs finalprashant rai
 
IRJET- Design of Three Spindle Drilling, Spot facing Horizontal SPM for C...
IRJET-  	  Design of Three Spindle Drilling, Spot facing Horizontal SPM for C...IRJET-  	  Design of Three Spindle Drilling, Spot facing Horizontal SPM for C...
IRJET- Design of Three Spindle Drilling, Spot facing Horizontal SPM for C...IRJET Journal
 
Optimization of Cylindrical Grinding of Alloy Steel using desirability functi...
Optimization of Cylindrical Grinding of Alloy Steel using desirability functi...Optimization of Cylindrical Grinding of Alloy Steel using desirability functi...
Optimization of Cylindrical Grinding of Alloy Steel using desirability functi...IRJET Journal
 
Assignment of weights method for the optimization of ti n coated carbide reaming
Assignment of weights method for the optimization of ti n coated carbide reamingAssignment of weights method for the optimization of ti n coated carbide reaming
Assignment of weights method for the optimization of ti n coated carbide reamingIAEME Publication
 
IRJET - Mathematical Modelling to Predict Bead Geometry and Shape Relationshi...
IRJET - Mathematical Modelling to Predict Bead Geometry and Shape Relationshi...IRJET - Mathematical Modelling to Predict Bead Geometry and Shape Relationshi...
IRJET - Mathematical Modelling to Predict Bead Geometry and Shape Relationshi...IRJET Journal
 
IRJET- CFD Analysis of 4 Cylinder Intake Manifold using STAR CCM+
IRJET- CFD Analysis of 4 Cylinder Intake Manifold using STAR CCM+IRJET- CFD Analysis of 4 Cylinder Intake Manifold using STAR CCM+
IRJET- CFD Analysis of 4 Cylinder Intake Manifold using STAR CCM+IRJET Journal
 
IRJET- Experimental Analysis and Geometrical Effect on Mild Steel with Un...
IRJET-  	  Experimental Analysis and Geometrical Effect on Mild Steel with Un...IRJET-  	  Experimental Analysis and Geometrical Effect on Mild Steel with Un...
IRJET- Experimental Analysis and Geometrical Effect on Mild Steel with Un...IRJET Journal
 
IRJET - To Study the Strength Characteristics of Concrete by Replacement ...
IRJET -  	  To Study the Strength Characteristics of Concrete by Replacement ...IRJET -  	  To Study the Strength Characteristics of Concrete by Replacement ...
IRJET - To Study the Strength Characteristics of Concrete by Replacement ...IRJET Journal
 
AN INVESTIGATION ON SEISMIC STABILITY OF MINE OVERBURDEN DUMP SLOPE
AN INVESTIGATION ON SEISMIC STABILITY OF MINE OVERBURDEN DUMP SLOPEAN INVESTIGATION ON SEISMIC STABILITY OF MINE OVERBURDEN DUMP SLOPE
AN INVESTIGATION ON SEISMIC STABILITY OF MINE OVERBURDEN DUMP SLOPEIRJET Journal
 
Productivity Escalation and Cost Optimisation of Equipment’s used in Pavement...
Productivity Escalation and Cost Optimisation of Equipment’s used in Pavement...Productivity Escalation and Cost Optimisation of Equipment’s used in Pavement...
Productivity Escalation and Cost Optimisation of Equipment’s used in Pavement...IRJET Journal
 

Similar to Reliability assessment of surface miners using Weibull analysis (20)

Study of Influence of Tool Nose Radius on Surface Roughness and Material Remo...
Study of Influence of Tool Nose Radius on Surface Roughness and Material Remo...Study of Influence of Tool Nose Radius on Surface Roughness and Material Remo...
Study of Influence of Tool Nose Radius on Surface Roughness and Material Remo...
 
IRJET - Fabrication of Four Way Machining by using Scotch Yoke Mechanism
IRJET - Fabrication of Four Way Machining by using Scotch Yoke MechanismIRJET - Fabrication of Four Way Machining by using Scotch Yoke Mechanism
IRJET - Fabrication of Four Way Machining by using Scotch Yoke Mechanism
 
AN INVESTIGATION ON MINE OVERBURDEN DUMP SLOPE STABILITY
AN INVESTIGATION ON MINE OVERBURDEN DUMP SLOPE STABILITYAN INVESTIGATION ON MINE OVERBURDEN DUMP SLOPE STABILITY
AN INVESTIGATION ON MINE OVERBURDEN DUMP SLOPE STABILITY
 
Published 1
Published 1Published 1
Published 1
 
A Theoretical Study on Strata Behaviour and Ground Control in Coal Mines
A Theoretical Study on Strata Behaviour and Ground Control in Coal MinesA Theoretical Study on Strata Behaviour and Ground Control in Coal Mines
A Theoretical Study on Strata Behaviour and Ground Control in Coal Mines
 
IRJET- Characteristic and Failure Analysis of Frp Composite Tank used for Sod...
IRJET- Characteristic and Failure Analysis of Frp Composite Tank used for Sod...IRJET- Characteristic and Failure Analysis of Frp Composite Tank used for Sod...
IRJET- Characteristic and Failure Analysis of Frp Composite Tank used for Sod...
 
IRJET- Multi-Objective Optimization of Machining Parameters by using Response...
IRJET- Multi-Objective Optimization of Machining Parameters by using Response...IRJET- Multi-Objective Optimization of Machining Parameters by using Response...
IRJET- Multi-Objective Optimization of Machining Parameters by using Response...
 
Increase the Life of Bend Pulley Lagging of HL-3 Conveyor using TQM
Increase the Life of Bend Pulley Lagging of HL-3 Conveyor using TQMIncrease the Life of Bend Pulley Lagging of HL-3 Conveyor using TQM
Increase the Life of Bend Pulley Lagging of HL-3 Conveyor using TQM
 
IRJET- Simulation of Structural Vibration Controlled System using Semi Active...
IRJET- Simulation of Structural Vibration Controlled System using Semi Active...IRJET- Simulation of Structural Vibration Controlled System using Semi Active...
IRJET- Simulation of Structural Vibration Controlled System using Semi Active...
 
IRJET- To Study the Impact of Crumb Rubber on Young’s Modulus of Concrete
IRJET- To Study the Impact of Crumb Rubber on Young’s Modulus of ConcreteIRJET- To Study the Impact of Crumb Rubber on Young’s Modulus of Concrete
IRJET- To Study the Impact of Crumb Rubber on Young’s Modulus of Concrete
 
Prashant_rai_Mech8 yrs final
Prashant_rai_Mech8 yrs finalPrashant_rai_Mech8 yrs final
Prashant_rai_Mech8 yrs final
 
IRJET- Design of Three Spindle Drilling, Spot facing Horizontal SPM for C...
IRJET-  	  Design of Three Spindle Drilling, Spot facing Horizontal SPM for C...IRJET-  	  Design of Three Spindle Drilling, Spot facing Horizontal SPM for C...
IRJET- Design of Three Spindle Drilling, Spot facing Horizontal SPM for C...
 
Optimization of Cylindrical Grinding of Alloy Steel using desirability functi...
Optimization of Cylindrical Grinding of Alloy Steel using desirability functi...Optimization of Cylindrical Grinding of Alloy Steel using desirability functi...
Optimization of Cylindrical Grinding of Alloy Steel using desirability functi...
 
Assignment of weights method for the optimization of ti n coated carbide reaming
Assignment of weights method for the optimization of ti n coated carbide reamingAssignment of weights method for the optimization of ti n coated carbide reaming
Assignment of weights method for the optimization of ti n coated carbide reaming
 
IRJET - Mathematical Modelling to Predict Bead Geometry and Shape Relationshi...
IRJET - Mathematical Modelling to Predict Bead Geometry and Shape Relationshi...IRJET - Mathematical Modelling to Predict Bead Geometry and Shape Relationshi...
IRJET - Mathematical Modelling to Predict Bead Geometry and Shape Relationshi...
 
IRJET- CFD Analysis of 4 Cylinder Intake Manifold using STAR CCM+
IRJET- CFD Analysis of 4 Cylinder Intake Manifold using STAR CCM+IRJET- CFD Analysis of 4 Cylinder Intake Manifold using STAR CCM+
IRJET- CFD Analysis of 4 Cylinder Intake Manifold using STAR CCM+
 
IRJET- Experimental Analysis and Geometrical Effect on Mild Steel with Un...
IRJET-  	  Experimental Analysis and Geometrical Effect on Mild Steel with Un...IRJET-  	  Experimental Analysis and Geometrical Effect on Mild Steel with Un...
IRJET- Experimental Analysis and Geometrical Effect on Mild Steel with Un...
 
IRJET - To Study the Strength Characteristics of Concrete by Replacement ...
IRJET -  	  To Study the Strength Characteristics of Concrete by Replacement ...IRJET -  	  To Study the Strength Characteristics of Concrete by Replacement ...
IRJET - To Study the Strength Characteristics of Concrete by Replacement ...
 
AN INVESTIGATION ON SEISMIC STABILITY OF MINE OVERBURDEN DUMP SLOPE
AN INVESTIGATION ON SEISMIC STABILITY OF MINE OVERBURDEN DUMP SLOPEAN INVESTIGATION ON SEISMIC STABILITY OF MINE OVERBURDEN DUMP SLOPE
AN INVESTIGATION ON SEISMIC STABILITY OF MINE OVERBURDEN DUMP SLOPE
 
Productivity Escalation and Cost Optimisation of Equipment’s used in Pavement...
Productivity Escalation and Cost Optimisation of Equipment’s used in Pavement...Productivity Escalation and Cost Optimisation of Equipment’s used in Pavement...
Productivity Escalation and Cost Optimisation of Equipment’s used in Pavement...
 

More from IRJET Journal

TUNNELING IN HIMALAYAS WITH NATM METHOD: A SPECIAL REFERENCES TO SUNGAL TUNNE...
TUNNELING IN HIMALAYAS WITH NATM METHOD: A SPECIAL REFERENCES TO SUNGAL TUNNE...TUNNELING IN HIMALAYAS WITH NATM METHOD: A SPECIAL REFERENCES TO SUNGAL TUNNE...
TUNNELING IN HIMALAYAS WITH NATM METHOD: A SPECIAL REFERENCES TO SUNGAL TUNNE...IRJET Journal
 
STUDY THE EFFECT OF RESPONSE REDUCTION FACTOR ON RC FRAMED STRUCTURE
STUDY THE EFFECT OF RESPONSE REDUCTION FACTOR ON RC FRAMED STRUCTURESTUDY THE EFFECT OF RESPONSE REDUCTION FACTOR ON RC FRAMED STRUCTURE
STUDY THE EFFECT OF RESPONSE REDUCTION FACTOR ON RC FRAMED STRUCTUREIRJET Journal
 
A COMPARATIVE ANALYSIS OF RCC ELEMENT OF SLAB WITH STARK STEEL (HYSD STEEL) A...
A COMPARATIVE ANALYSIS OF RCC ELEMENT OF SLAB WITH STARK STEEL (HYSD STEEL) A...A COMPARATIVE ANALYSIS OF RCC ELEMENT OF SLAB WITH STARK STEEL (HYSD STEEL) A...
A COMPARATIVE ANALYSIS OF RCC ELEMENT OF SLAB WITH STARK STEEL (HYSD STEEL) A...IRJET Journal
 
Effect of Camber and Angles of Attack on Airfoil Characteristics
Effect of Camber and Angles of Attack on Airfoil CharacteristicsEffect of Camber and Angles of Attack on Airfoil Characteristics
Effect of Camber and Angles of Attack on Airfoil CharacteristicsIRJET Journal
 
A Review on the Progress and Challenges of Aluminum-Based Metal Matrix Compos...
A Review on the Progress and Challenges of Aluminum-Based Metal Matrix Compos...A Review on the Progress and Challenges of Aluminum-Based Metal Matrix Compos...
A Review on the Progress and Challenges of Aluminum-Based Metal Matrix Compos...IRJET Journal
 
Dynamic Urban Transit Optimization: A Graph Neural Network Approach for Real-...
Dynamic Urban Transit Optimization: A Graph Neural Network Approach for Real-...Dynamic Urban Transit Optimization: A Graph Neural Network Approach for Real-...
Dynamic Urban Transit Optimization: A Graph Neural Network Approach for Real-...IRJET Journal
 
Structural Analysis and Design of Multi-Storey Symmetric and Asymmetric Shape...
Structural Analysis and Design of Multi-Storey Symmetric and Asymmetric Shape...Structural Analysis and Design of Multi-Storey Symmetric and Asymmetric Shape...
Structural Analysis and Design of Multi-Storey Symmetric and Asymmetric Shape...IRJET Journal
 
A Review of “Seismic Response of RC Structures Having Plan and Vertical Irreg...
A Review of “Seismic Response of RC Structures Having Plan and Vertical Irreg...A Review of “Seismic Response of RC Structures Having Plan and Vertical Irreg...
A Review of “Seismic Response of RC Structures Having Plan and Vertical Irreg...IRJET Journal
 
A REVIEW ON MACHINE LEARNING IN ADAS
A REVIEW ON MACHINE LEARNING IN ADASA REVIEW ON MACHINE LEARNING IN ADAS
A REVIEW ON MACHINE LEARNING IN ADASIRJET Journal
 
Long Term Trend Analysis of Precipitation and Temperature for Asosa district,...
Long Term Trend Analysis of Precipitation and Temperature for Asosa district,...Long Term Trend Analysis of Precipitation and Temperature for Asosa district,...
Long Term Trend Analysis of Precipitation and Temperature for Asosa district,...IRJET Journal
 
P.E.B. Framed Structure Design and Analysis Using STAAD Pro
P.E.B. Framed Structure Design and Analysis Using STAAD ProP.E.B. Framed Structure Design and Analysis Using STAAD Pro
P.E.B. Framed Structure Design and Analysis Using STAAD ProIRJET Journal
 
A Review on Innovative Fiber Integration for Enhanced Reinforcement of Concre...
A Review on Innovative Fiber Integration for Enhanced Reinforcement of Concre...A Review on Innovative Fiber Integration for Enhanced Reinforcement of Concre...
A Review on Innovative Fiber Integration for Enhanced Reinforcement of Concre...IRJET Journal
 
Survey Paper on Cloud-Based Secured Healthcare System
Survey Paper on Cloud-Based Secured Healthcare SystemSurvey Paper on Cloud-Based Secured Healthcare System
Survey Paper on Cloud-Based Secured Healthcare SystemIRJET Journal
 
Review on studies and research on widening of existing concrete bridges
Review on studies and research on widening of existing concrete bridgesReview on studies and research on widening of existing concrete bridges
Review on studies and research on widening of existing concrete bridgesIRJET Journal
 
React based fullstack edtech web application
React based fullstack edtech web applicationReact based fullstack edtech web application
React based fullstack edtech web applicationIRJET Journal
 
A Comprehensive Review of Integrating IoT and Blockchain Technologies in the ...
A Comprehensive Review of Integrating IoT and Blockchain Technologies in the ...A Comprehensive Review of Integrating IoT and Blockchain Technologies in the ...
A Comprehensive Review of Integrating IoT and Blockchain Technologies in the ...IRJET Journal
 
A REVIEW ON THE PERFORMANCE OF COCONUT FIBRE REINFORCED CONCRETE.
A REVIEW ON THE PERFORMANCE OF COCONUT FIBRE REINFORCED CONCRETE.A REVIEW ON THE PERFORMANCE OF COCONUT FIBRE REINFORCED CONCRETE.
A REVIEW ON THE PERFORMANCE OF COCONUT FIBRE REINFORCED CONCRETE.IRJET Journal
 
Optimizing Business Management Process Workflows: The Dynamic Influence of Mi...
Optimizing Business Management Process Workflows: The Dynamic Influence of Mi...Optimizing Business Management Process Workflows: The Dynamic Influence of Mi...
Optimizing Business Management Process Workflows: The Dynamic Influence of Mi...IRJET Journal
 
Multistoried and Multi Bay Steel Building Frame by using Seismic Design
Multistoried and Multi Bay Steel Building Frame by using Seismic DesignMultistoried and Multi Bay Steel Building Frame by using Seismic Design
Multistoried and Multi Bay Steel Building Frame by using Seismic DesignIRJET Journal
 
Cost Optimization of Construction Using Plastic Waste as a Sustainable Constr...
Cost Optimization of Construction Using Plastic Waste as a Sustainable Constr...Cost Optimization of Construction Using Plastic Waste as a Sustainable Constr...
Cost Optimization of Construction Using Plastic Waste as a Sustainable Constr...IRJET Journal
 

More from IRJET Journal (20)

TUNNELING IN HIMALAYAS WITH NATM METHOD: A SPECIAL REFERENCES TO SUNGAL TUNNE...
TUNNELING IN HIMALAYAS WITH NATM METHOD: A SPECIAL REFERENCES TO SUNGAL TUNNE...TUNNELING IN HIMALAYAS WITH NATM METHOD: A SPECIAL REFERENCES TO SUNGAL TUNNE...
TUNNELING IN HIMALAYAS WITH NATM METHOD: A SPECIAL REFERENCES TO SUNGAL TUNNE...
 
STUDY THE EFFECT OF RESPONSE REDUCTION FACTOR ON RC FRAMED STRUCTURE
STUDY THE EFFECT OF RESPONSE REDUCTION FACTOR ON RC FRAMED STRUCTURESTUDY THE EFFECT OF RESPONSE REDUCTION FACTOR ON RC FRAMED STRUCTURE
STUDY THE EFFECT OF RESPONSE REDUCTION FACTOR ON RC FRAMED STRUCTURE
 
A COMPARATIVE ANALYSIS OF RCC ELEMENT OF SLAB WITH STARK STEEL (HYSD STEEL) A...
A COMPARATIVE ANALYSIS OF RCC ELEMENT OF SLAB WITH STARK STEEL (HYSD STEEL) A...A COMPARATIVE ANALYSIS OF RCC ELEMENT OF SLAB WITH STARK STEEL (HYSD STEEL) A...
A COMPARATIVE ANALYSIS OF RCC ELEMENT OF SLAB WITH STARK STEEL (HYSD STEEL) A...
 
Effect of Camber and Angles of Attack on Airfoil Characteristics
Effect of Camber and Angles of Attack on Airfoil CharacteristicsEffect of Camber and Angles of Attack on Airfoil Characteristics
Effect of Camber and Angles of Attack on Airfoil Characteristics
 
A Review on the Progress and Challenges of Aluminum-Based Metal Matrix Compos...
A Review on the Progress and Challenges of Aluminum-Based Metal Matrix Compos...A Review on the Progress and Challenges of Aluminum-Based Metal Matrix Compos...
A Review on the Progress and Challenges of Aluminum-Based Metal Matrix Compos...
 
Dynamic Urban Transit Optimization: A Graph Neural Network Approach for Real-...
Dynamic Urban Transit Optimization: A Graph Neural Network Approach for Real-...Dynamic Urban Transit Optimization: A Graph Neural Network Approach for Real-...
Dynamic Urban Transit Optimization: A Graph Neural Network Approach for Real-...
 
Structural Analysis and Design of Multi-Storey Symmetric and Asymmetric Shape...
Structural Analysis and Design of Multi-Storey Symmetric and Asymmetric Shape...Structural Analysis and Design of Multi-Storey Symmetric and Asymmetric Shape...
Structural Analysis and Design of Multi-Storey Symmetric and Asymmetric Shape...
 
A Review of “Seismic Response of RC Structures Having Plan and Vertical Irreg...
A Review of “Seismic Response of RC Structures Having Plan and Vertical Irreg...A Review of “Seismic Response of RC Structures Having Plan and Vertical Irreg...
A Review of “Seismic Response of RC Structures Having Plan and Vertical Irreg...
 
A REVIEW ON MACHINE LEARNING IN ADAS
A REVIEW ON MACHINE LEARNING IN ADASA REVIEW ON MACHINE LEARNING IN ADAS
A REVIEW ON MACHINE LEARNING IN ADAS
 
Long Term Trend Analysis of Precipitation and Temperature for Asosa district,...
Long Term Trend Analysis of Precipitation and Temperature for Asosa district,...Long Term Trend Analysis of Precipitation and Temperature for Asosa district,...
Long Term Trend Analysis of Precipitation and Temperature for Asosa district,...
 
P.E.B. Framed Structure Design and Analysis Using STAAD Pro
P.E.B. Framed Structure Design and Analysis Using STAAD ProP.E.B. Framed Structure Design and Analysis Using STAAD Pro
P.E.B. Framed Structure Design and Analysis Using STAAD Pro
 
A Review on Innovative Fiber Integration for Enhanced Reinforcement of Concre...
A Review on Innovative Fiber Integration for Enhanced Reinforcement of Concre...A Review on Innovative Fiber Integration for Enhanced Reinforcement of Concre...
A Review on Innovative Fiber Integration for Enhanced Reinforcement of Concre...
 
Survey Paper on Cloud-Based Secured Healthcare System
Survey Paper on Cloud-Based Secured Healthcare SystemSurvey Paper on Cloud-Based Secured Healthcare System
Survey Paper on Cloud-Based Secured Healthcare System
 
Review on studies and research on widening of existing concrete bridges
Review on studies and research on widening of existing concrete bridgesReview on studies and research on widening of existing concrete bridges
Review on studies and research on widening of existing concrete bridges
 
React based fullstack edtech web application
React based fullstack edtech web applicationReact based fullstack edtech web application
React based fullstack edtech web application
 
A Comprehensive Review of Integrating IoT and Blockchain Technologies in the ...
A Comprehensive Review of Integrating IoT and Blockchain Technologies in the ...A Comprehensive Review of Integrating IoT and Blockchain Technologies in the ...
A Comprehensive Review of Integrating IoT and Blockchain Technologies in the ...
 
A REVIEW ON THE PERFORMANCE OF COCONUT FIBRE REINFORCED CONCRETE.
A REVIEW ON THE PERFORMANCE OF COCONUT FIBRE REINFORCED CONCRETE.A REVIEW ON THE PERFORMANCE OF COCONUT FIBRE REINFORCED CONCRETE.
A REVIEW ON THE PERFORMANCE OF COCONUT FIBRE REINFORCED CONCRETE.
 
Optimizing Business Management Process Workflows: The Dynamic Influence of Mi...
Optimizing Business Management Process Workflows: The Dynamic Influence of Mi...Optimizing Business Management Process Workflows: The Dynamic Influence of Mi...
Optimizing Business Management Process Workflows: The Dynamic Influence of Mi...
 
Multistoried and Multi Bay Steel Building Frame by using Seismic Design
Multistoried and Multi Bay Steel Building Frame by using Seismic DesignMultistoried and Multi Bay Steel Building Frame by using Seismic Design
Multistoried and Multi Bay Steel Building Frame by using Seismic Design
 
Cost Optimization of Construction Using Plastic Waste as a Sustainable Constr...
Cost Optimization of Construction Using Plastic Waste as a Sustainable Constr...Cost Optimization of Construction Using Plastic Waste as a Sustainable Constr...
Cost Optimization of Construction Using Plastic Waste as a Sustainable Constr...
 

Recently uploaded

Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...Dr.Costas Sachpazis
 
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...Dr.Costas Sachpazis
 
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130Suhani Kapoor
 
Microscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptxMicroscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptxpurnimasatapathy1234
 
Analog to Digital and Digital to Analog Converter
Analog to Digital and Digital to Analog ConverterAnalog to Digital and Digital to Analog Converter
Analog to Digital and Digital to Analog ConverterAbhinavSharma374939
 
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...ranjana rawat
 
Introduction and different types of Ethernet.pptx
Introduction and different types of Ethernet.pptxIntroduction and different types of Ethernet.pptx
Introduction and different types of Ethernet.pptxupamatechverse
 
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINEMANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINESIVASHANKAR N
 
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptxDecoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptxJoão Esperancinha
 
Call Girls Delhi {Jodhpur} 9711199012 high profile service
Call Girls Delhi {Jodhpur} 9711199012 high profile serviceCall Girls Delhi {Jodhpur} 9711199012 high profile service
Call Girls Delhi {Jodhpur} 9711199012 high profile servicerehmti665
 
chaitra-1.pptx fake news detection using machine learning
chaitra-1.pptx  fake news detection using machine learningchaitra-1.pptx  fake news detection using machine learning
chaitra-1.pptx fake news detection using machine learningmisbanausheenparvam
 
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...ranjana rawat
 
Extrusion Processes and Their Limitations
Extrusion Processes and Their LimitationsExtrusion Processes and Their Limitations
Extrusion Processes and Their Limitations120cr0395
 
College Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service NashikCollege Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service NashikCall Girls in Nagpur High Profile
 
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur High Profile
 
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Serviceranjana rawat
 
the ladakh protest in leh ladakh 2024 sonam wangchuk.pptx
the ladakh protest in leh ladakh 2024 sonam wangchuk.pptxthe ladakh protest in leh ladakh 2024 sonam wangchuk.pptx
the ladakh protest in leh ladakh 2024 sonam wangchuk.pptxhumanexperienceaaa
 

Recently uploaded (20)

Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
 
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
 
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
 
Microscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptxMicroscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptx
 
Analog to Digital and Digital to Analog Converter
Analog to Digital and Digital to Analog ConverterAnalog to Digital and Digital to Analog Converter
Analog to Digital and Digital to Analog Converter
 
Call Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCR
Call Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCRCall Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCR
Call Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCR
 
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...
 
Introduction and different types of Ethernet.pptx
Introduction and different types of Ethernet.pptxIntroduction and different types of Ethernet.pptx
Introduction and different types of Ethernet.pptx
 
★ CALL US 9953330565 ( HOT Young Call Girls In Badarpur delhi NCR
★ CALL US 9953330565 ( HOT Young Call Girls In Badarpur delhi NCR★ CALL US 9953330565 ( HOT Young Call Girls In Badarpur delhi NCR
★ CALL US 9953330565 ( HOT Young Call Girls In Badarpur delhi NCR
 
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINEMANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
 
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptxDecoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
 
Exploring_Network_Security_with_JA3_by_Rakesh Seal.pptx
Exploring_Network_Security_with_JA3_by_Rakesh Seal.pptxExploring_Network_Security_with_JA3_by_Rakesh Seal.pptx
Exploring_Network_Security_with_JA3_by_Rakesh Seal.pptx
 
Call Girls Delhi {Jodhpur} 9711199012 high profile service
Call Girls Delhi {Jodhpur} 9711199012 high profile serviceCall Girls Delhi {Jodhpur} 9711199012 high profile service
Call Girls Delhi {Jodhpur} 9711199012 high profile service
 
chaitra-1.pptx fake news detection using machine learning
chaitra-1.pptx  fake news detection using machine learningchaitra-1.pptx  fake news detection using machine learning
chaitra-1.pptx fake news detection using machine learning
 
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
 
Extrusion Processes and Their Limitations
Extrusion Processes and Their LimitationsExtrusion Processes and Their Limitations
Extrusion Processes and Their Limitations
 
College Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service NashikCollege Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
 
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
 
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service
 
the ladakh protest in leh ladakh 2024 sonam wangchuk.pptx
the ladakh protest in leh ladakh 2024 sonam wangchuk.pptxthe ladakh protest in leh ladakh 2024 sonam wangchuk.pptx
the ladakh protest in leh ladakh 2024 sonam wangchuk.pptx
 

Reliability assessment of surface miners using Weibull analysis

  • 1. International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056 Volume: 07 Issue: 01 | Jan 2020 www.irjet.net p-ISSN: 2395-0072 © 2020, IRJET | Impact Factor value: 7.34 | ISO 9001:2008 Certified Journal | Page 1794 GEO- Mining Based Reliability Assessment of Continuous Surface Miners–A Critical Review Hemant Sharad Pande1, Dr. Manish. D. Uttarwar2, Prof. M.S. Tiwari3 1Chief Manager (Mining), Gevra Area, S.E.C.L 2Professor (On Lien), Department of Mining Engineering, R C E R T, Chandrapur 3Associate Professor, Ramdeobaba College of Engineering & Management ---------------------------------------------------------------------***---------------------------------------------------------------------- Abstract -At present the demand of coal is more than 1000MT in spite of more focus by Govt. on solar and other non conventional source of energy. The new perspective requires systematic operational planning and strict operational control of capital intensive machine. The proactive approach of equipment reliability assessment will be beneficial for surface coal mines. The quantitivly production paradigm is now shifting towards qualitatively. The conventional methods of coal extraction in surface mining does not sustained with qualitative aspect. The application of Surface Miners minimizes the mining activities up to a limited extent. Due to wide application and adoptability in surface coal mining, it shows that Surface miner is a proved technology can beneficial in different aspects. if its reliability and productivity parameters are handled with due diligence. The surface miner equipment handled the required gigantic and qualitative coal target. This technology is used as hallmark for selective mining. At present, Out of 422 Approximately 150 Surface Miners of different make and capacity are operated in India at different sectors. Appropriate use of technology fulfills techno-safe, economical and quality requirements along with avoidance strategy of blasting and crushing. Ability of surface miner to operate and cut coal effectively is limited to strength of coal. Update knowledge of coal characteristics and machine interactions utmost necessary for gigantic production and smooth operation. For best utilization of this technology, it is required to predict surface miner reliabilities on basis of geo mining parameter. GEVRA OCP is world’s third highest coal producing mine, the yearly production target is 45 MT and subsequently increases up to 70 MT in next three years. Eleven numbers of surface miners are used as a part of systematic method of coal production along with Pay- loader & surface trucks. The Overburden handling uses Shovel-Dumper combination. Reliability assessment and evaluation of surface miner by Weibull analysis is detailed in this paper. Break down details of sub parts & whole of surface miner in three years is used in this study. Output element of this study is line fit plot & probability of failure of different subparts. Performance of the Surface miner are assessed through comparative evaluation of line fit plot & geo mining parameters. Probability of failure is helpful to design proactive maintenance strategy in advance. Due to compatibility & adoptability in production growth, there may be future scope of application in different mines so the reliability analyses of these equipments are to be studied. Key Words: Reliability, Weibull Analysis, Reliability Evaluation, Reliability Assessment, Surface miner. 1. INTRODUCTION India’s two-third commercial energy mainly comes from coal and will be increased in subsequent years. The difference between demand and supply needs to cope up through reforming the process of coal production and technology adopted. There are various reasons related to government strategies, which hinder the coal production and appropriate measures required to boost up coal production. Opencast mines share almost four-fifth of total coal production in India so boost up the opencast mines production is a prime target for coal Industry. Govt. strategies also enforce to improve efficiency of the coal sectors in level of international standards. The output norms of capital intensive machines reviewed and become comparable with international levels. Incredible pressure on Coal Company wants boost up the opencast production have become thrust areas. Reliability related with better utilizations of human resource and capital investment. Better equipment reliability is a choice and reliability analysis at initial operational stage is essential to verify the reliability of the same equipment for further deployment Reliability analysis of mining equipment is helpful to estimate the failure patterns. In this study the sub-parts of Surface miner is integrated to evaluate the actual equipment reliability. A case study of surface miners presented in this paper to evaluate reliability as an early operating reliability. 1.1 Glimpses of Gevra Opencast Mine The coal block of the project consist thick coal bench and strike direction is NW-SE to E-W in major part of the block. The average stripping ratio in this OCP is 1.3 along with thickness range 117 -174 m and seam gradient is 40 to 90 Surface miners are used for coal production, the slope angle of coal bench is of 600 to 750. Mainly 42 cum shovel- 240 Te dumper combinations with large diametric deep hole drills of 20 meters depth and 381 mm diameter are used for OB handling. The slope angle
  • 2. International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056 Volume: 07 Issue: 01 | Jan 2020 www.irjet.net p-ISSN: 2395-0072 © 2020, IRJET | Impact Factor value: 7.34 | ISO 9001:2008 Certified Journal | Page 1795 of coal bench is of 600 to 750. In the year 2019 the coal and OB production targets 45 million tons and 58 million cubic meters respectively. It is expected to be the slated at a production target of 70 million tons in forthcoming years. To meet the gigantic target, A number of high capacity capital intensive mining machineries used that needs to reliable. Reliability is a performance indicator of overall equipment condition. 1.2 Technical description of Surface Miner under study The quality production management in opencast mine due to layers of shale, & stone bands has become a difficult task. The application of Surface Miners was extended for coal mining in the year 1999. The design concept for the surface miner is based on the milling principal. Deployment of the Surface Miner technology largely succeeded and to increase the quality coal production along with minimizing terminal effect of mining. At present in every mega project of Coal India, maximum coal production is obtained by this technology. The technology is not only contributed as mass production technology but also produce appropriate size of fragmentation that is the emergent need of today. In Gevra OCP there are 12 numbers of surface miners for coal production which are of different make but Wirtgen Surface Miner 2200 SM was considered in this study. The technical specifications are been mentioned below: Table 1- Technical & Operating Parameters of SM Figure- 1: Overview of Surface Miner 2. RELIABILITY OF SURFACE MINERS’ Productivity is major concern even in hired Surface Miner or departmental surface miner. The evaluation & prediction of reliability of surface miner was considered the geo-mining parameter of coal. With this emergent issue some field observations and data study are being carried out with respect to operation of Surface Miner taken under study. The study of failure pattern is immense importance as the prevailing stiff targets of coal overcome by maintaining High equipment reliability, which may come from providing good operational environmental conditions. The classification of miners as milling type, bucket wheel type and ranging-shearer-drum type on basis of cutting drum, choice is decided on the required capacity and geo mining parameter of cutting strata. The evaluation of reliability of Surface miner is been studied in this paper and the methodology of the same is been developed. Mainly the methodologies applied for reliability estimations are Stress Analysis, Reliability Predictions (MTBF: Mean Time Between Failures), FMCA ( Failures Mode and Effect Analysis) & FMECA ( Failures Mode Effects and Criticality Analysis).The flow chart reliability evaluation of 2200 SM through Weibull analysis. The breakdown data of the machine has been acquired from the daily record data base of the component. From the OEM specifications and manuals, the specific life of the major assemblies and its sub-assemblies can be acquired. From the obtained results the probability of occurrence of error in data selecting for components failure, uncertainty is evaluated. Even a minor failure of the selected components leads to system failure and system operation breakdown and this is the case study of this research. Working width` 2.20 m Max. cutting depth 0.35 m Engine power 811 PS Weight 51 t Cutting drum drive Mechanical Number of crawlers 4 Travel drive Hydraulic Working width` 2.20 m Max. cutting depth 0.35 m Engine power 811 PS Weight 51 t Cutting drum drive Mechanical Number of crawlers 4 Travel drive Hydraulic
  • 3. International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056 Volume: 07 Issue: 01 | Jan 2020 www.irjet.net p-ISSN: 2395-0072 © 2020, IRJET | Impact Factor value: 7.34 | ISO 9001:2008 Certified Journal | Page 1796 Figure -2: Flow chart of study work . Operating failure data collected from routine day wise data base. Intercalation pebbles & shale-sandstone bands other adversely impact on machine health. Reliability aspects of the equipment play important role for forecast of sub parts failure .On the basis of reliability forecast appropriate pro active maintenance scheduled and minimize the cost. The 2200 SM surface miner is selected for this study. Weibull analysis is used for a method for reliability evaluation. The Weibull formula for two parameter distribution is R(x) = e (-(x/α) ^β) ; for x>0 Where “β” is the shape parameter, “α” is the characteristics life “x” is the time to failure. The Bernard’s approximation formula for calculating Median rank is F (t) = (i-0.3)/ (n+0.4) Where “i” is the corresponding rank of the data “n” is the total number of samples Weibull Analysis is beneficial in ascertain the failure probability; the output of this analysis is easier line fit plots. The two defining parameters of the Weibull line are the shape parameter β, and the characteristic life α. The Weibull distribution’s easily approximate an exponential, a normal or a skewed distribution in Excel and not required more upgraded software. 3. DATA ANALYSIS In this case study, the Average compressive strength, Tensile strength, Shear strength & Average density of three consecutive years has been collected from borehole logs and correlated with machine reliability. The geo mining parameter of the coal for the selected years is computed separately and is depicted in the Table given below. As can be observed from the data given above, the major breakdowns in Surface Miner are attributed to high engine temperatures, hydraulic Cylinder leakages, idler cracking, drive pump failures, coupling failures, main control panel, water sprinklers, lighting, engine firing and air-conditioning unit. The Table given below shows the coal production from surface miner, breakdown hours, maintenance hours, idle hours and working hours in percentage for the Surface Miner Model SM 2200/3800 Table 3- Geo mining matrix Table 4- Year wise production and breakdown details 4. OUTPUT OF WEIBULL ANALYSIS Figure -3: Year – 1 Overall Breakdown Figure- 4: Year –2 Overall Breakdown Year Avg Compressive strength Avg Tensile strength Avg shear strength Avg density 2013- 14 8.50642857 0.626428571 1.519285714 1.527142857 2014- 15 17.3117949 0.506410256 1.203846154 1.444102564 2015- 16 15.8763895 0.739216152 0.948764846 1.527102138 Year Production Breakdown hour 2013-14 3842800 2200.5 2014-15 3867600 2168.5 2015-16 3873200 2173 Field data base collection Time to Failure Weibull Analysis Interpretation by Weibull plot Reliability prediction at diff. hours Correlation with geo mining parameters Geo-mining reliability Component & its relation identification
  • 4. International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056 Volume: 07 Issue: 01 | Jan 2020 www.irjet.net p-ISSN: 2395-0072 © 2020, IRJET | Impact Factor value: 7.34 | ISO 9001:2008 Certified Journal | Page 1797 Figure -5: Year –3 Overall Breakdown 4.1 Analysis of Weibull plots In the line plots blue colored line represents the available reliability and red color line represents predicted reliability. From the line plot of 1st year over all breakdowns, it can be observed that the predicted reliability of 1st year follows almost same path all along the year except mild increasing trend of actual reliability in the middle. At final quarter of the year actual reliability follows same pattern while predicted reliability is in increasing trend .From the line plot of 2nd year overall breakdown, it can be observed that the predicted reliability of 2nd year follows straight line path throughout the year while actual reliability is lower at the initial phase of the year & after that follows increasing trend up to some extent till higher than predicted reliability. At the final quarter of year actual reliability is slightly lower than predicted reliability and again increasing trend. From the line fit plot of Year 3 overall breakdown it can be observed that at some particular operating hours the predicted reliability line is lower compared to available reliability line which clearly show that the reliability of the machine is much better than the predicted reliability. The main cause for this condition to occur is the scheduled maintenance and mini shutdown system which means the maintenance carried out at some particular interval of time. 4.2 Reliability study of surface miner by using Weibull analysis: Table -5:Reliability study of surface miner by using weibull analysis 4.3 Reliability analysis of surface miner under the given geo-mining conditions This section depicted to establish a relation between selected year wise associated reliability estimates of surface miner and geo-mining parameters of coal. The following observation established after comparative analysis of the reliability graphical plots of the surface miners with the selected three years and selected geo- mining parameters. In this paper only two intervals of 1000 hours and 2000 hours are taken under study in selected three years. 1-It can be primarily established that the reliability of the surface miners decreases after a certain initial hours of deployment with the increasing compressive strength of the coal material to be handled. 2 -It can be primarily established that the reliability of the surface miners decreases after a certain initial hours of deployment with the increasing tensile strength of the coal material to be handled 3-It can be primarily established that the reliability of the surface miners decreases after a certain initial hours of deployment with the increasing shear strength of the coal material to be handled Year Year 1 Year 2 Year 3 CYCLE Reliability Reliability Reliability 100 0.986068992 1 1 200 0.966491752 1 1 500 0.895663704 0.999999933 1 1000 0.765136741 0.999995674 1 2000 0.521856309 0.99972067 0.999999992 5000 0.122132088 0.933311539 0.999918873 10000 0.006046543 0.011600464 0.913017417 20000 4.07665E-06 0 0 30000 8.73357E-10 0 0 40000 8.06022E-14 0 0 50000 0 0 0 60000 0 0 0
  • 5. International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056 Volume: 07 Issue: 01 | Jan 2020 www.irjet.net p-ISSN: 2395-0072 © 2020, IRJET | Impact Factor value: 7.34 | ISO 9001:2008 Certified Journal | Page 1798 4.4 Reliability impact of compressive strength Figure -6: Compressive strength Vs Reliability at 1000 Hrs Figure-7: Compressive strength Vs Reliability at 2000 Hrs 4.5 Reliability impact of shear strength Figure-8: Shear strength Vs Reliability at 1000 Hrs Figure-9: Shear strength Vs Reliability at 2000 Hrs 4.6 Reliability impact of Tensile strength Figure-10: Tensile strength Vs Reliability at 1000 Hrs Figure-11: Tensile strength Vs Reliability at 2000 Hrs
  • 6. International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056 Volume: 07 Issue: 01 | Jan 2020 www.irjet.net p-ISSN: 2395-0072 © 2020, IRJET | Impact Factor value: 7.34 | ISO 9001:2008 Certified Journal | Page 1799 4.7 Graph between yearly reliability and working hours for all the 3 years: Figure-12: Reliability verses working hours 4.8 Observations Reliability graph in the year 2013-14 follows drastically down trend at initial hours of deployment up to 2000 hrs. Reliability graph in the year 2014-15 follows straight line path during initial hours of deployment up to 2000 hrs. of working. Reliability graph in the year 2015-16 follows straight line path at initial hours of deployment up to 5000 hrs. Finally it shows that Reliability has a correlation with working hours & the geo mining characteristics of coal. Both are the prime factors that are responsible for variation in Reliability of surface miner. 4.9 Final Inference Geo-mining parameters during the period of the study under different coal characteristics were analyzed individually and it was found that the reason of breakdowns were common except it was noted that the frequency of electrical problem is higher which required the review of the system from the point of view of original equipment manufacturer (OEM). The preparedness for pro-active maintenance strategy to improve the Reliability of machine is an essential function to be looked into. Operational failure will be minimized by way of provision for maintenance strategy formulation with regard to deployment of the surface miner. 5. CONCLUSIONS AND SUGGESTED FUTURE WORK Different geo mining parameters during deployment of surface miner machine were considered primarily in this study. All the major heads of breakdowns were identified & they were analyzed by regression method of Weibull including the maintenance strategy of surface miner. In this study the importance of operational parameters were highlighted. The relations between all the operational parameters of surface miner machine and the mechanical reliability, which was calculated by Weibull analysis were developed and that are found useful to find out the predicted reliability at different phases of machine with respect to geo mining parameters .The study was aimed at improving the reliability of surface miner technology by identifying major thrust hold categories of breakdowns at different known geo mining parameters. The studies of various parameters including the breakdowns of the machine were found useful to identify the areas of concern from the operational point of view as well as from machine design point of view. The study also focused on possibility of few design changes from the OEM point of view. The major inferences which were derived from this research work are discussed in the following section. 5.1 Suggested maintenance strategy The study suggested some of the areas as critical areas including the breakdown areas in the machine. The impact of all the breakdown reasons of all the electrical and mechanical nature during the study period was identified and Reliability of the machine was studied. Definitely the breakdown reasons are responsible for reduction of the reliability of the machine but the study was done to find out the greatest impact factor to suggest improvement in maintenance strategy of the machine. The following point should be considered during formulation of maintenance strategy: 1. A reliability review team will be trained in each mine. 2. Reliability review interval should be decided on basis of planned machine deployment strategy. 3. A three tier maintenance strategy should be developed. 4. Safety parameters of machine are also considered as input parameter during reliability analysis. 5.2 Suggested Deployment strategy In future, a number of surface miners are planned to be deployed in this mega project as the target of the project is going to be doubled in the coming years. This study undertaken thus provides a guideline for predicted deployment with respect to the reliability as well as the productivity of the given surface miner. 5.3 Suggested future work The studies of some of the important geo-mining parameters of surface miner were considered in this research study. In future the other parameters such as wear & tear of cutting picks, impact of deeper cut on machine reliability can suggest new relationship to find out the better way for improving reliability. The study of different make of surface miners deployed in other minerals can also be useful in strengthening the established relationship between different parameters which are suggested in this study.
  • 7. International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056 Volume: 07 Issue: 01 | Jan 2020 www.irjet.net p-ISSN: 2395-0072 © 2020, IRJET | Impact Factor value: 7.34 | ISO 9001:2008 Certified Journal | Page 1800 5.4 Recommendations for the effective utilization of the surface miner 1. Operational reliability can be improvised by planning activities like “campaign” strategy, whereby a “mini-shutdowns” are programmed at regular intervals to perform all necessary maintenance and inspections. 2. On line machine diagnostics and down time minimizing techniques can enhance reliability of the machine. 3. Immediate action to be taken for frequently impacting breakdowns. Proper scientific layout, face availability can help reduce idle/waiting time to a greater extent. ACKNOWLEDGEMENT The work proposed in this paper forms a part of the Post Graduate study of the first author. The author expresses his thankfulness towards the supervisors of the study and department of mining engineering, RCERT Chandrapur for providing varied facilities. The permission and subsequent field support from Gevra OCP, S.E.C.L. is deeply acknowledged with thanks. The view expressed in this paper is those of authors and not necessarily of the organizations they represent nor of the sector under study. REFERENCES [1] WIRTGEN(1984).WRITGEN INFORMATION/IW- 2/84-22/5/84 [2] Wiilliam W. Dorner (1999), Using Microsoft Excel for Weibull Analysis, http://www.qualitydigest.com/pdfs/weibull.xls [3] Coal India Limited, www.cil.nic.in